SU1145144A1 - Mine construction method - Google Patents

Mine construction method Download PDF

Info

Publication number
SU1145144A1
SU1145144A1 SU833657455A SU3657455A SU1145144A1 SU 1145144 A1 SU1145144 A1 SU 1145144A1 SU 833657455 A SU833657455 A SU 833657455A SU 3657455 A SU3657455 A SU 3657455A SU 1145144 A1 SU1145144 A1 SU 1145144A1
Authority
SU
USSR - Soviet Union
Prior art keywords
trunk
horizons
opening
mine
rock
Prior art date
Application number
SU833657455A
Other languages
Russian (ru)
Inventor
Игорь Васильевич Бодня
Валентин Николаевич Скуба
Николай Григорьевич Дубынин
Казбек Георгиевич Каргинов
Original Assignee
Институт горного дела Севера Якутского филиала СО АН СССР
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт горного дела Севера Якутского филиала СО АН СССР filed Critical Институт горного дела Севера Якутского филиала СО АН СССР
Priority to SU833657455A priority Critical patent/SU1145144A1/en
Application granted granted Critical
Publication of SU1145144A1 publication Critical patent/SU1145144A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

СПОСОБ СТРОИТЕЛЬСТВА ШАХТЫ, включающий вскрытие подготавливаемых верхних горизонтов одним из центрально-сдвоенных стволов, вскрытие нижних горизонтов другим стволом и выдачу породы от проходки каждого ствола по соседнему стволу, отличающийс  тем, что, с целью сокращени  сроков строительства, в пределах верхних горизонтов сооружают капитальный рудопуск в приствольной части первого ствола с одной разгрузочной камерой в нижней его части, а затем вспомогательные рудоспуск в приствольной части второго ствола в пределах нижних вскрьшаемых горизонтов . (ЛA MINE CONSTRUCTION METHOD, which includes opening the prepared upper horizons by one of the centrally doubled trunks, opening the lower horizons by the other trunk and discharging the rock from the penetration of each trunk into the adjacent trunk, characterized in that, in order to shorten the construction time, a capital mine is constructed within the upper horizons in the near-trunk part of the first shaft with one discharge chamber in its lower part, and then auxiliary ore passes in the near-stem part of the second trunk within the lower parts your horizons. (L

Description

Изобретение относитс  к горному делу, в частности к способам строительства глубоких шахт, и может быт использовано при подъемной разработ ке полезных ископаемых в горнодобывйющей промышленности. . Известен способ-погоризонтного: вскрыти  и подготовки месторождени  полезных ископаемых, состо щий в последовательном вскрытии нижележащих горизонтов по мере отработки вышележащих горизонтов с постепенной углубкой стволов.различными способами ll . Недостатком данного способа  вл  етс  весьма сложна  организаци  раб по углубке обоих стволов при наличи действующих рабочих горизонтов, поскольку ухудшаютс  услови  ТВ дл  рабочих, зан тых на углубочных работах , усложн етс  работа шахтного подъема и снижаетс  производительность по выдаче горной массы, В дан ном способе иногда примен ют третий вспомогательный ствой специально дл  углубочных работ, однако его применение требует больших дополнительных капитальных затрат, что. рез ко увеличивает себестоимость добываемого полезного ископаемого. Наиболее близким к предлагаемому по технической сущности и достигаемому результату  вл етс  способ строительства шахты, включающий вскрытие подготавливаемых верхних горизонтов одним из центрально-сдво енных стволов, вскрытие нижних горизонтов другим стволом и выдачу породы от проходки каждого ствола по соседнему стволу 2 . Недостатками известного способа  вл ютс  длительные сроки углубки стволов и подготовки вскрываемых нижележащих горизонтов, оборудование клетевого ствола дополнительным подъемом, дополнительные капзатраты и трудности при организации выдачи породы от углубки ствола в первый подготавливаемый горизонт с последующей перегрузкой породы дл  выдач ее на поверхность по грузовому ство . jy, невозможность совместить по усл ви м ТВ углубку стволов с проходкой горных выработок на вскрываемых горизонтах . Цель изобретени  - сокращение сроков строительства. 442 Указанна  цель достигаетс  тем, что согласно способу, включающему вскрытие подготавливаемых верхних горизонтов одним из центрально-сдвоенных стволов, вскрытие нижних горизонтов другим стволом и выдачу породы от проходки каждого ствола по соседнему стволу, в пределах верхних горизонтов сооружают капитальный рудоспуск в приствольной части первого ствола с одной разгрузочной камерой в нижней его части , а затем вспомогательный рудоспуск в приствольной части второго ствола в пределах нижних вскрываемых горизонтов. На фиг. 1 и 2 изображены различные стадии строительства шахты; на фиг. 3 - сечение А-А на фиг. 1. Способ осуществл етс  следующим образом. Грузовым стволом 1 производ т вск 1ытие рудного тела 2 на глубину первоочередных вскрываемых горизонтов 3 и временно приостанавливают проходку этого ствола. Затем сооружают капитальный рудоспуск 4 дл  обслуживани  всех горизонтов посредством сооружени  одной камеры загрузки скипов 5. После оборудовани  ствола скипо-клетевым подъемом проход т горизонтальные сбойки 6 под ось и вертикальные выработки (восстающие ) 7 узким сечением по оси будущей проходки второго ствола с разделкой сопр жений 8. Проходку второго ствола на участке, где пройден восстающий , осуществл ют с использованием грохотной решетки 9 дл  безопасности стволовых рабочих. Горную породу от проходки ствола на этом участке перепускают по восстающим рудоспускам , груз т в вагонетки на нижней сбойке и разгружают в камеру загрузки скипов первого ствола и далее шахтным подъемом первого ствола выдают на поверхность. После сбойки второго ствола с верхними подготав .ливаемыми горизонтами, в соответствии с требовани ми ЕПБ о необходимости иметь два выхода на поверхность, приступают к подготовке верхних вскрываемых горизонтов со стороны скипо-клетевого (первого) ствола.Одновременно осуществл ют проходку второго ствола на полную глубину до проектной отметки (фиг. 2). По окончании проходки второго ствола в приствольной его части проход т временный рудоспуск 10, который необходим дл  одновременного проведени  сбоек 11 на нижних вскрываемых горизонтах с целью их одновременной проходки. Затем проход т горизонтальные сбойки 11 под ось и вертикаль ную выработку 12 по оси будущей углубки первого ствола. После этого осуществл ют углубку первого ствола с выдачей горной породы от углубки с.с. к.с. 114 шахтным подъемом второго ствола. Шахтный подъем первого ствола в период его углубки служит только дл  выдачи горной породы с верхних подготавливаемых горизонтов. Углубка производитс  под защитой л д 13 и прочного перекрыти  14. Предлагаемый способ сокращает срок строительства пусковых очередей за счет совмещени  во времени проходки и углубки стволов и подготовки пусковых горизонтов. с.с.К-с.The invention relates to mining, in particular to methods for constructing deep mines, and can be used in the lifting of minerals in the mining industry. . The known method is horizontal: opening and preparation of mineral deposits, consisting in the sequential opening of the underlying horizons as the overlying horizons are developed with a gradual deepening of the stems. Various methods ll. The disadvantage of this method is the very difficult organization of work for the deepening of both trunks with the presence of working working horizons, since the conditions for TV for workers engaged in the excavation work are deteriorating, the mine lifting work is complicated and the mining mass delivery performance sometimes decreases. The third auxiliary equipment is used specifically for in-depth work, but its use requires large additional capital outlays, which. drastically increases the cost of the extracted mineral. The closest to the proposed technical essence and the achieved result is a method of constructing a mine, including opening the prepared upper horizons by one of the centrally double shafts, opening the lower horizons to another by the trunk and discharging the rock from the penetration of each trunk along the adjacent trunk 2. The disadvantages of this method are the long periods of dredging and preparation of opening lower horizons, equipping the cage stem with an additional lift, additional capital expenditures and difficulties in organizing the release of rock from the well into the first prepared horizon with subsequent overload of the rock to release it to the surface of the cargo. jy, the impossibility of combining, according to TV conditions, the deepening of trunks with the excavation of mine workings on the open horizons. The purpose of the invention is to reduce the construction time. 442 This goal is achieved in that, according to a method involving opening one prepared upper horizon by one of the centrally doubled trunks, opening the lower horizons by another trunk and discharging the rock from the penetration of each trunk through the adjacent trunk, within the upper horizons, a capital ore discharge in the trunk part of the first trunk is constructed with one discharge chamber in its lower part, and then an auxiliary ore pass in the near-stem part of the second shaft within the lower open horizons. FIG. 1 and 2 depict various stages of mine construction; in fig. 3 is a section A-A in FIG. 1. The method is carried out as follows. The cargo barrel 1 produces an accumulation of the ore body 2 to the depth of the priority horizons 3 and temporarily suspends the penetration of this trunk. Then, a major ore-launch 4 is constructed to service all horizons by constructing one skip-loading chamber 5. After the trunk is equipped with a skip-cage lift, horizontal connections 6 under the axis and vertical workings (rising) 7 with a narrow section along the axis of the future penetration of the second trunk with mating 8. The penetration of the second bore in the area where the insurgent was passed is carried out using a screen grating 9 for the safety of stem workers. The rock from the sinking of the trunk in this area is bypassed by the rising ore passes, loaded into the trolleys on the lower linkage and unloaded into the chamber the skips of the first trunk are loaded and then the mine lifting of the first trunk is delivered to the surface. After the second barrel is connected with the upper horizons prepared, in accordance with the requirements of the EPB, to have two exits to the surface, they start preparing the upper horizons from the skip-cage (first) trunk. At the same time, the second trunk is penetrated to the full depth to the design mark (Fig. 2). At the end of the penetration of the second borehole, temporary ore passes 10, which are necessary for the simultaneous carrying out of connections 11 on the lower horizons, with the aim of their simultaneous penetration, are held in the near-stem part. Then there are horizontal ssi 11 under the axis and vertical generation 12 along the axis of the future deepening of the first barrel. After that, the first hole is dredged with the rock from the dredging of the village of p. cv 114 mine rise of the second trunk. The mine rise of the first shaft during its dredging period serves only to dispense the rock from the upper prepared horizons. The dredging is carried out under the protection of ld 13 and durable overlap 14. The proposed method shortens the construction time of the start-up queues by combining in time the penetration and deepening of the barrels and the preparation of the launch horizons. S.S.S.

Claims (1)

СПОСОБ СТРОИТЕЛЬСТВА ШАХТЫ, включающий вскрытие подготавливаемых верхних горизонтов одним из центрально-сдвоенных стволов, вскрытие нижних горизонтов другим стволом и выда чу породы от проходки каждого ствола по соседнему стволу, отличающийся тем, что, с целью сокращения сроков строительства, в пределах верхних горизонтов сооружают капитальный рудопуск в приствольной части первого ствола с одной разгрузочной камерой в нижней его части, а затем вспомогательные рудоспуск в приствольной части второго ствола в пределах нижних вскрываемых горизон- >METHOD FOR CONSTRUCTION OF A SHAFT, including opening the prepared upper horizons with one of the centrally doubled trunks, opening the lower horizons with another trunk and outputting the rock from each trunk penetrating the adjacent trunk, characterized in that, in order to reduce the construction time, a capital structure is constructed within the upper horizons the ore pass in the near-barrel part of the first trunk with one discharge chamber in its lower part, and then open the ore pass in the near-barrel part of the second trunk within the lower ones x horizontal>
SU833657455A 1983-10-28 1983-10-28 Mine construction method SU1145144A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU833657455A SU1145144A1 (en) 1983-10-28 1983-10-28 Mine construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU833657455A SU1145144A1 (en) 1983-10-28 1983-10-28 Mine construction method

Publications (1)

Publication Number Publication Date
SU1145144A1 true SU1145144A1 (en) 1985-03-15

Family

ID=21087286

Family Applications (1)

Application Number Title Priority Date Filing Date
SU833657455A SU1145144A1 (en) 1983-10-28 1983-10-28 Mine construction method

Country Status (1)

Country Link
SU (1) SU1145144A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2528756C1 (en) * 2013-04-09 2014-09-20 Федеральное государственное автономное образовательное учреждение высшего профессионального образования "Белгородский государственный национальный исследовательский университет" (НИУ "БелГУ") Method of construction of shelter on space object
RU2777633C1 (en) * 2022-01-01 2022-08-08 Федеральное государственное бюджетное образовательное учреждение высшего образования Северо-Кавказский горно-металлургический институт государственный технологический университет) Method for opening the deposit during geological exploration

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Бурчаков А.С. и др. Технологи подъемной разработки .пластовых месторождений полезных ископаемых. М., Недра, 1978. 2. Авторское свидетельство СССР 891935, кл. Е 21 D 1/00, 1980 (прототип). *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2528756C1 (en) * 2013-04-09 2014-09-20 Федеральное государственное автономное образовательное учреждение высшего профессионального образования "Белгородский государственный национальный исследовательский университет" (НИУ "БелГУ") Method of construction of shelter on space object
RU2777633C1 (en) * 2022-01-01 2022-08-08 Федеральное государственное бюджетное образовательное учреждение высшего образования Северо-Кавказский горно-металлургический институт государственный технологический университет) Method for opening the deposit during geological exploration

Similar Documents

Publication Publication Date Title
SU1145144A1 (en) Mine construction method
SU1652560A1 (en) Method for mining steep orebodies by sublevel caving
CN109630118A (en) Mining method for steeply inclined unstable thin ore body
RU2063512C1 (en) Method for mining steeply dipping ore bodies
SU1532705A1 (en) Method of mining mineral deposits
SU878937A1 (en) Ore mining method
RU2064045C1 (en) Method for mining steeply dipping ore bodies and methods for mining, processing and concentration of copper and/or copper-zinc and/or zinc and/or sulfur ores with possible content of gold, silver and other precious and rare-earth elements from steeply dipping ore bodies
CN102913244A (en) Underground mining method for kaolin mine
SU1747682A1 (en) Method of robbing rib pillars
SU754070A1 (en) Method of mining gently sloping and sloping ore deposits
RU2202041C2 (en) Process of development of reserves of thick steeply deepening deposits of ore located under pits
SU1456571A1 (en) Method of mining sloping mineral bodies
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
SU1105649A1 (en) Method of constructing a crushing station in quarry
SU1006753A1 (en) Method for working thick ore deposits
SU757710A1 (en) Inclined-seam working method
SU1707200A1 (en) Method of mining flat stratified deposits
SU1612080A1 (en) Method of mining ore pillars
SU715798A1 (en) Method of mining gently sloping ore bodies
SU754068A1 (en) Method of mining thin sloping seams
SU699184A1 (en) Method of mining mineral fields
SU1608343A1 (en) Method of mining mineral deposits
RU2065053C1 (en) Method for exploitation of steeply dipping ore bodies and methods for mining, processing and beneficiation of copper and/or copper/zinc, and/or zinc, and/or sulfur ores possibly containing gold, silver and other precious and rare-earth elements of steeply dipping ore bodies
SU631657A1 (en) Method of excavating thick orebodies
SU1624155A1 (en) Method of mining steep ore deposits