CN203834304U - Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same - Google Patents

Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same Download PDF

Info

Publication number
CN203834304U
CN203834304U CN201420200688.3U CN201420200688U CN203834304U CN 203834304 U CN203834304 U CN 203834304U CN 201420200688 U CN201420200688 U CN 201420200688U CN 203834304 U CN203834304 U CN 203834304U
Authority
CN
China
Prior art keywords
roadbed
layer
enclosed
totally
composite construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420200688.3U
Other languages
Chinese (zh)
Inventor
武可爽
刘泽
李卫炎
朱川曲
奚兵
龚清富
林琼
陈高
傅永刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG TRANSPORTATION ENGINEERING CONSTRUCTION GROUP NO3 TRANSPORTATION ENGINEERING Co Ltd
Hunan University of Science and Technology
Original Assignee
ZHEJIANG TRANSPORTATION ENGINEERING CONSTRUCTION GROUP NO3 TRANSPORTATION ENGINEERING Co Ltd
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG TRANSPORTATION ENGINEERING CONSTRUCTION GROUP NO3 TRANSPORTATION ENGINEERING Co Ltd, Hunan University of Science and Technology filed Critical ZHEJIANG TRANSPORTATION ENGINEERING CONSTRUCTION GROUP NO3 TRANSPORTATION ENGINEERING Co Ltd
Priority to CN201420200688.3U priority Critical patent/CN203834304U/en
Application granted granted Critical
Publication of CN203834304U publication Critical patent/CN203834304U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a fully-closed roadbed waterproof and drainage composite structure. The fully-closed roadbed waterproof and drainage composite structure comprises a geogrid layer, and seamless waterproof layers are connected to the upper surface and the lower surface of the geogrid layer in a glued mode respectively; each seamless waterproof composite layer comprises more than two glass fabric layers soaked and glued by waterproof factice, wherein each glass fabric layer is formed by mutually overlapping multiple pieces of glass fabric, and all the glass fabric layers are glued into a whole through the waterproof factice. A roadbed structure comprises a foundation bed bottom layer and a roadbed foundation, and the fully-closed roadbed waterproof and drainage composite structure is laid between the foundation bed bottom layer and the roadbed foundation. The fully-closed roadbed waterproof and drainage composite structure has the advantages of being good in waterproof and drainage effect and easy to construct and having certain tensile strength, and laying length and width are not limited.

Description

The anti-draining composite construction of totally-enclosed roadbed and there is the road structure of this composite construction
Technical field
The utility model relates to the anti-water discharge technology of civil works field, is specifically related to the anti-draining composite construction of a kind of totally-enclosed roadbed and has the road structure of this composite construction.
Background technology
For various water sensitive Rock Subgrades, as expansive soil (rock) roadbed, collapsible loess subgrade, water is the main cause that causes various subgrade defects, therefore, when the design of this class roadbed and construction, must take effective measures the Moisture Damage that prevents roadbed.Being applied to now the anti-drainage measure of roadbed mainly contains: 1, in roadbed, (surface layer of subgrade bed or bottom) arranges composite geo-membrane roadbed is sealed, and avoids extraneous water source to infiltrate bedding; 2, in roadbed side, gutter is set, the various water in the external world is converged to gutter and discharge.
Because various geomembranes are subject to plant produced condition restriction, in length, impossible endless, also can not meet width of subgrade requirement at width, therefore, during actual laying, unavoidably will splice.There is no at present the antiseepage problem that reliable method solves composite geo-membrane stitching portion, composite geo-membrane also cannot well be connected with roadbed gutter simultaneously, makes extraneous water source survey infiltration roadbed from geomembrane stitching portion and gutter, causes subgrade defect.
Utility model content
The technical problems to be solved in the utility model is to overcome the deficiency that prior art exists, provide a kind of anti-drainage effect good, there is the anti-draining composite construction of totally-enclosed roadbed that certain tensile strength, laying length and width are unrestricted, be easy to construction, also corresponding provide a kind of anti-drainage effect good, be easy to the road structure that construction, lower, life-span of cost are grown.
For solving the problems of the technologies described above, the utility model provides a kind of totally-enclosed roadbed anti-draining composite construction, comprise geogrids layer, the upper and lower surface of described geogrids layer is all bonded with seamless waterproof layer, described seamless waterproof composite bed comprises and two-layerly above by waterproofing unction, soaks into bonding glass layer of cloth, each layer of glass layer of cloth mutually overlapped and forms by polylith glass-fiber-fabric, and is integral by waterproofing unction is bonding.
In above-mentioned composite construction, in each seamless waterproof layer, described two-layer above glass layer of cloth is crisscross shape stack and arranges.
In above-mentioned composite construction, the width of adjacent glass-fiber-fabric faying surface is 10cm ~ 15cm.
In above-mentioned composite construction, described geogrids layer is bonding by waterproofing unction and seamless waterproof layer, and described waterproofing unction is impregnated in described geogrids layer.
As a total technical conceive, the utility model also provides a kind of road structure, comprises bottom layer of subgrade and foundation of road bed, is equipped with the anti-draining composite construction of above-mentioned totally-enclosed roadbed between described bottom layer of subgrade and foundation of road bed.
In above-mentioned road structure, the both sides of described road structure are provided with gutter, and the anti-draining composite construction of described totally-enclosed roadbed extends in the diapire and two side of gutter.
In above-mentioned road structure, the both sides of described road structure are provided with gutter, and the anti-draining composite construction of described totally-enclosed roadbed extends in the sidewall of gutter near road structure one side.
In above-mentioned road structure, the width that the anti-draining composite construction of described totally-enclosed roadbed is arranged in described sidewall is 10 ~ 15cm.
In above-mentioned road structure, diapire and the sidewall of described gutter are concrete body.
Compared with prior art, the utility model has the advantage of:
The anti-draining composite construction of the totally-enclosed roadbed of the utility model, there is anti-drain function and can bear certain pulling force, length and the width laid are unrestricted, the anti-drainage measure of roadbed can be extended to gutter position or realize connection with gutter, solved the antiseepage problem of current composite geo-membrane stitching portion, its cost is lower, construction is also very convenient.Road structure of the present utility model has been owing to having adopted above-mentioned composite construction, have anti-drainage effect good, be easy to construction, the advantage such as cost is lower, the life-span is long.
Accompanying drawing explanation
Fig. 1 is the sectional structure schematic diagram of the anti-draining composite construction of the totally-enclosed roadbed of the utility model.
Fig. 2 is the structural representation of the utility model road structure the first embodiment.
Fig. 3 is the construction process figure of the utility model road structure the first embodiment.
Fig. 4 is the partial structurtes schematic diagram of the utility model road structure the second embodiment.
Marginal data:
1, geogrids layer; 2, seamless waterproof layer; 21, waterproofing unction; 22, glass layer of cloth; 3, bottom layer of subgrade; 4, foundation of road bed; 5, gutter; 51, diapire; 52, sidewall; 6, the anti-draining composite construction of totally-enclosed roadbed.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is described in further detail.
Embodiment 1:
As shown in Figure 1, the anti-draining composite construction of a kind of totally-enclosed roadbed, comprise geogrids layer 1, geogrids layer 1 adopts the geo-grid that existing civil engineering is used to make, geogrids layer 1 upper, soffit is all bonded with seamless waterproof layer 2, geogrids layer 1 is bonding by waterproofing unction 21 and seamless waterproof layer 2, and waterproofing unction 21 is impregnated in geogrids layer 1, seamless waterproof layer 2 comprises and two-layerly above by waterproofing unction 21, soaks into bonding glass layer of cloth 22, each layer of glass layer of cloth 22 mutually overlapped and forms by polylith glass-fiber-fabric, and be integral by waterproofing unction 21 is bonding, thereby form holistic Waterproof structural course, waterproofing unction 21 can on-the-spot allotment also can be bought the barreled liquid repellent ointment 21 that specialized factory produces.This geogrids layer 1 upper, soffit is all bonded with the composite construction of seamless waterproof layer 2, there is anti-drain function and can bear certain pulling force, do not exist and at roadbed middle part, need the problem of overlap joint because of anti-drainage blanket short of width, length and the width of its laying are unrestricted, the anti-drainage measure of roadbed can be extended to gutter position or realize connection with gutter, can avoid because of the anti-drainage measure of traditional roadbed because of composite geo-membrane size restrictions need overlap joint, cause Shui Zi lap-joint and gutter side to infiltrate the difficult problem that roadbed causes disease, can be used for the highway to Moisture Damage sensitivity, speedway and railway bed, as expansive soil (rock) roadbed, collapsible loess subgrade etc.Its cost is lower, construction is also very convenient.
In the present embodiment, in each seamless waterproof layer 2, be equipped with 22, three layers of glass layer of cloth 22 of three layers of glass layer of cloth and be the staggered stack layout of transverse and longitudinal, and be integral by waterproofing unction 21 is bonding.In same layer glass layer of cloth 22, the width of adjacent glass-fiber-fabric faying surface is 10 ~ 15cm.During construction, after each layer of glass layer of cloth 22 completed, liquid repellent ointment 21 sprinkles, on the geogrids layer 1 laying, glass layer of cloth 22, after soaking into glass layer of cloth 22 and solidify, it are formed to the anti-draining composite construction of totally-enclosed roadbed that has anti-drain function and have certain tensile strength.In other embodiments, two-layer or four layers of above glass layer of cloth 22 also can be set in seamless waterproof layer 2.
Embodiment 2:
As shown in Figure 2, a kind of road structure, comprises bottom layer of subgrade 3 and foundation of road bed 4, is equipped with the anti-draining composite construction 6 of totally-enclosed roadbed described in embodiment 1 between bottom layer of subgrade 3 and foundation of road bed 4.The both sides of road structure are provided with gutter 5, and diapire 51 and the sidewall 52 of gutter 5 are concrete body, and the anti-draining composite construction 6 of totally-enclosed roadbed extends in the diapire 51 and two side 52 of gutter 5.Be the anti-draining composite construction 6 of totally-enclosed roadbed after stretch out the side of bottom layer of subgrade 3 and foundation of road bed 4, repave to the concrete of 5 one diapires 51 of gutter and two side 52, gutter 5 is surrounded.The present embodiment is to describe the anti-draining composite construction 6 of totally-enclosed roadbed is laid on to the bottom of road cutting type protecting embankment bedding.
The anti-draining composite construction 6 of totally-enclosed roadbed can be according to concrete roadbed design form of fracture, be laid on (bottom layer of subgrade 3 times) on foundation of road bed 4 and form totally enclosed type waterproof/drainage structure, also can be laid on bottom layer of subgrade 3, and can apply in various forms of beddings.
As shown in Figure 3, road structure of the present utility model, when Specific construction, adopts following steps,
(1) repeat to roll foundation of road bed 4, and check foundation of road bed 4 quality, until meet the requirement of filling compacting;
(2) at the both sides of foundation of road bed 4 excavation gutter 5;
(3) at the end face of foundation of road bed 4, lay three layers of glass layer of cloth 22, glass layer of cloth 22 is along horizontal and vertical staggered laying the successively of road structure, glass layer of cloth 22 is routed to diapire 51 and two sidewalls 52 of the gutter 5 having excavated simultaneously, the glass layer of cloth 22 at gutter 5 places should be an integral body with the glass layer of cloth 22 of foundation of road bed 4 end faces, does not cut off;
(4) on bottom seamless waterproof layer 2, lay geo-grid and form geogrids layer 1;
(5) repeating step (3) is laid three layers of glass layer of cloth 22 at geogrids layer 1 end face;
(6) the even sprinkle of liquid repellent ointment 21 is being laid in glass layer of cloth 22 and geogrids layer 1, during sprinkle waterproofing unction 21, foundation of road bed 4 end faces and gutter 5 places carry out simultaneously, allow waterproofing unction 21 fully soak into glass layer of cloth 22, after waterproofing unction 21 solidifies, form the anti-draining composite construction 6 of totally-enclosed roadbed;
(7) check the quality of the anti-draining composite construction 6 of totally-enclosed roadbed, qualified rear laying bottom layer of subgrade 3, then carry out subsequent processing by subgrade construction technique.
In above-mentioned work progress, the geogrids layer 1 in the anti-draining composite construction 6 of the totally-enclosed roadbed at gutter 5 places can not spread.
More than so that the anti-draining composite construction 6 of totally-enclosed roadbed is laid on foundation of road bed 4 and is described, when be laid on or bottom layer of subgrade 3 on time, construction method and flow process are constant.
Embodiment 3:
As shown in Figure 4, a kind of road structure, comprises bottom layer of subgrade 3 and foundation of road bed 4, is equipped with the anti-draining composite construction 6 of totally-enclosed roadbed described in embodiment 1 between bottom layer of subgrade 3 and foundation of road bed 4.The both sides of this road structure are provided with gutter 5, diapire 51 and the sidewall 52 of gutter 5 are concrete body, the anti-draining composite construction 6 of totally-enclosed roadbed extends in the sidewall 52 of gutter 5 near road structure one side, in the diapire 51 of gutter 5 and the sidewall 52 away from road structure one side, does not lay the anti-draining composite construction 6 of totally-enclosed roadbed.In the present embodiment, the width that the anti-draining composite construction 6 of totally-enclosed roadbed is arranged in sidewall 52 is 10cm ~ 15cm.
The construction technology of the present embodiment and embodiment's 2 is basic identical, difference is, when implementation step (3) and step (5), at foundation of road bed 4 end faces, lay in the process of glass layer of cloth 22, at the reserved wide glass-fiber-fabric of 10cm ~ 15cm of gutter 5 sides, when gutter 5 is built by laying bricks or stones, glass-fiber-fabric is imbedded in the concrete of its sidewall 52.
The above is only preferred embodiment of the present utility model, and protection domain of the present utility model is also not only confined to above-described embodiment.For those skilled in the art, do not departing under the utility model technical conceive prerequisite resulting improvement and conversion also should be considered as protection domain of the present utility model.

Claims (9)

1. the anti-draining composite construction of totally-enclosed roadbed, it is characterized in that: comprise geogrids layer (1), the upper and lower surface of described geogrids layer (1) is all bonded with seamless waterproof layer (2), described seamless waterproof composite bed (2) comprises and two-layerly above by waterproofing unction (21), soaks into bonding glass layer of cloth (22), each layer of glass layer of cloth (22) mutually overlapped and forms by polylith glass-fiber-fabric, and by bonding being integral of waterproofing unction (21).
2. the anti-draining composite construction of totally-enclosed roadbed according to claim 1, is characterized in that: in each seamless waterproof layer (2), described two-layer above glass layer of cloth (22) is crisscross shape stack and arranges.
3. the anti-draining composite construction of totally-enclosed roadbed according to claim 1, is characterized in that: the width of adjacent glass-fiber-fabric faying surface is 10cm ~ 15cm.
4. according to the anti-draining composite construction of totally-enclosed roadbed described in claim 1 or 2 or 3, it is characterized in that: described geogrids layer (1) is bonding by waterproofing unction (21) and seamless waterproof layer (2), and described waterproofing unction (21) is impregnated in described geogrids layer (1).
5. a road structure, comprise bottom layer of subgrade (3) and foundation of road bed (4), it is characterized in that: between described bottom layer of subgrade (3) and foundation of road bed (4), be equipped with the anti-draining composite construction of totally-enclosed roadbed (6) as described in any one in claim 1 to 4.
6. road structure according to claim 5, it is characterized in that: the both sides of described road structure are provided with gutter (5), the anti-draining composite construction of described totally-enclosed roadbed (6) extends in the diapire (51) and two side (52) of gutter (5).
7. road structure according to claim 5, it is characterized in that: the both sides of described road structure are provided with gutter (5), the anti-draining composite construction of described totally-enclosed roadbed (6) extends to gutter (5) near in the sidewall (52) of road structure one side.
8. road structure according to claim 7, is characterized in that: the width that the anti-draining composite construction of described totally-enclosed roadbed (6) is arranged in described sidewall (52) is 10 ~ 15cm.
9. according to the road structure described in claim 6 or 7 or 8, it is characterized in that: diapire (51) and the sidewall (52) of described gutter (5) are concrete body.
?
CN201420200688.3U 2014-04-24 2014-04-24 Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same Expired - Fee Related CN203834304U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420200688.3U CN203834304U (en) 2014-04-24 2014-04-24 Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420200688.3U CN203834304U (en) 2014-04-24 2014-04-24 Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same

Publications (1)

Publication Number Publication Date
CN203834304U true CN203834304U (en) 2014-09-17

Family

ID=51512164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420200688.3U Expired - Fee Related CN203834304U (en) 2014-04-24 2014-04-24 Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same

Country Status (1)

Country Link
CN (1) CN203834304U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108486963A (en) * 2018-04-27 2018-09-04 西南交通大学 Non-fragment orbit guarded drainage subgrade bed structure and its laying method
CN113931025A (en) * 2021-12-01 2022-01-14 中国铁道科学研究院集团有限公司铁道建筑研究所 Three-dimensional drainage system and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108486963A (en) * 2018-04-27 2018-09-04 西南交通大学 Non-fragment orbit guarded drainage subgrade bed structure and its laying method
CN108486963B (en) * 2018-04-27 2023-08-01 西南交通大学 Ballastless track waterproof roadbed bed structure and paving method thereof
CN113931025A (en) * 2021-12-01 2022-01-14 中国铁道科学研究院集团有限公司铁道建筑研究所 Three-dimensional drainage system and construction method thereof

Similar Documents

Publication Publication Date Title
CN104631254B (en) A kind of construction method of Fill Reinforced With Geogrids clay bound edge CHARACTERISTICS OF TAILINGS SAND roadbed
CN104928996B (en) Railway light soil side broad way based structures
CN103882884B (en) A kind of anchor cable geo-grid retaining structure and construction method thereof
CN205977229U (en) Arcading tunnel non - flushes entrance to a cave structure suitable for bias voltage condition
CN204940030U (en) Reconstruction and extension project new-old concrete bond Pavement mosaic structure
CN103233406B (en) A kind of road and storage yard pavement structure layer of long-term durable stable use and construction method thereof
CN103321122B (en) The construction method of a kind of highway, road structure and highway pavement
CN106368238A (en) Honeycomb geocell earth retaining wall with ecological restoration function and construction method thereof
CN108457150A (en) A kind of road widening project anticracking crack structure and its construction method
CN103696397A (en) Anti-seepage treatment method for artificial dam
CN106351239A (en) Cement modified soil strengthened geogrid reinforced soil structure and construction method thereof
CN203834304U (en) Fully-closed roadbed waterproof and drainage composite structure and roadbed structure with same
CN104594297B (en) A kind of double face slab rock-fill dams and construction method thereof
CN205617390U (en) A softer side of sears layer excavation supporting system for loess area
CN203947406U (en) The flexible splicing construction of new and old bridge longitudinal elasticity concrete
CN106522244B (en) A kind of embankment combination binding structure and its construction method
CN103572679B (en) A kind of embankment structure and dam filling construction reducing bumping at bridge-head incidence
CN105544696B (en) A kind of domatic rush infiltration method that dams of Mountain Area water and soil conservation
CN107419628A (en) A kind of construction method of the rapid build road on reclaimed ground
CN103835310A (en) Crib gravity retaining wall
CN206157760U (en) Honeycomb geotechnique check room retaining wall with ecological recovery function
CN103321123B (en) A kind of construction method of highway pavement
CN208088040U (en) A kind of widened structure applied to mountain highway barricade section
CN207512762U (en) A kind of friction pile repairs structure with the breakage mountain body that TGXG is combined
CN101003963A (en) Method for forming pavement of highway resisting large deformation of ground

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140917

Termination date: 20150424

EXPY Termination of patent right or utility model