RU2521521C1 - Method for laying subsurface pipeline - Google Patents

Method for laying subsurface pipeline Download PDF

Info

Publication number
RU2521521C1
RU2521521C1 RU2013121510/06A RU2013121510A RU2521521C1 RU 2521521 C1 RU2521521 C1 RU 2521521C1 RU 2013121510/06 A RU2013121510/06 A RU 2013121510/06A RU 2013121510 A RU2013121510 A RU 2013121510A RU 2521521 C1 RU2521521 C1 RU 2521521C1
Authority
RU
Russia
Prior art keywords
trench
pipeline
carpet
soil
carpets
Prior art date
Application number
RU2013121510/06A
Other languages
Russian (ru)
Inventor
Юрий Дмитриевич Тарасов
Александр Константинович Николаев
Василий Иванович Климко
Original Assignee
Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" filed Critical Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный"
Priority to RU2013121510/06A priority Critical patent/RU2521521C1/en
Application granted granted Critical
Publication of RU2521521C1 publication Critical patent/RU2521521C1/en

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

FIELD: construction.
SUBSTANCE: method consists in excavation of a trench, laying of a pipeline in the trench, overlapping its bottom, lateral surfaces and the trench benching with flexible carpets with formation of lateral pockets, their filling and filling of the pipeline top with soil, soil overlapping with longitudinal areas of the carpets and final filling of the trench with formation of the outer ridge. Before the pipeline laying into the trench, an additional lower flexible carpet is laid, the width of which is larger that the length of the inner transversal perimeter of the trench. The end parts of the additional lower carpet are designed with holes with the possibility of placing in them the pins, securing the carpet on the berms after the final filling of the trench with soil. Metal hinges are fastened at the ends of the lower and upper carpets with the possibility of interaction of lifting mechanisms, used when carrying out repair operations on the pipeline, with hooks. The hinges at the ends of the upper carpet after soil filling into the trench can be interconnected by means of a detachable device.
EFFECT: reduction of time consumption and labour intensity at the repair of the pipeline, increase of fixation reliability of the pipeline laid in the trench.
2 cl, 3 dwg

Description

Изобретение относится к строительству трубопроводов на обводненных и болотистых участках трассы.The invention relates to the construction of pipelines on flooded and marshy sections of the route.

Известен принятый за прототип способ прокладки подземного трубопровода, заключающийся в раскопке траншеи, укладке в траншею трубопровода, перекрытии части его дна, боковых поверхностей и берм траншеи гибкими коврами с образованием боковых карманов, засыпке их и верха трубопровода грунтом, перекрытии грунта продольными участками ковров и окончательной засыпке траншеи с образованием наружного валика, один из двух боковых карманов каждого ковра выполняют с провисанием над дном траншеи, а у смежных развернутых ковров карманы с провисанием располагают в шахматном порядке относительно оси трубопровода, при этом каждый ковер со стороны провисающего кармана сначала фиксируют от сдвига на берме траншеи грунтовой насыпью, затем засыпают противоположный карман до верха трубопровода, препятствуя сдвигу ковра по его поверхности частичной засыпкой провисающего кармана, а затем продолжая его засыпку и засыпку траншеи в целом, при этом расчетную длину участка ковра, образующего провисающий карман, определяют в зависимости от модуля упругости и прочности при растяжении материала ковра (Пат. РФ №2467240, МПК F16L 1/028, 1/06, опубл. 20.11.20012 г., бюл. №32).A known accepted as a prototype method of laying an underground pipeline, which consists in excavating a trench, laying in a trench pipe, overlapping part of its bottom, side surfaces and berm trenches with flexible carpets with the formation of side pockets, filling them and the top of the pipeline with soil, covering the ground with longitudinal sections of carpets and the final backfilling the trench with the formation of the outer roller, one of the two side pockets of each carpet is sagging above the bottom of the trench, and for adjacent unfolded carpets, the pockets are sagging m are arranged in a checkerboard pattern relative to the axis of the pipeline, with each carpet from the side of the sagging pocket being first fixed from shear on the berm of the trench with an embankment, then the opposite pocket is filled up to the top of the pipeline, preventing the carpet from being moved along its surface by partially filling the sagging pocket, and then continuing to backfilling and backfilling of the trench as a whole, while the estimated length of the section of carpet forming a sagging pocket is determined depending on the modulus of elasticity and tensile strength of the material carpet (Pat. RF №2467240, IPC F16L 1/028, 1/06, publ. 11/20/20012, bull. No. 32).

Однако недостатками известного способа являются сложность, увеличенные временные затраты и большая трудоемкость доступа к трубопроводу в случае его ремонта и замены труб его отдельных участков за счет сложности захвата свободных концов ковров и их подъема со значительным весом размещенного в них грунта, а также подъема, при необходимости, участка трубопровода.However, the disadvantages of this method are the complexity, increased time and laborious access to the pipeline in case of repair and replacement of pipes of its individual sections due to the difficulty of capturing the free ends of the carpets and lifting them with a significant weight of the soil placed in them, as well as lifting, if necessary section of the pipeline.

Техническим результатом изобретения является прокладка подземного трубопровода с возможностью упрощения, уменьшения временных затрат и трудоемкости работ при ремонте трубопровода.The technical result of the invention is the laying of an underground pipeline with the ability to simplify, reduce time and labor costs during the repair of the pipeline.

Технический результат достигается тем, что в способе прокладки подземного трубопровода, заключающемся в раскопке траншеи, укладке в траншею трубопровода, перекрытии части его дна, боковых поверхностей и берм траншеи гибкими коврами с образованием боковых карманов, засыпке их и верха трубопровода грунтом, перекрытии грунта продольными участками ковров и окончательной засыпке траншеи с образованием наружного валика, перед укладкой трубопровода в траншею укладывают дополнительный нижний гибкий ковер, ширина которого принята равной больше длины внутреннего поперечного периметра траншеи, а концевые части дополнительного нижнего ковра выполняют с отверстиями с возможностью размещения в них штырей, фиксирующих ковер на бермах после окончательной засыпки траншеи грунтом, а на концах нижнего и верхнего ковров закрепляют металлические петли с возможностью взаимодействия с крюками грузоподъемных механизмов, используемых при выполнении ремонтных операций на трубопроводе. Петли на концах верхнего ковра после засыпки грунта в траншею могут быть соединены между собой разъемным устройством.The technical result is achieved by the fact that in the method of laying an underground pipeline, which involves digging a trench, laying a pipeline in a trench, blocking part of its bottom, side surfaces and trench berm with flexible carpets with the formation of side pockets, backfilling them and the top of the pipeline with soil, covering the soil with longitudinal sections carpets and the final filling of the trench with the formation of the outer roller, before laying the pipeline into the trench, lay an additional lower flexible carpet, the width of which is taken to be equal to more than the length of the inner transverse perimeter of the trench, and the end parts of the additional lower carpet are made with holes with the possibility of placing pins in them that fix the carpet on the berm after final filling of the trench with soil, and metal loops are fixed at the ends of the lower and upper carpets with the possibility of interaction with hooks of lifting mechanisms used during repair operations on the pipeline. The loops at the ends of the upper carpet after filling the soil into the trench can be interconnected by a detachable device.

На фиг.1 показано поперечное сечение траншеи с трубопроводом, размещенным на дополнительном ковре и частично засыпанным верхним ковром, на фиг.2 - то же, после окончательной засыпки траншеи грунтом, на фиг.3 - то же, при соединенных между собой концах верхнего ковра.Figure 1 shows the cross section of the trench with the pipeline placed on the additional carpet and partially covered with the upper carpet, figure 2 is the same, after the final filling of the trench with soil, figure 3 is the same, with the ends of the upper carpet connected to each other .

Способ прокладки подземного трубопровода 1 заключается в том, после раскопки траншеи 2 перед укладкой трубопровода 1 в траншею 2 укладывают дополнительный нижний гибкий ковер 3, ширина которого принята равной больше длины внутреннего поперечного периметра траншеи 2. После этого боковые поверхности трубопровода 1, части его дна и бермы 4 траншеи 2 перекрываются верхними гибкими коврами 5 с образованием боковых карманов, которые засыпают вместе с верхней частью трубопровода 1 грунтом 6. После этого грунт 6 перекрывают продольными участками ковров 5 и окончательно засыпают траншею 2 с образованием наружного валика 7. Концевые части дополнительного нижнего ковра 3 выполняют с отверстиями 8 с возможностью размещения в них штырей 9, фиксирующих ковер 3 на бермах 4 после окончательной засыпки траншеи 2 грунтом 6 и 7 (фиг.2). На концах нижнего 3 и верхнего 5 ковров закрепляют металлические петли 10 и 11 с возможностью взаимодействия с крюками грузоподъемных механизмов (не показаны), используемых при выполнении ремонтных операций на трубопроводе 1. Петли 11 на концах верхнего ковра 5 после засыпки грунта 6 в траншею 2 могут быть соединены между собой разъемным устройством 12.The method of laying the underground pipeline 1 is that after excavating the trench 2 before laying the pipeline 1, an additional lower flexible carpet 3 is laid in the trench 2, the width of which is taken to be equal to the length of the inner transverse perimeter of the trench 2. After that, the side surfaces of the pipeline 1, parts of its bottom and Berm 4 trenches 2 overlap the upper flexible carpets 5 with the formation of side pockets, which fall asleep together with the upper part of the pipeline 1 soil 6. After that, soil 6 is blocked by longitudinal sections of the forks 5 and finally fill the trench 2 with the formation of the outer roller 7. The end parts of the additional lower carpet 3 are made with holes 8 with the possibility of placing pins 9 in them, fixing the carpet 3 on the berm 4 after the final filling of the trench 2 with soil 6 and 7 (Fig. 2 ) At the ends of the lower 3 and upper 5 carpets, metal loops 10 and 11 are fixed with the possibility of interaction with hooks of lifting mechanisms (not shown) used during repair operations on the pipeline 1. Loops 11 at the ends of the upper carpet 5 after filling the soil 6 into trench 2 can be interconnected by a detachable device 12.

Наличие дополнительного нижнего ковра 3 и выполнение обоих ковров 3 и 5 с металлическими петлями 10 и 11 на концах позволяет в значительной мере облегчить и ускорить процесс освобождения трубопровода 1 от грунта 6 и 7 за счет захвата и подъема с помощью грузоподъемных механизмов верхнего ковра 5 с размещенным на нем грунтом 6 и 7 и дополнительного ковра 3 с размещенным на нем поднимаемым участком трубопровода 1. Наличие металлических петель 10 и 11 на концах ковров 3 и 5 облегчает их захват и подъем. А наличие отверстий 8 на концах нижнего дополнительного ковра 3 обеспечивает его надежную фиксацию на бермах 4 с помощью штырей 9. Соединение с помощью разъемного устройства 12 обеих петель 11 на концах верхнего ковра 5, размещенных над трубопроводом 1, позволяет не только уменьшить ширину верхнего ковра 5, но и совместно с дополнительным нижним ковром 3 повышает надежность поперечной фиксации размещенного в траншее 2 трубопровода 1 с исключением его поперечного смещения в процессе эксплуатации.The presence of an additional lower carpet 3 and the execution of both carpets 3 and 5 with metal loops 10 and 11 at the ends can significantly facilitate and accelerate the process of releasing the pipeline 1 from the soil 6 and 7 due to the capture and lifting by means of lifting mechanisms of the upper carpet 5 with on it with soil 6 and 7 and an additional carpet 3 with a lifting section of pipeline 1 placed on it. The presence of metal loops 10 and 11 at the ends of carpets 3 and 5 facilitates their grasp and rise. And the presence of holes 8 at the ends of the lower additional carpet 3 ensures its reliable fixation on the berm 4 using the pins 9. The connection using the detachable device 12 of both loops 11 at the ends of the upper carpet 5, located above the pipeline 1, allows not only to reduce the width of the upper carpet 5 , but also in conjunction with an additional bottom carpet 3 increases the reliability of lateral fixation of the pipeline 1 placed in the trench 2 with the exception of its lateral displacement during operation.

Таким образом, отличительные признаки изобретения обеспечивают прокладку подземного трубопровода с возможностью упрощения, уменьшения временных затрат и трудоемкости работ при ремонте трубопровода, а также повышенную надежность фиксации размещенного в траншее трубопровода.Thus, the distinguishing features of the invention provide the laying of an underground pipeline with the possibility of simplification, reduction of time and laboriousness of work during the repair of the pipeline, as well as increased reliability of fixing placed in the trench of the pipeline.

Claims (2)

1. Способ прокладки подземного трубопровода, заключающийся в раскопке траншеи, укладке в траншею трубопровода, перекрытии его дна, боковых поверхностей и берм траншеи гибкими коврами с образованием боковых карманов, засыпке их и верха трубопровода грунтом, перекрытии грунта продольными участками ковров и окончательной засыпке траншеи с образованием наружного валика, отличающийся тем, что перед укладкой трубопровода в траншею укладывают дополнительный нижний гибкий ковер, ширина которого принята равной больше длины внутреннего поперечного периметра траншеи, а концевые части дополнительного нижнего ковра выполняют с отверстиями с возможностью размещения в них штырей, фиксирующих ковер на бермах после окончательной засыпки траншеи грунтом, а на концах нижнего и верхнего ковров закрепляют металлические петли с возможностью взаимодействия с крюками грузоподъемных механизмов, используемых при выполнении ремонтных операций на трубопроводе.1. A method of laying an underground pipeline, which involves digging a trench, laying a pipeline in a trench, blocking its bottom, side surfaces and trench berm with flexible carpets to form side pockets, backfilling them and the top of the pipeline with soil, covering the ground with longitudinal sections of carpets and finally filling the trench with the formation of an outer roller, characterized in that before laying the pipeline in the trench, an additional lower flexible carpet is laid, the width of which is taken equal to more than the length of the inner cross the perimeter of the trench, and the end parts of the additional lower carpet are made with holes with the possibility of placing pins in them, fixing the carpet on the berm after the soil is finally filled with trench, and metal loops are fixed at the ends of the lower and upper carpets with the possibility of interaction with the hooks of the lifting mechanisms used in performing repair operations on the pipeline. 2. Способ по п.1, отличающийся тем, что петли на концах верхнего ковра после засыпки грунта в траншею соединяют между собой разъемным устройством. 2. The method according to claim 1, characterized in that the loops at the ends of the upper carpet after filling the soil into the trench are connected to each other by a detachable device.
RU2013121510/06A 2013-05-07 2013-05-07 Method for laying subsurface pipeline RU2521521C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2013121510/06A RU2521521C1 (en) 2013-05-07 2013-05-07 Method for laying subsurface pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2013121510/06A RU2521521C1 (en) 2013-05-07 2013-05-07 Method for laying subsurface pipeline

Publications (1)

Publication Number Publication Date
RU2521521C1 true RU2521521C1 (en) 2014-06-27

Family

ID=51218315

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2013121510/06A RU2521521C1 (en) 2013-05-07 2013-05-07 Method for laying subsurface pipeline

Country Status (1)

Country Link
RU (1) RU2521521C1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1404737A1 (en) * 1968-01-15 1988-06-23 Всесоюзный Научно-Исследовательский И Проектный Институт По Транспорту Природного Газа "Внипитрансгаз" Method of laying underground pipe-line
SU1638419A1 (en) * 1988-06-29 1991-03-30 Всесоюзный научно-исследовательский институт по строительству магистральных трубопроводов A method for laying underground piping
SU1717893A1 (en) * 1985-07-29 1992-03-07 Всесоюзный научно-исследовательский институт по строительству магистральных трубопроводов Method for laying pipelines in trench on wear soils
RU2153119C2 (en) * 1998-04-20 2000-07-20 Всероссийский научно-исследовательский институт природных газов и газовых технологий РАО "Газпром" Method of ballasting subterranean pipe line
RU2467240C1 (en) * 2011-05-16 2012-11-20 Общество с ограниченной ответственностью "Газпром трансгаз Ухта" Underground pipeline routing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1404737A1 (en) * 1968-01-15 1988-06-23 Всесоюзный Научно-Исследовательский И Проектный Институт По Транспорту Природного Газа "Внипитрансгаз" Method of laying underground pipe-line
SU1717893A1 (en) * 1985-07-29 1992-03-07 Всесоюзный научно-исследовательский институт по строительству магистральных трубопроводов Method for laying pipelines in trench on wear soils
SU1638419A1 (en) * 1988-06-29 1991-03-30 Всесоюзный научно-исследовательский институт по строительству магистральных трубопроводов A method for laying underground piping
RU2153119C2 (en) * 1998-04-20 2000-07-20 Всероссийский научно-исследовательский институт природных газов и газовых технологий РАО "Газпром" Method of ballasting subterranean pipe line
RU2467240C1 (en) * 2011-05-16 2012-11-20 Общество с ограниченной ответственностью "Газпром трансгаз Ухта" Underground pipeline routing method

Similar Documents

Publication Publication Date Title
CN103590836B (en) Method for processing tunnel collapse caused by shallow-buried excavation
CN104653195B (en) A kind of coombe landforms tunnel portal structure and its construction method
CN107938463A (en) A kind of road seepage-proof structure and tunnel road surface infiltration Treatment Methods
RU2521521C1 (en) Method for laying subsurface pipeline
RU2015131903A (en) Permanent frozen drainage system
CN108194764A (en) The means of defence of underground piping during a kind of excavation pipe trench
RU114468U1 (en) DEVICE FROM GEOTEXTILE MATERIALS AS A FORMING SHIELD OF A PILES
CN108824466A (en) A kind of foundation pit side-wall water burst gushes the processing method of sand
USRE30185E (en) Trench shoring assembly
CN203834304U (en) Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same
CN209398426U (en) A kind of tunnel structure
RU124349U1 (en) STRUCTURE OF THE Trench for laying the pipe in the areas of tectonic faults
RU106632U1 (en) WEIGHT-PRECIOUS REINFORCED CONCRETE WEIGHT COVERING TYPE UBO-UM
ES2424805T3 (en) Tuning device to trench trenches
RU2411360C1 (en) Method of underground mining of massive steep ore deposits
RU2342586C1 (en) Textile container for pipeline ballasting
RU85206U1 (en) SOFT PIPELINE BALLASTING CONTAINER
JP6814581B2 (en) Pipe burying method
CN111691392B (en) Backfill construction method for sludge texture foundation
KR20060063827A (en) Prefabricated drainage pipe and rapid drainage method using the same
RU2467240C1 (en) Underground pipeline routing method
KR101525827B1 (en) Panel Module for Constructing Retaining Wall
RU2498141C1 (en) Method of underwater pipeline naked section repair
RU2465509C1 (en) Method to protect units of underground pipelines in areas with higher seismicity in permafrost soils
RU2176758C1 (en) Method of laying preliminarily ballasted pipe line in flooded sections

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees