RU2248446C1 - Method for determining sheeting parameters for rock solids in massif and device for realization of said method - Google Patents

Method for determining sheeting parameters for rock solids in massif and device for realization of said method Download PDF

Info

Publication number
RU2248446C1
RU2248446C1 RU2004100455/03A RU2004100455A RU2248446C1 RU 2248446 C1 RU2248446 C1 RU 2248446C1 RU 2004100455/03 A RU2004100455/03 A RU 2004100455/03A RU 2004100455 A RU2004100455 A RU 2004100455A RU 2248446 C1 RU2248446 C1 RU 2248446C1
Authority
RU
Russia
Prior art keywords
rod
wells
electrodes
brittle
parameters
Prior art date
Application number
RU2004100455/03A
Other languages
Russian (ru)
Inventor
Н.Г. Кю (RU)
Н.Г. Кю
Original Assignee
Институт горного дела Сибирского отделения Российской Академии наук (статус государственного учреждения)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт горного дела Сибирского отделения Российской Академии наук (статус государственного учреждения) filed Critical Институт горного дела Сибирского отделения Российской Академии наук (статус государственного учреждения)
Priority to RU2004100455/03A priority Critical patent/RU2248446C1/en
Application granted granted Critical
Publication of RU2248446C1 publication Critical patent/RU2248446C1/en

Links

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

FIELD: mining industry.
SUBSTANCE: method includes drilling wells and mounting electrodes with conductors therein, which are connected to recording equipment. Signal lines are formed by filling wells with hardening mass, which after hardening forms fragile electric-conductive rods, rigidly engaged with well walls. Change of electric resistance between electrodes is measured in time, moments of tears of signal lines are recorded and parameters of rock solids sheeting are determined. Fragile electric-conductive rods can be formed in such a way, that their specific resistance depended on pressure. As hardening mass a mixture of graphic powder, cement and water can be used. Between fragile electric-conductive rods and wells walls a layer of fragile dielectric material can be previously formed. Device for method realization includes signal line in form of fragile and electric-conductive rod. Inside the rod a wire is placed, on which electrodes are mounted being in contact with rod and connected by conductors to recording equipment. Specific electric resistance of rod can depend on pressure. On surface of rod a layer of fragile dielectric material can be applied.
EFFECT: higher efficiency.
2 cl, 1 dwg

Description

Техническое решение относится к горному делу и предназначено для контроля возникновения и распространения трещин и расслоений в массиве горных пород.The technical solution relates to mining and is intended to control the occurrence and propagation of cracks and delaminations in the rock mass.

Известен способ определения расслоений в кровле горных выработок по авт. свид. СССР №1008445, кл. Е 21 С 39/00, опубл. в БИ №12, 1983 г. В этом способе в кровле осуществляют бурение шпура. Затем закрепляют в нем с помощью цементного раствора эталонный цилиндрический стержень, выполненный из хрупкого материала. В стержень излучают ультразвуковые импульсные колебания. О наличии расслоений в кровле судят по колебаниям, излученным в цилиндрический стержень и отраженным от трещины, образовавшейся в нем.There is a method of determining stratifications in the roof of mine workings according to ed. testimonial. USSR No. 1008445, class E 21 C 39/00, publ. in BI No. 12, 1983. In this method, drilling a hole is carried out in the roof. Then, a reference cylindrical rod made of brittle material is fixed in it using cement mortar. Ultrasonic pulsed oscillations are emitted into the rod. The presence of delamination in the roof is judged by the vibrations radiated into the cylindrical rod and reflected from the crack formed in it.

Этот способ не позволяет определять количество расслоений и расстояния между ними. Кроме того, для его реализации требуется специальная акустическая аппаратура.This method does not allow to determine the number of bundles and the distance between them. In addition, its implementation requires special acoustic equipment.

Наиболее близким по технической сущности и совокупности существенных признаков является способ определения параметров расслоений горных пород в массиве по авт. свид. СССР №1196505, кл. Е 21 С 39/00, опубл. в БИ №45, 1985 г., основанный на регистрации возникающих трещин посредством фиксации разрывов сигнальных линий, закрепленных в скважине. В нем сигнальные линии устанавливают по квадратной сетке, фиксируют моменты разрывов сигнальных линий и определяют скорость движения фронта расслоения по установленной зависимости.The closest in technical essence and the set of essential features is a method for determining the parameters of rock stratifications in the massif according to ed. testimonial. USSR No. 1196505, cl. E 21 C 39/00, publ. in BI No. 45, 1985, based on the registration of emerging cracks by fixing breaks in signal lines fixed in the well. In it, the signal lines are set on a square grid, the moments of breaks in the signal lines are recorded, and the velocity of the separation front is determined according to the established dependence.

Способ позволяет осуществлять контроль параметров расслоения только в одной плоскости, проходящей через скважины в пределах заданного участка.The method allows you to control the parameters of stratification only in one plane passing through the wells within a given area.

Известно устройство для определения расслоений в кровле горных выработок по авт. свид. СССР №1008445, кл. Е 21 С 39/00, опубл. в БИ №12, 1983 г. Оно включает аппаратуру для излучения и регистрации ультразвуковых импульсных колебаний и эталонный цилиндрический стержень, выполненный из хрупкого материала.A device for determining stratifications in the roof of mine workings according to ed. testimonial. USSR No. 1008445, class E 21 C 39/00, publ. in BI No. 12, 1983. It includes equipment for the emission and registration of ultrasonic pulsed oscillations and a reference cylindrical rod made of brittle material.

Это устройство является сложным из-за наличия в нем аппаратуры для излучения и регистрации ультразвуковых импульсных колебаний. Оно не позволяет следить за процессом образования трещин, возникающих в нескольких плоскостях.This device is complex due to the presence in it of equipment for radiation and registration of ultrasonic pulsed oscillations. It does not allow you to follow the process of formation of cracks that occur in several planes.

Наиболее близким по технической сущности и совокупности существенных признаков является устройство для определения параметров расслоений горных пород в массиве по авт. свид. СССР №1196505, кл. Е 21 С 39/00, опубл. в БИ №45, 1985 г. Оно содержит сигнальную линию, выполненную с регистрирующей аппаратурой. Стержень выполнен полым из диэлектрического материала и заполнен электропроводящей жидкостью под давлением. На торцах стержня установлены заглушки с электродами.The closest in technical essence and the set of essential features is a device for determining the parameters of rock stratifications in the massif according to ed. testimonial. USSR No. 1196505, cl. E 21 C 39/00, publ. in BI No. 45, 1985. It contains a signal line made with recording equipment. The rod is made hollow of a dielectric material and is filled with an electrically conductive liquid under pressure. At the ends of the rod are plugs with electrodes.

Устройство трудоемко в изготовлении. Оно не позволяет фиксировать моменты образования трещин в нескольких плоскостях.The device is laborious to manufacture. It does not allow fixing the moments of cracking in several planes.

Решаемая техническая задача заключается в повышении информативности способа за счет возможности слежения за процессом расслоений массива горных пород в нескольких плоскостях одновременно и эффективности устройства за счет упрощения конструкции и возможности фиксации трещин, возникающих на различных уровнях.The technical problem to be solved is to increase the information content of the method due to the possibility of tracking the process of stratification of the rock mass in several planes at the same time and the efficiency of the device due to the simplification of the design and the possibility of fixing cracks that occur at different levels.

Задача решается тем, что в способе определения параметров расслоений горных пород в массиве, включающем бурение скважин, установку в них сигнальных линий, фиксацию моментов разрывов сигнальных линий и определение параметров расслоений, согласно предлагаемому техническому решению в скважинах на различных уровнях устанавливают электроды с проводниками для подключения к регистрирующей аппаратуре, а сигнальные линии формируют заполнением скважин твердеющей массой, которая после отвердения образует хрупкие электропроводящие стержни, жестко сцепленные со стенками скважин, определяют изменение во времени электрического сопротивления между электродами и по нему судят о параметрах расслоений горных пород в массиве.The problem is solved in that in the method for determining the parameters of rock stratifications in the array, including drilling wells, installing signal lines in them, fixing the moments of breaks in the signal lines and determining the parameters of the bundles, according to the proposed technical solution, electrodes with conductors for connecting to the recording equipment, and the signal lines are formed by filling the wells with a hardening mass, which after hardening forms brittle electrically conductive rods, w JCOMM coupled with the walls of wells, determining the change in electrical resistance between the electrodes and the time thereon judged parameters bundles of rocks in the array.

Формирование сигнальных линий заполнением скважин твердеющей массой, которая после отвердения образует хрупкие электропроводящие стержни, жестко сцепленные со стенками скважин, позволяет судить о параметрах расслоения массива горных пород по изменению электрического сопротивления этих стержней в результате образования в них трещин. Установка в скважинах на различных уровнях электродов с проводниками для подключения к регистрирующей аппаратуре позволяет определять изменение электрического сопротивления хрупких электропроводящих стержней между электродами. Определение изменения электрического сопротивления между электродами во времени обеспечивает получение информации о характере образования трещин по всему объему хрупкого электропроводящего стержня. Совокупность отмеченных признаков обеспечивает возможность слежения за процессом расслоений массива горных пород в нескольких плоскостях одновременно. Это существенно повышает информативность способа.The formation of signal lines by filling the wells with a hardening mass, which, after hardening, forms brittle electrically conductive rods rigidly adhered to the walls of the wells, allows us to judge the parameters of the stratification of the rock mass by the change in the electrical resistance of these rods as a result of the formation of cracks in them. Installation in the wells at different levels of electrodes with conductors for connection to the recording equipment allows you to determine the change in the electrical resistance of brittle electrically conductive rods between the electrodes. Determination of the change in electrical resistance between the electrodes over time provides information on the nature of the formation of cracks throughout the volume of a brittle electrically conductive rod. The set of marked features provides the ability to monitor the process of stratification of the rock mass in several planes simultaneously. This significantly increases the information content of the method.

Целесообразно скважины заполнять твердеющей массой, которая после отвердения образует хрупкие электропроводящие стержни, удельное электрическое сопротивление которых зависит от давления. Это позволяет не только следить за процессом расслоения, но и за характером деформации стенок скважины, что значительно повышает информативность способа, ибо в этом случае появляется возможность оценивать изменение напряжений в массиве.It is advisable to fill the well with a hardening mass, which after hardening forms brittle conductive rods, the electrical resistivity of which depends on pressure. This allows not only to monitor the process of separation, but also the nature of the deformation of the walls of the well, which significantly increases the information content of the method, because in this case it becomes possible to evaluate the change in stress in the array.

Целесообразно при этом в качестве твердеющей массы использовать смесь графитового порошка, цемента и воды. Такая смесь изменением соотношения составляющих ее компонентов позволяет образовывать хрупкие электропроводящие стержни различной прочности и обладающие удельным электрическим сопротивлением, которое зависит от давления и наличия в них трещин.It is advisable to use a mixture of graphite powder, cement and water as a hardening mass. Such a mixture by changing the ratio of its constituent components allows the formation of brittle electrically conductive rods of various strengths and having a specific electrical resistance, which depends on the pressure and the presence of cracks in them.

Целесообразно между хрупкими электропроводящими стержнями и стенками скважин предварительно образовывать прослойку из хрупкого диэлектрического материала. Это обеспечивает возможность слежения за процессом расслоения в горных породах с любой электрической проводимостью.It is advisable between the brittle electrically conductive rods and the walls of the wells to pre-form a layer of brittle dielectric material. This provides the ability to monitor the stratification process in rocks with any electrical conductivity.

Задача решается также тем, что в устройстве для определения параметров расслоений горных пород в массиве, включающем сигнальную линию в виде стержня и электроды, подключенные к регистрирующей аппаратуре, согласно предлагаемому техническому решению стержень выполнен хрупким и электропроводящим, внутри стержня проложен провод, на котором установлены электроды, контактирующие со стержнем и подключенные проводниками к регистрирующей аппаратуре.The problem is also solved by the fact that in the device for determining the parameters of rock stratifications in the array, including a signal line in the form of a rod and electrodes connected to the recording equipment, according to the proposed technical solution, the rod is made brittle and electrically conductive, a wire is laid inside the rod on which electrodes are installed in contact with the rod and connected by conductors to the recording equipment.

Выполнение стержня хрупким и электропроводящим позволяет по изменению его электрического сопротивления фиксировать моменты возникновения в нем трещин. Прокладка внутри стержня провода, на котором установлены электроды, контактирующие с ним и подключенные проводниками к регистрирующей аппаратуре, дает возможность по характеру образования трещин в этом стержне следить за процессом расслоения массива горных пород в нескольких плоскостях одновременно. Кроме этого, устройство имеет более простую конструкцию по сравнению с прототипом и поэтому является более надежным в работе. Все это повышает эффективность устройства.The implementation of the rod brittle and electrically conductive allows you to record the moments of occurrence of cracks in it by changing its electrical resistance. Laying inside the wire rod, on which electrodes are installed, which are in contact with it and connected by conductors to the recording equipment, makes it possible, by the nature of the formation of cracks in this rod, to monitor the stratification of the rock mass in several planes simultaneously. In addition, the device has a simpler design compared to the prototype and therefore is more reliable in operation. All this increases the efficiency of the device.

Целесообразно хрупкий электропроводящий стержень выполнять таким, чтобы его удельное электрическое сопротивление зависело от давления. Это позволяет оценивать изменение напряжений в массиве горных пород.It is advisable to carry a brittle conductive rod so that its electrical resistivity depends on pressure. This allows you to evaluate the change in stress in the rock mass.

Целесообразно на поверхность хрупкого электропроводящего стержня нанести слой хрупкого диэлектрического материала. Это обеспечивает возможность слежения за процессом расслоения в горных породах с любой электрической проводимостью.It is advisable to apply a layer of brittle dielectric material on the surface of a brittle electrically conductive rod. This provides the ability to monitor the stratification process in rocks with any electrical conductivity.

Сущность технического решения поясняется примером конкретного исполнения и чертежом.The essence of the technical solution is illustrated by an example of a specific design and drawing.

На чертеже показана схема реализации способа определения параметров расслоений горных пород в массиве и устройство для его осуществления.The drawing shows a diagram of an implementation of a method for determining the parameters of rock stratifications in an array and a device for its implementation.

Способ реализуют с помощью устройства следующим образом.The method is implemented using the device as follows.

В массиве горных пород бурят скважину 1, в которую подают устройство, включающее провод 2, оголенный на конце 3, установленные на проводе 2 электроды 4 с проводниками 5. В скважине 1 формируют сигнальные линии (поз. не обозначены) заполнением ее твердеющей массой, которая после отвердения образует хрупкий электропроводящий стержень 6 (далее стержень), жестко сцепленный со стенками скважины 1 и имеющий удельное электрическое сопротивление, зависящее от давления. Проводники 5 и провод 2 подключают к регистрирующей аппаратуре 7 (например, измерителю электрического сопротивления). Определяют изменение электрического сопротивления между электродами 4 во времени и по нему судят о параметрах расслоений 8 и оценивают изменение напряжений в массиве. Оголенный конец 3 провода 2 используют в качестве одного из электродов 4 (последнего от устья скважины 1).A well 1 is drilled in the rock mass, into which a device is supplied, including wire 2, bare at the end 3, electrodes 4 with conductors 5 installed on wire 2. In the well 1, signal lines (not marked) are formed by filling it with a hardening mass, which after hardening, it forms a brittle electrically conductive rod 6 (hereinafter the rod), rigidly adhered to the walls of the well 1 and having a specific electrical resistance that depends on pressure. Conductors 5 and wire 2 are connected to a recording apparatus 7 (for example, an electrical resistance meter). The change in electrical resistance between the electrodes 4 in time is determined, and it is used to judge the parameters of the bundles 8 and evaluate the change in stresses in the array. The bare end 3 of the wire 2 is used as one of the electrodes 4 (the last from the wellhead 1).

Отметим, что на кривой изменения электрического сопротивления между электродами 4 во времени скачки соответствуют моментам возникновения трещин (разрыва сигнальной линии фронтом расслоения 8), а ее плавное изменение во времени соответствует изменению давления на стержень 6 со стороны стенок скважины 1 (на контакте с горной порой). Поэтому с помощью одних и тех же стержней 6 с указанными свойствами фиксируют моменты разрыва сигнальных линий (образование расслоений) и предшествующее этому изменение давления в массиве горных пород (в стержнях 6).Note that on the curve of the change in electrical resistance between the electrodes 4 in time, the jumps correspond to the moments of cracking (rupture of the signal line by the delamination front 8), and its smooth change in time corresponds to the change in pressure on the rod 6 from the side of the walls of the well 1 (at the contact with the mountain pore ) Therefore, with the help of the same rods 6 with the indicated properties, the moments of rupture of signal lines (the formation of bundles) and the previous change in pressure in the rock mass (in rods 6) are recorded.

Провод 2 и проводники 5 выполнены из материала (медь, алюминий), способного в отличие от горной породы и стержней 6 к большим деформациям без разрушения (обрыва провода 2 или проводников 5). Поэтому после образования в стержне 6 трещин электрическая связь между электродами 4 и измерителем 8 сопротивления не нарушается. Толщину провода 2 выбирают такой, чтобы его можно было независимо от длины (например, большей диаметра выработки, из которой ведутся наблюдения) путем изгибания подавать в скважину 1, но при этом, чтобы в скважине 1 он удерживал электроды 4 на требуемом расстоянии друг от друга.Wire 2 and conductors 5 are made of material (copper, aluminum), which, unlike rocks and rods 6, is capable of large deformations without destruction (wire break 2 or conductors 5). Therefore, after the formation of cracks in the rod 6, the electrical connection between the electrodes 4 and the resistance meter 8 is not violated. The thickness of the wire 2 is chosen so that it can be irrespective of the length (for example, a larger diameter of the excavation from which observations are made) to be fed into the well 1 by bending, but at the same time so that in the well 1 it holds the electrodes 4 at the required distance from each other .

В ряде случаев (когда диаметр выработки больше длины контролируемого участка) устройство изготавливают не в скважине 1, а в разборной цилиндрической форме (далее - форма). Для этого провод 2 с электродами 4 и проводниками 5 помещают в форму (на чертеже не показана), которую затем заполняют твердеющей массой. После отвердения поданной массы образуется стержень 6 с указанными свойствами. Этот стержень 6 извлекают из формы, подают в скважину 1 и скрепляют с ее стенками цементирующим материалом, что облегчает реализацию способа для восстающих скважин.In some cases (when the working diameter is greater than the length of the controlled section), the device is manufactured not in well 1, but in a collapsible cylindrical shape (hereinafter referred to as the form). To do this, wire 2 with electrodes 4 and conductors 5 is placed in a mold (not shown in the drawing), which is then filled with a hardening mass. After hardening the supplied mass, a rod 6 with the indicated properties is formed. This rod 6 is removed from the mold, fed into the well 1 and fastened with its walls with cementing material, which facilitates the implementation of the method for rising wells.

Образованию трещин (в результате расслоения массива) предшествует деформация горных пород, обусловленная изменением напряжений в массиве. Поэтому по деформации стенок скважины 1 можно оценивать изменения напряжений. В предлагаемом способе деформация стенок скважины 1 проявляется как изменение давления на стержни 6 (или внутри стержней 6). Поэтому, используя стержни 6, удельное электрическое сопротивление которых зависит от давления, можно по изменению во времени электрического сопротивления между установленными внутри стержней 6 электродами 4 оценивать характер изменения напряжений в массиве.The formation of cracks (as a result of stratification of the massif) is preceded by deformation of rocks due to changes in stresses in the massif. Therefore, according to the deformation of the walls of the well 1, stress changes can be estimated. In the proposed method, the deformation of the walls of the well 1 is manifested as a change in pressure on the rods 6 (or inside the rods 6). Therefore, using rods 6, the electrical resistivity of which depends on pressure, it is possible to evaluate the nature of the change in voltage in the array by the change in time of the electrical resistance between the electrodes 4 installed inside the rods 6.

В результате специальных исследований были найдена смесь, позволяющая формировать стержни 6, обладающие отмеченными свойствами. Это смесь графитового порошка, цемента и воды. Суммарный объем цемента и воды определяют из требований к прочности, хрупкости и удельной электропроводности стержней 6. Он может доходить до 40% общего объема смеси.As a result of special studies, a mixture was found that allows the formation of rods 6 having the noted properties. This is a mixture of graphite powder, cement and water. The total volume of cement and water is determined from the requirements for strength, brittleness and electrical conductivity of the rods 6. It can reach up to 40% of the total volume of the mixture.

На ряде рудников горная порода обладает высокой электрической проводимостью, способной шунтировать стержни 6. Чтобы предлагаемый способ не зависел от электрических свойств горных пород, между стержнями 6 и стенками скважины 1 предварительно образуют прослойку (на чертеже не показана) из хрупкого диэлектрического материала, например, эпоксидной смолы. При изготовлении устройства с применением формы (вне скважины 1) хрупкий диэлектрический материал наносят на его поверхность до подачи в скважину 1.At a number of mines, the rock has a high electrical conductivity capable of shunting the rods 6. To the proposed method does not depend on the electrical properties of the rocks, between the rods 6 and the walls of the borehole 1 previously form a layer (not shown) of brittle dielectric material, for example, epoxy pitches. In the manufacture of the device using the mold (outside the well 1), a brittle dielectric material is applied to its surface before being fed into the well 1.

На чертеже представлена простейшая схема реализации способа. Используя современное оборудование, на его основе можно создавать измерительные системы непрерывного контроля напряженно-деформированного состояния породного массива на заданном участке или в пределах всего горного предприятия в целом. Он позволяет также контролировать состояние искусственных сооружений, например плотин гидроэлектростанций.The drawing shows the simplest diagram of the implementation of the method. Using modern equipment, it can be used to create measuring systems for continuous monitoring of the stress-strain state of the rock mass at a given site or within the entire mining enterprise as a whole. It also allows you to monitor the status of artificial structures, such as dams of hydroelectric power plants.

Предлагаемым способом технически реализуют идею внедрения в массив горных пород элементов измерительной системы, которые подвергаются воздействию происходящих процессов непосредственно. Поэтому он является прямым методом измерения и позволяет получать достоверную информацию независимо от свойств горных пород в массиве. При использовании нескольких скважин можно определять скорости перемещения фронта расслоения (как в прототипе), ориентацию плоскости расслоения, следить за развитием расслоений по нескольким плоскостям одновременно, оценивать характер изменения напряжений в массиве, осуществлять диагностику (определять деформацию горных пород, характер развития трещин, устойчивость горных выработок) породного массива в заданной области. Кроме того, даже одна скважина позволяет оценивать изменение напряжений в конкретной области массива горных пород, определять количество расслоений и расстояния между ними. Способ и устройство могут применяться на любых горных предприятиях с использованием простых стандартных средств.The proposed method technically implements the idea of introducing elements of the measuring system into the rock mass, which are directly affected by the processes. Therefore, it is a direct measurement method and allows you to obtain reliable information regardless of the properties of rocks in the massif. When using several wells, it is possible to determine the velocities of the displacement of the stratification front (as in the prototype), the orientation of the stratification plane, monitor the development of stratifications along several planes at the same time, evaluate the nature of changes in stresses in the massif, and diagnose (determine the deformation of rocks, the nature of the development of cracks, the stability of mountain workings) of the rock mass in a given area. In addition, even one well allows you to evaluate the change in stress in a specific area of the rock mass, determine the number of bundles and the distance between them. The method and device can be applied at any mining enterprises using simple standard means.

Claims (7)

1. Способ определения параметров расслоений горных пород в массиве, включающий бурение скважин и установку в них сигнальных линий, фиксацию моментов разрывов сигнальных линий и определение параметров расслоений, отличающийся тем, что в скважинах на различных уровнях устанавливают электроды с проводниками для подключения к регистрирующей аппаратуре, а сигнальные линии формируют заполнением скважин твердеющей массой, которая после отвердения образует хрупкие электропроводящие стержни, жестко сцепленные со стенками скважин, определяют изменение во времени электрического сопротивления между электродами и по нему судят о параметрах расслоений горных пород в массиве.1. The method of determining the parameters of rock stratifications in the array, including drilling wells and installing signal lines in them, fixing the moments of breaks in the signal lines and determining the parameters of the bundles, characterized in that electrodes with conductors are installed at different levels in the wells for connecting to recording equipment, and the signal lines are formed by filling the wells with a hardening mass, which after hardening forms brittle electrically conductive rods, rigidly adhered to the walls of the wells, determine the time variation of the electrical resistance between the electrodes and it is used to judge the parameters of rock stratification in the massif. 2. Способ по п.1, отличающийся тем, что скважины заполняют твердеющей массой, которая после отвердения образует хрупкие электропроводящие стержни, удельное электрическое сопротивление которых зависит от давления.2. The method according to claim 1, characterized in that the wells are filled with a hardening mass, which after hardening forms brittle electrically conductive rods, the electrical resistivity of which depends on pressure. 3. Способ по п.1 или 2, отличающийся тем, что в качестве твердеющей массы используют смесь графитового порошка, цемента и воды.3. The method according to claim 1 or 2, characterized in that the mixture of graphite powder, cement and water is used as a hardening mass. 4. Способ по любому из пп.1-3, отличающийся тем, что между хрупкими электропроводящими стержнями и стенками скважин предварительно образуют прослойку из хрупкого диэлектрического материала.4. The method according to any one of claims 1 to 3, characterized in that between the brittle electrically conductive rods and the walls of the wells, a layer of brittle dielectric material is preliminarily formed. 5. Устройство для определения параметров расслоений горных пород в массиве, включающее сигнальную линию в виде стержня и электроды, подключенные к регистрирующей аппаратуре, отличающееся тем, что стержень выполнен хрупким и электропроводящим, внутри стержня проложен провод, на котором установлены электроды, контактирующие со стержнем и подключенные проводниками к регистрирующей аппаратуре.5. A device for determining the parameters of rock stratification in the array, including a signal line in the form of a rod and electrodes connected to recording equipment, characterized in that the rod is made brittle and electrically conductive, a wire is laid inside the rod on which electrodes are installed that are in contact with the rod and connected by conductors to the recording equipment. 6. Устройство по п.5, отличающееся тем, что удельное электрическое сопротивление хрупкого электропроводящего стержня зависит от давления.6. The device according to claim 5, characterized in that the electrical resistivity of a brittle electrically conductive rod depends on pressure. 7. Устройство по п.5 или 6, отличающееся тем, что на поверхность хрупкого электропроводящего стержня нанесен слой хрупкого диэлектрического материала.7. The device according to claim 5 or 6, characterized in that a layer of brittle dielectric material is applied to the surface of the brittle electrically conductive rod.
RU2004100455/03A 2004-01-05 2004-01-05 Method for determining sheeting parameters for rock solids in massif and device for realization of said method RU2248446C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2004100455/03A RU2248446C1 (en) 2004-01-05 2004-01-05 Method for determining sheeting parameters for rock solids in massif and device for realization of said method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2004100455/03A RU2248446C1 (en) 2004-01-05 2004-01-05 Method for determining sheeting parameters for rock solids in massif and device for realization of said method

Publications (1)

Publication Number Publication Date
RU2248446C1 true RU2248446C1 (en) 2005-03-20

Family

ID=35454153

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2004100455/03A RU2248446C1 (en) 2004-01-05 2004-01-05 Method for determining sheeting parameters for rock solids in massif and device for realization of said method

Country Status (1)

Country Link
RU (1) RU2248446C1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2583032C1 (en) * 2015-03-31 2016-04-27 Федеральное государственное бюджетное учреждение науки ИНСТИТУТ ПРОБЛЕМ КОМПЛЕКСНОГО ОСВОЕНИЯ НЕДР РОССИЙСКОЙ АКАДЕМИИ НАУК (ИПКОН РАН) Downhole method of determining zones of rock damage

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2583032C1 (en) * 2015-03-31 2016-04-27 Федеральное государственное бюджетное учреждение науки ИНСТИТУТ ПРОБЛЕМ КОМПЛЕКСНОГО ОСВОЕНИЯ НЕДР РОССИЙСКОЙ АКАДЕМИИ НАУК (ИПКОН РАН) Downhole method of determining zones of rock damage

Similar Documents

Publication Publication Date Title
CN201401174Y (en) System monitoring broken rock zone by high-density electrical resistivity
CN105840185B (en) A kind of consistent electric field fractured horizontal well Crack Monitoring method
EP2947456B1 (en) Method for positioning a sensor for concrete monitoring
CN103575769B (en) A kind of piezoelectric transducer for monitoring steel bar corrosion and monitoring steel bar corrosion method
CN109116411B (en) Microseismic sensors are fixed and recyclable device in a kind of hole suitable for different pore size
CN102822649A (en) Pile sensing device and method of using the same
CN108593721A (en) Method and device for detecting whether full grouting sleeve is full by resistance method
WO2015128831A1 (en) Grouted rock support testing apparatus and method
CN104018830A (en) Time and space evaluation method of coal seam hydraulic fracturing effect
CN103290827B (en) Mounting, burying and grouting method for multi-point displacement meter
RU2248446C1 (en) Method for determining sheeting parameters for rock solids in massif and device for realization of said method
CN112832301B (en) Electromagnetic cast-in-place pile and precast pile detection method based on cylindrical coordinate system
CN101343876A (en) Hydraulic rock anchor slip casting electronic logging and monitoring method
CN105004460A (en) Hollow inclusion strain gauge in composite structure
CN208606799U (en) Multi-parameter monitoring devices for roadway surrounding rock
WO2022252494A1 (en) Groove pipe device for tunnel surrounding rock internal micro-fracture development characteristics and monitoring method therefor
JP6230876B2 (en) Inspection method of cavity repair method of structure
CN105806275B (en) Device and method for monitoring continuous deformation of different areas of surrounding rock in real time
RU2441157C2 (en) Method to assess stressed condition of rocks and device for its realisation
CN201347454Y (en) Cathodic protection test probe for concrete pipe
CN111156944B (en) Real-time monitoring system and method for surrounding rock of roadway
CN101738368B (en) Concrete pipe cathode protection testing probe and testing method
CN114088774A (en) Anchor cable and rod grouting stage plumpness snap ring type detection device and detection method
CN208136889U (en) A kind of soil pressure cell fixed installation structure
RU2452796C1 (en) Subsurface anodic earth lead and activator of subsurface anodic earth lead

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20070106