RU2299174C1 - Upper part of tower crane foldable in traveling position - Google Patents

Upper part of tower crane foldable in traveling position Download PDF

Info

Publication number
RU2299174C1
RU2299174C1 RU2005131220/11A RU2005131220A RU2299174C1 RU 2299174 C1 RU2299174 C1 RU 2299174C1 RU 2005131220/11 A RU2005131220/11 A RU 2005131220/11A RU 2005131220 A RU2005131220 A RU 2005131220A RU 2299174 C1 RU2299174 C1 RU 2299174C1
Authority
RU
Russia
Prior art keywords
frame
strut
crane
tower
hinge
Prior art date
Application number
RU2005131220/11A
Other languages
Russian (ru)
Other versions
RU2005131220A (en
Inventor
Борис Клеоникович Марысаев (RU)
Борис Клеоникович Марысаев
Original Assignee
Закрытое акционерное общество "Машстройиндустрия"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Закрытое акционерное общество "Машстройиндустрия" filed Critical Закрытое акционерное общество "Машстройиндустрия"
Priority to RU2005131220/11A priority Critical patent/RU2299174C1/en
Publication of RU2005131220A publication Critical patent/RU2005131220A/en
Application granted granted Critical
Publication of RU2299174C1 publication Critical patent/RU2299174C1/en

Links

Images

Abstract

FIELD: mechanical engineering; tower cranes.
SUBSTANCE: proposed foldable part of tower crane has frame with eyes on its lower side for connection with tower and eyes in front part of frame for connection with crane boom, and strut, post and spring stop hinge coupled with frame. Frame is made with beam elongated towards strut and with hinged support secured on end of beam. Post and strut rest on beam and support in mounting and traveling positions of crane upper part. Spring stop is arranged on frame in horizontal position, strut is arranged on end of beam, and members of brace are arranged between strut and post. One member of brace rests by one end on front part of strut. In traveling position, upper end of post is located higher than hinge joint fastening it to frame. Free end of strut is located lower than hinge joint fastening it to frame. Hinge connecting members of brace is located between free end of strut and hinge joint connecting strut and frame.
EFFECT: reduced labor input in mounting of crane, increased safety in mounting.
2 cl, 3 dwg

Description

Изобретение относится к грузоподъемной технике, в частности к башенным кранам, верхние части которых скомпонованы в единый узел с целью удобства транспортировки крана и его монтажа на монтажных площадках строительных объектов.The invention relates to lifting equipment, in particular to tower cranes, the upper parts of which are arranged in a single unit for the purpose of ease of transportation of the crane and its installation on the installation sites of construction sites.

Известен башенный кран, конструкция которого предусматривает ее складывание в транспортное положение [1].Known tower crane, the design of which provides for its folding in transport position [1].

Наиболее близким техническим решением к данному изобретению является верхняя складываемая в транспортное положение часть башенного крана, содержащая раму с проушинами на нижней стороне для ее соединения с башней и с проушинами в передней части рамы для ее соединения со стрелой крана, шарнирно связанные с рамой распорку, стойку и пружинный упор [2].The closest technical solution to this invention is the upper part of the tower crane that can be folded into the transport position, containing a frame with eyes on the lower side for connecting it to the tower and with eyes in the front of the frame for connecting it to the crane boom, a spacer, a rack articulated to the frame and spring stop [2].

Решаемой и достигаемой задачей данного изобретения является снижение трудоемкости монтажа крана и повышение безопасности монтажа.Solved and achievable objective of the present invention is to reduce the complexity of installation of the crane and increase the security of installation.

Для этого в верхней складываемой в транспортное положение части башенного крана, содержащей раму с проушинами на нижней стороне для ее соединения с башней и с проушинами в передней части рамы для ее соединения со стрелой крана, шарнирно связанные с рамой распорку, стойку и пружинный упор, рама выполнена с удлиненной от нее в сторону распорки балкой и с шарнирно закрепленной на конце балки откидной опорой, на которой в монтажном и транспортном положениях верхней части крана оперта стойка и распорка, пружинные упоры расположены на раме в горизонтальном положении, распорка расположена на конце балки, звенья расчала расположены между распоркой и стойкой и одно из звеньев одним своим концом оперто на переднюю часть распорки, верхний конец стойки расположен выше шарнира ее крепления к раме, свободный конец распорки расположен ниже шарнира ее крепления к раме, шарнирное соединение, соединяющее звенья расчала, расположено между свободным концом распорки и шарниром соединения распорки с рамой с рамой.To do this, in the upper part of the tower crane that can be folded into the transport position, which contains a frame with eyes on the underside for connecting it to the tower and with eyes in the front of the frame for connecting it to the crane arm, a spacer, a strut and a spring stop, frame pivotally connected to the frame made with a beam extended from it towards the spreader and with a hinged support pivotally mounted on the end of the beam, on which the rack and the strut are supported in the mounting and transport positions of the upper part of the crane, the spring stops are located on the frame in the mountains in the upright position, the spacer is located at the end of the beam, the calculation links are located between the spacer and the strut and one of its links is supported at the front of the spacer, the upper end of the strut is located above the hinge of its attachment to the frame, the free end of the strut is located below the hinge of its attachment to the frame , the swivel connecting the calculated links is located between the free end of the strut and the hinge of connecting the strut to the frame with the frame.

Балка расположена на нижней стороне рамы между ее проушинами для соединения с башней.The beam is located on the underside of the frame between its eyes for connection with the tower.

На фиг.1 показана верхняя часть крана, сложенная в транспортное и монтажное положения.Figure 1 shows the upper part of the crane, folded into the transport and installation position.

На фиг.2 - схема расположения шарнира крепления пружинного упора на раме верхней части крана.Figure 2 - arrangement of the hinge mounting the spring stop on the frame of the upper part of the crane.

На фиг.3 - верхняя часть крана, приведенная в рабочее положение.Figure 3 - the upper part of the crane, brought into working position.

Верхняя складываемая в транспортное положение часть башенного крана содержит раму 1 башни, шарнирно связанные с рамой распорку 2, стойку 3 и пружинный упор 4. Рама выполнена с удлиненной от нее опорной балкой 5 с шарнирно закрепленной на ее конце поворотной в вертикальной плоскости опорой 6. В рабочем, транспортном и монтажном положениях верхней части крана опора 6 находится в вертикальном положении и на нее оперта стойка 3. Пружинный упор 4 расположен в транспортном положении верхней части крана на раме 1 в горизонтальном положении, распорка 2 в упомянутом положении верхней части крана опирается на конец балки 5. Верхняя часть крана имеет также звенья 7 и 8 расчала башни, которые расположены между распоркой 2 и стойкой 3. Стойка 3 расположена в наклоненном по часовой стрелке сторону от опорной балки 5 положении, распорка 2 расположена в наклоненном против часовой стрелки сторону к опорной балке 5 положении. Конец 9 звена 8 и связанный с ним конец 10 звена 7 расчала оперты на среднюю часть распорки 2. Конец 11 стойки 3 расположен выше шарнира 12 ее соединения с рамой 1. Свободный конец 13 распорки 2 расположен ниже шарнира 14 его соединения с рамой 1. Шарнирное соединение 15, соединяющее звенья 7 и 8 расчала, расположено между свободным концом 13 распорки 2 и шарниром 14 соединения распорки с рамой 1. Шарнир 16 (фиг.2) соединения пружинного упора 4 с рамой 1 расположен между шарнирами 12 соединения стойки 3 с рамой 1.The upper part of the tower crane that can be folded into the transport position comprises a tower frame 1, a spacer 2 pivotally connected to the frame, a strut 3 and a spring stop 4. The frame is made with a support beam 5 extended from it with a support 6. pivotally mounted on its end in a vertical plane 6. In working, transport and mounting positions of the upper part of the crane support 6 is in a vertical position and the column 3 is supported on it. The spring stop 4 is located in the transport position of the upper part of the crane on the frame 1 in a horizontal position, the spacer 2 in the aforementioned position, the upper part of the crane rests on the end of the beam 5. The upper part of the crane also has links 7 and 8 designed by the tower, which are located between the spacer 2 and the post 3. The post 3 is located in the clockwise inclined direction from the support beam 5, the spacer 2 is located in a counterclockwise direction tilted to the support beam 5 position. The end 9 of link 8 and the associated end 10 of link 7 are designed to support the middle part of the strut 2. The end 11 of the strut 3 is located above the hinge 12 of its connection to the frame 1. The free end 13 of the strut 2 is located below the hinge 14 of its connection to the frame 1. Hinged the connection 15 connecting the links 7 and 8 calculated, is located between the free end 13 of the strut 2 and the hinge 14 connecting the strut with the frame 1. The hinge 16 (figure 2) of the connection of the spring stop 4 with the frame 1 is located between the hinges 12 of the connection of the rack 3 with the frame 1 .

Все вышеуказанные элементы верхней части крана и связи между ними простираются в заднюю сторону рамы 1 от проушины 17 рамы, предназначенной для крепления к раме стрелы крана. Условно, сторона 18 рамы, на которой расположены проушины 17 для крепления к раме стрелы, является передней стороной, а сторона 19 рамы 1 является задней стороной.All of the above elements of the upper part of the crane and the connections between them extend to the rear side of the frame 1 from the eye 17 of the frame, designed to be attached to the frame of the crane jib. Conventionally, the side 18 of the frame on which the eyes 17 for fastening to the boom frame are located is the front side, and the side 19 of the frame 1 is the back side.

На раме 1 расположены в нерабочем положении тяги 20 стойки 3. Посредством тяги 20 и ее концевой части 21 стойка 3 фиксируется на раме 1 в рабочем положении во время монтажа крана. В нерабочем положении тяги 20 и их концевые части 21 разомкнуты, при этом концевые части 21 постоянно связаны с рамой 1 шарнирами 22. Каждая концевая часть 21 тяги имеет средство 22 регулировки ее длины. Каждая тяга 20 и ее концевые части 21 имеют соединяемые в рабочем положении верхней части крана соответствующие проушины 23 и 24. Другой конец тяги 20 связан шарниром 25 с проушиной 26 стойки 3. На стойке 3 расположен также канат 27 стрелового расчала.On the frame 1 are located in the inoperative position of the rod 20 of the rack 3. By means of the rod 20 and its end portion 21, the rack 3 is fixed on the frame 1 in the working position during installation of the crane. In the idle position of the rod 20 and their end parts 21 are open, while the end parts 21 are constantly connected to the frame 1 by hinges 22. Each end part 21 of the rod has means 22 for adjusting its length. Each rod 20 and its end parts 21 have respective eyes 23 and 24 connected in the working position of the upper part of the crane. The other end of the rod 20 is connected by a hinge 25 to the eye 26 of the rack 3. A boom rope 27 is also located on the rack 3.

Конец звена 7 расчала башни шарниром 28 соединен с концом 11 стойки 3. Конец звена 8 расчала шарниром 30 соединен с концом 13 распорки 2. Рама 1 имеет проушины 31 для ее соединения с проушинами 32 башни 33 крана. Проушины 31 расположены на боковых сторонах рамы 1 за опорной балкой 5 в переднюю сторону рамы. Опорная балка 5 расположена между проушинами 31 и простирается от нижней стороны рамы 1 так, что ее нижняя поверхность 34 находится на уровне горизонтальной оси, на которой расположены центры проушин 31. Откидная опора 6 шарниром 35 соединена с концом опорной балки 5. Стойка 3 имеет проушины 36 для крепления к ним строп 37.The end of the link 7 calculated the tower by a hinge 28 connected to the end 11 of the rack 3. The end of the link 8 calculated by the hinge 30 connected to the end 13 of the spacer 2. The frame 1 has eyes 31 for connecting it with the eyes 32 of the tower 33 of the crane. The eyes 31 are located on the sides of the frame 1 behind the support beam 5 in the front side of the frame. The support beam 5 is located between the eyes 31 and extends from the lower side of the frame 1 so that its lower surface 34 is at the level of the horizontal axis on which the centers of the eyes 31 are located. The hinged support 6 is pivotally connected to the end of the support beam 5. The post 3 has eyes 36 for attaching slings to them 37.

Работает верхняя часть башенного крана следующим образом. The top of the tower crane works as follows.

Посредством строп 37 верхнюю часть крана поднимают с монтажной площадки монтажным краном, вывешивают над башней 33, затем опускают до совмещения отверстий проушин 31 рамы 1 с отверстиями проушин 32 башни 33 крана, после чего раму 1 соединяют с башней 33 путем введения пальцев в отверстия проушин 31 и 32. После соединения верхней части крана с башней стропами 37 поднимают стойку 3 в ее верхнее рабочее положение. Вместе со стойкой поворачиваются вокруг своих шарниров крепления распорки 2 и звенья 7 и 8 расчала башни. При подъеме стойки 3 она поворачивается вокруг шарниров 12 относительно неподвижной рамы 1 до момента ее установки в наклоненном назад положении (фиг.3). В этом положении стойка 3 фиксируется на раме 1 тягами 20, для чего проушину 23 каждой тяги соединяют с проушиной 24 концевой части 21 тяги. При необходимости длину концевой части 21 каждой тяги 20 регулируют средством 22 изменения длины концевой части 21 и регулируют таким образом угол наклона стойки 3.By means of the slings 37, the upper part of the crane is lifted from the installation site by an installation crane, hung over the tower 33, then lowered to align the holes of the eyes 31 of the frame 1 with the holes of the eyes 32 of the tower 33 of the crane, after which the frame 1 is connected to the tower 33 by inserting fingers into the holes of the eyes 31 and 32. After connecting the upper part of the crane to the tower, slings 37 raise the rack 3 to its upper working position. Together with the rack, they rotate around their hinges for attaching struts 2 and links 7 and 8 of the towers When lifting the rack 3, it rotates around the hinges 12 relative to the fixed frame 1 until it is installed in a tilted back position (figure 3). In this position, the rack 3 is fixed on the frame 1 by rods 20, for which the eye 23 of each rod is connected to the eye 24 of the end portion 21 of the rod. If necessary, the length of the end portion 21 of each rod 20 is controlled by means 22 for changing the length of the end portion 21, and thus the angle of inclination of the strut 3 is adjusted.

При установке стойки 3 в рабочее положение распорка 2, звенья 7 и 8 расчала башни, поворачиваясь вокруг шарниров крепления, самоустанавливаются в рабочем положении так, как это показано на фиг.3.When installing the rack 3 in the operating position, the spacer 2, the links 7 and 8 calculated towers, turning around the hinges of fastening, self-mounted in the working position, as shown in Fig.3.

Источники информацииInformation sources

1. SU 146006, 1952.1. SU 146006, 1952.

2. Pointing the way: The HC-L cranes. Проспект фирмы Liebherr, Printed in Germany by Eberl LBC-487-12.97-10e (прототип, копия прилагается).2. Pointing the way: The HC-L cranes. Prospectus of the company Liebherr, Printed in Germany by Eberl LBC-487-12.97-10e (prototype, copy attached).

Claims (2)

1. Верхняя складываемая в транспортное положение часть башенного крана, содержащая раму с проушинами на нижней стороне для ее соединения с башней и с проушинами в передней части рамы для ее соединения со стрелой крана, шарнирно связанные с рамой распорку, стойку и пружинный упор, отличающаяся тем, что рама выполнена с удлиненной от нее в сторону распорки балкой и с шарнирно закрепленной на конце балки откидной опорой, на которую в монтажном и транспортном положениях верхней части крана опираются стойка и распорка, в транспортном положении пружинный упор расположен на раме в горизонтальном положении, распорка расположена на конце балки, звенья расчала расположены между распоркой и стойкой, и одно из звеньев одним своим концом опирается на переднюю часть распорки, верхний конец стойки расположен выше шарнира ее крепления к раме, свободный конец распорки расположен ниже шарнира ее крепления к раме, шарнирное соединение, соединяющее звенья расчала, расположено между свободным концом распорки и шарниром соединения распорки с рамой.1. The upper part of the tower crane that can be folded into the transport position, comprising a frame with eyelets on the lower side for connecting it to the tower and with eyes in the front of the frame for connecting it to the crane arm, a spacer, a stand and a spring stop pivotally connected to the frame, characterized in that the frame is made with a beam elongated from it towards the spreader and with a hinged support pivotally attached to the end of the beam, on which the rack and the strut rest in the mounting and transport positions of the upper part of the crane, in the transport position the spring support is located on the frame in a horizontal position, the strut is located at the end of the beam, the links are located between the strut and the rack, and one of its links rests on one front of the strut, the upper end of the rack is located above the hinge of its fastening to the frame, the free end of the strut located below the hinge of its attachment to the frame, the hinge connecting the races calculated, located between the free end of the strut and the hinge connecting the strut with the frame. 2. Верхняя складываемая в транспортное положение часть башенного крана по п.1, отличающаяся тем, что балка расположена на нижней стороне рамы между ее проушинами для соединения с башней.2. The upper part of the tower crane that can be folded into the transport position according to claim 1, characterized in that the beam is located on the lower side of the frame between its eyes for connection with the tower.
RU2005131220/11A 2005-10-10 2005-10-10 Upper part of tower crane foldable in traveling position RU2299174C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2005131220/11A RU2299174C1 (en) 2005-10-10 2005-10-10 Upper part of tower crane foldable in traveling position

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2005131220/11A RU2299174C1 (en) 2005-10-10 2005-10-10 Upper part of tower crane foldable in traveling position

Publications (2)

Publication Number Publication Date
RU2005131220A RU2005131220A (en) 2007-04-20
RU2299174C1 true RU2299174C1 (en) 2007-05-20

Family

ID=38036529

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2005131220/11A RU2299174C1 (en) 2005-10-10 2005-10-10 Upper part of tower crane foldable in traveling position

Country Status (1)

Country Link
RU (1) RU2299174C1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2532204C2 (en) * 2009-05-20 2014-10-27 МАНИТОВОК КРЕЙН КАМПЕНИЗ, ЭлЭлСи Lifting crane guys expander and method of its adjustment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2532204C2 (en) * 2009-05-20 2014-10-27 МАНИТОВОК КРЕЙН КАМПЕНИЗ, ЭлЭлСи Lifting crane guys expander and method of its adjustment

Also Published As

Publication number Publication date
RU2005131220A (en) 2007-04-20

Similar Documents

Publication Publication Date Title
RU2258664C2 (en) Tower crane slewing part and method of its mounting
CN105460807B (en) The full Terrain Cranes
DK2707322T3 (en) Tower Turntable
JP2010260725A (en) Telescopic crane having self-installation support device and installation method of support device
EP1225152B1 (en) Tower crane, self-assembling, with folding and telescoping tower, and foldable jib
WO2005092775A1 (en) Mobile crane sytsem comprising a mobile crane and an auxiliary device for assembly of a bracing device
CN107108186A (en) Method for shifting rotary tower crane
RU2299174C1 (en) Upper part of tower crane foldable in traveling position
RU2065397C1 (en) Tower crane
BR112021004510A2 (en) crane
JP7394077B2 (en) Large crane with boom
CN204877802U (en) Angle can be adjusted support and small wind turbine machine
RU98112609A (en) FOLDING MAST OF THREE ELEMENTS WITH FOLDING AND UNFOLDING DEVICE FOR TOWER CRANE
CN102407802B (en) Lighting vehicle
CA3120433A1 (en) Luffing crane featuring tipping over balance
JP4777821B2 (en) Tower crane
CN110088034A (en) Crane including foldable crane arm
RU2191156C2 (en) Mast-lifting device for tower crane with telescopic mast
CN215558561U (en) Tower crane A-shaped frame
RU2299173C1 (en) Method of mounting tower crane with upper part foldable in traveling position
RU2744873C1 (en) Construction of double-level subframe of raisable work platform
CN105174089A (en) Auxiliary arm system and arm rack system
RU2263623C2 (en) Method of and device for mounting tower crane sectional boom
CN110921532A (en) Lifting structure and crane
RU2225345C2 (en) Tower crane and method of its mounting

Legal Events

Date Code Title Description
PC4A Invention patent assignment

Effective date: 20100531

PC41 Official registration of the transfer of exclusive right

Effective date: 20110914

MM4A The patent is invalid due to non-payment of fees

Effective date: 20121011

NF4A Reinstatement of patent

Effective date: 20131120

PC41 Official registration of the transfer of exclusive right

Effective date: 20131121

MM4A The patent is invalid due to non-payment of fees

Effective date: 20141011

NF4A Reinstatement of patent

Effective date: 20170815

MM4A The patent is invalid due to non-payment of fees

Effective date: 20181011

NF4A Reinstatement of patent

Effective date: 20220113