SU649775A1 - Stand for investigating process of filling joints between dam blocks with mortar - Google Patents
Stand for investigating process of filling joints between dam blocks with mortarInfo
- Publication number
- SU649775A1 SU649775A1 SU772501504A SU2501504A SU649775A1 SU 649775 A1 SU649775 A1 SU 649775A1 SU 772501504 A SU772501504 A SU 772501504A SU 2501504 A SU2501504 A SU 2501504A SU 649775 A1 SU649775 A1 SU 649775A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- stand
- mortar
- dam blocks
- filling joints
- investigating process
- Prior art date
Links
Landscapes
- Revetment (AREA)
Description
пружинами 4. Зазор 5 между плитами / и 2 имитирует участок шва. По контуру зазора 5 установлено водонепроницаемое уилотнение 6. На одной из плит 2 смонтированы выпуски 7 дл подачи раствора в зазор 5, соединенные тр-у бками. 8, и дренажна штраба 5. springs 4. The gap 5 between the plates / and 2 simulates the seam area. Along the contour of the gap 5, a waterproof evacuation 6 is installed. On one of the plates 2 are mounted the outlets 7 for feeding the solution into the gap 5, connected by tr-sides. 8, and drainage stresses 5.
Плита 2 может изготовл тьс из железобетона или металла, в последнем случае она снабжена ребрами жесткости 10. Стенд снабжен контрольно-измерительными приспособлени ми //.Plate 2 can be made of reinforced concrete or metal, in the latter case it is equipped with stiffening ribs 10. The stand is equipped with instrumentation //.
Стенд работает следующим образом.The stand works as follows.
Через выпуски 7 и трубки 8 в зазор 5 между плитами У и 2 нагнетают твердеющий раствор, выход которого осуществл етс из дренажной щтрабы 9. Исследование процесса заполнени шва производ т путем анализа динамики изменени давлени , плотности и расхода (раствора в шве по дан ым контрольно-измерительных приспособлений 11. После разъема плит определ ют характер, степень заполнени шва и прочность заполнени .Through the outlets 7 and the tubes 8, a hardening solution is injected into the gap 5 between the plates Y and 2, the output of which is carried out from the drainage layer 9. -measuring devices 11. After connecting the plates, the nature, degree of filling of the seam and strength of filling are determined.
Таким образом, предлагаемый стенд в отличие от известных иозвол ет повысить точность результатов исследовани процесса заполнени щвов между блоками бетонных плотин твердеющим раствором за счет приближени условий проведени исследований к натурным услови м. Thus, the proposed bench, in contrast to the known ones, makes it possible to increase the accuracy of the results of the study of the process of filling the gaps between blocks of concrete dams with hardening mortar by approximating the conditions of the research to natural conditions.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU772501504A SU649775A1 (en) | 1977-06-28 | 1977-06-28 | Stand for investigating process of filling joints between dam blocks with mortar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU772501504A SU649775A1 (en) | 1977-06-28 | 1977-06-28 | Stand for investigating process of filling joints between dam blocks with mortar |
Publications (1)
Publication Number | Publication Date |
---|---|
SU649775A1 true SU649775A1 (en) | 1979-02-28 |
Family
ID=20715477
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU772501504A SU649775A1 (en) | 1977-06-28 | 1977-06-28 | Stand for investigating process of filling joints between dam blocks with mortar |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU649775A1 (en) |
-
1977
- 1977-06-28 SU SU772501504A patent/SU649775A1/en active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
FR2285721A2 (en) | SOLAR BATTERY CONSTRUCTION PROCESS | |
ES454713A1 (en) | Preparing tubing or pipelines for submarine installation | |
SU649775A1 (en) | Stand for investigating process of filling joints between dam blocks with mortar | |
IT1024193B (en) | JOINTS FOR REINFORCED CONCRETE STRUCTURES | |
ES414880A1 (en) | Fairing steel plate structures | |
GB1413330A (en) | Composite stressed wall construction | |
SU763509A1 (en) | Arrangement for studying structural joints | |
JPS57119004A (en) | Steel sheet cell embankment and construction thereof | |
IT982480B (en) | JOINT FOR REINFORCED CONCRETE BRIDGES | |
SU537825A1 (en) | Stand for the manufacture of prestressed concrete elements | |
JPS57155423A (en) | Method of construction of solidification of muddy water | |
GB564938A (en) | Improvements in the production of pre-stressed reinforced concrete sleepers | |
FR2436660A1 (en) | IMPROVEMENTS ON PRESTRESS BENCH MOLDS | |
CH528640A (en) | Method for the foundation of a building element under water | |
JPS5568931A (en) | Construction of block piled retaining wall and block | |
SU428055A1 (en) | TUNNEL TYPE PIPELINE | |
SU694787A1 (en) | Method of the determination of technical efficiency of bulldozers | |
JPS5448902A (en) | Large scale concrete block for civil engineering works | |
Fanelli et al. | Determining dam-breach flood waves: a review and analysis of existing calculation methods | |
JPS57124076A (en) | Hydroelectric power generator | |
JPS57155424A (en) | Executing method for underground outer wall | |
Austin | Field and Laboratory Tests for Safety of Dams Investigation at Salt River Project, Arizona | |
JPS5326414A (en) | Method of reinforced concrete construction by means of plate reinforcement | |
CH509489A (en) | Reinforcement process for a cracked reinforced concrete structure | |
JPS5641933A (en) | Execution method of reinforced concrete structure |