SU1034962A1 - Method of storing liquid industrial waste in natural cavities - Google Patents

Method of storing liquid industrial waste in natural cavities Download PDF

Info

Publication number
SU1034962A1
SU1034962A1 SU813312781A SU3312781A SU1034962A1 SU 1034962 A1 SU1034962 A1 SU 1034962A1 SU 813312781 A SU813312781 A SU 813312781A SU 3312781 A SU3312781 A SU 3312781A SU 1034962 A1 SU1034962 A1 SU 1034962A1
Authority
SU
USSR - Soviet Union
Prior art keywords
cells
depressions
dams
protection
filling
Prior art date
Application number
SU813312781A
Other languages
Russian (ru)
Inventor
Юрий Николаевич Сокольников
Виталий Владимирович Хомицкий
Александр Лукич Онуфриенко
Олег Степанович Юрин
Ерминингельд Стефанович Цайтц
Бронислав Васильевич Парий
Геннадий Николаевич Ворошилов
Эммануил Иосифович Гончар
Original Assignee
Институт гидромеханики АН УССР
Киевский Ордена Ленина Государственный Университет Им.Т.Г.Шевченко
Государственный Проектный Институт "Укрводоканалпроект"
Крымский содовый завод
Трест "Перекопхимстрой"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт гидромеханики АН УССР, Киевский Ордена Ленина Государственный Университет Им.Т.Г.Шевченко, Государственный Проектный Институт "Укрводоканалпроект", Крымский содовый завод, Трест "Перекопхимстрой" filed Critical Институт гидромеханики АН УССР
Priority to SU813312781A priority Critical patent/SU1034962A1/en
Application granted granted Critical
Publication of SU1034962A1 publication Critical patent/SU1034962A1/en

Links

Landscapes

  • Revetment (AREA)

Abstract

1. СПОСОБ СКЛАДИРОВАНИЯ ЖИДКИХ ПРОМЫШЛЕННЫХ ОТХОДОВ В ЕСТЕСТВЕННЫХ ВПАДИНАХ, включающий разделение впадин путем возведени  дамб, берегозащитные работы, выполненные с учетом расчетной дл  акватории заполн емой емкости, наибольшей высоты волн, и заполнение впадин отходами, отличающийс  тем, что, с целью снижени  сроков подготовки впадин к эксплуатации и уменьщени  затрат на подготовку впадин к складированию за счет снижени  стоимости берегозащитных работ, чашу каждой впадины раздел ют на  чейки, имеющие в плане форму выпуклых фигур с отношением наибольшего габаритного размера к наименьшему не более 2:1, производ т противоабразионную защиту дамб и берегозащитные работы с учетом наибольшей высоты волн, расчетной дл  акватории  чеек, а заполнение впадин производ т путем последовательного заполнени   чеек по мере их подготовки . 2.Способ по п. 1, отличающийс  тем, i что берегозащитные работы выполн ют путем сооружени  из легких грунтов по кон (О туру  чеек искусственных пл жей, примыкающих к телу дамб и бортам впадин и имеющих округлую линию уреза. 3.Способ по пп. 1 и 2, отличающийс  тем, что дно  чеек углубл ют, а вынутый грунт используют дл  берегозащитных работ . СА Nt: СО О5 Ю1. METHOD FOR STORING LIQUID INDUSTRIAL WASTE IN NATURAL DAMAGES, including the separation of depressions by erecting dams, bank protection works, taking into account the design for the water area of the filled tank, the highest wave height depressions for operation and reduction of costs for preparation of depressions for storage by reducing the cost of bank protection, the bowl of each depression is divided into cells, having in plan the shape of convex figures with the ratio of the largest to the smallest overall dimension of not more than 2: 1, ie is produced protivoabrazionnuyu dams and coast protection operation to the maximum height of waves, the water area calculated for the cells, and filling the depressions is produced by T cells fill sequentially as their preparation. 2. A method according to claim 1, characterized in that the bank protection work is carried out by constructing light soils at the end (O tour of artificial well pits, adjacent to the body of dams and the sides of the depressions and having a rounded line of the notch. 3. 1 and 2, characterized in that the bottom of the cells is deepened, and the excavated soil is used for water protection. CA Nt: CO O5 S

Description

Изобретение относитс  к способам изол ции , хранени  и складировани  промышленных отходов горнорудных , химических и других производств, например шламов, хвостов, транспортируемых и сбрасываемых в хранилища в виде пульп, жидких агрегатных смесей, рапы. Известен способ складировани  хвостов горнообогатительных комбинатов, включающий создание хвостохранилища, ограждение выделенной дл  его создани  территорий дамбой и заполнение хранилища жидкими отходами. Тело дамбы при этом обычно возвод т из местных грунтов, а территорию хранилища раздел ют дамбами на отдельные  чейки 1. Недостатками известного способа  вл ютс  необходимость изъ ти  из земельного фонда полезной площади, больщие затраты на возведение контурной оградительной дамбы, необходимость осуществлени  сложных и дорогосто щих меропри тий по защите от проникновени  агрессивных вод через дно хвостохранилища и ограждающую дамбу на окружающую территорию, а в р де случаев и в подстилающие пласты Наиболее близким по технической сущности и достигаемому результату к изобретению  вл етс  способ складировани  жидких промыщленных отходов в естественных впадинах, включающий берегозащитные работы, выполн емые с учетом расчетной дл  акватории впадины наибольшей высоты волн, и последующее заполнение впадины отходами. В случае наличи  по тальвегу понижени  водотона его ложе перегораживают поперечной дамбой 2. Недостатками известного способа  вл ютс  высока  стоимость инженерной защиты поверхности естественных бортов (берегов) от впадины, а также невозможность складировани  отходов до заверщени  полного объема берегозащитных работ и, следовательно , значительный срок окупаемости капитальных затрат. Цель изобретени  - снижение сроков подготовки впадины к эксплуатации и уменьщение затрат на подготовку впадин к складированию за счет снижени  стоимости берегозащитных работ. Поставленна  цель достигаетс  тем, что согласно известному.способу, включающему разделение впадин путем возведени  дамб, берегозащитные работы, выполн емые с с учетом расчетной дл  акватории заполн емой емкости наибольщей высоты волн, и заполнение впадин отходами, чащу каждой впадины раздел ют на  чейки, имеющие в плане форму выпуклых фигур с отношением наибольшего габаритного размера и наименьшему не более 2:1, производ т берегозащитные работы и противоабразионную защиту дамб с учетом наибольшей высоты волн, расчетной дл  акватории  чеек, а заполнение впадин производ т путем последовательного заполнени   чеек по мере их подготовки. Кроме того, берегозащитные работы выполн ют путем сооружени  из легких грунтов по контуру  чеек искусственных пл жей , примыкающих к телу дамб и бортам впадин и имеющих округлую линию уреза. Дно  чеек углубл ют, а вынутый грунт используют дл  берегозащитных работ. На чертеже изображена впадина естественного происхождени  - озеро № 1, выделенное дл  складировани  жидких промыщленных отходов. На чертеже показаны дамбы 1-16, отгороженные ими  чейки 17-29 и коллектор 30 дл  сбора воды, фильтрующей из хранилища . Согласно предлагаемому способу на акватории озера возвод т дамбы 1 и 2, которыми отгораживают  чейку 17. Акватори  отгороженной  чейки имеет в плане форму выпуклой плоской фигуры, в которой отношение наибольшего размера к наименьшему близко 1:1. Дамбы 1 и 2 возвод т как из грунта, забираемого со дна  чеек 17-18 и 19, так и вынутого при открытии участка коллектора 30, оконтуривающего  чейку 17со стороны берега. Ширину гребн  дамб устанавливают из расчета проезда и маневрировани  строительных механизмов равной 3 м. По конструктивным соображени м гребень дамб располагают на 0,5 м выше отметки максимального горизонта наполнени  хранилища , а заложение их откосов принимают равным т 1,5-2. После возведени  разделительных дамб к их телу и борту впадин по периметру образовавшейс   чейки намывают надводную часть пл жа, щирину которой определ ют по зависимости Ьм Ь„п1к или Ь„„ -ЬнШ, , где и btiH - ширина пл жа намытого соответственно из св зных или несв зных грунтов; 1зн - высота наката расчетной волны на пл ж, м; т ц т -коэффициент динамически устойчивого откоса пл жа из соответствующего грунта. Оптимальным отношением габаритов  чейки , при котором обеспечиваетс  наиболее высока  динамическа  устойчивость берегов по ее периметру,  вл етс  1:1, т.е. кругла  в плане форма акватории. Така  форма и придаетс  первой  чейке, огораживаемой на акватории. Отношение габаритов 2:1  вл етс  предельным, так как вдоль сторон, параллельных большому габариту , при его увеличении развиваютс  вдоль береговые течени , опасные дл  устойчивости берегов  чейки. Мористую границу надводной части пл жа располагают на отметке максимального допустимого горизонта заполнени  емкостиThis invention relates to methods for isolating, storing, and storing industrial waste from mining, chemical, and other industries, such as sludge, tailings, transported and discharged into storage in the form of slurries, liquid aggregate mixtures, brine. There is a known method of storing tailings of ore-dressing plants, including the creation of a tailing dump, a fence for the areas allocated for its creation and a filling of the store with liquid waste. In this case, the body of the dam is usually erected from local soils, and the storage area is dammed into individual cells 1. The disadvantages of this method are the need to remove the useful area from the land fund, the high costs of erecting a boundary dam, the need for complex and expensive measures to protect against the penetration of aggressive water through the bottom of the tailings and fencing of the dam to the surrounding territory, and in some cases to the underlying formations uschnosti and the result achieved to the invention is a method promyschlennyh waste liquid store the same in the natural depressions comprising bank protection work performed by taking into account the calculated maximum for waters trough wave height, and subsequent filling of cavities waste. In the case of a thalweg lowering the water tones, its bed is blocked by a transverse dam 2. The disadvantages of this method are the high cost of engineering protection of the surface of natural sides (shores) from the depression, as well as the impossibility of storing waste until the full extent of water protection works is completed and, consequently, a considerable payback period capital costs. The purpose of the invention is to reduce the time of preparation of the depression for exploitation and reduce the cost of preparing the cavities for storage by reducing the cost of water protection. This goal is achieved by the fact that according to the well-known method, which includes separation of depressions by erecting dams, shore protection works, carried out taking into account the maximum wave height calculated for the water area of the filled reservoir of the depressions, the depth of each depression is divided into cells having in terms of the shape of convex figures with the ratio of the largest overall size and the smallest no more than 2: 1, water protection works and anti-abrasion protection of the dams taking into account the greatest wave height calculated for the water area Cells, and the hollows are filled by successively filling the cells as they are prepared. In addition, shore protection works are performed by constructing light soils along the contour of the cells of artificial ridges, adjacent to the body of dams and sides of the depressions and having a rounded line of the notch. The bottom of the cells is deepened, and the excavated soil is used for water protection works. The drawing shows a depression of natural origin - Lake No. 1, allocated for the storage of liquid industrial waste. The drawing shows dykes 1-16, fenced off cells 17-29 and a collector 30 for collecting water filtering from the storage. According to the proposed method, in the water area of the lake, erecting dams 1 and 2, which enclose the cell 17. The water area of the fenced-off cell has the shape of a convex flat figure, in which the ratio of the largest size to the smallest close 1: 1. Dams 1 and 2 are erected both from the ground taken from the bottom of the 17-18 and 19 cells and taken out at the opening of the section of the collector 30, which delineates the cell 17 of the shore side. The width of the dam ridge is set at the rate of travel and maneuvering of construction mechanisms equal to 3 m. For constructive considerations, the dam crest is located 0.5 m above the mark of the maximum filling horizon of the storage facility, and the laying of their slopes is equal to m 1.5-2. After the construction of dividing dams to their body and the board of hollows along the perimeter of the formed cells, the surface part of the pit is washed up, the width of which is determined by the dependence of LM „P1k or B„ -SN, where btiH is the width of the washed site, respectively, from or inconsistent soils; 1n - height of the overrun of the calculated wave per square plane, m; t c t is the coefficient of the dynamically stable slope of the plj from the corresponding soil. The optimal ratio of cell dimensions at which the most dynamic stability of the banks along its perimeter is ensured is 1: 1, i.e. round in terms of the shape of the waters. This form is given to the first cell enclosed in the water area. The ratio of 2: 1 dimensions is limiting, since along the sides parallel to the large dimension, with its increase, coastal currents develop, which are dangerous for the stability of the banks of the cell. The sea boundary of the surface part of the surface is located at the mark of the maximum permissible filling horizon.

Claims (3)

1. СПОСОБ СКЛАДИРОВАНИЯ ЖИДКИХ ПРОМЫШЛЕННЫХ ОТХОДОВ В ЕСТЕСТВЕННЫХ ВПАДИНАХ, включающий разделение впадин путем возведения дамб, берегозащитные работы, выполненные с учетом расчетной для акватории заполняемой емкости, наибольшей высоты волн, и заполнение впадин отходами, отличающийся тем, что, с целью снижения сроков подготовки впадин к эксплуатации и уменьшения затрат на подготовку впадин к складированию за счет снижения стоимости берегозащитных работ, чашу каждой впадины разделяют на ячейки, имеющие в плане форму выпуклых фигур с отношением наибольшего габаритного размера к наименьшему не более 2:1, производят противоабразионную защиту дамб и берегозащитные работы с учетом наибольшей высоты волн, расчетной для акватории ячеек, а заполнение впадин производят путем последовательного заполнения ячеек по мере их подготовки.1. METHOD FOR STORAGE OF LIQUID INDUSTRIAL WASTE IN NATURAL DEPRESSIONS, including the separation of troughs by erecting dams, shore protection works performed taking into account the design capacity of the filled tank, the highest wave height, and filling the troughs with waste, characterized in that, in order to reduce the time for preparing troughs for operation and reducing the cost of preparing the depressions for storage by reducing the cost of shore protection work, the cup of each depression is divided into cells having the shape of convex figures in plan Ocean largest to the smallest overall dimension of not more than 2: 1, produce protivoabrazionnuyu dams and coast protection operation to the maximum height of waves calculated for waters cells, and filling cavities produced by sequentially filling cells as their preparation. 2. Способ по π. 1, отличающийся тем, с что берегозащитные работы выполняют пу- ® тем сооружения из легких грунтов по кон- f туру ячеек искусственных пляжей, примы- V кающих к телу дамб и бортам впадин и имею- f щих округлую линию уреза.2. The method according to π. 1, characterized in that the shore protection works are carried out by constructing from light soils along the contour of the cells of artificial beaches adjacent to the body of dams and sides of the valleys and having a rounded line of cut. 3. Способ по пп. 1 и 2, отличающийся а тем, что дно ячеек углубляют, а вынутый грунт используют для берегозащитных ра- , бот.3. The method according to PP. 1 and 2, characterized in that the bottom of the cells is deepened, and the excavated soil is used for shore protection, bot.
SU813312781A 1981-07-26 1981-07-26 Method of storing liquid industrial waste in natural cavities SU1034962A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813312781A SU1034962A1 (en) 1981-07-26 1981-07-26 Method of storing liquid industrial waste in natural cavities

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813312781A SU1034962A1 (en) 1981-07-26 1981-07-26 Method of storing liquid industrial waste in natural cavities

Publications (1)

Publication Number Publication Date
SU1034962A1 true SU1034962A1 (en) 1983-08-15

Family

ID=20967404

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813312781A SU1034962A1 (en) 1981-07-26 1981-07-26 Method of storing liquid industrial waste in natural cavities

Country Status (1)

Country Link
SU (1) SU1034962A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР по за вке Я« 2937650, кл. Е 21 С 41/00, 1980. 2. Рекомендации по намыву шламов (хвостов) в плотины и дамбы шламохранилищ железорудных горнообогатительных комбинатов. Киев, 1967, с. 11, фиг. а, б, г (прототип). *

Similar Documents

Publication Publication Date Title
CN100445470C (en) Underwater groins system for growing various living things
Moore Deltaic sedimentation
US3465530A (en) Dam construction
CN212561367U (en) Ecological wetland revetment structure based on river lake topography is remolded
SU1034962A1 (en) Method of storing liquid industrial waste in natural cavities
CN111893948A (en) Ecological wetland revetment structure based on river and lake terrain remodeling and construction method thereof
SU1714028A1 (en) Method for combined dumping of tailings and overburden rocks
Bird Potential effects of sea level rise on the coasts of Austrália, África, and Ásia
CN113045139B (en) Ecological restoration method for lugu lake big grass sea degraded wetland
SU1654426A1 (en) Method of protecting shores of seas and reservoirs from erosion by storm waves
Juday The inland lakes of Wisconsin
CN216865003U (en) Novel ecological seawall dyke foot structure
Volkov et al. The discharge of proglacial waters during the last glaciation of Western Siberia
CN107558434B (en) Ecological current-inhibiting system of hard shore
Zenkovich Geomorphological problems of protecting the Caucasian Black Sea coast
Fromme The hydrology of the Bot River estuary
SU583235A1 (en) Water intake
CN113293734A (en) Novel ecological seawall dike foot structure and construction method thereof
Minikin Practical river and canal engineering
SU1130652A1 (en) Method of depositing soil into water reservoir
GB2376258A (en) Water containment structure
Berry The Red Sea Coast of the Sudan
Kos' yan et al. Carbonate beaches of the eastern part of the Sea of Azov under anthropogenic impact
Fairbanks Practical physiography
Phillips et al. A post-Lake Minong transgressive event on the north shore of Lake Superior, Ontario: possible evidence of Lake Agassiz inflow