KR20190099747A - An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction - Google Patents

An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction Download PDF

Info

Publication number
KR20190099747A
KR20190099747A KR1020180019576A KR20180019576A KR20190099747A KR 20190099747 A KR20190099747 A KR 20190099747A KR 1020180019576 A KR1020180019576 A KR 1020180019576A KR 20180019576 A KR20180019576 A KR 20180019576A KR 20190099747 A KR20190099747 A KR 20190099747A
Authority
KR
South Korea
Prior art keywords
worker
database
work
construction
floor
Prior art date
Application number
KR1020180019576A
Other languages
Korean (ko)
Other versions
KR102613585B1 (en
Inventor
양경옥
Original Assignee
양경옥
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양경옥 filed Critical 양경옥
Priority to KR1020180019576A priority Critical patent/KR102613585B1/en
Publication of KR20190099747A publication Critical patent/KR20190099747A/en
Priority to KR1020230178158A priority patent/KR20230169923A/en
Application granted granted Critical
Publication of KR102613585B1 publication Critical patent/KR102613585B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to an apparatus for planning the personal moving route of work places by each floor or each zone, collecting performance data and judging the optimal worker moving route when a framework carpenter worker and a rebar worker, who work for framework constructions at an apartment house, move to a work place and a method thereof.

Description

공동주택 골조공사 작업자의 개인별 작업배정 장치 및 방법{An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction}An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction}

본 발명은 공동주택 아파트의 공사에서의 철근콘크리트 골조를 시공하는 형틀 목수 작업자와 철근 작업자의 개인별로 작업할 내용을 배정하는 방법에 관한 것으로, 작업자가 효율적으로 같은 층 또는 다음층으로 이동할 수 있도록, 동일한 골조 평면 구역 또는 위치에서 반복적으로 신속하게 작업할 수 있는 공사계획 및 인원투입 방법을 제공한다.The present invention relates to a method for assigning the content to work for each of the mold carpenter worker and the reinforcement worker to construct the reinforced concrete frame in the construction of apartment buildings, so that the worker can efficiently move to the same floor or the next floor, Provide construction planning and staffing methods that allow for rapid and repetitive work in the same framework plane area or location.

국토교통부 2017년 주택 인허가 발표에 따르면 아파트는 47만 가구이다. 아파트 공사는 2개동 내지 6개동으로 구성되며 최대 20개동의 대단지도 있다. According to the Ministry of Land, Infrastructure and Transport's 2017 housing permit, the apartment has 470,000 households. The apartment construction consists of 2 to 6 buildings, with a maximum of 20 buildings.

아파트 유형은 타워형과 판상형으로 구분된다. 판상형의 최근 유형은 일자형 또는 'ㄱ'자 'ㄴ'자 형태이다. 1개 층의 세대수는 4세대 내지 6세대이다. 세대는 남쪽 방향으로 배치되고 계단실 및 엘리베이터로 구성되는 코어는 북쪽에 위치하며 통상 2개이다.Apartment types are divided into tower type and plate type. Recent types of plaques are straight or 'a' or 'b'. The number of households in one floor is 4th generation to 6th generation. The households are arranged in the south direction and consist of staircases and elevators. The core is located in the north and is usually two.

판상형은 전면에 배치되는 공간이 많아 채광, 일조량이 우수하고 거실과 주방이 마주보는 형태로 맞통풍에 유리하다. 아파트 동을 'ㅡ'자로 구성하는 것보다 'ㄱ'자로 구성할 때 가구수를 최대화 할 수 있기 때문에 대부분 아파트들이 'ㄱ'자로 설계되고 있다. The plate type has a lot of space placed on the front, so it is excellent in daylighting and sunlight, facing the living room and kitchen, which is favorable for direct wind. Most apartments are designed as 'ㄱ' because the number of furniture can be maximized when the apartment building is composed of 'ㄱ' rather than 'ㅡ'.

평면의 배치는 'ㄱ'자의 모서리가 남쪽 방향으로 배치되는 V자 형태를 나타내는데 오전에 동쪽인 오른쪽 부분이 햇빛을 받고 오후에는 나머지 반쪽인 서쪽이 햇빛을 받도록 하기 위함이다. The layout of the plane is a V-shape where the corners of the 'a' are arranged in the south direction, so that in the morning, the right part of the east receives sunlight and in the afternoon the west, the other half, receives sunlight.

계단실 및 엘리베이터의 코어는 북쪽에 배치하여 조망이나 햇빛을 가리지 않도록 한다.The cores of staircases and elevators should be placed north so that they do not block view or sunlight.

대부분의 아파트 조감도나 동의 배치도를 보면 위와 같은 형태로 배치되는 것을 나타내고 있다.The most bird's eye view or the floor plan of the apartment shows the arrangement as above.

구조형식을 보면 철근콘크리트 구조이고 수직하중은 벽체가 지지하는 벽식구조이고 슬라브는 보가 없는 무량판 플랫 슬라브이다.The structural type is reinforced concrete structure, vertical load is wall structure supported by wall, and slab is flat slab without beam.

아파트 공사는 터파기를 한 후 아파트 기초 매트를 시공한 후 지하층을 완성한 후 지상층 철근콘크리트 골조공사와 마감공사의 순서로 진행된다. 이중 지상층 골조공사의 높이는 20층 내지 49층 규모이다. The construction of the apartment is carried out in the order of the construction of the foundation mat after the digging, the completion of the basement floor, and then the construction of the ground concrete reinforced concrete finishing and finishing work. The height of the double-layer framing construction is 20 to 49 stories.

지상 골조는 아래층을 시공한 후 위층으로 올라가며 10층을 시공한 후 11층을 시공하는 선행작업과 후행작업이 명확한 구조를 갖는 직렬방식의 공사 방식의 특징을 갖는다. The ground frame has the characteristics of a serial construction method that has a clear structure of the preliminary work and the subsequent work of constructing the 11th floor after constructing the 10th floor after constructing the lower floor.

골조공사는 건물의 뼈대이므로 공사기간이 길고 공사비가 많으며 다수의 작업자가 투입된다.Since the framework is the skeleton of the building, the construction period is long, expensive, and a large number of workers are involved.

이러한 골조공사는 인력에 의해 시공되는데 통상 1개층 시공에 6일 내지 8일이 소요된다. 1개층의 작업순서는 먹매김, 벽체 기둥 철근, 벽체 기둥 거푸집, 슬라브 동바리 및 슬라브 거푸집, 슬라브 철근, 콘크리트 타설 및 양생으로 진행된다. Such a frame construction is usually carried out by manpower takes 6 to 8 days in one floor construction. The work order for one floor consists of feeding, wall column reinforcement, wall column formwork, slab club and slab formwork, slab reinforcement, concrete pouring and curing.

여기서 형틀은 목수 작업자, 형틀 작업자에 의해 시공되며, 거푸집, 합판으로서 박스 기능을 하며 그 안에 철근을 넣고 콘크리트를 부어 넣으면 골조가 완성된다.Here, the mold is constructed by a carpenter worker, a mold worker, and functions as a box as formwork and plywood, and the frame is completed by adding reinforcing bars and pouring concrete into it.

콘크리트는 마지막날에 타설되므로 그 이전 단계는 대부분 목수작업인 거푸집 형틀 작업과 철근 작업의 주요 작업이다. 나머지는 전기, 설비 작업이 있다. Since concrete is poured on the last day, the previous stages are the main tasks of the formwork and reinforcing work, which is mostly carpenter work. The rest is electricity and equipment work.

아파트 1개층 4세대의 경우, 작업자가 150명 정도 투입된다. 이중 형틀(목수) 작업자가 가장 많고 다음으로 철근작업자이며 형틀 작업자와 철근 작업자를 합하면 전체의 약 70% 내지 80%를 차지한다.In the fourth generation of a single-floor apartment, about 150 workers are employed. The largest number of double molder (carpenter) workers, followed by the rebar workers, combined with the mold worker and reinforcing workers occupy about 70% to 80% of the total.

따라서 골조공사는 형틀 작업자와 철근 작업자에 의해 시공되어 생산된다고 볼 수 있다.Therefore, it can be seen that the frame construction is produced by the construction worker and the rebar worker.

한편 101동 10층 골조공사 기간이 6일 싸이클인 경우, 형틀 작업자와 철근 작업자는 일별로 필요한 인원수가 불규칙한 구조를 갖는다. On the other hand, in the case of a 10-day cycle for the 10-story frame construction of 101-dong, the molder and the rebar worker have an irregular structure.

마지막날인 6일차에는 콘크리트를 타설하므로 5일차까지 형틀이나 철근작업이 완료되어 6일차에는 형틀 작업자와 철근 작업자가 100명 이상이 필요가 없다. On the 6th day, the last day, concrete is poured, so the mold or reinforcement work is completed by the 5th day, and on the 6th day, there are no more than 100 molders and reinforcement workers.

1일차부터 5일차까지는 형틀이나 철근작업이 많거나 적게 불규칙하게 진행되므로 이에 따라 작업자도 불규칙하게 출역한다. From the first to the fifth day, many or less irregular work is carried out in the form or reinforcing bar work, so workers are irregularly dispatched.

이에 따라 남는 작업자는 다른 동인 102동에서 작업을 하거나, 다른 인근 현장에서 작업을 하게 된다. As a result, the remaining workers will work in another Dong-dong 102 building or another nearby site.

이러한 특징에 따라 제조업과 달리 건설 현장에서는 날짜별로 불규칙적인 작업자 수요에 따라 작업자를 배치해야 하므로 작업자 관리자의 작업자 동원 계획이나 관리 능력은 매우 중요하다.According to these characteristics, unlike the manufacturing industry, it is very important for a worker manager to mobilize or manage a worker because construction sites must be arranged according to irregular worker demand by date.

그러나 작업자 관리자가 형틀, 철근 작업자를 배치하는 작업은 현재 자신의 경험이나 노하우를 바탕으로 진행되고 있는 실정이다. However, the worker manager's placement of the mold and the rebar worker is currently being carried out based on his own experience or know-how.

기존의 작업자 배치 작업에 있어서 기존의 문제점은 다음과 같은 내용이다.The existing problems in the existing worker placement work are as follows.

아파트는 각각의 현장이나 동별로 평면 모양이 다양하여 경험을 적용하는 경우 오차가 커질 수 있다.As apartments vary in plan shape for each site or building, errors can increase when the experience is applied.

일별 인원수가 불규칙하므로 필요한 인원이나 남는 인원을 효율적으로 관리해야 인원이나 인건비 손실이 최소화할 수 있으나 이를 계산하는 방법이 수계산 방식을 사용하고 있다.Since the daily number of people is irregular, it is possible to minimize the loss of personnel or labor costs by efficiently managing the necessary or remaining personnel, but the method of calculating the number is used.

아파트 작업자 배치나 순환에 관한 기존의 논문이나 연구는 동별로 순환 싸이클인 순서를 제시하고 있으나, 아파트 평면이나 철근, 콘크리트 수량에 기반한 구체적인 형틀 및 철근 작업자의 인원수를 제시하는 방법은 없다.Existing papers and studies on apartment worker placement and circulation suggest the order of cycle cycles by apartment building, but there is no way to suggest concrete molds and the number of rebar workers based on apartment floor, rebar and concrete quantity.

형틀 및 철근 작업자는 몇 개의 팀으로 구성되고 다시 개인별로 작업 임무를 수행하고 있으나 팀별 개인별 작업장소 이동 또는 어떠한 부재(기둥)를 시공해야 하는지 구체적인 방법이 없다.Formwork and reinforcement workers are composed of several teams and perform work tasks individually, but there is no specific way of moving individual workplaces or building parts.

불규칙한 작업자 출역에 따른 남은 인원과 인원손실, 인건비를 최소화하기 위한 분석이나 신속 정확한 계산 사례가 제시되지 않고 있다.There are no examples of analysis or quick and accurate calculations to minimize the remaining personnel, personnel loss, and labor costs due to irregular worker service.

작업자가 하루에 얼마만큼의 시공을 하는지 작업생산성 실적을 수집하고 이를 계획에 반영함에 있어, 골조공사 작업자 개인별 분석 방법이나 실시예가 없다.In collecting the work productivity results and reflecting them in the plan how much construction is done per day, there is no individual analysis method or embodiment for each construction worker.

형틀 및 철근 작업자들은 개인별로 특정 부재를 작업하고 있으나, 작업자들이 시공해야 할 골조공사(예 101동 10층 골조)에 대하여 개인별로 역량을 고려하여 배정하지 않고 있다.Frame and rebar workers are working on specific members for each individual, but they do not allocate their own structure to each other in consideration of their capabilities.

따라서 이와 같은 기술과 관련하여 본 발명에서는 다수의 건물로 구성되는 아파트 골조공사에서 형틀 작업자와 철근 작업자가 작업 생산성을 높일 수 있는 작업자 개인의 작업장소 이동경로 배치계획 분석 방법을 고안하고자 한다.Therefore, in the present invention, in connection with such a technique, in the apartment frame construction consisting of a plurality of buildings, the molder and the reinforcement worker to improve the work productivity of the individual work place movement path arrangement plan analysis method.

본 발명은 상기와 같은 종래 기술에 따른 문제점을 해결하기 위하여 창안된 것으로서, 아파트 골조공사에서 형틀 및 철근 작업자가 시공해야 할 작업 장소, 작업 대상 및 수량을 개인별로 할당하고 성과를 분석하는 방법을 제공한다.The present invention has been made to solve the problems according to the prior art as described above, and provides a method for assigning a work place, work object and quantity for each individual to the mold and reinforcement workers in the construction of the apartment frame, and analyzing the performance do.

상기한 목적을 달성하고 상술한 종래기술의 문제점을 해결하기 위하여, 본 발명에 따른 아파트 골조공사에서 형틀 및 철근 작업자의 개인별 작업 배정 방법 및 장치는 1개층의 거푸집 및 철근 물량을 산출하고, 각각의 기둥(벽체)에 작업생산성을 고려하여 작업자를 할당하고, 슬라브의 실별 또는 면적을 기준으로 작업자를 배정한 후, 작업이 종료되면 다음 층이나 다른 존으로 이동하는 경로를 지정하여 각각의 부재에 대응하는 작업자가 산출된다.In order to achieve the above object and to solve the above-mentioned problems of the prior art, in the apartment frame construction according to the present invention, the individual work assignment method and apparatus of the mold and reinforcement worker calculates the formwork and the reinforcement quantity of each floor, Workers are assigned to columns (walls) in consideration of work productivity, workers are assigned based on the room or area of the slabs, and when the work is finished, a path is moved to the next floor or another zone to correspond to each member. The worker is calculated.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

골조공사의 각각의 기둥이나 벽체를 누가 언제 어떤 순서로 시공할 것인가를 세부적으로 계획할 수 있다.You can plan in detail who and when to construct each column or wall in a frame.

작업시간은 부재의 물량을 작업자의 1일 작업생산성으로 나누어 산출되므로 객관적이고 정확하다.Work time is objective and accurate because it is calculated by dividing the quantity of members by the worker's daily productivity.

작업자 개인은 각 층의 작업위치와 시간 및 작업할 수량을 사전에 정확히 알 수 있고 이에 따라 미래의 일을 사전에 알 수 있으므로 효율적인 작업을 할 수 있다. 또한 시공한 수량을 알 수 있고 자신의 일당 또는 임금 추이를 사전에 알 수 있다.Workers can work efficiently because they can know in advance the location and time of work on each floor and the quantity to be worked in advance. You can also see how much you have built and know your daily or wage trends in advance.

작업자를 배정하는 작업자 관리자는 작업자 개인의 역량을 고려하여 작업자를 배정할 수 있고 성과측정을 과학적으로 할 수 있다. 이에 따라 작업자의 특성을 반영하여 다음 층 또는 다른 공사에서 보다 효율적인 작업자 배정을 할 수 있다.Worker managers who assign workers can assign workers and perform performance measurement scientifically, taking into account their individual capabilities. This allows for more efficient worker assignment on the next floor or other construction, reflecting the characteristics of the worker.

시공사는 계획한 작업자 배정 대비 시공한 실적을 비교하여 문제점을 세부적이고 체계적으로 개인별로 알 수 있어 문제점을 파악이 용이하고 대책을 수립할 수 있다. The contractor can identify the problems in detail and systematically by comparing the construction performances with the planned worker assignments, so it is easy to identify the problems and establish countermeasures.

예를 들어 101동 901호 안방의 작업이 다른 구역보다 지연되어 전체 일정이 영향을 받는 경우, 안방에 배정된 작업자가 누구 인지 알 수 있고 생산성을 분석하여 작업자를 추가로 투입하거나 교체하는 등 대책수립이 신속하고 용이해진다.For example, if the work of 101-901 is delayed compared to other areas, the entire schedule is affected, so that you can know who is assigned to the room, analyze the productivity, and add or replace workers. This becomes quick and easy.

작업자 개인의 작업배정을 합하여 팀별 시공계획을 수립하고 시공사 전체의 시공계획이 정확히 수립된다. 이에 따라 다양한 시뮬레이션을 통해 공기단축과 최소의 작업자수를 배정하여 인건비를 절감하는 공사방법을 만들어 낼 수 있다. The work plan of each worker is combined to establish a construction plan for each team, and the construction plan for the entire construction is accurately established. Accordingly, various simulations can be used to create construction methods that reduce labor costs by allocating air shortening and the minimum number of workers.

작업자가 잘 알고 있거나 손에 익숙한 작업에 배정하고, 반복적으로 작업할 수 있도록 배정하므로써 학습효과나 습숙효과를 발휘할 수 있도록 할 수 있다. 이에 따라 작업생산성이 10% 이상 높아질 수 있다. By assigning to tasks that the worker is familiar with or familiar with, and assigning them to be able to work repeatedly, the learning or learning effects can be exerted. This can increase work productivity by more than 10%.

작업생산성이 높아지면 동일한 인원으로 공사시간을 단축할 수 있거나 공사 인건비를 절감할 수 있다.If work productivity increases, construction time can be shortened by the same personnel or construction labor cost can be reduced.

불규칙한 작업자 출역이나 불합리한 배정에 따른 인력 및 시간손실을 줄어든다.Reduces manpower and time lost due to irregular worker launches or unreasonable assignments.

작업자가 동일하고 반복적으로 작업함에 따라 자산의 작업에 대해 보다 잘 알게 되므로 품질이 향상되고 안전사고의 위험도 줄어든다.As workers work in the same and repetitive manner, they become more aware of the work of the asset, improving quality and reducing the risk of safety accidents.

상기 작업자 배정 방법을 사용하는 건설사 또는 철근 콘크리트 전문건설업체는 다른 경쟁사에 비해 신속하고 정확하게 작업자를 배정 관리할 수 있고 공사 일수를 단축하고 인건비를 절감할 수 있어 아파트 골조공사의 수주 및 생존 경쟁력이 높아진다.The construction company or reinforced concrete construction company using the above-mentioned worker assignment method can quickly and accurately assign and manage workers compared to other competitors, and can shorten the number of construction days and reduce labor costs, thereby increasing the competitiveness of order and survival of apartment framing. .

도 1은 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 장치의 전체 구성도
도 2 내지 4는 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 방법의 전체 흐름도
도 5는 본 발명의 일실시예에 따른 판상형 아파트의 공사개요
도 6은 본 발명의 일실시예에 따른 골조공사 공정표
도 7은 본 발명의 일실시예에 따른 벽체 부재에 대한 번호부여도
도 8은 본 발명의 일실시예에 따른 각각의 부재에 대한 철근 수량
도 9는 본 발명의 일실시예에 따른 작업자의 개인별 생산성 실적 데이터
도 10은 본 발명의 일실시예에 따른 도 8의 각각의 부재에 작업자를 배정한 내용
도 11은 본 발명의 일실시예에 따른 일별 작업자의 이동경로의 표시
도 12는 본 발명의 일실시예에 따른 계획 대비 실적과의 차이
도 13은 본 발명의 일실시예에 따른 101동과 102동을 합한 2개동의 철근 작업자의 일별 소요인원 추이
1 is an overall configuration diagram of a construction method analysis apparatus for individual work assignment according to an embodiment of the present invention
2 to 4 is a flow chart of the construction method analysis method for individual work assignment according to an embodiment of the present invention
5 is a construction overview of the plate-like apartment according to an embodiment of the present invention
Figure 6 is a skeleton construction process table according to an embodiment of the present invention
Figure 7 is a numbering diagram for the wall member according to an embodiment of the present invention
8 is a rebar quantity for each member according to an embodiment of the present invention
9 is an individual productivity performance data of the worker according to an embodiment of the present invention
10 is a content assigned to the worker to each member of Figure 8 according to an embodiment of the present invention
11 is a display of the movement route of the daily worker according to an embodiment of the present invention
12 is a difference between the results compared to the plan according to an embodiment of the present invention
13 is a daily change of the number of reinforcing workers of the two reinforcement workers combined 101 and 102 dong according to an embodiment of the present invention

이하, 본 발명에 따른 아파트 골조공사의 형틀 및 철근공사의 작업자 개인별 작업 배정방법 분석장치 및 방법을 상세히 설명한다.Hereinafter, an apparatus and method for analyzing a work assignment method for each worker in a frame and reinforcing work of an apartment frame construction according to the present invention will be described in detail.

도 1은 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 장치의 전체 구성을 나타낸 것이다. Figure 1 shows the overall configuration of the construction method analysis apparatus for individual work assignment according to an embodiment of the present invention.

도 1을 참조하면, 본 실시예에 따른 개인별 작업배정을 위한 공사방법 분석장치(10)는 제어부(11), 건축 도면 데이터 베이스(12), 기준층 평면 공구 분할 데이터 베이스(13), 자재 수량 데이터 베이스(14), 작업자 개인별 작업생산성 데이터 베이스(15), 공정표 데이터 베이스(16) 및 작업자 배정 데이터 베이스(17)를 포함한다.Referring to FIG. 1, the construction method analysis apparatus 10 for individual work assignment according to the present embodiment includes a control unit 11, an architectural drawing database 12, a reference layer planar tool division database 13, and material quantity data. A base 14, a worker productivity database 15, a schedule table database 16, and a worker assignment database 17 are included.

상기 제어부(11)는 기준층 평면 공구 분할 데이터 베이스(13)상의 공구분할에 따른 공구별 자재 부재의 물량(수량)을 자재 물량 데이터 베이스(14)로 부터 산출하고, 작업자 개인별 작업생산성 데이터 베이스(15)로부터 부재(기둥, 벽체, 실별 슬라브)별 작업시간을 산출하고, 공정표 데이터 베이스(16)로부터 다음 공구 또는 층으로 작업자 이동 경로를 산출하고, 상기 산출된 결과를 작업자 배정 데이터 베이스(17)에 저장한다.The control unit 11 calculates the quantity (quantity) of material parts for each tool according to the tool division on the reference layer planar tool division database 13 from the material quantity database 14, and the worker productivity database 15 for each worker. ), The work time for each member (column, wall, slab for each room) is calculated, the worker movement path is calculated from the process table database 16 to the next tool or layer, and the calculated result is sent to the worker assignment database 17. Save it.

예를 들어 4개 동의 35층 아파트 골조공사에서 제어부(11)는 각 동의 건축도면과 구조도면, BIM 도면을 건축도면 데이터베이스(12)에 저장한다. 기준층 평면을 A와 B의 2개로 분할한다. For example, the control unit 11 stores the building drawings, the structural drawings, and the BIM drawings in the building drawing database 12 in the construction of four 35-story apartment buildings. The reference layer plane is divided into two, A and B.

101동 9층 901호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다의 면적과 기둥 벽체 슬라브의 거푸집과 철근 수량을 산출한다. 가장 바깥쪽의 안방은 4개의 벽체와 1개의 천정 슬라브로 구성되며 4개의 벽체를 시공하기 위한 벽체철근과 벽체형틀의 수량이 산출된다. Room 9, Room 901, 101, Living Room, Kitchen, Study Room, Small Room, Toilet, Toilet 1, Area of Porch Porch, Formation of Reinforcement and Reinforcement of Column Wall Slab. The outermost inner chamber consists of four walls and one ceiling slab, and the quantity of wall reinforcement and wall frame for the construction of four walls is calculated.

바닥인 슬라브를 시공하기 위한 슬라브 형틀과 철근 수량도 산출된다.The slab mold and the number of reinforcing bars for constructing slabs, which are floors, are also calculated.

안방 벽체1을 시공하기 위한 수량에 대한 작업자를 배정하며 작업시간은 수량을 1일 생산성 또는 시간당 생산성으로 나누어 산출한다. 생산성은 작업자 개인별 작업생산성 데이터 베이스(15)를 이용한다.The worker is assigned to the quantity for constructing the inner wall 1, and the working time is calculated by dividing the quantity by daily productivity or productivity per hour. Productivity uses the worker productivity database 15 for each worker.

위와 같은 순서로 901호 세대에 대한 작업자 배정이 완료되면, 그 옆 세대인 902호 세대에 배정한다. 그리고 계단과 엘리베이터로 구성된 코어 1번에 대한 배정된 실시한다. 다음으로 903호, 904호, 코어 2번에 대해서도 901호와 같은 방식으로 배정한다. When the worker assignment for the 901 households is completed in the above order, the worker is assigned to the 902 households next to the household. And the assigned number 1 for the core consisting of stairs and elevators. Next, 903, 904, and Core 2 are also assigned in the same manner as in 901.

공정표 데이터 베이스(16)로부터 공정표를 읽고 9층에 대한 배정이 완료되면, 다음으로 10층에 대한 배정을 실시한다. 그리고 그 상층인 11층부터 35층까지 작업자를 배정하고 그 결과를 작업자 배정 데이터 베이스(17)에 저장한다. When the process table is read from the process table database 16 and the allocation to the 9th floor is completed, the next 10th floor is allocated. The workers are assigned from the 11th floor to the 35th floor, and the result is stored in the worker assignment database 17.

건축도면 데이터베이스(12)는 건축도면, 구조도면, BIM을 저정한다. 작업인원과 자재 물량을 산정하기 평면도, 단면도, 층고, 기둥 벽체의 치수를 포함한다. 건설현장은 도면에 따라 시공하므로 도면은 공사 착수전에 이미 CAD 등으로 완성되어 있다. The architectural drawing database 12 stores architectural drawings, structural drawings, and BIM. Calculating workforce and material quantities include floor plans, cross sections, floor heights, and column wall dimensions. The construction site is constructed in accordance with the drawings, so the drawings are already completed in CAD, etc. before the start of construction.

기준층 평면분할 데이터 베이스(13)는 1개층을 일반적으로 2개의 공구 존으로 분할한 정보를 저장한다. The reference layer plane division database 13 stores information obtained by dividing one layer into two tool zones in general.

여기서 공구분할의 기준은 콘크리트를 타설하는 단위이다. 예를 들어 101동에 4개의 세대와 코어 2개로 구성되는 경우, 901호와 902호 및 코어 1번을 포함하는 A공구는 콘크리트를 월요일에 타설하고 나머지 B공구(903호, 904호, 코어 2번)는 수요일에 타설한다.Here, the criterion for tool division is the unit to cast concrete. For example, if building 101 consists of four generations and two cores, tool A, which includes 901, 902, and core 1, will cast concrete on Monday and the rest of tool B (903, 904, core 2). Times) pour on Wednesday.

자재 수량 데이터 베이스(14)는 세대별 실별 벽체 및 슬라브의 형틀, 철근의 수량정보를 저장한다. 예를 들어 101동 9층 901호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 벽체 및 슬라브의 거푸집과 철근 수량에 관한 정보를 저장한다. The material quantity database 14 stores quantity information of the form of the wall and the slab and the reinforcing bars for each room. For example, it stores information about the number of formwork and reinforcing bars of slabs and walls on the porch and the walls of the entrance porch.

상기 수량은 적산 전문회사에서 일반적으로 산출하고 있는 기존의 업무에 해당한다.The quantity corresponds to an existing task that is generally calculated by a professional company.

작업자의 개인별 작업생산성 데이터 베이스(15)는 형틀 작업자, 철근 작업자의 개인별 1일 시공능력 또는 시간당 시공능력에 관한 정보를 저장한다.The worker's individual work productivity database 15 stores information about a person's daily construction ability or construction capability per hour of the mold worker and the rebar worker.

예를 들어 철근 작업자 1번인 홍길동은 과거 기록상 벽체 철근을 하루에 1.2톤을 시공하며 슬라브 철근은 1.5톤을 시공하는 능력을 나타내고 있다.For example, Hong Gil-dong, the first reinforcing bar worker, has recorded 1.2 tons of wall reinforcing bars per day and 1.5 tons of slab rebars.

공정표 데이터 베이스(16)는 층별 세대별 작업일정을 나타낸 공사 일정이며 형틀 공사, 철근공사를 포함한다.The schedule table database 16 is a construction schedule showing a work schedule for each floor, and includes a frame construction and a reinforcement construction.

예를 들어 101동 9층 901호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 벽체 및 슬라브의 거푸집과 철근 시공에 관한 일자 및 시간 정보를 나타낸다. For example, it displays the date and time information on the construction of reinforcement and reinforcement of walls and slabs on the porch, the room, the living room, the kitchen, the study room, the bathroom, the bathroom, the bathroom and the porch.

작업자 배정 데이터 베이스(17)는 동별 층별 세대별 실별 부재에 대한 작업자를 배정한 결과를 저장한다. 예를 들어 101동 9층 901호의 안방 벽체 1번을 어떤 작업자가 언제 시공해야 하는지에 관한 내용을 나타낸다. 안방 벽체 1번 철근은 하루 만에 시공할 수 있으므로 철근 작업자 1번인 홍길동을 배정한다.The worker assignment database 17 stores a result of assigning a worker to each member of each room. For example, it describes the contents of which worker should construct the inner wall No. 1 of building 101, 9, 901. Reinforcement wall No. 1 can be constructed in one day, so we assign Hong Gil-dong, the reinforcement worker No. 1.

도 2 내지 4는 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 방법의 전체 흐름도이다.2 to 4 is a flow chart of the construction method analysis method for individual work assignment according to an embodiment of the present invention.

먼저 일 실시예에 따른 도 2를 참조하면, 아파트 골조의 건축도면, 구조도면, BIM 도면을 저장한다(S10). 아파트 각 동 1개 층을 2개의 존으로 분할한다(S20). 예를 들어 'ㄱ'자 모양의 평면 아파트에서 A존(101호, 102호, 코어 1번)과 B존(103호, 104호, 코어 2번)으로 2개로 분할한다.First, referring to FIG. 2 according to an embodiment, an architectural drawing, a structural drawing, and a BIM drawing of an apartment frame are stored (S10). Each floor of the apartment is divided into two zones (S20). For example, in a flat apartment of a 'b' shape, it is divided into two zones A (101, 102, core 1) and B zone (103, 104, core 2).

상기 분할된 A존과 B존에 대한 공정표를 작성하여 공정표 데이터 베이스(16)에 저장한다(S30). A process table for the divided zones A and B is prepared and stored in the process table database 16 (S30).

101동과 102동은 짝을 이루어 A공구로 분할되고, 각 동의 A존과 B존의 1개층 작업일수는 4일이며, A존과 B존은 2일 차이로 진행하고, 101동과 102동은 1일 차이 또는 3일 차이로 진행하는 공정표를 작성한다. 공정표의 최소 시간단위는 시간대별 또는 적어도 오전 오후 단위이다.Building 101 and 102 are paired and divided into tool A. The work days of each floor in zones A and B are 4 days, and zones A and B are 2 days apart. Prepares a timetable that progresses by one day or three days. The minimum time unit of the timetable is hourly or at least AM afternoon.

1일차에는 101동 A존 101호, 102호, 코어 1번에 대하여 먹매김, 철근 양중, 벽체 철근 설치, 벽체 형틀 설치 작업이 포함된다.The first day includes the filling, rebar lifting, wall reinforcement, and wall frame installation work for Building 101, Zone A, 101, and 102.

다음으로 각 실별 부재별 형틀 및 철근의 수량을 산출하여 자재 수량 데이터 베이스(14)에 저장한다(S40). Next, the quantity of molds and reinforcing bars for each thread is calculated and stored in the material quantity database 14 (S40).

예를 들어 101동 101호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 각각의 벽체와 슬라브에 대하여 거푸집과 철근 수량을 저장한다.For example, the number of formwork and reinforcing bars is stored for each wall and slab for the living room, kitchen, study room, small room, toilet, toilet, and porch.

그리고 각 실별 부재별 형틀 및 철근의 수량을 작업자 개인별 작업생산성 데이터 베이스(15)의 작업자 생산성으로 나누어 각 부재에 대해 작업자를 배정한다(S50).In addition, the worker is assigned to each member by dividing the number of molds and reinforcing bars for each room by the worker productivity of the work productivity database 15 for each worker (S50).

예를 들어 101동 101호의 안방의 4개의 벽체 중 벽체 1번과 2번의 철근이 각각 1,000kg이고 철근 작업자 1번인 홍길동의 생산성이 1일 1,500kg이면 벽체 1번에 과 철근 작업자 1번을 벽체 1번에 100% 배정하고 벽체 2번에 50%를 배정한 후, 2번 벽체의 나머지 50%에는 다음으로 2번 철근 작업자를 배정한다.For example, if the 1st and 2nd reinforcing bars are 1,000kg each of the four walls in the main room of 101-101, and the productivity of Hong Gil-dong, the reinforcing worker 1, is 1,500kg per day, the wall 1 and the reinforcing worker 1 will be wall 1 Allocate 100% at time, 50% at Wall 2, and the next two rebar workers at 50% of Wall 2.

위와 같은 방식으로 101호부터 104호 순서로 형틀 및 철근 작업자를 배정하여 1개층 배정을 완료한다.In the same way as above, the floor and the reinforcement workers are assigned in the order of No. 101 to No. 104 to complete the first floor assignment.

다음으로 그 상층인 2층에 대하여 작업자를 1층에서의 배정과 같은 방식으로 배정한다(S60). 그리고 마지막 층인 35층까지의 배정을 완료하여 골조공사에 대한 배정을 완료한다.Next, the worker is assigned to the second floor, which is the upper floor, in the same manner as in the first floor (S60). The final floor is assigned to the 35th floor to complete the allocation of the frame.

배정이 완료되면, 시간대별 오전 오후 단위로 필요한 작업자수를 산출하여 작업자 소요추이를 산출한다(S70). When the assignment is completed, the worker required trend is calculated by calculating the required number of workers on a morning and afternoon basis for each time zone (S70).

작업자수 추이를 판단한 결과 작업자수가 불규칙하면(S80), 다른 배정 안을 적용하여 인원을 산출하는 과정을 되풀이 한다(S90).When the number of workers is determined as a result of determining the number of workers (S80), the process of calculating the number of people by applying another assignment plan is repeated (S90).

다수의 경우의 수에 대한 작업자 배정안에 대한 시뮬레이션을 통해 시뮬레이션별 Simulation by worker simulation for the number of cases

인원수 소요추이, 작업시간에 대한 정량적인 분석 지수 지표를 산출한다(S100). The quantitative analysis index indicator for the number of people, the working time is calculated (S100).

이중 가장 우수한 작업자 배정안을 판단한 후 제1안으로 선정한다(S110).After determining the most excellent worker assignment among these is selected as the first proposal (S110).

상기 단계에서 제1안이 선정되면 부재리스트와 그에 대응하는 작업자 리스트를 표 또는 평면도 상에 나타내어 용이하게 알 수 있고 관리할 수 있도록 나타낸다(S120).When the first proposal is selected in the above step, the member list and the corresponding worker list are displayed on a table or a plan view so as to be easily understood and managed (S120).

이상의 과정을 통해 작업자 개인별 작업자 배정 계획이 수립완료 되었다.Through the above process, the worker assignment plan for each worker was completed.

상기 단계를 통해 산출된 작업자 배정 결과를 작업자 배정 데이터 베이스(17)에 저장한다(S130).The worker assignment results calculated through the above steps are stored in the worker assignment database 17 (S130).

다음은 공사착수에 따라 공사실적을 수집하는 단계를 설명한다.The following describes the steps to collect the construction results according to the start of construction.

1층 101동 101호 공사가 시작되면 1일차에 작업자를 투입하고 오전 오후 또는 1일차 작업 실적을 수집한 후 작업자 개인별 작업생산성 데이터 베이스(15)에 저장한다(S140).When the construction of the first floor 101 building 101 is started, the worker is put into the first day, and the work results are collected in the morning afternoon or the first day, and then stored in the work productivity database 15 for each worker (S140).

실적이 수집되면 상기(S50)의 계획단계의 생산성 값과 상기 (S140)단계의 실적 생산성 값을 비교하여 차이를 산출한다(S150). When the results are collected, the difference is calculated by comparing the productivity value of the planning step of S50 and the performance productivity value of the step S140 (S150).

그리고 산출된 생산성 데이터는 작업자 개인별 작업생산성 데이터 베이스(15)에 저장한다. 데이터는 공사명, 동, 층, 세대, 방의 명칭으로 구성된 위치 및 부위 정보에 대한 생산성 및 작업시간 정보를 포함한다.The calculated productivity data is stored in the work productivity database 15 for each worker. The data includes productivity and working time information for location and site information consisting of construction name, building, floor, household, and room name.

생산성 차이의 분석결과에 따라, 작업자 개인의 생산성 차이(작업한 철근 수량 차이)를 산출하여 미달되는 작업자와 초과하는 작업자를 판단한다(S160). According to the results of the analysis of the productivity difference, the productivity difference (working rebar quantity difference) of the individual worker is calculated to determine the less than worker and the excess worker (S160).

미달되는 공사구역에는 작업자를 추가로 투입하거나 교체하여 각 공사 구역별로 계획된 공사일정과 작업시간을 준수할 수 있도록 조치한다(S170).In the case of the construction zone that is not met, additionally inject or replace workers to comply with the planned construction schedule and working time for each construction zone (S170).

위와 같은 방식으로 계획 대비 실적을 비교 분석하고 차이에 대한 보정을 지속적이고 체계적으로 진행하는 과정을 반복한다(S180).In the above manner, the process of comparing and analyzing the performance compared to the plan and correcting the difference is continuously and systematically repeated (S180).

골조공사 몇 개층 단위, 5개층 또는 10개층 단위 그리고 골조공사 완료 시점에 대한 개인별 및 전체 생산성 분석을 실시한다(S190).The individual and total productivity analysis is performed for several floor units, five or ten floor units, and when the framework is completed (S190).

이상의 과정을 통해 작업자가 101동과 102동의 구역을 이동해가면서 한 개층 한 개층 시공하는 과정에 대한 공사방법을 분석하였다.Through the above process, the construction method was analyzed for the process of building one floor one by one while moving the 101 and 102 areas.

다음은 본 발명의 실제 공사에 대한 적용의 실시예를 설명한다.The following describes an embodiment of the application to the actual construction of the present invention.

도 5는 본 발명의 일실시예에 따른 판상형 아파트의 공사개요이다. 조감도를 보면 아파트 동수는 20개동 3,000세대 이상의 초대형 아파트 단지이며 중앙의 배치도를 보면 평면은 'ㄱ'자 형태이고 4개 세대와 2개의 코어로 구성되어 있다. 하단 세대 평면도를 보면 침실 1(안방) 작은방 거실 부엌 화장실 등이다. 5 is a construction overview of a plate-like apartment according to an embodiment of the present invention. In the bird's-eye view, the number of apartments is 20 apartment buildings of over 3,000 households. In the central layout, the plane is shaped like 'a' and consists of four households and two cores. The bottom generation floor plan is Bedroom 1 (room), small living room, kitchen and bathroom.

구조는 철근콘크리트 벽식구조와 무량판 슬라브이다.The structure is reinforced concrete wall structure and flat plate slab.

도 6은 본 발명의 일실시예에 따른 골조공사 공정표이다. 각 동은 A존(2세대와 코어 1번)과 B존(2개 세대와 코어 2번)으로 분할되고, A존과 B존은 층당 4일 싸이클이며, 2일차이로 진행된다. 101동과 102동은 A공구로 분할되고 1일 또는 3일 차이로 진행된다.Figure 6 is a skeleton construction process table according to an embodiment of the present invention. Each building is divided into Zone A (2nd Generation and Core No. 1) and Zone B (2nd Generation and Core No. 2). Zones A and B are 4 days cycles per floor, with 2 days difference. Buildings 101 and 102 are divided into section A and run one or three days apart.

예를 들어 101동 5층 A존(501호, 502호, 코어 1번)은 월요일에 콘크리트를 타설하고 102동 5층 A존(501호, 502호, 코어 1번)은 화요일에 타설하고, 101동 5층 B존(503호, 504호, 코어 2번)은 수요일에 콘크리트를 타설하고, 102동 5층 B존(503호, 504호, 코어 2번)은 목요일에 타설하는 일정으로 진행한다.For example, Building 101 5-F Zone A (501, 502, Core 1) will be poured concrete on Monday, and Building 102 5-F Zone A (501, 502, Core 1) will be poured on Tuesday. Building 5, B-floor B (503, 504, Core 2) will be concrete on Wednesday, and building 102, 5F B-zone (503, 504, Core 2) will be poured on Thursday. do.

도 6보다 하위 레벨의 상세 공정표로서 일자별 존별 세대별 부재별 상세 공정표는 별도로 작성되고 저장된다.As a detailed process table at a lower level than FIG. 6, a detailed process table for each member for each generation for each zone is created and stored separately.

도 7은 본 발명의 일실시예에 따른 101동 501호 세대의 각각의 벽체 부재에 대한 번호부여를 세대 평면도상에 나타낸 것이다. 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 벽체 및 슬라브의 거푸집과 철근 부재 리스트를 포함한다.Figure 7 shows the numbering for each wall member of the 101-501 generation, in accordance with an embodiment of the present invention on a household plan view. Home Living Room Kitchen Study Room Small Room Toilet 1 Toilet 2, wall and slab formwork and reinforcement list for porch.

도 8은 본 발명의 일실시예에 따른 도 7의 각각의 부재에 대한 각 실별 벽체 부재에 대한 철근 수량을 나타낸 것이다. 이 외에 슬라브 철근, 벽체 형틀, 슬라브 형틀 수량을 산출된다.FIG. 8 illustrates the rebar quantity for each wall member for each room of each member of FIG. 7 according to an exemplary embodiment of the present invention. In addition, the number of slab reinforcing bars, wall molds, and slab molds is calculated.

상기 부재별 수량은 적산 전문회사에서 일반적으로 산출하고 있으나 자재 종류와 규격별로 층별로 집계하므로 다시 세대 및 부재별로 나눌 필요가 있다.The quantity for each member is generally calculated by a professional company for integration, but it is necessary to divide it again by generation and member because it is aggregated by floor by material type and standard.

도 9는 본 발명의 일실시예에 따른 작업자의 개인별 생산성 실적 데이터를 나타낸 것이다. 철근 작업자 1번인 홍길동의 벽체 철근과 슬라브 철근의 1일 생산성 데이터가 표시되어 있다. 철근 콘크리트 전문회사에 속하는 형틀 작업자와 철근 작업자의 생산성 데이터의 일부가 표시되어 있다. Figure 9 shows the individual productivity performance data of the worker according to an embodiment of the present invention. The daily productivity data of the wall and slab reinforcement of Hong Gil-dong, the reinforcement worker number 1, is displayed. Some of the productivity data of the frameworkers and rebar workers belonging to the reinforced concrete company are shown.

형틀 작업자의 생산성 데이터도 별도로 산출되고 관리된다.The productivity data of the molder is also calculated and managed separately.

도 10은 본 발명의 일실시예에 따른 도 8의 각각의 부재에 작업자를 배정한 내용을 나타낸 것이다. 101동 501호 안방 벽체 01번에는 철근작업자 1번 홍길동이 배정되어 있고, 주방 벽체 04번에는 철근작업자 1번 홍길동과 철근 5번 작업자가 동시에 배정되어 있다.10 is a view showing the contents of assigning an operator to each member of FIG. 8 according to an embodiment of the present invention. The reinforcement worker No. 1 Hong Gil-dong is assigned to the house wall 01, and the reinforcement worker No. 1 Hong-gil-dong and the rebar No. 5 worker are assigned to the kitchen wall 04 at the same time.

형틀 작업자도 위와 같은 방식으로 각 실에 배정되게 된다.The molder will be assigned to each room in the same way.

도 11은 본 발명의 일실시예에 따른 일별 작업자의 이동경로를 도면상에 나타낸 것이다. 철근 작업자 1번 홍길동은 1일차에는 101동 A존인 501호에서 작업하고 2일차에는 102동 A존 501호에서 작업하고 3일차에는 101동 B존인 503호에서 작업을 하게 되는 내용을 나타내고 있다.11 is a view showing a movement route of a daily worker according to an embodiment of the present invention. Reinforcement worker No. 1 Hong Gil-dong is working on 501, A zone 101, on the first day, 102 A on zone 501, on the second day, and 503 on B zone 101 on the third day.

도 12는 본 발명의 일실시예에 따른 계획 대비 실적과의 차이를 나타낸 것이다. 철근 작업자 1번 홍길동은 1일차에는 101동 A존인 501호에서 작업하였으나 계획된 수량을 시공하지 못하였다. 이에 따라 관리자는 작업자를 추가로 투입하거나 야간작업을 지시하거나 작업자 교체를 실시할 수 있다.Figure 12 shows the difference with the performance compared to the plan according to an embodiment of the present invention. Reinforcement worker No. 1 Hong Gil-dong worked in Room 501, Building 101, on Day 1, but failed to construct the planned quantity. This allows managers to add additional workers, direct night work, or replace workers.

원인과 문제점을 개인별로 정확하게 파악할 수 있으므로 필요한 조치도 신속하고 용이하게 취할 수 있다. 이에 따라 정해진 공정표대로 공사를 진행하는 능력이 높아진다.The cause and problem can be accurately identified by individual, so that necessary actions can be taken quickly and easily. As a result, the ability to proceed with the construction according to the set schedule.

도 13은 본 발명의 일실시예에 따른 101동과 102동을 합한 2개동의 철근 작업자의 일별 소요인원 추이를 나타낸다. 소요인원이 균등함을 나타내며 월요일에 101동에서 남은 인원이 102동에서 작업하면 반대의 경우로 화요일에는 102동에서 남은 인원이 101동에서 작업하면서 전체적인 밸런스를 나타내고 있다. FIG. 13 is a diagram showing the daily shift of required number of reinforcing worker of two buildings, which combined 101 and 102, according to an embodiment of the present invention. The number of people required is equal, and if the number of people left in building 101 on Monday is working in 102, the opposite is the case. On Tuesday, the number of people remaining in building 102 is working in 101, showing the overall balance.

이와 같은 균등한 작업자 수요는 작업자 손실을 줄여 인건비를 절감하고 품질을 확보하고 안전사고를 예방하여 공사기간과 작업시간을 단축하고 빠른 시간에 동일한 부재를 시공함에 따라 학습효과를 통한 생산성 향상을 나타내게 된다.This equal demand for workers reduces labor loss, reduces labor costs, secures quality, prevents safety accidents, shortens construction periods and working hours, and improves productivity through learning effects as soon as the same members are constructed. .

상술한 개인별 작업자 배정 방법으로부터 팀별 작업자 배정방법을 적용할 수 있으며 철근 콘크리트 전문 건설회사는 상기 개념과 사상을 이용하여 효율적인 작업자 배정과 운용관리를 할 수 있을 것이다.The worker assignment method for each team can be applied from the above-mentioned individual worker assignment method, and a reinforced concrete construction company can perform efficient worker assignment and operation management using the concepts and ideas.

이상과 같이 본 발명은 아파트 골조공사의 핵심인 철근 및 형틀 작업자의 최소단위인 작업자 개인별 작업계획을 수립할 수 있는 작업자 운용방법을 목적으로 한다.As described above, an object of the present invention is to provide a method for operating a worker who can establish a work plan for each worker, which is the minimum unit of reinforcing bar and frame worker, which is the core of apartment framing.

작업해야할 대상인 형틀과 철근 수량과 이를 소화하는 작업자의 개인 역량에 따라 작업시간과 순서를 결정하여 최적의 공사방법을 위한 작업자 배정 방법을 분석하여 최적의 인력운용 방법을 찾아내는 것이다. It is to find the optimal manpower management method by analyzing the work assignment method for the optimal construction method by determining the working time and order according to the mold and the number of reinforcing bars and the individual capacity of the worker to extinguish it.

본 실시예서는 판상형 아파트에 방법을 적용하였으나 타워형 아파트, 주상복합, 오피스텔 골조공사도 동일하거나 유사한 방법과 순서로 골조공사를 시공하므로 상기 방법이 동일하게 적용될 수 있음을 건설기술자들은 명백히 알 수 있을 것이다.In the present embodiment, the method is applied to the flat-type apartments, but the construction engineers will clearly know that the above-described methods can be applied in the same manner or similar to the construction of the tower-type apartments, the residential complex, and the officetel framing. .

개인별 작업 배정 방법을 위한 공사방법 분석장치(10)
제어부(11)
건축도면 데이터베이스(12)
기준층 평면분할 데이터 베이스(13)
자재 수량 데이터 베이스(14)
작업자 개인별 작업생산성 데이터 베이스(15)
공정표 데이터 베이스(16)
작업자 배정 데이터 베이스(17)
Construction Method Analysis Apparatus for Individual Work Assignment Method (10)
Control unit 11
Architectural Drawings Databases (12)
Reference Layer Planarization Database (13)
Material Quantity Database (14)
Worker Productivity Database by Worker (15)
Milestone Database (16)
Worker Assignment Database (17)

Claims (2)

아파트 골조의 건축도면, 구조도면, BIM 도면을 저장하는 단계(S10) ;
아파트 각 동 1개 층을 2개의 존으로 분할하는 단계 (S20) ;
상기 2개로 분할된 존에 대한 공정표를 작성하여 공정표 데이터 베이스에 저장하는 단계 (S30) ;
각 실별 부재별 형틀 및 철근의 수량을 산출하여 자재 수량 데이터 베이스에 저장하는 단계 (S40) ;
각 실별 부재별 형틀 및 철근의 수량을 작업자 개인별 작업생산성 데이터 베이스의 작업자 생산성으로 나누어 각 부재에 대해 작업자를 배정하는 단계(S50) ;
그 상층인 각 층에 대하여 작업자를 1층에서의 배정과 같은 방식으로 배정한는 단계 (S60) ;
시간대별 오전 오후 단위로 필요한 작업자수를 산출하여 작업자 소요추이를 산출하는 단계 (S70) ;
부재리스트와 그에 대응하는 작업자 리스트를 표 또는 평면도 상에 나타내는 단계 (S80) ;
산출된 작업자 배정 결과를 작업자 배정 데이터 베이스에 저장하는 단계 (S90) ;
작업자를 투입하고 오전 오후 또는 일별 작업 실적을 수집한 후 작업자 개인별 작업생산성 데이터 베이스에 저장하는 단계 (S100) ;
계획단계의 생산성 값과 실적 생산성 값을 비교하여 차이를 산출하고 작업자 개인별 작업생산성 데이터 베이스에 저장하는 단계 (S110)를 포함하는 공동주택 골조공사 작업자의 작업장소 이동경로 분석 방법.
Storing an architectural drawing, a structural drawing, and a BIM drawing of the apartment frame (S10);
Dividing one floor of each apartment building into two zones (S20);
Creating a milestone for the two divided zones and storing the milestone in a milestone database (S30);
Calculating the quantity of form and reinforcing bar for each room member and storing the quantity in the material quantity database (S40);
(S50) assigning a worker to each member by dividing the number of molds and reinforcing bars for each room by worker productivity in a work productivity database for each worker;
Assigning a worker to each floor which is the upper floor in the same manner as in the first floor (S60);
Calculating a worker requirement trend by calculating a required number of workers in the morning and afternoon unit by time (S70);
Displaying an absence list and a corresponding operator list on a table or a plan view (S80);
Storing the calculated worker assignment results in a worker assignment database (S90);
Injecting the worker and collecting the morning afternoon or daily work performance and storing in a work productivity database for each worker (S100);
Comparing the productivity value and the performance productivity value of the planning stage to calculate the difference and store in the work productivity database for each worker (S110) comprising the step of moving the work site movement path analysis of the apartment house framing construction workers.
제어부(11), 건축 도면 데이터 베이스(12), 기준층 평면 공구 분할 데이터 베이스(13), 자재 수량 데이터 베이스(14), 작업자 개인별 작업생산성 데이터 베이스(15), 공정표 데이터 베이스(16) 및 작업자 배정 데이터 베이스(17)를 포함하고 상기 제어부는 제1항의 방법을 실행하는 동주택 골조공사 작업자의 작업장소 이동경로 분석 시스템.
Control unit 11, building drawing database 12, reference layer planar tool splitting database 13, material quantity database 14, work productivity database 15 for each worker, process table database 16 and worker assignment A moving place analysis system for a workplace of a building construction worker including a database (17), wherein the controller executes the method of claim 1.
KR1020180019576A 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction KR102613585B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020180019576A KR102613585B1 (en) 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
KR1020230178158A KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180019576A KR102613585B1 (en) 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020230178158A Division KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Publications (2)

Publication Number Publication Date
KR20190099747A true KR20190099747A (en) 2019-08-28
KR102613585B1 KR102613585B1 (en) 2023-12-12

Family

ID=67775293

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1020180019576A KR102613585B1 (en) 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
KR1020230178158A KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Family Applications After (1)

Application Number Title Priority Date Filing Date
KR1020230178158A KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Country Status (1)

Country Link
KR (2) KR102613585B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102253818B1 (en) * 2020-09-10 2021-05-18 윤지용 Method of providing construction materials production and server performing the same

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002056048A (en) * 2000-08-08 2002-02-20 Maeda Corp System and method for construction scheduling
KR20070077159A (en) * 2007-06-25 2007-07-25 광운대학교 산학협력단 Failure reason analysis system
KR20120068114A (en) * 2010-12-17 2012-06-27 현대건설주식회사 Method of construction planning of supertall buildings

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002056048A (en) * 2000-08-08 2002-02-20 Maeda Corp System and method for construction scheduling
KR20070077159A (en) * 2007-06-25 2007-07-25 광운대학교 산학협력단 Failure reason analysis system
KR20120068114A (en) * 2010-12-17 2012-06-27 현대건설주식회사 Method of construction planning of supertall buildings

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102253818B1 (en) * 2020-09-10 2021-05-18 윤지용 Method of providing construction materials production and server performing the same

Also Published As

Publication number Publication date
KR102613585B1 (en) 2023-12-12
KR20230169923A (en) 2023-12-18

Similar Documents

Publication Publication Date Title
Elbeltagi et al. Dynamic layout of construction temporary facilities considering safety
Kavanagh SIREN: A repetitive construction simulation model
Huang et al. Planning gang formwork operations for building construction using simulations
US20060074609A1 (en) System and method for determining variance in building structures
KR20240004188A (en) Structure construction method for multiple buildings with wall structure
KR20230169923A (en) An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
US8244569B2 (en) Non-destructive element splitting using location-based construction planning models
Safa et al. A decision-making method for choosing concrete forming systems
CN117993671A (en) Construction dispatching method, system and storage medium
Tam et al. Evaluation of construction methods and performance for high rise public housing construction in Hong Kong
Sacks et al. A project model for an automated building system: design and planning phases
Rosenfeld Innovative construction methods
Sommer Project management for building construction: 35 years of innovation at drees & sommer
JPH0589211A (en) Integrated production managing system for building
Okodi-Iyah A comparative evaluation of the environmental impact of prefabrication versus conventional construction in UAE’s construction industry
Yi et al. Network creation and development for repetitive-unit projects
Blyth et al. Developing a framework for a standardized works programme for building projects
Leung et al. Scheduling for high-rise building construction using simulation techniques
Williamstown Sterling and Francine Clark Art Institute
EP4407504A1 (en) Building planning system and method
Zhang Construction productivity improvement through industrialized construction methods
Zholtikov et al. Improving the efficiency of applying the method of slab and floor lifting
Florez et al. Labor management in masonry construction: a sustainable approach
Desogus et al. The building information modeling for the retrofitting of existing buildings. A case study in the University of Cagliari.
Abidin Simulation of industrialised building system formation for housing construction

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant