RU2022102811A - DRILLING REINFORCED CONCRETE COLUMN AND METHOD FOR ITS CONSTRUCTION - Google Patents

DRILLING REINFORCED CONCRETE COLUMN AND METHOD FOR ITS CONSTRUCTION Download PDF

Info

Publication number
RU2022102811A
RU2022102811A RU2022102811A RU2022102811A RU2022102811A RU 2022102811 A RU2022102811 A RU 2022102811A RU 2022102811 A RU2022102811 A RU 2022102811A RU 2022102811 A RU2022102811 A RU 2022102811A RU 2022102811 A RU2022102811 A RU 2022102811A
Authority
RU
Russia
Prior art keywords
column
reinforcing
reinforced concrete
cage
concrete
Prior art date
Application number
RU2022102811A
Other languages
Russian (ru)
Other versions
RU2798149C2 (en
Inventor
Павел Борисович Юркевич
Original Assignee
Общество с ограниченной ответственностью "Инженерное бюро Юркевича"
Filing date
Publication date
Application filed by Общество с ограниченной ответственностью "Инженерное бюро Юркевича" filed Critical Общество с ограниченной ответственностью "Инженерное бюро Юркевича"
Publication of RU2022102811A publication Critical patent/RU2022102811A/en
Application granted granted Critical
Publication of RU2798149C2 publication Critical patent/RU2798149C2/en

Links

Claims (8)

1. Железобетонная колонна, включающая замоноличенный бетонной смесью арматурный каркас (4, 6), состоящая из верхней опорной (9) и нижней фундаментной (8) частей, отличающаяся тем, что арматурный каркас (6) в зоне соединения верхней опорной части (9) колонны соединен жестко или нахлестом, арматурный каркас верхней опорной части заключен в неизвлекаемую металлическую трубу-опалубку (5), являющуюся внешним армирующим элементом арматурного каркаса (6) одновременно, железозобетонная колонна содержит монолитное силовое соединение в зоне соединения (7) арматурного каркаса (4) нижней фундаментной части (8) колонны с верхней опорной частью (9), омоноличенное в заделке (10), трехуровневое по горизонтали закрепления от смещения арматурного каркаса в процессе возведения колонны, размещенные в граничных областях колонны - верх, низ и содержит область сопряжения верхней опорной и нижней фундаментной частей.1. Reinforced concrete column, including a reinforcement cage (4, 6) embedded in a concrete mixture, consisting of an upper support (9) and a lower foundation (8) parts, characterized in that the reinforcement cage (6) in the connection area of the upper support part (9) the columns are connected rigidly or overlapped, the reinforcing cage of the upper supporting part is enclosed in a non-removable metal pipe-formwork (5), which is the external reinforcing element of the reinforcing cage (6) at the same time, the reinforced concrete column contains a monolithic power connection in the connection zone (7) of the reinforcing cage (4) the lower foundation part (8) of the column with the upper supporting part (9), monolithic in the embedment (10), three-level horizontal fastening from the displacement of the reinforcement cage during the erection of the column, placed in the boundary areas of the column - top, bottom and contains the interface area of the upper support and lower base parts. 2. Железобетонная колонна по п. 1, отличающаяся тем, что колонна выполнена в виде единого арматурного каркаса, вывешенного с технологическим зазором (14) по отношению к дну скважины (3) с выделением функционального «жесткого» соединения стержней арматурных каркасов (6, 4) - верхней опорной (9) и нижней фундаментной (8) частей и заделкой (10) в зоне соединений (7) при омоноличивании колонны с опиранием ее на цементируемое трещиноватое и кавернозное полускальное или скальное основание.2. Reinforced concrete column according to claim 1, characterized in that the column is made in the form of a single reinforcing cage, hung with a technological gap (14) in relation to the bottom of the well (3) with the release of a functional "rigid" connection of reinforcing cage rods (6, 4 ) - upper support (9) and lower foundation (8) parts and embedding (10) in the connection zone (7) when the column is monolithic with its support on a cemented fractured and cavernous semi-rock or rock base. 3. Железобетонная колонна по п. 1, отличающаяся тем, что колонна выполнена с уширенной пятой из двух раздельных арматурных каркасов - вывешенного каркаса (6) верхней опорной части (9) и опущенного на дно скважины (3) арматурного каркаса (4) нижней фундаментной (8) части с соединением каркасов «внахлест» с зазорами по отношению друг к другу и формированием зоны соединения (7) и заделки (10) при омоноличивании колонны с опиранием ее на основание из дисперсных грунтов, упрочняемое опрессовочной цементацией.3. Reinforced concrete column according to claim 1, characterized in that the column is made with a broadened heel of two separate reinforcing cages - a suspended frame (6) of the upper support part (9) and a reinforcing cage (4) lowered to the bottom of the well (3) of the lower foundation (8) parts with “overlap” connection of frameworks with gaps relative to each other and formation of a connection zone (7) and termination (10) when the column is monolithic with its support on a base of dispersed soils, strengthened by pressing cementation. 4. Способ возведения буровой железобетонной колонны, включающий операции бурения скважины под защитой от обрушения до проектной глубины, инклинометрию, изготовление арматурного каркаса колонны, помещение арматурного каркаса колонны в обсадную трубу, опускание бетоновода через внутреннюю часть арматурного каркаса колонны и укладку под защитой от обрушения бетонной смеси (16) нижней фундаментной части (8) на высоту, достаточную для фиксации нижней части буровой железобетонной колонны, подъем бетоновода на высоту не более высоты укладки бетонной смеси для фиксации, выдержку уложенной бетонной смеси до набора бетонной смесью минимальной прочности, проверку фиксации арматурного каркаса колонны и продолжение бетонирования до проектных отметок с одновременным извлечением из скважины обсадной трубы и заполнением межтрубного пространства цементно-песчаным раствором, отличающийся тем, что бурение скважины и возведение колонны выполняют под комплексной защитой металлической обсадной трубы (1) и бурового глинистого раствора (2), в уровне форшахты вывешивают арматурный каркас (6), производят инклинометрию для оценки вертикальности арматурного каркаса (6) верхней опорной части (9) колонны с помощью инклинометра, устанавливаемого в технологическом трубопроводе колонны, осуществляют центрирование арматурного каркаса (6) верхней опорной (9) части колонны с помощью центрирующего кондуктора (12) в уровне форшахты и съемных гидравлических домкратов (15), размещаемых на внешней армирующей трубе (5) арматурного каркаса (6) верхней опорной части (9) колонны ближе к низу обсадной трубы (1) с последующим закреплением арматурного каркаса (6) от смещения в трех уровнях, выполняют непрерывное бетонирование методом вертикально перемещающейся внутри пространственных арматурных каркасов (4, 6) бетонолитной трубы с использованием бетонной смеси, однородной по своему составу и свойствам, с параллельной засыпкой зазора между обсадной трубой (1) и внешней армирующей трубой (5) арматурного каркаса (6) верхней опорной части (9) колонны зернистым материалом (17).4. A method for erecting a reinforced concrete drill string, including operations of drilling a well under collapse protection to the design depth, inclinometry, manufacturing of the column reinforcement cage, placing the column reinforcement cage in the casing, lowering the concrete conduit through the inside of the column reinforcement cage and laying the concrete under collapse protection mixture (16) of the lower foundation part (8) to a height sufficient to fix the lower part of the drilled reinforced concrete column, lifting the concrete pipeline to a height not exceeding the height of the concrete mix for fixing, holding the laid concrete mix until the concrete mix reaches the minimum strength, checking the fixation of the reinforcing cage columns and continuation of concreting to design levels with simultaneous extraction of the casing pipe from the well and filling the annular space with cement-sand mortar, characterized in that the drilling of the well and the erection of the column are carried out under the complex protection of the metal casing pipe (1) and b uric clay solution (2), a reinforcing cage (6) is hung at the level of the foreshaft, inclinometry is performed to assess the verticality of the reinforcing cage (6) of the upper support part (9) of the column using an inclinometer installed in the technological pipeline of the column, the reinforcing cage (6) is centered ) the upper support (9) part of the string using a centering jig (12) at the level of the foreshaft and removable hydraulic jacks (15) placed on the outer reinforcing pipe (5) of the reinforcing cage (6) of the upper support part (9) of the string closer to the bottom of the casing pipes (1) with the subsequent fixing of the reinforcement cage (6) from displacement in three levels, perform continuous concreting by the method of vertically moving inside the spatial reinforcement cages (4, 6) concrete-cast pipe using a concrete mixture that is homogeneous in composition and properties, with parallel backfilling gap between the casing pipe (1) and the outer reinforcing pipe (5) of the reinforcing cage (6) upper support part (9) of the column with granular material (17). 5. Способ возведения буровой железобетонной колонны по п. 4, отличающийся тем, что бурение скважины осуществляют диаметром Dc>Dк на величину α=(2εг+2Δ+2τ) с учетом возможного отклонения оси скважины как в плане, так и от вертикали, где Dк - максимальный эквивалентный диаметр арматурного каркаса колонны, εг - эксцентриситет проекции геометрической оси и проекции оси центра масс колонны в плоскости подвеса (верха) колонны, Δ - отклонение оси буровой скважины от вертикали, τ - отклонение оси буровой скважины в плане.5. The method of erecting a drilled reinforced concrete column according to claim 4, characterized in that the drilling of the well is carried out with a diameter D c >D k by the value α=(2ε g +2Δ+2τ) taking into account the possible deviation of the axis of the well both in plan and from vertical, where D to - the maximum equivalent diameter of the reinforcement cage of the column, ε g - the eccentricity of the projection of the geometric axis and the projection of the axis of the center of mass of the column in the plane of the suspension (top) of the column, Δ - deviation of the axis of the borehole from the vertical, τ - deviation of the axis of the borehole in plan. 6. Способ возведения буровой железобетонной колонны по п. 4, отличающийся тем, что после замоноличивания арматурных каркасов колонны через технологический трубопровод, размещаемый внутри колонны, осуществляют цементацию (18) трещиноватых и кавернозных пород полускального или скального основания или опрессовочную цементацию (19а) основания в дисперсных грунтах.6. The method of erecting a drilled reinforced concrete column according to claim 4, characterized in that, after embedding the reinforcing cages of the column through the technological pipeline placed inside the column, cementation (18) of fractured and cavernous rocks of a semi-rocky or rocky base or pressure cementation (19a) of the base in dispersed soils. 7. Способ возведения буровой железобетонной колонны по п. 4, отличающийся тем, что в уровне форшахты вывешивают арматурный каркас колонны, включающий каркас верхней опорной и нижней фундаментной частей колонны.7. The method of erecting a drilled reinforced concrete column according to claim 4, characterized in that the reinforcing frame of the column is hung out at the level of the foreshaft, including the frame of the upper supporting and lower foundation parts of the column. 8. Способ возведения буровой железобетонной колонны по п. 4, отличающийся тем, что в уровне форшахты вывешивают арматурный каркас верхней опорной части колонны.8. A method for erecting a drilled reinforced concrete column according to claim 4, characterized in that a reinforcing cage of the upper supporting part of the column is hung out at the level of the foreshaft.
RU2022102811A 2022-02-04 Drilling reinforced concrete column and method for its construction RU2798149C2 (en)

Publications (2)

Publication Number Publication Date
RU2022102811A true RU2022102811A (en) 2022-05-25
RU2798149C2 RU2798149C2 (en) 2023-06-16

Family

ID=

Similar Documents

Publication Publication Date Title
US7585134B2 (en) Reinforced-concrete column in the soil pit and method of its construction
CN205742213U (en) Foundation pit supporting construction
CN110424380B (en) Accurate guiding construction method for cast-in-situ bored pile
CN110847177A (en) Fixed verticality adjusting and upward floating preventing device and method with steel pipe supporting column serving as structural column
CN109763483B (en) Up-going type sectional grouting process for thick fourth-system deep-buried mining cave-in broken stratum
CN113027462B (en) Reinforcing method for shaft penetrating through weak surrounding rock
CN107989057A (en) A kind of Bridge Pile Foundation Construction method
CN111945714A (en) Steel sleeve guiding method combined with steel upright column inserting construction method
JP2022553449A (en) External expansion pipe construction method for drilling in the mining zone
RU2375521C1 (en) Method of erecting piled foundation designed for high loads
RU2022102811A (en) DRILLING REINFORCED CONCRETE COLUMN AND METHOD FOR ITS CONSTRUCTION
RU2798149C2 (en) Drilling reinforced concrete column and method for its construction
RU2229557C1 (en) Screw reinforced concrete column and building method thereof
CN115853009A (en) Photovoltaic support foundation suitable for sandy soil geology and construction method thereof
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN103015433A (en) Method for constructing super-large diameter round and square combination deep foundation pit
RU2674480C1 (en) Method of drilling reinforced concrete column erection
CN113123793B (en) Weak stratum vertical shaft derrick structure and construction method thereof
RU34952U1 (en) Reinforced concrete drill string
CN216515545U (en) Karst area drilling bored concrete pile structure
CN211713982U (en) Deep backfill infilled wall foundation structure
CN216517822U (en) Drill and dig prefabricated well structure of quick installation of pore-forming and drill and dig pore-forming device
CN217760994U (en) Shallow buried tunnel supporting structure
JP3233145U (en) Steel pipe column for underground construction-pile structure
CN206721873U (en) A kind of technique pore structure