SU1170051A1 - Overhead transverse matching of approach tunnel to underground railway station - Google Patents

Overhead transverse matching of approach tunnel to underground railway station Download PDF

Info

Publication number
SU1170051A1
SU1170051A1 SU833558091A SU3558091A SU1170051A1 SU 1170051 A1 SU1170051 A1 SU 1170051A1 SU 833558091 A SU833558091 A SU 833558091A SU 3558091 A SU3558091 A SU 3558091A SU 1170051 A1 SU1170051 A1 SU 1170051A1
Authority
SU
USSR - Soviet Union
Prior art keywords
tunnel
approach
railway station
lining
underground railway
Prior art date
Application number
SU833558091A
Other languages
Russian (ru)
Inventor
Виктор Иванович Акатов
Зинаида Александровна Щетникова
Original Assignee
Akatov Viktor
Shchetnikova Zinaida A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Akatov Viktor, Shchetnikova Zinaida A filed Critical Akatov Viktor
Priority to SU833558091A priority Critical patent/SU1170051A1/en
Application granted granted Critical
Publication of SU1170051A1 publication Critical patent/SU1170051A1/en

Links

Description

Изобретение относится к подземному строительству, а именно к конструкции обделки верхнего поперечного примыкания подходного тоннеля к эксплуатируемой станции метрополитена глубокого заложения в слабых грунтах.The invention relates to underground construction, and in particular to the construction of the lining of the upper transverse junction of the approach tunnel to the operated underground station of deep laying in soft soils.

Цель изобретения - повышение безопасности сооружения примыкания без перерыва эксплуатации станции метрополитена и надежности работы в условиях слабых грунтов.The purpose of the invention is to increase the safety of the adjacency structure without interruption in the operation of the subway station and the reliability of operation in soft soils.

На фиг. 1 изображено верхнее поперечное примыкание подходного тоннеля к станции метроподитена, продольный разрез; на фиг.2 - то же, поперечный разрез.In FIG. 1 shows the upper transverse junction of the approach tunnel to the metro station, a longitudinal section; figure 2 is the same, cross section.

поперечное тоннеля 1, ! примыкание обделка кото2, свода из монолитного к среднемуtransverse tunnel 1,! adjoining lining of koto2, arch from monolithic to middle

Верхнее подходного рого состоит из стен сборных элементов 3, лотка 4 с распоркой 5, тоннелю станции метрополитена 6, делка которого выполнена из сборных элементов 7, проходит над обделкой эксплуатируемого перегонного тоннеля 8, обделка 9 которого выполнена изThe upper approach horn consists of the walls of prefabricated elements 3, a tray 4 with a spacer 5, a subway station tunnel 6, which is made of prefabricated elements 7, passes over the lining of the operated distillation tunnel 8, the lining 9 of which is made of

сборных элементов и усилена на период производства работ конструкциями 10, включая цилиндрическую оболочку 11, примыкающую снаружи к обделке 9 пересекаемого перегонного тоннеля 8, воспринимающую от него уп(Ругий отпор и передающую его через размещенные вдоль ее кромок и жестко связанные с ней балки 12 на стены 2 верхнего поперечного примыкания подходного тоннеля 1.prefabricated elements and reinforced for the period of construction works 10, including a cylindrical shell 11 adjacent to the outside of the lining 9 of the crossed distillation tunnel 8, taking up from it (rug repulse and passing it through the beams 12 along the edges and rigidly connected with it to the walls 2 upper transverse abutment of approach tunnel 1.

Верхнее поперечное примыкание подходного тоннеля 1 к среднему тоннелю станции метрополитена 6 осуществляется в следующей последовательности: на период производства работ усиливается обделка 9 из сборных элементов перегонного тоннеля 8 конструкциями 10, штольневым способом е опусканием колодцев сооружаются его стены 2, укладчиком контролируется обделка верхнего свода из сборных элементов 3, участками в соответствии с проектом организации работ сооружаются продольные балки 12, цилиндрическая оболочка 11 над перегонным тоннелем 8 и монолитный обратный свод 4 с распоркой 5.The upper transverse adjoining of approach tunnel 1 to the middle tunnel of metro station 6 is carried out in the following sequence: for the period of work, the lining of 9 of the prefabricated elements of the distillation tunnel is strengthened by structures 8 10, its walls 2 are constructed using the tunnel method and lowering the wells, and the lining of the upper arch of precast is controlled by the stacker elements 3, in accordance with the project of the organization of work, longitudinal beams 12, a cylindrical shell 11 above the distillation tunnel 8 and are monolithic Reverse vault 4 with spacer 5.

Claims (1)

ВЕРХНЕЕ ПОПЕРЕЧНОЕ ПРИМЫКАНИЕ ПОДХОДНОГО ТОННЕЛЯ К СТАНЦИИ МЕТРОПОЛИТЕНА со сборными из элементов боковыми, средним и примыкающи- ми перегонными тоннелями, включающее поперечную камеру со сводом, лотком, боковыми и торцовой стенками, о тличающееся тем, что, с целью повышения безопасности сооружения примыкания без перерыва эксплуатации станции метрополитена и надежности работы в условиях слабых грунтов, лоток камеры снабжен примыкающей к обделке пересекаемого перегонного тоннеля с наружной стороны цилиндрической оболочкой, контактирующей с боковыми стенками камеры через размещенные вдоль ее кромок и жестко связанные с ней балки. S sun„ 1170051UPPER CROSS JOINT OF AN APPROACH TUNNEL TO A METRO STATION with prefabricated from the elements side, middle and adjacent distillation tunnels, including a transverse chamber with a vault, a tray, side and end walls, which is characterized by the fact that, in order to increase the safety without interrupting the construction of the adjoining metro station and reliability in weak soils, the camera tray is equipped with a cylindrical shell adjacent to the lining of the crossed distillation tunnel from the outside, the contact a guide chamber through the side walls arranged along its edges and is rigidly associated beam. S su n „1170051 Фиг. 1FIG. 1
SU833558091A 1983-02-28 1983-02-28 Overhead transverse matching of approach tunnel to underground railway station SU1170051A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU833558091A SU1170051A1 (en) 1983-02-28 1983-02-28 Overhead transverse matching of approach tunnel to underground railway station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU833558091A SU1170051A1 (en) 1983-02-28 1983-02-28 Overhead transverse matching of approach tunnel to underground railway station

Publications (1)

Publication Number Publication Date
SU1170051A1 true SU1170051A1 (en) 1985-07-30

Family

ID=21051599

Family Applications (1)

Application Number Title Priority Date Filing Date
SU833558091A SU1170051A1 (en) 1983-02-28 1983-02-28 Overhead transverse matching of approach tunnel to underground railway station

Country Status (1)

Country Link
SU (1) SU1170051A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2717324C1 (en) * 2019-07-29 2020-03-20 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Upper transverse abutment of approach tunnel to operating metro station, constructed without interruption of operation of station with middle and side tunnels
CN112267897A (en) * 2020-11-03 2021-01-26 中国建筑土木建设有限公司 Laminated tunnel cave group excavation construction method
RU2745310C1 (en) * 2020-08-31 2021-03-23 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Method for creating upper cross-cut abutting joint of approach tunnel to existing metropolitan pilot station constructed without interruption of station operation

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 523946, кл. Е 02 D 29/04, 1976. Тоннели и метрополитены. М.: Транспорт, 1975, с. 464-469. *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2717324C1 (en) * 2019-07-29 2020-03-20 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Upper transverse abutment of approach tunnel to operating metro station, constructed without interruption of operation of station with middle and side tunnels
RU2745310C1 (en) * 2020-08-31 2021-03-23 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Method for creating upper cross-cut abutting joint of approach tunnel to existing metropolitan pilot station constructed without interruption of station operation
CN112267897A (en) * 2020-11-03 2021-01-26 中国建筑土木建设有限公司 Laminated tunnel cave group excavation construction method
CN112267897B (en) * 2020-11-03 2022-06-17 中国建筑土木建设有限公司 Construction method of laminated tunnel hole group

Similar Documents

Publication Publication Date Title
SU912053A3 (en) Method of constructing large-area underground working
SU1170051A1 (en) Overhead transverse matching of approach tunnel to underground railway station
DE3462529D1 (en) Preformed-segments bridge, prestressed by exterior cables, segments for this bridge and methods of producing them
JP2698821B2 (en) Tunnel concrete lining equipment
SU1017778A1 (en) Single-vault station for deep underground electric railway
SU1087670A1 (en) Method of constructing change station of single-vault structure for underground electric railways
RU2039261C1 (en) Method for mining of contiguous gently dipping beds
RU96114649A (en) DOUBLE-TIRE SINGLE DIGITAL TRANSFER STATIONARY SUB-ASSEMBLY DEEP LOAD
SU1145086A1 (en) Overhead transverse matching of ingoing tunnel to underground railway station
SU1164425A1 (en) Method of constructing the station complex of deep underground railway
SU1465584A1 (en) Method of constructing a tunnel under existing structure
RU2057939C1 (en) Process of construction of contiguity of transfer tunnel of built line of underground railway to transfer tunnel of operational line
RU2200840C2 (en) Process of development of gently dipping and inclined coal formations with use of cleaning powered complexes
SU898067A1 (en) Method of working thick coal beds
JPH06317095A (en) Tunnel constructing method
SU1559178A1 (en) Method of constructing pylons of underground railway stations of pylon type from prefabricated ferroconcrete in joined hard rock
SU768984A1 (en) Method of working thick steep coal seams
SU564422A1 (en) Method for mining thick gently sloping beds
SU1506110A1 (en) Method of mining sloping and steep coal seams with cohesive roof
JP2747486B2 (en) Replacement method of middle pillar in lining of multiple tunnels
SU765509A1 (en) Method of transferring power roof support into adjacent layer when mining thick beds
SU640007A1 (en) Steel-concrete beam
SU866193A1 (en) Method of working thick sloping coal seams
SU1089266A1 (en) Method of mining thick coal beds
SU962617A1 (en) Method of mining gently-sloping ore deposits