SU1141259A2 - Method of laying underwater pipeline from ice to water reservoir bottom - Google Patents

Method of laying underwater pipeline from ice to water reservoir bottom Download PDF

Info

Publication number
SU1141259A2
SU1141259A2 SU833660405A SU3660405A SU1141259A2 SU 1141259 A2 SU1141259 A2 SU 1141259A2 SU 833660405 A SU833660405 A SU 833660405A SU 3660405 A SU3660405 A SU 3660405A SU 1141259 A2 SU1141259 A2 SU 1141259A2
Authority
SU
USSR - Soviet Union
Prior art keywords
ice
pipeline
lanes
field
ice field
Prior art date
Application number
SU833660405A
Other languages
Russian (ru)
Inventor
Виктор Леонтьевич Трофимов
Юрий Павлович Яблонский
Original Assignee
Государственный научно-исследовательский и проектный институт нефтяной и газовой промышленности им.В.И.Муравленко
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Государственный научно-исследовательский и проектный институт нефтяной и газовой промышленности им.В.И.Муравленко filed Critical Государственный научно-исследовательский и проектный институт нефтяной и газовой промышленности им.В.И.Муравленко
Priority to SU833660405A priority Critical patent/SU1141259A2/en
Application granted granted Critical
Publication of SU1141259A2 publication Critical patent/SU1141259A2/en

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

СПОСОБ ПРОЮ1АДКИ ПОДВОДНОГО ТРУБОПРОВОДА СО ЛЬДА НА ДНО ВОДОЕМА по авт.св. № 594389, отличающийс  тем, что, с целью повьшени  безопасности .работ при образова-. НИИ майн путем искшоченй  осевого поворота высоко расположенного обе- тонированного трубопровода вместе с вырезанным участком ледового пол , перед образованием майн на ледовом поле по сторонам трубопровода и над ним выше верхних отметок его балласта намораживают узкий ледовый слой с посто нной толщиной не менее глубины водоама под ледовым полем и шириной не менее удалени  друг от друга майн. INO сл соMETHOD OF PROCESSING UNDERWATER PIPELINE FROM ICE TO THE BOTTOM OF THE WATER, auton. No. 594389, characterized in that, in order to increase safety. The SRI of the lanes, by means of axial rotation of a highly located oblatonated pipeline with a cut out ice field, before forming lanes on the ice field on the sides of the pipeline and above the upper marks of its ballast freeze a narrow ice layer with a constant thickness not less than the depth of the water below the ice field and a width of not less than the distance from each other lanes. INO cl with

Description

1 Изобретение относитс  к области строительства и может найти применение при прокладке подводных магистральных трубопроводов. Известны способы прокладки подвод ных трубопроводов со льда на дно водоема. По основному авт . св. № 594389 известен способ, который заключаетс  в размещении и креплении на дедовом поле трубопроводау образовании майи по обеим сторонам трубопровода параллельно его оси и погружении трубопровода на дно водоема D3. Недостатком известного способа в случае его использовани  дл  погружени  забалластированного, имеющего отрицательную плавучесть, трубопровода  вл етс  возникновение осевого поворота этого высоко расположенного трубопровода вместе с вьфезанным участком ледового пол , в результате чего ведение работ по образованию майн сопр жено с опасностью. Целью изобретени   вл етс  повышение безопасности работ при образовании майн путем исключени  осевого поворота высоко расположенного обетонированного трубопровода вместе с вырезанным участком ледового пол  Дл  достижени  указанной цели согласно способу прокладки подводног трубопровода со льда на дно водоема перед образованием майн на ледовом поле по сторонам трубопровода и над 592 ним быше верхних отметок его балласта намораживают узкий ледовый слой с посто нной толщиной не менее глубины водоема под ледовым полем и шириной не менее удалени  друг от друга майн. На чертеже схематически представлен погруженный трубопровод, фронтальный вид. В соответствии со способом прокладки подводного трубопровода со льда на дно водоема размещают и креп т на ледовом поле 1 трубопровод 2, забалластированный сплошным балластом или одиночными ут желител ми 3, а затем по сторонам трубопровода и над ним выше верхних отметок его балласта намораживают узкий ледовый слой 4 с, посто нной толщиной не менее глубины мелководного водоема 5 под ледовым полем 1. В заключение в ледовом поле прорезают параллельно оси трубопровода две майны 6, что обеспечивает погружение трубопровода изгибом. Осевого поворота трубопровода вместе с вырезанным участком 7 ледового сло  4 не происходит, чему преп тствуют достаточно высокие боковые стенки вырезанного участка. Таким образом, благодар  большой высоте намораживающего сло  исключаетс  возможность его осевого поворота под действием веса высоко расположенного трубопровода, чем обеспечиваетс  повьшение безопасности работ при прорезке майн.1 The invention relates to the field of construction and may find application in the construction of underwater trunk pipelines. Methods are known for laying underwater pipelines from ice to the bottom of a reservoir. According to the main author. St. No. 594389 a method is known which consists in placing and fastening a pipeline in the old-fashioned field to form maya on both sides of the pipeline parallel to its axis and immersing the pipeline to the bottom of the reservoir D3. The disadvantage of the known method in case of its use for immersing the ballasted, negative buoyancy pipeline is the occurrence of the axial rotation of this highly located pipeline together with the extruded area of the ice field, as a result of which work on the formation of mines is associated with danger. The aim of the invention is to increase the safety of operations during the formation of lanes by eliminating the axial rotation of a high-spaced obtonirovanny pipeline together with a cut-out section of the ice floor. it is faster than the upper marks of its ballast that freeze a narrow ice layer with a constant thickness not less than the depth of the reservoir under the ice field and a width not less than Do not move away from each other. The drawing schematically shows the immersed pipeline, front view. In accordance with the method of laying the underwater pipeline from the ice to the bottom of the reservoir, pipe 2 is sealed and fixed on the ice field 1, ballasted with solid ballast or single attenuators 3, and then on the sides of the pipeline and above the upper marks of the ballast they block the narrow ice layer 4 sec., With a constant thickness of at least the depth of the shallow water body 5 under the ice field 1. Finally, two lanes 6 are cut in the ice field parallel to the pipeline axis, which ensures that the pipeline is submerged in a bend. An axial rotation of the pipeline together with the cut out section 7 of the ice layer 4 does not occur, which is prevented by the relatively high side walls of the cut out section. Thus, due to the high height of the freezing layer, the possibility of its axial rotation under the action of the weight of the highly located pipeline is excluded, which ensures the safety of work during the cutting of the mine.

Claims (1)

СПОСОБ ПРОКЛАДКИ ПОДВОДНОГО ТРУБОПРОВОДА СО ЛЬДА НА ДНО ВОДОЕМА по авт.св. If 594389, отличающийся тем, что, с целью повышения безопасности работ при образова-. нии майн путем исключения осевого поворота высоко расположенного обетонированного трубопровода вместе с : вырезанным участком ледового поля, перед образованием майн на ледовом поле по сторонам трубопровода и над ним выше верхних отметок его балласта намораживают узкий ледовый слой с постоянной толщиной не менее глубины водоема под ледовым полем и шириной не менее удаления друг от друга майн. Λ н*METHOD OF LAYING UNDERWATER PIPELINE FROM ICE TO THE BOTTOM OF THE RESERVOIR If 594389, characterized in that, in order to increase the safety of work with education. lanes by eliminating the axial rotation of a highly located concrete pipeline along with : a cut section of the ice field, before the formation of lanes on the ice field on the sides of the pipeline and above it above the upper marks of its ballast, a narrow ice layer with a constant thickness of at least the depth of the reservoir under the ice field is frozen and width not less than the distance from each other lanes. Λ n * SU „1141259 /777777/77777777777777777777777777 >SU „1141259/777777/77777777777777777777777777777777> 1 11411141
SU833660405A 1983-11-01 1983-11-01 Method of laying underwater pipeline from ice to water reservoir bottom SU1141259A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU833660405A SU1141259A2 (en) 1983-11-01 1983-11-01 Method of laying underwater pipeline from ice to water reservoir bottom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU833660405A SU1141259A2 (en) 1983-11-01 1983-11-01 Method of laying underwater pipeline from ice to water reservoir bottom

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
SU594389A Addition SU121020A2 (en) 1958-03-10 1958-03-10 Embroidery method of fabric

Publications (1)

Publication Number Publication Date
SU1141259A2 true SU1141259A2 (en) 1985-02-23

Family

ID=21088338

Family Applications (1)

Application Number Title Priority Date Filing Date
SU833660405A SU1141259A2 (en) 1983-11-01 1983-11-01 Method of laying underwater pipeline from ice to water reservoir bottom

Country Status (1)

Country Link
SU (1) SU1141259A2 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР 1 594389, кл. F 16 L 1/04, 1978 (прототип). *

Similar Documents

Publication Publication Date Title
Svensson Is the cross-section of a glacial valley a parabola?
SU1141259A2 (en) Method of laying underwater pipeline from ice to water reservoir bottom
KR20170083908A (en) System and Method for Modeling Shoreline Movement for Wave Period Average Numerical Modeling
Armstrong Excavations in the Pin Hole Cave, Creswell Crags, Derbyshire
NO854796L (en) BOILGE REFUSES WITH ZAKKSAKK FORM.
US3660983A (en) Apparatus and method for the prevention of ice in waterways
RU2728476C1 (en) Ice-fishing vessel
Niewiarowski Levels in subglacial channels and their significance in determining the channel origin and evolution
SU874860A1 (en) Method of driving a canal in ice, particularly, for laying underwater pipeline
RU2753031C1 (en) Sea-going ice navigation vessel
RU2132898C1 (en) Method for creating ice-bound crossing
RU2065964C1 (en) Method for mining shallow placer deposits by dredges
SU707556A1 (en) Method of slowing-down the freezing of a pond
SU1015025A1 (en) Method of fighting glacial mud flows
SU647452A2 (en) Method of filling-up excavated space
SU894051A1 (en) Method of dewatering peat deposits
RU152441U1 (en) TYPICAL UNDERWATER TUNNEL BRIDGE
JPS6047407B2 (en) Ocean construction method using old ship hulls
RU2066806C1 (en) Method for laying of pipeline in medium having buoyant force
SU1059050A1 (en) Method and apparatus for paperforming engineering work with ice
RU2144967C1 (en) Method of formation of ice load-carrying platform
SU1125333A1 (en) Method of decreasing water inflow in mine workings in mining coal seams
SU1134715A1 (en) Method of strip-mining of bed deposits of minerals
JPS6098006A (en) Concrete structure in icy waters
SU1357490A1 (en) Canal