KR102613585B1 - An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction - Google Patents

An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction Download PDF

Info

Publication number
KR102613585B1
KR102613585B1 KR1020180019576A KR20180019576A KR102613585B1 KR 102613585 B1 KR102613585 B1 KR 102613585B1 KR 1020180019576 A KR1020180019576 A KR 1020180019576A KR 20180019576 A KR20180019576 A KR 20180019576A KR 102613585 B1 KR102613585 B1 KR 102613585B1
Authority
KR
South Korea
Prior art keywords
worker
database
floor
workers
rebar
Prior art date
Application number
KR1020180019576A
Other languages
Korean (ko)
Other versions
KR20190099747A (en
Inventor
양경옥
Original Assignee
양경옥
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양경옥 filed Critical 양경옥
Priority to KR1020180019576A priority Critical patent/KR102613585B1/en
Publication of KR20190099747A publication Critical patent/KR20190099747A/en
Priority to KR1020230178158A priority patent/KR20230169923A/en
Application granted granted Critical
Publication of KR102613585B1 publication Critical patent/KR102613585B1/en

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

본 발명은 공동주택 아파트 공사의 골조공사를 건설하는 형틀 목수 작업자와 철근 작업자의 작업장소 이동함에 있어서 층별 또는 존별 작업 장소의 이동 경로를 개인별로 계획하고 실적자료를 수집하여 최적의 작업자 이동경로를 판단하는 장치 및 방법에 관한 것이다. The present invention determines the optimal worker movement route by individually planning the movement route of the work place by floor or zone and collecting performance data when moving to the work place of the frame carpenter and rebar worker constructing the frame work of the apartment complex construction. It relates to a device and method for doing so.

Description

공동주택 골조공사 작업자의 개인별 작업배정 장치 및 방법{An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction}{An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction}

본 발명은 공동주택 아파트의 공사에서의 철근콘크리트 골조를 시공하는 형틀 목수 작업자와 철근 작업자의 개인별로 작업할 내용을 배정하는 방법에 관한 것으로, 작업자가 효율적으로 같은 층 또는 다음층으로 이동할 수 있도록, 동일한 골조 평면 구역 또는 위치에서 반복적으로 신속하게 작업할 수 있는 공사계획 및 인원투입 방법을 제공한다.The present invention relates to a method of assigning work to each individual frame carpenter and rebar worker constructing a reinforced concrete frame in the construction of an apartment complex, so that workers can efficiently move to the same floor or the next floor, Provides a construction plan and personnel input method that can work quickly and repeatedly in the same frame plan area or location.

국토교통부 2017년 주택 인허가 발표에 따르면 아파트는 47만 가구이다. 아파트 공사는 2개동 내지 6개동으로 구성되며 최대 20개동의 대단지도 있다. According to the Ministry of Land, Infrastructure and Transport's 2017 housing licensing announcement, there are 470,000 apartments. Apartment construction consists of 2 to 6 buildings, and there are also large complexes with up to 20 buildings.

아파트 유형은 타워형과 판상형으로 구분된다. 판상형의 최근 유형은 일자형 또는 'ㄱ'자 'ㄴ'자 형태이다. 1개 층의 세대수는 4세대 내지 6세대이다. 세대는 남쪽 방향으로 배치되고 계단실 및 엘리베이터로 구성되는 코어는 북쪽에 위치하며 통상 2개이다.Apartment types are divided into tower type and plate type. The latest types of plate shapes are straight or 'ㄱ' or 'ㄴ' shaped. The number of households on one floor is 4 to 6 households. The units are arranged in the south direction, and the core consisting of the staircase and elevator is located in the north, and there are usually two.

판상형은 전면에 배치되는 공간이 많아 채광, 일조량이 우수하고 거실과 주방이 마주보는 형태로 맞통풍에 유리하다. 아파트 동을 'ㅡ'자로 구성하는 것보다 'ㄱ'자로 구성할 때 가구수를 최대화 할 수 있기 때문에 대부분 아파트들이 'ㄱ'자로 설계되고 있다. The plate type has a lot of space in the front, so it has excellent lighting and sunlight, and the living room and kitchen face each other, which is advantageous for cross ventilation. Most apartments are designed in an 'ㄱ' shape because the number of households can be maximized when the apartment building is structured in an 'ㄱ' shape rather than in a 'ㅡ' shape.

평면의 배치는 'ㄱ'자의 모서리가 남쪽 방향으로 배치되는 V자 형태를 나타내는데 오전에 동쪽인 오른쪽 부분이 햇빛을 받고 오후에는 나머지 반쪽인 서쪽이 햇빛을 받도록 하기 위함이다. The layout of the floor plan represents a V-shape with the corners of the letter 'L' facing south. This is to ensure that the right eastern half receives sunlight in the morning and the western half receives sunlight in the afternoon.

계단실 및 엘리베이터의 코어는 북쪽에 배치하여 조망이나 햇빛을 가리지 않도록 한다.The core of the staircase and elevator is placed on the north side so as not to block the view or sunlight.

대부분의 아파트 조감도나 동의 배치도를 보면 위와 같은 형태로 배치되는 것을 나타내고 있다.If you look at most apartment bird's eye views or building layout plans, they are laid out in the form above.

구조형식을 보면 철근콘크리트 구조이고 수직하중은 벽체가 지지하는 벽식구조이고 슬라브는 보가 없는 무량판 플랫 슬라브이다.Looking at the structural type, it is a reinforced concrete structure, the vertical load is a wall structure supported by the wall, and the slab is a massless flat slab without beams.

아파트 공사는 터파기를 한 후 아파트 기초 매트를 시공한 후 지하층을 완성한 후 지상층 철근콘크리트 골조공사와 마감공사의 순서로 진행된다. 이중 지상층 골조공사의 높이는 20층 내지 49층 규모이다. Apartment construction is carried out in the following order: excavation, construction of an apartment foundation mat, completion of the basement floor, and reinforced concrete framing and finishing work on the ground floor. The height of the ground floor framing construction ranges from 20 to 49 floors.

지상 골조는 아래층을 시공한 후 위층으로 올라가며 10층을 시공한 후 11층을 시공하는 선행작업과 후행작업이 명확한 구조를 갖는 직렬방식의 공사 방식의 특징을 갖는다. The above-ground frame has the characteristics of a serial construction method with a clear structure of preceding and succeeding works, such as constructing the lower floor, then moving up to the upper floor, constructing the 10th floor, and then constructing the 11th floor.

골조공사는 건물의 뼈대이므로 공사기간이 길고 공사비가 많으며 다수의 작업자가 투입된다.Frame work is the framework of a building, so the construction period is long, construction costs are high, and many workers are involved.

이러한 골조공사는 인력에 의해 시공되는데 통상 1개층 시공에 6일 내지 8일이 소요된다. 1개층의 작업순서는 먹매김, 벽체 기둥 철근, 벽체 기둥 거푸집, 슬라브 동바리 및 슬라브 거푸집, 슬라브 철근, 콘크리트 타설 및 양생으로 진행된다. This type of framing work is performed by manpower, and it usually takes 6 to 8 days to construct one floor. The work order for one floor consists of filling, wall column reinforcement, wall column form, slab framing and slab form, slab reinforcement, concrete pouring, and curing.

여기서 형틀은 목수 작업자, 형틀 작업자에 의해 시공되며, 거푸집, 합판으로서 박스 기능을 하며 그 안에 철근을 넣고 콘크리트를 부어 넣으면 골조가 완성된다.Here, the form is constructed by carpenters and form workers, and functions as a box as formwork and plywood. The frame is completed by placing rebar in it and pouring concrete.

콘크리트는 마지막날에 타설되므로 그 이전 단계는 대부분 목수작업인 거푸집 형틀 작업과 철근 작업의 주요 작업이다. 나머지는 전기, 설비 작업이 있다. Since the concrete is poured on the last day, the previous steps are mostly carpentry work, such as formwork and rebar work. The rest includes electrical and equipment work.

아파트 1개층 4세대의 경우, 작업자가 150명 정도 투입된다. 이중 형틀(목수) 작업자가 가장 많고 다음으로 철근작업자이며 형틀 작업자와 철근 작업자를 합하면 전체의 약 70% 내지 80%를 차지한다.In the case of 4 units on one floor of an apartment, about 150 workers are employed. Among these, form workers (carpenters) are the most numerous, followed by rebar workers. Together, form workers and rebar workers account for about 70% to 80% of the total.

따라서 골조공사는 형틀 작업자와 철근 작업자에 의해 시공되어 생산된다고 볼 수 있다.Therefore, it can be said that frame work is constructed and produced by form workers and rebar workers.

한편 101동 10층 골조공사 기간이 6일 싸이클인 경우, 형틀 작업자와 철근 작업자는 일별로 필요한 인원수가 불규칙한 구조를 갖는다. Meanwhile, when the construction period for the 10th floor of building 101 is a 6-day cycle, the number of form workers and rebar workers required per day is irregular.

마지막날인 6일차에는 콘크리트를 타설하므로 5일차까지 형틀이나 철근작업이 완료되어 6일차에는 형틀 작업자와 철근 작업자가 100명 이상이 필요가 없다. Since concrete is poured on the 6th day, which is the last day, the form and rebar work is completed by the 5th day, so there is no need for more than 100 form workers and rebar workers on the 6th day.

1일차부터 5일차까지는 형틀이나 철근작업이 많거나 적게 불규칙하게 진행되므로 이에 따라 작업자도 불규칙하게 출역한다. From the 1st to the 5th day, the formwork or rebar work progresses irregularly, with more or less work being done, so workers are also dispatched irregularly.

이에 따라 남는 작업자는 다른 동인 102동에서 작업을 하거나, 다른 인근 현장에서 작업을 하게 된다. Accordingly, the remaining workers will work in another building, Building 102, or at other nearby sites.

이러한 특징에 따라 제조업과 달리 건설 현장에서는 날짜별로 불규칙적인 작업자 수요에 따라 작업자를 배치해야 하므로 작업자 관리자의 작업자 동원 계획이나 관리 능력은 매우 중요하다.According to these characteristics, unlike manufacturing, construction sites must assign workers according to irregular demand for workers on a daily basis, so worker managers' ability to plan and manage worker mobilization is very important.

그러나 작업자 관리자가 형틀, 철근 작업자를 배치하는 작업은 현재 자신의 경험이나 노하우를 바탕으로 진행되고 있는 실정이다. However, the task of assigning form and rebar workers to worker managers is currently being carried out based on their own experience or know-how.

기존의 작업자 배치 작업에 있어서 기존의 문제점은 다음과 같은 내용이다.The existing problems in existing worker placement work are as follows.

아파트는 각각의 현장이나 동별로 평면 모양이 다양하여 경험을 적용하는 경우 오차가 커질 수 있다.Apartments have different floor plans for each site or building, so errors may increase when applying experience.

일별 인원수가 불규칙하므로 필요한 인원이나 남는 인원을 효율적으로 관리해야 인원이나 인건비 손실이 최소화할 수 있으나 이를 계산하는 방법이 수계산 방식을 사용하고 있다.Since the number of people per day is irregular, the loss of personnel or labor costs can be minimized by efficiently managing the required number of people or the remaining number of people. However, the manual calculation method is used to calculate this.

아파트 작업자 배치나 순환에 관한 기존의 논문이나 연구는 동별로 순환 싸이클인 순서를 제시하고 있으나, 아파트 평면이나 철근, 콘크리트 수량에 기반한 구체적인 형틀 및 철근 작업자의 인원수를 제시하는 방법은 없다.Existing papers or studies on apartment worker placement or circulation present the circulation cycle order for each building, but there is no way to present the specific number of form and rebar workers based on the apartment plan or the quantity of rebar and concrete.

형틀 및 철근 작업자는 몇 개의 팀으로 구성되고 다시 개인별로 작업 임무를 수행하고 있으나 팀별 개인별 작업장소 이동 또는 어떠한 부재(기둥)를 시공해야 하는지 구체적인 방법이 없다.Frame and rebar workers are organized into several teams and perform work duties individually, but there is no specific method for each team or individual to move to a work location or what members (columns) to construct.

불규칙한 작업자 출역에 따른 남은 인원과 인원손실, 인건비를 최소화하기 위한 분석이나 신속 정확한 계산 사례가 제시되지 않고 있다.There are no examples of analysis or quick and accurate calculations to minimize the remaining personnel, personnel losses, and labor costs due to irregular worker dispatch.

작업자가 하루에 얼마만큼의 시공을 하는지 작업생산성 실적을 수집하고 이를 계획에 반영함에 있어, 골조공사 작업자 개인별 분석 방법이나 실시예가 없다.In collecting work productivity performance, such as how much construction a worker does per day, and reflecting this in the plan, there is no analysis method or example for individual frame construction workers.

형틀 및 철근 작업자들은 개인별로 특정 부재를 작업하고 있으나, 작업자들이 시공해야 할 골조공사(예 101동 10층 골조)에 대하여 개인별로 역량을 고려하여 배정하지 않고 있다.Frame and rebar workers individually work on specific members, but the structural work that workers need to construct (e.g., the 10th floor of Building 101) is not assigned to each individual in consideration of their capabilities.

따라서 이와 같은 기술과 관련하여 본 발명에서는 다수의 건물로 구성되는 아파트 골조공사에서 형틀 작업자와 철근 작업자가 작업 생산성을 높일 수 있는 작업자 개인의 작업장소 이동경로 배치계획 분석 방법을 고안하고자 한다.Therefore, in relation to this technology, the present invention seeks to devise a method for analyzing the movement path arrangement plan of each worker's individual work location, which can increase the work productivity of form workers and rebar workers in apartment framing construction consisting of multiple buildings.

본 발명은 상기와 같은 종래 기술에 따른 문제점을 해결하기 위하여 창안된 것으로서, 아파트 골조공사에서 형틀 및 철근 작업자가 시공해야 할 작업 장소, 작업 대상 및 수량을 개인별로 할당하고 성과를 분석하는 방법을 제공한다.The present invention was created to solve the problems caused by the prior art as described above, and provides a method of allocating work locations, work objects, and quantities to each individual and analyzing performance by frame and rebar workers in apartment framing construction. do.

상기한 목적을 달성하고 상술한 종래기술의 문제점을 해결하기 위하여, 본 발명에 따른 아파트 골조공사에서 형틀 및 철근 작업자의 개인별 작업 배정 방법 및 장치는 1개층의 거푸집 및 철근 물량을 산출하고, 각각의 기둥(벽체)에 작업생산성을 고려하여 작업자를 할당하고, 슬라브의 실별 또는 면적을 기준으로 작업자를 배정한 후, 작업이 종료되면 다음 층이나 다른 존으로 이동하는 경로를 지정하여 각각의 부재에 대응하는 작업자가 산출된다.In order to achieve the above-mentioned purpose and solve the problems of the prior art described above, the method and device for assigning individual work to formwork and rebar workers in apartment framing construction according to the present invention calculates the quantity of formwork and rebar for one floor, and calculates the amount of formwork and rebar for each floor. Workers are assigned to columns (walls) in consideration of work productivity, workers are assigned based on the room or area of the slab, and when the work is completed, the route to the next floor or other zone is designated to respond to each member. Workers are produced.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

골조공사의 각각의 기둥이나 벽체를 누가 언제 어떤 순서로 시공할 것인가를 세부적으로 계획할 수 있다.It is possible to plan in detail who will construct each column or wall of the frame work, when, and in what order.

작업시간은 부재의 물량을 작업자의 1일 작업생산성으로 나누어 산출되므로 객관적이고 정확하다.Working hours are objective and accurate because they are calculated by dividing the quantity of absences by the worker's daily work productivity.

작업자 개인은 각 층의 작업위치와 시간 및 작업할 수량을 사전에 정확히 알 수 있고 이에 따라 미래의 일을 사전에 알 수 있으므로 효율적인 작업을 할 수 있다. 또한 시공한 수량을 알 수 있고 자신의 일당 또는 임금 추이를 사전에 알 수 있다.Individual workers can work efficiently because they can accurately know the work location, time, and quantity of work on each floor in advance, and thus know future work in advance. In addition, you can know the quantity of construction and know your daily wage or wage trend in advance.

작업자를 배정하는 작업자 관리자는 작업자 개인의 역량을 고려하여 작업자를 배정할 수 있고 성과측정을 과학적으로 할 수 있다. 이에 따라 작업자의 특성을 반영하여 다음 층 또는 다른 공사에서 보다 효율적인 작업자 배정을 할 수 있다.Worker managers who assign workers can assign workers by considering each worker's capabilities and measure performance scientifically. Accordingly, more efficient worker assignment can be made to the next floor or other construction work by reflecting the worker's characteristics.

시공사는 계획한 작업자 배정 대비 시공한 실적을 비교하여 문제점을 세부적이고 체계적으로 개인별로 알 수 있어 문제점을 파악이 용이하고 대책을 수립할 수 있다. By comparing the construction performance against the planned worker allocation, the construction company can learn about problems in detail and systematically on an individual basis, making it easier to identify problems and establish countermeasures.

예를 들어 101동 901호 안방의 작업이 다른 구역보다 지연되어 전체 일정이 영향을 받는 경우, 안방에 배정된 작업자가 누구 인지 알 수 있고 생산성을 분석하여 작업자를 추가로 투입하거나 교체하는 등 대책수립이 신속하고 용이해진다.For example, if work in room 901 of building 101 is delayed compared to other areas and the overall schedule is affected, you can find out who the workers assigned to the master room are, analyze productivity, and establish countermeasures such as adding or replacing workers. This becomes quick and easy.

작업자 개인의 작업배정을 합하여 팀별 시공계획을 수립하고 시공사 전체의 시공계획이 정확히 수립된다. 이에 따라 다양한 시뮬레이션을 통해 공기단축과 최소의 작업자수를 배정하여 인건비를 절감하는 공사방법을 만들어 낼 수 있다. By combining the work assignments of individual workers, a construction plan is established for each team, and the construction plan for the entire construction company is accurately established. Accordingly, through various simulations, it is possible to create a construction method that reduces labor costs by shortening the construction period and assigning the minimum number of workers.

작업자가 잘 알고 있거나 손에 익숙한 작업에 배정하고, 반복적으로 작업할 수 있도록 배정하므로써 학습효과나 습숙효과를 발휘할 수 있도록 할 수 있다. 이에 따라 작업생산성이 10% 이상 높아질 수 있다. By assigning workers to tasks they know well or are familiar with, and assigning them to work repeatedly, a learning or habituation effect can be achieved. As a result, work productivity can increase by more than 10%.

작업생산성이 높아지면 동일한 인원으로 공사시간을 단축할 수 있거나 공사 인건비를 절감할 수 있다.As work productivity increases, construction time can be shortened with the same number of people or construction labor costs can be reduced.

불규칙한 작업자 출역이나 불합리한 배정에 따른 인력 및 시간손실을 줄어든다.Reduces manpower and time loss due to irregular worker dispatch or unreasonable assignment.

작업자가 동일하고 반복적으로 작업함에 따라 자산의 작업에 대해 보다 잘 알게 되므로 품질이 향상되고 안전사고의 위험도 줄어든다.As workers perform the same, repetitive tasks, they become more familiar with the asset's operation, improving quality and reducing the risk of safety accidents.

상기 작업자 배정 방법을 사용하는 건설사 또는 철근 콘크리트 전문건설업체는 다른 경쟁사에 비해 신속하고 정확하게 작업자를 배정 관리할 수 있고 공사 일수를 단축하고 인건비를 절감할 수 있어 아파트 골조공사의 수주 및 생존 경쟁력이 높아진다.Construction companies or specialized reinforced concrete construction companies that use the above worker assignment method can assign and manage workers more quickly and accurately than other competitors, shorten the number of construction days, and reduce labor costs, thereby increasing the competitiveness of winning orders and surviving in apartment framing construction. .

도 1은 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 장치의 전체 구성도
도 2 내지 4는 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 방법의 전체 흐름도
도 5는 본 발명의 일실시예에 따른 판상형 아파트의 공사개요
도 6은 본 발명의 일실시예에 따른 골조공사 공정표
도 7은 본 발명의 일실시예에 따른 벽체 부재에 대한 번호부여도
도 8은 본 발명의 일실시예에 따른 각각의 부재에 대한 철근 수량
도 9는 본 발명의 일실시예에 따른 작업자의 개인별 생산성 실적 데이터
도 10은 본 발명의 일실시예에 따른 도 8의 각각의 부재에 작업자를 배정한 내용
도 11은 본 발명의 일실시예에 따른 일별 작업자의 이동경로의 표시
도 12는 본 발명의 일실시예에 따른 계획 대비 실적과의 차이
도 13은 본 발명의 일실시예에 따른 101동과 102동을 합한 2개동의 철근 작업자의 일별 소요인원 추이
1 is an overall configuration diagram of a construction method analysis device for individual work assignment according to an embodiment of the present invention.
2 to 4 are overall flowcharts of the construction method analysis method for individual work assignment according to an embodiment of the present invention.
Figure 5 is an outline of the construction of a plate-type apartment according to an embodiment of the present invention.
Figure 6 is a framing construction process table according to an embodiment of the present invention.
Figure 7 is a numbering diagram for wall members according to an embodiment of the present invention
Figure 8 shows the quantity of reinforcing bars for each member according to an embodiment of the present invention.
Figure 9 shows individual productivity performance data of workers according to an embodiment of the present invention.
Figure 10 shows the assignment of workers to each member of Figure 8 according to an embodiment of the present invention.
Figure 11 is a display of the daily movement path of workers according to an embodiment of the present invention
Figure 12 shows the difference between plan and performance according to an embodiment of the present invention
Figure 13 is a trend of the daily number of rebar workers in two buildings, including buildings 101 and 102, according to an embodiment of the present invention.

이하, 본 발명에 따른 아파트 골조공사의 형틀 및 철근공사의 작업자 개인별 작업 배정방법 분석장치 및 방법을 상세히 설명한다.Hereinafter, the apparatus and method for analyzing the work assignment method for each worker in the frame and rebar construction of apartment framing construction according to the present invention will be described in detail.

도 1은 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 장치의 전체 구성을 나타낸 것이다. Figure 1 shows the overall configuration of a construction method analysis device for individual work assignment according to an embodiment of the present invention.

도 1을 참조하면, 본 실시예에 따른 개인별 작업배정을 위한 공사방법 분석장치(10)는 제어부(11), 건축 도면 데이터 베이스(12), 기준층 평면 공구 분할 데이터 베이스(13), 자재 수량 데이터 베이스(14), 작업자 개인별 작업생산성 데이터 베이스(15), 공정표 데이터 베이스(16) 및 작업자 배정 데이터 베이스(17)를 포함한다.Referring to FIG. 1, the construction method analysis device 10 for individual work assignment according to this embodiment includes a control unit 11, an architectural drawing database 12, a reference floor plane tool division database 13, and material quantity data. It includes a base (14), an individual worker's work productivity database (15), a schedule database (16), and a worker assignment database (17).

상기 제어부(11)는 기준층 평면 공구 분할 데이터 베이스(13)상의 공구분할에 따른 공구별 자재 부재의 물량(수량)을 자재 물량 데이터 베이스(14)로 부터 산출하고, 작업자 개인별 작업생산성 데이터 베이스(15)로부터 부재(기둥, 벽체, 실별 슬라브)별 작업시간을 산출하고, 공정표 데이터 베이스(16)로부터 다음 공구 또는 층으로 작업자 이동 경로를 산출하고, 상기 산출된 결과를 작업자 배정 데이터 베이스(17)에 저장한다.The control unit 11 calculates the quantity (quantity) of material members for each tool according to the tool division on the reference layer plane tool division database 13 from the material quantity database 14, and calculates the quantity of material members for each tool from the material quantity database 14 and the work productivity database 15 for each worker. ), the working time for each member (column, wall, slab by room) is calculated, the worker movement path to the next tool or floor is calculated from the schedule database 16, and the calculated results are stored in the worker assignment database 17. Save.

예를 들어 4개 동의 35층 아파트 골조공사에서 제어부(11)는 각 동의 건축도면과 구조도면, BIM 도면을 건축도면 데이터베이스(12)에 저장한다. 기준층 평면을 A와 B의 2개로 분할한다. For example, in the construction of a 35-story apartment building in four buildings, the control unit 11 stores the architectural drawings, structural drawings, and BIM drawings of each building in the architectural drawing database 12. Divide the reference floor plane into two, A and B.

101동 9층 901호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다의 면적과 기둥 벽체 슬라브의 거푸집과 철근 수량을 산출한다. 가장 바깥쪽의 안방은 4개의 벽체와 1개의 천정 슬라브로 구성되며 4개의 벽체를 시공하기 위한 벽체철근과 벽체형틀의 수량이 산출된다. Calculate the area of room 901 on the 9th floor of building 101, living room, kitchen, study room, small room, bathroom 1, bathroom 2, and entrance veranda, as well as the formwork and rebar for the column wall slab. The outermost master bedroom consists of four walls and one ceiling slab, and the quantity of wall rebar and wall form to construct the four walls is calculated.

바닥인 슬라브를 시공하기 위한 슬라브 형틀과 철근 수량도 산출된다.The quantity of slab formwork and rebar for constructing the slab floor is also calculated.

안방 벽체1을 시공하기 위한 수량에 대한 작업자를 배정하며 작업시간은 수량을 1일 생산성 또는 시간당 생산성으로 나누어 산출한다. 생산성은 작업자 개인별 작업생산성 데이터 베이스(15)를 이용한다.Workers are assigned for the quantity to construct master bedroom wall 1, and the working time is calculated by dividing the quantity by daily productivity or hourly productivity. Productivity uses the work productivity database (15) for each worker.

위와 같은 순서로 901호 세대에 대한 작업자 배정이 완료되면, 그 옆 세대인 902호 세대에 배정한다. 그리고 계단과 엘리베이터로 구성된 코어 1번에 대한 배정된 실시한다. 다음으로 903호, 904호, 코어 2번에 대해서도 901호와 같은 방식으로 배정한다. Once worker assignment to household 901 is completed in the above order, they are assigned to household 902, which is the next generation. And carry out the assigned core number 1, which consists of stairs and elevators. Next, rooms 903, 904, and core 2 are assigned in the same manner as room 901.

공정표 데이터 베이스(16)로부터 공정표를 읽고 9층에 대한 배정이 완료되면, 다음으로 10층에 대한 배정을 실시한다. 그리고 그 상층인 11층부터 35층까지 작업자를 배정하고 그 결과를 작업자 배정 데이터 베이스(17)에 저장한다. When the schedule is read from the schedule database 16 and assignment to the 9th floor is completed, assignment to the 10th floor is then performed. Then, workers are assigned to the upper floors, from the 11th floor to the 35th floor, and the results are stored in the worker assignment database 17.

건축도면 데이터베이스(12)는 건축도면, 구조도면, BIM을 저정한다. 작업인원과 자재 물량을 산정하기 평면도, 단면도, 층고, 기둥 벽체의 치수를 포함한다. 건설현장은 도면에 따라 시공하므로 도면은 공사 착수전에 이미 CAD 등으로 완성되어 있다. The architectural drawing database 12 stores architectural drawings, structural drawings, and BIM. To calculate the number of workers and materials, include floor plans, cross-sections, floor heights, and pillar wall dimensions. Construction sites are constructed according to drawings, so the drawings are already completed in CAD, etc. before construction begins.

기준층 평면분할 데이터 베이스(13)는 1개층을 일반적으로 2개의 공구 존으로 분할한 정보를 저장한다. The reference floor plane division database 13 generally stores information about dividing one floor into two tool zones.

여기서 공구분할의 기준은 콘크리트를 타설하는 단위이다. 예를 들어 101동에 4개의 세대와 코어 2개로 구성되는 경우, 901호와 902호 및 코어 1번을 포함하는 A공구는 콘크리트를 월요일에 타설하고 나머지 B공구(903호, 904호, 코어 2번)는 수요일에 타설한다.Here, the standard for tool division is the unit for pouring concrete. For example, if Building 101 consists of 4 households and 2 cores, the concrete for Tool A, which includes Units 901 and 902 and Core No. 1, is poured on Monday, and the remaining Tool B (No. 903, No. 904, Core 2) is poured on Monday. number) will be poured on Wednesday.

자재 수량 데이터 베이스(14)는 세대별 실별 벽체 및 슬라브의 형틀, 철근의 수량정보를 저장한다. 예를 들어 101동 9층 901호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 벽체 및 슬라브의 거푸집과 철근 수량에 관한 정보를 저장한다. The material quantity database 14 stores quantity information of walls and slabs and reinforcing bars for each room by household. For example, in room 901 on the 9th floor of Building 101, information about the quantity of molds and reinforcing bars for the walls and slabs for the master bedroom, living room, kitchen, study room, small room, bathroom 1, bathroom 2, and the entrance veranda is stored.

상기 수량은 적산 전문회사에서 일반적으로 산출하고 있는 기존의 업무에 해당한다.The above quantity corresponds to existing work generally calculated by companies specializing in integration.

작업자의 개인별 작업생산성 데이터 베이스(15)는 형틀 작업자, 철근 작업자의 개인별 1일 시공능력 또는 시간당 시공능력에 관한 정보를 저장한다.The worker's individual work productivity database 15 stores information on the daily or hourly construction ability of each individual form worker or rebar worker.

예를 들어 철근 작업자 1번인 홍길동은 과거 기록상 벽체 철근을 하루에 1.2톤을 시공하며 슬라브 철근은 1.5톤을 시공하는 능력을 나타내고 있다.For example, Hong Gil-dong, rebar worker number 1, shows the ability to construct 1.2 tons of wall rebar per day and 1.5 tons of slab rebar according to past records.

공정표 데이터 베이스(16)는 층별 세대별 작업일정을 나타낸 공사 일정이며 형틀 공사, 철근공사를 포함한다.The schedule database 16 is a construction schedule showing the work schedule for each floor and household and includes formwork and rebar work.

예를 들어 101동 9층 901호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 벽체 및 슬라브의 거푸집과 철근 시공에 관한 일자 및 시간 정보를 나타낸다. For example, it shows the date and time information regarding the construction of the formwork and rebar for the walls and slabs for the master bedroom, living room, kitchen, study room, small room, bathroom 1, bathroom 2, and the entrance veranda in room 901 on the 9th floor of Building 101.

작업자 배정 데이터 베이스(17)는 동별 층별 세대별 실별 부재에 대한 작업자를 배정한 결과를 저장한다. 예를 들어 101동 9층 901호의 안방 벽체 1번을 어떤 작업자가 언제 시공해야 하는지에 관한 내용을 나타낸다. 안방 벽체 1번 철근은 하루 만에 시공할 수 있으므로 철근 작업자 1번인 홍길동을 배정한다.The worker assignment database 17 stores the results of assigning workers to absences by building, floor, household, and room. For example, it indicates which worker should construct wall number 1 in the master bedroom of room 901 on the 9th floor of Building 101 and when. Since the No. 1 rebar for the master bedroom wall can be constructed in one day, Hong Gil-dong, the No. 1 rebar worker, is assigned.

도 2 내지 4는 본 발명의 일실시예에 따른 개인별 작업배정을 위한 공사방법 분석 방법의 전체 흐름도이다.2 to 4 are overall flowcharts of a construction method analysis method for individual work assignment according to an embodiment of the present invention.

먼저 일 실시예에 따른 도 2를 참조하면, 아파트 골조의 건축도면, 구조도면, BIM 도면을 저장한다(S10). 아파트 각 동 1개 층을 2개의 존으로 분할한다(S20). 예를 들어 'ㄱ'자 모양의 평면 아파트에서 A존(101호, 102호, 코어 1번)과 B존(103호, 104호, 코어 2번)으로 2개로 분할한다.First, referring to FIG. 2 according to one embodiment, the architectural drawing, structural drawing, and BIM drawing of the apartment frame are stored (S10). One floor of each apartment building is divided into two zones (S20). For example, in an 'ㄱ' shaped flat apartment, it is divided into two: Zone A (No. 101, No. 102, Core No. 1) and Zone B (No. 103, No. 104, Core No. 2).

상기 분할된 A존과 B존에 대한 공정표를 작성하여 공정표 데이터 베이스(16)에 저장한다(S30). A schedule for the divided A zone and B zone is created and stored in the schedule database 16 (S30).

101동과 102동은 짝을 이루어 A공구로 분할되고, 각 동의 A존과 B존의 1개층 작업일수는 4일이며, A존과 B존은 2일 차이로 진행하고, 101동과 102동은 1일 차이 또는 3일 차이로 진행하는 공정표를 작성한다. 공정표의 최소 시간단위는 시간대별 또는 적어도 오전 오후 단위이다.Buildings 101 and 102 are paired and divided into section A, the number of working days for one floor in zone A and zone B of each building is 4 days, zone A and zone B are carried out 2 days apart, and building 101 and 102 are divided into sections. Creates a schedule that progresses by 1 day or 3 days. The minimum time unit of the schedule is by time zone or at least morning and afternoon units.

1일차에는 101동 A존 101호, 102호, 코어 1번에 대하여 먹매김, 철근 양중, 벽체 철근 설치, 벽체 형틀 설치 작업이 포함된다.Day 1 includes filling, lifting rebar, installing wall rebar, and installing wall frame for Building 101, Zone A, No. 101, No. 102, and Core No. 1.

다음으로 각 실별 부재별 형틀 및 철근의 수량을 산출하여 자재 수량 데이터 베이스(14)에 저장한다(S40). Next, the quantity of frames and reinforcing bars for each member in each room is calculated and stored in the material quantity database 14 (S40).

예를 들어 101동 101호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 각각의 벽체와 슬라브에 대하여 거푸집과 철근 수량을 저장한다.For example, the quantity of formwork and rebar is stored for each wall and slab for the master bedroom, living room, kitchen, study room, small room, bathroom 1, bathroom 2, and entrance veranda in building 101, room 101.

그리고 각 실별 부재별 형틀 및 철근의 수량을 작업자 개인별 작업생산성 데이터 베이스(15)의 작업자 생산성으로 나누어 각 부재에 대해 작업자를 배정한다(S50).Then, the quantity of frames and reinforcing bars for each member in each room is divided by the worker productivity of the individual worker work productivity database (15) to assign a worker to each member (S50).

예를 들어 101동 101호의 안방의 4개의 벽체 중 벽체 1번과 2번의 철근이 각각 1,000kg이고 철근 작업자 1번인 홍길동의 생산성이 1일 1,500kg이면 벽체 1번에 과 철근 작업자 1번을 벽체 1번에 100% 배정하고 벽체 2번에 50%를 배정한 후, 2번 벽체의 나머지 50%에는 다음으로 2번 철근 작업자를 배정한다.For example, among the four walls of the master bedroom of building 101, number 101, if the rebar for walls 1 and 2 is 1,000 kg each, and the productivity of Hong Gil-dong, the rebar worker No. 1, is 1,500 kg per day, then the productivity of rebar worker No. 1 is 1,500 kg per day, and the rebar worker No. 1 is placed on wall 1. After allocating 100% to Wall No. 2 and 50% to Wall No. 2, rebar worker No. 2 is then assigned to the remaining 50% of Wall No. 2.

위와 같은 방식으로 101호부터 104호 순서로 형틀 및 철근 작업자를 배정하여 1개층 배정을 완료한다.In the same manner as above, frame and rebar workers are assigned in the order from No. 101 to No. 104 to complete the assignment of one floor.

다음으로 그 상층인 2층에 대하여 작업자를 1층에서의 배정과 같은 방식으로 배정한다(S60). 그리고 마지막 층인 35층까지의 배정을 완료하여 골조공사에 대한 배정을 완료한다.Next, workers are assigned to the upper second floor in the same manner as the first floor (S60). And by completing the allocation to the 35th floor, which is the last floor, the allocation for the framing work is completed.

배정이 완료되면, 시간대별 오전 오후 단위로 필요한 작업자수를 산출하여 작업자 소요추이를 산출한다(S70). Once assignment is completed, the number of workers required is calculated in the morning and afternoon for each time zone, and the worker requirement trend is calculated (S70).

작업자수 추이를 판단한 결과 작업자수가 불규칙하면(S80), 다른 배정 안을 적용하여 인원을 산출하는 과정을 되풀이 한다(S90).As a result of judging the trend in the number of workers, if the number of workers is irregular (S80), the process of calculating the number of people is repeated by applying a different allocation plan (S90).

다수의 경우의 수에 대한 작업자 배정안에 대한 시뮬레이션을 통해 시뮬레이션별 Through simulation of worker assignment plans for a large number of cases, each simulation

인원수 소요추이, 작업시간에 대한 정량적인 분석 지수 지표를 산출한다(S100). Calculate quantitative analysis indices for the number of people required and work hours (S100).

이중 가장 우수한 작업자 배정안을 판단한 후 제1안으로 선정한다(S110).Among these, the best worker assignment plan is judged and selected as the first plan (S110).

상기 단계에서 제1안이 선정되면 부재리스트와 그에 대응하는 작업자 리스트를 표 또는 평면도 상에 나타내어 용이하게 알 수 있고 관리할 수 있도록 나타낸다(S120).If the first plan is selected in the above step, the member list and the corresponding worker list are displayed on a table or floor plan so that they can be easily seen and managed (S120).

이상의 과정을 통해 작업자 개인별 작업자 배정 계획이 수립완료 되었다.Through the above process, a worker assignment plan for each worker was established.

상기 단계를 통해 산출된 작업자 배정 결과를 작업자 배정 데이터 베이스(17)에 저장한다(S130).The worker assignment results calculated through the above steps are stored in the worker assignment database 17 (S130).

다음은 공사착수에 따라 공사실적을 수집하는 단계를 설명한다.The following describes the steps for collecting construction performance following the start of construction.

1층 101동 101호 공사가 시작되면 1일차에 작업자를 투입하고 오전 오후 또는 1일차 작업 실적을 수집한 후 작업자 개인별 작업생산성 데이터 베이스(15)에 저장한다(S140).When construction of building 101, room 101 on the first floor begins, workers are assigned on the first day, work performance in the morning and afternoon or on the first day is collected and stored in the work productivity database 15 for each worker (S140).

실적이 수집되면 상기(S50)의 계획단계의 생산성 값과 상기 (S140)단계의 실적 생산성 값을 비교하여 차이를 산출한다(S150). When the performance is collected, the productivity value of the planning stage (S50) is compared with the performance productivity value of the (S140) stage and the difference is calculated (S150).

그리고 산출된 생산성 데이터는 작업자 개인별 작업생산성 데이터 베이스(15)에 저장한다. 데이터는 공사명, 동, 층, 세대, 방의 명칭으로 구성된 위치 및 부위 정보에 대한 생산성 및 작업시간 정보를 포함한다.And the calculated productivity data is stored in the work productivity database 15 for each worker. The data includes productivity and work time information on location and area information consisting of construction name, building, floor, household, and room name.

생산성 차이의 분석결과에 따라, 작업자 개인의 생산성 차이(작업한 철근 수량 차이)를 산출하여 미달되는 작업자와 초과하는 작업자를 판단한다(S160). According to the results of the analysis of the productivity difference, the difference in productivity of each worker (difference in the number of rebars worked) is calculated to determine which workers are under-performing and those who are over-performing (S160).

미달되는 공사구역에는 작업자를 추가로 투입하거나 교체하여 각 공사 구역별로 계획된 공사일정과 작업시간을 준수할 수 있도록 조치한다(S170).Measures are taken to ensure compliance with the construction schedule and work hours planned for each construction zone by adding additional workers or replacing them in construction areas where the work capacity is insufficient (S170).

위와 같은 방식으로 계획 대비 실적을 비교 분석하고 차이에 대한 보정을 지속적이고 체계적으로 진행하는 과정을 반복한다(S180).In the same manner as above, the process of comparing and analyzing performance against plan and correcting for differences is repeated continuously and systematically (S180).

골조공사 몇 개층 단위, 5개층 또는 10개층 단위 그리고 골조공사 완료 시점에 대한 개인별 및 전체 생산성 분석을 실시한다(S190).Individual and overall productivity analysis is performed for several floors of framing work, 5 or 10 floors, and the time of completion of framing work (S190).

이상의 과정을 통해 작업자가 101동과 102동의 구역을 이동해가면서 한 개층 한 개층 시공하는 과정에 대한 공사방법을 분석하였다.Through the above process, the construction method for the process of constructing each floor while workers moved between buildings 101 and 102 was analyzed.

다음은 본 발명의 실제 공사에 대한 적용의 실시예를 설명한다.The following describes an example of application of the present invention to actual construction.

도 5는 본 발명의 일실시예에 따른 판상형 아파트의 공사개요이다. 조감도를 보면 아파트 동수는 20개동 3,000세대 이상의 초대형 아파트 단지이며 중앙의 배치도를 보면 평면은 'ㄱ'자 형태이고 4개 세대와 2개의 코어로 구성되어 있다. 하단 세대 평면도를 보면 침실 1(안방) 작은방 거실 부엌 화장실 등이다. Figure 5 is an outline of the construction of a plate-type apartment according to an embodiment of the present invention. Looking at the bird's eye view, it is a very large apartment complex with 20 apartment buildings and more than 3,000 households. Looking at the central layout, the floor plan is in an 'ㄱ' shape and consists of 4 apartments and 2 cores. If you look at the floor plan of the unit below, you will see bedroom 1 (main room), a small room, living room, kitchen, bathroom, etc.

구조는 철근콘크리트 벽식구조와 무량판 슬라브이다.The structure is a reinforced concrete wall structure and a mass plate slab.

도 6은 본 발명의 일실시예에 따른 골조공사 공정표이다. 각 동은 A존(2세대와 코어 1번)과 B존(2개 세대와 코어 2번)으로 분할되고, A존과 B존은 층당 4일 싸이클이며, 2일차이로 진행된다. 101동과 102동은 A공구로 분할되고 1일 또는 3일 차이로 진행된다.Figure 6 is a framing construction process table according to an embodiment of the present invention. Each building is divided into Zone A (2nd generation and Core 1) and Zone B (2 households and Core 2), and Zones A and B have a 4-day cycle per floor, with 2 days difference. Buildings 101 and 102 are divided into Section A and are held 1 or 3 days apart.

예를 들어 101동 5층 A존(501호, 502호, 코어 1번)은 월요일에 콘크리트를 타설하고 102동 5층 A존(501호, 502호, 코어 1번)은 화요일에 타설하고, 101동 5층 B존(503호, 504호, 코어 2번)은 수요일에 콘크리트를 타설하고, 102동 5층 B존(503호, 504호, 코어 2번)은 목요일에 타설하는 일정으로 진행한다.For example, concrete is poured for Zone A on the 5th floor of Building 101 (Rooms 501, 502, Core No. 1) on Monday, and Zone A on the 5th floor of Building 102 (Rooms 501, 502, Core No. 1) is poured on Tuesday. Concrete will be poured in Zone B on the 5th floor of Building 101 (Rooms 503, 504, Core No. 2) on Wednesday, and Zone B on the 5th floor of Building 102 (Rooms 503, 504, Core No. 2) on Thursday. do.

도 6보다 하위 레벨의 상세 공정표로서 일자별 존별 세대별 부재별 상세 공정표는 별도로 작성되고 저장된다.As a detailed schedule at a lower level than Figure 6, the detailed schedule for each date, zone, generation, and member is created and stored separately.

도 7은 본 발명의 일실시예에 따른 101동 501호 세대의 각각의 벽체 부재에 대한 번호부여를 세대 평면도상에 나타낸 것이다. 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 벽체 및 슬라브의 거푸집과 철근 부재 리스트를 포함한다.Figure 7 shows the numbering of each wall member of unit 501 in building 101 according to an embodiment of the present invention on a household floor plan. Includes a list of formwork and rebar members for walls and slabs for the master bedroom, living room, kitchen, study room, small room, bathroom 1, bathroom 2, and the entrance veranda.

도 8은 본 발명의 일실시예에 따른 도 7의 각각의 부재에 대한 각 실별 벽체 부재에 대한 철근 수량을 나타낸 것이다. 이 외에 슬라브 철근, 벽체 형틀, 슬라브 형틀 수량을 산출된다.Figure 8 shows the quantity of reinforcing bars for each wall member in each room for each member in Figure 7 according to an embodiment of the present invention. In addition, the quantity of slab rebar, wall form, and slab form is calculated.

상기 부재별 수량은 적산 전문회사에서 일반적으로 산출하고 있으나 자재 종류와 규격별로 층별로 집계하므로 다시 세대 및 부재별로 나눌 필요가 있다.The quantity for each member is generally calculated by a company specializing in integration, but since it is calculated by layer by material type and standard, it is necessary to divide it again by household and member.

도 9는 본 발명의 일실시예에 따른 작업자의 개인별 생산성 실적 데이터를 나타낸 것이다. 철근 작업자 1번인 홍길동의 벽체 철근과 슬라브 철근의 1일 생산성 데이터가 표시되어 있다. 철근 콘크리트 전문회사에 속하는 형틀 작업자와 철근 작업자의 생산성 데이터의 일부가 표시되어 있다. Figure 9 shows individual productivity performance data of workers according to an embodiment of the present invention. The daily productivity data of wall rebar and slab rebar for Hong Gil-dong, rebar worker number 1, is displayed. Some of the productivity data of form workers and rebar workers belonging to a company specializing in reinforced concrete are displayed.

형틀 작업자의 생산성 데이터도 별도로 산출되고 관리된다.Productivity data of form workers is also calculated and managed separately.

도 10은 본 발명의 일실시예에 따른 도 8의 각각의 부재에 작업자를 배정한 내용을 나타낸 것이다. 101동 501호 안방 벽체 01번에는 철근작업자 1번 홍길동이 배정되어 있고, 주방 벽체 04번에는 철근작업자 1번 홍길동과 철근 5번 작업자가 동시에 배정되어 있다.Figure 10 shows the assignment of workers to each member of Figure 8 according to an embodiment of the present invention. Rebar worker No. 1 Hong Gil-dong is assigned to wall number 01 of the master bedroom in room 501 of building 101, and rebar worker number 1 Hong Gil-dong and rebar worker number 5 are assigned to kitchen wall number 04.

형틀 작업자도 위와 같은 방식으로 각 실에 배정되게 된다.Form workers are also assigned to each room in the same manner as above.

도 11은 본 발명의 일실시예에 따른 일별 작업자의 이동경로를 도면상에 나타낸 것이다. 철근 작업자 1번 홍길동은 1일차에는 101동 A존인 501호에서 작업하고 2일차에는 102동 A존 501호에서 작업하고 3일차에는 101동 B존인 503호에서 작업을 하게 되는 내용을 나타내고 있다.Figure 11 shows the daily movement path of a worker according to an embodiment of the present invention. This shows that Hong Gil-dong, rebar worker No. 1, works in room 501, zone A of building 101, on the first day, in room 501, zone A of building 102, on the second day, and in room 503, zone B of building 101, on the third day.

도 12는 본 발명의 일실시예에 따른 계획 대비 실적과의 차이를 나타낸 것이다. 철근 작업자 1번 홍길동은 1일차에는 101동 A존인 501호에서 작업하였으나 계획된 수량을 시공하지 못하였다. 이에 따라 관리자는 작업자를 추가로 투입하거나 야간작업을 지시하거나 작업자 교체를 실시할 수 있다.Figure 12 shows the difference between plan and performance according to an embodiment of the present invention. Rebar worker No. 1 Hong Gil-dong worked in room 501, zone A of building 101, on the first day, but was unable to construct the planned quantity. Accordingly, managers can add additional workers, order night work, or replace workers.

원인과 문제점을 개인별로 정확하게 파악할 수 있으므로 필요한 조치도 신속하고 용이하게 취할 수 있다. 이에 따라 정해진 공정표대로 공사를 진행하는 능력이 높아진다.Because causes and problems can be accurately identified for each individual, necessary measures can be taken quickly and easily. As a result, the ability to proceed with construction according to the set schedule increases.

도 13은 본 발명의 일실시예에 따른 101동과 102동을 합한 2개동의 철근 작업자의 일별 소요인원 추이를 나타낸다. 소요인원이 균등함을 나타내며 월요일에 101동에서 남은 인원이 102동에서 작업하면 반대의 경우로 화요일에는 102동에서 남은 인원이 101동에서 작업하면서 전체적인 밸런스를 나타내고 있다. Figure 13 shows the trend of the daily number of rebar workers in two buildings, including buildings 101 and 102, according to an embodiment of the present invention. This indicates that the number of people required is equal. On Monday, the remaining people from Building 101 work in Building 102. Conversely, on Tuesday, the remaining people from Building 102 work in Building 101, indicating overall balance.

이와 같은 균등한 작업자 수요는 작업자 손실을 줄여 인건비를 절감하고 품질을 확보하고 안전사고를 예방하여 공사기간과 작업시간을 단축하고 빠른 시간에 동일한 부재를 시공함에 따라 학습효과를 통한 생산성 향상을 나타내게 된다.This equal demand for workers reduces labor costs by reducing worker losses, secures quality, and prevents safety accidents, shortening the construction period and work hours, and improving productivity through learning effects by constructing the same members in a faster time. .

상술한 개인별 작업자 배정 방법으로부터 팀별 작업자 배정방법을 적용할 수 있으며 철근 콘크리트 전문 건설회사는 상기 개념과 사상을 이용하여 효율적인 작업자 배정과 운용관리를 할 수 있을 것이다.From the above-described individual worker allocation method, the team worker allocation method can be applied, and a construction company specializing in reinforced concrete will be able to efficiently assign workers and manage operations using the above concepts and ideas.

이상과 같이 본 발명은 아파트 골조공사의 핵심인 철근 및 형틀 작업자의 최소단위인 작업자 개인별 작업계획을 수립할 수 있는 작업자 운용방법을 목적으로 한다.As described above, the purpose of the present invention is to provide a worker operation method that can establish a work plan for each individual worker, who is the minimum unit of rebar and formwork workers, which are the core of apartment framing construction.

작업해야할 대상인 형틀과 철근 수량과 이를 소화하는 작업자의 개인 역량에 따라 작업시간과 순서를 결정하여 최적의 공사방법을 위한 작업자 배정 방법을 분석하여 최적의 인력운용 방법을 찾아내는 것이다. The task is to determine the work time and sequence according to the quantity of frames and rebars to be worked on and the individual capabilities of the workers handling them, and to analyze the worker assignment method for the optimal construction method to find the optimal method of manpower management.

본 실시예서는 판상형 아파트에 방법을 적용하였으나 타워형 아파트, 주상복합, 오피스텔 골조공사도 동일하거나 유사한 방법과 순서로 골조공사를 시공하므로 상기 방법이 동일하게 적용될 수 있음을 건설기술자들은 명백히 알 수 있을 것이다.In this example, the method was applied to a plate-type apartment, but construction engineers will clearly know that the method can be applied in the same way to tower-type apartments, residential-commercial complexes, and officetels, since the framework work is also constructed using the same or similar methods and order. .

개인별 작업 배정 방법을 위한 공사방법 분석장치(10)
제어부(11)
건축도면 데이터베이스(12)
기준층 평면분할 데이터 베이스(13)
자재 수량 데이터 베이스(14)
작업자 개인별 작업생산성 데이터 베이스(15)
공정표 데이터 베이스(16)
작업자 배정 데이터 베이스(17)
Construction method analysis device for individual work assignment method (10)
Control unit (11)
Architectural drawing database (12)
Base floor plane division database (13)
Material Quantity Database(14)
Work productivity database for individual workers (15)
Schedule database (16)
Worker Assignment Database (17)

Claims (2)

제어부(11)가 아파트 골조의 건축도면, 구조도면, BIM 도면을 건축 도면 데이터 베이스(12)에 저장하는 단계(S10);
상기 제어부(11)가 아파트 각 동 1개 층을 2개의 존으로 분할하는 단계(S20);
상기 제어부(11)가 상기 2개로 분할된 존에 대한 공정표를 작성하여 공정표 데이터 베이스(16)에 저장하는 단계(S30);
상기 제어부(11)가 각 실별 부재별 형틀 및 철근의 수량을 산출하여 자재 수량 데이터 베이스(14)에 저장하는 단계(S40);
각 실별 부재별 형틀 및 철근의 수량을 작업자 개인별 작업생산성 데이터 베이스(15)의 작업자 생산성으로 나누어 각 부재에 대해 작업자를 배정하는 단계(S50);
상기 제어부(11)가 그 상층인 각 층에 대하여 작업자를 1층에서의 배정과 같은 방식으로 배정하는 단계(S60);
상기 제어부(11)가 시간대별 오전 오후 단위로 필요한 작업자수를 산출하여 작업자 소요추이를 산출하는 단계(S70);
상기 제어부(11)가 부재리스트와 그에 대응하는 작업자 리스트를 표 또는 평면도 상에 나타내는 단계(S80);
상기 제어부(11)가 산출된 작업자 배정 결과를 작업자 배정 데이터 베이스(17)에 저장하는 단계(S90) ;
작업자를 투입하고 오전 오후 또는 일별 작업 실적을 수집한 후 상기 작업자 개인별 작업생산성 데이터 베이스(15)에 저장하는 단계(S100) ;
계획단계의 생산성 값과 실적 생산성 값을 비교하여 차이를 산출하고 상기 작업자 개인별 작업생산성 데이터 베이스(15)에 저장하는 단계(S110)를 포함하고,

상기 단계(S20)는, 'ㄱ'자 모양의 평면 아파트를 A존(101호, 102호, 코어 1번)과 B존(103호, 104호, 코어 2번)으로 분할하고,
상기 단계(S30)는 101동과 102동은 짝을 이루어 A공구로 분할되고, 각 동의 A존과 B존의 1개층 작업일수는 4일이며, A존과 B존은 2일 차이로 진행하고, 101동과 102동은 1일 차이 또는 3일 차이로 진행하는 공정표를 작성하되,
상기 공정표의 최소 시간단위는 시간대별 또는 적어도 오전 오후 단위이고,
1일차에는 101동 A존 101호, 102호, 코어 1번에 대하여 먹매김, 철근 양중, 벽체 철근 설치, 벽체 형틀 설치 작업이 포함되고,
상기 단계(S40)는 101동 101호의 안방 거실 주방 공부방 작은방 화장실1 화장실2, 현관 베란다에 대한 각각의 벽체와 슬라브에 대하여 거푸집과 철근 수량을 상기 자재 수량 데이터 베이스(14)에 저장하고,
상기 단계(S50)는, 101동 101호의 안방의 4개의 벽체 중 벽체 1번과 2번의 철근이 각각 1,000kg이고 철근 작업자 1번인 홍길동의 생산성이 1일 1,500kg이면 벽체 1번에 과 철근 작업자 1번을 벽체 1번에 100% 배정하고 벽체 2번에 50%를 배정한 후, 2번 벽체의 나머지 50%에는 다음으로 2번 철근 작업자를 배정하며, 이러한 방식으로 101호부터 104호 순서로 형틀 및 철근 작업자를 배정하여 1개층 배정을 완료하는 것을 특징으로 하는
공동주택 골조공사 작업자의 작업장소 이동경로 분석 방법.
A step (S10) of the control unit 11 storing architectural drawings, structural drawings, and BIM drawings of the apartment frame in the architectural drawing database 12;
The control unit 11 divides one floor of each apartment building into two zones (S20);
A step (S30) of the control unit 11 creating a schedule for the two zones and storing the schedule in the schedule database 16;
The control unit 11 calculates the quantity of frames and reinforcing bars for each room and member and stores them in the material quantity database 14 (S40);
A step of assigning workers to each member by dividing the quantity of frames and reinforcing bars for each member in each room by the worker productivity of the individual worker work productivity database (15) (S50);
The control unit 11 assigns workers to each upper floor in the same manner as the first floor (S60);
A step (S70) in which the control unit 11 calculates the number of workers required for each time zone in the morning and afternoon and calculates the worker requirement trend;
A step (S80) of the control unit 11 displaying the member list and the corresponding worker list on a table or floor plan;
A step (S90) of the control unit 11 storing the calculated worker assignment results in the worker assignment database 17;
A step (S100) of deploying workers and collecting work performance in the morning, afternoon, or daily, and then storing them in the worker's individual work productivity database (15);
Comprising the step (S110) of comparing the productivity value of the planning stage and the actual productivity value to calculate the difference and storing it in the work productivity database 15 for each worker,

In the step (S20), the 'ㄱ' shaped flat apartment is divided into A zone (No. 101, No. 102, Core No. 1) and B zone (No. 103, No. 104, Core No. 2),
In the above step (S30), buildings 101 and 102 are paired and divided into section A, the number of working days for one floor in zone A and zone B of each building is 4 days, and zone A and zone B are carried out 2 days apart. , Buildings 101 and 102 must prepare a progress schedule with a difference of 1 or 3 days.
The minimum time unit of the schedule is by time zone or at least the morning and afternoon units,
Day 1 includes work on filling, lifting rebar, installing wall rebar, and installing wall form for Building 101, Zone A, No. 101, No. 102, and Core No. 1.
In the step (S40), the quantity of formwork and rebar for each wall and slab for the master bedroom, living room, kitchen, study room, small room, toilet 1, toilet 2, and entrance veranda of Building 101, Room 101 is stored in the material quantity database 14,
In the step (S50), among the four walls of the master bedroom of Building 101, Room 101, if the reinforcing bars for walls 1 and 2 are 1,000 kg each and the productivity of Hong Gil-dong, the reinforcing bar worker No. 1, is 1,500 kg per day, then wall No. 1 and reinforcing bar worker 1 After allocating 100% of the number to wall number 1 and 50% to wall number 2, the number 2 rebar worker is assigned to the remaining 50% of wall number 2, and in this way, the form and frame are installed in order from number 101 to number 104. Characterized by assigning a rebar worker to complete the assignment of one floor
Analysis method of workplace movement path of apartment building construction workers.
제어부(11), 건축 도면 데이터 베이스(12), 기준층 평면 공구 분할 데이터 베이스(13), 자재 수량 데이터 베이스(14), 작업자 개인별 작업생산성 데이터 베이스(15), 공정표 데이터 베이스(16) 및 작업자 배정 데이터 베이스(17)를 포함하고 상기 제어부는 제1항의 방법을 실행하는 동주택 골조공사 작업자의 작업장소 이동경로 분석 시스템.
Control unit (11), architectural drawing database (12), reference floor plane tool division database (13), material quantity database (14), individual worker work productivity database (15), schedule database (16), and worker assignment A system for analyzing the movement path of a home framing worker, including a database (17), wherein the control unit executes the method of claim 1.
KR1020180019576A 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction KR102613585B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020180019576A KR102613585B1 (en) 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
KR1020230178158A KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180019576A KR102613585B1 (en) 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020230178158A Division KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Publications (2)

Publication Number Publication Date
KR20190099747A KR20190099747A (en) 2019-08-28
KR102613585B1 true KR102613585B1 (en) 2023-12-12

Family

ID=67775293

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1020180019576A KR102613585B1 (en) 2018-02-19 2018-02-19 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
KR1020230178158A KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Family Applications After (1)

Application Number Title Priority Date Filing Date
KR1020230178158A KR20230169923A (en) 2018-02-19 2023-12-08 An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction

Country Status (1)

Country Link
KR (2) KR102613585B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102253818B1 (en) * 2020-09-10 2021-05-18 윤지용 Method of providing construction materials production and server performing the same

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002056048A (en) * 2000-08-08 2002-02-20 Maeda Corp System and method for construction scheduling

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070077159A (en) * 2007-06-25 2007-07-25 광운대학교 산학협력단 Failure reason analysis system
KR101162458B1 (en) * 2010-12-17 2012-07-04 현대건설주식회사 Method of construction planning of supertall buildings

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002056048A (en) * 2000-08-08 2002-02-20 Maeda Corp System and method for construction scheduling

Also Published As

Publication number Publication date
KR20190099747A (en) 2019-08-28
KR20230169923A (en) 2023-12-18

Similar Documents

Publication Publication Date Title
Elbeltagi et al. Dynamic layout of construction temporary facilities considering safety
Riley et al. Patterns of construction-space use in multistory buildings
US20060074609A1 (en) System and method for determining variance in building structures
KR20230169923A (en) An apparatus and method for analyzing a working area and route of form worker and rebar worker at a housing construction
Huang et al. Planning gang formwork operations for building construction using simulations
US8244569B2 (en) Non-destructive element splitting using location-based construction planning models
KR20190039012A (en) Analysis device for constructing frame of building for calculating number of worker and method for the same
Lee et al. Automated system for form layout to increase the proportion of standard forms and improve work efficiency
Faghirinejadfard et al. Economic comparison of industrialized building system and conventional construction system using building information modeling
Wu et al. BIM-based estimation of vertical transportation demands during the construction of high-rise buildings
Sacks et al. A project model for an automated building system: design and planning phases
JP2006201979A (en) Program for supporting construction planning of building
KR101162458B1 (en) Method of construction planning of supertall buildings
JPH0589211A (en) Integrated production managing system for building
US20070239410A1 (en) Location-based construction planning and scheduling system
Schramm et al. The role of production system design in the management of complex projects
Francis et al. Spatiotemporal chronographical modeling of procurement and material flow for building projects
Okodi-Iyah A comparative evaluation of the environmental impact of prefabrication versus conventional construction in UAE’s construction industry
Heineck et al. Transparency in building construction: a case study
Katti et al. Project Crashing to Solve Time-Cost TradeOff
Birgisson Discrete-event simulations of construction related production system
Hazem et al. Construction Automation: Post-Pandemic Integrated Robotized Construction Sites
Abidin Simulation of industrialised building system formation for housing construction
Zhang Construction productivity improvement through industrialized construction methods
CN117993671A (en) Construction dispatching method, system and storage medium

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant