KR20230140196A - Building Slab Structure with Gravelly Layer and Construction Method thereof - Google Patents

Building Slab Structure with Gravelly Layer and Construction Method thereof Download PDF

Info

Publication number
KR20230140196A
KR20230140196A KR1020220039054A KR20220039054A KR20230140196A KR 20230140196 A KR20230140196 A KR 20230140196A KR 1020220039054 A KR1020220039054 A KR 1020220039054A KR 20220039054 A KR20220039054 A KR 20220039054A KR 20230140196 A KR20230140196 A KR 20230140196A
Authority
KR
South Korea
Prior art keywords
layer
gravel
hot water
concrete
concrete layer
Prior art date
Application number
KR1020220039054A
Other languages
Korean (ko)
Other versions
KR102669744B1 (en
Inventor
박정웅
Original Assignee
박정웅
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박정웅 filed Critical 박정웅
Priority to KR1020220039054A priority Critical patent/KR102669744B1/en
Publication of KR20230140196A publication Critical patent/KR20230140196A/en
Application granted granted Critical
Publication of KR102669744B1 publication Critical patent/KR102669744B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/18Separately-laid insulating layers; Other additional insulating measures; Floating floors
    • E04F15/20Separately-laid insulating layers; Other additional insulating measures; Floating floors for sound insulation
    • E04F15/203Separately-laid layers for sound insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/02Specially adapted covering, lining or flooring elements not otherwise provided for for accommodating service installations or utility lines, e.g. heating conduits, electrical lines, lighting devices or service outlets
    • E04F2290/023Specially adapted covering, lining or flooring elements not otherwise provided for for accommodating service installations or utility lines, e.g. heating conduits, electrical lines, lighting devices or service outlets for heating
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/04Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire
    • E04F2290/041Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire against noise
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/04Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire
    • E04F2290/044Specially adapted covering, lining or flooring elements not otherwise provided for for insulation or surface protection, e.g. against noise, impact or fire against impact

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

본 발명은 온수파이프의 열기가 자갈층의 자갈로 전도되도록 하여 에너지를 절감할 수 있도록 하는 자갈층을 갖는 건축물용 슬라브 구조체 및 그 시공 방법에 관한 것이다. 본 발명은 온수파이프에 온수가 공급되면, 온수파이프와 접촉된 자갈층의 자갈로 열이 전도되므로, 바닥 난방 보온이 장시간 유지될 수 있고, 한국의 온돌 전통방식인 구들장 역할을 하고, 에너지 절감에 효율적인 효과가 있다. 또한, 콘크리트층에 온수파이프를 시공한 후 자갈을 포설하여 자갈층을 형성한 후 바닥층을 시공하면, 바닥층의 상부에 충격이 가해진다 하더라도 자갈층에서 1차 완충 역할을 하므로, 주거시설의 경우, 층간소음이 절반으로 감소되고, 아래층에 전달되는 충격이나 음향을 현저하게 감소시킬 수 있는 효과가 있다.The present invention relates to a slab structure for a building with a gravel layer that allows heat from a hot water pipe to be conducted to the gravel in the gravel layer, thereby saving energy, and to a method of constructing the same. In the present invention, when hot water is supplied to the hot water pipe, heat is conducted to the gravel of the gravel layer in contact with the hot water pipe, so floor heating can be maintained for a long time, serves as a gudeuljang, a traditional Korean ondol method, and is efficient for energy saving. It works. In addition, if a hot water pipe is constructed on a concrete layer and then gravel is laid to form a gravel layer and then the bottom layer is constructed, even if an impact is applied to the upper part of the bottom layer, the gravel layer acts as a primary buffer, so in the case of residential facilities, inter-floor noise This is reduced by half, and has the effect of significantly reducing shock or sound transmitted to the lower floor.

Description

자갈층을 갖는 건축물용 슬라브 구조체 및 그 시공 방법{Building Slab Structure with Gravelly Layer and Construction Method thereof}Building slab structure with gravel layer and construction method thereof {Building Slab Structure with Gravelly Layer and Construction Method there}

본 발명은 자갈층을 갖는 건축물용 슬라브 구조체 및 그 시공 방법에 관한 것으로, 보다 상세하게는 온수파이프의 열기가 자갈층의 자갈로 전도되도록 하여 에너지를 절감할 수 있도록 하는 자갈층을 갖는 건축물용 슬라브 구조체 및 그 시공 방법에 관한 것이다.The present invention relates to a building slab structure having a gravel layer and a construction method thereof. More specifically, to a building slab structure having a gravel layer that allows heat from a hot water pipe to be conducted to the gravel in the gravel layer to save energy, and to a building slab structure having a gravel layer and its construction method. It's about construction methods.

일반적으로 주택 등의 건축물에는 고온의 온수가 슬라브에 설치되는 온수파이프를 경유 및 순환되도록 하여 건물 내부를 난방하는 온수 난방 시스템이 적용되어 있다. 온수 난방 시스템은 우리나라 고유의 온돌 방식을 차용한 것으로, 세계적으로도 거의 예가 없는 독특한 형식을 취하고 있다.In general, buildings such as houses are equipped with a hot water heating system that heats the inside of the building by circulating high temperature hot water through hot water pipes installed on the slab. The hot water heating system is adapted from Korea's unique Ondol method and has a unique form that is rarely seen in the world.

온수 난방 시스템의 구조를 살펴보면, 슬라브 역할을 하는 콘크리트층의 상부에 난방용 온수피프가 시공되고, 난방용 온수파이프가 시공되면, 시멘트재의 몰탈 마감층을 타설하여 미장 처리하도록 구성된다. 그리고 온수파이프에서 발산하는 열은 마감층에 축열되어 복사 난방이 진행된다. Looking at the structure of the hot water heating system, hot water pipes for heating are constructed on the upper part of the concrete layer that acts as a slab, and when the hot water pipes for heating are constructed, a mortar finish layer of cement is poured and plastered. And the heat emitted from the hot water pipes is stored in the finishing layer and radiant heating occurs.

이러한 마감층의 축열 성능은 콘크리트 자체의 열용량에 크게 의존하는데, 마감층의 크기와 형태는 구조적 안정성을 확보하는 차원에서 물리적 치수가 결정되므로, 임의로 축열 용량을 증대시키기에는 제약이 있게 된다. 따라서 온수파이프에서 발산하는 열이 마감층에 오랫동안 축열되지 않아, 난방 효율이 떨어지는 문제점이 있다.The heat storage performance of this finishing layer is largely dependent on the heat capacity of the concrete itself. Since the size and shape of the finishing layer are determined by physical dimensions to ensure structural stability, there are restrictions on arbitrarily increasing the heat storage capacity. Therefore, there is a problem in that the heat emitted from the hot water pipe is not stored in the finishing layer for a long time, resulting in low heating efficiency.

한편, 우리나라는 급격한 산업화로 인한 도시화 및 핵가족화 등이 급속하게 진행됨에 따라 1980년대 말부터 공동주택이 본격적으로 보급되었고, 현재는 국민 3명 중 2명이 공동주택에서 거주하고 있다. 얇은 벽과 바닥을 사이에 두고 생활하는 공동주택의 특성상 층간 소음은 당연히 발생할 수밖에 없는 것으로 인식되고 있다.Meanwhile, in Korea, as urbanization and nuclear families have progressed rapidly due to rapid industrialization, apartment complexes have been popularized in earnest since the late 1980s, and currently, two out of three citizens live in apartment complexes. Due to the nature of apartment complexes where people live with thin walls and floors in between, it is recognized that noise between floors is inevitable.

층간 소음은 건설 현장에서 적당히 가수하고 타설된 후 표면 고르기를 하여 양생된 슬라브 바닥일 경우 더욱 심해진다. 이러한 슬라브의 경우 적당한 충격에도 콘크리트 내부의 물 빠짐에 의한 미세한 공간에서 공진(共振) 현상이 발생하여 북소리 비슷한 소리(울림)가 발생할 수 있으며, 위층에서 바닥 충격 시 울림 현상이 발생하여 층간 소음이 증폭된다.The noise between floors becomes even worse if the floor is a slab that has been properly watered and poured at a construction site, then leveled the surface and cured it. In the case of these slabs, even with a moderate impact, a resonance phenomenon may occur in a small space due to water draining inside the concrete, resulting in a drum-like sound (ringing). In the case of floor impact on the upper floor, a ringing phenomenon may occur, amplifying the noise between floors. do.

이러한 층간소음은 공동 주거 형태를 이루는 빌라나 아파트와 같은 주거환경에서 주거환경을 해치는 가장 높은 문제점으로 인식되는 것으로, 특히, 신경쇠약 환자나 사회생활에 갑작스러운 스트레스 혹은 불면증을 가지고 있는 사람에게는 치명적인 요인이 될 수 있다. 층간소음으로 인해 이웃과 갈등 문제가 생기면 해결책을 찾기 힘들어 항의하다가 진전이 보이지 않으면 회피하고 타 지역으로의 이주를 계획하거나, 이웃관계가 피해자와 가해자 관계로 이어지는 안타까운 경우도 많이 발생한다.This noise between floors is recognized as the most damaging problem in residential environments such as villas or apartments that form communal housing. In particular, it is a fatal factor for patients with nervous breakdowns, sudden stress in social life, or insomnia. This can be. When there is a conflict with neighbors due to noise between floors, it is difficult to find a solution, so people protest, but when no progress is made, they avoid it and plan to move to another area, or there are many unfortunate cases where the relationship between neighbors leads to a relationship between victims and perpetrators.

층간소음을 해결하기 위한 기술적인 접근으로서, 건축물 요소의 성능을 높이는 방법이 있다. 예를 들면 깊이 210m/m의 슬라브 콘크리트 타설일 경우 물 빠짐 현상이나 양생 과정의 수축현상을 감안하여 타설 깊이가 5%~10% 정도 증가되도록 타설하여 양생 후의 슬라브 깊이(슬럼프)가 시방서의 목표치에 접근하도록 하여야 한다.As a technical approach to solving inter-floor noise, there is a way to increase the performance of building elements. For example, in the case of slab concrete pouring with a depth of 210m/m, the pouring depth is increased by about 5% to 10% to account for water drainage or shrinkage during the curing process, so that the slab depth (slump) after curing is within the target value in the specifications. must be accessible.

국내공개특허공보 제10-2018-0029335호Domestic Patent Publication No. 10-2018-0029335

상기와 같은 종래기술의 문제점을 해결하기 위한 본 발명의 목적은 온수파이프의 열기가 자갈층의 자갈에 축열되도록 하여 난방 효율을 극대화 하고, 에너지를 절감할 수 있도록 하는 자갈층을 갖는 건축물용 슬라브 구조체 및 그 시공 방법을 제공하는 것이다.The purpose of the present invention to solve the problems of the prior art as described above is to provide a slab structure for buildings with a gravel layer that maximizes heating efficiency and saves energy by allowing the heat of the hot water pipe to accumulate in the gravel of the gravel layer, and the same. It provides construction methods.

또한, 본 발명의 다른 목적은 슬라브의 두께를 두껍게 형성하지 않고서도 층간 소음을 현저하게 저감시킬 수 있도록 하는 자갈층을 갖는 건축물용 슬라브 구조체 및 그 시공 방법을 제공하는 것이다.In addition, another object of the present invention is to provide a slab structure for a building with a gravel layer that can significantly reduce inter-floor noise without increasing the thickness of the slab, and a method of constructing the same.

상기 목적을 달성하기 위하여 본 발명은 건축물용 슬라브 구조체에 있어서, 콘크리트 재료를 배합하여 시공되는 콘크리트층; 상기 콘크리트층의 상부에 지그재그 형태로 설치되는 온수파이프; 상기 온수파이프가 설치된 상기 콘크리트층의 상부에 자갈을 포설하여 형성되는 자갈층; 및 상기 자갈층의 상부에 시공되는 바닥층을 포함하여 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체를 제공한다.In order to achieve the above object, the present invention provides a slab structure for buildings, including a concrete layer constructed by mixing concrete materials; A hot water pipe installed in a zigzag shape on top of the concrete layer; A gravel layer formed by placing gravel on the upper part of the concrete layer where the hot water pipe is installed; and a bottom layer constructed on top of the gravel layer. It provides a slab structure for buildings having a gravel layer.

또한, 상기 자갈의 직경은 25mm 내지 40mm 인 것으로 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체를 제공한다.In addition, a slab structure for buildings having a gravel layer is provided, wherein the gravel has a diameter of 25 mm to 40 mm.

또한, 상기 콘크리트층과 상기 온수파이프 사이에 와이어매쉬가 설치되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체를 제공한다.In addition, it provides a slab structure for buildings having a gravel layer, characterized in that a wire mesh is installed between the concrete layer and the hot water pipe.

또한, 상기 온수파이프에 온수가 공급되면 온수의 열 에너지가 상기 온수파이프와 맞닿은 자갈로 전도되도록 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체를 제공한다.In addition, it provides a slab structure for buildings having a gravel layer, wherein when hot water is supplied to the hot water pipe, the heat energy of the hot water is conducted to gravel in contact with the hot water pipe.

또한, 본 발명은 건축물용 슬라브 구조체의 시공 방법에 있어서, 콘크리트 재료를 배합하여 콘크리트층을 시공하는 콘크리트층 시공 과정; 상기 콘크리트층의 상부에 온수파이프를 지그재그 형태로 설치하는 온수파이프 설치 과정; 상기 온수파이프가 설치된 상기 콘크리트층의 상부에 자갈을 포설하여 자갈층을 시공하는 자갈층 시공 과정; 및 상기 자갈층의 상부에 바닥층을 시공하는 바닥층 시공 과정을 포함하여 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 제공한다.In addition, the present invention relates to a method of constructing a slab structure for a building, including a concrete layer construction process of mixing concrete materials to construct a concrete layer; A hot water pipe installation process of installing hot water pipes in a zigzag shape on the upper part of the concrete layer; A gravel layer construction process of constructing a gravel layer by laying gravel on the upper part of the concrete layer where the hot water pipe is installed; and a bottom layer construction process of constructing a bottom layer on top of the gravel layer. It provides a construction method of a slab structure for a building having a gravel layer.

또한, 상기 자갈층 시공 과정에서, 상기 자갈의 직경은 25mm 내지 40mm 인 것으로 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 제공한다.In addition, in the process of constructing the gravel layer, a method of constructing a slab structure for a building having a gravel layer is provided, wherein the diameter of the gravel is 25 mm to 40 mm.

또한, 상기 콘크리트층 시공 과정과 상기 온수파이프 설치 과정 사이에, 상기 콘크리트층의 상부에 와이어매쉬를 설치하는 와이어매쉬 설치 과정을 더 포함하고, 상기 온수파이프 설치 과정에서, 상기 와이어매쉬의 상부에 온수파이프를 설치하는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 제공한다.In addition, between the concrete layer construction process and the hot water pipe installation process, it further includes a wire mesh installation process of installing a wire mesh on the upper part of the concrete layer, and in the hot water pipe installation process, hot water is installed on the upper part of the wire mesh. Provides a method of constructing a slab structure for a building with a gravel layer, characterized by installing pipes.

또한, 상기 콘크리트층 시공 과정은: 콘크리트 재료를 배합하여 혼합하는 혼합단계: 혼합한 콘크리트를 시공 위치에 타설하여 콘크리트층을 형성하는 타설단계; 바이브레이터를 이용하여 콘크리트층에 진동을 부여하는 진동단계; 및 콘크리트층을 양생시키는 양생단계를 포함하여 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 제공한다.In addition, the concrete layer construction process includes: a mixing step of mixing and mixing concrete materials; a pouring step of pouring the mixed concrete at the construction location to form a concrete layer; A vibration step of applying vibration to the concrete layer using a vibrator; and a curing step of curing the concrete layer. It provides a method of constructing a slab structure for a building having a gravel layer.

본 발명은 온수파이프에 온수가 공급되면, 온수파이프에서 발산하는 열이 온수파이프와 접촉된 자갈층의 자갈에 오랫동안 축열되므로, 바닥 난방 보온이 장시간 유지될 수 있어 난방 효율이 향상되고, 에너지를 절감할 수 있는 효과가 있다.In the present invention, when hot water is supplied to the hot water pipe, the heat emitted from the hot water pipe is stored in the gravel of the gravel layer in contact with the hot water pipe for a long time, so floor heating can be maintained for a long time, improving heating efficiency and saving energy. There is a possible effect.

또한, 콘크리트층에 온수파이프를 시공한 후 자갈을 포설하여 자갈층을 형성한 후 바닥층을 시공하면, 바닥층의 상부에 충격이 가해진다 하더라도 자갈층에서 1차 완충 역할을 하므로, 주거시설의 경우, 층간소음이 절반으로 감소되고, 아래층에 전달되는 충격이나 음향을 현저하게 감소시킬 수 있는 효과가 있다.In addition, if a hot water pipe is constructed on a concrete layer and then gravel is laid to form a gravel layer and then the bottom layer is constructed, even if an impact is applied to the upper part of the bottom layer, the gravel layer acts as a primary buffer, so in the case of residential facilities, inter-floor noise This is reduced by half, and has the effect of significantly reducing shock or sound transmitted to the lower floor.

또한, 콘크리트가 타설되어 형성된 콘크리트층에 바이브레이터를 이용하여 진동을 가해주도록 구성되므로 콘크리트층 내부에 수포현상(물주머니) 및 공기층이 생성되지 않아 콘크리트층의 밀도가 높아지고 이로 인하여 공기층에 의한 공진 현상이 발생되지 않아 층간 소음이 발생되지 않는 효과가 있다. In addition, since it is configured to apply vibration using a vibrator to the concrete layer formed by pouring the concrete, blisters (water pockets) and air layers are not created inside the concrete layer, increasing the density of the concrete layer and causing resonance due to the air layer. This has the effect of preventing inter-floor noise from being generated.

또한, 바이브레이터를 통하여 철근에 진동을 가하게 되면 철근을 통하여 타설된 콘크리트의 전 지역으로 고르게 진동이 전달되므로, 콘크리트층 내부에 공기층이 생성되지 않아 콘크리트층의 밀도가 더욱 높아져서 층간 소음이 발생되지 않는 효과가 있다.In addition, when vibration is applied to the rebar through a vibrator, the vibration is transmitted evenly through the rebar to the entire area of the poured concrete, so an air layer is not created inside the concrete layer, which further increases the density of the concrete layer and prevents noise between layers. There is.

또한, 바이브레이터를 이용하여 콘크리트층에 형성되는 각각의 단위 면적 별로 진동을 부여하도록 구성되므로, 콘크리트층의 전 지역으로 고르게 진동을 가해줄 수 있어, 콘크리트층의 밀도가 고르게 높아지는 효과가 있다.In addition, since it is configured to apply vibration to each unit area formed in the concrete layer using a vibrator, vibration can be applied evenly to the entire area of the concrete layer, which has the effect of evenly increasing the density of the concrete layer.

또한, 바이브레이터가 콘크리트층에 삽입된 상태로 이동되면 바이브레이터를 신속하게 이동시킬 수 있으므로, 빠른 속도로 콘크리트층에 진동을 가해줄 수 있는 효과가 있다.In addition, when the vibrator is moved while inserted into the concrete layer, the vibrator can be moved quickly, which has the effect of applying vibration to the concrete layer at a high speed.

또한, 콘크리트층의 두께가 목표치를 초과하도록 콘크리트를 타설하므로, 양생 과정에서 물빠짐이 발생된다 하더라도, 슬라브의 두께가 목표치에 근접하도록 시공되는 효과가 있다.In addition, since the concrete is poured so that the thickness of the concrete layer exceeds the target value, even if water drainage occurs during the curing process, there is an effect of constructing the slab so that the thickness is close to the target value.

또한, 슬라브의 두께를 필요 이상으로 두껍게 형성하지 않아도 되므로, 층간 소음을 해결하기 위하여 층고를 높일 필요가 없고, 공사 비용을 증가시키지 않는 효과가 있다.In addition, since the thickness of the slab does not need to be thicker than necessary, there is no need to increase the floor height to solve inter-floor noise, and there is an effect of not increasing construction costs.

도 1은 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 개략적으로 도시한 도면이다.
도 2는 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법의 콘크리트층 시공 과정을 개략적으로 도시한 도면이다.
도 3 내지 도 6은 본 발명의 바람직한 실시예에 따른 콘크리트층 시공 과정의 진동 단계를 설명하기 위한 다양한 예시를 개략적으로 도시한 도면이다.
도 7은 본 발명의 바람직한 실시예에 따른 콘크리트층 시공 과정의 정지단계를 설명하기 위하여 개략적으로 도시한 도면이다.
도 8은 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법에 의하여 시공된 자갈층을 갖는 건축물용 슬라브 구조체를 개략적으로 도시한 도면이다.
도 9는 본 발명의 바람직한 실시예에 따른 표본틀을 도시한 도면이다.
도 10은 본 발명의 바람직한 실시예에 따른 표본틀에 콘크리트를 타설하는 상태를 도시한 도면이다.
도 11은 본 발명의 바람직한 실시예에 따른 표본틀에 콘크리트가 타설되어 콘크리트층이 형성된 상태를 도시한 도면이다.
도 12는 본 발명의 바람직한 실시예에 따른 표본틀에 형성된 콘크리트층에 진동을 부여하는 작업을 도시한 도면이다.
도 13은 본 발명의 바람직한 실시예에 따른 진동이 가해진 콘크리트층의 표면을 평탄화 처리한 상태를 도시한 도면이다.
도 14는 본 발명의 바람직한 실시예에 따른 시공이 완료된 슬라브를 도시한 도면이다.
도 15는 본 발명의 바람직한 실시예에 따른 시공이 완료된 슬라브의 옆면을 도시한 도면이다.
도 16은 본 발명의 슬라브와 비교하기 위한 비교 슬라브를 시공하기 위한 표본틀을 도시한 도면이다.
도 17은 본 발명의 슬라브와 비교하기 위한 비교 슬라브를 도시한 도면이다.
도 18은 본 발명의 슬라브와 비교하기 위한 비교 슬라브의 옆면을 도시한 도면이다.
도 19 및 도 20은 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법에 의하여 시공한 슬라브에 가해지는 소음을 서로 다른 스마트폰을 이용하여 측정한 결과를 도시한 도면이다.
도 21 및 도 22는 본 발명의 슬라브와 비교하기 위한 비교 슬라브에 가해지는 소음을 서로 다른 스마트폰을 이용하여 측정한 결과를 도시한 도면이다.
Figure 1 is a diagram schematically showing a method of constructing a slab structure for a building with a gravel layer according to a preferred embodiment of the present invention.
Figure 2 is a diagram schematically showing the concrete layer construction process of the construction method of a slab structure for a building with a gravel layer according to a preferred embodiment of the present invention.
3 to 6 are diagrams schematically showing various examples for explaining the vibration stage of the concrete layer construction process according to a preferred embodiment of the present invention.
Figure 7 is a diagram schematically showing the stopping stage of the concrete layer construction process according to a preferred embodiment of the present invention.
Figure 8 is a diagram schematically showing a slab structure for a building with a gravel layer constructed by the method of constructing a slab structure for a building with a gravel layer according to a preferred embodiment of the present invention.
Figure 9 is a diagram showing a sampling frame according to a preferred embodiment of the present invention.
Figure 10 is a diagram showing the state of pouring concrete into a specimen frame according to a preferred embodiment of the present invention.
Figure 11 is a diagram showing a state in which concrete is poured into a specimen frame according to a preferred embodiment of the present invention to form a concrete layer.
Figure 12 is a diagram showing the operation of applying vibration to a concrete layer formed in a specimen frame according to a preferred embodiment of the present invention.
Figure 13 is a diagram showing a state in which the surface of a concrete layer subjected to vibration has been flattened according to a preferred embodiment of the present invention.
Figure 14 is a diagram showing a slab on which construction has been completed according to a preferred embodiment of the present invention.
Figure 15 is a view showing the side of a slab on which construction has been completed according to a preferred embodiment of the present invention.
Figure 16 is a diagram showing a sample frame for constructing a comparative slab for comparison with the slab of the present invention.
Figure 17 is a diagram showing a comparative slab for comparison with the slab of the present invention.
Figure 18 is a view showing a side view of a comparative slab for comparison with the slab of the present invention.
Figures 19 and 20 are diagrams showing the results of measuring noise applied to a slab constructed by the construction method of a building slab structure with a gravel layer according to a preferred embodiment of the present invention using different smartphones.
Figures 21 and 22 are diagrams showing the results of measuring noise applied to a comparison slab for comparison with the slab of the present invention using different smartphones.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 더욱 상세히 설명한다.Hereinafter, the construction method of a slab structure for a building with a gravel layer according to a preferred embodiment of the present invention will be described in more detail with reference to the attached drawings.

도 1은 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법을 개략적으로 도시한 도면이다.Figure 1 is a diagram schematically showing a method of constructing a slab structure for a building with a gravel layer according to a preferred embodiment of the present invention.

도 1을 참조하면, 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법은 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법에 있어서, 콘크리트 재료를 배합하여 콘크리트층을 시공하는 콘크리트층 시공 과정(S100), 상기 콘크리트층의 상부에 와이어매쉬를 설치하는 와이어매쉬 설치 과정(S200), 상기 콘크리트층의 상부에 설치되는 와이어매쉬의 상부에 온수파이프를 지그재그 형태로 설치하는 온수파이프 설치 과정(S300), 온수파이프가 설치된 상기 콘크리트층의 상부에 자갈을 포설하여 자갈층을 시공하는 자갈층 시공 과정(S400) 및 상기 자갈층의 상부에 바닥층을 시공하는 바닥층 시공 과정(S500)을 포함한다. 이하, 도면을 참조하여 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법에 대하여 세부적으로 설명하기로 한다.Referring to Figure 1, the method of constructing a slab structure for a building having a gravel layer according to a preferred embodiment of the present invention is a method of constructing a slab structure for a building having a gravel layer, wherein the concrete layer is constructed by mixing concrete materials. Construction process (S100), wire mesh installation process (S200) of installing a wire mesh on the upper part of the concrete layer, hot water pipe installation process of installing a hot water pipe in a zigzag shape on the upper part of the wire mesh installed on the upper part of the concrete layer (S300), a gravel layer construction process (S400) of constructing a gravel layer by laying gravel on top of the concrete layer where the hot water pipe is installed, and a bottom layer construction process (S500) of constructing a bottom layer on top of the gravel layer. Hereinafter, the construction method of a building slab structure with a gravel layer will be described in detail with reference to the drawings.

도 2는 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법의 콘크리트층 시공 과정을 개략적으로 도시한 도면이고, 도 3 내지 도 6은 본 발명의 바람직한 실시예에 따른 콘크리트층 시공 과정의 진동 단계를 설명하기 위한 다양한 예시를 개략적으로 도시한 도면이며, 도 7은 본 발명의 바람직한 실시예에 따른 콘크리트층 시공 과정의 정지단계를 설명하기 위하여 개략적으로 도시한 도면이다.Figure 2 is a diagram schematically showing the concrete layer construction process of the construction method of a building slab structure with a gravel layer according to a preferred embodiment of the present invention, and Figures 3 to 6 are concrete layers according to a preferred embodiment of the present invention. This is a diagram schematically showing various examples for explaining the vibration stage of the construction process, and Figure 7 is a diagram schematically showing the stopping stage of the concrete layer construction process according to a preferred embodiment of the present invention.

도 2을 참조하면, 콘크리트층 시공 과정은(S100), 콘크리트 재료를 배합하여 혼합하는 혼합 단계(S110), 혼합한 콘크리트를 시공 위치에 타설하여 콘크리트층(100)을 형성하는 타설 단계(S120), 바이브레이터(10)를 이용하여 형성된 콘크리트층(100)에 진동을 부여하는 진동 단계(S130), 형성된 콘크리트층(100)의 표면을 평탄화 하는 정지 단계(S140) 및 형성된 콘크리트층(100)을 양생시키는 양생 단계(S150)를 포함한다.Referring to Figure 2, the concrete layer construction process (S100) includes a mixing step (S110) in which concrete materials are mixed and mixed, and a pouring step (S120) in which the mixed concrete is poured at the construction location to form the concrete layer 100. , a vibration step (S130) of applying vibration to the formed concrete layer 100 using the vibrator 10, a stopping step (S140) of flattening the surface of the formed concrete layer 100, and curing the formed concrete layer 100. It includes a curing step (S150).

혼합 단계(S110)Mixing step (S110)

콘크리트 재료를 혼합하여 콘크리트를 조성한다. 콘크리트 재료의 배합 비율은 시멘트 5 내지 15 중량부, 잔골재 15 내지 25 중량부, 굵은골재 35 내지 45 중량부 및 물 0.5 내지 5 중량부를 혼합하여 조성된다. 이러한 콘크리트 재료는 현장에서 믹서기를 이용하여 충분하게 혼합하는 것이 바람직하다. 콘크리트 재료의 배합 비율을 벗어나게 되면 시공성이 저하되는 문제가 있다.Concrete is created by mixing concrete materials. The mixing ratio of concrete materials is made by mixing 5 to 15 parts by weight of cement, 15 to 25 parts by weight of fine aggregate, 35 to 45 parts by weight of coarse aggregate, and 0.5 to 5 parts by weight of water. It is desirable to sufficiently mix these concrete materials on site using a mixer. If the mixing ratio of concrete materials is exceeded, there is a problem of deterioration of constructability.

타설 단계(S120)Pouring stage (S120)

혼합된 콘크리트는 시공위치에 타설되어 콘크리트층(100)을 형성한다. 시공위치라 함은 예를 들면 건축물용 슬라브 즉, 바닥, 천장 등을 시공하기 위한 건축물용 슬라브를 형성하기 위한 거푸집으로 구성될 수 있을 것이다. 여기서 시공위치에는 강도를 높이기 위하여 철근(110)이 미리 격자상으로 배근되어 있는 것이 바람직하다.The mixed concrete is poured at the construction location to form the concrete layer 100. The construction location may, for example, consist of a formwork for forming a building slab, that is, a building slab for constructing floors, ceilings, etc. Here, it is preferable that reinforcing bars 110 are previously arranged in a grid at the construction location to increase strength.

그리고 혼합된 콘크리트를 시공위치에 타설하여 콘크리트층(100)을 형성할 때, 콘크리트층(100)의 두께가 목표치의 5% 이상 초과하도록 콘크리트를 타설하여, 콘크리트의 물빠짐(배수, 背水) 현상을 대비하는 것이 바람직하다. 즉, 콘크리트층(100)은 양생 과정에서 물빠짐 현상이 발생되는데, 이는 슬라브의 두께를 목표치의 두께보다 얇아지도록 하여, 부실 시공의 원인이 된다. 본 발명은 이를 해결하기 위하여 타설 단계에서, 콘크리트층(100)의 두께가 목표치의 5% 이상 초과하도록 콘크리트를 타설하여, 양생 과정에서 물빠짐이 발생된다 하더라도, 슬라브의 두께가 목표치에 근접하도록 두껍게 시공한다. 이처럼 본 발명은 타설 단계에서, 콘크리트층(100)의 두께가 목표치를 초과하도록 콘크리트를 타설하므로, 양생 과정에서 물빠짐이 발생된다 하더라도, 슬라브의 두께가 목표치에 근접하도록 시공되는 효과가 있다.And, when pouring the mixed concrete at the construction location to form the concrete layer 100, the concrete is poured so that the thickness of the concrete layer 100 exceeds the target value by more than 5%, causing the phenomenon of concrete draining. It is advisable to prepare for. In other words, the concrete layer 100 experiences water loss during the curing process, which causes the thickness of the slab to become thinner than the target thickness, causing poor construction. In order to solve this problem, the present invention pours concrete so that the thickness of the concrete layer 100 exceeds the target value by more than 5% at the pouring stage, so that even if water drainage occurs during the curing process, the thickness of the slab is thick enough to be close to the target value. Construction. As such, in the present invention, in the pouring stage, concrete is poured so that the thickness of the concrete layer 100 exceeds the target value, so even if water drainage occurs during the curing process, there is an effect of constructing the slab so that the thickness is close to the target value.

진동 단계(S130)Oscillation stage (S130)

시공위치에 콘크리트층(100)이 형성되면, 형성된 콘크리트층(100)의 밀도를 높이기 위하여 진동을 가해준다. 이를 위하여 도 3와 같이, 바이브레이터(10: 도 12 참조)를 이용하여 시공 위치에 형성된 콘크리트층(100)에 진동을 직접 부여할 수 있다. 이때, 바이브레이터(10)는 철근(110)과 철근(110) 사이에 형성된 콘크리트층(100)에 진동을 주면서 다짐 작업을 하여, 콘크리트층(100) 내부에 수포에 의한 공기집이 생성되지 않도록 하고, 콘크리트층(100)의 밀도를 높이도록 한다. 바이브레이터(10)는 콘크리트층(100)에 깊숙하게 삽입할 수 있도록 길이방향을 따라 길게 형성되며 진동이 공급된다.When the concrete layer 100 is formed at the construction location, vibration is applied to increase the density of the formed concrete layer 100. For this purpose, as shown in FIG. 3, vibration can be directly applied to the concrete layer 100 formed at the construction location using a vibrator 10 (see FIG. 12). At this time, the vibrator 10 performs compaction while vibrating the concrete layer 100 formed between the reinforcing bars 110 and the reinforcing bars 110 to prevent air pockets due to blisters from being created inside the concrete layer 100. , to increase the density of the concrete layer 100. The vibrator 10 is formed long along the longitudinal direction so that it can be inserted deeply into the concrete layer 100, and vibration is supplied.

이처럼 본 발명은 형성된 콘크리트층(100)에 진동을 가해주도록 구성되므로 콘크리트층(100) 내부에 공기층이 생성되지 않아 콘크리트층(100)의 밀도가 높아진다. 이처럼 콘크리트층(100)의 밀도가 높아지면 공기층에 의한 공진 현상이 발생되지 않아 층간 소음이 발생되지 않는 효과가 있다. In this way, since the present invention is configured to apply vibration to the formed concrete layer 100, an air layer is not created inside the concrete layer 100, thereby increasing the density of the concrete layer 100. As the density of the concrete layer 100 increases, the resonance phenomenon caused by the air layer does not occur, which has the effect of preventing inter-floor noise.

또한, 도 4과 같이, 바이브레이터(10)를 이용하여 시공 위치에 배근된 철근(110)에 진동을 부여하여, 시공 위치에 형성된 콘크리트층(100)에 진동을 간접적으로 부여할 수도 있다. 이처럼 바이브레이터(10)를 이용하여 철근(110)에 진동을 가해주면 철근(110) 전체에 가해진 진동이 콘크리트층(100)으로 전달되어, 콘크리트층(100)은 음영 구간 없이 고르게 진동이 가해진다.Additionally, as shown in FIG. 4, vibration may be applied to the reinforcing bars 110 placed at the construction location using the vibrator 10, thereby indirectly providing vibration to the concrete layer 100 formed at the construction location. In this way, when vibration is applied to the reinforcing bar 110 using the vibrator 10, the vibration applied to the entire reinforcing bar 110 is transmitted to the concrete layer 100, and the concrete layer 100 is subjected to vibration evenly without any shaded areas.

이처럼 본 발명은 철근(110)을 통하여 형성된 콘크리트층(100)의 전 지역으로 고르게 진동을 가해주도록 구성되므로 콘크리트층(100) 내부에 공기층이 생성되지 않아 콘크리트층(100)의 밀도가 더욱 높아지는 효과가 있다. 이처럼 콘크리트층(100)의 밀도가 높아지면 공기층에 의한 공진 현상이 발생되지 않아 층간 소음이 발생되지 않는 효과가 있다.In this way, the present invention is configured to apply vibration evenly to the entire area of the concrete layer 100 formed through the reinforcing bars 110, so an air layer is not created inside the concrete layer 100, which has the effect of further increasing the density of the concrete layer 100. There is. As the density of the concrete layer 100 increases, the resonance phenomenon caused by the air layer does not occur, which has the effect of preventing inter-floor noise.

또한, 도 5와 같이, 진동 단계(S130)는 거푸집(M)에 형성된 콘크리트층(100)의 상면을 복수 개의 단위 면적(a)으로 설정한 이후, 각각의 단위 면적(a)에 해당하는 포인트(P)마다 바이브레이터(10)를 삽입시키도록 구성될 수도 있다. 각각의 단위 면적(a)에 해당하는 포인트(P)는 예를 들면 각각의 단위 면적(a)의 중앙에 위치될 수 있다. 그리고 작업자는 일 단위 면적(a)의 포인트(P)에 바이브레이터(10)를 삽입시켜서 일 단위 면적(a)에 진동을 부여한 후, 일 단위 면적(a)과 인접한 다른 단위 면적(a)의 포인트(P)로 바이브레이터(10)를 이동시켜서, 각각의 단위 면적(a)의 포인트(P) 별로 진동을 가하도록 구성될 수 있다.In addition, as shown in FIG. 5, the vibration step (S130) is performed by setting the upper surface of the concrete layer 100 formed in the form M to a plurality of unit areas (a), and then dividing the points corresponding to each unit area (a). It may be configured to insert the vibrator 10 for each (P). The point P corresponding to each unit area (a) may be located, for example, at the center of each unit area (a). Then, the worker inserts the vibrator 10 into the point P of the unit area a to give vibration to the unit area a, and then inserts the vibrator 10 into the point P of the unit area a, and then gives vibration to the point P of the unit area a. By moving the vibrator 10 to (P), it may be configured to apply vibration to each point (P) of each unit area (a).

이처럼 본 발명은 바이브레이터(10)를 이용하여 콘크리트층(100)에 형성되는 각각의 단위 면적(a) 별로 진동을 부여하도록 구성되므로, 콘크리트층(100)의 전 지역으로 고르게 진동을 가해줄 수 있어, 콘크리트층(100)의 밀도가 고르게 높아지는 효과가 있다.In this way, the present invention is configured to apply vibration to each unit area (a) formed in the concrete layer 100 using the vibrator 10, so that vibration can be applied evenly to the entire area of the concrete layer 100. , which has the effect of uniformly increasing the density of the concrete layer 100.

또한, 도 6와 같이, 진동 단계(S130)는 거푸집(M)에 형성된 콘크리트층(100)의 상면을 복수 개의 단위 면적(a)으로 설정한 이후, 복수 개의 단위 면적(a) 중 첫번째 단위 면적(a)에 바이브레이터(10)가 삽입된 상태로 마지막 단위 면적(a)까지 차례로 지나가도록 구성될 수도 있다. 예를 들면 첫번째 단위 면적(a)에 바이브레이터(10)가 삽입된 상태로 지그재그 형태(W)로 이동되면서 마지막 단위 면적(a)에 도달하는 것이다.In addition, as shown in FIG. 6, the vibration step (S130) is performed after setting the upper surface of the concrete layer 100 formed in the form M to a plurality of unit areas (a), and then the first unit area of the plurality of unit areas (a) It may be configured to pass sequentially up to the last unit area (a) with the vibrator 10 inserted in (a). For example, the vibrator 10 is inserted into the first unit area (a) and moves in a zigzag shape (W) to reach the last unit area (a).

이처럼 바이브레이터(10)가 콘크리트층(100)에 삽입된 상태로 이동되면 바이브레이터(10)를 신속하게 이동시킬 수 있으므로, 빠른 속도로 콘크리트층(100)에 진동을 가해줄 수 있는 효과가 있다.In this way, when the vibrator 10 is moved while inserted into the concrete layer 100, the vibrator 10 can be moved quickly, which has the effect of applying vibration to the concrete layer 100 at a high speed.

정지 단계(S140)Stop phase (S140)

진동 단계가 완료되면, 형성된 콘크리트층(100)의 울퉁불퉁한 표면을 고르게 평탄화 하여 바닥면이 매끄럽게 마무리 되도록 한다.When the vibration step is completed, the uneven surface of the formed concrete layer 100 is evenly flattened so that the floor surface is finished smoothly.

양생 단계(S150)Curing stage (S150)

정지 단계가 완료되면, 형성된 콘크리트층(100)을 25일 내지 35일 동안 양생시켜서 슬라브를 형성하는 작업이 진행된다. 그리고 형성된 콘크리트층(100)을 양생하는 도중 표면 건조를 방지하기 위하여 형성된 콘크리트층(100)의 표면에 물을 살포한다. 이때, 표면 건조를 방지하기 위하여 형성된 콘크리트층(100)의 표면에 물을 25일 내지 35일 동안 살포하되, 1일마다 1회 살포할 수 있다. 바람직하게는 양생 기간을 30일 정도로 하여, 물은 매일 1회 살포하는 것이다. 그리고 양생 시공이 완료된 후 거푸집을 해체하여 도 7과 같이 콘크리트층(100)을 완성한다.Once the stopping step is completed, the formed concrete layer 100 is cured for 25 to 35 days to form a slab. Then, water is sprayed on the surface of the formed concrete layer 100 to prevent surface drying while curing the formed concrete layer 100. At this time, water is sprayed on the surface of the formed concrete layer 100 for 25 to 35 days to prevent surface drying, and can be sprayed once per day. Preferably, the curing period is about 30 days, and water is sprayed once a day. And after the curing construction is completed, the form is dismantled to complete the concrete layer 100 as shown in FIG. 7.

이처럼 본 발명은 큰크리트층의 시공 과정(S100)에서 타설된 콘크리트에 진동을 부여하는 간단한 방법으로 구성되므로, 슬라브의 두께를 필요 이상으로 두껍게 형성하지 않아도 되어, 층간 소음을 해결하기 위하여 부득이하게 층고를 높일 필요가 없고, 공사 비용을 증가시키지 않는 효과가 있다.As such, the present invention consists of a simple method of imparting vibration to the poured concrete during the construction process (S100) of the large concrete layer, so there is no need to make the slab thicker than necessary, so it is inevitable to increase the floor height in order to solve inter-floor noise. There is no need to increase , and it has the effect of not increasing construction costs.

도 8은 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법에 의하여 시공된 자갈층을 갖는 건축물용 슬라브 구조체를 개략적으로 도시한 도면이다.Figure 8 is a diagram schematically showing a slab structure for a building with a gravel layer constructed by the method of constructing a slab structure for a building with a gravel layer according to a preferred embodiment of the present invention.

도 1 및 도 8을 참조하면, 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법은 콘크리트층 시공 과정(S100), 와이어매쉬 설치 과정(S200), 온수파이프 설치 과정(S300), 자갈층 시공 과정(S400) 및 바닥층 시공 과정(S500)을 포함한다. 콘크리트층 시공 과정(S100)은 상술하였으므로, 이하에서는 와이어매쉬 설치 과정(S200), 온수파이프 설치 과정(S300), 자갈층 시공 과정(S400) 및 바닥층 시공 과정(S500)에 대하여 설명하기로 한다.Referring to Figures 1 and 8, the construction method of a building slab structure with a gravel layer according to a preferred embodiment of the present invention includes a concrete layer construction process (S100), a wire mesh installation process (S200), and a hot water pipe installation process (S300). ), gravel layer construction process (S400), and bottom layer construction process (S500). Since the concrete layer construction process (S100) has been described above, the following will describe the wire mesh installation process (S200), the hot water pipe installation process (S300), the gravel layer construction process (S400), and the bottom layer construction process (S500).

와이어매쉬 설치 과정(S200) 및 온수파이프 설치 과정(S300)Wire mesh installation process (S200) and hot water pipe installation process (S300)

콘크리트층 시공 과정(S100)에서 콘크리트층(100)이 시공되면, 콘크리트층(100)의 상부에 받침대 역할을 하기 위한 와이어매쉬(210)를 시공한다(S200). 그 후, 와이어매쉬(210)의 상부에 온수파이프를 시공한다(S300). 온수파이프(220)는 온수가 공급되는 것으로, 온수의 온기가 콘크리트층(100)의 상부에서 사방으로 고르게 퍼지도록 촘촘하게 설치한다. When the concrete layer 100 is constructed in the concrete layer construction process (S100), a wire mesh 210 to serve as a support is constructed on the upper part of the concrete layer 100 (S200). Afterwards, a hot water pipe is constructed on the top of the wire mesh 210 (S300). The hot water pipe 220 supplies hot water, and is installed tightly so that the warmth of the hot water spreads evenly in all directions from the top of the concrete layer 100.

자갈층 시공 과정(S400)Gravel layer construction process (S400)

그 후, 온수파이프(220)가 설치된 콘크리트층(100)의 상부에 자갈을 포설하여 자갈층(200)을 시공한다(S400). 이때, 온수파이프(220)의 사이 사이에 자갈이 배치되도록 하여 자갈이 온수파이프(220)에 접촉되도록 배치시킨다. Afterwards, the gravel layer 200 is constructed by laying gravel on the upper part of the concrete layer 100 where the hot water pipe 220 is installed (S400). At this time, gravel is placed between the hot water pipes 220 so that the gravel is in contact with the hot water pipe 220.

자갈층(200)에 구비되는 자갈의 직경은 25mm 내지 40mm 인 것으로 구성될 수 있다. 자갈의 직경이 25mm보다 작으면 온기를 오랫동안 유지될 수 없는 문제점이 있고, 자갈의 직경이 40mm보다 크면 자갈과 자갈 사이에 빈 공간이 발생되는 문제점이 있다.The gravel provided in the gravel layer 200 may have a diameter of 25 mm to 40 mm. If the diameter of the gravel is smaller than 25 mm, there is a problem that the warmth cannot be maintained for a long time, and if the diameter of the gravel is larger than 40 mm, there is a problem that an empty space is created between the gravel.

그리고 온수파이프(220)에 온수가 공급되면 온수의 열 에너지가 온수파이프(220)와 맞닿은 자갈로 전도되어, 자갈은 온기를 오랫동안 유지할 수 있는 효과가 있다. 이처럼 본 발명은 온수파이프(220)에 온수가 공급되면, 온수파이프(220)와 접촉된 자갈층(200)의 자갈로 열이 전도되므로, 바닥 난방 보온이 장시간 유지될 수 있고, 한국의 온돌 전통방식인 구들장 역할을 하고, 에너지 절감에 효율적인 효과가 있다.And when hot water is supplied to the hot water pipe 220, the heat energy of the hot water is conducted to the gravel in contact with the hot water pipe 220, so the gravel has the effect of maintaining warmth for a long time. In this way, in the present invention, when hot water is supplied to the hot water pipe 220, heat is conducted to the gravel of the gravel layer 200 in contact with the hot water pipe 220, so floor heating can be maintained for a long time, and the traditional Korean ondol method. It serves as a food source and is effective in saving energy.

바닥층 시공 과정(S500)Bottom layer construction process (S500)

그 후, 시멘트몰탈, 미장몰탈 등을 이용하여 바닥층(300)을 시공한다(S500). 이처럼 콘크리트층에 온수파이프를 시공한 후 자갈을 포설한 후 바닥층을 시공하면, 바닥층의 상부에 충격이 가해진다 하더라도 자갈층에서 1차 완충 역할을 하므로, 주거시설의 경우, 층간소음이 40 내지 50% 이상 절감되고, 아래층에 전달되는 충격이나 음향을 90% 이상 감소될 수 있는 효과가 있다.Afterwards, the bottom layer 300 is constructed using cement mortar, plastering mortar, etc. (S500). In this way, when a hot water pipe is constructed on a concrete layer and then gravel is laid before constructing the bottom layer, even if an impact is applied to the upper part of the bottom layer, the gravel layer acts as a primary buffer, so in the case of residential facilities, inter-floor noise is reduced by 40 to 50%. This has the effect of reducing shock and sound transmitted to the lower floor by more than 90%.

이하, 본 발명의 바람직한 실시예에 따른 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법에 의하여 시공한 콘크리트층과 일반 공법으로 시공한 비교 콘크리트층의 형태 비교 결과를 설명한다.Hereinafter, the results of comparing the shapes of a concrete layer constructed by the construction method of a building slab structure with a gravel layer according to a preferred embodiment of the present invention and a comparative concrete layer constructed by a general method will be described.

도 9는 본 발명의 바람직한 실시예에 따른 표본틀을 도시한 도면이고, 도 10은 본 발명의 바람직한 실시예에 따른 표본틀에 콘크리트를 타설하는 상태를 도시한 도면이며, 도 11은 본 발명의 바람직한 실시예에 따른 표본틀에 콘크리트가 타설되어 콘크리트층이 형성된 상태를 도시한 도면이고, 도 12는 본 발명의 바람직한 실시예에 따른 표본틀에 형성된 콘크리트층에 진동을 부여하는 작업을 도시한 도면이며, 도 13은 본 발명의 바람직한 실시예에 따른 진동이 가해진 콘크리트층의 표면을 평탄화 처리한 상태를 도시한 도면이고, 도 14는 본 발명의 바람직한 실시예에 따른 시공이 완료된 콘크리트층를 도시한 도면이며, 도 15는 본 발명의 바람직한 실시예에 따른 시공이 완료된 콘크리트층의 옆면을 도시한 도면이다.Figure 9 is a diagram showing a specimen frame according to a preferred embodiment of the present invention, Figure 10 is a diagram showing a state of pouring concrete into a specimen frame according to a preferred embodiment of the present invention, and Figure 11 is a diagram showing a specimen frame according to a preferred embodiment of the present invention. This is a diagram showing a state in which concrete is poured into a specimen frame according to a preferred embodiment to form a concrete layer, and Figure 12 is a diagram showing the operation of applying vibration to the concrete layer formed in the specimen frame according to a preferred embodiment of the present invention. 13 is a view showing a state in which the surface of a concrete layer subjected to vibration has been flattened according to a preferred embodiment of the present invention, and FIG. 14 is a view showing a concrete layer on which construction has been completed according to a preferred embodiment of the present invention. 15 is a view showing the side of a concrete layer on which construction has been completed according to a preferred embodiment of the present invention.

먼저, 도 10 및 도 11을 참조하면, 콘크리트 재료 즉, 시멘트, 잔골재(모래), 굵은골재(자갈) 및 물을 1: 2: 4: 0.2의 비율로 배합하여 혼합하였다. 그리고 충분히 믹싱된 콘크리트를 시공 위치에 타설하여 콘크리트층을 형성하였다. 이때, 시공 위치는 층간 소음을 측정하기 위하여 도 9과 같이 가로 100cm, 세로 100cm 및 깊이 25.5cm의 표본틀을 제작하고, 표본틀을 시공 위치로 하였다. 표본틀에는 철근 배근을 가로 10cm 세로 10cm 교차 배열하였으며, 2열로 배치하여 상부 목측(目測)시 각 5cm로 배열하였다. 콘크리트 타설 깊이를 21cm로 감안하여 하부 3cm 중간 15cm 상부 3cm로 철근을 시공하였다. First, referring to Figures 10 and 11, concrete materials, that is, cement, fine aggregate (sand), coarse aggregate (gravel), and water, were mixed at a ratio of 1: 2: 4: 0.2. Then, sufficiently mixed concrete was poured at the construction location to form a concrete layer. At this time, in order to measure inter-floor noise, a sample frame with a width of 100 cm, a length of 100 cm, and a depth of 25.5 cm was manufactured as shown in Figure 9, and the sample frame was set as the construction location. In the specimen frame, reinforcing bars were arranged crosswise at a width of 10 cm and a height of 10 cm, and were arranged in two rows, each 5 cm apart when viewed from the top. Considering the concrete pouring depth of 21cm, rebar was installed at the bottom 3cm, the middle 15cm, and the top 3cm.

그 후, 도 12를 참조하면, 시공위치에 콘크리트가 타설된 이후, 콘크리트의 밀도를 높이기 위하여 바이브레이터(10)를 이용하여 콘크리트층에 진동을 충분하게 가해주었다. Thereafter, referring to FIG. 12, after the concrete was poured at the construction location, sufficient vibration was applied to the concrete layer using the vibrator 10 to increase the density of the concrete.

그 후, 도 13을 참조하면, 콘크리트층(A)의 표면을 평탄화 처리하는 정지 작업을 진행하였고, 도 14를 참조하면, 정지 작업을 마친 콘크리트층(A)을 양생 시공하되 이 과정에서 표면 건조를 방지하기 위하여 콘크리트층(A)의 표면에 30일 동안 매일 1회 물을 살포하였다. 그리고 양생 시공이 완료된 후 포본틀을 해체하여 콘크리트층(A)을 완성하였다. 콘크리트층(A)의 두께는 정석 타설(22cm)에 1cm 추가 타설 후 진동을 가해주고, 양생한 결과 최종 21.5cm로 시공되었음을 알 수 있다. 시공 목표인 21cm보다 0.5cm 증가한 21.5cm 두께의 콘크리트층(A)을 확보할 수 있었다.Afterwards, referring to Figure 13, grading work was performed to flatten the surface of the concrete layer (A), and referring to Figure 14, the concrete layer (A) that completed the grading work was cured, but during this process, the surface was dried. To prevent this, water was sprayed on the surface of the concrete layer (A) once a day for 30 days. And after the curing construction was completed, the foam frame was dismantled to complete the concrete layer (A). It can be seen that the thickness of the concrete layer (A) was built at a final thickness of 21.5cm as a result of adding 1cm to the regular stone pouring (22cm), applying vibration, and curing. We were able to secure a concrete layer (A) with a thickness of 21.5cm, which is 0.5cm more than the construction target of 21cm.

최종적으로 도 15를 참조하면, 본 발명의 콘크리트층(A)은 시공위치에 콘크리트를 타설한 후 밀도(密度)를 높이기 위하여 바이브레이터로 콘크리트층(A)에 진동을 부여하였으므로, 콘크리트층(A) 내부에 수포에 의한 공기층을 발견할 수 없으며 육안으로도 견고함을 알 수 있다.Finally, referring to FIG. 15, the concrete layer (A) of the present invention was vibrated by a vibrator to increase the density after pouring the concrete at the construction location, so the concrete layer (A) No air layer due to blisters can be found inside, and you can tell that it is solid with the naked eye.

도 16은 본 발명의 콘크리트층과 비교하기 위한 비교 콘크리트층를 시공하기 위한 표본틀을 도시한 도면이고, 도 17은 본 발명의 콘크리트층과 비교하기 위한 비교 콘크리트층를 도시한 도면이며, 도 18은 본 발명의 콘크리트층과 비교하기 위한 비교 콘크리트층의 옆면을 도시한 도면이다.Figure 16 is a diagram showing a sample frame for constructing a comparative concrete layer for comparison with the concrete layer of the present invention, Figure 17 is a diagram showing a comparative concrete layer for comparison with the concrete layer of the present invention, and Figure 18 is a diagram showing the comparative concrete layer for comparison with the concrete layer of the present invention. This is a drawing showing the side of a comparative concrete layer for comparison with the concrete layer of the invention.

도 16 및 도 17을 참조하면, 본 발명의 콘크리트층과 비교하기 위한 비교 콘크리트층(B: 도 17 도시)은 본 발명에서 진동단계를 제거한 것을 제외하고는 본 발명의 콘크리트층과 동일하게 시공된다. 즉, 도 16의 표본틀에 혼합한 콘크리트가 타설되고, 이렇게 타설된 콘크리트는 정지 및 양생 과정을 거친 후 표본틀을 해체하여 비교 콘크리트층(B)으로 시공된다. Referring to Figures 16 and 17, the comparative concrete layer (B: shown in Figure 17) for comparison with the concrete layer of the present invention is constructed in the same manner as the concrete layer of the present invention except that the vibration step is removed in the present invention. . That is, the mixed concrete is poured into the sample frame of FIG. 16, and the poured concrete goes through a grading and curing process, and then the sample frame is dismantled and constructed as a comparative concrete layer (B).

최종적으로 도 18을 참조하면, 비교 콘크리트층(B)은 시공위치에 콘크리트를 타설한 후 밀도(密度)를 높이기 위한 진동 시공을 하지 않아, 비교 콘크리트층(B) 내부에 수포에 의한 공기층이 형성되었음을 알 수 있다. 이러한 공기층은 층간 소음의 원인이 발생하였을시 공진(共振) 현상을 수반하는 문제점이 있다.Finally, referring to FIG. 18, the comparative concrete layer (B) did not undergo vibration construction to increase density after pouring the concrete at the construction location, and an air layer was formed due to blisters inside the comparative concrete layer (B). You can see that it has been done. This air layer has the problem of accompanying a resonance phenomenon when the cause of inter-floor noise occurs.

이하, 본 발명의 바람직한 실시예에 따른 건축물용 콘크리트층의 시공 방법에 의하여 시공한 콘크리트층과 일반 공법으로 시공한 비교 콘크리트층의 층간 소음 파장 비교 결과를 설명한다.Hereinafter, the results of comparing the inter-floor noise wavelength of a concrete layer constructed by the construction method of a building concrete layer according to a preferred embodiment of the present invention and a comparative concrete layer constructed by a general method will be described.

도 19 및 도 20은 본 발명의 바람직한 실시예에 따른 건축물용 콘크리트층의 시공 방법에 의하여 시공한 콘크리트층에 가해지는 소음을 서로 다른 스마트폰을 이용하여 측정한 결과를 도시한 도면이다.Figures 19 and 20 are diagrams showing the results of measuring noise applied to a concrete layer constructed by the method of constructing a concrete layer for a building according to a preferred embodiment of the present invention using different smartphones.

도 19를 참조하면, 실험자가 본 발명의 콘크리트층(A: 도 15 도시)에 1KG 해머(망치)를 힘껏 타격하여 충격을 가하였다. 그 후 삼성社의 갤럭시 노트 20 스마트폰을 콘크리트층(A)에 접촉하여 콘크리트층(A)에 가해지는 소음을 측정하였다. 측정 결과를 보면 콘크리트층(A)에 가해지는 소음은 밀도(密度)가 높은 바위를 가격할 때와 같은 작은 소음이 측정됨을 알 수 있다.Referring to Figure 19, the experimenter applied an impact to the concrete layer (A: shown in Figure 15) of the present invention by forcefully hitting it with a 1KG hammer. Afterwards, Samsung's Galaxy Note 20 smartphone was brought into contact with the concrete layer (A) to measure the noise applied to the concrete layer (A). Looking at the measurement results, it can be seen that the noise applied to the concrete layer (A) is a small noise similar to that of hitting a rock with high density.

도 20을 참조하면, 실험자가 본 발명의 콘크리트층(A: 도 15 도시)에 1KG 해머(망치)를 힘껏 타격하여 충격을 가하였다. 그 후 애플社의 아이폰 11 프로 스마트폰을 콘크리트층(A)에 접촉하여 콘크리트층(A)에 가해지는 소음을 측정하였다. 측정 결과를 보면 콘크리트층(A)에 가해지는 소음은 밀도(密度)가 높은 바위를 가격할 때와 같은 작은 소음이 측정됨을 알 수 있다.Referring to Figure 20, the experimenter applied an impact to the concrete layer (A: shown in Figure 15) of the present invention by forcefully hitting it with a 1KG hammer. Afterwards, Apple's iPhone 11 Pro smartphone was brought into contact with the concrete layer (A) to measure the noise applied to the concrete layer (A). Looking at the measurement results, it can be seen that the noise applied to the concrete layer (A) is a small noise similar to that of hitting a rock with high density.

이처럼 본 발명은 콘크리트층(A)을 시공하는 과정에서 바이브레이터를 이용하여 진동을 부여하므로, 콘크리트 내부에 수포에 의한 공기층이 형성되지 않아 밀도가 높아지도록 형성되고, 이에 따라 본 발명의 콘크리트층(A)는 공기층에 의한 공진 현상이 발생되지 않아 층간 소음이 발생되지 않는 것으로 판단된다.In this way, the present invention applies vibration using a vibrator in the process of constructing the concrete layer (A), so that an air layer due to water bubbles is not formed inside the concrete, so that the density is increased, and accordingly, the concrete layer (A) of the present invention is formed. ) is judged to not generate noise between floors because the resonance phenomenon caused by the air layer does not occur.

도 21 및 도 22는 본 발명의 콘크리트층과 비교하기 위한 비교 콘크리트층에 가해지는 소음을 서로 다른 스마트폰을 이용하여 측정한 결과를 도시한 도면이다.Figures 21 and 22 are diagrams showing the results of measuring noise applied to a comparative concrete layer for comparison with the concrete layer of the present invention using different smartphones.

도 21을 참조하면, 실험자가 비교 콘크리트층(B: 도 18 도시)에 1KG 해머(망치)를 힘껏 타격하여 충격을 가하였다. 그 후 삼성社의 갤럭시 노트 20 스마트폰을 비교 콘크리트층(B)에 접촉하여 비교 콘크리트층(B)에 가해지는 소음을 측정하였다. 측정 결과를 보면 비교 콘크리트층(B)에 가해지는 소음은 북소리와 비슷한 중저음의 울림이 측정됨을 알 수 있다.Referring to Figure 21, the experimenter applied an impact to the comparison concrete layer (B: shown in Figure 18) by forcefully hitting it with a 1KG hammer. Afterwards, Samsung's Galaxy Note 20 smartphone was brought into contact with the comparative concrete layer (B) to measure the noise applied to the comparative concrete layer (B). Looking at the measurement results, it can be seen that the noise applied to the comparative concrete layer (B) is a mid-low sound similar to the sound of a drum.

도 22를 참조하면, 실험자가 비교 콘크리트층(B: 도 18 도시)에 1KG 해머(망치)를 힘껏 타격하여 충격을 가하였다. 그 후 애플社의 아이폰 11 프로 스마트폰을 비교 콘크리트층(B)에 접촉하여 비교 콘크리트층(B)에 가해지는 소음을 측정하였다. 측정 결과를 보면 비교 콘크리트층(B)에 가해지는 소음은 북소리와 비슷한 중저음의 울림이 측정됨을 알 수 있다.Referring to Figure 22, the experimenter applied an impact to the comparison concrete layer (B: shown in Figure 18) by forcefully hitting it with a 1KG hammer. Afterwards, Apple's iPhone 11 Pro smartphone was brought into contact with the comparative concrete layer (B) to measure the noise applied to the comparative concrete layer (B). Looking at the measurement results, it can be seen that the noise applied to the comparative concrete layer (B) is a mid-low sound similar to the sound of a drum.

이처럼 비교 콘크리트층(B)는 시공 과정에서 바이브레이터를 이용한 진동 부여 과정이 생략되었으므로, 콘크리트 내부에 수포에 의한 공기층이 형성되어, 밀도가 낮아지도록 형성되고, 이에 따라 비교 콘크리트층(B)는 공기층에 의한 공진 현상이 발생되어 층간 소음이 발생되는 것으로 판단된다.In this way, since the process of applying vibration using a vibrator was omitted during the construction process of the comparative concrete layer (B), an air layer is formed due to water bubbles inside the concrete, so that the density is lowered. Accordingly, the comparative concrete layer (B) is formed in the air layer. It is believed that a resonance phenomenon occurs due to this, resulting in noise between floors.

본 발명은 상기 실시예에서 상세히 설명되었지만, 본 발명을 이로 한정하지 않음은 당연하고, 본 발명의 기술사상 범위 내에서 다양한 변형 및 수정이 가능함은 당업자에게 있어서 명백한 것이며, 이러한 변형 및 수정이 첨부된 청구범위의 범주에 속하는 것이라면 그 기술사상 역시 본 발명에 속하는 것으로 보아야 한다.Although the present invention has been described in detail in the above embodiments, it is obvious that the present invention is not limited thereto, and it is clear to those skilled in the art that various changes and modifications are possible within the scope of the technical idea of the present invention, and such changes and modifications are attached. If it falls within the scope of the claims, the technical idea should also be considered as belonging to the present invention.

10: 바이브레이터
100: 콘크리트층 110: 철근
200: 자갈층 210: 와이어매쉬
220: 온수파이프 300: 바닥층
10: Vibrator
100: concrete layer 110: rebar
200: gravel layer 210: wire mesh
220: hot water pipe 300: bottom layer

Claims (8)

건축물용 슬라브 구조체에 있어서,
콘크리트 재료를 배합하여 시공되는 콘크리트층;
상기 콘크리트층의 상부에 지그재그 형태로 설치되는 온수파이프;
상기 온수파이프가 설치된 상기 콘크리트층의 상부에 자갈을 포설하여 형성되는 자갈층; 및
상기 자갈층의 상부에 시공되는 바닥층을 포함하여 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체.
In the slab structure for buildings,
A concrete layer constructed by mixing concrete materials;
A hot water pipe installed in a zigzag shape on top of the concrete layer;
A gravel layer formed by placing gravel on the upper part of the concrete layer where the hot water pipe is installed; and
A slab structure for buildings having a gravel layer, characterized in that it includes a bottom layer constructed on top of the gravel layer.
제 1 항에 있어서,
상기 자갈의 직경은 25mm 내지 40mm 인 것으로 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체.
According to claim 1,
A slab structure for buildings having a gravel layer, characterized in that the diameter of the gravel is 25 mm to 40 mm.
제 1 항에 있어서,
상기 콘크리트층과 상기 온수파이프 사이에 와이어매쉬가 설치되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체.
According to claim 1,
A slab structure for buildings having a gravel layer, characterized in that a wire mesh is installed between the concrete layer and the hot water pipe.
제 1 항에 있어서,
상기 온수파이프에 온수가 공급되면 온수의 열 에너지가 상기 온수파이프와 맞닿은 자갈로 전도되도록 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체.
According to claim 1,
A slab structure for a building having a gravel layer, characterized in that when hot water is supplied to the hot water pipe, the heat energy of the hot water is conducted to gravel in contact with the hot water pipe.
건축물용 슬라브 구조체의 시공 방법에 있어서,
콘크리트 재료를 배합하여 콘크리트층을 시공하는 콘크리트층 시공 과정;
상기 콘크리트층의 상부에 온수파이프를 지그재그 형태로 설치하는 온수파이프 설치 과정;
상기 온수파이프가 설치된 상기 콘크리트층의 상부에 자갈을 포설하여 자갈층을 시공하는 자갈층 시공 과정; 및
상기 자갈층의 상부에 바닥층을 시공하는 바닥층 시공 과정을 포함하여 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법.
In the construction method of a building slab structure,
Concrete layer construction process of mixing concrete materials to construct a concrete layer;
A hot water pipe installation process of installing hot water pipes in a zigzag shape on top of the concrete layer;
A gravel layer construction process of constructing a gravel layer by laying gravel on the upper part of the concrete layer where the hot water pipe is installed; and
A method of constructing a slab structure for a building having a gravel layer, comprising a bottom layer construction process of constructing a bottom layer on top of the gravel layer.
제 5 항에 있어서,
상기 자갈층 시공 과정에서,
상기 자갈의 직경은 25mm 내지 40mm 인 것으로 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법.
According to claim 5,
During the gravel layer construction process,
A method of constructing a slab structure for a building having a gravel layer, characterized in that the diameter of the gravel is 25 mm to 40 mm.
제 5 항에 있어서,
상기 콘크리트층 시공 과정과 상기 온수파이프 설치 과정 사이에,
상기 콘크리트층의 상부에 와이어매쉬를 설치하는 와이어매쉬 설치 과정을 더 포함하고,
상기 온수파이프 설치 과정에서, 상기 와이어매쉬의 상부에 온수파이프를 설치하는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법.
According to claim 5,
Between the concrete layer construction process and the hot water pipe installation process,
Further comprising a wire mesh installation process of installing a wire mesh on the upper part of the concrete layer,
In the process of installing the hot water pipe, a method of constructing a slab structure for a building having a gravel layer, characterized in that installing a hot water pipe on the upper part of the wire mesh.
제 5 항에 있어서,
상기 콘크리트층 시공 과정은:
콘크리트 재료를 배합하여 혼합하는 혼합단계:
혼합한 콘크리트를 시공 위치에 타설하여 콘크리트층을 형성하는 타설단계;
바이브레이터를 이용하여 콘크리트층에 진동을 부여하는 진동단계; 및
콘크리트층을 양생시키는 양생단계를 포함하여 구성되는 것을 특징으로 하는 자갈층을 갖는 건축물용 슬라브 구조체의 시공 방법.
According to claim 5,
The concrete layer construction process is:
Mixing step of mixing concrete materials:
A pouring step of pouring the mixed concrete at the construction location to form a concrete layer;
A vibration step of applying vibration to the concrete layer using a vibrator; and
A method of constructing a slab structure for a building with a gravel layer, comprising a curing step of curing the concrete layer.
KR1020220039054A 2022-03-29 2022-03-29 Construction Method of Building Slab Structure with Gravelly Layer KR102669744B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220039054A KR102669744B1 (en) 2022-03-29 2022-03-29 Construction Method of Building Slab Structure with Gravelly Layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220039054A KR102669744B1 (en) 2022-03-29 2022-03-29 Construction Method of Building Slab Structure with Gravelly Layer

Publications (2)

Publication Number Publication Date
KR20230140196A true KR20230140196A (en) 2023-10-06
KR102669744B1 KR102669744B1 (en) 2024-05-27

Family

ID=88296226

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220039054A KR102669744B1 (en) 2022-03-29 2022-03-29 Construction Method of Building Slab Structure with Gravelly Layer

Country Status (1)

Country Link
KR (1) KR102669744B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100490757B1 (en) * 2004-08-06 2005-05-19 금강하이텍주식회사 Shock absorber, double-layered floor structure for diminishing a impact sound and construction method thereof
KR100771441B1 (en) * 2006-07-13 2007-10-30 송영택 A system for polishing concrete floor of using a leveling device
KR20180029335A (en) 2016-09-12 2018-03-21 이종철 The construction method for floor structure for preventing interlayer noise
KR102319581B1 (en) * 2021-01-11 2021-10-29 성기관 Floor constructing method for reducing floor noise

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100490757B1 (en) * 2004-08-06 2005-05-19 금강하이텍주식회사 Shock absorber, double-layered floor structure for diminishing a impact sound and construction method thereof
KR100771441B1 (en) * 2006-07-13 2007-10-30 송영택 A system for polishing concrete floor of using a leveling device
KR20180029335A (en) 2016-09-12 2018-03-21 이종철 The construction method for floor structure for preventing interlayer noise
KR102319581B1 (en) * 2021-01-11 2021-10-29 성기관 Floor constructing method for reducing floor noise

Also Published As

Publication number Publication date
KR102669744B1 (en) 2024-05-27

Similar Documents

Publication Publication Date Title
AU2009316945B2 (en) Lightweight building structure produced by using a mortar and a method for the production
CN104947846B (en) A kind of prefabricated integral frame light filling lining and preparation method thereof
WO2018099199A1 (en) Prefabricated thermal insulation wall cladding manufacturing method
CN105113706A (en) Reinforced truss gypsum plate with insulation layer, novel dismantling-free formwork and their construction method
RU2643055C1 (en) Three-layer bearing panel manufacturing method
CN103821263A (en) Precast assembly self-heat preservation concrete shear wall system and construction method thereof
KR102669744B1 (en) Construction Method of Building Slab Structure with Gravelly Layer
AU2011206926B2 (en) A brick panel and method of forming a brick panel
RU2378461C1 (en) Structure of precast floor and method of its erection
KR20230067301A (en) Construction Method for Building Slab to Reduce Noise between Floors
JP2862147B2 (en) Basement wall construction method using concrete formwork panels
CN205502301U (en) Energy -concerving and environment -protective whole compound core light building wall that presss from both sides
RU2452620C2 (en) Method to manufacture panels
CN108824692A (en) Concrete prefabricated board, concrete folding plate and concrete prefabricated board construction method
EP3719229B1 (en) Concrete floor panel, method of production of such panel and floor made of this panel
RU2572579C2 (en) Slab structure with inbuilt pipe for floor heating
RU213689U1 (en) Multilayer wall panel
RU2794678C1 (en) Method for manufacturing a reinforced concrete block room for a mobile workshop for block housing construction
RU2658849C1 (en) Progressive shuttering
AU2004203867B2 (en) A building system
RU2010928C1 (en) Method of monolithic three-layered construction production
Marriage Structure: concrete
WO2015128786A1 (en) A cast structural element
KR100648469B1 (en) A panel and manufacturing method of it's
RU68021U1 (en) BRICK-FRAME BUILDING

Legal Events

Date Code Title Description
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant