SU620536A1 - Method of erecting reinforced concrete foundation - Google Patents

Method of erecting reinforced concrete foundation

Info

Publication number
SU620536A1
SU620536A1 SU762393451A SU2393451A SU620536A1 SU 620536 A1 SU620536 A1 SU 620536A1 SU 762393451 A SU762393451 A SU 762393451A SU 2393451 A SU2393451 A SU 2393451A SU 620536 A1 SU620536 A1 SU 620536A1
Authority
SU
USSR - Soviet Union
Prior art keywords
foundation
reinforced concrete
ground
pit
creation
Prior art date
Application number
SU762393451A
Other languages
Russian (ru)
Inventor
Виктор Алексеевич Кириллов
Original Assignee
Kirillov Viktor A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kirillov Viktor A filed Critical Kirillov Viktor A
Priority to SU762393451A priority Critical patent/SU620536A1/en
Application granted granted Critical
Publication of SU620536A1 publication Critical patent/SU620536A1/en

Links

Landscapes

  • Foundations (AREA)

Description

1 one

Изобретение относитс  к фундаментостроению и может быть использовано При возведении фундаментов гражданских и промьанленных зданий и сооружений .The invention relates to foundation construction and can be used in the construction of the foundations of civil and industrial buildings.

Наиболее близким к изобретению по технической сущности и достигаемому результату  вл етс  способ возведени  железобетонного фундамента,включающий образование котлована в грунте, уста-Ю новку арматурного каркаса, создание опорной плиты и вертикального элемента l .The closest to the invention to the technical essence and the achieved result is a method of erecting a reinforced concrete foundation, including the formation of a pit in the ground, the installation of a reinforcing cage, the creation of a base plate and a vertical element l.

Согласно этетлу способу предусматриваетс  разработка котлована на всю рину опорной плиты, установка опалуб и и ajwiaTypHoro каркаса и последующее бетонирование, что требует большого объема земл ных работ, а грунтовое основание такого фундамента имеет не- высокие прочностные характеристики, что снижает несущую способность фундамента . According to this method, it is envisaged to develop the excavation of the entire reed of the base plate, install a formwork and ajwiaTypHoro frame and subsequent concreting, which requires a large amount of earthwork, and the soil foundation of such a foundation has low strength characteristics, which reduces the bearing capacity of the foundation.

Цель изобретени  - уменьшение объема земл ных работ и повьнпение несущей способности фундамента.The purpose of the invention is to reduce the volume of land works and to increase the bearing capacity of the foundation.

Это достигаетс  тем, что при осу рествлении предложенного способа возведени  железобетонного фундамента, йключакздего образование котлована в , 30This is achieved by the fact that when the proposed method of erecting a reinforced concrete foundation is implemented, the formation of a pit in, 30

грунте, установку арматурного каркаса, создание опорной плиты и вертикального элемента, котлован разрабатывают шириной, равной ширине вертикального элемента, а создание опорной плиты осуществл ют путем поочередного погружени  на дно котлована железобетонных элементов и горизонтального вдавливани  их в грунт, бетонировани  пространства между ними, причем арматурный каркас устанавливают после вдавливани  железобетонных элементов в грунт перед бетонированием пространства между ними.the ground, the installation of the reinforcement cage, the creation of the base plate and the vertical element, the excavation is developed with a width equal to the width of the vertical element The frame is installed after pressing the reinforced concrete elements into the soil before concreting the space between them.

На фиг.1 изображено горизонтальное вдавливание железобетонных элементов в грунт; на фиг.2 - установка арматурного каркаса на фиг.З - бетонирование .Figure 1 shows the horizontal indentation of reinforced concrete elements in the ground; figure 2 - installation of the reinforcement cage of fig.Z - concreting.

Предлагаемый ::пособ возведени  же:лезобетонного фундамента заключаетс  в следующем.The proposed :: construction aid is the same: a concrete foundation is as follows.

Разрабатывают котлован шириной, равной ширине вертикального элемента фуадгилента. Сборные железобетонные элементы; (консольные части опорной плиты фундгшента) укладывают на дне котлована на поддон 2. В пазах 3 сборных , элементов 1 устанавливают гидроtt62 домкраты 4, соединенные с насосной установкой. Каждый паз 3 закрьшают сверху фартуком 5 , шарнирно прикреп ленным к гидродомкрату 4,предотвращающим попадание грунта внутрь. Противоположный конец домкрата опирают на пластину 6, распредел ющую давление домкрата на грунтовую стену кот ,лрвана. Под действием гидродомкрата желе- эобетонный элемент 1 вдавливаетс  р грунт. При нехватке хода домкрата ме ду стеной котлована и пластиной 6 .вкладывают дерев нные брусь  7. Выпус ки арматуры 8 железобетонных элементе 1 объедин ют с арматурньми стерж н ми 9 монолитной части 10 опорной плиты, причем отогнутые концы 11 арматурн к стержней 9 завод т в петли арматуры 8 и загибают. Затем в котлован устанавливают арматурный ка|жас 12 вертикального элемента 13, бетонируют монолитную часть 10 опорной плиты между элементами 1 и верти кальный элемент 13, использу  в качестве опалубки стены котлована. Бетонирование вертикального элеме та в распор со стенами котлована обеспечивает надежное сцепление боко вой поверхности фундамента со сло ми ненарушенного грунта, а вдавливание консольных частей опорной плиты создает в грунте зону уплотнени , JTO существенно повышает несущую способ3 уA pit is developed with a width equal to the width of the vertical element of the fugilent. Precast reinforced concrete elements; (cantilever parts of the base plate of the foundation) are placed on the bottom of the pit on the pallet 2. In the slots 3 of the prefabs, elements 1, hydrott62 jacks 4 are installed, connected to the pump unit. Each groove 3 is closed with an apron 5 on top, pivotally attached to the hydrojack 4, which prevents the ingress of soil into it. The opposite end of the jack is supported on the plate 6, which distributes the pressure of the jack on the cat wall, which is broken. Under the action of the jack, the gel-concrete element 1 is pressed into the ground. If there is a shortage of the jack stroke between the wall of the excavation and the plate 6, wooden bars 7 are inserted. Reinforcement 8 of reinforced concrete element 1 is combined with reinforcing rods 9 of the solid part 10 of the base plate, and the bent ends 11 of the reinforcement to the rods 9 are turned into rebar loop 8 and bend. Then, a reinforcing junction 12 of the vertical element 13 is installed in the pit, the monolithic part 10 of the base plate between the elements 1 and the vertical element 13 are concreted, using the walls of the excavation as the formwork. Concreting a vertical element into a ram with the walls of the excavation ensures reliable adhesion of the lateral surface of the foundation with layers of undisturbed soil, while pressing in the cantilever parts of the base plate creates a compaction zone in the soil, JTO significantly increases the load-bearing method

шsh

в tin t

фиг 1fig 1

J5W : w5w4% WJ5W: w5w4% W

Claims (1)

Хл ность фундамента. Кроме того, значительно сокращаетс  объём земл ных работ и исключаетс  использование опалубки. Формула изобретени . Способ возведени  железобетонного фундамента, включающий образование котлована в грунте, установку арматурного каркаса, создание опорной плиты и вертикального элет«1ента, о т л ичаюЬ ийс  тем, что, с целью уменьшени  объема земл ных работ и повышени  несущей способности фундамента , котлован образуют шириной, равной ширине вертикального элемента, а создание опорной плиты осуществл ют путем поочередного погружени  на дно котлована железобетонных элементов и горизонтального вдавливани  их в грунт, бетонировани  пространства между ними, пркч&л арматурный каркас устанавливают после вдавливани  железобетонных элементов в грунт перед бетонированием пространства между ними. Источники информации, прин тые во внимание при экспертизе: 1, Справочник по общестроительным работам. Основани  и фундаменты. М., Стройиздат, 1974, с, 116-118, рис. 1У-16.Chlnost foundation. In addition, the volume of earthworks is significantly reduced and formwork is eliminated. Claims. The method of erection of reinforced concrete foundation, including the formation of a pit in the ground, the installation of a reinforcement cage, the creation of a base plate and a vertical flat panel, which, in order to reduce the volume of earthworks and increase the bearing capacity of the foundation, form a pit, equal to the width of the vertical element, and the creation of the support plate is carried out by alternately immersing reinforced concrete elements on the bottom of the excavation and horizontal pressing them into the ground, concreting the space between it and, install & l reinforcement cage is installed after pressing concrete elements into the ground before concreting the space between them. Sources of information taken into account in the examination: 1, Handbook of general construction work. Foundations and foundations. M., stroiizdat, 1974, p. 116-118, fig. 1U-16. VX WW Wi;; X%: S 5%VX WW Wi ;; X%: S 5% фце.2fts.2
SU762393451A 1976-08-05 1976-08-05 Method of erecting reinforced concrete foundation SU620536A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU762393451A SU620536A1 (en) 1976-08-05 1976-08-05 Method of erecting reinforced concrete foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU762393451A SU620536A1 (en) 1976-08-05 1976-08-05 Method of erecting reinforced concrete foundation

Publications (1)

Publication Number Publication Date
SU620536A1 true SU620536A1 (en) 1978-08-25

Family

ID=20673106

Family Applications (1)

Application Number Title Priority Date Filing Date
SU762393451A SU620536A1 (en) 1976-08-05 1976-08-05 Method of erecting reinforced concrete foundation

Country Status (1)

Country Link
SU (1) SU620536A1 (en)

Similar Documents

Publication Publication Date Title
CN106088650B (en) A kind of method and building suitable for building with brick-concrete structure underground increasing layer
US20030233798A1 (en) Post-tensioned, below-grade concrete foundation system
US5433557A (en) Method for underpinning an existing footing
CN212801564U (en) Foundation ditch steel sheet pile supporting construction
SU620536A1 (en) Method of erecting reinforced concrete foundation
US3091938A (en) Method and structure for underpinning
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
FI74096B (en) FOERFARANDE FOER FRAMSTAELLNING AV FUNDAMENT FOER EN KONSTRUKTION OCH ETT I FOERFARANDET ANVAENT MELLANSTYCKE.
JPS62288269A (en) Method for extending underground stair of building
JPH03262833A (en) Construction of underground floor
RU2130996C1 (en) Method of reinforcement of strip foundation
JP3057466B2 (en) How to build underground structures
RU212965U1 (en) FOUNDATION STRUCTURE OF SHALLOW PLACE ON ADJUSTABLE BALL JOINTS
JPS611729A (en) Construction of foundation for structure
RU220490U1 (en) Precast concrete foundation
SU607888A2 (en) Foundation for buildings and structures
CN217758906U (en) Assembled anti-settlement beam slab foundation structure
RU2229562C1 (en) Method of dangerous and reconstruct able building foundations reinforcement
RU2692383C1 (en) Reinforcing tape shallow foundation method
RU2045627C1 (en) Wall of underground structure
US4796398A (en) Foundation of a building or installation erected across a ravine extending along a slope
SU958594A1 (en) Prefabricated-monolythic wall in soil
JPH07894B2 (en) Construction method for underground wall
RU1789632C (en) Method of superstructing a building
GB2381014A (en) Load bearing pile in line of perimeter wall