SU1612082A1 - Method of mining sloping thick ore deposits - Google Patents

Method of mining sloping thick ore deposits Download PDF

Info

Publication number
SU1612082A1
SU1612082A1 SU884647418A SU4647418A SU1612082A1 SU 1612082 A1 SU1612082 A1 SU 1612082A1 SU 884647418 A SU884647418 A SU 884647418A SU 4647418 A SU4647418 A SU 4647418A SU 1612082 A1 SU1612082 A1 SU 1612082A1
Authority
SU
USSR - Soviet Union
Prior art keywords
ore
development
mining
workings
reducing
Prior art date
Application number
SU884647418A
Other languages
Russian (ru)
Inventor
Александр Валентинович Максимов
Владимир Иванович Штеле
Дмитрий Михайлович Бронников
Казбек Георгиевич Каргинов
Original Assignee
А. В. Максимов, В. И.,Штеле, Д. М. Бронников и К Г. Каргинов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by А. В. Максимов, В. И.,Штеле, Д. М. Бронников и К Г. Каргинов filed Critical А. В. Максимов, В. И.,Штеле, Д. М. Бронников и К Г. Каргинов
Priority to SU884647418A priority Critical patent/SU1612082A1/en
Application granted granted Critical
Publication of SU1612082A1 publication Critical patent/SU1612082A1/en

Links

Abstract

Изобретение относитс  к разработке сильнонарушенных руд. Цель изобретени  - повышение производительности горных работ за счет снижени  интенсивности разрушени  выпускных выработок и снижени  потерь руды при разработке сильнонарушенных рудных залежей. Осуществл ют подготовку залежи к разработке. Отработку камер производ т лентами, которые отрабатывают сло ми. Выработанное пространство лент закладывают твердеющими смес ми. В закладочном массиве оформл ют воронки и выработки днища. До отбойки отрабатываемой ленты на границе с последующей лентой формируют вертикальный упрочн ющий слой руды бурением скважин. Затем осуществл ют восход щую отбойку слоев в ленте. В кровле слоев образуют выемки зеркально относительно выпускных выработок днище первоначальным взрыванием скважин в центре выемки и последующим взрыванием остальных скважин по ее периметру. Выпуск и отгрузку руды ведут через выработки днища с формированием рудной подушки на бетонном днище камеры. 3 ил.The invention relates to the development of highly ores. The purpose of the invention is to increase the productivity of mining by reducing the intensity of the destruction of the exhaust workings and reducing the loss of ore during the development of highly disturbed ore deposits. The reservoir is being prepared for development. Chambers are manufactured by ribbons, which are worked out in layers. The developed space of tapes is laid with hardening mixtures. Funnels and bottom workings are formed in the filling array. Prior to the breaking of the tape being worked, a vertical reinforcing layer of ore is drilled at the border with the subsequent tape. Then, an upward shearing of the layers in the belt is carried out. In the top of the layers, the grooves are mirrored relative to the exhaust workings at the bottom of the initial blasting of wells in the center of the excavation and the subsequent blasting of the remaining wells along its perimeter. The release and shipment of ore lead through the development of the bottom with the formation of the ore cushion on the concrete bottom of the chamber. 3 il.

Description

Изобретение относитс  к горной промышленности и может быть использовано при отработке cильнoнapyuJeнныx горизонтальных и пологих рудных тел большой мош- ности.The invention relates to the mining industry and can be used in the mining of strong horizontal and flat ore bodies of great magnitude.

Цель изобретени  - повышение производительности горных работ за счет снижени  интенсивности процесса разрушени  выпускных выработок и снижени  потерь руды при разработке сильнонарушенных рудных залежей.The purpose of the invention is to increase the productivity of mining by reducing the intensity of the process of destroying exhaust workings and reducing the loss of ore during the development of highly disturbed ore deposits.

На фиг. 1 изображены вынимаемые ленты, поперечное сечение, вертикальный разрез; на фиг. 2 - разрез А-А на фиг. 1 (по горизонту выпуска и доставки руды); на фиг. 3 - разрез Б-Б на фиг. 2 (в отрабатываемой камере).FIG. 1 shows removable tapes, cross section, vertical section; in fig. 2 shows section A-A in FIG. 1 (on the horizon of production and delivery of ore); in fig. 3 shows a section BB in FIG. 2 (in the working chamber).

Способ осушествл етс  следуюшим образом .The method is as follows.

Осуществл ют подготовку залежи к разработке . Пологопадающую мощную рудную залежь 1 отрабатывают комбинированным вариантом слоевой системы с закладкой выработанного пространства твердеющими смес ми. Лента 2 последней отрабатываетс  этим пор дком по рудам средней нарушен- ности. С переходом горных работ на последующие ленты 3 и 4 руды в них определены как сильнонарушенные, что не дает возможность отбивать слои в восход щем пор дке из-за опасности обрушений в очистное пространство . В этом случае возможен, переход на сплошную камерную систему разработки без захода людей в очистное пространство . Дл  этого в закладочном массиве ленты 2 по почве проходит транспортно- доставочный штрек 5 (ТДШ). Параллельно с проходкой штрека вынимают нижнююThe reservoir is being prepared for development. The hard-falling powerful ore deposit 1 is worked out with a combined version of the layered system with the laying of the developed space with hardening mixtures. Tape 2 of the latter is processed by this order for medium-disturbed ores. With the transfer of mining operations to subsequent ribbons 3 and 4, the ores in them are identified as strongly broken, which makes it impossible to beat the layers in an upward order because of the danger of collapses into the clearing space. In this case, it is possible to switch to a continuous chamber development system without people entering the cleaning space. For this, in the filling array of the tape 2, the soil passes a transport and delivery drift 5 (TDSH). In parallel with the drift drift, take out the bottom

О)ABOUT)

tctc

оabout

0000

юYu

часть ленты 3 известным кровлеуступным или почвоуступным способом с горизонтальным располг жением шпуров.a portion of the tape 3 in a known krovleustupnom or soil-access method with the horizontal location of the holes.

После отработки нижней части ленты выработанное пространство закладываетс  с иедозакладом твердеющими смес ми с повы- |шенным содержанием в жущего.After the lower part of the tape has been worked out, the developed space is laid out with a deposit inlet by hardening mixtures with an increased content in the ghost.

С ТДШ 5 под углом к нему до середины ленты 3 через 12 м проход тс  заезды 6. Из зоны заезда 6, наход щейс  в камере, азбуриваетс  бетон под полуворонку с по- :ледующим формированием трех скатов ее од углом естественного откоса отбивае- ой горной массы.From TPS 5 at an angle to it to the middle of the belt 3, races 6 are passed through 12 meters. From the zone of arrival 6 in the chamber, concrete is half-cracked, with the following: followed by the formation of three slopes one angle of repose of the mountain masses.

Извлекаемый .в результате проходки ГДШ, за ездов, разделки полуворонки бетон этгружаетс  в подготовленную под закладку амеру.The concrete that is retrieved as a result of penetration of the GDSh, for driving, cutting the half-funnel, is loaded into the amera prepared for the laying.

Под железобетонным перекрытием рудной тал щи 7 по оси границ лент 3 и 4 проходитс  вентил ционный штрек 8, который азбуривают до границы ленты 2 (т.е. до „етона) и, взрыванием с последующей за- нисткой подготавливают подсечку 9, из которой производ т обуривание рудного массива Нисход щими вертикальными скважинами ;10, а также вдоль рудного борта под- Сечки на границе отрабатываемой и после- |дующей лент забуривают р д скважин 11 1од канатные анкера (до уровн  верхних Гребней бетонных откосов). До отбойки ленты в скважины 11 ввод т канатные анкера , подают порцию бетона и после схва- гывани  его напр гают канаты и заливают 1скважины до усть . Таким образом фор- ируетс  вертикальный слой упрочненной уды, преп тствующий обрущени м горной ассы с бортов камеры в очистное про- |странство.Under the reinforced concrete overlap of ore tare 7 along the axis of the edges of the belts 3 and 4, a ventilation drift 8 passes, which is encased up to the border of the belt 2 (i.e., to the “tone”) and cutting 9 is made by blasting followed by cleaning. t the ore massif downsizing with the descending vertical wells; 10, as well as along the ore flange under the Sechka, at the border of the working and subsequent tapes, a number of wells 11 and one of the cable anchors are drilled (to the level of the upper ridge of concrete slopes). Before breaking the tape, cable anchors are introduced into wells 11, a portion of concrete is supplied and, after it has been grabbed, the ropes are strung and the wells are poured to the mouth. In this way, a vertical layer of reinforced beams is formed, which prevents the collapse of the mountain asy from the sides of the chamber to the clearing space.

; После частичной отгрузки бетона из за- |ездов осуществл ют слоевую восход щую Отбойку запасов, секционно взрыва  скважины . Отбойку слоев осуществл ют с образованием в кровле выемок, зеркально отображающих полуворонки днища (контур Отрыва сло  показан на фиг. 1 и 3 пунктиром ). При инициировании скважин с целью предохранени  бетонных откосов первоначально взрываютс  центральные скважины зеркальной выемки с образованием врубовой полости, а затем последовательно все отдельные по периметру полости. Отгрузку руды ведут с формированием рудной по- дущки на бетонном днище, не обнажа  бетонные гребки откосов.; After partial shipment of the concrete from the driveway, layer-by-layer breaking up of reserves, sectional explosion of the well is carried out. The stripping of layers is carried out with the formation of recesses in the roof that mirror the bottom half-funnels (the layer of separation of the layer is shown in Fig. 1 and 3 with a dotted line). When wells are initiated, in order to protect the concrete slopes, the central wells of the mirror-like excavation initially blow up to form the heel cavity, and then all the individual cavities around the perimeter are sequentially. The shipment of ore is carried out with the formation of the ore feeder on the concrete bottom, without exposing the concrete padding of the slopes.

После окончани  отбойки руды на всюAfter the end of ore breaking

высоту камеры и отгрузки горной массы с помощью обычных погрузочно-доставочных мащин (ПДМ) на зачистке днища и бетонных скатов используют ПДМ с дистанционным управлением. При отработке ленты 4the height of the chamber and the shipment of rock mass using conventional loading and hauling machines (PDM) to clean the bottom and concrete slopes use remote-controlled PDM. When working out the tape 4

канатные анкера скважин И извлекают и после прока-тки через обжимные валики с целью удалени  с них бетона используют повторно.The cable anchors of the wells are both removed and, after being rolled through the squeeze rollers, in order to remove concrete from them, they are reused.

2020

Claims (1)

Формула изобретени Invention Formula Способ разработки мощных рудных по- логопадающих залежей, включающий подготовку залежи к разработке, отработку камерных запасов лентами с закладкой выработанного пространства лент твердеющей смесью, оформление воронок и выработок днища в закладочном массиве и выпуск руды через выработки днища, отличающийс  тем, что, с целью повышени  производительности горных работ зат счет сни0 жени  интенсивности процесса разрущени  выпускных выработок и снижени  потерь руды при разработке сильнонарущенных рудных залежей, от отбойки отрабатываемой ленты на ее границе с последующей лентой формируют вертикальный упрочнен5 ный слой руды, затем осуществл ют восход щую отбойку ленты сло ми, при этом в кровле формируют выемки, зеркально относительно выпускных выработок днища первоначальным взрыванием скважин в центре выемки и последующим взрыванием остальныхA method of developing powerful ore-occurring deposits, which includes preparing the deposit for development, mining chamber stocks with tapes with laying the developed space of tapes with a hardening mixture, shaping the craters and bottom workings in the filling mass, and releasing ore through bottom mining, characterized in mining productivity at the expense of reducing the intensity of the process of destroying exhaust workings and reducing ore losses in the development of highly-damaged ore deposits, from breaking down oh the tape at its edge with a subsequent vertical ribbon form uprochnen5 ny layer ore is then carried out the breaking of the ascending belt layers, wherein the recess is formed in the roof, the outlet openings specularly relative to original bottom blasting holes in the center of the recess and then blasting the remaining скважин по ее периметру, а отгрузку руды производ т с формированием рудной подушки на бетонном днище камеры. boreholes along its perimeter, and shipment of ore is carried out with the formation of an ore cushion on the concrete bottom of the chamber. / // / Д , /, ... А -.. v7TT7 АЛ . ft . . . д. Х- .. VA i- - АD, /, ... A - .. v7TT7 AL. ft. . . d. X- .. VA i- - A Г . . рG. . R / // / . v7TT7 . VA i- . v7TT7. VA i- //// г.2d.2
SU884647418A 1988-12-26 1988-12-26 Method of mining sloping thick ore deposits SU1612082A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884647418A SU1612082A1 (en) 1988-12-26 1988-12-26 Method of mining sloping thick ore deposits

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884647418A SU1612082A1 (en) 1988-12-26 1988-12-26 Method of mining sloping thick ore deposits

Publications (1)

Publication Number Publication Date
SU1612082A1 true SU1612082A1 (en) 1990-12-07

Family

ID=21427339

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884647418A SU1612082A1 (en) 1988-12-26 1988-12-26 Method of mining sloping thick ore deposits

Country Status (1)

Country Link
SU (1) SU1612082A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102748028A (en) * 2012-07-18 2012-10-24 中南大学 Building block type constructing method of standardized prefabricated module of bottom structure of underground mining
CN106761842A (en) * 2017-03-17 2017-05-31 新疆大学 A kind of method of underground mining bottom moat ditch inner lining structure reclaiming of residual ore

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Бронников Д. М. и др. Основы технологии подземной разработки рудных месторождений с закладкой. М.: Наука, 1973, с. 114-116. Гребенюк В. А. и др. С правочник по горнорудному делу. М.: Недра, 1983, с. 494. *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102748028A (en) * 2012-07-18 2012-10-24 中南大学 Building block type constructing method of standardized prefabricated module of bottom structure of underground mining
CN106761842A (en) * 2017-03-17 2017-05-31 新疆大学 A kind of method of underground mining bottom moat ditch inner lining structure reclaiming of residual ore
CN106761842B (en) * 2017-03-17 2018-12-18 新疆大学 A kind of method of underground mining bottom moat ditch inner lining structure reclaiming of residual ore

Similar Documents

Publication Publication Date Title
SU1612082A1 (en) Method of mining sloping thick ore deposits
SU1710742A1 (en) Method of mining thick gently-dipping ore deposits
SU706536A1 (en) Method of mining great ore deposits
US4440448A (en) Method for opening mineral deposit and subsequent mining thereof
RU2148712C1 (en) Method for underground development of ore deposits
SU898074A1 (en) Method of working gently sloping ore deposits
RU2093678C1 (en) Method for mining thick steep ore bodies
SU1129354A1 (en) Method of underground working of mineral deposits
SU829953A1 (en) Method of excavating support pillars
SU1162977A1 (en) Method of mining thin steep veins
SU742589A1 (en) Method of mining super-thin sharply assending seams
SU905467A1 (en) Method of working unstable ores
SU898071A1 (en) Method of working ore deposits
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
SU750072A1 (en) Method of working sloping ore deposits
SU742590A1 (en) Method of mining sharply ascending ore bodies
SU920216A1 (en) Method of working ore deposits
SU883459A1 (en) Tunnel construction method
SU602684A1 (en) Method of mining mineral deposits
RU1803563C (en) Method of working ore deposits
SU812922A1 (en) Method of consolidating slopes
SU1065600A1 (en) Method of working mineral deposits
SU1335702A1 (en) Method of mining ore in chamber-and-pillar system
SU1252492A1 (en) Method of driving an ascending mine working
SU1629538A1 (en) Method of mining mineral deposits