US3465530A - Dam construction - Google Patents

Dam construction Download PDF

Info

Publication number
US3465530A
US3465530A US651526A US3465530DA US3465530A US 3465530 A US3465530 A US 3465530A US 651526 A US651526 A US 651526A US 3465530D A US3465530D A US 3465530DA US 3465530 A US3465530 A US 3465530A
Authority
US
United States
Prior art keywords
dam
piers
beams
water
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US651526A
Inventor
John C Renfro
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JOHN C RENFRO
Original Assignee
JOHN C RENFRO
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JOHN C RENFRO filed Critical JOHN C RENFRO
Application granted granted Critical
Publication of US3465530A publication Critical patent/US3465530A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/102Permanently installed raisable dykes

Definitions

  • a dam construction comprises spaced piers, the piers having recess in their surfaces for the interfitting reception of beams extending between and supported by the piers, piles extending through the piers into the earth foundation and cables secured to the piers and to hold down the beams.
  • a dam construction preferably of the overflow type, in which the height of the dam is relatively small and which will impound water behind the dam to permit infiltration of water into gravel stratas to prevent excessive flooding, especially in the mountainous areas.
  • An object of my invention is to provide a novel darn construction which can be readily prefabricated and subsequently transported to the desired dam site where it can be erected for the purpose of entraping water in a meadow, ravine, gully, wash, or the like.
  • Another object of my invention is to provide a novel dam construction which can be transported to remote areas, or where excessive water runoff would cause erosion or other damage, and also where the runoff water would be subsequently lost by drainage into an ocean or lake.
  • My dam construction is of the low level type which might be described as a beaver type dam, where water is impounded back of the dam and subsequently percolates through the soil into water bearing gravels or sands where it is stored for subsequent use by native plants, trees, etc.
  • Still another Object of my invention is to provide a novel darn construction which is simple to erect, and which can be transported by a minimum number of workmen, and which can be readily erected to form an effective dam to impound water in desired areas.
  • FIGURE 1 is a perspective view of my dam construction erected in a gully, ravine, or the like.
  • FIGURE 2 is an enlarged sectional view taken on line 22 of FIGURE 1.
  • FIGURE 3 is a fragmentary sectional view taken on line 33'of FIGURE 2.
  • FIGURE 4 is a transverse sectional view of my dam construction illustrating a means to drain the lake or pond back of the dam.
  • the numeral 1 indicates a ravine', gully or water drainage area that is to impound water in a lake or pond 2 back of the dam structure 3.
  • a restraining dam To prevent excessive water runoff in mountainous or other remote areas it is desirable to entrap flood waters or the like back of a restraining dam, and to permit the water to percolate downwardly through the soil, gravel or sand, and thus prevent excessive runoff and subsequent loss of fresh water into oceans or lakes.
  • piers 4 and 5 are fixedly positioned in the side walls of the "ice ravine, gully, or the like, and these piers when rigidly anchored in position form the foundation or base for the dam wall, which will be subsequently described.
  • the piers 4 and 5 are identical in construction and, consequently, only one will be described in detail.
  • a pier foundation member 6 is embedded securely in the wall of the ravine 1 and it may be formed of wood, concrete, or the like.
  • a plurality of downwardly extending teeth or serrations 7 are formed on the bottom of the pier and project downwardly into the soil or strata of the ravine.
  • a plurality of upwardly projecting teeth 8 are formed on the foundation 6 and are adapted to receive the upper pier member 9.
  • the pier member 9 is also formed with teeth 10 which fit the teeth 8 and thus lock the parts 6 and 9 together to prevent shifting or horizontal movement of these pier members.
  • the pier members 6 and 9 are formed with vertical holes 1112 respectively, which receive the piles 13 and 14 which are driven into the soil at each end of the pier structure 4.
  • the pier is rigidly and fixedly mounted in the ravine or gully, and especially at both sides thereof across which the completed dam extends.
  • each beam section is square in cross section so that they will accurately fit one against the other, especially as shown in FIGURE 2.
  • the lowermost layer of beams 15 fit into the upwardly directed teeth 16 of the pier section 9.
  • the superimposed layers of beams 15 will be tied into the piers 4 and 5 to form the restraining dam 3.
  • tie-down cables 17 which are fastened to the pilings 13- 14 and which extend over the beams 15, thus securely tying these beams down to the piling and preventing ac cidental dislodgement of these dam members.
  • I provide a pipeline 18 under the dam 3, and thence to a drilled well 19 which extends down to a sand or gravel bed 20.
  • a valve 21 in the pipe 18 will control the flow of Water into the drilled well 19.
  • a dam construction comprising a dam foundation including spaced piers, and beams extending between said piers, means on said piers shaped to receive said beams, and means on the piers extending into the dam foundation to prevent horizontal shifting of said piers relative to the dam foundation, and piles extending through said piers and into the dam foundation.
  • a dam construction as recited in claim 1 piles extending through said piers and into the dam foundation, a cable extending between the piles and over said beams, and said means on the piers to fit the beams being tooth shaped, and the beams being polygonal in cross section to fit into said teeth.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Description

United States Patent 3,465,530 DAM CONSTRUCTION John C. Renfro, 48 Doheny Park Village, 34202 Del Obispo, Dana Point, Calif. 92629 Filed July 6, 1967, Ser. No. 651,526 Int. Cl. E02b 7/02, 3/10 US. Cl. 61-30 7 Claims ABSTRACT OF THE DISCLOSURE A dam construction comprises spaced piers, the piers having recess in their surfaces for the interfitting reception of beams extending between and supported by the piers, piles extending through the piers into the earth foundation and cables secured to the piers and to hold down the beams.
A dam construction, preferably of the overflow type, in which the height of the dam is relatively small and which will impound water behind the dam to permit infiltration of water into gravel stratas to prevent excessive flooding, especially in the mountainous areas.
An object of my invention is to provide a novel darn construction which can be readily prefabricated and subsequently transported to the desired dam site where it can be erected for the purpose of entraping water in a meadow, ravine, gully, wash, or the like.
Another object of my invention is to provide a novel dam construction which can be transported to remote areas, or where excessive water runoff would cause erosion or other damage, and also where the runoff water would be subsequently lost by drainage into an ocean or lake.
My dam construction is of the low level type which might be described as a beaver type dam, where water is impounded back of the dam and subsequently percolates through the soil into water bearing gravels or sands where it is stored for subsequent use by native plants, trees, etc.
Still another Object of my invention is to provide a novel darn construction which is simple to erect, and which can be transported by a minimum number of workmen, and which can be readily erected to form an effective dam to impound water in desired areas.
Other objects, advantages and features of invention may appear from the accompanying drawing, the subjoined detailed description and the appended claims.
In the drawing:
FIGURE 1 is a perspective view of my dam construction erected in a gully, ravine, or the like.
FIGURE 2 is an enlarged sectional view taken on line 22 of FIGURE 1.
FIGURE 3 is a fragmentary sectional view taken on line 33'of FIGURE 2.
FIGURE 4 is a transverse sectional view of my dam construction illustrating a means to drain the lake or pond back of the dam.
Referring more particularly to the drawing, the numeral 1 indicates a ravine', gully or water drainage area that is to impound water in a lake or pond 2 back of the dam structure 3. To prevent excessive water runoff in mountainous or other remote areas it is desirable to entrap flood waters or the like back of a restraining dam, and to permit the water to percolate downwardly through the soil, gravel or sand, and thus prevent excessive runoff and subsequent loss of fresh water into oceans or lakes.
When the dam site has been selected in the appropriate ravine, gully, wash, or the like 1, two or more piers 4 and 5 are fixedly positioned in the side walls of the "ice ravine, gully, or the like, and these piers when rigidly anchored in position form the foundation or base for the dam wall, which will be subsequently described. The piers 4 and 5 are identical in construction and, consequently, only one will be described in detail. A pier foundation member 6 is embedded securely in the wall of the ravine 1 and it may be formed of wood, concrete, or the like. A plurality of downwardly extending teeth or serrations 7 are formed on the bottom of the pier and project downwardly into the soil or strata of the ravine. A plurality of upwardly projecting teeth 8 are formed on the foundation 6 and are adapted to receive the upper pier member 9. The pier member 9 is also formed with teeth 10 which fit the teeth 8 and thus lock the parts 6 and 9 together to prevent shifting or horizontal movement of these pier members. The pier members 6 and 9 are formed with vertical holes 1112 respectively, which receive the piles 13 and 14 which are driven into the soil at each end of the pier structure 4. Thus the pier is rigidly and fixedly mounted in the ravine or gully, and especially at both sides thereof across which the completed dam extends.
When the piers 4 have been fixedly positioned as described, the beam or wall units 15 are placed in position. These beams or wall sections are formed of wood, concrete, or the like, and are multilaterally shaped. The beams 15 may be solid or hollow as required for the proper strength. As shown, each beam section is square in cross section so that they will accurately fit one against the other, especially as shown in FIGURE 2. The lowermost layer of beams 15 fit into the upwardly directed teeth 16 of the pier section 9. Thus the superimposed layers of beams 15 will be tied into the piers 4 and 5 to form the restraining dam 3. To prevent the beams 15 from shifting or moving under pressure of water, I provide tie-down cables 17 which are fastened to the pilings 13- 14 and which extend over the beams 15, thus securely tying these beams down to the piling and preventing ac cidental dislodgement of these dam members.
To facilitate more rapid percolation of water into a sand or gravel bed from the lake or pond 2, I provide a pipeline 18 under the dam 3, and thence to a drilled well 19 which extends down to a sand or gravel bed 20. A valve 21 in the pipe 18 will control the flow of Water into the drilled well 19.
Having described my invention, I claim:
1. A dam construction comprising a dam foundation including spaced piers, and beams extending between said piers, means on said piers shaped to receive said beams, and means on the piers extending into the dam foundation to prevent horizontal shifting of said piers relative to the dam foundation, and piles extending through said piers and into the dam foundation.
2. A dam construction as recited in claim 1, and piles extending through said piers and into the dam foundation, and a cable extending between the piles and over said beams.
3. A dam construction as recited in claim 1, and holddown means extending over the beams to secure said beams to the piers.
4. A dam construction as recited in claim 1, and said means on the piers to fit the beam being tooth shaped, and the beams being polygonal in cross section to fit into said teeth.
5. A dam construction as recited in claim 1, and holddown means extending over the beams to secure said beams to the piers, said means on the piers to fit the beams being tooth shaped, and the beams being polygonal in cross section to fit into said teeth.
6. A dam construction as recited in claim 1, and piles extending through said piers and into the dam foundation, hold-down means extending over the beams to secure said beams to the piers, and said means on the piers to fit the beams being tooth shaped, and the beams being polygonal in cross section to fit into said teeth.
7. A dam construction as recited in claim 1, piles extending through said piers and into the dam foundation, a cable extending between the piles and over said beams, and said means on the piers to fit the beams being tooth shaped, and the beams being polygonal in cross section to fit into said teeth.
References Cited UNITED STATES PATENTS JACOB SHAPIRO, Primary Examiner US. Cl. X.R.
US651526A 1967-07-06 1967-07-06 Dam construction Expired - Lifetime US3465530A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US65152667A 1967-07-06 1967-07-06

Publications (1)

Publication Number Publication Date
US3465530A true US3465530A (en) 1969-09-09

Family

ID=24613181

Family Applications (1)

Application Number Title Priority Date Filing Date
US651526A Expired - Lifetime US3465530A (en) 1967-07-06 1967-07-06 Dam construction

Country Status (1)

Country Link
US (1) US3465530A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3969900A (en) * 1974-08-29 1976-07-20 Raymond International, Inc. Breakwater construction
US4784520A (en) * 1986-12-01 1988-11-15 Stevens C Leigh Shoreline protecting system and apparatus
ES2159996A1 (en) * 1998-01-13 2001-10-16 Univ Sevilla Small valley water prefabricated protective outlet consists of an e.g. concrete dam with continuous water discharge preventing turbulence
US6588979B1 (en) * 2002-08-21 2003-07-08 Peter Pasij Flood fence
US6641329B1 (en) 1998-02-13 2003-11-04 Flood Services Inc. Liquid containment/diversion dike
US7214005B1 (en) * 2006-06-12 2007-05-08 Davis George T Sectionalized flood control barrier
US20100209192A1 (en) * 2006-06-23 2010-08-19 Hans Christian Behm Adjustable weir for hydroelectric dam installations
US20120207545A1 (en) * 2011-12-14 2012-08-16 Clarence A. Cassidy Rapid Deployment, Self-Inflating, Interlocking, Modular Flood-Water Barrier Wall System
US20150240437A1 (en) * 2014-02-27 2015-08-27 Caylym Technologies International, Llc Rapid deployment barrier system
US20190136651A1 (en) * 2017-11-08 2019-05-09 Jose Guerrero, JR. Fluid containment structure and system
US10975539B2 (en) * 2019-06-26 2021-04-13 Robert John Parsons Rapidly deployable flood defence system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US601407A (en) * 1898-03-29 Anchor for securing jetties
US828469A (en) * 1906-02-09 1906-08-14 Charles E Fowler Bridge-pier.
US1075128A (en) * 1910-03-08 1913-10-07 Theodore H Skinner Dam.

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US601407A (en) * 1898-03-29 Anchor for securing jetties
US828469A (en) * 1906-02-09 1906-08-14 Charles E Fowler Bridge-pier.
US1075128A (en) * 1910-03-08 1913-10-07 Theodore H Skinner Dam.

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3969900A (en) * 1974-08-29 1976-07-20 Raymond International, Inc. Breakwater construction
US4784520A (en) * 1986-12-01 1988-11-15 Stevens C Leigh Shoreline protecting system and apparatus
ES2159996A1 (en) * 1998-01-13 2001-10-16 Univ Sevilla Small valley water prefabricated protective outlet consists of an e.g. concrete dam with continuous water discharge preventing turbulence
US6641329B1 (en) 1998-02-13 2003-11-04 Flood Services Inc. Liquid containment/diversion dike
US6588979B1 (en) * 2002-08-21 2003-07-08 Peter Pasij Flood fence
US7214005B1 (en) * 2006-06-12 2007-05-08 Davis George T Sectionalized flood control barrier
US20100209192A1 (en) * 2006-06-23 2010-08-19 Hans Christian Behm Adjustable weir for hydroelectric dam installations
US20120207545A1 (en) * 2011-12-14 2012-08-16 Clarence A. Cassidy Rapid Deployment, Self-Inflating, Interlocking, Modular Flood-Water Barrier Wall System
US20150240437A1 (en) * 2014-02-27 2015-08-27 Caylym Technologies International, Llc Rapid deployment barrier system
US9512581B2 (en) * 2014-02-27 2016-12-06 Caylym Technologies International, Llc Rapid deployment barrier system
US20190136651A1 (en) * 2017-11-08 2019-05-09 Jose Guerrero, JR. Fluid containment structure and system
US10822894B2 (en) * 2017-11-08 2020-11-03 Jose Guerrero, JR. Fluid containment structure and system
US10975539B2 (en) * 2019-06-26 2021-04-13 Robert John Parsons Rapidly deployable flood defence system

Similar Documents

Publication Publication Date Title
US5697736A (en) Seawalls and shoreline reinforcement systems
US7708495B1 (en) Levee system
US8177457B2 (en) Pipeline protection and levee module system
US3465530A (en) Dam construction
RU2582814C1 (en) Method for construction of landslide protection structure of biopositive
US20090252555A1 (en) Protective wall, dyke and method of producing a dyke
CN112030877A (en) Bank protection engineering construction method and bank protection structure thereof
Weiss Construction technique of passing floods over earth dams
Duvivier THE SELSEY COAST PROTECTION SCHEME.
RU2800918C1 (en) Method for construction of retaining wall of armor ground design using flexible mattresses and slabs
RU2768715C1 (en) Earth dam drainage system
RU2791119C1 (en) Method for construction of geotechnical structures in the water area of urban rivers and canals
RU2243319C2 (en) Module of bank protective structure
Heibaum Natural disasters mitigation by using construction methods with geosynthetics (flooding)
O'Neill Jr Structural methods for controlling coastal erosion
Newman Earthwork Slips and Subsidences Upon Public Works: Their Causes, Prevention, and Reparation. Especially Written to Assist Those Engaged in the Construction Or Maintenance of Railways, Docks, Canals, Roads, Waterworks, River-banks, Reclamation Embankments, Drainage Works, Etc
US1900341A (en) Means for protecting earthen dams, river levees, etc.
DE315867C (en)
Brater Low cost shore protection used on the Great Lakes
Coche Pond construction for freshwater fish culture: pond-farm structures and layouts
Escoffier Design and performance of sea walls in Mississippi Sound
CN115710933A (en) Construction method of gravity retaining wall under wading condition
Heibaum The importance of geosynthetics in erosion control of canal and river banks
JPS5949371B2 (en) Coastal construction method
Burd High Dams on Pervious Glacial Drift