CN104594297B - A kind of double face slab rock-fill dams and construction method thereof - Google Patents

A kind of double face slab rock-fill dams and construction method thereof Download PDF

Info

Publication number
CN104594297B
CN104594297B CN201410703396.6A CN201410703396A CN104594297B CN 104594297 B CN104594297 B CN 104594297B CN 201410703396 A CN201410703396 A CN 201410703396A CN 104594297 B CN104594297 B CN 104594297B
Authority
CN
China
Prior art keywords
high polymer
enrockment
concrete
composite panel
polymer composite
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410703396.6A
Other languages
Chinese (zh)
Other versions
CN104594297A (en
Inventor
杨贵
蒋裕丰
陈灵伟
胡鑫
郑延平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YUSHUN ECOLOGICAL CONSTRUCTION Co Ltd
Nanjing Hehai Technology Co Ltd
Original Assignee
YUSHUN ECOLOGICAL CONSTRUCTION Co Ltd
Nanjing Hehai Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUSHUN ECOLOGICAL CONSTRUCTION Co Ltd, Nanjing Hehai Technology Co Ltd filed Critical YUSHUN ECOLOGICAL CONSTRUCTION Co Ltd
Priority to CN201410703396.6A priority Critical patent/CN104594297B/en
Publication of CN104594297A publication Critical patent/CN104594297A/en
Application granted granted Critical
Publication of CN104594297B publication Critical patent/CN104594297B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Abstract

The invention discloses a kind of double face slab rock-fill dams, it includes enrockment accumulation body, concrete slab, geomembrane and high polymer composite panel, upstream side at enrockment accumulation body covers high polymer composite panel, overburden soil work film on high polymer composite panel, covers concrete slab on geomembrane.The invention also discloses the construction method of these double face slab rock-fill dams.The present invention dam body accumulation body filled require relatively low, it is to avoid conventional panels rock-fill dams need higher filling degree of compaction and have the loaded filter of antiseepage effect during filling;Effectively reduce the heat of hydration of concrete, the advantages such as construction link is few;Strengthen the seepage capability of dam body, it is to avoid construct loaded filter and transition zone at panel rear;Geomembrane is laid, it is possible to effective prevention self-compacting concrete flows in accumulation body between double face slab;The construction method speed of application of the present invention is fast, and technique is simple, and suitable popularization and application possess good practicality.

Description

A kind of double face slab rock-fill dams and construction method thereof
Technical field
The invention belongs to hydraulic engineering technical field, particularly relate to a kind of double face slab rock-fill dams and construction method thereof.
Background technology
Rock occurs in the mining area of the California, USA Sierra Nevada fifties in 19th century the earliest, Rock-fill dams at that time use wooden boards antiseepage.Through the development in more than 150 years, modern rock is the most mixed Solidifying soil rock, because it has the advantages that cost is low, the duration is short, CFRD has obtained fluffy Vigorous development, the most successfully builds the high dam of 200m level.Rock is mainly made up of three parts: antiseepage face Plate, antiseepage ground structure and enrockment dam body;Face slab for water retaining is the main permeation-inhibiting members of rock-fill dams, and panel is by week Side seam is connected with antiseepage ground structure.
The method having several building earth and rockfill dam in prior art: 1) use self-compacting concrete material building coagulation The construction method of soil dam, the method is mainly used in building and has the dam structure of bigger concrete seepage-proofing body, Such as concrete core-wall rock-fill dams, concrete gravity dam etc.;2) use the panel made of composite panel material and Impervious body construction method, this earth and rockfill dam uses a kind of composite to replace concrete to make panel, its composite Panel working procedure is complicated, needs to design impervious body and assists antiseepage, long in time limit and seepage capability it is difficult to ensure that;3) The face slab for water retaining being made up of glass screed and frp layer and construction method thereof, this barrier sheet essence falls within one Planting composite material face, its execution conditions require higher, construction complexity.Meanwhile, set up greatly according to existing embankment Dam, or set up dam on the basis of existing earthquake accumulation body, in these special places, the main building material of dam Material is not to fill according to the design requirement of dam work, and it fills indices and can not grasp completely.
Summary of the invention
Goal of the invention: it is an object of the invention to provide a kind of double face slab rock-fill dams, strengthens dam body intensity and prevents Ooze, it is adaptable to existing embankment sets up dam and newly-built dam engineering on the basis of setting up dam, existing accumulation body;This The purpose of invention is to provide the construction method of these double face slab rock-fill dams.
Technical scheme: for achieving the above object, the present invention adopts the following technical scheme that
A kind of double face slab rock-fill dams, it includes that enrockment accumulation body, concrete slab, geomembrane and high polymer are multiple Closing panel, the upstream side at described enrockment accumulation body covers high polymer composite panel, at high polymer composite panel Upper overburden soil work film, covers concrete slab on geomembrane.
The described enrockment trapezoidal shape of accumulation body cross section.
Described concrete slab is poured by bar-mat reinforcement and self-compacting concrete and forms;The ratio of reinforcement of concrete slab It is 60~100kg/m3
Described high polymer composite panel is made up of the high polymer being filled in accumulation body and enrockment;High polymer is combined The thickness of panel is not less than 50cm.
The construction method of described double face slab rock-fill dams, comprises the following steps:
1) enrockment is piled up
Embankment or earthquake enrockment accumulation body are carried out heavy type roll, form trapezoidal dam body;
2) slip casting
It is axial that upstream side at trapezoidal dam body is perpendicular to dam, and be in tilted layout high polymer grouting pipe, at high polymer grouting Pipe outer side covers lays one layer of geomembrane;The template of concrete slab is built, inside template outside geomembrane Put into bar-mat reinforcement, bar-mat reinforcement inserts concrete grouting pipe cast self-compacting concrete, forms concrete slab; Injecting high polymer toward high polymer grouting pipe is internal, there is chemical reaction, body in high polymer inside high polymer grouting pipe Long-pending expansion, forms high polymer composite panel by the hole of the injected hole filling periphery enrockment of periphery together with enrockment, The thickness of high polymer composite panel is not less than 50cm, high polymer composite panel the enrockment being covered with is heap clitter Long-pending body;
3) form removal
The template of dismounting concrete slab.
Beneficial effect: compared with prior art, the double face slab rock-fill dams of the present invention can be on existing embankment or ground Build dam on the basis of shake accumulation body, dam body accumulation body filled require relatively low, it is to avoid conventional panels Rock-fill dams need higher filling degree of compaction and have the loaded filter of antiseepage effect during filling;Concrete surface Plate uses reinforcing bar and self-compacting concrete to pour and form, and can effectively reduce the heat of hydration of concrete, and construction link is few Etc. advantage;Use high polymer composite panel, strengthen the seepage capability of dam body, it is to avoid construct anti-filter at panel rear Layer and transition zone, construction is simple;Geomembrane is laid, it is possible to effective prevention self-compaction mixes between double face slab Solidifying soil flows in accumulation body, provides guarantee for forming the high polymer composite panel of even intensity;The present invention executes Work method speed of application is fast, and technique is simple, and suitable popularization and application possess good practicality.
Accompanying drawing explanation
Fig. 1 is the generalized section of double face slab rock-fill dams;
Fig. 2 is concrete slab floor map;
Fig. 3 is high polymer panel plane schematic diagram;
Fig. 4 is dam body local A enlarged diagram.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is described further.
As shown in figures 1-4, a kind of double face slab rock-fill dams include enrockment accumulation body 1, concrete slab 2, soil Work film 3 and high polymer composite panel 4, the upstream side at enrockment accumulation body 1 covers high polymer composite panel 4, Overburden soil work film 3 on high polymer composite panel 4, covers concrete slab 2 on geomembrane 3.
Wherein, the trapezoidal shape of cross section of enrockment accumulation body 1, concrete slab 2 is by bar-mat reinforcement 5 with from close Real concrete 6 pours and forms;The ratio of reinforcement of concrete slab is 60~100kg/m3.High polymer composite panel 4 High polymer 7 and enrockment by being filled in accumulation body form;The thickness of high polymer composite panel 4 is not less than 50cm.
The construction method of double face slab rock-fill dams, comprises the following steps:
1) enrockment is piled up
Embankment or earthquake enrockment accumulation body are carried out heavy type roll, form trapezoidal dam body;Simultaneously according to embankment and ground The intensive parameter of shake dam body materials carries out slope trimming;
2) slip casting
Upstream side at trapezoidal dam body is perpendicular to dam axially inclined layout high polymer grouting pipe 8, adjacent high polymer Spacing 5~10m between Grouting Pipe 8, lays one layer of geomembrane 3 in high polymer grouting pipe 8 outer side covers;? Build the template of concrete slab 2 outside geomembrane 3, inside template, put into bar-mat reinforcement 5, at bar-mat reinforcement 5 Middle insertion concrete grouting pipe cast self-compacting concrete 6, forms concrete slab 2;Toward high polymer grouting pipe 8 internal inject high polymers 7, and high polymer 7 occurs chemical reaction inside high polymer grouting pipe 8, volumetric expansion, High polymer composite panel 4 is formed together with enrockment by the hole of the injected hole 9 filling periphery enrockment of periphery, high The thickness of polymers composite panel 4 is not less than 50cm, high polymer composite panel 4 enrockment being covered with is enrockment Accumulation body 1;
3) form removal
The template of dismounting concrete slab 2.

Claims (2)

1. double face slab rock-fill dams, it is characterised in that: it includes enrockment accumulation body (1), concrete surface Plate (2), geomembrane (3) and high polymer composite panel (4), in the upstream of described enrockment accumulation body (1) Side covers high polymer composite panel (4), at upper overburden soil work film (3) of high polymer composite panel (4), at soil Concrete slab (2) is covered on work film (3);The construction method of described double face slab rock-fill dams, including with Lower step:
1) enrockment is piled up
Embankment or earthquake enrockment accumulation body are carried out heavy type roll, form trapezoidal dam body;
2) slip casting
It is axial that upstream side at trapezoidal dam body is perpendicular to dam, and be in tilted layout high polymer grouting pipe (8), at high polymer Grouting Pipe (8) outer side covers lays one layer of geomembrane (3);Concrete slab is built in geomembrane (3) outside (2) template, puts into bar-mat reinforcement (5) inside template, inserts concrete grouting pipe in bar-mat reinforcement (5) Cast self-compacting concrete (6), forms concrete slab (2);Inject toward high polymer grouting pipe (8) is internal High polymer (7), high polymer (7) is generation chemical reaction inside high polymer grouting pipe (8), volumetric expansion, High polymer composite panel (4) is formed together with enrockment by the hole of injected hole (9) the filling periphery enrockment of periphery, The thickness of high polymer composite panel (4) is not less than 50cm, high polymer composite panel (4) heap being covered with Stone is enrockment accumulation body (1);
3) form removal
The template of dismounting concrete slab (2).
Double face slab rock-fill dams the most according to claim 1, it is characterised in that: described concrete surface Plate (2) is poured formed by bar-mat reinforcement (5) and self-compacting concrete (6);The ratio of reinforcement of concrete slab is 60~100kg/m3
CN201410703396.6A 2014-11-26 2014-11-26 A kind of double face slab rock-fill dams and construction method thereof Active CN104594297B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410703396.6A CN104594297B (en) 2014-11-26 2014-11-26 A kind of double face slab rock-fill dams and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410703396.6A CN104594297B (en) 2014-11-26 2014-11-26 A kind of double face slab rock-fill dams and construction method thereof

Publications (2)

Publication Number Publication Date
CN104594297A CN104594297A (en) 2015-05-06
CN104594297B true CN104594297B (en) 2016-12-07

Family

ID=53120324

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410703396.6A Active CN104594297B (en) 2014-11-26 2014-11-26 A kind of double face slab rock-fill dams and construction method thereof

Country Status (1)

Country Link
CN (1) CN104594297B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105178259A (en) * 2015-08-24 2015-12-23 中国科学院力学研究所 Joint designing method of cushion course and transition layer of concrete faced rockfill dam
CN105625272B (en) * 2016-01-30 2017-08-11 清华大学 The 3D building systems and method of construction of earth and rockfill dam
CN107503322A (en) * 2017-07-19 2017-12-22 江西省水利科学研究院 A kind of preparation method for the earth and rockfill dam downstream patch slope concrete slab for filtering native draining
CN108797522A (en) * 2018-06-13 2018-11-13 靳恬静 A kind of dykes and dams blocking method
CN109629524A (en) * 2018-12-20 2019-04-16 重庆大学 A kind of FRP Combined concrete panel earth and rockfill dam and its construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073339A (en) * 1998-06-15 2000-03-07 Natl Res Inst Of Agricultural Engineering Inspection gallery in fill-type dam and construction method of inspection gallery in fill-type dam
CN100535254C (en) * 2005-12-21 2009-09-02 中国水利水电建设集团公司 Once forming construction technique for concrete panel rock fill dam bedding material and slope fixing mortar
CN101831889B (en) * 2010-05-05 2011-10-05 河海大学 Anti-seismic combination slab for earth and rockfill dam and construction method thereof
CN102561271B (en) * 2012-01-11 2015-04-08 河海大学 Polymer grout injected earth-rock dam and construction method thereof
CN103422473A (en) * 2013-07-10 2013-12-04 大连理工大学 Anti-seismic face plate structure for rock-fill dam with concrete face plate and method for constructing face plate anti-seismic structure

Also Published As

Publication number Publication date
CN104594297A (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN104153380B (en) A kind of antiseepage cofferdam structure and construction technology
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN104594297B (en) A kind of double face slab rock-fill dams and construction method thereof
CN110847197B (en) Comprehensive treatment method for loess tunnel entrance section crossing landslide body
CN105155541B (en) A kind of dual slurry closure construction method of catch pit
CN105297685B (en) A kind of pedestal CFRD and its construction method
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN203393530U (en) Anti-floating lightweight high-fill embankment structure
CN111119128B (en) Danger-removing, reinforcing and seepage-proofing method for natural rock-fill dam of barrier lake
CN105019425B (en) A kind of construction method of displacement hull and cured layer combined foundation structure
CN105064157A (en) Treatment method of settlement of high-speed railway roadbeds in soft-soil areas
CN106049379B (en) Interim electricity-generating method and enrockment self bursting dam during the construction hysteresis of spillway downstream
CN111851505A (en) Construction method and structure of pouring type impervious core earth-rock dam
CN105386458B (en) A kind of embedded plasticity cement mixing method groove inside of continuous underground wall construction method
CN110778328A (en) Loess tunnel entrance section construction method for passing through landslide body
CN104652371A (en) Overflow cemented rock-fill dam established based on old dam and construction method thereof
CN107119695A (en) A kind of operation support body and construction method for cancelling outer wall of basement backfill
CN106498959A (en) Gutter for deep overburden
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN205530580U (en) System for collection is prevented osmosis membrane anchor, is cut flood and current as an organic whole
CN107881987A (en) Deep covering layer top panel Rockfill Dam based moisture barrier structure
CN203007961U (en) Gabion cofferdam structure
CN102787608A (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN206189430U (en) A escape canal for deep overburden ground
CN206298869U (en) A kind of concrete guard wall structure of free drainage

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 315099, Zhejiang Province, Haishu District, Zhongshan Ningbo West Road, No. 2 hang Long Center (15-9) (Yu Shun Ecological Construction Co., Ltd.)

Co-patentee after: Hehai Science & Technology Co., Ltd.

Patentee after: YUSHUN ECOLOGICAL CONSTRUCTION CO., LTD.

Address before: 7, building 487, building 17, Ning Xing Fortune Plaza, No. 315000, Cheng Cheng North Road, Zhejiang, Ningbo

Co-patentee before: Hehai Science & Technology Co., Ltd.

Patentee before: YUSHUN ECOLOGICAL CONSTRUCTION CO., LTD.

CP02 Change in the address of a patent holder