KR102253818B1 - Method of providing construction materials production and server performing the same - Google Patents

Method of providing construction materials production and server performing the same Download PDF

Info

Publication number
KR102253818B1
KR102253818B1 KR1020200116004A KR20200116004A KR102253818B1 KR 102253818 B1 KR102253818 B1 KR 102253818B1 KR 1020200116004 A KR1020200116004 A KR 1020200116004A KR 20200116004 A KR20200116004 A KR 20200116004A KR 102253818 B1 KR102253818 B1 KR 102253818B1
Authority
KR
South Korea
Prior art keywords
households
frame
receiving
apartment
household
Prior art date
Application number
KR1020200116004A
Other languages
Korean (ko)
Inventor
윤지용
Original Assignee
윤지용
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤지용 filed Critical 윤지용
Priority to KR1020200116004A priority Critical patent/KR102253818B1/en
Application granted granted Critical
Publication of KR102253818B1 publication Critical patent/KR102253818B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Manufacturing & Machinery (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

A building material production management method performed in a building material production management server according to an embodiment of the present invention comprises the steps of: receiving material production information for each site through a production standard set registration procedure to create a production standard set; upon receiving apartment information corresponding to each of empty apartment blocks, generating a frame diagram by using a production reference set and apartment information input to each of the empty apartment blocks; upon receiving a material operation processing request message for each generation on the production standard set or the frame diagram, processing the corresponding operation to be performed according to the type of operation; upon receiving a material order request message for each household on the production standard set or the frame diagram, selecting a material for the household and then calculating an order bar for material management by using the required amount of a material; and managing the incoming and outgoing management of a material according to the order bar for material management and the production standard set.

Description

건축 자재 생산 관리 방법 및 이를 실행하는 서버{METHOD OF PROVIDING CONSTRUCTION MATERIALS PRODUCTION AND SERVER PERFORMING THE SAME}Construction material production management method and server executing it {METHOD OF PROVIDING CONSTRUCTION MATERIALS PRODUCTION AND SERVER PERFORMING THE SAME}

본 발명은 건축 자재 생산 관리 방법 및 이를 실행하는 서버에 관한 것이다.The present invention relates to a building material production management method and a server for executing the same.

일반적으로 건설 또는 자재의 생산 현장에서 여러 단계에 걸쳐 발행하는 생산, 위치, 품질, 시공 정보 등의 수집, 관리는 수작업이나 종이문서기록에 의해 처리되기 때문에 소요 시간이 많이 걸리고 정보 누락 등의 문제가 발생한다. In general, collection and management of production, location, quality, and construction information issued over several stages at the construction or material production site are handled by manual or paper document recording, so it takes a lot of time and causes problems such as information omission. Occurs.

예컨대, 건설업은 여러 작업 현장과 회사 사무실이 물리적으로 먼 거리에 위치해 있으며 한 공사 당 적으면 몇 십 개, 많을 경우 수 백여 개에 달하는 여러 회사들이 얽혀있다는 특성상 정보화가 가장 절실하고도 유용하게 쓰일 수 있는 대표적인 분야이다. For example, in the construction industry, informatization is the most desperate and useful due to the nature of the fact that several work sites and company offices are physically located at a long distance, and there are several tens of thousands of companies per construction and hundreds of thousands of companies per construction. It is a representative field.

특히 감리 업무 수행 시 다수의 현장에서 관계된 협력업체별로 사용하는 문서양식 및 구조가 모두 틀리며 70~80% 이상이 시공사에서 보고 받는 문서들이다.In particular, when performing supervision work, the document format and structure used for each partner company involved in a number of sites are all different, and more than 70-80% of the documents are reported by the contractor.

이러한 문서들은 결재 후에 색인화하여 문서 보관함에 보관되고, 현장 프로젝트 종료 시 보존해야 할 문서를 제외하고는 폐기된다. 이 과정에서 많은 문서들이 분실되고, 종료 후에는 대량의 종이문서들이 발생하여 보관이 어려울 뿐만 아니라 문서의 공유나 재활용이 불가능하다.These documents are indexed after approval and stored in the document archive, and discarded except for documents to be preserved at the end of the on-site project. In this process, many documents are lost, and after completion, a large amount of paper documents are generated, making it difficult to store and share or recycle documents.

또한, 자재 생산 공장과 건설 현장의 공사참여기간 정보공유 및 의사소통이 원활하지 못하여 효과적인 자재 수급이 어려우며 관리비용이 발생하고 적시적소에 자재가 공급되지 못하는 문제로 인하여 공사가 지연되는 문제가 발생하고 있다.In addition, there is a problem of delayed construction due to problems in which effective material supply and demand is incurred due to difficulties in sharing and communicating information during the construction participation period between the material production plant and the construction site. have.

따라서, 현장의 관리 감독 업무를 수행하기 위하여 관련 담당자가 직접 현장에 나가 확인하는 불편함을 해소하고, 보다 효과적이며 효율적으로 작업을 진행시킬 수 있도록 작업의 현황 파악을 보다 용이하게 할 수 있는 물류관리 자동화 시스템 또는 통합 모니터링 시스템이 요구되고 있다.Therefore, logistics management that can make it easier to understand the status of work so that the relevant person in charge can directly go to the site to perform the work of management and supervision of the site and check it, and so that the work can be carried out more effectively and efficiently. An automated system or an integrated monitoring system is required.

본 발명은 주택을 건축할 때 자재의 시공 계획, 생산 계획, 작업 지시, 출고 지시 등의 작업 처리를 통합하여 처리할 수 있도록 하는 건축 자재 생산 관리 방법 및 이를 실행하는 서버를 제공하는 것을 목적으로 한다. It is an object of the present invention to provide a building material production management method and a server for executing the same, in which work processing such as material construction plan, production plan, work order, and release order can be integrated and processed when building a house. .

또한, 본 발명은 현장 별 골조도를 구성한 후 골조도를 통해 세대 별 제품 설정, 작업 지시, 생산, 출고 및 시공 결과를 처리함으로써 전체의 동의 작업 현황을 한 화면을 통해 확인할 수 있도록 하는 건축 자재 생산 관리 방법 및 이를 실행하는 서버를 제공하는 것을 목적으로 한다. In addition, the present invention is a building material production that allows you to check the overall consent work status on one screen by configuring the frame map for each site and then processing the product setting, work instruction, production, delivery, and construction results for each generation through the frame drawing. It aims to provide a management method and a server that executes it.

또한, 본 발명은 자재 주문 시 자재의 소요량을 이용하여 자재 관리용 주문바를 산출한 후, 자재 관리용 주문바 및 생산 기준 세트에 따라 상기 자재의 입출고 관리를 진행할 수 있도록 하는 건축 자재 생산 관리 방법 및 이를 실행하는 서버를 제공하는 것을 목적으로 한다. In addition, the present invention is a building material production management method for calculating the material management order bar using the required amount of the material when ordering materials, and then performing the input/output management of the material according to the material management order bar and production standard set, and Its purpose is to provide a server that executes this.

본 발명의 목적들은 이상에서 언급한 목적으로 제한되지 않으며, 언급되지 않은 본 발명의 다른 목적 및 장점들은 하기의 설명에 의해서 이해될 수 있고, 본 발명의 실시예에 의해 보다 분명하게 이해될 것이다. 또한, 본 발명의 목적 및 장점들은 특허 청구 범위에 나타낸 수단 및 그 조합에 의해 실현될 수 있음을 쉽게 알 수 있을 것이다.The objects of the present invention are not limited to the above-mentioned objects, and other objects and advantages of the present invention that are not mentioned can be understood by the following description, and will be more clearly understood by examples of the present invention. In addition, it will be easily understood that the objects and advantages of the present invention can be realized by the means shown in the claims and combinations thereof.

이러한 목적을 달성하기 위한 건축 자재 생산 관리 서버에서 실행되는 건축 자재 생산 관리 방법은 생산 기준 세트 등록 절차를 통해 현장 별 자재 생산 정보를 수신하여 생산 기준 세트를 생성하는 단계, 공백 아파트 블록 각각에 해당하는 아파트 정보를 수신하면, 상기 생산 기준 세트 및 상기 공백 아파트 블록 각각에 입력된 아파트 정보를 이용하여 골조도를 생성하는 단계, 상기 생산 기준 세트 또는 상기 골조도 상의 세대 별 자재 작업 처리 요청 메시지를 수신하면 작업 종류에 따라 해당 작업이 수행되도록 처리하는 단계, 상기 생산 기준 세트 또는 상기 골조도 상의 세대 별 자재 주문 요청 메시지를 수신하면, 해당 세대의 자재를 선택한 후 해당 자재의 소요량을 이용하여 자재 관리용 주문바를 산출하는 단계 및 상기 자재 관리용 주문바 및 생산 기준 세트에 따라 상기 자재의 입출고 관리를 진행하는 단계를 포함한다.To achieve this purpose, the building material production management method executed on the building material production management server is the step of generating a production standard set by receiving material production information for each site through the production standard set registration process, corresponding to each blank apartment block. Upon receiving the apartment information, generating a frame map using the apartment information input to each of the production standard set and the blank apartment block, receiving a request message for processing material work for each generation on the production standard set or the frame map The step of processing so that the work is performed according to the type of work, when receiving a message for requesting a material order for each generation on the production standard set or the framework, select a material for the corresponding generation and order for material management using the required amount of the material And calculating a bar, and performing input/output management of the material according to the material management order bar and a set of production standards.

또한 이러한 목적을 달성하기 위한 건축 자재 생산 관리 서버는 공백 아파트 블록 각각에 해당하는 아파트 정보를 수신하면, 상기 공백 아파트 블록 각각에 입력된 아파트 정보를 이용하여 골조도를 생성하는 골조도 관리부, 상기 골조도 상의 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 작업 처리 요청 메시지를 수신하면 작업 종류에 따라 해당 작업이 수행되도록 처리하는 작업 처리부, 상기 골조도 상의 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 주문 요청 메시지를 수신하면, 해당 세대의 자재를 선택한 후 해당 자재의 소요량을 이용하여 자재 관리용 주문바를 산출하는 자재 관리용 주문바 산출부 및 상기 자재 관리용 주문바 및 생산 기준 세트에 따라 상기 자재의 입출고 관리를 진행하는 입출고 관리부를 포함한다.In addition, the building material production management server to achieve this purpose, when receiving apartment information corresponding to each blank apartment block, using the apartment information input to the blank apartment block, a frame diagram management unit that generates a frame diagram, the frame A job processing unit that processes the work to be performed according to the type of work upon receipt of a request message for material work processing for a specific household on the road or for a plurality of households selected by the user, a specific household on the framework or a plurality of households selected by the user When receiving the material order request message for, select the material of the relevant household, and then use the material requirements to calculate the material management order bar calculation unit and the material management order bar and production standard set. Accordingly, it includes an input/output management unit for managing the input/output of the material.

전술한 바와 같은 본 발명에 의하면, 주택을 건축할 때 자재의 시공 계획, 생산 계획, 작업 지시, 출고 지시 등의 작업 처리를 통합하여 처리할 수 있다는 장점이 있다.According to the present invention as described above, when building a house, there is an advantage that it is possible to integrate and process work processes such as a construction plan, a production plan, a work instruction, and a delivery instruction.

또한 본 발명에 의하면, 현장 별 골조도를 구성한 후 골조도를 통해 세대 별 제품 설정, 작업 지시, 생산, 출고 및 시공 결과를 처리함으로써 전체의 동의 작업 현황을 한 화면을 통해 확인할 수 있다는 장점이 있다.In addition, according to the present invention, there is an advantage that it is possible to check the overall agreement work status on one screen by processing the product setting, work instruction, production, delivery, and construction results for each generation through the frame level after configuring the frame level for each site. .

또한 본 발명에 의하면, 자재 주문 시 자재의 소요량을 이용하여 자재 관리용 주문바를 산출한 후, 자재 관리용 주문바 및 생산 기준 세트에 따라 상기 자재의 입출고 관리를 진행할 수 있다는 장점이 있다.In addition, according to the present invention, there is an advantage in that the material management order bar can be calculated using the required amount of the material when ordering materials, and then the input/output management of the material can be performed according to the material management order bar and the production standard set.

도 1은 본 발명의 일 실시예에 따른 건축 자재 생산 관리 시스템을 설명하기 위한 네트워크 구성도이다.
도 2는 본 발명의 일 실시예에 따른 건축 자재 생산 관리 서버의 내부 구조를 설명하기 위한 블록도이다.
도 3은 본 발명에 따른 건축 자재 생산 관리 방법의 일 실시예를 설명하기 위한 흐름도이다.
도 4 내지 도 7은 도 3의 실행 과정을 설명하기 위한 예시도이다.
도 8 및 도 9는 본 발명의 일 실시예에 따른 골조도를 설명하기 위한 예시도이다.
1 is a network configuration diagram for explaining a building material production management system according to an embodiment of the present invention.
2 is a block diagram illustrating an internal structure of a building material production management server according to an embodiment of the present invention.
3 is a flowchart illustrating an embodiment of a method for managing production of a building material according to the present invention.
4 to 7 are exemplary diagrams for explaining the execution process of FIG. 3.
8 and 9 are exemplary views for explaining a skeleton view according to an embodiment of the present invention.

전술한 목적, 특징 및 장점은 첨부된 도면을 참조하여 상세하게 후술되며, 이에 따라 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 본 발명의 기술적 사상을 용이하게 실시할 수 있을 것이다. 본 발명을 설명함에 있어서 본 발명과 관련된 공지 기술에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 상세한 설명을 생략한다. 이하, 첨부된 도면을 참조하여 본 발명에 따른 바람직한 실시예를 상세히 설명하기로 한다. 도면에서 동일한 참조부호는 동일 또는 유사한 구성요소를 가리키는 것으로 사용된다.The above-described objects, features, and advantages will be described later in detail with reference to the accompanying drawings, and accordingly, a person of ordinary skill in the art to which the present invention pertains will be able to easily implement the technical idea of the present invention. In describing the present invention, if it is determined that a detailed description of a known technology related to the present invention may unnecessarily obscure the subject matter of the present invention, a detailed description will be omitted. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the drawings, the same reference numerals are used to indicate the same or similar elements.

도 1은 본 발명의 일 실시예에 따른 건축 자재 생산 관리 시스템을 설명하기 위한 네트워크 구성도이다.1 is a network configuration diagram for explaining a building material production management system according to an embodiment of the present invention.

도 1을 참조하면, 건축 자재 생산 관리 시스템은 건축 자재 생산 관리 서버(100) 및 시공사 단말(200_1~200_N)을 포함한다. Referring to FIG. 1, the building material production management system includes a building material production management server 100 and a construction company terminal 200_1 to 200_N.

먼저, 건축 자재 생산 관리 서버(100)는 생산 기준 세트 등록 절차를 통해 현장 별 자재 생산 정보를 수신하여 생산 기준 세트를 생성한다. First, the building material production management server 100 generates a production standard set by receiving material production information for each site through a production standard set registration procedure.

일 실시예에서, 건축 자재 생산 관리 서버(100)는 제품 등록 절차를 통해 현장 별 품명, 모형, 규격, 동, 호수, 층수, 상태, 제조사, 거래처, 현장 및 일자를 수신하여 저장한다. 이때, 건축 자재 생산 관리 서버(100)는 제작하고자 하는 창호의 사양을 수신하면 사양에 따라 자재의 길이 및 수량을 산출한다. In one embodiment, the building material production management server 100 receives and stores the product name, model, standard, building, number of floors, state, manufacturer, customer, site and date for each site through a product registration procedure. At this time, the building material production management server 100 calculates the length and quantity of the material according to the specification upon receiving the specification of the window to be manufactured.

다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 호차 변경 절차를 통해 호차가 변경되면 변경된 호차에 따라 창호의 무게를 산출하여 사양을 변경한다. In another embodiment, when the door car is changed through the door car change procedure, the building material production management server 100 calculates the weight of the window according to the changed door car and changes specifications.

또한, 건축 자재 생산 관리 서버(100)는 생산 기준 세트를 기초로 현장 별 골조도를 구성, 세대 별 제품 설정, 작업 지시, 생산, 출고 및 시공 결과를 처리한다. 이때, 골조도는 줄 아파트의 골조 형식으로 세대 별 제품 관리를 위해 생산된다.In addition, the building material production management server 100 configures a frame diagram for each site based on a production standard set, sets a product for each generation, a work instruction, and processes production, delivery, and construction results. At this time, the frame is produced for product management for each generation in the form of a frame for a row apartment.

먼저, 건축 자재 생산 관리 서버(100)는 공백 아파트 블록을 시공사 단말(200_1~200_N)에 제공하며 공백 아파트 블록 각각에 해당하는 아파트 정보(예를 들어, 아파트 동호수)를 수신한다. 그 후, 건축 자재 생산 관리 서버(100)는 생산 기준 세트 및 공백 아파트 블록 각각에 입력된 아파트 정보를 기초로 골조도를 생성한다. First, the building material production management server 100 provides a blank apartment block to the construction company terminals 200_1 to 200_N, and receives apartment information (eg, number of apartment buildings) corresponding to each blank apartment block. Thereafter, the building material production management server 100 generates a frame diagram based on the apartment information input to each of the production standard set and the blank apartment block.

또한, 건축 자재 생산 관리 서버(100)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 작업 정보를 생성하여 표시한다.In addition, the building material production management server 100 generates and displays job information for a specific household or a plurality of households selected by a user based on the frame roughness.

일 실시예에서, 건축 자재 생산 관리 서버(100)는 사용자에 의해 선택된 복수의 세대에 대한 자재 요청 메시지를 수신하면, 복수의 세대에 시공된 자재 정보를 추출하여 표시한다.In an embodiment, when receiving a material request message for a plurality of households selected by a user, the building material production management server 100 extracts and displays information on materials constructed in the plurality of households.

다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 창호 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. In another embodiment, the building material production management server 100 receives a window job processing request message for a specific household or a plurality of households selected by a user so that the corresponding job is performed according to the type of processing.

예를 들어, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 창호 시공 계획, 창호 생산 계획, 창호 작업 지시, 창호 생산 완료 지시, 창호 출고 지시, 창호 시공 지시 등과 같은 창호 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. For example, the building material production management server 100 may provide a window construction plan, a window production plan, a window work instruction, a window production completion instruction, a window release instruction, a window construction instruction, etc. for a specific household or a plurality of households selected by a user. When the same window operation request message is received, the corresponding operation is performed according to the type of processing.

다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 처리 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. In another embodiment, when receiving a request message for processing a glass processing operation for a specific household or a plurality of households selected by a user, the building material production management server 100 performs the corresponding operation according to the type of processing.

예를 들어, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 발주 일자, 작지 일자 등을 수신하면 유리 발주 일자, 작지 일자 등을 설정할 수 있다.For example, the building material production management server 100 may set a glass order date, a small place date, etc., upon receiving a glass order date, a small place date, etc. for a specific household or a plurality of households selected by a user.

또 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재의 제품군을 설정한다. In another embodiment, the building material production management server 100 sets a product family of materials installed in a specific household according to a request for group designation of materials for a specific household or a plurality of households selected by a user.

또 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재를 하나의 그룹으로 설정한다. In another embodiment, the building material production management server 100 sets materials installed in a specific household as one group according to a request for group designation of materials for a specific household or a plurality of households selected by a user.

또 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 주문 요청 메시지를 수신하면, 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 자재 양을 산출하여 주문 되도록 한다. In yet another embodiment, when receiving a material order request message for a specific household or a plurality of households selected by a user, the building material production management server 100 determines the amount of materials of a specific household or a plurality of households selected by the user. Calculate and order.

또 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 좌우 지정 메시지를 수신하면 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 창호의 핸들의 좌우 방향을 설정한다. 이때, “정”은 생산 기준 세트와 동일한 방향의 핸들을 의미하고, “역”은 생산 기준 세트와 반대 방향의 핸들을 의미한다. In another embodiment, the building material production management server 100 receives the left and right designation messages for a specific household or a plurality of households selected by a user, and the left and right handles of the windows and doors of a specific household or a plurality of households selected by the user are received. Set the direction. At this time, "positive" means a handle in the same direction as the production standard set, and "reverse" means a handle in the opposite direction to the production standard set.

또 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 보류 지정 메시지를 수신하면 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 작업을 보류로 지정한다. 이때, 보류로 지정된 라인은 승강기 철수 후 시공을 진행하기 때문에 보류로 지정되는 것이며, 작업 지시서에서 제외될 수 있다. In another embodiment, the building material production management server 100 designates a job of a specific household or a plurality of households selected by a user as a hold upon receiving a hold designation message for a specific household or a plurality of households selected by a user do. At this time, the line designated as a hold is designated as a hold because construction proceeds after the elevator is withdrawn, and may be excluded from the work order.

또 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 주문바 산출 보류 지정 요청 메시지를 수신하면 해당 세대를 주문바 산출 보류 세대로 지정한다. 이러한 경우, 건축 자재 생산 관리 서버(100)는 주문바 생성 시 해당 세대의 자재 소요량을 제외시킨 후 자재 관리용 주문바를 생성한다. In another embodiment, the building material production management server 100 designates the corresponding household as the order bar calculation pending household when receiving a request message for specifying an order bar calculation hold for a specific household or a plurality of households selected by a user. In this case, the building material production management server 100 generates an order bar for material management after excluding the material requirements of the corresponding generation when generating the order bar.

또한, 건축 자재 생산 관리 서버(100)는 자재 관리용 주문바를 산출한다. In addition, the building material production management server 100 calculates an order bar for material management.

일 실시예에서, 건축 자재 생산 관리 서버(100)는 골조도와 연관된 자재 또는 생산 기준 세트의 자재 중 특정 자재가 선택되면 해당 자재의 정보를 이용하여 주문바를 산출한다. In one embodiment, the building material production management server 100 calculates an order bar using the information of the material when a specific material is selected from among materials related to the frame roughness or materials of the production standard set.

상기의 실시예에서, 건축 자재 생산 관리 서버(100)는 주문바 생성 시 해당 세대가 주문바 산출 보류 세대로 설정되어 있는 경우, 해당 세대의 자재 소요량을 제외시킨 후 자재 관리용 주문바를 생성한다. In the above embodiment, when the order bar is generated, the building material production management server 100 generates an order bar for material management after excluding the material requirement of the corresponding household when the corresponding household is set as the order bar calculation pending household.

또한, 건축 자재 생산 관리 서버(100)는 관리용 주문바에 따라 자재의 입출고 관리를 진행한다. In addition, the building material production management server 100 manages the incoming and outgoing materials according to the management order bar.

또한, 건축 자재 생산 관리 서버(100)는 자재 입고 관리 절차를 통해 지제입고에 대한 제조사, 입고처, 현장, 입고 창고, 제품, 수량 및 금액을 수신하여 저장한다. In addition, the building material production management server 100 receives and stores a manufacturer, a warehouse, a site, a warehouse, a product, a quantity, and an amount for paper receipt through a material warehousing management procedure.

또한, 건축 자재 생산 관리 서버(100)는 자재 출고 관리 절차를 통해 자재출고에 대한 출고 현황, 출고 창고, 제품, 수량 및 금액을 수신하여 저장한다. In addition, the building material production management server 100 receives and stores the delivery status, delivery warehouse, product, quantity, and amount for material delivery through a material delivery management procedure.

또한, 건축 자재 생산 관리 서버(100)는 기준 자재 및 기타 자재의 재고 이동 및 재고 조정을 관리한다. 이때, 재고 이동은 임가공업체, 창고 이동 등에 사용되고, 재고 조정은 임의로 재고를 조정하는데 사용된다. In addition, the building material production management server 100 manages stock movement and inventory adjustment of reference materials and other materials. At this time, the stock movement is used to move the processing company, the warehouse, and the like, and the stock adjustment is used to arbitrarily adjust the stock.

건축 자재 생산 관리 서버(100)는 품질 관리를 위한 공정 코드 관리 절차를 통해 코드 및 공정명을 수신하면 코드 및 공정명을 대응시켜 저장한다. When receiving the code and process name through the process code management procedure for quality control, the building material production management server 100 stores the code and process name in correspondence with each other.

또한, 건축 자재 생산 관리 서버(100)는 품질 관리를 위한 설비 코드 관리 절차를 통해 코드 및 설비명을 수신하면 코드 및 설비명을 대응시켜 저장한다. In addition, when the building material production management server 100 receives the code and the facility name through the facility code management procedure for quality control, the code and the facility name are matched and stored.

또한, 건축 자재 생산 관리 서버(100)는 품질 관리를 위한 품질 검사 코드 관리 절차를 통해 코드, 검사명 및 검사 종류를 수신하면, 코드, 검사명 및 검사 종류를 대응시켜 저장한다. In addition, when the building material production management server 100 receives a code, an inspection name, and an inspection type through a quality inspection code management procedure for quality control, the code, inspection name, and inspection type are stored in correspondence with each other.

시공사 단말(200_1~200_N)은 건축 자재 생산 관리 서버(100)에 접속하여 건축 자재에 대한 정보를 입력하는 사용자가 보유하는 단말이다. The construction company terminals 200_1 to 200_N are terminals held by a user who accesses the building material production management server 100 and inputs information on building materials.

도 2는 본 발명의 일 실시예에 따른 건축 자재 생산 관리 서버의 내부 구조를 설명하기 위한 블록도이다.2 is a block diagram illustrating an internal structure of a building material production management server according to an embodiment of the present invention.

도 2를 참조하면, 건축 자재 생산 관리 서버(100)는 생산 기준 세트 관리부(110), 골조도 관리부(120), 작업 처리부(130), 자재 관리용 주문바 산출부(140) 및 입출고 관리부(150)를 포함한다. Referring to FIG. 2, the building material production management server 100 includes a production standard set management unit 110, a frame level management unit 120, a work processing unit 130, an order bar calculation unit 140 for material management, and an incoming and outgoing management unit ( 150).

생산 기준 세트 관리부(110)는 생산 기준 세트 등록 절차를 통해 현장 별 자재 생산 정보를 수신하여 생산 기준 세트를 생성한다. The production standard set management unit 110 generates a production standard set by receiving material production information for each site through a production standard set registration procedure.

일 실시예에서, 생산 기준 세트 관리부(110)는 제품 등록 절차를 통해 상태, 제조사, 거래처, 현장 및 일자를 수신하여 저장한다. 이때, 건축 자재 생산 관리 서버(100)는 제작하고자 하는 창호의 사양을 수신하면 사양에 따라 자재의 길이 및 수량을 산출한다. In one embodiment, the production standard set management unit 110 receives and stores the status, the manufacturer, the customer, the site and the date through the product registration procedure. At this time, the building material production management server 100 calculates the length and quantity of the material according to the specification upon receiving the specification of the window to be manufactured.

다른 일 실시예에서, 생산 기준 세트 관리부(110)는 호차 변경 절차를 통해 호차가 변경되면 변경된 호차에 따라 창호의 무게를 산출하여 사양을 변경한다. In another embodiment, when the door car is changed through the door car change procedure, the production standard set management unit 110 calculates the weight of the window according to the changed door car and changes specifications.

골조도 관리부(120)는 현장 별 골조도를 구성한 후 골조도를 통해 세대 별 제품 설정, 작업 지시, 생산, 출고 및 시공 결과를 처리한다. 이때, 골조도는 줄 아파트의 골조 형식으로 세대 별 제품 관리를 위해 생산되며, 세대 별 창호 구성 및 좌우 방향이 설정된다.After configuring the frame drawing for each site, the frame drawing management unit 120 processes product setting, work instruction, production, delivery, and construction results for each generation through the frame drawing. At this time, the frame is produced for product management for each generation in the form of a frame of a row apartment, and the window composition and left and right directions for each generation are set.

먼저, 골조도 관리부(120)는 공백 아파트 블록을 시공사 단말(200_1~200_N)에 제공하며 공백 아파트 블록 각각에 해당하는 아파트 정보(예를 들어, 아파트 동호수)를 수신한다. 그 후, 건축 자재 생산 관리 서버(100)는 공백 아파트 블록 각각에 입력된 아파트 정보를 기초로 골조도를 생성한다. First, the framework management unit 120 provides a blank apartment block to the contractor terminals 200_1 to 200_N and receives apartment information (eg, number of apartment buildings) corresponding to each blank apartment block. Thereafter, the building material production management server 100 generates a frame map based on the apartment information input to each blank apartment block.

작업 처리부(130)는 골조도 상의 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 작업 처리 요청 메시지를 수신하면 작업 종류에 따라 해당 작업이 수행되도록 처리한다. The job processing unit 130 processes the corresponding job to be performed according to the type of job when receiving a material job processing request message for a specific generation on the skeleton or a plurality of generations selected by a user.

일 실시예에서, 작업 처리부(130)는 골조도를 기초로 사용자에 의해 선택된 복수의 세대에 대한 자재 요청 메시지를 수신하면, 복수의 세대에 시공된 자재 정보를 추출하여 표시한다.In one embodiment, when receiving a material request message for a plurality of households selected by the user based on the frame roughness, the work processing unit 130 extracts and displays material information constructed in the plurality of households.

다른 일 실시예에서, 작업 처리부(130)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 창호 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. In another embodiment, when receiving a window job processing request message for a specific household or a plurality of households selected by a user on the basis of the frame roughness, the job processing unit 130 causes the job to be performed according to the type of processing.

예를 들어, 작업 처리부(130)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 창호 시공 계획, 창호 생산 계획, 창호 작업 지시, 창호 생산 완료 지시, 창호 출고 지시, 창호 시공 지시 등과 같은 창호 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. For example, the work processing unit 130 is a window construction plan, window production plan, window work instruction, window production completion instruction, window release instruction, window construction for a plurality of households selected by a specific household or user based on the frame roughness Upon receiving a message requesting window work processing such as an instruction, the corresponding work is performed according to the type of processing.

다른 일 실시예에서, 작업 처리부(130)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 처리 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. In another embodiment, when receiving a request message for processing a glass processing operation for a specific household or for a plurality of households selected by a user based on the frame roughness, the job processing unit 130 causes the job to be performed according to the type of processing.

예를 들어, 작업 처리부(130)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 발주 일자, 작지 일자 등을 수신하면 유리 발주 일자, 작지 일자 등을 설정할 수 있다.For example, the job processing unit 130 may set a glass order date, a small place date, etc., upon receiving a glass order date, a small place date, etc. for a specific household or a plurality of households selected by a user based on the frame roughness.

또 다른 일 실시예에서, 작업 처리부(130)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재의 제품군을 설정한다. In another embodiment, the work processing unit 130 sets a product family of materials installed in a specific household according to a request for group designation of materials for a specific household or for a plurality of households selected by a user based on the frame roughness.

또 다른 일 실시예에서, 작업 처리부(130)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재를 하나의 그룹으로 설정한다. In another embodiment, the work processing unit 130 sets materials installed in a specific household as one group according to a request for group designation of materials for a specific household or for a plurality of households selected by a user based on the frame roughness. .

또 다른 일 실시예에서, 작업 처리부(130)는 골조도를 기초로특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 주문 요청 메시지를 수신하면, 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 자재 양을 산출하여 주문 되도록 한다. In another embodiment, when receiving a material order request message for a specific household or a plurality of households selected by a user based on the frame roughness, the work processing unit 130 Calculate the quantity and order.

자재 관리용 주문바 산출부(140)는 자재 관리용 주문바를 산출한다. The material management order bar calculation unit 140 calculates an order bar for material management.

일 실시예에서, 자재 관리용 주문바 산출부(140)는 골조도와 연관된 자재를 추출한 후 자재 중 특정 자재가 선택되면 해당 자재의 정보를 이용하여 주문바를산출한다.In one embodiment, the material management order bar calculation unit 140 extracts a material related to the frame roughness and then calculates an order bar using the information of the material when a specific material is selected from among the materials.

도 3은 본 발명에 따른 건축 자재 생산 관리 방법의 일 실시예를 설명하기 위한 흐름도이다. 도 4 내지 도 7은 도 3의 실행 과정을 설명하기 위한 예시도이다.3 is a flowchart illustrating an embodiment of a method for managing production of a building material according to the present invention. 4 to 7 are exemplary diagrams for explaining the execution process of FIG. 3.

도 3을 참조하면, 건축 자재 생산 관리 서버(100)는 생산 기준 세트 등록 절차를 통해 현장 별 자재 생산 정보를 수신하여 생산 기준 세트를 생성한다(단계 S310).3, the building material production management server 100 generates a production standard set by receiving material production information for each site through a production standard set registration procedure (step S310).

건축 자재 생산 관리 서버(100)는 공백 아파트 블록 각각에 해당하는 아파트 정보를 수신하면, 생산 기준 세트 및 공백 아파트 블록 각각에 입력된 아파트 정보를 이용하여 골조도를 생성한다(단계 S320). When receiving the apartment information corresponding to each of the blank apartment blocks, the building material production management server 100 generates a frame diagram using the production standard set and the apartment information input to each of the blank apartment blocks (step S320).

예를 들어, 건축 자재 생산 관리 서버(100)는 공백 아파트 블록 각각에 해당하는 아파트 정보를 수신하면, 생산 기준 세트 및 공백 아파트 블록 각각에 입력된 아파트 정보를 이용하여 도 4와 같은 골조도(400)를 생성한다. For example, when receiving apartment information corresponding to each blank apartment block, the building material production management server 100 uses the production standard set and apartment information input to each of the blank apartment blocks, as shown in FIG. 4. ).

건축 자재 생산 관리 서버(100)는 생산 기준 세트 또는 상기 골조도 상의 세대 별 자재 작업 처리 요청 메시지를 수신하면(단계 S325), 작업 종류에 따라 해당 작업이 수행되도록 처리한다(단계 S330). Building material production management server 100, upon receiving a production standard set or a material task processing request message for each generation on the framework (step S325), processes the task to be performed according to the task type (step S330).

단계 330에 대한 일 실시예에서, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 창호 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. In an embodiment of step 330, when the building material production management server 100 receives a window job processing request message for a specific household or a plurality of households selected by a user, the corresponding job is performed according to the type of processing.

예를 들어, 건축 자재 생산 관리 서버(100)는 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 창호 시공 계획(참조번호 5(a)), 창호 생산 계획(참조번호 5(b)), 창호 작업 지시(참조번호 5(c)), 창호 생산 완료 지시(참조번호 5(e)), 창호 출고 지시(참조번호 5(f)), 창호 시공 지시(참조번호 5(g)) 등과 같은 창호 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. For example, the building material production management server 100 is a window construction plan (reference number 5(a)), a window production plan (reference number 5(b)), windows and doors for a specific household or a plurality of households selected by a user. Windows such as work instructions (reference number 5(c)), window production completion instruction (reference number 5(e)), window release instruction (reference number 5(f)), window construction instruction (reference number 5(g)), etc. Upon receiving a job processing request message, the job is performed according to the type of processing.

단계 330에 대한 다른 일 실시예에서, 건축 자재 생산 관리 서버(100)는골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 처리 작업 처리 요청 메시지를 수신하면 처리 종류에 따라 해당 작업이 수행되도록 한다. In another embodiment for step 330, the building material production management server 100 receives a glass processing operation request message for a specific household or a plurality of households selected by a user based on the frame structure, according to the type of processing. Let the work get done.

예를 들어, 건축 자재 생산 관리 서버(100)는 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 발주 일자, 작지 일자 등을 수신하면 유리 발주 일자(참조번호 6(a)), 작지 일자(참조번호 6(b)) 등을 설정할 수 있다.For example, the building material production management server 100 receives a glass order date for a specific household or a plurality of households selected by a user based on the frame roughness, the glass order date (reference number 6(a)) ), date of work (reference number 6(b)), etc. can be set.

건축 자재 생산 관리 서버(100)는 생산 기준 세트 또는 상기 골조도 상의 세대 별 자재 주문 요청 메시지를 수신하면(단계 S335), 해당 세대의 자재를 선택한 후 해당 자재의 소요량을 이용하여 자재 관리용 주문바를 산출한 후, 자재 관리용 주문바 및 생산 기준 세트에 따라 상기 자재의 입출고 관리를 진행한다(단계 S350).Building material production management server 100, upon receiving a production standard set or a material order request message for each generation on the framework (step S335), selects a material of the corresponding household and then opens an order bar for material management using the required amount of the material. After the calculation, the material management is carried out according to the material management order bar and the production standard set (step S350).

단계 S350에 대한 일 실시예에서, 건축 자재 생산 관리 서버(100)는 주문바 산출 데이터를 근거로 매입 정보를 생성함으로써 자재의 입출고 관리를 진행할 수 있다.In an embodiment of step S350, the building material production management server 100 may proceed with the input/output management of the material by generating purchase information based on the order bar calculation data.

예를 들어, 건축 자재 생산 관리 서버(100)는 도 7과 같이 골조도 상의 세대 별 자재 주문 요청 메시지를 수신하면, 해당 세대의 자재를 선택한 후 해당 자재의 소요량을 이용하여 주문될 수 있도록 한다. For example, when receiving a material order request message for each generation on the framework as shown in FIG. 7, the building material production management server 100 selects a material of the corresponding household and then allows the order to be ordered using the required amount of the material.

도 8 및 도 9는 본 발명의 일 실시예에 따른 골조도를 설명하기 위한 예시도이다.8 and 9 are exemplary views for explaining a skeleton view according to an embodiment of the present invention.

도 8 및 도 9를 참조하면, 공백 아파트 블록을 시공사 단말(200_1~200_N)에 제공하며 공백 아파트 블록 각각에 해당하는 아파트 정보(예를 들어, 아파트 동호수)를 수신한다. 그 후, 건축 자재 생산 관리 서버(100)는 생산 기준 세트 및 공백 아파트 블록 각각에 입력된 아파트 정보를 기초로 골조도를 생성한다. 8 and 9, a blank apartment block is provided to the contractor terminals 200_1 to 200_N, and apartment information (eg, number of apartment buildings) corresponding to each blank apartment block is received. Thereafter, the building material production management server 100 generates a frame diagram based on the apartment information input to each of the production standard set and the blank apartment block.

상술한 도 4 내지 도 7의 과정을 통해 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 작업을 처리되면, 건축 자재 생산 관리 서버(100)는 도 8과 같이 전체동을 한 화면을 통해 표시한다. 따라서, 시공사는 도 8과 같은 골조도를 통해 세대 별 작업 상태를 한번에 확인할 수 있는 것이다.When processing materials for a specific household or a plurality of households selected by a user based on the frame roughness through the above-described processes of FIGS. 4 to 7, the building material production management server 100 operates the entire building as shown in FIG. 8. Display through one screen. Therefore, the contractor can check the working state for each generation at once through the frame diagram as shown in FIG. 8.

도 8의 골조도를 더 상세히 표현한 도면은 도 9와 같다. 도 9에서와 같이, 골조도는 각 라이의 세대 별 작업 상태를 표시하였다. 예를 들어, 시공 보류 세대에 해당하면 “H”를 이용하여 표시하고, 샘플 세대에 해당하면 “S”를 이용하여 표시하고, 정”은 생산 기준 세트와 동일한 방향의 핸들을 의미하고, “역”은 생산 기준 세트와 반대 방향의 핸들을 의미한다. A view showing the frame diagram of FIG. 8 in more detail is the same as that of FIG. 9. As shown in Fig. 9, the skeleton diagram represents the working state of each lie by generation. For example, if it is a construction pending household, mark it using “H”, if it is a sample generation, mark it using “S”, and if it is a sample generation, mark it with “S”, and “positive” means a handle in the same direction as the production standard set, and “reverse ”Means the handle in the opposite direction to the production standard set.

한정된 실시예와 도면에 의해 설명되었으나, 본 발명은 상기의 실시예에 한정되는 것은 아니며, 이는 본 발명이 속하는 분야에서 통상의 지식을 가진 자라면 이러한 기재로부터 다양한 수정 및 변형이 가능하다. 따라서, 본 발명 사상은 아래에 기재된 특허청구범위에 의해서만 파악되어야 하고, 이의 균등 또는 등가적 변형 모두는 본 발명 사상의 범주에 속한다고 할 것이다.Although described by the limited embodiments and drawings, the present invention is not limited to the above embodiments, which can be various modifications and variations from these descriptions by those of ordinary skill in the field to which the present invention pertains. Therefore, the idea of the present invention should be grasped only by the claims set forth below, and all equivalent or equivalent modifications thereof will be said to belong to the scope of the idea of the present invention.

100: 건축 자재 생산 관리 서버,
110: 생산 기준 세트 관리부
120: 골조도 관리부
130: 작업 처리부
140: 자재 관리용 주문바 산출부
150: 입출고 관리부
100: building material production management server,
110: production standard set management unit
120: framework management department
130: job processing unit
140: order bar calculation unit for material management
150: Incoming and outgoing management department

Claims (2)

건축 자재 생산 관리 서버에서 실행되는 건축 자재 생산 관리 방법에 있어서,
공백 아파트 블록 각각에 해당하는 아파트 정보를 수신하면, 상기 공백 아파트 블록 각각에 입력된 아파트 정보를 이용하여 줄 아파트의 골조 형식으로 세대 별 제품 관리, 세대 별 창호 구성 및 좌우 방향을 관리 하기 위해 골조도를 생성하는 단계;
상기 골조도를 기초로 사용자에 의해 선택된 복수의 세대에 대한 자재 요청 메시지를 수신하면, 복수의 세대에 시공된 자재 정보를 추출하여 표시하는 단계;
상기 골조도의 복수의 세대 중 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 발주 일자 및 작지 일자를 수신하면 상기 유리 발주 일자 및 작지 일자를 설정하는 단계;
상기 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재의 제품군을 설정하고, 상기 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재를 하나의 그룹으로 설정하는 단계;
상기 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 주문 요청 메시지를 수신하면, 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 자재 양을 산출하여 주문 되도록 하여 골조도를 통해 세대 별 작업 상태를 관리하는 단계; 및를 포함하는 것을 특징으로 하는
건축 자재 생산 관리 방법.
In the building material production management method executed in the building material production management server,
When receiving the apartment information corresponding to each blank apartment block, using the apartment information entered in each of the blank apartment blocks, the frame diagram is used to manage products for each generation in the form of a frame of a row apartment, and to manage the window composition and left and right directions for each generation. Generating a;
When receiving a material request message for a plurality of households selected by a user based on the frame roughness, extracting and displaying material information constructed in the plurality of households;
Setting a glass ordering date and a construction site date when receiving a glass ordering date and a construction site date for a specific generation or a plurality of generations selected by a user among the plurality of generations of the framework;
Based on the frame roughness, a product family of materials installed in a specific household is set according to a request for group designation of materials for a specific household or a plurality of households selected by a user, and selected by a specific household or user based on the frame roughness. Setting materials installed in a specific household as one group according to a request for group designation of materials for a plurality of households;
When receiving a material order request message for a specific household or a plurality of households selected by a user based on the frame roughness, the amount of material for a specific household or a plurality of households selected by the user is calculated and ordered, and the household through the frame diagram Managing each work state; Characterized in that it comprises and
How to manage the production of building materials.
공백 아파트 블록 각각에 해당하는 아파트 정보를 수신하면, 상기 공백 아파트 블록 각각에 입력된 아파트 정보를 이용하여 줄 아파트의 골조 형식으로 세대 별 제품 관리, 세대 별 창호 구성 및 좌우 방향을 관리 하기 위해 골조도를 생성하는 골조도 관리부; 및
상기 골조도를 기초로 사용자에 의해 선택된 복수의 세대에 대한 자재 요청 메시지를 수신하면, 복수의 세대에 시공된 자재 정보를 추출하여 표시하고, 상기 골조도의 복수의 세대 중 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 유리 발주 일자 및 작지 일자를 수신하면 상기 유리 발주 일자 및 작지 일자를 설정하고, 상기 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재의 제품군을 설정하고, 상기 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재의 그룹 지정 요청에 따라 특정 세대에 설치되는 자재를 하나의 그룹으로 설정하고, 상기 골조도를 기초로 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 자재 주문 요청 메시지를 수신하면, 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 자재 양을 산출하여 주문 되도록 하여 골조도를 통해 세대 별 작업 상태를 관리하고, 상기 특정 세대 또는 사용자에 의해 선택된 복수의 세대에 대한 좌우 지정 메시지를 수신하면 특정 세대 또는 사용자에 의해 선택된 복수의 세대의 창호의 핸들의 좌우 방향을 설정하는 작업 처리부를 포함하는 것을 특징으로 하는
건축 자재 생산 관리 서버.
When receiving the apartment information corresponding to each blank apartment block, using the apartment information entered in each of the blank apartment blocks, the frame diagram is used to manage products for each generation in the form of a frame of a row apartment, and to manage the window composition and left and right directions for each generation. A skeleton degree management unit that generates a; And
Upon receiving a material request message for a plurality of households selected by the user based on the frame roughness, the material information constructed in the plurality of households is extracted and displayed, and a specific household or user among the plurality of households of the frame roughness Upon receiving the glass ordering date and construction site date for a plurality of selected households, the glass ordering date and construction site date are set, and a request for group designation of materials for a specific household or for a plurality of households selected by a user based on the frame roughness According to the request to designate a group of materials for a specific household or for multiple households selected by a user based on the frame roughness, the material installed in a specific household is set as one group. And, upon receiving a material order request message for a specific household or for a plurality of households selected by a user based on the frame roughness, the amount of material for a specific household or a plurality of households selected by the user is calculated and ordered to determine the frame roughness. A task processing unit that manages the work status of each household through the operation and sets the left and right directions of the handles of the windows of a specific household or a plurality of households selected by a user upon receiving the left and right designation messages for the plurality of households selected by the specific household or user. Characterized in that it comprises a
Building material production management server.
KR1020200116004A 2020-09-10 2020-09-10 Method of providing construction materials production and server performing the same KR102253818B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200116004A KR102253818B1 (en) 2020-09-10 2020-09-10 Method of providing construction materials production and server performing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200116004A KR102253818B1 (en) 2020-09-10 2020-09-10 Method of providing construction materials production and server performing the same

Publications (1)

Publication Number Publication Date
KR102253818B1 true KR102253818B1 (en) 2021-05-18

Family

ID=76158540

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200116004A KR102253818B1 (en) 2020-09-10 2020-09-10 Method of providing construction materials production and server performing the same

Country Status (1)

Country Link
KR (1) KR102253818B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020092339A (en) * 2002-11-20 2002-12-11 흥동개발 주식회사 The on-line system for preengaging design and sale house
KR100800547B1 (en) * 2006-12-28 2008-02-04 주식회사 포스코건설 Method of construction process management connecting cost information by element
KR20190099747A (en) * 2018-02-19 2019-08-28 양경옥 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020092339A (en) * 2002-11-20 2002-12-11 흥동개발 주식회사 The on-line system for preengaging design and sale house
KR100800547B1 (en) * 2006-12-28 2008-02-04 주식회사 포스코건설 Method of construction process management connecting cost information by element
KR20190099747A (en) * 2018-02-19 2019-08-28 양경옥 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Similar Documents

Publication Publication Date Title
Dresch et al. Inducing Brazilian manufacturing SMEs productivity with Lean tools
AU2015101964A4 (en) Construction management system
Kim et al. A PDA and wireless web-integrated system for quality inspection and defect management of apartment housing projects
US8989887B2 (en) Use of prediction data in monitoring actual production targets
US20130253968A1 (en) Facility control system (fcs, c1) to manage assets planning, design, construction, fabrication, operating, maintence and products
CN101639687B (en) Integrated technology quality control system and realization method thereof
US20120221379A1 (en) Facility control system (fcs) to manage assets and products
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN110580567A (en) Intelligent property mobile operation management method
KR102370134B1 (en) Process management system and method using smart construction platform
JP2019153051A (en) Information collection display system, information collection method, and information display method
Yilmaz et al. Low-cost (Shoestring) digital solution areas for enabling digitalisation in construction SMEs
Czumanski et al. State-based analysis of labour productivity
US20140058963A1 (en) Facility control system (fcs-c2) (introduction of traveler form) to manage assets planning, design, construction, fabrication, operating, maintence and products fabrication
Bhuinyan et al. Measuring project performance and success factors of construction sites
Nimr et al. Improving performance of project through utilizing statistical control chart based on adaptive management and scientific engineering
KR102253818B1 (en) Method of providing construction materials production and server performing the same
KR100945523B1 (en) On-line construction management method
Ayalew et al. Characterization of waste in Ethiopian building construction projects
JP2021002138A (en) Information system and information management method
JP2020129312A (en) Building performance management method and performance management system
KR102356330B1 (en) Construction process automatic management system using qr code
WO2020056671A1 (en) Data growth method and device for fabricated building construction platform
CN114626954A (en) Intelligent manufacturing cooperative system
KR20150137151A (en) Integrated production management system for E-beam irradiation processes and the method

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant