SU1122828A1 - Method of combination mining of seam deposits - Google Patents

Method of combination mining of seam deposits Download PDF

Info

Publication number
SU1122828A1
SU1122828A1 SU833553335A SU3553335A SU1122828A1 SU 1122828 A1 SU1122828 A1 SU 1122828A1 SU 833553335 A SU833553335 A SU 833553335A SU 3553335 A SU3553335 A SU 3553335A SU 1122828 A1 SU1122828 A1 SU 1122828A1
Authority
SU
USSR - Soviet Union
Prior art keywords
trenches
mining
development
transport
opening
Prior art date
Application number
SU833553335A
Other languages
Russian (ru)
Inventor
Феликс Михайлович Киржнер
Валентин Николаевич Скуба
Юрий Давыдович Чугунов
Original Assignee
Институт горного дела Севера Якутского филиала СО АН СССР
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт горного дела Севера Якутского филиала СО АН СССР filed Critical Институт горного дела Севера Якутского филиала СО АН СССР
Priority to SU833553335A priority Critical patent/SU1122828A1/en
Application granted granted Critical
Publication of SU1122828A1 publication Critical patent/SU1122828A1/en

Links

Abstract

СПОСОБ КОМБИНИРОВАННОЙ РАЗРАБОТКИ ПЛАСТОВЫХ МЕСТОРОЖДЕНИИ,включакиций проходку на флангах участка месторождени  вскрывающих траншей, образование на наклонной поверхности дна указанных траншей транспортных коммуникаций j проходку траншей до предельного контура разработки с поддержанием транспотных коммуникаций , проведение из траншей разрезной выработки, отработку полезного ископаемого лавой до границы очистной выемки и закладку выработанного пространства , отличающийс  тем, что, с целью снижени  себестоимости разработки за c4ieT сокращени  объемов вскрьш1ных работ, проходку вскрывающих траншей до предельного контура разработки ведут поочередно на каждом из флангов после проведени  разрезной выработки с отсыпкой вскрьш1ных пород в выработанное пространство, совмещгиот проходку указанных траншей с отработкой полезногоископаемого и при подходе лавы к границе очистной выемки срабатьшают транспортные коммуникации с формированием наклонных поверхностей дна траншей на предельном контуре разработки под углом естественного откоса,а транс-. портные коммуникации образуют на отсыпаемых породах. Фиг.1METHOD OF COMBINED DEVELOPMENT OF PLASTIC DEPOSITS, including screenings on the flanks of the site of the opening trenches, formation on the inclined bottom of the bottom of the said transport trenches j and trenching to the development limit contour with maintenance of transport communications, cutting out of the trenches, mining the mining trenches, mining minerals to the mining section, maintaining transport communications, carrying out split trenches, mining minerals, mining mineral pipelines and laying the developed space, characterized in that, in order to reduce the development cost of c4ieT reducing the amount of open work, penetration of opening trenches to the marginal contour of the development are alternately carried out on each flank after conducting split production with filling up of open pit rocks into the developed space, combining the penetration of the said trenches with mining of the discovered mine and when the lava approaches the boundary of the clearing notch, the transport trenches the formation of inclined surfaces of the bottom of the trenches on the marginal contour of the development at an angle of repose, and trans-. tailor communications form on sleeps. 1

Description

.« -и Изобретение относитс  к горной промьшшенностн и может быть использовано при добыче полезных ископаемь1Х на пластовых и россыпных месторождени х Э услови х многолетней мерзлоты. Йзйестен способ разработки место|Н}ждений , включающий вскрытий транше ми , отработку узкими панел ми с оставлением арёменных целиков н зак ладку выработанного пространства Ll Недостатками способа  вл ютс  п родрлжитепькь 11. срок подготовки месторождени  к началу добычных работ, значительные потери полезного ископаемого , а т.акже необходимость проведени  дополнительных меропри тий по сохранению устойчивости бортов траШ1еи в летний период . Наиболее близкий к изобретению по техиче кой сущности и достигаемому рёзуль.тату  вл етс  способ ком бинированной {разработки пластовых месторождений) включающий проходку на флангах участка месторождени  вскрывающ1{х траншей, образование на наклонной поверхйости дна указан ных траншей транспортных коммуникаций , проходку трайшей до предельното контура разработки с поддержанием транспортных коммуникаций,tipoведе 1ие из траншей разрезной выработки , отрабатку полезного ископаемого лавой до границы очистной выем ки и закладку выработанного прост ранства . ; Не Е остатком известнрго способа  вл етс  высрк   себестоимость добы чй, обусловленна  объектом вскрышных рабвт и необходимостью пр ведени  дополнительных меропри тий itp обеейечейада длительной устойчиBOCTI б6;ртов траншеи. Целью изобретений  вл етс  сниже ние себестоимость разработки за счё сркращеии  рбьемов вскрышных работ. Поставленна  цель дрстигаетс  те что согласно способу комбинированно разработки пластовых местррождений, вкл(дча{( проходку ца флангах участ ка. м&сторождени всрыв юошх траншей рбразов 1киё на наклонной поверхности дйа указанных траншей транспортных коммуникаций, проходку Траншей до предельнрго контура разработки с, подцержа1й1ем транспортных коммуни кkцийj проведение из трашаей разрез ной йыработки, отработку . полезного 82 ископаемого лавой до границы очист- . ной выемки и закладку выработанного пространства, проходку вскрывающих траншей до предельного контура разработки ведут поочередно на.каждом из флангов йосле проведени  разрез- . ной выработки с отсыпкой вскрьш1Ных пород в выработанное пространство, совмещают проходку указанных траншей с отработкой полезного ископаемого и при подходе лавы к границе очистной выемки срабатывают транспортные коммуникации с формированием наклонных поверхностей дна траншей на предельном контуре разработки под углом естественного откоса, а транспортные коммуникации образуют на отсыпаемых породах. На 4 1г. I показано расположение траншей в начальный период вскрыти , подготовка и направление развити  очистной дрбычи} на фиг. 2 - развитие горных работ в транше х и в подземном участке ; на фиг.З-завершающа  стади  .отработки участка месторождени . Способ комбинированной разработ- ; ки пластовых месторождений состоит в следующем. ria флангах участка месторождени  1 проход т вскрывающие траншеи. На наклонной поверхности дна траншей образуют транспортные крммуникации 2 При этом выезд из траншей осуществл ют в направлении отработки полезного ископаемого. Вскрываюв е фланговые траншеи соедин ют путем прове-. дени  разрезной выработки 3, после чего начинают отработку полезнрго ископаемого лавой и ведут проходку траншей поочереднр на каждом из флангов до предельного контура разработки с отсыпкой вскрьпиных пород в выработанное пространство 4. Поочередна  проходка траншей позвол ет одновременно осуществл ть работы по вскрытию месторождени  на одном из флангов и его отработке подземным участком , вскрывающа  транше  на другом фланге служит транспортной св зью между подземным участком и поверх ностью . Затем вскрытие месторождени  производ т проходкой траншеи на другом , фланге, а НА наклонной поверхкости дна, первоначально пройденной траншеи, образуют транспортную коммуникацию . Такую последовательность выполнени  операций по вскрытию 3 месторождени  сохран ют до достижени  вскрывающимитранше ми предельного контура разработки, что в комплексе с отсыпкой, вскрышных пород в выработанное пространство дает возможность увеличить угол откоса бортов траншей и тем самым, сократить объем вскрьшных работ. Отработку полезного ископаемого лавой ведут до границы очистной вые ки. Выработанное пространство подземного участка поддерживают заклад кой из отсыпаемых вскрышных пород с отставанием закладки от груди забо  на рассто ние, определ емое отношением величины дoпycти ыx дефор8 мации пород кровли к тангенсу угла прогиба кровли. При подходе лавы к границе очистной выемки транспортные коммуникации срабатывают и. формируют наклонные поверхности дна всхрываюпщх траншей на предельном контуре разработки под углом естественного откоса, а транспортные коммуникации образуют на отсыпаемых породах 5. Такой прием позвол ет снизить объемы вскрышлых работ на предельном контуре разработки. Предлагаемый способ позвол ет снизить себестоимость добычи за счет сокращени  объемов вскрьвоиых работ на 15-17%.The invention relates to the mining industry and can be used in the extraction of minerals in the reservoir and placer deposits of the permafrost conditions. A good way to develop a site | N}, including opening trenches, working out narrow panels, leaving armenian pillars on an open space Ll. The disadvantages of the method are 11. The period of preparation of the field for the start of mining operations, significant loss of minerals, and Also, there is a need for additional measures to preserve the stability of the side walls in summer. The closest to the invention in terms of its technical nature and the result achieved is a combination (development of stratal deposits) including penetration on the flanks of a section of the deposit by opening 1 {x trenches, forming on an inclined bottom of the bottom trenches of transport communications, development with the maintenance of transport communications, tipovide 1 of the trenches of the split production, the mining of mineral lava to the border of the clearing excavation and the laying of nnogo spaces. ; Not E the remainder of the known method is the high cost of production, due to the object of overburden and the need for additional measures itp both long-term stable BOCTI b6; trench mouths. The aim of the inventions is to reduce the development cost by developing the overburden stripping work. The goal is set by those that according to the method of combined development of reservoir deposits, on (d {) ((penetration of the flanks of the plot of m & Communicating from the trash the cuttings, mining the useful 82 minerals from the lava to the border of the clearing recess and laying the mined-out space that penetrates the Before the marginal contour, the development is carried out alternately on each of the flanks of the slit production with dumping of open rock into the developed space; the bottom of the trenches on the marginal contour of the development at an angle of repose, and transport communications form on the rocks. At 4 1g. I shows the location of the trenches in the initial period of the opening, preparation and direction of the development of the cleaning plant} in FIG. 2 - development of mining in the trench and in the underground section; Fig. 3 is the final stage of the development of a plot of the field. Combined development method; Key reservoir deposits is as follows. The ria of the flanks of the plot of field 1 is penetrating the trenches. On the sloping surface of the bottom of the trenches form transport communications 2 In this case, the exit from the trenches is carried out in the direction of mining of the mineral. Opening the flank trenches is connected by wiring. days 3, after which they start mining mineral lava and drive trenches alternately on each of the flanks to the development limit contour with dumping of the open pit rocks into the excavated space 4. The alternate trenching allows simultaneous opening of a deposit on one of the flanks and its testing by the underground section, the opening trench on the other flank serves as a transport link between the underground section and the surface. Then, the opening of the field is carried out by sinking a trench on the other flank, and ON the sloping surface of the bottom, originally passed through the trench, form a transport communication. Such a sequence of operations on opening 3 fields is maintained until the opening of the excavation pipeline’s limit contour, which, combined with dumping, overburden into the developed space, makes it possible to increase the angle of slope of the trenches and thereby reduce the amount of opening work. The mining of minerals by lava lead to the boundary of the sewage treatment plant. The developed space of the underground section is supported by a foundation of dumped overburden with a backlog behind the chest at a distance determined by the ratio of the value of the maximum deformation of the roof rocks to the tangent of the roof deflection. At the approach of lava to the border of the clearing recess transport communications are triggered and. they form inclined surfaces of the bottom of the accumulated trenches on the marginal contour of the development at an angle of repose, and transport communications form on the rocks produced 5. Such a technique allows to reduce the volume of overburden work on the marginal contour of the development. The proposed method makes it possible to reduce the cost of production by reducing the volume of open-pit works by 15-17%.

Claims (1)

СПОСОБ КОМБИНИРОВАННОЙ РАЗРАБОТКИ ПЛАСТОВЫХ МЕСТОРОЖДЕНИЙ,включающий проходку на флангах участка месторождения вскрывающих траншей, что, с целью снижения себестоимости разработки за счёт сокращения объемов вскрышных работ, проходку вскрывающих траншей до предельного контура разработки ведут поочередно на каждом из флангов после проведения разрез ной выработки с отсыпкой вскрышных пород в выработанное пространство, совмещают проходку указанных траншей с отработкой полезного’ископаемого и при подходе лавы к границе очистной выемки срабатывают транспортные коммуникации с формированием наклонных поверхностей дна траншей в на предельном контуре разработки под с образование на наклонной поверхности дна указанных траншей транспортных коммуникаций ;·· проходку траншей углом естественного откоса ,а транс—, портные коммуникации образуют на от- . сыпаемых породах.METHOD FOR COMBINED DEVELOPMENT OF LAYERED DEPOSITS, which includes opening trenches on the flanks of the deposit site, which, in order to reduce the cost of development by reducing the volume of overburden operations, opening trenches to the limit circuit of the development are carried out alternately on each of the flanks after cutting the excavation of loose ground rocks into the worked out space, combine the excavation of these trenches with the mining of minerals and when approaching the lava to the boundary of the treatment excavation transport communications are triggered with the formation of inclined surfaces of the bottom of the trenches in the boundary development circuit under the formation of the indicated trenches of transport communications on the inclined surface of the bottom of the trenches; loose breeds. ко ьо 00kyo 00 N0 ίN0 ί
SU833553335A 1983-02-16 1983-02-16 Method of combination mining of seam deposits SU1122828A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU833553335A SU1122828A1 (en) 1983-02-16 1983-02-16 Method of combination mining of seam deposits

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU833553335A SU1122828A1 (en) 1983-02-16 1983-02-16 Method of combination mining of seam deposits

Publications (1)

Publication Number Publication Date
SU1122828A1 true SU1122828A1 (en) 1984-11-07

Family

ID=21049956

Family Applications (1)

Application Number Title Priority Date Filing Date
SU833553335A SU1122828A1 (en) 1983-02-16 1983-02-16 Method of combination mining of seam deposits

Country Status (1)

Country Link
SU (1) SU1122828A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
I.Максименко А.И. и др. Предпосылки к обоснованию комбинированного способа разработки россыпей СевероВостока. -Разработка вечномерзлых россыпных и рудных месторождений полезных ископаемых, Магадан, 1980,с.55-57. .2.Патент US № 4017122, КЛ.29У-11, опублик. 1977 (прототип). *

Similar Documents

Publication Publication Date Title
RU2344291C2 (en) System of deposit development
SU1122828A1 (en) Method of combination mining of seam deposits
RU2425220C1 (en) Method for formation of steeply inclined transport access track
RU2114307C1 (en) Method for opencast mining of flooded mineral deposits
RU2224107C1 (en) Process of opencast-underground mining of mineral resources
RU2099524C1 (en) Combined method of mining of formation of steeply dipping coal seams
SU706530A1 (en) Trenching method
RU2715503C1 (en) Method for open-underground development of flat-lying formations
SU1323716A1 (en) Method of remining mineral deposits
Hughes et al. The River Aire slope failure at the St. Aidans Extension Opencast Coal Site, West Yorkshire, United Kingdom
SU1763661A1 (en) Method of hydraulic laying of worked space in mining coal beds
RU2798370C1 (en) Method for reconstruction of a flooded mine mined by open-underground method
RU2418168C1 (en) Compound development method of series of gently sloping beds of mine fields
RU2106494C1 (en) Method for handling overburden earth
RU2091583C1 (en) Method of mining of mineral upper horizons
RU2459082C2 (en) Method for extraction of hard mineral resources from deep-lying water-flooded deposit
SU1434107A1 (en) Method of forming opened heading
SU812922A1 (en) Method of consolidating slopes
RU2290510C1 (en) Open underground method for extracting formations of mineral resources
RU1806267C (en) Process of combined development of deposit
SU639995A1 (en) Method of shoring slopes
RU1768754C (en) Method for opencast mining of water-bearing deposits
SU1023085A1 (en) Method of stripping and working deposits in contour-adjoining gones of open mine
SU1735585A1 (en) Open-pit mining method for steep and inclined deposits
RU2215146C1 (en) Method of salt deposit mining