SU1578341A1 - Method of mining ore body - Google Patents

Method of mining ore body Download PDF

Info

Publication number
SU1578341A1
SU1578341A1 SU884479299A SU4479299A SU1578341A1 SU 1578341 A1 SU1578341 A1 SU 1578341A1 SU 884479299 A SU884479299 A SU 884479299A SU 4479299 A SU4479299 A SU 4479299A SU 1578341 A1 SU1578341 A1 SU 1578341A1
Authority
SU
USSR - Soviet Union
Prior art keywords
panel
workings
ore
drilling
delivery
Prior art date
Application number
SU884479299A
Other languages
Russian (ru)
Inventor
Евгений Александрович Белкин
Вячеслав Васильевич Шкиль
Александр Иосифович Сигаев
Алексей Романович Хариноев
Original Assignee
Иркутский государственный научно-исследовательский институт редких и цветных металлов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Иркутский государственный научно-исследовательский институт редких и цветных металлов filed Critical Иркутский государственный научно-исследовательский институт редких и цветных металлов
Priority to SU884479299A priority Critical patent/SU1578341A1/en
Application granted granted Critical
Publication of SU1578341A1 publication Critical patent/SU1578341A1/en

Links

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

Изобретение относитс  к подземной разработке крутопадающих месторождений. Цель - снижение разубоживани  руды и затрат на добычу и повышение безопасности работ. Выемку руды осуществл ют панел ми. Панели отрабатывают всплошную. Запасы обуривают и отбивают из буровых выработок /БВ/. При этом БВ и доставочные выработки /ДВ/ проход т шириной, равной ширине панели. При этом ДВ каждой подлежащей к отработке панели формируют в почве последующей смежной панели, а БВ подлежащей к отработке панели проход т в этой панели со ступенчатым смещением по вертикали по кровле ДВ отработанной смежной панели, заложенной твердеющей смесью. Отбитые запасы панели выпускают через погрузочные заезды между БВ и ДВ. При этом формирование погрузочных заездов в отрабатываемую панель осуществл ют под БВ этой панели установкой пневмооболочек в ДВ отработанной панели перед ее закладкой с последующим извлечением пневмооболочек после затвердевани  закладки. Отбитую руду транспортируют по ДВ. Выработанное пространство панелей и подготовительных выработок закладывают твердеющими смес ми. 3 ил.The invention relates to steeply dipping underground mining. The goal is to reduce the dilution of ore and the cost of production and increase safety of work. The ore is excavated by panels. Panels work out the continuum. Stocks are clogged and discarded from drilling workings / BV /. At the same time, the BV and delivery openings / DV / are made in a width equal to the width of the panel. At the same time, the LW of each panel to be worked out is formed in the soil of the subsequent adjacent panel, and the BV of the panel to be tested is passed in this panel with a stepped displacement vertically along the roof of the LW waste adjacent panel laid with a hardening mixture. Repulsed stocks of the panel are released through the loading races between BV and LW. In this case, the formation of loading races into the panel being worked out is carried out under the BV of this panel by installing the air shells in the DV of the waste panel before it is laid down with the subsequent removal of the air shells after the bookmark is solidified. Broken ore is transported in the Far East. The developed space of the panels and preparatory workings are laid with hardening mixtures. 3 il.

Description

Изобретение относитс  к горнодобывающей промышленности и может быть использовано при подземной разработке крутопадающих месторождений ценных руд, залегающих в сложных горно-геологических услови х, с закладкой выработанного пространства твердеющей смесью.The invention relates to the mining industry and can be used in the underground mining of steeply dipping deposits of valuable ores occurring in difficult mining and geological conditions, with the laying of the developed space with a hardening mixture.

Цель изобретени  - снижение разубо- живани  руды и затрат на добычу и повышение безопасности работ.The purpose of the invention is to reduce ore cutting and mining costs and increase work safety.

На фиг.1 показана схема отработки выемочного участка, разрез по простиранию рудного тела; на фиг.2 - разрез А-А на фиг.1, (схема подготовки днища выемочного участка); на фиг.З - схема формировани  погрузочных заездов.Figure 1 shows the scheme of mining mining site, a section along the strike of the ore body; figure 2 - section aa in figure 1, (the scheme of preparation of the bottom of the excavation site); FIG. 3 is a diagram of the formation of loading races.

Способ осуществл етс  следующим образом .The method is carried out as follows.

Выемочный участок (блок, этаж, подэтаж и др.) 1 отрабатывают всплошную вертикальными панел ми 2, которые подготавливают буровыми выработками 3 и до- ставочными выработками 4, соединенными между собой погрузочными заездами 5 (фиг.1 и 2). Буровую выработку 3 располагают всплошную к предыдущей буровой выработке 6 отработанной панели, заложенной твердеющей закладкой, и проход т по контуру подлежащей к отработке панели 2 по кровле 7 доставочной выработки отработанной смежной панели. Доставочную выработку 4 каждой подлежащей к отработкеThe excavation area (block, floor, basement, etc.) 1 is worked out by vertical panels 2, which are prepared by drilling workings 3 and extension workings 4 connected by loading races 5 (Figures 1 and 2). The drilling production 3 is positioned flush with the previous drilling production 6 of the used panel, laid down by the hardening tab, and passes along the contour of the panel 2 to be tested on the roof 7 of the delivery generation of the used adjacent panel. Delivery production 4 each subject to development

елate

х|x |

OSOS

саsa

NN

«Jl"Jl

панели провод т в почве последующей смежной панели 8. При этом выработки 3 и 4 проход т со ступенчатым смещением по вертикали по отношению одна к другой и располагают всплошную к аналогичным вы- работкам отработанной панели,the panels are carried out in the soil of the subsequent adjacent panel 8. At the same time, the openings 3 and 4 are passed with a stepwise vertical shift relative to one another and have a full facet of similar panel

Отработка крутопадающих рудных тел со сплошной выемкой руды вертикальными панел ми, при которой буровые идоставоч- кые выработки проход т по контуру пане- лей (т.е. ширина панели равна ширине выработки), позвол ет вести отработку запасов с небольшой площадью обнажени  вис чего бока, что обеспечивает его сохранность при неустойчивых вмещающих поро- дах, т.е. исключает самообрушение пород вис чего бока в очистное пространство панели и, следовательно, обеспечивает повышение безопасности ведени  горных работ, снижает разубоживание руды и затраты на выемку.Working out steeply dipping ore bodies with a continuous excavation of ore with vertical panels, in which drilling and part mining workings pass along the contour of the panels (i.e., the width of the panel is equal to the width of production), allows the development of reserves with a small surface area of which the sides are exposed. that ensures its preservation under unstable host rocks, i.e. eliminates the self-destruction of rocks of the hanging side into the cleaning space of the panel and, therefore, improves the safety of mining, reduces the dilution of ore and the cost of excavation.

После проведени  подготовительных работ приступают к очистной выемке панели 2. Из буровой выработки 3 производ т бурение скважин 9 и послойную отбойку руды (фиг.1). Отгрузку отбитой руды ведут через погрузочные заезды 5 по доставочной выработке 4 (фиг.2). Формирование погрузочных заездов в отрабатываемую панель осуществл ют под буровой выработкой этой панели. Дл  этого после отработки панели 2 в ее доставочной выработке 4 отработанной панели размещают пневмооболочки 10 (фиг.З), размеры которых равны размерам погрузочных заездов 5. Затем очистное про- странство отработанной панели 2 с соответствующими подготовительными выработками 3, 4 и заездов 5 изолируют и заполн ют твердеющей смесью. После набора закладкой необходимой прочности цикл подготовки и очистной выемки очередной панели 8 повтор ют аналогичным способом . В процессе подготовки панели 8After the preparatory work is carried out, they start cleaning the excavation of panel 2. Drilling wells 3 and layered ore blasting are made from drilling production 3 (figure 1). The shipment of broken ore lead through the loading races 5 on the delivery formulation 4 (figure 2). The formation of loading runs into the panel being worked out is carried out under the drilling development of this panel. To do this, after working the panel 2 in its delivery development 4 of the used panel, pneumatic shells 10 (FIG. 3) are placed, the dimensions of which are equal to the size of the loading races 5. Then the cleaning space of the used panel 2 with the corresponding preparatory workings 3, 4 and races 5 isolate and filled with hardening mixture. After setting the required strength with a pad, the cycle of preparation and cleaning of the next panel 8 is repeated in the same way. In the process of preparing panel 8

пневмооболочки 10 извлекают из доставочной выработки 4, заложенной твердеющей закладкой, образу  очередные погрузочные заезды. Таким способом отрабатывают рудное тело на прот жении всего горизонта. Выемку запасов на нижележащем горизонте производ т вышеописанным способом под защитой искусственного массива из твердеющей закладки.the air shells 10 are removed from the delivery making 4, laid down by a hardening tab, to form the next loading runs. In this way, the ore body is processed throughout the entire horizon. Inventories in the underlying horizon are removed in the manner described above under the protection of an artificial array of hardening bookmarks.

Claims (1)

Формула изобретени  Способ разработки рудных тел, включающий сплошную выемку руды вертикальными панел ми, проведение буровых и доставочных выработок и погрузочных заездов между буровыми и доставочными выработками , обуривание и отработку запасов панели из буровой выработки, отгрузку руды через погрузочные заезды, транспортирование ее по доставочным выработкам и закладку выработанного пространства панелей и подготовительных выработок твердеющими смес ми,отличающийс  тем, что, с целью снижени  разубоживани  руды и затрат на добычу и повышени  безопасности работ, буровые и доставочные выработки проход т шириной, равной ширине панели, при этом доставочную выработку каждой подлежащей к отработке панели формируют в почве последующей смежной панели, а буровую выработку подлежащей к отработке панели проход т в этой панели со ступенчатым смещением по вертикали по кровле доставочной выработки отработанной смежной панели, заложенной твердеющей смесью, причем формирование погрузочных заездов в отрабатываемой панели осуществл ют под буровой выработкой этой панели установкой пневмооболочек в доставочной выработке отработанной панели перед ее закладкой с последующим извлечением пневмооболочек после затвердевани  закладки.The invention The method of developing ore bodies, including a continuous excavation of ore by vertical panels, carrying out drilling and delivery workings and loading races between drilling and delivery workings, drilling and mining reserves of the panel from the drilling workings, shipping the ore through loading races, transporting it through delivery workings and laying the worked-out space of the panels and preparatory workings with hardening mixtures, characterized in that, in order to reduce the dilution of ore and the cost of mining Increasing the safety of work, drilling and delivery workings are made a width equal to the width of the panel, while the production workings of each panel to be worked out are formed in the soil of the subsequent adjacent panel, and the workings of the panel to be tested are passed in stepwise offset verticals on the roof of the delivery formulation of the waste adjacent panel laid down by a hardening mixture, the formation of loading races in the panel being worked out is carried out under the drilling development of this panel installing the air shells in the delivery development of the waste panel before it is laid, with the subsequent removal of the air shells after the bookmark is solidified. У . W. : ::v: : 4v yrv:ts/ iV:-.:&:.:-«:: :: v:: 4v yrv: ts / iV: -.: &:.: - “: : .i . 7м.. . -о --о .. NA .V Л .  : .i. 7m .. -o -o .. NA .V l. : о: about .v-l .: ..v-l.:. б . оb. about .-.. р. „ t . О-Ь... .-.. R. „T. Oh ... . О «-.I. About "-.I МЙMY 5 3 75 3 7 -в«,гв  -in ", gv X;: iv .i -V-ivMX ;: iv .i -V-ivM ° о   ° o I . J -I I. J -I :.т/л: .t / l V.; :p.v . «.V .; : p.v. ". / J- -. lV./ J- -. lV. /у|Щ /7y | y / 7 Фиг.11 Фиг. 2FIG. 2 10 10 410 10 4 -.. M-:,J - .. M -:, J .. 1 ,i.«;. К.. 1, i. “;. TO -J . -:-J. -: чh «.  ". .IV-T. .IV-T. v..To-Д-;v..To-D-; v:-;t -;v: -; t -; fl . . Оfl. . ABOUT .о - о .o - about Фаг.ЗPhage.Z
SU884479299A 1988-09-01 1988-09-01 Method of mining ore body SU1578341A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884479299A SU1578341A1 (en) 1988-09-01 1988-09-01 Method of mining ore body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884479299A SU1578341A1 (en) 1988-09-01 1988-09-01 Method of mining ore body

Publications (1)

Publication Number Publication Date
SU1578341A1 true SU1578341A1 (en) 1990-07-15

Family

ID=21397813

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884479299A SU1578341A1 (en) 1988-09-01 1988-09-01 Method of mining ore body

Country Status (1)

Country Link
SU (1) SU1578341A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2445461C1 (en) * 2010-09-22 2012-03-20 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Method to mine thick steep deposits of unstable ores

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 905470, кл. Е21 С 41/06, 1980. Авторское свидетельство СССР №1182168, Кл. Е21 С 41/06, 1984. *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2445461C1 (en) * 2010-09-22 2012-03-20 Государственное образовательное учреждение высшего профессионального образования "Санкт-Петербургский государственный горный институт имени Г.В. Плеханова (технический университет)" Method to mine thick steep deposits of unstable ores

Similar Documents

Publication Publication Date Title
US4458947A (en) Mining method
SU1578341A1 (en) Method of mining ore body
RU2010972C1 (en) Method of working interchamber pillar
SU1615366A1 (en) Method of controlling the process of rock shift under protected objects
SU1571249A1 (en) Method of making artificial roof coal of chamber
SU1421015A1 (en) Mining method
SU898065A1 (en) Method of excavating minerals by auger-drill unit
SU907256A1 (en) Method of mining steep ore bodies
SU1219806A1 (en) Method of mining thick gently-sloping ore deposits
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
SU1335702A1 (en) Method of mining ore in chamber-and-pillar system
SU1642005A1 (en) Method of mining ore deposits
SU825962A1 (en) Method of controlling hard-to-cave roofs
SU1071003A1 (en) Method of underground leaching of useful minerals from ore bodies
RU1819998C (en) Method for extraction of steeply dipping ore bodies of small and medium thickness and filling of worked out spaces
SU1265334A1 (en) Method of deposit-mining
SU621879A1 (en) Method of excavating orebodies
SU1364726A1 (en) Method of mining gently-sloping ore deposits
SU512290A1 (en) The method of underground mining of ore deposits
SU796428A1 (en) Method of working gently sloping and sloping adjoining coal beds
RU2083833C1 (en) Method for development of steep coal seams with backing worked-out area
SU1091641A1 (en) Method of developing steep ore bodies
SU829950A1 (en) Method of working adjacent sloping beds of minerals
SU1481406A1 (en) Method of mining thick steep mineral deposits
SU1305345A1 (en) Method of open-cast mining of sloping deposits