SU1008157A1 - Method of lifting long structures - Google Patents

Method of lifting long structures Download PDF

Info

Publication number
SU1008157A1
SU1008157A1 SU813355710A SU3355710A SU1008157A1 SU 1008157 A1 SU1008157 A1 SU 1008157A1 SU 813355710 A SU813355710 A SU 813355710A SU 3355710 A SU3355710 A SU 3355710A SU 1008157 A1 SU1008157 A1 SU 1008157A1
Authority
SU
USSR - Soviet Union
Prior art keywords
support
mounting
axis
lifting
hinge
Prior art date
Application number
SU813355710A
Other languages
Russian (ru)
Inventor
Анатолий Валентинович Цитович
Галина Валентиновна Гущина
Алексей Леонидович Кудояров
Original Assignee
Всесоюзный Государственный Проектно-Изыскательский И Научно-Исследовательский Институт Энергетических Систем И Электрических Сетей "Энергосетьпроект"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный Государственный Проектно-Изыскательский И Научно-Исследовательский Институт Энергетических Систем И Электрических Сетей "Энергосетьпроект" filed Critical Всесоюзный Государственный Проектно-Изыскательский И Научно-Исследовательский Институт Энергетических Систем И Электрических Сетей "Энергосетьпроект"
Priority to SU813355710A priority Critical patent/SU1008157A1/en
Application granted granted Critical
Publication of SU1008157A1 publication Critical patent/SU1008157A1/en

Links

Landscapes

  • Emergency Lowering Means (AREA)

Description

110 Изобретение относитс  к строитель ству, в частности, может быть исполь зовано при монтаже длинномерных нет сущих строительных элементов, преимущественно V-образных и одностоечиых опор линий электропередачи, имею щих шарнирное соединение с фундаментом . Известен способ монтажа V-образных и одностоечных опор линий переда чи, заключающийс  в повороте собранной на горизонтальной площадке опоры монтажной стрелой с удерживанием опо ры в процессе поворота в плоскости подъема с помощью нескольких вспомогательныл механизмов tl. Недостатком способа  вл етс  необходимость во вспомогательных механизмах и больших размеров площадки дл  их размещени . Наиболее близким к предлагаемому  вл етс  способ подъема длинномерных конструкций, преимущественно опор воздушных линий электропередачи , имеющих один опорный узел, включающий предварительную сборку опоры в горизонтальном положении, соедине ние ее с опорным шарниром, устройство монтажных  корей с последующим соединением их посредством монтажных расчалок с опорой и поворот конструкции относительно опорного шарнира 2. Недостатками известного способа  вл ютс  низка  эффективность и слож ность монтажа из-за большого объемй ручных работ по закреплению монтажных блоков и запасовке в них такелаж ного троса, больша  веро тность повреждени  элементов креплени  посто н ных отт жек, рассчитанных на одностороннюю осевую нагрузку, из-за воз никающих в процессе мс 1тажа измен ющихс  по величине и направлению нагрузок , кроме того необходимость в специальном навесном оборудовании двухбарабанной лебедки, а также необходимость в посто нном высококвалифицированном контроле за монтируемой конструкцией из-за повышенной опасности работ в случае неравномерного нат жени  такелажных тросов. Цель изобретени  - снижение трудо емкости и стоимости, а также повышение безопасности работ. Поставленна  цель достигаетс  тем что согласно способу подъема длинномерных конструкций, преимущественно опор воздушных линий электропередачи , имеющих один опорный узел, включающий предварительную сборку опоры в горизонтальном положении, соединение ее с опорным шарниром, устройство монтажных  корей с последующим соединением их посредством монтажных расчалок с опорой и поворот конструкции относительно опорного шарнира, монтажные расчалки выполн ют посто нной длины, располагают их в плоскости симметрии опоры, перпендикул рной оси линии электропередачи, и креп т к  кор м по оси поворота опоры. На фиг. 1 изображена опора линии электропередачи, выложенна  на месте установки и подготовленна  к подъему , общий вид; на фиг. 2 - опора линии электропередачи, установленна  в рабочее положение, общий вид. Способ осуществл ют следующим образом . Опору 1, имеющую один опорный узел 2, полностью собирают и выкладывают на месте установки, креп т посто нные отт жки 3 со стороны выкладки опоры, устраивают по оси симметрии опоры, перпендикул рной оси линии электропередачи, монтажные  кор  k, например винтовые. Монтажные отт жки 5 креп т одним концом к  корю k, другим к силовому узлу 1 опоры. Регулировки нат жени  монтажных отт жек 5 производ т при помощи талрепов 6, при этом узлы креплени  отт жек наход тс  на одной оси 7 с опорным узлом 2 конструкции. Поворот в рабочее положение - подготовленной к подъему опоры 1 производ т с помощью вспомогательного оборудовани , например, падающей стрелой 8, вожжей 9 и т гового троса 10, соединенного с силовым механизмом 11. Закрепление посто нных отт жек 3 со стороны, противоположной выкладке опоры, производ т после подъема опоры 1 в рабочее положение. Предлагаемый способ подъема опор линий электропередачи позвол ет снизить трудоемкость иостоимость строительно-монтажных работ за счет упрощени  конструкции монтажных раст жек и исключени  ручных работ по закреплению блоков полиспаста и его запасовке. Кроме того, предлагаемый способ позвол ет повысить безопасность работ за счет создани  расположением монтажных раст жек и  корей неизмен емой в процессе подъема системы.110 The invention relates to the construction, in particular, can be used for the installation of lengthy no existing building elements, mainly V-shaped and single-carriage pylons of power transmission lines that have a hinged connection to the foundation. There is a known method of mounting V-shaped and single-rack supports of transmission lines, which consist of turning the assembly boom on the horizontal platform of the support with the mounting boom holding the support in the process of turning in the plane of lifting with the help of several auxiliary mechanisms tl. The disadvantage of this method is the need for auxiliary mechanisms and large sizes of the site for their placement. The closest to the present invention is a method of lifting long structures, mainly supports of overhead transmission lines, having one supporting unit, including pre-assembling the support in a horizontal position, connecting it to the supporting hinge, mounting koreas, and then connecting them by means of mounting braces to the support and rotation of the structure relative to the support hinge 2. The disadvantages of this method are low efficiency and complexity of installation due to the large volume of hand-held a bot for fastening the mounting blocks and stocking the rigging cable in them, is more likely to damage the fastening elements of constant pulls designed for one-sided axial load, due to changes in magnitude and direction of loads, in addition to the need for special attachment of a two-drum winch, as well as the need for constant highly skilled control of the mounted structure due to the increased risk of work in case of uneven tension kelazhnyh cables. The purpose of the invention is to reduce labor capacity and cost, as well as increase work safety. The goal is achieved by the method of lifting lengthy structures, mainly supports of overhead power lines, having one support unit, including pre-assembling the support in a horizontal position, connecting it to the support hinge, mounting korya devices, then connecting them by means of mounting braces with the support and turning constructions relative to the support hinge, the mounting braces are of constant length, arranged in the plane of symmetry of the support, perpendicular to the axis of the power line, and attached to the cor m along the axis of rotation of the support. FIG. 1 shows a power line support, laid out on the installation site and prepared for lifting, general view; in fig. 2 - transmission line support, installed in working position, general view. The method is carried out as follows. The support 1, having one support unit 2, is completely assembled and laid out at the installation site, the fixed braces 3 are fixed on the side of the bearing layout, arranged on the axis of symmetry of the support, perpendicular to the axis of the transmission line, mounting cortex k, for example screw. The mounting braces 5 are fastened at one end to the bark k, the other to the power node 1 of the support. Tension adjustments for mounting tacks 5 are made using lanyards 6, with the mounting points of tackers being on the same axis 7 with supporting unit 2 of the structure. Turning to the working position — the support 1 prepared for lifting is produced by ancillary equipment, for example, a falling arrow 8, reins 9 and a pull cable 10 connected to the force mechanism 11. Fixing the constant displacements 3 on the side opposite to the support layout, produced after lifting support 1 into position. The proposed method of lifting power line poles reduces the laboriousness and cost of construction and installation work by simplifying the design of the installation stretch and eliminating the manual work of securing the polyspast blocks and its reserve. In addition, the proposed method makes it possible to increase the safety of work by making the location of the installation stretch bars and Korea unchanged during the lifting process.

Claims (1)

СПОСОБ ПОДЪЕМА ДЛИННОМЕРНЫХ КОНСТРУКЦИЙ, преимущественно опор воздушных линий электропередачи, имеющих один опорный узел, включающий предварительную сборку опоры в горизонтальном положении, соединение ее с опорным шарниром, устройство монтажных якорей с последующим соединением их посредством монтажных расчалок с опорой и поворот конструкции относительно опорного шарнира, отличающийся тем, что, с целью снижения трудоем! кости и повышения безопасности работ, монтажные расчалки выполняют . постояннной длины, располагают их в плоскости симметрии опоры, перпендикулярной оси линии электропередачи, и крепят к якорям по оси поворота опоры.METHOD FOR LIFTING LONG-DIMENSIONAL STRUCTURES, mainly overhead power transmission line supports having one support unit, including pre-assembly of the support in horizontal position, connecting it to the support hinge, mounting anchors with their subsequent connection with mounting brackets with the support and turning the structure relative to the support hinge so that, in order to reduce labor! bones and increase the safety of work, mounting braces perform. of constant length, place them in the plane of symmetry of the support perpendicular to the axis of the power line, and fasten to the anchors along the axis of rotation of the support. SU „„1008157 >SU „„ 1008157> 1 1008157 2 1 1008157 2
SU813355710A 1981-11-02 1981-11-02 Method of lifting long structures SU1008157A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813355710A SU1008157A1 (en) 1981-11-02 1981-11-02 Method of lifting long structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813355710A SU1008157A1 (en) 1981-11-02 1981-11-02 Method of lifting long structures

Publications (1)

Publication Number Publication Date
SU1008157A1 true SU1008157A1 (en) 1983-03-30

Family

ID=20983115

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813355710A SU1008157A1 (en) 1981-11-02 1981-11-02 Method of lifting long structures

Country Status (1)

Country Link
SU (1) SU1008157A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Технологические карты на сооружение ВЛ 35-500 кВ, шифр К-Ш-31. К-Ш-32. Сб. Оргэнергострой, М., 197А.. 2. Авторское свидетельство СССР № 5 9«1б, кл. В 66 F 11/02, 1975 (прототип), *

Similar Documents

Publication Publication Date Title
SU1008157A1 (en) Method of lifting long structures
CN217000804U (en) Climb frame with stay cable formula prestressing force cantilever beam integrated configuration
KR200407667Y1 (en) B-cable long span using principle of a bow
SU1092261A1 (en) Method of mounting a guy-rope girder
JP2984700B2 (en) Control method of installation distance in lift-up method of beam string
SU1617513A1 (en) Overpass of power transmission line
SU973771A1 (en) Method of erecting a power transmission line support
SU751948A1 (en) Detachable ladder
SU1500747A1 (en) Support of power transmission line
SU1010240A1 (en) Power transmission line support
SU1567752A1 (en) Power transmission line support
SU898026A1 (en) Power transmission line construction method
CN218147821U (en) Telescopic general operating platform in cable-stayed bridge cable tower
SU988761A1 (en) Arrangement for installation of elongated structures
SU846503A1 (en) Method of hoisting long-sized structures
SU965988A1 (en) Method for installtaion of tower of power transmission line
SU1087640A1 (en) Jig for mounting sub-frames
SU1219771A1 (en) Corner support for power transmission line
RU2152496C1 (en) Power transmission line support and method for its installation
SU141281A1 (en) Building flooring with construction truss girders having a sloped bottom along
SU1025845A1 (en) Prestrained spatial truss and method of erecting same
SU1004583A1 (en) Method of mounting elongated structures
SU1733608A1 (en) Traverse of supply line ferroconcrete pylon
SU1059106A1 (en) Power transmission line support
KR950014588B1 (en) Method of assembling bridge