KR20190096751A - Methods for top-down constructing panel type retaining wall structure - Google Patents

Methods for top-down constructing panel type retaining wall structure Download PDF

Info

Publication number
KR20190096751A
KR20190096751A KR1020180016557A KR20180016557A KR20190096751A KR 20190096751 A KR20190096751 A KR 20190096751A KR 1020180016557 A KR1020180016557 A KR 1020180016557A KR 20180016557 A KR20180016557 A KR 20180016557A KR 20190096751 A KR20190096751 A KR 20190096751A
Authority
KR
South Korea
Prior art keywords
retaining wall
block
wall block
cut slope
cut
Prior art date
Application number
KR1020180016557A
Other languages
Korean (ko)
Other versions
KR102132470B1 (en
Inventor
양종인
조충식
Original Assignee
다원엔지니어링 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 다원엔지니어링 주식회사 filed Critical 다원엔지니어링 주식회사
Priority to KR1020180016557A priority Critical patent/KR102132470B1/en
Publication of KR20190096751A publication Critical patent/KR20190096751A/en
Application granted granted Critical
Publication of KR102132470B1 publication Critical patent/KR102132470B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/025Retaining or protecting walls made up of similar modular elements stacked without mortar
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

Disclosed is a top-down panel type retaining wall construction method. The method includes: a step (a) of cutting a position in which a first retaining wall block is expected to be installed; a step (b) of installing a first foundation block having a fixed width on a floor adjacent to the cut slope; a step (c) of placing the first retaining wall block on the first foundation block obliquely in a direction to the cut slope; a step (d) of fixing the first retaining wall block to the ground of the cut slope; a step (e) of cutting a position, in which a second retaining wall block is expected to be installed, by excavating a width outer floor surface of the first foundation block; a step (f) of installing a second foundation block having a fixed width on a floor adjacent to the cut slope; a step (g) of placing the second retaining wall block on the second foundation block obliquely in a direction to the cut slope; a step (h) of fixing the second retaining wall block to the ground of the cut slope; a step (i) of cutting a position, in which a third retaining wall block is expected to be installed, by excavating a width outer floor surface of the second foundation block; and a step (j) of constructing n-number of retaining wall blocks as stairs by repeating processes, which are practically the same as the steps from (f) to (i), on the third to n-number of retaining wall blocks. Therefore, the method is capable of increasing working efficiency by preventing interference between excavating machines.

Description

탑다운이 가능한 패널식 옹벽 시공방법{Methods for top-down constructing panel type retaining wall structure}Method for top-down constructing panel type retaining wall structure}

본 발명은 패널식 옹벽 시공방법에 관한 것으로서, 더욱 상세하게는 프리캐스트 패널을 사면에 설치하여 지반을 보강하는 패널식 옹벽 시공방법에 관한 것이다.The present invention relates to a panel retaining wall construction method, and more particularly to a panel retaining wall construction method for reinforcing the ground by installing a precast panel on the slope.

일반적으로, 옹벽은 토압력에 저항하여 흙이 무너지지 않도록 지지하는 구조물이다. 최근에는 블록과 같은 적층부재를 다수 쌓아서 옹벽을 만들고 있는데, 이러한 옹벽은 철근콘크리트 옹벽 등에 비하여 사면의 절개를 최소화 할 수 있고, 미려한 전면 벽을 연출할 수 있으며, 철근콘크리트 옹벽보다 제조가 간편하고 용이하며 현장까지의 운반이 용이하다는 장점이 있기 때문에 널리 시공되고 있다.In general, the retaining wall is a structure that supports the soil so that it does not collapse by resisting earth pressure. Recently, the retaining wall is made by stacking a large number of laminated members such as blocks.The retaining wall can minimize the incision of the slope compared to the reinforced concrete retaining wall, can produce a beautiful front wall, and is easier and easier to manufacture than the reinforced concrete retaining wall. It is widely used because it has the advantage of easy transportation to the site.

적층부재를 이용하는 여러 방식의 옹벽 공법들 중에 보강재를 활용한 가압식 그라우팅 공법이 있다. 이 공법은 보강재를 지반에 정착시킨 후 프리캐스트 패널(이하, '옹벽 블록'이라고 함)을 토공면에 지면과 수직으로 설치하여 보강재와 연결하고, 가압식 그라우팅을 실시하여 지반을 보강하는 공법이다. 여기서, 보강재로는 강관이나 이형 철근, 앵커 등 다양한 종류가 채용 가능하다.Among several retaining wall methods using a laminated member, there is a pressurized grouting method using a reinforcing material. This method is a method of reinforcing the ground by fixing the reinforcement on the ground and then connecting the reinforcement by installing a precast panel (hereinafter referred to as a 'retaining wall block') perpendicular to the ground on the earthwork surface. Here, as the reinforcing material, various kinds such as steel pipes, deformed reinforcing bars, and anchors may be employed.

깎기사면이나 자연사면의 경우에는 옹벽 블록을 사면에 설치하여 지반을 보강하는 사면 옹벽 공법이 요구된다. 사면 보강 옹벽 공법에 사용되는 옹벽 블록은 일반적으로 소정의 베이스 부재에 올려진 상태에서 후방으로 기울이는 시공에 의해 사면 위에 배치된다. 또한, 어느 하나의 옹벽 블록의 상부에 다른 하나의 옹벽 블록을 올려 놓는 작업을 반복하여 연쇄적으로 연결함으로써 계단형의 옹벽 시공이 이루어진다.In the case of shearing slopes or natural slopes, a slope retaining wall method for reinforcing the ground by installing retaining wall blocks on the slope is required. The retaining wall block used in the slope reinforcing retaining wall method is generally disposed on the slope by a construction inclined backward while being mounted on a predetermined base member. In addition, the step of retaining wall construction is achieved by repeatedly connecting the other retaining wall block on the top of any one retaining wall block chain.

가압식 그라우팅 공정은, 보강재를 통해 가압 그라우팅을 실시하여 보강 그라우트재를 주입하고 보강 부재를 정착시킴으로써 지반과 실질적으로 일체화된 보강 구조를 형성한다.The pressure grouting process forms a reinforcement structure substantially integrated with the ground by applying pressure grouting through the reinforcement to inject the reinforcement grout material and fix the reinforcement member.

프리캐스트 패널의 배면과 지반의 사면 사이의 간극에는 토사나 뒤채움 그라우트 또는 콘크리트를 투입하여 뒤채움 시공을 한다. 이에 따라, 프리캐스트 패널의 배면과 사면 사이는 뒤채움재로 채워진다.In the gap between the back surface of the precast panel and the slope of the ground, earth or back filling grout or concrete is used to back fill the construction. As a result, the backfill surface is filled with the backfill material.

상기와 같이 종래의 사면 보강 옹벽 구조물은 옹벽 블록을 크레인 등으로 들어 올려 연쇄적으로 쌓아 올리는 방식으로 조립이 되는데, 통상적으로 옹벽 블록은 콘크리트에 의해 성형되어 막대한 중량을 가지므로 적층 작업이 쉽지 않고 공사기간이 오래 소요되는 단점이 있다.As described above, the conventional slope-reinforced retaining wall structure is assembled by lifting the retaining wall block with a crane, etc., and stacking the chain in a stacked manner. Usually, the retaining wall block is formed by concrete and has a huge weight, so that the stacking work is not easy. The disadvantage is that it takes a long time.

또한, 적층 과정에서 상하로 인접한 프리캐스트 패널들 간의 접촉면에 슬립이 발생하여 안전사고가 유발될 수 있는 취약점이 있으므로 이에 대한 개선이 요구된다.In addition, there is a vulnerability that can cause a safety accident due to slip occurs in the contact surface between the adjacent precast panels in the stacking process is required to improve this.

본 발명은 상기와 같은 문제점을 고려하여 창안된 것으로서, 옹벽 블록이 설치될 지점을 파내려가면서 계단형의 옹벽 구조물을 시공할 수 있는 탑다운이 가능한 패널식 옹벽 시공방법을 제공하는 데 그 목적이 있다.The present invention was conceived in view of the above problems, and the object of the present invention is to provide a top-down panel retaining wall construction method capable of constructing a step retaining wall structure while digging a point where the retaining wall block is to be installed. have.

본 발명의 다른 목적은 옹벽 블록이 설치될 지점에 대한 절토 작업시 기설치된 옹벽 블록과 굴착장비 간의 간섭을 예방하여 작업 효율을 향상시킬 수 있는 탑다운이 가능한 패널식 옹벽 시공방법을 제공하는 데 있다.It is another object of the present invention to provide a panel retaining wall construction method capable of top-down, which can improve work efficiency by preventing interference between pre-installed retaining wall blocks and excavation equipment during cutting work for a point where the retaining wall blocks are to be installed. .

본 발명의 또 다른 목적은 각각의 옹벽 블록별로 하중을 분산시킬 수 있는 설치 구조를 가진 탑다운이 가능한 패널식 옹벽 시공방법을 제공하는 데 있다.Still another object of the present invention is to provide a top-down panel retaining wall construction method having a mounting structure capable of distributing load for each retaining wall block.

상기와 같은 목적을 달성하기 위해 본 발명은 (a) 제1 옹벽 블록이 설치될 지점을 절토하는 단계; (b) 절토된 사면에 인접한 바닥에 정해진 폭을 가진 제1 기초 블록을 설치하는 단계; (c) 상기 제1 기초 블록 위에 제1 옹벽 블록을 상기 절토된 사면 방향으로 비스듬히 기울어지게 배치하는 단계; (d) 상기 제1 옹벽 블록을 상기 절토된 사면의 지반에 고정하는 단계; (e) 상기 제1 기초 블록의 외곽 바닥면을 굴착하여 제2 옹벽 블록이 설치될 지점을 절토하는 단계; (f) 절토된 사면에 인접한 바닥에 정해진 폭을 가진 제2 기초 블록을 설치하는 단계; (g) 상기 제2 기초 블록 위에 제2 옹벽 블록을 상기 절토된 사면 방향으로 비스듬히 기울어지게 배치하는 단계; (h) 상기 제2 옹벽 블록을 상기 절토된 사면의 지반에 고정하는 단계; (i) 상기 제2 기초 블록의 외곽 바닥면을 굴착하여 제3 옹벽 블록이 설치될 지점을 절토하는 단계; (j) 제3 옹벽 블록 내지 제n 옹벽 블록에 대해서도 상기 (f) 내지 (i) 단계와 실질적으로 동일한 공정을 하방으로 가면서 반복하여 n개의 옹벽 블록을 계단형으로 시공하는 일련의 공정을 포함하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법을 제공한다.In order to achieve the above object, the present invention comprises the steps of (a) cutting the point where the first retaining wall block is to be installed; (b) installing a first foundation block having a predetermined width at a floor adjacent to the cut slope; (c) arranging a first retaining wall block at an angle to said cut slope obliquely over said first foundation block; (d) fixing the first retaining wall block to the ground of the cut slope; (e) cutting the point where the second retaining wall block is to be installed by excavating the outer bottom surface of the first foundation block; (f) installing a second foundation block having a predetermined width at a floor adjacent to the cut slope; (g) arranging a second retaining wall block at an angle to said cut slope obliquely over said second foundation block; (h) securing the second retaining wall block to the ground of the cut slope; (i) cutting an outer bottom surface of the second foundation block to cut a point where a third retaining wall block is to be installed; (j) including a series of steps for constructing the n retaining wall blocks stepwise by repeating the steps substantially the same as the above steps (f) to (i) for the third retaining wall block to the nth retaining wall block. It provides a top-down panel retaining wall construction method characterized in that.

상기 제1 옹벽 블록 내지 제n 옹벽 블록은 하단에 인접한 전면에 옹벽 블록의 전면으로부터 배면을 향해 경사진 제1 테이퍼부를 구비하고, 제2 내지 제n 옹벽 블록이 설치될 지점을 절토할 때 상기 제1 테이퍼부의 경사면을 이용하여 절토를 진행함으로써 굴착의 용이성을 확보하는 것이 바람직하다.The first retaining wall block to the n-th retaining wall block have a first taper portion inclined from the front surface of the retaining wall block to the rear surface at a front surface adjacent to a lower end thereof, and when cutting the point where the second to n-th retaining wall blocks are to be installed. It is preferable to ensure the ease of excavation by carrying out cutting using the inclined surface of the 1 taper part.

상기 굴착 및 옹벽 블록 고정이 완료된 후에 상기 제1 테이퍼부의 경사면에 마감 블록을 설치하는 공정을 더 포함할 수 있다.The method may further include installing a finishing block on the inclined surface of the first taper part after the excavation and retaining wall block fixing is completed.

상기 제1 옹벽 블록 내지 제n 옹벽 블록의 상단에 인접한 배면에는 옹벽 블록의 배면으로부터 전면을 향해 경사진 제2 테이퍼부가 형성되어 있고, 상기 제1 옹벽 블록의 제2 테이퍼부와 상기 절토된 사면 사이에 마감 블록을 설치하는 공정을 더 포함할 수 있다.On the rear surface adjacent to the upper end of the first retaining wall block to the n-th retaining wall block, a second taper portion inclined toward the front surface from the rear surface of the retaining wall block is formed, and between the second tapered portion of the first retaining wall block and the cut slope The process may further include installing a finishing block.

옹벽 블록이 설치될 지점을 절토하여 사면을 형성한 후 옹벽 블록을 절토된 사면에 배치하기 전에 상기 절토된 사면의 지반에 보강재를 삽입하여 지반을 보강하고, 상기 보강재의 노출 부위를 옹벽 블록에 형성된 홀에 삽입하여 옹벽 블록을 상기 절토된 사면에 배치하는 것이 바람직하다.After forming the slope by cutting the point where the retaining wall block is to be installed, reinforcing the ground by inserting a reinforcement into the ground of the cut slope before placing the retaining wall block on the cut slope, and the exposed portion of the reinforcement is formed on the retaining wall block. It is preferable to insert the retaining wall block on the cut slope by inserting it into the hole.

각 옹벽 블록을 절토된 사면에 배치한 후 상기 옹벽 블록과 상기 절토된 사면 사이의 공간을 토사 및/또는 뒤채움재로 채워서 뒤채움하는 공정을 더 포함할 수 있다.After each retaining wall block is disposed on the cut slope, the process may further include filling the space between the retaining wall block and the cut slope with earth and / or backfill.

본 발명에 따른 탑다운이 가능한 패널식 옹벽 시공방법은 다음과 같은 효과가 있다.Panel-type retaining wall construction method capable of top-down according to the present invention has the following effects.

첫째, 옹벽 블록이 설치될 지점을 파내려가면서 계단형의 옹벽 구조물을 시공하는 탑다운 방식으로 공정이 진행되므로 작업이 편리하고 시공중 안정성을 확보할 수 있다.First, since the process proceeds in a top-down manner to construct a stepped retaining wall structure while digging the point where the retaining wall block is to be installed, it is convenient to work and ensure stability during construction.

둘째, 옹벽 블록의 하단에 위치한 테이퍼부를 이용해 작업공간을 확보하여 다음번 옹벽 블록이 설치될 지점에 대한 굴착이 이루어지므로 기설치된 옹벽 블록과 굴착장비 간의 간섭을 예방하여 작업 효율을 향상시킬 수 있다.Second, since the excavation is made to the point where the next retaining wall block will be installed by securing a working space using a taper portion located at the bottom of the retaining wall block, the work efficiency can be improved by preventing interference between the retaining wall block and the excavating equipment.

셋째, 각각의 옹벽 블록이 수평 바닥면 위에 놓여진 설치 블록에 의해 지지되므로 효과적으로 하중을 분산시킬 수 있다.Third, each retaining wall block is supported by a mounting block placed on a horizontal bottom surface, thereby effectively distributing the load.

넷째, 옹벽 구조물이 계단형으로 완만하게 시공되어 외관이 미려하고 시각적으로 안정성을 느끼게 해주며 경관이 우수한 장점이 있다.Fourth, the retaining wall structure is gently constructed in a staircase shape, which makes the exterior beautiful and visually stable and has an excellent view.

다섯째, 옹벽 블록의 상단에 위치한 테이퍼부를 이용해 상광하협 형상의 뒤채움재 주입구를 형성할 수 있으므로 뒤채움 공정의 작업성을 향상시킬 수 있다.Fifth, it is possible to form the filling material injection hole of the upper and lower narrow shape using the taper portion located on the top of the retaining wall block can improve the workability of the back filling process.

여섯째, 상하로 인접한 옹벽 블록들 사이에 기초 블록과 마감 블록이 개재되므로 옹벽 블록들 간에 슬립이 발생하지 않으며 옹벽의 조립 구조물을 안정적으로 유지할 수 있다.Sixth, since the foundation block and the finishing block are interposed between the vertically adjacent retaining wall blocks, slip does not occur between the retaining wall blocks and the assembly structure of the retaining wall can be stably maintained.

본 명세서에 첨부되는 다음의 도면들은 본 발명의 바람직한 실시예를 예시하는 것이며, 후술되는 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 그러한 도면에 기재된 사항에만 한정되어 해석되어서는 아니된다.
도 1은 본 발명의 바람직한 실시예에 따른 탑다운이 가능한 패널식 옹벽 시공방법이 수행되는 과정을 도시한 흐름도이다.
도 2는 제1 옹벽 블록이 설치될 지점을 절토하고 제1 그라우트 강관을 삽입한 구성을 도시한 단면도이다.
도 3은 도 2에서 제1 옹벽 블록을 설치한 구성을 도시한 단면도이다.
도 4는 도 3에서 제2 옹벽 블록이 설치될 지점을 절토한 구성을 도시한 단면도이다.
도 5는 도 4에서 제2 그라우트 강관을 삽입한 구성을 도시한 단면도이다.
도 6은 도 5에서 제2 옹벽 블록을 설치한 구성을 도시한 단면도이다.
도 7은 도 6에서 마감 블록을 설치한 구성을 도시한 단면도이다.
도 8은 제1 내지 제4 옹벽 블록을 설치한 시공예를 도시한 단면도이다.
The following drawings attached to this specification are illustrative of the preferred embodiments of the present invention, and together with the detailed description of the invention to serve to further understand the technical spirit of the present invention, the present invention is a matter described in such drawings It should not be construed as limited to.
1 is a flowchart illustrating a process of performing a top-down panel retaining wall construction method according to a preferred embodiment of the present invention.
2 is a cross-sectional view showing a configuration in which the first retaining wall block is cut and the first grout steel pipe is inserted.
3 is a cross-sectional view illustrating a configuration in which the first retaining wall block is provided in FIG. 2.
FIG. 4 is a cross-sectional view illustrating a structure in which the second retaining wall block is cut in FIG. 3.
5 is a cross-sectional view illustrating a configuration in which a second grout steel pipe is inserted in FIG. 4.
FIG. 6 is a cross-sectional view illustrating a structure in which a second retaining wall block is provided in FIG. 5.
7 is a cross-sectional view showing a configuration in which the finishing block is installed in FIG.
8 is a cross-sectional view showing a construction example in which the first to fourth retaining wall blocks are provided.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예를 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms or words used in the specification and claims should not be construed as having a conventional or dictionary meaning, and the inventors should properly explain the concept of terms in order to best explain their own invention. Based on the principle that can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention. Therefore, the embodiments described in the specification and the drawings shown in the drawings are only the most preferred embodiment of the present invention and do not represent all of the technical idea of the present invention, various modifications that can be replaced at the time of the present application It should be understood that there may be equivalents and variations.

도 1은 본 발명의 바람직한 실시예에 따른 탑다운이 가능한 패널식 옹벽 시공방법이 수행되는 과정을 도시한 흐름도이며, 도 2 내지 도 8은 절토 및 옹벽 블록의 설치 공정을 순차적으로 도시한 단면도이다.1 is a flowchart illustrating a process of performing a top-down panel retaining wall construction method according to a preferred embodiment of the present invention, Figures 2 to 8 are cross-sectional views sequentially showing the installation process of the cut and retaining wall block. .

도 1 내지 도 8을 참조하면, 본 발명의 바람직한 실시예에 따른 탑다운이 가능한 패널식 옹벽 시공방법은 제1 절토사면(2a)을 형성하는 제1 절토 공정 및 제1 옹벽 블록(30)의 마운트 공정과, 제1 절토사면(2a)의 하방에서 단차가 진 제2 절토사면(2b)을 형성하는 제2 절토 공정 및 제2 옹벽 블록(31)의 마운트 공정과, 제2 절토사면(2b)의 하방에서 단차가 진 제3 절토사면(2c)을 형성하는 제3 절토 공정 및 제3 옹벽 블록(32)의 마운트 공정을 포함한다. 또한, 이와 같이 하향으로 가면서 단차가 형성되도록 하방으로 가면서 굴착을 하고 각각의 절토사면에 옹벽 블록을 마운트하는 탑다운 방식의 시공은 제4 내지 제n 옹벽 블록에 대해서도 반복적으로 수행된다.1 to 8, a top-down panel retaining wall construction method according to a preferred embodiment of the present invention includes a first cutting process for forming a first cut slope 2a and a first retaining wall block 30. Mounting process, the 2nd cutting process of forming the 2nd cut slope 2b with a step below the 1st cut slope 2a, and the mounting process of the 2nd retaining wall block 31, and the 2nd cut slope 2b And a third cutting process for forming a third cut slope 2c having a step below, and a mounting process for the third retaining wall block 32. In addition, the construction of the top-down method of excavating downward and mounting the retaining wall blocks on the respective cut slopes is repeatedly performed for the fourth to n-th retaining wall blocks.

먼저, 도 1 및 도 2에 도시된 바와 같이 옹벽 설치 시작 지점에 제1 절토사면(2a)을 형성하는 제1 절토 공정을 수행한다(단계 S100). 제1 절토사면(2a)의 경사각은 그 위에 비스듬히 기울어지게 배치될 제1 옹벽 블록(30)의 배치 각도와 실질적으로 일치한다.First, as shown in FIG. 1 and FIG. 2, a first cutting process of forming a first cut slope 2a at the start point of installing the retaining wall is performed (step S100). The inclination angle of the first cut slope 2a substantially coincides with the placement angle of the first retaining wall block 30 to be inclined obliquely thereon.

제1 그라우트 강관(10)의 삽입 공정에서는 절토된 제1 절토사면(2a)의 지반(1)에 미리 천공홀을 형성한 후 지반을 보강하기 위한 보강재로서 제1 그라우트 강관(10)을 삽입한다(단계 S101). 제1 그라우트 강관(10)의 끝부분은 제1 옹벽 블록(30)을 관통하도록 정해진 길이만큼 제1 절토사면(2a)의 바깥으로 노출된다. 본 발명에서 상기 보강재는 그라우트 강관에 한정되지 않고 이형 철근이나 앵커 등 다양한 종류가 채용 가능하다. 이하에서는, 그라우트 강관을 이용해 지반을 보강하는 실시예를 중심으로 본 발명의 구성을 설명하기로 한다.In the insertion process of the first grout steel pipe 10, the first grout steel pipe 10 is inserted as a reinforcing material for reinforcing the ground after forming a drilling hole in the ground 1 of the first cut slope 2a. (Step S101). An end portion of the first grout steel pipe 10 is exposed to the outside of the first cut slope 2a by a length determined to penetrate the first retaining wall block 30. In the present invention, the reinforcing material is not limited to a grout steel pipe, and various kinds of reinforcing bars or anchors may be employed. Hereinafter, the configuration of the present invention will be described based on the embodiment of reinforcing the ground using a grout steel pipe.

다음, 절토된 제1 절토사면(2a)에 인접한 수평 바닥면(3a)에 정해진 길이(기초 블록의 전면에서 볼 때 가로방향 치수)와 폭(기초 블록의 전면에서 볼 때 세로방향 치수) 및 높이를 가진 제1 기초 블록(20)을 설치한다(단계 S102). 제1 기초 블록(20)은 제1 절토사면(2a)과 수평 바닥면(3a)이 만나는 지점에 접하도록, 또는 해당 지점과 소정의 간격을 두고 배치된다. 제1 기초 블록(20)은 소정의 핀에 의해 지반에 견고히 고정되는 것이 바람직하다.Next, the length (horizontal dimension viewed from the front of the foundation block) and the width (vertical dimension viewed from the front of the foundation block) and the height of the horizontal bottom surface 3a adjacent to the cut first cut surface 2a A first foundation block 20 having a structure is installed (step S102). The first foundation block 20 is disposed so as to contact a point where the first cut surface 2a and the horizontal bottom surface 3a meet or at a predetermined distance from the point. It is preferable that the first foundation block 20 is firmly fixed to the ground by a predetermined pin.

제1 옹벽 블록(30)은 도 3에 도시된 바와 같이 제1 기초 블록(20) 위에 세워져서 절토된 제1 절토사면(2a) 방향으로 비스듬히 기울어지게 배치되어 마운트된다(단계 S103). 제1 옹벽 블록(30)은 프리캐스트 패널로 이루어지되, 하단에 인접한 앞면에 제1 테이퍼부(A)가 형성되어 이후의 절토 공정 시 굴착의 용이성을 확보하는 것이 바람직하다. 제1 테이퍼부(A)는, 제1 옹벽 블록(30)의 하단 방향으로 가면서 점진적으로 옹벽 두께가 얇아지되 제1 옹벽 블록(30)의 전면에서 후방으로 비스듬히 경사진 표면을 갖도록 형성된다.As shown in FIG. 3, the first retaining wall block 30 is mounted on the first foundation block 20 so as to be inclined obliquely in the direction of the first cut slope 2a cut (step S103). Although the first retaining wall block 30 is made of a precast panel, it is preferable that the first taper portion A is formed on the front surface adjacent to the lower end to ensure ease of excavation during the subsequent cutting process. The first taper portion A is formed to have a surface gradually inclined backward from the front surface of the first retaining wall block 30 while gradually decreasing in thickness while going toward the lower end of the first retaining wall block 30.

제1 옹벽 블록(30)의 배치를 완료한 후에는 제1 옹벽 블록(30)의 외부로 노출된 제1 그라우트 강관(10)에 그라우트재를 주입하여 제1 옹벽 블록(30)을 제1 절토사면(2a)의 지반(1)에 견고히 고정한다(단계 S104). 그라우트재의 주입을 통한 제1 그라우트 강관(10)의 고정 공정은 제1 옹벽 블록(30)을 마운트하기 전에 실시되어도 무방하다.After the arrangement of the first retaining wall block 30 is completed, the grout material is injected into the first grout steel pipe 10 exposed to the outside of the first retaining wall block 30 to cut the first retaining wall block 30 first. It is firmly fixed to the ground 1 of the slope 2a (step S104). The fixing process of the first grout steel pipe 10 through the injection of grout material may be performed before mounting the first retaining wall block 30.

단계 S104 이후에는, 제1 옹벽 블록(30)의 배면과 제1 절토사면(2a) 사이의 간극에 뒤채움 그라우트나 콘크리트를 주입하여 제1 뒤채움부(40)를 형성한다(단계 S105). 대안으로는, 제1 옹벽 블록(30)의 배면과 제1 절토사면(2a) 사이의 간극에 토사나 자갈 등을 투입하는 공정도 수행할 수 있다.After step S104, a back filling grout or concrete is injected into the gap between the rear surface of the first retaining wall block 30 and the first cut slope 2a to form the first back filling portion 40 (step S105). Alternatively, a process of injecting soil, gravel or the like into the gap between the rear surface of the first retaining wall block 30 and the first cut surface 2a may be performed.

제1 옹벽 블록(30)의 상단에 인접한 배면에는 뒤채움 공정의 용이성을 확보하기 위해 제2 테이퍼부(B)가 형성되어 있다. 제2 테이퍼부(B)는, 제1 옹벽 블록(30)의 상단 방향으로 가면서 점진적으로 옹벽 두께가 얇아지되 제1 옹벽 블록(30)의 배면에 비스듬히 경사진 표면을 갖도록 형성된다. 제2 테이퍼부(B)에 의해, 제1 옹벽 블록(30)의 상단에 인접한 배면과 제1 절토사면(2a) 사이에는 실질적으로 상광하협 형상의 뒤채움용 주입구가 형성될 수 있다.The second taper portion B is formed on the rear surface adjacent to the upper end of the first retaining wall block 30 to ensure the ease of the backfilling process. The second taper portion B is formed such that the thickness of the retaining wall gradually decreases in the upper direction of the first retaining wall block 30, but has an obliquely inclined surface on the rear surface of the first retaining wall block 30. By the second taper B, a back filling injection hole having a substantially upper and lower narrowing shape may be formed between the rear surface adjacent to the upper end of the first retaining wall block 30 and the first cut surface 2a.

상기 뒤채움용 주입구를 통해 뒤채움재를 주입하여 뒤채움 공정을 완료한 후에는 제2 테이퍼부(B)와 제1 절토사면(2a) 사이에 제1 마감 블록(50)을 끼워 넣어 마감 작업을 한다(단계 S106).After completing the backfilling process by injecting the backfilling material through the backfilling inlet, the finishing work is completed by inserting the first finishing block 50 between the second taper portion B and the first cut surface 2a. (Step S106).

도 4에 도시된 바와 같이 제1 기초 블록(20)의 폭방향 외곽 바닥면(도 3의 3a 참조)으로부터 하방으로 굴착 작업을 실시하여 제2 옹벽 블록(31)이 설치될 지점에 제2 절토사면(2b)을 형성하는 제2 절토 공정을 수행한다(단계 S107). 따라서, 제2 절토사면(2b)은 제1 절토사면(2a)으로부터 적어도 제1 기초 블록(20)의 세로방향 폭(도 4의 d) 만큼 이격되게 단차가 진 구조로 형성된다. 제2 절토사면(2b)의 경사각은 그 위에 비스듬히 기울어지게 배치될 제2 옹벽 블록(31)의 배치 각도와 실질적으로 일치한다. 이와 같이 상하 방향으로 인접한 서로 다른 절토사면이 수평 방향으로 적어도 d 만큼 이격된 구조는 탑다운 방식의 옹벽 시공을 가능하게 하며, 옹벽 구조물의 표면을 계단형이 되도록 하여 시각적 안정감과 유려한 경관을 제공한다.As shown in FIG. 4, the second cut is performed at the point where the second retaining wall block 31 is to be installed by carrying out excavation work downward from the widthwise outer bottom surface (see 3a of FIG. 3) of the first foundation block 20. A second cut process for forming the slope 2b is performed (step S107). Accordingly, the second cut slope 2b is formed in a stepped structure spaced apart from the first cut slope 2a by at least the longitudinal width (d of FIG. 4) of the first foundation block 20. The inclination angle of the second cut slope 2b substantially coincides with the placement angle of the second retaining wall block 31 to be inclined obliquely thereon. The structure in which different cut slopes adjacent to each other in the vertical direction are spaced apart by at least d in the horizontal direction enables top-down retaining wall construction, and the surface of the retaining wall structure becomes stepped to provide visual stability and a beautiful view. do.

이어서, 도 5에 도시된 바와 같이 제2 그라우트 강관(11)의 삽입 공정을 진행하여 절토된 제2 절토사면(2b)의 지반(1)에 천공홀을 형성한 후 제2 그라우트 강관(11)을 삽입한다(단계 S108). 제2 그라우트 강관(11)의 끝부분은 제1 옹벽 블록(30)을 관통하도록 정해진 길이만큼 제2 절토사면(2b)의 바깥으로 노출된다.Subsequently, as shown in FIG. 5, after the insertion process of the second grout steel pipe 11 is performed, a perforation hole is formed in the ground 1 of the cut second cut slope 2b, and then the second grout steel pipe 11 is formed. Is inserted (step S108). An end portion of the second grout steel pipe 11 is exposed to the outside of the second cut slope 2b by a length determined to penetrate the first retaining wall block 30.

절토된 제2 절토사면(2b)에 인접한 수평 바닥면(3b)에는 제2 기초 블록(21)을 설치한다(단계 S109). 제2 기초 블록(21)은 제2 절토사면(2b)과 수평 바닥면(3b)이 만나는 지점에 접하도록, 또는 해당 지점으로부터 소정 간격을 두고 배치된다. 제2 기초 블록(21)은 소정의 핀에 의해 지반에 견고히 고정되는 것이 바람직하다.The second foundation block 21 is installed on the horizontal bottom 3b adjacent to the cut second cut slope 2b (step S109). The second foundation block 21 is disposed so as to contact a point where the second cut slope 2b and the horizontal bottom surface 3b meet or at a predetermined distance from the point. It is preferable that the second foundation block 21 is firmly fixed to the ground by a predetermined pin.

제2 옹벽 블록(31)은 도 6에 도시된 바와 같이 제2 기초 블록(21) 위에 세워져서 절토된 제2 절토사면(2b) 방향으로 비스듬히 기울어지게 배치되어 마운트된다(단계 S110). 제2 옹벽 블록(31)은, 제1 옹벽 블록(30)과 동일하게 프리캐스트 패널로 이루어지되 하단에 인접한 앞면에 제1 테이퍼부(A)가 형성되어 절토 공정 시 굴착의 용이성을 확보하는 것이 바람직하다. 제1 테이퍼부(A)는, 제2 옹벽 블록(31)의 하단으로 방향으로 가면서 점진적으로 옹벽 두께가 얇아지되 제2 옹벽 블록(31)의 전면에서 후방으로 비스듬히 경사진 표면을 갖도록 형성된다.As shown in FIG. 6, the second retaining wall block 31 is mounted on the second foundation block 21 so as to be inclined obliquely in the direction of the second cut slope 2b cut (step S110). The second retaining wall block 31 is made of a precast panel in the same manner as the first retaining wall block 30, but the first tapered portion A is formed on the front surface adjacent to the lower end to ensure easy excavation during the cutting process. desirable. The first taper portion A is formed such that the thickness of the retaining wall gradually decreases in the direction toward the lower end of the second retaining wall block 31, but has an inclined surface obliquely rearward from the front surface of the second retaining wall block 31.

제2 옹벽 블록(31)의 배치를 완료한 후에는 제2 옹벽 블록(31)의 외부로 노출된 제2 그라우트 강관(11)에 그라우트재를 주입하여 제2 옹벽 블록(31)을 제2 절토사면(2b)의 지반(1)에 견고히 고정한다(단계 S111). 그라우트재의 주입을 통한 제2 그라우트 강관(11)의 고정 공정은 제2 옹벽 블록(31)을 마운트하기 전에 실시되어도 무방하다.After the arrangement of the second retaining wall block 31 is completed, the grout material is injected into the second grout steel pipe 11 exposed to the outside of the second retaining wall block 31 to cut the second retaining wall block 31 into the second cut. It is firmly fixed to the ground 1 of the slope 2b (step S111). The fixing process of the second grout steel pipe 11 through the injection of grout material may be performed before mounting the second retaining wall block 31.

제2 옹벽 블록(31)의 배면과 제2 절토사면(2b) 사이의 간극에는 뒤채움 그라우트나 콘크리트를 주입하여 제2 뒤채움부(41)를 형성한다(단계 S112). 대안으로는, 제2 옹벽 블록(31)의 배면과 제2 절토사면(2b) 사이의 간극에 토사나 자갈 등을 투입하는 공정도 수행할 수 있다.A back filling grout or concrete is injected into the gap between the back surface of the second retaining wall block 31 and the second cut slope 2b to form a second back filling portion 41 (step S112). Alternatively, a process of injecting soil, gravel, or the like into the gap between the rear surface of the second retaining wall block 31 and the second cut slope 2b may be performed.

제2 옹벽 블록(31)의 상단에 인접한 배면에는 뒤채움 공정의 용이성을 확보하기 위해 제2 테이퍼부(B)가 형성되어 있다. 제2 테이퍼부(B)는, 제2 옹벽 블록(31)의 상단으로 방향으로 가면서 점진적으로 옹벽 두께가 얇아지되 제2 옹벽 블록(31)의 배면에 비스듬히 경사진 표면을 갖도록 형성된다. 제2 테이퍼부(B)에 의해, 제2 옹벽 블록(31)의 배면과 제1 기초 블록(20) 사이에는 실질적으로 상광하협 형상의 뒤채움용 주입구가 형성될 수 있다. 뒤채움 공정은 상기 뒤채움용 주입구까지 뒤채움재로 완전히 채울 때까지 수행되는 것이 바람직하다. 이때, 제2 테이퍼의 상방에 위치한 제1 옹벽 블록(30)의 제1 테이퍼부(A)는 상기 뒤채움용 주입구로 뒤채움재를 유도하기 위한 가이드 역할도 할 수 있다.A second taper portion B is formed on the back surface adjacent to the upper end of the second retaining wall block 31 to ensure the ease of the backfilling process. The second taper portion B is formed such that the thickness of the retaining wall gradually decreases in the direction toward the upper end of the second retaining wall block 31, but has an obliquely inclined surface on the rear surface of the second retaining wall block 31. By the second taper portion B, a backfilling inlet having a substantially upper and lower narrow shape may be formed between the rear surface of the second retaining wall block 31 and the first foundation block 20. The back filling process is preferably performed until the back filling inlet is completely filled with a back filling material. In this case, the first taper portion A of the first retaining wall block 30 positioned above the second taper may also serve as a guide for inducing a backfill material into the backfill inlet.

제2 뒤채움부를 형성한 후에는 도 7에 도시된 바와 같이 제1 옹벽 블록(30)의 제1 테이퍼부(A)와 제2 옹벽 블록(31)의 상단면 사이에 끼워지도록 제2 마감 블록(60)을 설치하여 마감 작업을 한다(단계 S113).After forming the second backfill portion, as shown in FIG. 7, the second finishing block is fitted between the first tapered portion A of the first retaining wall block 30 and the top surface of the second retaining wall block 31. Install 60 to finish the work (step S113).

계속해서, 제3 옹벽 블록(32) 내지 제n 옹벽 블록에 대해서도 이전의 절토 및 마운팅 공정과 실질적으로 동일한 일련의 공정을 하방으로 가면서 반복하여 n개의 옹벽 블록을 계단형으로 시공한다.Subsequently, for the third retaining wall block 32 to the n-th retaining wall block, a series of steps substantially the same as those of the previous cutting and mounting steps are performed downward, and the n retaining wall blocks are stepped.

도 8에는 지반(1)의 표면 상부로부터 하부로 가면서 절토 및 마운팅 공정을 반복적으로 수행하여 제1 옹벽 블록(30), 제2 옹벽 블록(31), 제3 옹벽 블록(32) 및 제4 옹벽 블록(33)이 계단형으로 시공된 옹벽 구조물이 도시되어 있다. 이러한 옹벽 구조물은 제1 내지 제4 옹벽 블록(30,31,32,33)의 하부에 제1 내지 제4 기초 블록(20,21,22,23)이 일대일 대응되게 배치되어 있고, 제1 내지 제4 옹벽 블록(30,31,32,33)은 제1 내지 제4 기초 블록(20,21,22,23)의 세로폭(d) 만큼 인접 블록들이 서로 수평 방향으로 이격되어 전체적으로 계단형으로 시공된다.In FIG. 8, the first retaining wall block 30, the second retaining wall block 31, the third retaining wall block 32, and the fourth retaining wall are repeatedly formed by repeatedly cutting and mounting processes from the upper surface to the lower surface of the ground 1. A retaining wall structure is shown in which block 33 is constructed stepwise. In such a retaining wall structure, the first to fourth foundation blocks 20, 21, 22, and 23 are disposed in a one-to-one correspondence below the first to fourth retaining wall blocks 30, 31, 32, and 33. The fourth retaining wall blocks 30, 31, 32, and 33 have a stepped shape in which the adjacent blocks are spaced apart from each other in the horizontal direction by the vertical width d of the first to fourth foundation blocks 20, 21, 22, and 23. It is constructed.

또한, 옹벽 구조물은 제1 내지 제4 옹벽 블록(30,31,32,33)의 배면과 제1 내지 제4 절토사면(2a,2b,2c,2d) 사이에 채워진 제1 내지 제4 뒤채움부(40,41,42,43)를 구비한다.In addition, the retaining wall structure has a first to fourth backfill filled between the rear surfaces of the first to fourth retaining wall blocks 30, 31, 32, and 33 and the first to fourth cut slopes 2a, 2b, 2c, and 2d. The parts 40, 41, 42, and 43 are provided.

상술한 바와 같이 본 발명에 따른 탑다운이 가능한 패널식 옹벽 시공방법은 옹벽 블록의 설치를 위한 절토 및 마운팅 공정을 지반(1)의 상부로부터 하부로 가면서 계단형으로 진행하는 탑다운 공정을 구현함으로써 시각적, 구조적으로 안정성을 확보할 수 있으며 각 옹벽 블록별로 하중을 분산시킬 수 있다.As described above, the top-down panel retaining wall construction method according to the present invention implements a top-down process of cutting and mounting processes for installing the retaining wall block from the top of the ground 1 to the bottom, while proceeding stepwise. Stability can be secured visually and structurally, and the load can be distributed for each retaining wall block.

또한, 기설치된 옹벽 블록의 하단에 형성된 제1 테이퍼부(A)를 이용해 작업공간을 확보하여 다음번 옹벽 블록이 설치될 지점에 대한 굴착이 이루어지므로 작업효율을 높일 수 있고, 뒤채움 공정에서는 옹벽 블록의 상단에 형성된 제2 테이퍼부(B)에 의해 형성된 상광하협 형상의 주입구를 이용해 뒤채움재를 쉽게 주입할 수 있는 장점이 있다.In addition, the work space is secured by using the first tapered portion A formed at the bottom of the retaining wall block, which is installed at the bottom of the retaining wall block, so that excavation is performed at the point where the next retaining wall block is to be installed. There is an advantage that can easily inject the back-filling material by using the inlet of the upper and lower narrow shape formed by the second tapered portion (B) formed on the top.

이상에서 본 발명은 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 발명은 이것에 의해 한정되지 않으며 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 의해 본 발명의 기술사상과 아래에 기재될 특허청구범위의 균등범위 내에서 다양한 수정 및 변형이 가능함은 물론이다.Although the present invention has been described above by means of limited embodiments and drawings, the present invention is not limited thereto and will be described below by the person skilled in the art to which the present invention pertains. Of course, various modifications and variations are possible within the scope of the claims.

A: 제1 테이퍼부 B: 제2 테이퍼부
1: 지반 2a: 제1 절토사면
2b: 제2 절토사면 2c: 제3 절토사면
2d: 제4 절토사면 3a,3b: 바닥면
10: 제1 그라우트 강관 11: 제2 그라우트 강관
12: 제3 그라우트 강관 13: 제4 그라우트 강관
20: 제1 기초 블록 21: 제2 기초 블록
22: 제3 기초 블록 23: 제4 기초 블록
30: 제1 옹벽 블록 31: 제2 옹벽 블록
32: 제3 옹벽 블록 33: 제4 옹벽 블록
40: 제1 채움부 41: 제2 채움부
42: 제3 채움부 43: 제4 채움부
50: 제1 마감블록 60,61,62: 제2 마감블록
A: 1st taper part B: 2nd taper part
1: Soil 2a: First Cut Slope
2b: second cut slope 2c: third cut slope
2d: fourth cut slope 3a, 3b: bottom surface
10: first grout steel pipe 11: second grout steel pipe
12: third grout steel pipe 13: fourth grout steel pipe
20: first basic block 21: second basic block
22: third basic block 23: fourth basic block
30: first retaining wall block 31: second retaining wall block
32: third retaining wall block 33: fourth retaining wall block
40: first filling portion 41: second filling portion
42: third filler 43: fourth filler
50: first finishing block 60, 61, 62: second finishing block

Claims (6)

(a) 제1 옹벽 블록이 설치될 지점을 절토하는 단계;
(b) 절토된 사면에 인접한 바닥에 정해진 폭을 가진 제1 기초 블록을 설치하는 단계;
(c) 상기 제1 기초 블록 위에 제1 옹벽 블록을 상기 절토된 사면 방향으로 비스듬히 기울어지게 배치하는 단계;
(d) 상기 제1 옹벽 블록을 상기 절토된 사면의 지반에 고정하는 단계;
(e) 상기 제1 기초 블록의 폭방향 외곽 바닥면을 굴착하여 제2 옹벽 블록이 설치될 지점을 절토하는 단계;
(f) 절토된 사면에 인접한 바닥에 정해진 폭을 가진 제2 기초 블록을 설치하는 단계;
(g) 상기 제2 기초 블록 위에 제2 옹벽 블록을 상기 절토된 사면 방향으로 비스듬히 기울어지게 배치하는 단계;
(h) 상기 제2 옹벽 블록을 상기 절토된 사면의 지반에 고정하는 단계;
(i) 상기 제2 기초 블록의 폭방향 외곽 바닥면을 굴착하여 제3 옹벽 블록이 설치될 지점을 절토하는 단계; 및
(j) 제3 옹벽 블록 내지 제n 옹벽 블록에 대해서도 상기 (f) 내지 (i) 단계와 실질적으로 동일한 공정을 하방으로 가면서 반복하여 n개의 옹벽 블록을 계단형으로 시공하는 일련의 공정을 포함하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법.
(a) cutting the point where the first retaining wall block is to be installed;
(b) installing a first foundation block having a predetermined width at a floor adjacent to the cut slope;
(c) arranging a first retaining wall block at an angle to said cut slope obliquely over said first foundation block;
(d) fixing the first retaining wall block to the ground of the cut slope;
(e) cutting the point at which the second retaining wall block is to be installed by excavating a widthwise outer bottom surface of the first foundation block;
(f) installing a second foundation block having a predetermined width at a floor adjacent to the cut slope;
(g) arranging a second retaining wall block at an angle to said cut slope obliquely over said second foundation block;
(h) securing the second retaining wall block to the ground of the cut slope;
(i) cutting the point where the third retaining wall block is to be installed by excavating a widthwise outer bottom surface of the second foundation block; And
(j) including a series of steps for constructing the n retaining wall blocks stepwise by repeating the steps substantially the same as the above steps (f) to (i) for the third retaining wall block to the nth retaining wall block. Panel-type retaining wall construction method capable of top-down, characterized in that.
제1항에 있어서,
상기 제1 옹벽 블록 내지 제n 옹벽 블록은 하단에 인접한 전면에 옹벽 블록의 전면으로부터 배면을 향해 경사진 제1 테이퍼부를 구비하고,
제2 내지 제n 옹벽 블록이 설치될 지점을 절토할 때 상기 제1 테이퍼부의 경사면을 이용하여 절토를 진행함으로써 굴착의 용이성을 확보하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법.
The method of claim 1,
The first retaining wall block to the n-th retaining wall block have a first tapered portion inclined from the front surface of the retaining wall block to the rear surface at a front surface adjacent to a lower end thereof,
When cutting the point where the second to n-th retaining wall block is to be installed, the top-down panel retaining wall construction method, characterized in that the ease of excavation by securing the cutting using the inclined surface of the first tapered portion.
제2항에 있어서,
상기 굴착 및 옹벽 블록 고정이 완료된 후에 상기 제1 테이퍼부의 경사면에 마감 블록을 설치하는 공정을 더 포함하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법.
The method of claim 2,
And a step of installing the finishing block on the inclined surface of the first tapered part after the excavation and retaining wall block fixing is completed.
제3항에 있어서,
상기 제1 옹벽 블록 내지 제n 옹벽 블록의 상단에 인접한 배면에는 옹벽 블록의 배면으로부터 전면을 향해 경사진 제2 테이퍼부가 형성되어 있고,
상기 제1 옹벽 블록의 제2 테이퍼부와 상기 절토된 사면 사이에 마감 블록을 설치하는 공정을 더 포함하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법.
The method of claim 3,
On the rear surface adjacent to the upper end of the first retaining wall block to the n-th retaining wall block, a second taper portion inclined toward the front surface from the rear surface of the retaining wall block is formed,
And a step of installing a finishing block between the second tapered portion of the first retaining wall block and the cut slopes.
제1항에 있어서,
옹벽 블록이 설치될 지점을 절토하여 사면을 형성한 후 옹벽 블록을 절토된 사면에 배치하기 전에 상기 절토된 사면의 지반에 보강재를 삽입하여 지반을 보강하고, 상기 보강재의 노출 부위를 옹벽 블록에 형성된 홀에 삽입하여 옹벽 블록을 상기 절토된 사면에 배치하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법.
The method of claim 1,
After forming the slope by cutting the point where the retaining wall block is to be installed, reinforcing the ground by inserting a reinforcement into the ground of the cut slope before placing the retaining wall block on the cut slope, and the exposed portion of the reinforcement is formed on the retaining wall block. A panel-type retaining wall construction method capable of top-down, wherein the retaining wall block is inserted into a hole and disposed on the cut slope.
제1항에 있어서,
각 옹벽 블록을 절토된 사면에 배치한 후 상기 옹벽 블록과 상기 절토된 사면 사이의 공간을 토사 및/또는 뒤채움재로 채워서 뒤채움하는 공정을 더 포함하는 것을 특징으로 하는 탑다운이 가능한 패널식 옹벽 시공방법.
The method of claim 1,
And placing each retaining wall block on the cut slope, and then filling the space between the retaining wall block and the cut slope with earth and / or backfill to further backfill the panel retaining wall. Construction method.
KR1020180016557A 2018-02-09 2018-02-09 Methods for top-down constructing panel type retaining wall structure KR102132470B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180016557A KR102132470B1 (en) 2018-02-09 2018-02-09 Methods for top-down constructing panel type retaining wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180016557A KR102132470B1 (en) 2018-02-09 2018-02-09 Methods for top-down constructing panel type retaining wall structure

Publications (2)

Publication Number Publication Date
KR20190096751A true KR20190096751A (en) 2019-08-20
KR102132470B1 KR102132470B1 (en) 2020-07-09

Family

ID=67807685

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180016557A KR102132470B1 (en) 2018-02-09 2018-02-09 Methods for top-down constructing panel type retaining wall structure

Country Status (1)

Country Link
KR (1) KR102132470B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102478730B1 (en) * 2022-04-08 2022-12-21 한주이엔씨 주식회사 Inspection passage structure for retaining wall

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100651607B1 (en) * 2006-04-24 2006-11-30 (주)브니엘컨설턴트 Post-tension soil nailing apparatus and the assembling soil nailing method using the stiff facing plate
KR20100087858A (en) * 2009-01-29 2010-08-06 심석래 Retaining wall using anchor and concrete panel and its construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100651607B1 (en) * 2006-04-24 2006-11-30 (주)브니엘컨설턴트 Post-tension soil nailing apparatus and the assembling soil nailing method using the stiff facing plate
KR20100087858A (en) * 2009-01-29 2010-08-06 심석래 Retaining wall using anchor and concrete panel and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102478730B1 (en) * 2022-04-08 2022-12-21 한주이엔씨 주식회사 Inspection passage structure for retaining wall

Also Published As

Publication number Publication date
KR102132470B1 (en) 2020-07-09

Similar Documents

Publication Publication Date Title
KR101641293B1 (en) Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall
KR102218604B1 (en) Earth retaining construction method for using pile and inclined ground anchor
KR101568956B1 (en) Excavation method for sluice on soft ground using front h-pile with multi-wire
CN106522236A (en) Structure for shoring of foundation trench and construction method
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR101793037B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR20070002328A (en) Construction method of pipe roof structures
KR20200011068A (en) Butress type Self-reliance retaining wall construction method having arching earth pressure by the silo earth pressure
JP6934151B2 (en) Construction method of civil engineering structure, and civil engineering construction block and fixing member used in the construction method.
JP2000352296A (en) Method o constructing passage just under underground structure
KR102132470B1 (en) Methods for top-down constructing panel type retaining wall structure
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
KR102476068B1 (en) Retaining wall structure with multidirectional anchor fixtures and construction method thereof
KR20040031451A (en) Prestressed scaffolding method
KR100974513B1 (en) Caisson type pile method
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
KR100793510B1 (en) Tension soil nail and construction method of underground wall using the same
KR101744378B1 (en) Method for Constructing Retaining Wall
JP5830068B2 (en) Slope reinforcement method
KR100401330B1 (en) A method of construction for earth-protection walls of building
JP6307145B1 (en) Open shield method and concrete box used for it
KR200308716Y1 (en) Prestressed scaffolding method
KR100479500B1 (en) The slope tree-planting structure using socket type steel pipe, and his construction method
KR102654389B1 (en) Soil retaning structure for two rows pile using longitudinal prestress

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right