SU1020506A1 - Steel-concrete shaft lining - Google Patents
Steel-concrete shaft lining Download PDFInfo
- Publication number
- SU1020506A1 SU1020506A1 SU813351437A SU3351437A SU1020506A1 SU 1020506 A1 SU1020506 A1 SU 1020506A1 SU 813351437 A SU813351437 A SU 813351437A SU 3351437 A SU3351437 A SU 3351437A SU 1020506 A1 SU1020506 A1 SU 1020506A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- lining
- concrete
- steel
- shaft lining
- stiffeners
- Prior art date
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Rigid Pipes And Flexible Pipes (AREA)
- Lining And Supports For Tunnels (AREA)
Description
Изобретение относится к подземному строительству вертикальных турбинных водоводов ГЭС и ГАЭС.The invention relates to the underground construction of vertical turbine pipelines of hydroelectric power stations and PSPs.
Известна сталебетонная обделка;шахты, включающая обетонированный в вертикальной выработке стальной трубопро- * вод, снабженный кольцевыми ребрами жесткости, расположенными на внешней поверхности трубопровода L1J.Steel-concrete lining is known; shafts, including steel piping * concreted in a vertical working out, equipped with ring stiffeners located on the outer surface of the L1J pipeline.
В этой обделке стальной трубопровод имеет достаточную несущую спо- W собность на воздействие подземных вод и давление бетонной смеси при возведении обделки.In this lining, the steel pipeline has sufficient load-bearing ability to influence groundwater and the pressure of the concrete mixture during the construction of the lining.
Однако при заполнении затрубного .пространства бетонной смесью под реб-15 рами жесткости,как под потолочными поверхностями,образуются незаполненные полости.При остановлении этих полостей, в них собирается подземная вода, которая оказывает на трубопро- 20 вод как силовое, так и агрессивное воздействие. Кроме того, наличие полостей ослабляет заделку ребер жесткости в бетон, что снижает эксплуатационную надежность обделки. Для не- 25 допущения образования- полостей в ребрах жесткости устраивают проемы, однако последние не обеспечивают наг дежного контакта нижних поверхностей ребер с бетонным заполнением.. Для ™ ликвидации оставшихся под ребрами полостей (пустот) в оболочке стального трубопровода выполняют отверстия, через которые инъецируют в пустоты омонолйчивающий, например, цементный •раствор. После окончания инъецирова- 5 ния отверстия герметично заваривают и зашлифовывают. Таким образом, современная конструкция Сталебетонной обделки требует для своего исполнения дополнительные непроизводитель-ч '40 ные затраты и обделка имеет недостаточную эксплуатационную надежность.However, when the annular space is filled with concrete mixture under stiffening ribs, under the ceiling surfaces, empty cavities are formed. When these cavities stop, underground water collects in them, which has both force and aggressive effect on the pipeline. In addition, the presence of cavities weakens the sealing of stiffeners in concrete, which reduces the operational reliability of the lining. In order to prevent the formation of cavities in the stiffeners, openings are arranged, however, the latter do not ensure reliable contact of the lower surfaces of the ribs with concrete filling. voids are monolithic, such as cement mortar. After injection 5, the holes are hermetically sealed and ground. Thus, the modern design of reinforced concrete lining requires for its fulfillment additional neproizvoditel- h '40 nye costs and lining has insufficient operational reliability.
Известна также сталебетонная обделка шахты, включающая обетонированный в вертикальной плоскости сталь- 45 ной трубопровод с наружными спиральными ребрами жесткости £2].A steel-concrete lining of the shaft is also known, including a steel pipe concrete-cased in the vertical plane with external spiral stiffening ribs £ 2].
Однако известная обделка не исключаем указанных недостатков существующих конструкций, хотя и повышает не-50 сущую способность конструкции.However, the known lining does not exclude the indicated drawbacks of existing structures, although it increases the non-50 existing ability of the structure.
Цель изобретения - упрощение кон-, струкции, повышение качества бетони рбвания и сокращение трудозатрат н<* выполнение обделки.The purpose of the invention is to simplify the design, structure, improve the quality of concrete breaking and reduce labor costs n <* lining.
Указанная цель достигается тем, что наружные спиральные ребра жесткости выполнены в виде короба, размещенного основанием книзу и прикрепленного одной из боковых стенок к трубопроводу.This goal is achieved by the fact that the external spiral stiffening ribs are made in the form of a duct placed with the base down and attached to one of the side walls to the pipeline.
На фиг. 1 показана шахта, закрепленная предлагаемой обделкой, вертикальный разрез; на фиг. 2 - разрез А-А на фиг. 1. Обделка включает стальной трубопровод 1, смонтированный в вертикальной выработке 2 и обетонированный слоем бетона 3 враспор с породой 4. На внешней поверхности трубопровода 1 закреплены ребра жесткости 5, расположенные по спиральным линиям. Причем спирали могут быть выполнены как одноэвходными, так и двух- и более заходными. Это определяют в каждом конкретном случае расчетом в зависимости от диаметра трубопровода 1, действующей на него внешней нагрузки и несущей способности поперечного сечения ребра жесткости 5.In FIG. 1 shows a shaft fixed by the proposed lining, a vertical section; in FIG. 2 is a section AA in FIG. 1. The lining includes a steel pipe 1 mounted in a vertical excavation 2 and concrete-coated with a layer of concrete 3 at a time with the rock 4. On the outer surface of the pipe 1, stiffening ribs 5 are arranged along spiral lines. Moreover, the spirals can be made as single-exit, and two or more entry. This is determined in each case by calculation depending on the diameter of the pipeline 1, the external load acting on it and the bearing capacity of the cross section of the stiffener 5.
Ребра жесткости выполнены коробчатой формы, причем они своим основанием направлены книзу шахты..The stiffeners are box-shaped, with their base directed down the shaft ..
Обделку возводят следующим образом.The lining is erected as follows.
После проходки выработки 2 в ней монтируют трубопровод 1 с предварительно наваренными на него ребрами жесткости 5. Затем из дозатора, размещенного у устья шахты, в коробчатое ребро жесткости подают бетонную смесь, которая самотеком, двигаясь по спиральному желобу, поступает в нижнюю часть шахты. При этом благодаря тому, что к горизонтальным сечениям шахты ребра жесткости 5 подходят под углом, бетонная смесь плотно прилегает к нижней поверхности ребер без образования под последними пустот, что исключает необходимость выполнения в оболочке трубопровода отверстий л проведения инъекционных (работ под ребра жесткости.After driving the mine 2, a pipeline 1 is mounted in it with stiffeners 5 pre-welded onto it. Then, a concrete mixture is fed from the batcher located at the mouth of the shaft into the box-shaped stiffener, which flows by gravity into the lower part of the shaft by gravity. Moreover, due to the fact that the stiffeners 5 approach the horizontal sections of the shaft at an angle, the concrete mix fits snugly to the lower surface of the ribs without forming voids under the latter, which eliminates the need for injection holes to be made in the pipe shell (work under stiffeners.
Таким образом, предлагаемая сталебетонная обделка шахты позволяет сократить строительные затраты и повысить эксплуатационную надежность обделкиThus, the proposed steel-concrete lining of the mine allows to reduce construction costs and increase the operational reliability of the lining
ВНИИПИ Заказ 3855/25 Тираж 673 ПодписноеВНИИПИ Order 3855/25 Circulation 673 Subscription
Филиал ППП Патент,Branch of PPP Patent,
г.Ужгород, ул.Проектная,4Uzhhorod, Project 4,
4'44'4
фи9-1fi9-1
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813351437A SU1020506A1 (en) | 1981-10-27 | 1981-10-27 | Steel-concrete shaft lining |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813351437A SU1020506A1 (en) | 1981-10-27 | 1981-10-27 | Steel-concrete shaft lining |
Publications (1)
Publication Number | Publication Date |
---|---|
SU1020506A1 true SU1020506A1 (en) | 1983-05-30 |
Family
ID=20981605
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU813351437A SU1020506A1 (en) | 1981-10-27 | 1981-10-27 | Steel-concrete shaft lining |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU1020506A1 (en) |
-
1981
- 1981-10-27 SU SU813351437A patent/SU1020506A1/en active
Non-Patent Citations (1)
Title |
---|
1. Клингёрт К.В, и др. Стальные трубопроводы гидроэлектростанций М., Энерги , 1973, с. 1Г4-119. 2. Авторское свйдетельство СССР 610969, кл. Е 04 Н 12/28, 1976. * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206636579U (en) | A kind of subway shield tunnel construction feeding device | |
SU1020506A1 (en) | Steel-concrete shaft lining | |
US3307361A (en) | Method of constructing an underground structure | |
Yurkevich | Developments in segmental concrete linings for subway tunnels in Belarus | |
KR102103978B1 (en) | Reinforcement and waterproof structure of vertical shafts for utility interface | |
CN213063587U (en) | Prevention and control device for upward floating of full-section rocky stratum slurry shield segment | |
WO2021151289A1 (en) | Underwater tunnel, construction method thereof and water blocking machine for construction | |
KR970070352A (en) | New construction method of underground structures under non-installation | |
CN112228076A (en) | Fast excavation construction method for hard rock large-span tunnel | |
US3117423A (en) | Method for the production of underwater foundations | |
JPH0788759B2 (en) | Tunnel lining method | |
RU2114377C1 (en) | Combination lining of special underground structure | |
CN216240643U (en) | Joint structure for receiving shield machine in mine tunnel | |
SU1765288A1 (en) | Water pipeline shaft | |
McKenzie et al. | MERSEY KINGSWAY TUNNEL: CONSTRUCTION. | |
CN210460662U (en) | Shield constructs manhole | |
Wassif | Interconnecting tunnel for the Ameriaa pumping station of the greater Cairo wastewater project | |
IL34532A (en) | System for the deepening of the bottom in front of moles and retaining walls of marine and river installations and the re-inforced moles so obtained | |
SU861614A1 (en) | Method of erecting steel-concrete lining | |
SU1081352A1 (en) | Method and apparatus for erecting monolithic concrete lining of mine shaft | |
SU1070269A1 (en) | Combination lining for hydraulic engineering shaft | |
Terris et al. | NEW TUNNELS NEAR POTTERS BAR IN THE EASTERN REGION OF BRITISH RAILWAYS. | |
JP2023128599A (en) | Supporting structure and tunnel construction method | |
RU20925U1 (en) | TUNNEL LINING | |
JPH0339598A (en) | Tunnel lining made of steel sheet concrete |