PL181551B1 - Method of erecting high buildings and adjusting device for use in that method - Google Patents

Method of erecting high buildings and adjusting device for use in that method

Info

Publication number
PL181551B1
PL181551B1 PL96343311A PL34331196A PL181551B1 PL 181551 B1 PL181551 B1 PL 181551B1 PL 96343311 A PL96343311 A PL 96343311A PL 34331196 A PL34331196 A PL 34331196A PL 181551 B1 PL181551 B1 PL 181551B1
Authority
PL
Poland
Prior art keywords
wall element
elements
face
upper face
reinforcement
Prior art date
Application number
PL96343311A
Other languages
Polish (pl)
Inventor
Ralf Sebald
Original Assignee
Ralf Sebald
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ralf Sebald filed Critical Ralf Sebald
Publication of PL181551B1 publication Critical patent/PL181551B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/161Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/0025Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects with installation or service material, e.g. tubes for electricity or water
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/022Means for inserting reinforcing members into the mould or for supporting them in the mould
    • B28B23/024Supporting means
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/44Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose
    • E04C2/52Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits
    • E04C2/521Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the purpose with special adaptations for auxiliary purposes, e.g. serving for locating conduits serving for locating conduits; for ventilating, heating or cooling
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • E04G11/10Forms, which are completely dismantled after setting of the concrete and re-built for next pouring of elements without beams which are mounted during erection of the shuttering to brace or couple the elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Ceramic Engineering (AREA)
  • Electromagnetism (AREA)
  • Physics & Mathematics (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Building Environments (AREA)
  • Finishing Walls (AREA)
  • Glass Compositions (AREA)
  • Panels For Use In Building Construction (AREA)
  • Installation Of Indoor Wiring (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The reinforcement (7,8) which is embedded before the casting material set protrudes over the lower end face and upper end face of the wall element to form a reinforced connection. The load-absorbing edge strips of the upper end face are flat. Length-adjustable levelling members (15) such as threaded rods and screw sleeves for the wall element are embedded spaced out from each other in the lower end face. At least the upper end face has additionally two spaced anchorage members for fixing lifting tools. Empty tubes (11) for electric cables can be embedded in the wall element to protrude over the relevant end faces of the wall element.

Description

Przedmiotem wynalazku jest sposób wznoszenia wysokich budynków i urządzenie regulacyjne do wznoszenia wysokich budynków dla ustawiania elementu ściennego, który ma wysokość jednego piętra.The present invention relates to a method for erecting tall buildings and an adjusting device for erecting tall buildings for positioning a wall element which is one story high.

Prefabrykowane elementy ścienne były stosowane w większym zakresie do wznoszenia wysokich budynków jedynie w ramach tzw. budownictwa płytowego. Wady takiego budownictwa są ogólnie znane i polegają na tym, że prefabrykowane elementy ścienne ustawia sięPrefabricated wall elements were used to a greater extent for the construction of tall buildings only as part of the so-called slab construction. The disadvantages of such construction are generally known and are that the prefabricated wall elements are positioned

181 551 zasadniczo jedynie jeden na drugim piętrami bez stosowania pomiędzy nimi odpowiedniego siłowego połączenia według wymagań statyki budynku. W związku z tym z budownictwa takiego rezygnuje się.181 551 essentially only one on top of the other storeys without any suitable force-locking between them as required by the statics of the building. Therefore, such construction is abandoned.

Prefabrykowane elementy ścienne można stosować zwłaszcza do wznoszenia ścian wewnętrznych, ponieważ jak wiadomo nie mus^a mieć one żadnej aktywności oddychania. Daje to znaczne zalety, przede wszystkim kiedy wykorzystuje się możliwość wykonywania w trakcie prefabrykacji elementu ściennego nie tylko otworów, zwłaszcza drzwi, ale również całej instalacji elektrycznej i ewentualnie sanitarnej. Można do tego celu wykorzystywać technikę CAD/CAM i uwzględniać w krótkim czasie również późniejsze zmiany w planach, a zwłaszcza w wewnętrznej ścianie deskowania. Automatyzację prefabrykacji można osiągnąć przez zastosowanie robotów przemysłowych sterowanych komputerowo, a zwłaszcza do wkładania zbrojenia i ewentualnych części instalacji oraz do umieszczania elementów rezerwujących miejsce na otwory itp.The prefabricated wall elements can be used in particular for erecting interior walls, since, as is known, they do not have to have any breathing activity. This gives considerable advantages, especially when it is possible to make not only openings, especially doors, but also the entire electrical and possibly sanitary installation during the prefabrication of the wall element. For this purpose, CAD / CAM technology can be used and subsequent changes to the plans, especially to the inner wall of the formwork, can also be quickly taken into account. Automation of the prefabrication can be achieved by the use of computer-controlled industrial robots, especially for inserting reinforcement and possible parts of the installation and for placing space reserve elements for holes, etc.

Celem wynalazku jest opracowanie sposobu wznoszenia wysokich budynków i urządzenie regulacyjne do ustawiania elementu ściennego za pomocą którego można łatwo i dokładnie ustawiać duży element ścienny przed jego trwałym połączeniem z częściami łączącymi bryły budynku.The object of the invention is to provide a method for erecting tall buildings and an adjustment device for positioning a wall element with which a large wall element can be easily and accurately positioned before it is permanently connected to the connecting parts of the building bodies.

Sposób wznoszenia wysokich budynków według wynalazku z zastosowaniem prefabrykowanego elementu ściennego z zalewanym zbrojeniem i elementami instalacyjnymi, mającego wystające z dolnej i górnej powierzchni czołowej zbrojenie łączeniowe, na górnej powierzchni czołowej płaskie pasy brzegowe oraz elementy kotwiące dla uchwytu dźwigu, a w dolnej powierzchni czołowej rozmieszczone w odstępach od siebie elementy niwelacyjne o regulowjulej długości iconajmmaj jedną bocrnąpowierochnięczołowąz wąprofilowfnyw rowkiem do zalewowego łączenia dwóch przyległych elementów ściennych, charakteryzuje się tym, że po przeciwległych stronach każdego umieszczonego w położeniu montażu elementu ściennego zamocowuje się przynajmniej jedno urządzenie regulacyjne do pionowego ustawiania i ustawia ten element ścienny nad górną powierzchnią czołową elementu ściennego niższego piętra opuszczając go w szczelinę pomiędzy dwoma wspartymi na tej górnej powierzchni czołowej elementami stropowymi niższego piętra, aż jego elementy niwelacyjne dojdą do górnej powierzchni czołowej i tak osadzony element ścienny ustawia się w poziomie za pomocą jego elementów niwelacyjnych oraz w pionie za pomocą urządzenia regulacyjnego, przy czym powstałą szczelinę pomiędzy dolną powierzchnią czołową ustawionego elementu ściennego i powierzchnia czołową elementu ściennego umieszczonego poniżej wypełnia się betonem korzystnie stosując wibrację, a po stwardnieniu betonu usuwa się urządzenie regulacyjne.The method of erecting tall buildings according to the invention with the use of a prefabricated wall element with flooded reinforcement and installation elements, having joining reinforcement protruding from the lower and upper face, flat edge strips on the upper face and anchoring elements for the crane handle, and spaced apart in the lower face leveling elements with adjustable length, each with one surface and a rectangular surface with a narrow groove for the flood connection of two adjacent wall elements, characterized by the fact that on opposite sides of each wall element placed in the installation position, at least one adjusting device for vertical positioning is attached and this wall element is positioned over upper face of the lower story wall element, lowering it into the gap between the two floor elements of the lower story supported on this upper face, until its the leveling elements will reach the upper face and the embedded wall element is aligned horizontally with its leveling elements and vertically with the help of an adjusting device, the gap between the lower face of the aligned wall element and the face of the wall element below is filled with concrete preferably using vibration, and after the concrete has hardened, the adjusting device is removed.

Urządzenie regulacyjne według wynalazku do ustawiania prefabrykowanego elementu ściennego z zalewanym zbrojeniem i elementami instalacyjnymi, mającego wystające z dolnej i górnej powierzchni czołowej zbrojenie łączeniowe, na górnej powierzchni czołowej płaskie pasy brzegowe oraz elementy kotwiące dla uchwytu dźwigu, a w Oolnbj powierzchni czołowej rozmieszczone w odstępach od siebie elementy wwblacyjwb o regulowanej długości i co najmniej jedną boczną powierzchnię czołową z wyprofilowanym rowkiem do zalewowego łączenia dwóch przyległych elementów ściennych, charakteryzuje się tym, że ma w przybliżeniu kształt litery L, przy czym jego długie ramię ma przy jednym końcu odchodzące pod kątem prostym krótkie ramię na którego wolnym końcu jest umieszczona przestawna w pionie noga. Dwa długie ramiona korzystnie są połączone ze sobą z przeciwległych stron elementu ściennego ponad jego górną krawędzią i z dolną krawędzią tego elementu. Przestawna w pionie noga ma gwintowany trzpień, który jest połączony gwintem z krótkim ramieniem i zakończony stożkową wsporczą stopą, przy czym, krótkie ramię jest wsparte na długim ramieniu poprzez ukośną poprzeczkę.Adjustment device according to the invention for positioning a prefabricated wall element with poured reinforcement and installation elements, having joining reinforcement protruding from the lower and upper face, flat edge strips on the upper face and anchor elements for the crane handle, and spaced apart in the front face length-adjustable wblation elements and at least one side face with a profiled groove for the flood connection of two adjacent wall elements, characterized by being approximately L-shaped, with its long arm having a short arm extending at right angles at one end at the free end of which is a vertically adjustable leg. The two long arms are preferably connected to each other on opposite sides of the wall element above its upper edge and to the lower edge of the wall element. The vertically adjustable leg has a threaded spindle which is threadedly connected to the short arm and terminates in a conical support foot, the short arm being supported on the long arm by a diagonal crossbar.

Manipulowanie urządzeniem regulacyjnym jest uproszczone, gdy długie ramiona kształtowników w kształcie litery L są po obu stronach elementu ściecwbgo połączone ze sobą ponad jego krawędzią górną i/lub z jego krawędzią dolną. Przynajmniej jedno z tych połączeń może być wykonane jako rozłączane.Manipulation of the adjusting device is simplified when the long legs of the L-shaped sections are connected to each other over its upper edge and / or to its lower edge on both sides of the bead element. At least one of these connections may be made releasable.

181 551181 551

Nogi są regulowane w pionie przy każdym wolnym końcu krótkiego ramienia urządzenia regulacyjnego i mogą przykładowo mieć jeden umieszczony w gwintowanej tulei gwintowany trzpień zakończony stożkową stopą wsporczą. Po wylaniu betonu i jego utwardzeniu, a więc wtedy, gdy można już usunąć urządzenia regulacyjne, pozostają jedynie stożkowe zagłębienia, które przed położeniem jastrychu trzeba tylko wypełnić masą szpachlową lub podobnąThe legs are vertically adjustable at each free end of the short arm of the adjusting device, and may, for example, have one threaded pin in a threaded sleeve terminating in a conical support foot. After the concrete has been poured and hardened, i.e. when the adjusting devices can be removed, only the conical cavities remain, which only need to be filled with putty or similar before laying the screed

Wynalazek jest dokładniej objaśniony na rysunku, na którym: fig. 1 przedstawia element ścienny przygotowany do magazynowania lub do montażu, fig. 2 przedstawia sytuację przy montażu elementu ściennego w przekroju, fig. 3 przedstawia sytuację montażu w widoku perspektywicznym, fig. 4 przedstawia zamontowany element ścienny podczas zalewania betonem, fig. 5 przedstawia zamontowany element ścienny po wykonaniu stropu międzypiętrowego łącznie z jastrychem, i fig. 5 przedstawia połączone elementy ścienne umieszczone obok siebie w uproszczonym widoku.The invention is explained in more detail in the drawing, in which: Fig. 1 shows a wall element prepared for storage or assembly, Fig. 2 shows a situation in section when installing a wall element, Fig. 3 shows a situation of assembly in a perspective view, Fig. 4 shows installed a wall element during pouring with concrete, fig. 5 shows the mounted wall element after the inter-story ceiling including screed has been made, and fig. 5 shows the connected wall elements placed side by side in a simplified view.

Na fig. 1 przedstawiono element ścienny w ustawieniu odpowiadającym późniejszej sytuacji przy montażu. Wszystkie widoczne powierzchnie są płaskie, podobnie jak przyjmujące obciążenie pasy brzegowe górnej powierzchni czołowej, tak że powstaje czyste przejście do dołączonego stropu międzypiętrowego (patrz również fig. 2 i dalsze). Element ścienny jest wyposażony w dwa urządzenia regulacyjne 21 i 22, których konstrukcja jest identyczna i dlatego dalej zostanie objaśnione tylko urządzenie regulacyjne 21. Zawiera ono dwa kształtowniki, których długie ramiona 21a, 21b przy swych górnych końcach są połączone przez gwintowany drążek 21c zabezpieczony przez nakrętki. Przy dolnych końcach długie ramiona 21a, 21b mająotwory do umieszczenia śrub 18a, które wchodząw gwintowane tuleje 18 elementu ściennego, dzięki czemu urządzenie regulacyjne 21 jest mocowane również przy swym dolnym końcu. Przy końcu krótkiego ramienia 21d wspartego na długim ramieniu 21b poprzez ukośną poprzeczkę 21e, znajduje się przestawna w pionie noga w postaci gwintowanego trzpienia 25, który jest umieszczony w gwintowanym otworze lub gwintowanej tulei krótkiego ramienia 21d i u góry ma uchwyt dla klucza, a od dołu jest zakończony stożkową stopą wsporczą 26.Fig. 1 shows the wall element in an alignment for the subsequent assembly situation. All visible surfaces are flat, as are the load-bearing edge bands of the upper face, so that a clean transition to the attached inter-story floor is created (see also Fig. 2 et seq.). The wall element is provided with two adjusting devices 21 and 22, the structure of which is identical, and therefore only the adjusting device 21 will be explained in the following. It comprises two sections, the long legs of which 21a, 21b at their upper ends are connected by a threaded rod 21c secured by nuts. . At the lower ends, the long arms 21a, 21b have holes for receiving screws 18a which engage the threaded sleeves 18 of the wall element, whereby the adjusting device 21 is also fastened at its lower end. At the end of the short arm 21d supported on the long arm 21b by a diagonal crossbar 21e, there is a vertically adjustable leg in the form of a threaded pin 25, which is inserted into a threaded hole or threaded sleeve of the short arm 21d and has a key holder at the top, and at the bottom is ended with a conical support foot 26.

Na fig. 2 i 3 przedstawiono sytuację podczas ustawiania nowego, prefabrykowanego elementu ściennego B na takim samym prefabrykowanym elemencie ściennym A niższego piętra. Do dolnego elementu ściennego A jest dołączony gładko i prawie bez szczelin strop międzypiętrowy, w postaci częściowo prefabrykowanego stropu 30 z nałożonym zbrojeniem 31. Podczas ustawiania nowy element ścienny poziomuje się za pomocą umieszczonego w nim elementu niwelacyjnego. W tym celu element niwelacyjny ma gwintowany drążek z zamocowaną na nim nakrętką do założenia klucza. Wystarczająco długie wystające odcinki zbrojenia 7, 8, w tym przypadku zarówno dolnego jak i górnego elementu ściennego, zachodzą na siebie (patrz fig. 2) i w razie potrzeby mogą być łączone ze sobą również za pomocą znanych tulei gwintowanych, tulei kotwiących itp. Jeżeli jest to konieczne ze względu na statykę budynku, to alternatywnie lub dodatkowo w zachodzące na siebie łukowe pałąki 19 elementów ściennych A, B można wprowadzić krótkie pręty zbrojeniowe 33, jak pokazano zwłaszcza na fig. 3. Wystające końce rurek 11 instalacji elektrycznej łączy się ze sobą. Podobnie postępuje się z ewentualną instalacją sanitarną (nie pokazano).Figures 2 and 3 show the situation when a new, prefabricated wall element B is positioned on the same prefabricated wall element A of the lower story. An inter-storey ceiling, in the form of a partially prefabricated ceiling 30 with reinforcement 31 applied, is connected to the lower wall element A smoothly and almost without gaps. During positioning, the new wall element is leveled by means of the leveling element placed therein. For this purpose, the leveling element has a threaded rod with a nut fitted thereon for inserting a key. Sufficiently long protruding sections of reinforcement 7, 8, in this case both of the lower and the upper wall element, overlap (see Fig. 2) and, if necessary, can also be connected to each other by means of known threaded sleeves, anchor sleeves, etc. necessary for the statics of the building, short reinforcing bars 33 may alternatively or additionally be introduced into the overlapping arches 19 of the wall elements A, B, as shown in particular in Fig. 3. The protruding ends of the pipes 11 of the electrical installation are connected to each other. The same is done for a possible sanitary installation (not shown).

Jak pokazano na fig. 4, element ścienny ustawia się w pionie za pomocą urządzeń regulacyjnych 21, 22 (to ostatnie nie pokazane na rysunku). Krótkie ramię 21 d urządzenia regulacyjnego jest tak zwymiarowane, że stożkowa stopa wsporcza 26 jest ustawiona dokładnie nad podporą 32 stropu 30 niższego piętra. Na fig. 4 pokazano ponadto układanie betonu 35 stropu między piętrami (dla uproszczenia nie pokazano zbrojenia stropu). Beton ten wypełnia również całkowicie przestrzeń pomiędzy dolną krawędzią właśnie ustawionego elementu ściennego B, a górną krawędzią elementu ściennego A niższego piętra.As shown in Fig. 4, the wall element is vertically adjusted by means of the adjusting devices 21, 22 (the latter not shown in the drawing). The short arm 21 d of the adjusting device is dimensioned such that the conical support foot 26 is positioned exactly above the support 32 of the floor 30 of the lower story. Fig. 4 also shows the concrete laying of the floor between the floors (for simplicity, the reinforcement of the floor is not shown). The concrete also completely fills the space between the lower edge of the wall element B just placed and the upper edge of the wall element A of the lower story.

Gdy górny element ścienny jest połączony z dolnym elementem ściennym, to po stwardnieniu betonu 35, można usunąć urządzenia regulacyjne 21, 22 bez naruszenia statyki budynku i połączeń siłowych.When the upper wall element is connected to the lower wall element, after the concrete 35 has hardened, the adjusting devices 21, 22 can be removed without disturbing the statics of the building and the force connections.

Następnie wypełnia się betonem stożkowe zagłębienia 36 pozostawione przez stopy 26 urządzeń regulacyjnych jak pokazano na fig. 5 oraz układa jastrych, który zwykle złożony jestThe conical cavities 36 left by the feet 26 of the adjusting devices are then filled with concrete as shown in Fig. 5 and the screed is laid, which is usually folded

181 551 z warstwy izolującej 37 i właściwego jastrychu 38. Jak pokazano na fig. 1-4 otrzymuje się wtedy również gładkie przejście jastrychu 38 do powierzchni ściany bez konieczności stosowania dodatkowej obróbki. W szczególności jastrych 38 przykrywa również otwory gwintowanych tulei umieszczonych w elemencie ściennym, które służyły do mocowania urządzeń regulacyjnych.181 551 from the insulating layer 37 and the actual screed 38. As shown in FIGS. 1-4, a smooth transition of the screed 38 to the wall surface is then also obtained without any additional treatment. In particular, the screed 38 also covers the holes of the threaded sleeves disposed in the wall element, which served to fasten the adjusting devices.

Na fig. 6 przedstawiono w przekroju widok trzech stykających się elementów ściennych, z których dwa tworzą narożnik. Ponieważ elementy ścienne wychodzą z deskowania z dokładnym utrzymaniem wymiarów i z płaskimi powierzchniami (za wyjątkiem późniejszej dolnej powierzchni czołowej) oraz mają jakość betonu licowego, to można je dokładnie i zgodnie zestawiać praktycznie bez szczelin. Przeciwległe rowki 20 tworzą zamknięte kanały. W kanały te wchodzi beton 35 przy wylewaniu usytuowanego u dołu stropu międzypiętrowego i po stwardnieniu tworzy tzw. plombę, która zapewnia połączenie siłowe pomiędzy elementami ściennymi w kierunku poziomym.Figure 6 is a sectional view of three adjoining wall elements, two of which form a corner. As the wall elements come out of the formwork with exact dimensions and flat surfaces (except for the later lower end face) and have the quality of exposed concrete, they can be assembled precisely and consistently with virtually no gaps. Opposing grooves 20 define closed channels. Concrete 35 enters these channels when pouring the inter-story ceiling located at the bottom, and after hardening it forms the so-called a seal that provides a force connection between the wall elements in the horizontal direction.

181 551181 551

Fig.6Fig. 6

20twenty

181 551181 551

Fig. 5Fig. 5

181 551181 551

Fig.4 τ'Fig. 4 τ '

181 551181 551

Fig.3Fig.3

181 551181 551

Fig. 2Fig. 2

181 551181 551

Fig.1Fig.1

Departament Wydawnictw UP RP. Nakład 70 egz.Publishing Department of the UP RP. Circulation of 70 copies

Cena 4,00 zł.Price PLN 4.00.

Claims (5)

Zastrzeżenia patentowePatent claims 1. Sposób wznoszenia wysokich budynków z zastosowaniem prefabrykowanego elementu ściennego z zalewanym zbrojeniem i elementami instalacyjnymi, mającego wystające z dolnej i górnej powierzchni czołowej zbrojenie łączeniowe, na górnej powierzchni czołowej płaskie pasy brzegowe oraz elementy kotwiące dla uchwytu dźwigu, a w dolnej powierzchni czołowej rozmieszczone w odstępach od siebie elementy niwelacyjne o regulowanej długości i co najmniej jedną boczną powierzchnię czołową z wyprofilowanym rowkiem do zalewowego łączenia dwóch przyległych elementów ściennych, w którym elementy ścienne ustawia się dźwigiem jeden na drugim, i/lub jeden obok drugiego, łączy ich zbrojenie i zalewa połączenia betonem, znamienny tym, że po przeciwległych stronach każdego umieszczonego w położeniu montażu elementu ściennego (B) umieszcza się co najmniej jedno urządzenie regulacyjne (21, 22) do pionowego ustawiania i ustawia się ten element nad górną powierzchnią czołową elementu ściennego niższego piętra opuszczając go w szczelinę pomiędzy dwoma wspartymi na tej górnej powierzchni czołowej elementami stropowymi (30) niższego piętra, aż elementy niwelacyjne (15) dojdą do górnej powierzchni czołowej i tak osadzony element ścienny ustawia się w poziomie za pomocą jego elementów niwelacyjnych (15) oraz w pionie za pomocą urządzenia regulacyjnego (21, 22), a powstałą szczelinę pomiędzy dolną powierzchnią czołową ustawionego elementu ściennego i powierzchnią czołową elementu ściennego umieszczonego poniżej wypełnia się betonem (35) korzystnie stosując wibrację i po stwardnieniu betonu usuwa się urządzenie regulacyjne (21,22).1. The method of erecting tall buildings with the use of a prefabricated wall element with flooded reinforcement and installation elements, having joining reinforcement protruding from the lower and upper face, flat edge strips on the upper face and anchoring elements for the crane handle, and spaced at intervals in the lower face length-adjustable leveling elements from each other and at least one side face with a profiled groove for flood connection of two adjacent wall elements, in which the wall elements are placed one on top of the other by a crane and / or next to each other, they are joined by their reinforcement and the joints are poured with concrete , characterized in that on opposite sides of each wall element (B) placed in the mounting position at least one adjusting device (21, 22) for vertical alignment is provided and positioned above the upper face of the wall element of the lower story opus by connecting it into the gap between the two floor elements (30) of the lower floor, supported on this upper face, until the leveling elements (15) reach the upper face and the mounted wall element is aligned horizontally with its leveling elements (15) and vertically by means of the adjusting device (21, 22), and the resulting gap between the lower face of the aligned wall element and the end face of the wall element located below is filled with concrete (35), preferably by vibration, and after the concrete has hardened, the adjusting device (21, 22) is removed . 2. Urządzenie regulacyjne do wznoszenia wysokich budynków przy instalacji prefabrykowanych elementów ściennych z zalewanym zbrojeniem i elementami instalacyjnymi, mających wystające z dolnej i górnej powierzchni czołowej zbrojenie łączeniowe, na górnej powierzchni czołowej płaskie pasy brzegowe oraz elementy kotwiące dla uchwytu dźwigu, a w dolnej powierzchni czołowej rozmieszczone w odstępach od siebie elementy niwelacyjne o regulowanej długości i co najmniej jedną boczną powierzchnię czołową z wyprofilowanym rowkiem do zalewowego łączenia dwóch przyległych elementów ściennych, znamienne tym, że ma w przybliżeniu kształt litery L, przy czym długie ramię (21a, 21b) urządzenia regulacyjnego (21, 22) ma przy jednym końcu odchodzące pod kątem prostym krótkie ramię (21d) na którego wolnym końcu jest umieszczona przestawna w pionie noga.2. Regulating device for erecting high-rise buildings with the installation of prefabricated wall elements with flooded reinforcement and installation elements, with joining reinforcement protruding from the lower and upper face, flat edge strips on the upper face and anchoring elements for the crane handle, and arranged in the lower face spaced apart leveling elements with adjustable length and at least one lateral face with a profiled groove for connecting two adjacent wall elements by flooding, characterized in that it is approximately L-shaped, the long arm (21a, 21b) of the adjustment device ( 21, 22) has at one end a right-angled short arm (21d) at the free end of which is arranged a vertically adjustable leg. 3. Urządzenie regulacyjne według zastrz. 2, znamienne tym, że dwa długie ramiona (21a, 21b) są połączone ze sobą z przeciwległych stron elementu ściennego (B) ponad jego górną krawędzią i korzystnie z dolną krawędzią tego elementu.3. The adjustment device according to claim 1 A device according to claim 2, characterized in that the two long arms (21a, 21b) are connected to each other on opposite sides of the wall element (B) above its upper edge and preferably to the lower edge of the wall element. 4. Urządzenie regulacyjne według zastrz. 2, znamienne tym, że przestawna w pionie noga ma gwintowany trzpień (25), który jest połączony gwintem z krótkim ramieniem (21d) i zakończony stożkową wsporczą stopą (26).4. The adjustment device according to claim 1 The leg as claimed in claim 2, characterized in that the vertically adjustable leg has a threaded spindle (25) which is threadedly connected to the short arm (21d) and terminated in a conical support foot (26). 5. Urządzenie regulacyjne według zastrz. 2, znamienne tym, że krótkie ramię (21d) jest wsparte na długim ramieniu (21b) poprzez ukośnąpoprzeczkę (21e).The regulating device according to claim 1 A device according to claim 2, characterized in that the short arm (21d) is supported on the long arm (21b) by an oblique crossbar (21e).
PL96343311A 1995-06-30 1996-06-27 Method of erecting high buildings and adjusting device for use in that method PL181551B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19523997 1995-06-30

Publications (1)

Publication Number Publication Date
PL181551B1 true PL181551B1 (en) 2001-08-31

Family

ID=7765762

Family Applications (2)

Application Number Title Priority Date Filing Date
PL96343311A PL181551B1 (en) 1995-06-30 1996-06-27 Method of erecting high buildings and adjusting device for use in that method
PL96314995A PL181672B1 (en) 1995-06-30 1996-06-27 Wall unit for high buildings and method of making same

Family Applications After (1)

Application Number Title Priority Date Filing Date
PL96314995A PL181672B1 (en) 1995-06-30 1996-06-27 Wall unit for high buildings and method of making same

Country Status (6)

Country Link
EP (1) EP0751262B1 (en)
AT (1) ATE257879T1 (en)
CZ (2) CZ294093B6 (en)
DE (1) DE59610890D1 (en)
DK (1) DK0751262T3 (en)
PL (2) PL181551B1 (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU8091598A (en) * 1998-07-03 2000-01-24 Christian Koppensteiner Building element
EP1046758A1 (en) * 1999-04-19 2000-10-25 Rolf Bless Construction method of a slab and a wall-shuttering , prefabricated shuttering element
AU2003260522A1 (en) * 2003-08-20 2005-03-10 Incoribe, S.L. Building construction system
US20090165408A1 (en) * 2004-06-15 2009-07-02 Norman Gordon Pask Construction elements and methods of construction
NL2001814C2 (en) * 2008-07-16 2010-01-22 1 2 3 Huis B V Housing element manufacturing method for building i.e. apartment complex, involves extending vertical wall section from floor section to outside, and forming housing element with vertical and horizontal wall sections and floor section
CN104060819B (en) * 2013-03-19 2016-05-04 中建四局第三建筑工程有限公司 Utilize the method for typified form construction shear wall and typified form used
CN105133829B (en) * 2015-09-18 2018-03-23 深圳市创兴建设股份有限公司 Grouting wallboard formwork and the method constructed using the formwork
CN110219459A (en) * 2019-06-19 2019-09-10 银广厦集团有限公司 A kind of Multicarity thin-walled steel plate concrete combined shear wall construction method
CN115492381B (en) * 2021-06-17 2024-01-26 中核华辰建筑工程有限公司 Elastic leakage-proof structure of aluminum alloy template
CN113622562B (en) * 2021-08-19 2022-02-18 阜阳市水利建筑安装工程公司 House building engineering adds stationary form
CN115506534B (en) * 2022-09-30 2023-09-19 青岛嘉枫城市建设有限公司 Shear wall structure and building

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2914920A1 (en) * 1978-04-19 1979-10-31 Kurt Ing Beranek Light concrete prefabricated wall section - has horizontal reinforcing bars and protruding top batten of ceiling thickness (OE 15.7.79)
PT70931B (en) * 1980-03-11 1981-07-01 Helio Guiod De Castro BUILDING CONSTRUCTION SYSTEM
DE3228342A1 (en) * 1982-07-29 1984-02-09 Friedrich 7250 Leonberg Eger Method for constructing buildings and prefabricated building parts for carrying out the method
DE3302821A1 (en) * 1983-01-28 1984-08-02 Klaus Dipl.-Ing. 8000 München Dahm Concrete shuttering
GB2207688A (en) * 1986-08-14 1989-02-08 Unan Pty Ltd Modular building system
US4996770B1 (en) * 1990-01-05 1997-05-06 Wilian Holding Co Method of assembling a concrete form brace
DE4332793C1 (en) * 1993-09-27 1995-01-12 Eberhard Schrade Process for producing structures, and prefabricated module

Also Published As

Publication number Publication date
CZ190096A3 (en) 1997-03-12
CZ290537B6 (en) 2002-08-14
EP0751262A1 (en) 1997-01-02
DK0751262T3 (en) 2004-05-17
DE59610890D1 (en) 2004-02-19
CZ294093B6 (en) 2004-10-13
PL181672B1 (en) 2001-08-31
ATE257879T1 (en) 2004-01-15
PL314995A1 (en) 1997-01-06
EP0751262B1 (en) 2004-01-14

Similar Documents

Publication Publication Date Title
US7958687B2 (en) Concrete panel construction system
US8490363B2 (en) Modular concrete building
US6223480B1 (en) Pre-cast concrete panels for construction of a building
EP0055504B1 (en) Method and structural element for erecting a building and building thus formed
EP0208529A1 (en) Reinforced-concrete building structures
EA010805B1 (en) Insulated concrete form system with variable length wall ties
US9399867B2 (en) Concrete panel corner connection
US3678638A (en) Building construction of modular units with settable material therebetween
EP1007799B1 (en) Building panel for use in the construction of buildings
WO2018067067A1 (en) Prefabricated prefinished volumetric construction module
PL181551B1 (en) Method of erecting high buildings and adjusting device for use in that method
US5950396A (en) Method and apparatus for producing and erecting precast concrete walls using sawing
WO1992010623A2 (en) Improvements in or relating to accommodation modules
RU2459913C2 (en) Set of leave-in-place form by vv podsevalov
GB2428434A (en) Modular floor units
EP3828364A1 (en) Assembly kit and method for assembling a safety railing, as well as such a safety railing
EP2022905A1 (en) Device for partitioning and closures of vertical type
CA2311222C (en) Concrete panel construction system
JP2786412B2 (en) Exterior panel covering structure of concrete building and covering construction method
AU2004203867B2 (en) A building system
EP1185748B1 (en) Concrete panel construction system
KR200147067Y1 (en) Inside and outside wall setting-up device
EP3935234A1 (en) Permanent formwork, building structure and method for creating the building structure
KR930000808B1 (en) Construction method of a high-rise by slide form
FI13466Y1 (en) Joint solution

Legal Events

Date Code Title Description
LAPS Decisions on the lapse of the protection rights

Effective date: 20080627