KR20220094843A - Supporting part of permanent waling and under ground structure construction method using it - Google Patents

Supporting part of permanent waling and under ground structure construction method using it Download PDF

Info

Publication number
KR20220094843A
KR20220094843A KR1020200186483A KR20200186483A KR20220094843A KR 20220094843 A KR20220094843 A KR 20220094843A KR 1020200186483 A KR1020200186483 A KR 1020200186483A KR 20200186483 A KR20200186483 A KR 20200186483A KR 20220094843 A KR20220094843 A KR 20220094843A
Authority
KR
South Korea
Prior art keywords
wale
support member
permanent
wall
girder
Prior art date
Application number
KR1020200186483A
Other languages
Korean (ko)
Other versions
KR102548906B1 (en
Inventor
양숙경
Original Assignee
양숙경
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양숙경 filed Critical 양숙경
Priority to KR1020200186483A priority Critical patent/KR102548906B1/en
Publication of KR20220094843A publication Critical patent/KR20220094843A/en
Application granted granted Critical
Publication of KR102548906B1 publication Critical patent/KR102548906B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

The present invention relates to a permanent wale support installed on an outer wall below a wale and a girder so as to support the wale installed in front of an outer wall and the girder connected to the wale. The permanent wale support of the present invention is fixedly joined to the outer surface of the outer wall below a position where the wale and the girder are installed to support the wale and the girder, and has the flat upper surface. Therefore, a wale support member is not attached to a main column of a retaining wall at a time of construction at a site, but is attached at a factory before the construction at the site, and then site construction is performed, so that fall of a worker can be prevented. In addition, since a welding work is not performed in a field, corrosion and fire can be prevented. In addition, since an accident is prevented in advance, safety can be improved.

Description

영구용 띠장 받침부재 및 이를 이용한 지중구조물 시공방법{SUPPORTING PART OF PERMANENT WALING AND UNDER GROUND STRUCTURE CONSTRUCTION METHOD USING IT}Permanent wale support member and underground structure construction method using the same

본 발명은 토목 기술분야에 관한 것으로서, 상세하게는, 무가시설 지하구조물 시공에 사용되는 영구용 띠장 받침부재 및 이를 이용한 지중구조물 시공방법에 관한 것이다.The present invention relates to the field of civil engineering, and more particularly, to a permanent wale support member used for construction of an underground structure without a facility, and to a method of constructing an underground structure using the same.

도 1은 종래의 띠장 및 거더의 설치 상태를 도시한 단면도이다. 1 is a cross-sectional view showing the installation state of a conventional wale and girder.

종래의 지중 구조물의 시공방법은 벽체의 내측에 띠장(40)을 설치한 후, 스트럿(30)을 설치하는 순서로 시공이 이루어진다.In the conventional construction method of the underground structure, the construction is performed in the order of installing the strut 30 after installing the wale 40 on the inside of the wall.

여기서, 띠장(40) 및 스트럿(30)은 공사 중 토류의 횡토압에 저항하는 기능을 하며, 공용 중에는 골조 구조의 기능을 하는 거더를 설치하여야 한다.Here, the wale 40 and the strut 30 function to resist the transverse earth pressure of the earth during construction, and a girder that functions as a frame structure should be installed during common use.

이러한 종래의 시공방법은 벽체와 띠장(40) 사이에 발생하는 홈에 홈메우기를 할 필요가 있다.In this conventional construction method, it is necessary to fill in the groove generated between the wall and the wale (40).

즉, 종래에는 벽체를 시공한 후, 소정의 심도로 굴착하여 벽체의 말뚝이 노출되도록 하고, 노출된 말뚝에 브라켓을 접합한 후 띠장(40)을 거치하고 수평방향으로 스트럿(30)을 설치한다.That is, in the prior art, after constructing the wall, excavating to a predetermined depth to expose the piles of the wall, attaching the bracket to the exposed piles, mounting the wale 40, and installing the struts 30 in the horizontal direction.

띠장(40)이 벽체에 밀착되어 설치됨으로써 토압을 지지하는 것이 이상적이나, 실질적으로는 벽체의 말뚝이 일정하게 배치되지 않거나 벽체의 단면이 고르지 않으므로, 벽체와 띠장(40) 사이에 자연스럽게 홈이 형성되는 것이다.Ideally, the wale 40 is installed in close contact with the wall to support the earth pressure, but in reality, the piles of the wall are not uniformly arranged or the cross-section of the wall is uneven, so a groove is naturally formed between the wall and the wale 40 will be.

따라서, 띠장(40)의 설치 작업성이 저하되고, 토압이 균등하게 띠장에 전달되지 않기 때문에 구조적 안정성이 저하되는 문제점이 있다.Therefore, there is a problem in that the installation workability of the wale 40 is lowered, and the structural stability is lowered because the earth pressure is not evenly transmitted to the wale.

종래에는 이 홈에 콘크리트 또는 몰탈로 이루어진 홈메우기 재료를 충전하거나 홈메우기용 블록을 설치하는 방식을 통해 각각의 말뚝과 띠장(40)의 접지면이 일정하도록 한다.Conventionally, through a method of filling the groove with a filling material made of concrete or mortar or installing a block for filling the groove, the ground plane of each stake and the wale 40 is uniform.

그리고, 띠장(40)과 스트럿(30)이나 혹은 거더의 하측에는 이들을 지지할 수 있도록 하는 별도의 브라켓(50)이 설치되는데, 브라켓(50)은 벽체에 대하여 수직 방향으로 배치되어 직접적으로 띠장(40)과 스트럿(30)이나 혹은 거더와 접촉되는 수평 지지부(51)와 수평 지지부(51)의 하면 일측을 지지하도록 벽체와 경사를 이루도록 배치되는 경사 지지부(52)로 이루어진다. In addition, a separate bracket 50 for supporting them is installed on the lower side of the wale 40 and the strut 30 or the girder, and the bracket 50 is disposed in the vertical direction with respect to the wall and directly 40) and the strut 30 or the horizontal support part 51 in contact with the girder and the inclined support part 52 arranged to form an inclination with the wall to support one side of the lower surface of the horizontal support part 51 .

이러한 브라켓(50)을 구성하는 수평 지지부(51)와 경사 지지부(52)는 각각 현장에서 용접 등의 접합 방식에 의하여 벽체의 외면에 고정 결합시키게 된다. The horizontal support part 51 and the inclined support part 52 constituting the bracket 50 are fixedly coupled to the outer surface of the wall by a bonding method such as welding in the field, respectively.

따라서, 종래의 지중 구조물의 시공방법에 있어서는, 상술한 바와 같이 브라켓(50)을 구성하는 수평 지지부(51)와 경사 지지부(52)와 같은 구성을 공사 현장에서 용접 등과 같은 접합 방식에 의하여 벽체의 외면에 고정시키기 때문에 용접 작업시에 현장 화재가 발생할 수 있기 때문에 안정성이 저하되어 건설 산재 사고의 발생 빈도가 높아질 수 있다는 문제점이 있다. Therefore, in the conventional construction method of an underground structure, as described above, the components such as the horizontal support part 51 and the inclined support part 52 constituting the bracket 50 are formed of the wall by a joining method such as welding at the construction site. Since it is fixed to the outer surface, there is a problem that the frequency of occurrence of construction accidents may increase due to reduced stability because on-site fires may occur during welding work.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 흙막이 구조벽의 주기둥에 띠장 받침부재를 현장에서 시공시에 부착하는 것이 아니라 현장 시공 전에 공장에서 부착시킨 후에 현장 시공이 이루어지도록 함으로써 작업자의 추락을 방지할 수 있도록 하고 현장에서의 용접 작업이 이루어지지 않도록 하여 부식과 화재를 예방하고 안전사고를 미연에 방지하여 안전성을 향상시킬 수 있도록 하는 영구용 띠장 받침부재를 제시하는 것을 그 목적으로 한다.The present invention was derived to solve the above problems, and instead of attaching the wale support member to the main pole of the retaining structure wall at the time of construction at the site, attach it at the factory before construction at the site, and then perform the site construction. The purpose of this is to present a permanent wale support member that prevents corrosion and fire and improves safety by preventing corrosion and fire by preventing the fall of the device and preventing welding work in the field. do.

상기 과제의 해결을 위하여, 본 발명은 외벽체의 전방에 설치되는 띠장과 상기 띠장과 연결되는 거더를 지지하도록 상기 띠장과 상기 거더 하측의 상기 외벽체에 설치되는 영구용 띠장 받침으로서, 상기 띠장과 상기 거더가 설치되는 위치 하측의 상기 외벽체 외면에 고정 접합되어 상기 띠장과 상기 거더를 지지하도록 하며 평탄한 상면을 구비한 것을 특징으로 하는 영구용 띠장 받침부재를 제시한다. In order to solve the above problems, the present invention is a wale belt installed in front of the outer wall and a permanent wale support installed on the outer wall below the girder to support the wale and the girder connected to the girder, the wale and the girder It is fixedly bonded to the outer surface of the outer wall below the installation position to support the wale and the girder, and provides a permanent wale support member, characterized in that it has a flat upper surface.

여기서, 상기 영구용 띠장 받침부재는 상기 외벽체의 폭방향과 나란하게 배치되며 일정 간격 이격되게 설치되는 한 쌍의 가로받침부재와, 상기 외벽체의 높이 방향과 나란하게 배치되어 상기 가로받침부재와 가로받침부재 사이에 상기 가로받침부재와 일체로 구비되는 세로받침부재를 포함할 수 있다. Here, the permanent wale supporting member is arranged in parallel with the width direction of the outer wall and a pair of transverse supporting members are installed to be spaced apart from each other, and the horizontal supporting member and the transverse supporting member are arranged in parallel with the height direction of the outer wall. It may include a vertical support member provided integrally with the horizontal support member between the members.

그리고, 상기 가로받침부재의 폭은 상기 외벽체의 폭과 동일한 폭을 갖도록 형성될 수 있다. And, the width of the horizontal support member may be formed to have the same width as the width of the outer wall.

또한, 상기 영구용 띠장 받침부재는 시공 현장이 아닌 공장에서 상기 외벽체를 구성하는 기둥의 외면에 접합되어 상기 기둥에 고정된 상태에서 상기 시공 현장으로 운반되도록 할 수 있다. In addition, the permanent wale support member is bonded to the outer surface of the pillar constituting the outer wall in the factory, not the construction site, so that it can be transported to the construction site in a state fixed to the pillar.

상기 과제의 해결을 위하여, 본 발명은 상기 영구용 띠장 받침부재가 상기 외벽체를 구성하는 기둥의 외면에 접합되도록 하는 제1단계와; 상기 외벽체를 시공하고자 하는 지반을 상기 기둥과 상기 영구용 띠장 받침부재 전체의 폭만큼 천공하여 상기 외벽체를 시공하는 제2단계와; 상기 외벽체의 전방의 지반을 터파기한 후에 상기 거더의 일측 하면이 상기 영구용 띠장 받침부재의 상면에 안착되도록 설치하는 제3단계와; 상기 거더와 상기 외벽체 사이의 공간에 띠장을 설치하여 상기 띠장과 상기 거더가 상호 고정되도록 하는 제4단계를; 포함한 것을 특징으로 하는 영구용 띠장 받침부재를 이용한 지중구조물 시공방법을 제시한다. In order to solve the above problems, the present invention includes a first step of joining the permanent wale support member to the outer surface of the pillar constituting the outer wall body; a second step of constructing the outer wall by perforating the ground on which the outer wall is to be constructed as much as the width of the pillar and the entire permanent wale supporting member; a third step of installing one lower surface of the girder to be seated on the upper surface of the permanent wale support member after excavating the ground in front of the outer wall; a fourth step of installing a wale in a space between the girder and the outer wall so that the wale and the girder are mutually fixed; We present a method of constructing an underground structure using a permanent wale support member, characterized in that it includes

여기서, 상기 영구용 띠장 받침부재는 시공 현장이 아닌 공장에서 상기 외벽체를 구성하는 기둥의 외면에 접합되어 상기 기둥에 고정된 상태에서 상기 시공 현장으로 운반되도록 할 수 있다. Here, the permanent wale support member is bonded to the outer surface of the pillar constituting the outer wall in the factory, not the construction site, so that it can be transported to the construction site in a state fixed to the pillar.

본 발명에 따른 영구용 띠장 받침부재는 흙막이 구조벽의 주기둥에 띠장 받침부재를 현장에서 시공시에 부착하는 것이 아니라 현장 시공 전에 공장에서 부착시킨 후에 현장 시공이 이루어지도록 함으로써 작업자의 추락을 방지할 수 있는 효과가 있다. The permanent wale support member according to the present invention is not attached to the main pillar of the retaining structure wall at the time of construction, but at the factory before on-site construction. can have an effect.

그리고, 흙막이 구조벽의 주기둥에 띠장 받침부재를 현장에서 용접 작업이 이루어지지 않도록 하여 부식과 화재를 예방하고 안전사고를 미연에 방지함으로써 안전성을 향상시킬 수 있는 효과가 있다. In addition, there is an effect that can improve safety by preventing corrosion and fire and preventing safety accidents in advance by preventing welding of the wale support member to the main pillar of the retaining structure wall in the field.

도 1은 종래의 띠장 및 거더의 설치 상태를 도시한 단면도이고,
도 2는 본 발명의 일 실시예에 따른 영구용 띠장 받침부재가 외벽체에 접합된 구조를 도시한 사시도이며,
도 3은 본 발명의 일 실시예에 따른 영구용 띠장 받침부재를 포함하여 띠장 및 거더가 설치된 상태를 도시한 단면도이며,
도 4는 본 발명의 일 실시예에 따른 영구용 띠장 받침부재가 외벽체에 설치된 구조를 도시한 평면도이고,
도 5는 본 발명의 일 실시예에 따른 영구용 띠장 받침부재를 이용한 지중구조물 시공방법을 순차적으로 기재한 시공흐름도이다.
1 is a cross-sectional view showing the installation state of a conventional wale and girder,
2 is a perspective view showing a structure in which a permanent wale support member is joined to an outer wall according to an embodiment of the present invention;
3 is a cross-sectional view showing a state in which a wale and a girder are installed, including a permanent wale supporting member according to an embodiment of the present invention;
4 is a plan view showing a structure in which a permanent wale support member is installed on an outer wall according to an embodiment of the present invention;
5 is a construction flow chart sequentially describing a method of constructing an underground structure using a permanent wale support member according to an embodiment of the present invention.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2는 본 발명의 일 실시예에 따른 영구용 띠장 받침부재가 외벽체에 접합된 구조를 도시한 사시도이며, 도 3은 본 발명의 일 실시예에 따른 영구용 띠장 받침부재를 포함하여 띠장 및 거더가 설치된 상태를 도시한 단면도이며, 도 4는 본 발명의 일 실시예에 따른 영구용 띠장 받침부재가 외벽체에 설치된 구조를 도시한 평면도이고, 도 5는 본 발명의 일 실시예에 따른 영구용 띠장 받침부재를 이용한 지중구조물 시공방법을 순차적으로 기재한 시공흐름도이다. 2 is a perspective view showing a structure in which a permanent wale supporting member is joined to an outer wall according to an embodiment of the present invention, and FIG. is a cross-sectional view showing a state in which is installed, Figure 4 is a plan view showing a structure in which the permanent wale supporting member is installed on the outer wall according to an embodiment of the present invention, Figure 5 is a permanent wale according to an embodiment of the present invention This is a construction flow chart sequentially describing the construction method of an underground structure using a supporting member.

이들 도면에 도시된 바와 같이, 본 발명에 의한 영구용 띠장 받침부재는, 외벽체(1)의 전방에 설치되는 띠장(2)과 상기 띠장(2)과 연결되는 거더(3)를 지지하도록 상기 띠장(2)과 상기 거더(3) 하측의 상기 외벽체(1)에 설치되는 영구용 띠장 받침으로서, 상기 띠장(2)과 상기 거더(3)가 설치되는 위치 하측의 상기 외벽체 외면에 고정 접합되어 상기 띠장(2)과 상기 거더(3)를 지지하도록 하며 평탄한 상면을 구비한 것을 특징으로 한다. As shown in these drawings, the permanent wale supporting member according to the present invention supports the wale 2 installed in front of the outer wall 1 and the girder 3 connected to the wale 2 (2) and the girder (3) as a permanent wale support installed on the outer wall body (1) below the girder (2) and the girder (3) is fixedly bonded to the outer surface of the outer wall below the location where the girder (3) is installed. It is characterized in that it is provided with a flat upper surface to support the wale (2) and the girder (3).

본 발명에 의한 영구용 띠장 받침부재는 상술한 바와 같이, 외벽체(1)의 전방에 설치되는 띠장(2)과 띠장(2)과 연결되는 거더(3)와 같은 구조물을 지지하여 구조적인 안정성을 향상시킬 수 있도록 하는 역할을 한다. As described above, the permanent wale supporting member according to the present invention provides structural stability by supporting structures such as the wale 2 installed in front of the outer wall 1 and the girder 3 connected to the wale 2 role in improving it.

종래의 영구용 띠장 받침부재는 시공 현장에서 용접 등의 접합 방법에 의하여 설치하였으나, 본 발명은 공장에서 영구용 띠장 받침부재를 시공 현장이 아닌 공장에서 제작 및 접합시키므로 시공 현장에서의 작업을 감소시켜 시공 현장 인력 작업을 최소화하여 시공 현장에서 발생가능한 건설산재사고를 최소화할 수 있게 된다. The conventional permanent wale supporting member was installed by a bonding method such as welding at the construction site, but the present invention reduces the work at the construction site because the permanent wale supporting member is manufactured and joined at the factory instead of the construction site. By minimizing the work of manpower at the construction site, it is possible to minimize construction accidents that may occur at the construction site.

다만, 도 3에서 거더(3)와 거더를 수직 방향으로 유동을 방지하고자 지지하고 있는 받침의 경우에 가설용도(설치공사 후 철거)일 경우에는 도 3에 도시한 바와 같이 볼트로 조립하지만, 영구적으로 사용할 경우에는 공장에서 용접하여 현장으로 운반하게 된다. However, in the case of the girder 3 and the bearing supporting the girder to prevent the flow in the vertical direction in FIG. 3, if it is for temporary use (demolition after installation construction), it is assembled with bolts as shown in FIG. 3, but permanently In the case of using it as a welding machine, it is welded at the factory and transported to the site.

이러한 영구용 띠장 받침부재(100)는 외벽체(1)의 폭방향과 나란하게 배치되며 일정 간격 이격되게 설치되는 한 쌍의 가로받침부재(110)와, 외벽체(1)의 높이 방향과 나란하게 배치되어 가로받침부재(110)와 가로받침부재(110) 사이에 가로받침부재(110)와 일체로 구비되는 세로받침부재(120)를 포함하여 구성되어 있다. This permanent wale support member 100 is arranged in parallel with the width direction of the outer wall body 1, and a pair of horizontal support members 110 installed to be spaced apart from each other by a predetermined interval, and the outer wall body 1, arranged in parallel with the height direction It is configured to include the horizontal support member 110 and the horizontal support member 110 and the vertical support member 120 provided integrally with the horizontal support member (110).

가로받침부재(110)는 외벽체(1)를 구성하는 기둥의 폭과 나란하게 배치되어 평탄한 상면을 형성하도록 하고, 상기 기둥의 높이 방향을 따라 일정 간격 이격되게 한 쌍으로 설치되는 부재이다. The horizontal support member 110 is a member that is arranged in parallel with the width of the pillars constituting the outer wall body 1 to form a flat upper surface, and is installed in pairs to be spaced apart from each other by a predetermined interval along the height direction of the pillar.

가로받침부재(110)는 용접 등의 접합 방법에 의하여 외벽체(1)를 구성하는 기둥의 외면에 고정 결합되며, 가로받침부재(110)가 거더(3)와 같은 구조물을 지지하는 지지력을 높일 수 있도록 일정 간격 이격된 위치에 가로받침부재(110)를 추가로 설치하고 한 쌍의 가로받침부재(110)가 세로받침부재(120)에 의하여 연결되도록 하는 것이 효과적이다. The horizontal support member 110 is fixedly coupled to the outer surface of the column constituting the outer wall body 1 by a bonding method such as welding, and the horizontal support member 110 can increase the supporting force for supporting a structure such as the girder 3 . It is effective to additionally install the horizontal support member 110 at a location spaced apart by a predetermined interval so that the pair of horizontal support members 110 are connected by the vertical support member 120 .

그리고, 가로받침부재(110)의 폭은 외벽체(1)를 구성하는 기둥의 폭과 동일한 폭으로 형성되어 상기 기둥의 외면에 접합되도록 함으로써 지지력을 극대화할 수 있도록 하는 것이 효과적이다. In addition, the width of the horizontal support member 110 is formed to have the same width as the width of the column constituting the outer wall body 1, so that it is effective to maximize the supporting force by bonding to the outer surface of the column.

세로받침부재(120)는 상술한 바와 같이 가로받침부재(110)가 거더(3)와 같은 구조물을 지지하는 지지력을 향상시킬 수 있도록 가로받침부재(110)와 가로받침부재(110) 사이에 이들을 연결하도록 세로 방향으로 구비되는 부재이다. The vertical support member 120 is a horizontal support member 110 between the horizontal support member 110 and the horizontal support member 110 to improve the supporting force for supporting a structure such as the girder 3 as described above. It is a member provided in the longitudinal direction to connect.

세로받침부재(120)는 구조적인 안정성 및 강성을 높일 수 있도록 가로받침부재(110)와 일체로 형성되어 외벽체(1)를 구성하는 기둥의 외면에 가로받침부재(110)와 함께 용접 등의 접합 방법에 의하여 고정 결합되어 있다. The vertical support member 120 is integrally formed with the horizontal support member 110 to increase structural stability and rigidity, and is joined together with the horizontal support member 110 on the outer surface of the column constituting the outer wall 1 by welding, etc. It is fixedly coupled by a method.

세로받침부재(120)의 길이는 가로받침부재(110)의 상면에 안착되는 거더(3)와 같은 구조물의 중량에 따라 결정되는 것이 바람직하다. The length of the vertical support member 120 is preferably determined according to the weight of the structure, such as the girder (3) seated on the upper surface of the horizontal support member (110).

가로받침부재(110)의 상면에 안착되는 거더(3)와 같은 구조물의 중량이 큰 경우에는 지지력을 높일 수 있도록 상대적으로 긴 길이를 갖도록 형성되어 외벽체(1)의 외면에 접합되도록 하고, 거더(3)와 같은 구조물의 중량이 작은 경우에는 자재 비용을 절감할 수 있도록 상대적으로 짧은 길이를 갖도록 형성하는 것이 효과적이다. When the weight of a structure such as the girder 3 seated on the upper surface of the horizontal support member 110 is large, it is formed to have a relatively long length so as to increase the supporting force, so that it is joined to the outer surface of the outer wall body 1, and the girder ( When the weight of the structure as in 3) is small, it is effective to form it to have a relatively short length to reduce material costs.

가로받침부재(110)와 세로받침부재(120)로 구성되는 영구용 띠장 받침부재(100)는 시공 현장이 아닌 공장에서 상기 외벽체(1)를 구성하는 기둥의 외면에 접합되어 상기 기둥에 고정된 상태에서 상기 시공 현장으로 운반되는 것이 바람직하다. Permanent wale support member 100 consisting of a horizontal support member 110 and a vertical support member 120 is bonded to the outer surface of the column constituting the outer wall body 1 at the factory, not the construction site, and is fixed to the column. It is preferable to be transported to the construction site in the state.

영구용 띠장 받침부재(100)가 시공 현장이 아닌 공장에서 외벽체(1)를 구성하는 기둥의 외면에 접합되어 고정된 상태에서 시공 현장으로 운반되어 외벽체(1)의 시공이 이루어지도록 함으로써 시공 현장에서의 작업을 감소시켜 시공 현장 인력 작업을 최소화하여 시공 현장에서 발생가능한 건설산재사고를 최소화하고, 시공 현장에서 용접 등의 접합 작업시에 발생할 수 있는 화재의 위험을 현저하게 감소시킬 수 있는 효과가 있다. The permanent wale support member 100 is bonded to the outer surface of the pillar constituting the exterior wall 1 at the factory, not the construction site, and is transported to the construction site in a fixed state so that the construction of the exterior wall 1 is made at the construction site. It has the effect of minimizing the work of manpower at the construction site by reducing the work of .

상술한 바와 같은 구성을 갖는 본 발명에 따른 영구용 띠장 받침부재를 이용하여 띠장 및 거더를 시공하는 과정을 도 5를 참조하여 설명하면 다음과 같다. The process of constructing a wale and a girder using the permanent wale supporting member according to the present invention having the above-described configuration will be described with reference to FIG. 5 as follows.

우선, 영구용 띠장 받침부재(100)를 시공 현장이 아닌 공장에서 외벽체(1)를 구성하는 기둥의 외면에 용접 등의 방식에 의하여 접합시켜 고정된 상태에서 시공 현장으로 운반한다. First, the permanent wale support member 100 is joined to the outer surface of the pillar constituting the outer wall 1 at the factory, not the construction site, by welding or the like, and transported to the construction site in a fixed state.

그리고, 외벽체(1)를 시공하고자 하는 지반을 상기 기둥과 영구용 띠장 받침부재 전체의 폭만큼 천공하여 영구용 띠장 받침부재(100)가 고정된 기둥을 천공홀에 관입하여 외벽체(1)를 시공한다. Then, the ground on which the outer wall body 1 is to be constructed is drilled as much as the width of the entire width of the pillar and the permanent wale supporting member, and the pillar to which the permanent wale supporting member 100 is fixed is penetrated into the drilling hole to construct the outer wall (1). do.

그 후, 외벽체(1) 전방의 지반을 터파기하여 공간을 마련한 후에 거더(3)의 일측 하면을 본 발명에 따른 영구용 띠장 받침부재(100)를 구성하는 가로받침부재(110)의 평탄한 상면에 안착시키게 된다. After that, after digging the ground in front of the outer wall (1) to prepare a space, one lower surface of the girder (3) is placed on the flat upper surface of the horizontal support member (110) constituting the permanent wale support member (100) according to the present invention will settle down

여기서, 거더(3)의 일측 하면이 가로받침부재(110)에 의하여 안정적으로 지지될 수 있도록 가로받침부재(110)의 평탄한 상면과 접촉되는 면적을 최대화하기 위하여 거더(3)를 외벽체(1)와 최대한 밀착시키는 것이 효과적이다. Here, in order to maximize the area in contact with the flat upper surface of the transverse supporting member 110 so that the lower surface of one side of the girder 3 can be stably supported by the transverse supporting member 110, the girder 3 is attached to the outer wall body (1). It is effective to make it as close as possible to the

그리고, 띠장(2)의 일측면을 거더(3)의 일측면에 고정시키면 띠장(2)과 외벽체(1) 사이가 일정 간격 이격되어 이격공간이 형성된다. And, when one side of the wale 2 is fixed to one side of the girder 3, the wale 2 and the outer wall 1 are spaced apart by a predetermined interval to form a spaced space.

이러한 상태에서 상기 이격공간에 별도의 고정부재를 설치하여 거더(3)가 상기 영구용 띠장 받침부재에 의하여 외벽체(1)와 견고하게 연결되도록 함으로써 지중구조물의 시공이 완료된다. In this state, the construction of the underground structure is completed by installing a separate fixing member in the separation space so that the girder 3 is firmly connected to the outer wall 1 by the permanent wale support member.

상술한 바와 같이, 본 발명에 따른 영구용 띠장 받침부재는, 흙막이 구조벽의 주기둥에 띠장 받침부재를 현장에서 시공시에 부착하는 것이 아니라 현장 시공 전에 공장에서 부착시킨 후에 현장 시공이 이루어지도록 함으로써 작업자의 추락을 방지할 수 있도록 하고 현장에서의 용접 작업이 이루어지지 않도록 하여 부식과 화재를 예방하고 안전사고를 미연에 방지하여 안전성을 향상시킬 수 있게 된다. As described above, the permanent wale supporting member according to the present invention does not attach the wale supporting member to the main pillar of the retaining structure at the time of construction at the site, but attaches it at the factory before on-site construction. It is possible to prevent a worker from falling, prevent corrosion and fire by preventing welding work in the field, and to improve safety by preventing safety accidents in advance.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has only been described with respect to some of the preferred embodiments that can be implemented by the present invention, as noted, the scope of the present invention should not be construed as being limited to the above embodiments, and It will be said that the technical idea and the technical idea with the root are all included in the scope of the present invention.

1 : 외벽체 2 : 띠장
3 : 거더
100 : 영구용 띠장 받침부재
110 : 가로받침부재 120 : 세로받침부재
1 : Exterior wall 2 : Belt
3: girder
100: permanent band support member
110: horizontal support member 120: vertical support member

Claims (6)

외벽체(1)의 전방에 설치되는 띠장(2)과 상기 띠장(2)과 연결되는 거더(3)를 지지하도록 상기 띠장(2)과 상기 거더(3) 하측의 상기 외벽체(1)에 설치되는 영구용 띠장 받침으로서,
상기 띠장(2)과 상기 거더(3)가 설치되는 위치 하측의 상기 외벽체 외면에 고정 접합되어 상기 띠장(2)과 상기 거더(3)를 지지하도록 하며 평탄한 상면을 구비한 것을 특징으로 하는 영구용 띠장 받침부재.
To support the wale 2 installed in front of the outer wall 1 and the girder 3 connected to the wale 2, it is installed in the outer wall 1 below the wale 2 and the girder 3 As a permanent wale support,
Permanent, characterized in that it is fixedly bonded to the outer surface of the outer wall below the position where the wale 2 and the girder 3 are installed to support the wale 2 and the girder 3 and has a flat upper surface. Belt support member.
제1항에 있어서,
상기 영구용 띠장 받침부재(100)는 상기 외벽체(1)의 폭방향과 나란하게 배치되며 일정 간격 이격되게 설치되는 한 쌍의 가로받침부재(110)와, 상기 외벽체(1)의 높이 방향과 나란하게 배치되어 상기 가로받침부재(110)와 가로받침부재(110) 사이에 상기 가로받침부재(110)와 일체로 구비되는 세로받침부재(120)를 포함한 것을 특징으로 하는 영구용 띠장 받침부재.
According to claim 1,
The permanent wale support member 100 is arranged in parallel with the width direction of the outer wall body 1 and is parallel to the height direction of the pair of horizontal support members 110 and the outer wall body 1 which are installed to be spaced apart from each other by a predetermined interval. Permanent wale support member, characterized in that it comprises a vertical support member (120) provided integrally with the horizontal support member (110) between the horizontal support member (110) and the horizontal support member (110).
제2항에 있어서,
상기 가로받침부재(110)의 폭은 상기 외벽체(1)의 폭과 동일한 폭을 갖도록 형성된 것을 특징으로 하는 영구용 띠장 받침부재.
3. The method of claim 2,
The width of the horizontal support member (110) is a permanent wale support member, characterized in that it is formed to have the same width as the width of the outer wall (1).
제1항에 있어서,
상기 영구용 띠장 받침부재(100)는 시공 현장이 아닌 공장에서 상기 외벽체(1)를 구성하는 기둥의 외면에 접합되어 상기 기둥에 고정된 상태에서 상기 시공 현장으로 운반되는 것을 특징으로 하는 영구용 띠장 받침부재.
According to claim 1,
The permanent wale support member 100 is bonded to the outer surface of the pillar constituting the outer wall 1 at the factory, not the construction site, and is transported to the construction site in a state fixed to the pillar. support member.
제1항 내지 제4항 중 어느 한 항에 따른 영구용 띠장 받침부재를 이용한 지중구조물 시공방법으로서,
상기 영구용 띠장 받침부재가 상기 외벽체(1)를 구성하는 기둥의 외면에 접합되도록 하는 제1단계와;
상기 외벽체(1)를 시공하고자 하는 지반을 상기 기둥과 상기 영구용 띠장 받침부재(100) 전체의 폭만큼 천공하여 상기 외벽체(1)를 시공하는 제2단계와;
상기 외벽체(1)의 전방의 지반을 터파기한 후에 상기 거더(3)의 일측 하면이 상기 영구용 띠장 받침부재(100)의 상면에 안착되도록 설치하는 제3단계와;
상기 거더(3)와 상기 외벽체(1) 사이의 공간에 띠장을 설치하여 상기 띠장(2)과 상기 거더(3)가 상호 고정되도록 하는 제4단계를;
포함한 것을 특징으로 하는 영구용 띠장 받침부재를 이용한 지중구조물 시공방법.
As a method of constructing an underground structure using the permanent wale support member according to any one of claims 1 to 4,
a first step of joining the permanent wale support member to the outer surface of the pillar constituting the outer wall body (1);
a second step of constructing the outer wall (1) by perforating the ground on which the outer wall (1) is to be constructed as much as the width of the pillar and the permanent wale support member (100);
a third step of installing the one side lower surface of the girder (3) to be seated on the upper surface of the permanent wale support member (100) after excavating the ground in front of the outer wall (1);
a fourth step of installing a wale in the space between the girder 3 and the outer wall 1 so that the wale 2 and the girder 3 are mutually fixed;
Underground structure construction method using a permanent wale support member, characterized in that it includes.
제5항에 있어서,
상기 영구용 띠장 받침부재(100)는 시공 현장이 아닌 공장에서 상기 외벽체(1)를 구성하는 기둥의 외면에 접합되어 상기 기둥에 고정된 상태에서 상기 시공 현장으로 운반되는 것을 특징으로 하는 영구용 띠장 받침부재를 이용한 지중구조물 시공방법.
6. The method of claim 5,
The permanent wale support member 100 is bonded to the outer surface of the pillar constituting the outer wall 1 at the factory, not the construction site, and is transported to the construction site in a state fixed to the pillar. A method of constructing an underground structure using a supporting member.
KR1020200186483A 2020-12-29 2020-12-29 Supporting part of permanent waling and under ground structure construction method using it KR102548906B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200186483A KR102548906B1 (en) 2020-12-29 2020-12-29 Supporting part of permanent waling and under ground structure construction method using it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200186483A KR102548906B1 (en) 2020-12-29 2020-12-29 Supporting part of permanent waling and under ground structure construction method using it

Publications (2)

Publication Number Publication Date
KR20220094843A true KR20220094843A (en) 2022-07-06
KR102548906B1 KR102548906B1 (en) 2023-06-27

Family

ID=82399965

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200186483A KR102548906B1 (en) 2020-12-29 2020-12-29 Supporting part of permanent waling and under ground structure construction method using it

Country Status (1)

Country Link
KR (1) KR102548906B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015038289A (en) * 2013-08-19 2015-02-26 ヒロセ株式会社 Earth retaining structure
KR20170005991A (en) * 2015-07-07 2017-01-17 김형민 soil retaining wall using PHC pile and its construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015038289A (en) * 2013-08-19 2015-02-26 ヒロセ株式会社 Earth retaining structure
KR20170005991A (en) * 2015-07-07 2017-01-17 김형민 soil retaining wall using PHC pile and its construction method

Also Published As

Publication number Publication date
KR102548906B1 (en) 2023-06-27

Similar Documents

Publication Publication Date Title
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR20170005991A (en) soil retaining wall using PHC pile and its construction method
JP6650257B2 (en) Mountain retaining structure and construction method thereof
CN109837907B (en) Foundation pit excavation construction method
JP2831909B2 (en) Connection structure of steel columns, piles and foundation beams
KR100642326B1 (en) A temporary apparatus for constructing girder by top-down style construction method
KR100912574B1 (en) Retaining wall system using strut assembly and excavating method using the same
KR20220094843A (en) Supporting part of permanent waling and under ground structure construction method using it
JP7011254B2 (en) Structure Shinbashira building method and structure Shinbashira building device
JP2002242302A (en) Beam-column connection structure of building steel frame and its connecting method
KR20220011604A (en) Double pile self-reliance retaining wall construction method
KR102307510B1 (en) Temporary earth retaining structure and Construction method using the same
JP7310406B2 (en) Support structure for earth retaining wall and method for supporting earth retaining wall
KR102065941B1 (en) Method for constructing soil retaining wall structure using h-pile
JPH0559728A (en) Sheathing work above underground structure
JP2876182B2 (en) Joint foundation for temporary shutter
KR20120126927A (en) A double Raker system of an underground temporary structure
KR102523155B1 (en) Connecting structure of middle girder and construction method thereof
JP2009264088A (en) Underground system temporary frame
JP3062910B2 (en) Construction method of steel basement reinforced concrete continuous basement wall
JP2016079651A (en) Support structure
JP3135495B2 (en) Construction method of avalanche and rock fall protection fence and avalanche and rock fall protection fence
JP5989597B2 (en) Temporary seismic structure and its construction method during construction of seismic isolation for existing frame
KR20140057989A (en) A temporary skeleton system used a top down underground construction method
KR102108622B1 (en) Support structure of temporary strut for construction period reduction

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant