KR20160130130A - the hybrid joint construction between column and beam, the hybrid joint construction between girder and beam - Google Patents
the hybrid joint construction between column and beam, the hybrid joint construction between girder and beam Download PDFInfo
- Publication number
- KR20160130130A KR20160130130A KR1020150078696A KR20150078696A KR20160130130A KR 20160130130 A KR20160130130 A KR 20160130130A KR 1020150078696 A KR1020150078696 A KR 1020150078696A KR 20150078696 A KR20150078696 A KR 20150078696A KR 20160130130 A KR20160130130 A KR 20160130130A
- Authority
- KR
- South Korea
- Prior art keywords
- column
- plate
- coupled
- girder
- steel
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/19—Three-dimensional framework structures
- E04B1/1903—Connecting nodes specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
Abstract
Description
BACKGROUND OF THE
For a steel-reinforced hybrid PC with a pillar steel frame and a general PC without a pillar steel frame,
When constructing the connecting portion between the column and the beam, conventionally
The following two methods are mainly used.
(1) It is a wet laying method of joining part where the general PC beam and column are installed and then the joint part is poured into concrete. This requires a lot of preparatory processes for casting the concrete such as formwork in the joint, and it can cause serious safety problems by exposing the reinforced concrete until the concrete is cured. In fact, there have been instances where the collapse of a joint has led to a loss of life.
(2) Simply place the PC beam member on a pedestal such as a cobell placed on a column. In this method, it is possible to reduce the construction period to some extent. However, since a separate lateral load resistance system must be provided to support the lateral load such as an earthquake, additional processing is required and the construction cost and construction period are increased again. In addition, since the both ends of the frame are simply joined, a large amount of structural reinforcement is required in the center of the beam where the moment is applied to support the vertical load.
However, the present invention can provide the following advantages by providing a structure detailing a column and a beam plate and connecting them with a bolt.
(1) In the present invention, a plate joint joined with a bolt to a column and a beam is configured to effectively support tension and compression forces due to moments. Therefore, it is possible to convert the conventional simple joint into moment joint, and it is not necessary to reinforce the structure required in the center of the beam where the additional transverse resistance system or the longitudinal moment, which is required in the conventional PC joint, is required. In the present invention, since the beam ends are rigidly connected, the load can be supported even at the beam ends, and thus the structure reinforcement at the center of the beam where the longitudinal vibration acts can be drastically reduced.
(2) In addition, this joint is dry connection using mechanical connection method, and it is possible to improve not only the air saving but also the safety at the construction site since the water such as water is not used at the time of joining part construction . Especially, it is possible to realize the simplification and standardization of the process as well as the reduction of the construction cost by making the form and the wet concrete unnecessary which are essential elements of the concrete pouring. Design standardization will organically link the entire design process and the construction process, enabling a systematic construction plan, which will contribute significantly to air reduction and cost reduction.
(3) The joining part of the present invention is a dry joining method composed of a plate and a bolt, so that not only the structure but also the disassembly can be easily performed, and the concept of DFD (Design For Dismantle) can be realized. It is not a dismantling of lifesaving structures by explosives, but it provides a breakthrough technology that can be easily disassembled and reassembled in other areas as needed. This makes it possible to realize an economical, sustainable construction method that is easy to construct and dismantle. It is a breakthrough method that can meet the global environmental conservation policy.
SUMMARY OF THE INVENTION The present invention has been made in order to solve the above-mentioned problems of the related art. The object of the present invention is to provide a steel-reinforced hybrid PC including a pillar steel frame and a general PC not including a pillar steel frame,
It is possible to use a double-sided nut and double-sided nut-filled reinforced bar to move away from the conventional method of using a conventional site-to-site connection and a beam-column simple installation method. And a hybrid structure of a girder and a beam.
According to an aspect of the present invention, there is provided a column structure, including: a column having a column steel frame selectively inserted therein and having a column plate coupled to an outer surface of the column column; And
A
, ≪ / RTI >
A
Since the
And the
In addition, a large
A small beam of
, ≪ / RTI >
A
Since the
And the
According to the present invention, in a steel-reinforced hybrid PC including a pillar steel frame and a general PC not including a pillar steel frame,
It is possible to use a double-sided nut and double-sided nut-filled reinforced bar to move away from the conventional method of using a conventional site-to-site connection and a beam-column simple installation method. Structure and a hybrid bonding structure of a girder and a beam.
1 is a sectional view of a hybrid bonding structure of a column plate and a column of the present invention.
Fig. 2 is a photograph of a construction view of a hybrid bonding structure of a column plate and a column of the present invention.
FIGS. 3 and 4 are photographs of a test of the bonding state of the double-sided nuts in the hybrid bonding structure of the column plate and the column of the present invention.
5 to 13 show various embodiments of the hybrid bonding structure of the column plate and the column of the present invention.
Figs. 14 to 16 show an embodiment of the hybrid bonding structure of a column and a beam of the present invention in order.
17 shows another embodiment of the hybrid bonding structure of the column and the beam according to the present invention.
Figs. 18 to 20 show another embodiment of the hybrid bonding structure of the column and the beam of the present invention in order.
Fig. 21 shows another embodiment of the hybrid bonding structure of a column and a beam according to the present invention.
22 to 24 illustrate another embodiment of the hybrid bonding structure of the column and the beam of the present invention in order.
25 and 26 show another embodiment of the hybrid bonding structure of the column and the beam of the present invention.
Figs. 27 to 29 show an embodiment of the hybrid bonding structure of the girder and the beam of the present invention in order.
Figs. 30 to 31 show an embodiment of a hybrid steel-joint structure of columns and beams according to the present invention in order.
32 to 42 illustrate another embodiment of the hybrid steel-joint structure of a column and a beam according to the present invention.
Figs. 43 to 53 show an embodiment in which a base template for transporting and constructing a skeleton unit according to the present invention is used.
Figs. 54 to 70 show an embodiment of a method of constructing the hybrid PC structure of the present invention in order.
Figs. 71 to 80 show an embodiment of a method of constructing the hybrid steel frame joint structure of the present invention in order.
81 to 97 show an embodiment of a method of constructing a steel-concrete hybrid PC structure according to the present invention in order.
98 is a cross-sectional view and an enlarged view of another embodiment of the hybrid bonding structure of the column and the beam of the present invention.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
Ⅰ. Hybrid Joining Structure of Column Plate and Column
FIG. 1 is a sectional view of a hybrid bonding structure of a column plate and a column of the present invention, and FIG. 2 is a photograph of a construction view of a hybrid bonding structure of a column plate and a column of the present invention.
FIGS. 3 and 4 are photographs of a test of a double-sided nut in a hybrid bonding structure of a column plate and a column according to the present invention, and FIGS. 5 to 13 show the hybrid bonding structure of a column plate and a column Fig.
A hybrid structure of a column plate and a column according to the present invention includes: a column (100) in which a column steel frame is selectively contained and a column plate (110) is coupled to an outer surface of the column concrete; And
A
, ≪ / RTI >
Side nut (BFN) having a female screw thread formed therein is welded (WD) to the rear surface of a plurality of bolt holes of the
The double-sided nut BFN and the double-sided nut-filled reinforcing
Hereinafter, the
6, 9 (b), 10 (b), and 11,
When the
The double-sided nut-filled reinforcing
As shown in Figs. 6, 9 (a), 10 (b), and 11,
When the
The double-sided nut-embedded reinforcing
As shown in Figs. 6 (b) and 8,
When the
The double-sided nut embedded
In the photographs of the test specimens of the double-sided nut-embedded reinforcing
Ⅱ. Pillars and beams hybrid Junction structure
Figs. 14 to 16 show an embodiment of the hybrid bonding structure of a column and a beam of the present invention in order.
A hybrid structure of a column and a beam according to the present invention includes a column (100) in which a column steel frame is selectively included and a column plate (110) is coupled to an outer surface of the column concrete; And
A
, ≪ / RTI >
A
Since the
And the
17 shows another embodiment of the hybrid bonding structure of the column and the beam according to the present invention.
17, the lower end of the
Although not shown, the lower end of the
And the lower end of the
17,
The present invention is characterized in that a guide plate GP is installed at both ends of the
Figs. 18 to 20 show another embodiment of the hybrid bonding structure of the column and the beam of the present invention in order.
As shown in Figs. 18 to 20,
A column (100) in which a column steel frame is selectively contained inside and a column plate (110) is coupled to an outer surface of the column concrete; And
A
, ≪ / RTI >
A
Since the
And the
Fig. 21 shows another embodiment of the hybrid bonding structure of a column and a beam according to the present invention.
21, the other end of the
Although not shown, the other side end of the
The other end of the
Also, as shown in Fig. 21,
The present invention is characterized in that a guide plate GP is installed at the upper and lower ends of the
22 to 24 illustrate another embodiment of the hybrid bonding structure of the column and the beam of the present invention in order.
As shown in Figures 22 to 24,
A column (100) in which a column steel frame is selectively contained inside and a column plate (110) is coupled to an outer surface of the column concrete; And
A
, ≪ / RTI >
A setting bolt SB is installed to protrude below the
A setting hole (SH) is formed under the beam plate (210)
Since the
And the
25 and 26 show another embodiment of the hybrid bonding structure of the column and the beam of the present invention.
As shown in Figures 25 and 26,
When two or
A plurality of bolts coupled to each of the two or
98 is a cross-sectional view and an enlarged view of another embodiment of the hybrid bonding structure of the column and the beam of the present invention.
98,
In the present invention, the nut plate (210) is provided with a nut hole, and the nut (N) is installed at the other end so as to protrude at one end,
Since the thickness of the
The amount of steel material of the
More specifically,
One end or end of the nut N is designed to be caught in the
Since the other end of the nut N is required to support the front end of the nut N about 7 mm in thickness, the required amount of steel material of the
And although not shown,
In the present invention, the
The
Ⅲ. Girder Beam hybrid Junction structure
Figs. 27 to 29 show an embodiment of the hybrid bonding structure of the girder and the beam of the present invention in order.
As shown in Figures 27 to 29,
The hybrid structure of the girder and the beam according to the present invention includes a
A small beam of
, ≪ / RTI >
A
Since the
And the
And although not shown,
In the present invention, the lower end of the
The lower end of the
The lower end of the
Also, although not shown,
The present invention relates to a large girder girder (300) in which a girder frame is optionally contained and a girder plate (310) is coupled to the outer surface of the girder concrete; And
A small beam of
, ≪ / RTI >
A setting bolt (not shown) protrudes from the bottom of the
A setting hole (not shown) is formed below the
Since the
Characterized in that the beam (400) is self-leveling and coupled to the correct position of the girder (300) by its own weight,
A guide plate GP is installed at both ends of the
IV. Pillars and beams hybrid Steel joint structure
Figs. 30 to 31 show an embodiment of a hybrid steel-joint structure of columns and beams according to the present invention in order.
As shown in Figs. 30 to 31,
The present invention relates to a steel column 100 'having a column flange 100'-1 and a column web 100'-2;
A steel beam 200 'to which the
, ≪ / RTI >
A setting bolt SB is installed to protrude from the column flange 100'-1,
A setting hole (SH) is formed under the beam plate (210)
After the steel frame 200 'is lowered by its own weight and the setting hole SH is set on the setting bolt SB, the column flange 100'-1 and the
And the steel beam 200 'is self-leveled and coupled to the exact position of the steel column 100' by its own weight.
32 to 42 illustrate another embodiment of the hybrid steel-joint structure of a column and a beam according to the present invention.
32,
A guide plate GP is installed at both ends of the column flange 100-1 so as to guide the
The lower end of the
The setting bolt SB and the setting hole SH may be omitted.
33,
The present invention is characterized in that a
A setting bolt SB is installed to protrude below the
The steel frame 200 'is coupled to the
Since the
And the steel beam 200 'is self-leveled and coupled to the exact position of the steel column 100' by its own weight.
The lower end of the
The setting bolt SB and the setting hole SH may be omitted.
33 (a) and 33 (c)
A nut (N) is fastened to the rear surface of the column plate (110) to fasten the bolt to the nut (N)
33 (b) and 33 (d)
The bolts B may be fastened to the rear surface of the
34 (a) and Fig. 35,
The present invention relates to a steel column 100 'having a column flange 100'-1 and a column web 100'-2;
A
, ≪ / RTI >
A setting bolt SB is installed to protrude from the column flange 100'-1,
A setting hole (SH) is formed under the bracket plate (520)
The
And the
The setting bolt SB and the setting hole SB may be omitted.
The present invention is characterized in that a guide plate GP is installed at both ends of the
34 (b), a
Although not shown, a setting bolt SB is installed to protrude below the
The
Since the
And the
As shown in Figures 36, 37, 39 and 40,
In the present invention, one end of a steel beam 200 'is coupled to the other end of the
A
The connecting
A fixing
The other end of the
And are corresponding to each other,
Is lowered without being caught by the other end of the column bracket (500) when one end of the steel beam (200 ') is lowered by its own weight.
36 and 37,
The other end of the
39,
The other end of the
40,
The shape of the other end of the
As shown in Fig. 38 (b)
And one end of the
41 and 42,
In the present invention, an
The upper end of the
When the other steel column 100 'descends from the upper part,
Is self-leveling and is coupled to an accurate center line with the steel column 100 'located at the bottom by the weight of the other steel column 100'.
33 (c) and 33 (d)
A guide plate GP is installed at both ends of the
At least one of the upper end of the
Ⅴ. Base for transportation and construction of frame unit Template
Figs. 43 to 53 show an embodiment in which a base template for transporting and constructing a skeleton unit according to the present invention is used.
As shown,
A base template (BS) for transporting and constructing a frame unit of the present invention comprises:
A plurality of template foundation nodes (TN) in which a framing column unit (1100) is detachably coupled to an upper portion and a vibration-isolating pad (PP) is provided at an interruption;
A frame P connecting the plurality of template base nodes TN;
A brace (CP) connecting the template base nodes (TN) in the diagonal direction among the plurality of template base nodes (TN);
, ≪ / RTI >
A
Is used as a temporary foundation for manufacturing the frame unit (1000) or used as a foundation of the structure directly,
The vibration absorbing pad PP absorbs and reduces vibrations generated when the
The frame (P)
(TN), including a fixed frame (P '), a length adjusting frame (P' ') and a length adjusting means,
The brace (CP)
Is connected to the template base node (TN) by a length adjusting frame (P '') including a length adjusting means and the length adjusting frame (P '') is hinged to the template base node , And diagonal direction template base nodes (TN).
A node top plate (NP) and a node bottom plate (NP ') are provided on the top and bottom of the template base node (TN)
A column end plate CF provided under the
A node lower plate NP 'of another anti-vibration base template BS is coupled to the node upper plate NP when two or more of the anti-vibration base templates BS are stacked and coupled,
As a basis for manufacturing the
Since the plurality of vibration damping pads PP are stacked, the effect of absorbing and reducing vibrations occurring at the time of manufacturing the
The vibration damping pad PP may be omitted if necessary.
The base template (BS) of the present invention,
Can be recycled,
It is used during the movement of the superstructure and it is used as the base of the structure directly in the earthquake zone to protect the superstructure from vibration such as earthquake.
VI. hybrid Construction method of PC structure
Figs. 54 to 70 show an embodiment of a method of constructing the hybrid PC structure of the present invention in order.
One. Pipe rack structure (pipe rack structure)
A method of constructing a hybrid PC structure according to the present invention comprises:
A pipe rack structure that does not require a separate refractory coating by using the
(1) As shown in FIG. 54 (a), a base template (BS) is prepared, which is composed of a plurality of template base nodes (TN) and a plurality of frames (P) connecting the template base nodes Template preparation step;
(2) a column mounting step of installing a plurality of the
(3) As shown in FIGS. 57 and 58, a plurality of
(4) a pipe installing step of installing a plurality of
(5) As shown in FIG. 63, a framing unit coupling step of coupling the completed
(6) As shown in FIGS. 64 and 66, the column end plate CF of the lower part of the
And a control unit,
The
As shown in Figure 65,
A setting cone insertion hole CFH is formed in the column end plate CF of the lower part of the
The setting cone (CFC) is inserted into the setting cone insertion hole (CFH)
The lower end column end plate CF of the completed
As shown in Figs. 66 and 67,
In the present invention, the step (6)
(FPM) is covered with a die unit (FU) divided into a plurality of members.
61,
(5) joining the frame units;
And a conveying step of conveying the combined frame unit (1000) and the base template (BS).
In the present invention, a plurality of the
The
(3) installation and refractory covering step; And (4) the pipe installation step is repeated from the bottom to the top at the various stages.
2. General building structure
68,
The present invention is characterized in that the
The end portion of the
The pipe installation step (4) is omitted,
(7) a slab concrete pouring step simultaneously placing the slab concrete in the upper part of the
, ≪ / RTI &
A slab is formed on the upper portion of the
A setting cone insertion hole CFH is formed in the column end plate CF of the lower part of the
The setting cone (CFC) is inserted into the setting cone insertion hole (CFH)
The lower end column end plate CF of the completed
(6) The refractory mortar coating step,
(FPM) is covered with a die unit (FU) divided into a plurality of members.
(5) joining the frame unit,
And a conveying step of conveying the combined frame unit (1000) and the base template (BS).
The plurality of
The
The step (3) of installing the beam and the step of coating the refractory is repeated from the bottom to the top at the various stages.
69 and 70, a general building structure without a base template BS will be described below.
The present invention is for the construction using pillars (100) and beams (200)
(1) a foundation installation step of excavating the ground and installing a plurality of bases (not shown);
(2) a column installation step of installing a plurality of the
(3) a beam installation step of installing a plurality of
(4) slab concrete pouring step for pouring slab concrete;
, ≪ / RTI >
The
As shown in FIG. 69, the ends of the
The slab concrete pouring step (4) is performed by simultaneously placing the slab concrete in an upper part of the beam concrete (205), the spacing part (207) and a slab forming position,
A slab is formed on the upper portion of the
VII. hybrid Construction method of steel joint structure
Figs. 71 to 80 show an embodiment of a method of constructing the hybrid steel frame joint structure of the present invention in order.
One. Pipe rack structure (pipe rack structure)
A method of constructing a hybrid steel-frame joint structure of the present invention comprises:
A steel pipe 200 'having a steel column 100' having a column flange 100'-1 and a column web 100'-2 and a steel plate 200 ' structure,
(1) A base template preparing step (step (a)) of preparing a base template (BS) composed of a plurality of frames P connecting the plurality of template base nodes TN and the template base nodes TN as shown in ;
(2) a column mounting step of installing a plurality of the steel column 100 'on the template base node TN of the base template BS as shown in FIGS. 71 (b) to 73;
(3) a beam installing step of installing a plurality of steel beams 200 'on the steel column 100' as shown in FIGS. 74 and 75;
(4) a pipe installation step of installing a plurality of
(5) a framing unit coupling step of coupling the completed
(6) As shown in FIG. 80, the lower end column end plate CF of the steel column 100 'of the completed
The present invention is directed to a pipe rack structure for constructing a pipe rack structure.
65,
A setting cone insertion hole CFH is formed in a lower end end plate CF of the steel column 100 'of the completed
The setting cone (CFC) is inserted into the setting cone insertion hole (CFH)
The column end plate CF of the lower part of the
(5) joining the frame unit,
And a conveying step of conveying the combined frame unit (1000) and the base template (BS).
The present invention is characterized in that a plurality of the steel bars 200 'are partially installed in the longitudinal direction first and the other parts are laterally installed laterally in the same or different levels.
The steel column 100 'is divided into several stages,
(3) installing the beam; And (4) the pipe installation step is repeated from the bottom to the top at the various stages.
2. General building structure
As shown in FIG. 78,
The pipe installation step (4) is omitted.
A setting cone insertion hole CFH is formed in a lower end end plate CF of the steel column 100 'of the completed
The setting cone (CFC) is inserted into the setting cone insertion hole (CFH)
The column end plate CF of the lower part of the
(5) joining the frame unit,
And a conveying step of conveying the combined frame unit (1000) and the base template (BS).
The present invention is characterized in that a plurality of the steel bars 200 'are partially installed in the longitudinal direction first, and the other parts are laterally installed laterally in the same or different levels.
Further, the steel column 100 'is divided into several stages,
And (3) the step of installing the beam is repeated from the bottom to the top at the various stages.
Hereinafter, a general building structure without a base template (BS) will be described.
The present invention relates to a method for constructing a steel column 100 'having a column flange 100'-1 and a column web 100'-2 by using a steel beam 200' As a result,
(1) a foundation installation step of excavating the ground and installing a plurality of bases (not shown);
(2) a column installation step of installing a plurality of the steel column 100 'on the foundation; And
(3) installing a plurality of steel beams 200 'on the steel column 100';
And a control unit.
As shown in Figs. 30 to 31,
A setting bolt SB is installed to protrude from the column flange 100'-1,
A setting hole (SH) is formed under the beam plate (210)
After the steel frame 200 'is lowered by its own weight and the setting hole SH is set on the setting bolt SB, the column flange 100'-1 and the
And the steel beam 200 'is self-leveled and coupled to the exact position of the steel column 100' by its own weight.
32,
A guide plate GP is installed at both ends of the column flange 100-1 so as to guide the
The lower end of the
The setting bolt SB and the setting hole SH may be omitted.
33,
The present invention is characterized in that a
A setting bolt SB is installed to protrude below the
The steel frame 200 'is coupled to the
Since the
And the steel beam 200 'is self-leveled and coupled to the exact position of the steel column 100' by its own weight.
The present invention is characterized in that a guide plate GP is installed at both ends of the
At least one of the upper end of the
33 (a) and 33 (c)
A nut (N) is fastened to the rear surface of the column plate (110) to fasten the bolt to the nut (N)
33 (b) and 33 (d)
The bolts B may be fastened to the rear surface of the
34 (a) and Fig. 35,
The present invention relates to a steel column 100 'having a column flange 100'-1 and a column web 100'-2;
A
, ≪ / RTI >
A setting bolt SB is installed to protrude from the column flange 100'-1,
A setting hole (SH) is formed under the bracket plate (520)
The
And the
The setting bolt SB and the setting hole SB may be omitted.
34 (b), a
Although not shown, a setting bolt SB is installed to protrude below the
The
Since the
And the
A nut (N) is fastened to the rear surface of the column plate (110) to fasten the bolt to the nut (N)
The bolts B may be fastened to the rear surface of the
As shown in Figures 36, 37, 39 and 40,
In the present invention, one end of a steel beam 200 'is coupled to the other end of the
A
The connecting
A fixing
The other end of the
And are corresponding to each other,
Is lowered without being caught by the other end of the column bracket (500) when one end of the steel beam (200 ') is lowered by its own weight.
36 and 37,
The other end of the
39,
The other end of the
And has a shape inclined from the top to the bottom.
40,
The shape of the other end of the
As shown in Fig. 38 (b)
And one end of the
41 and 42,
In the present invention, an
The upper end of the
When the other steel column 100 'descends from the upper part,
Is self-leveling and is coupled to an accurate center line with the steel column 100 'located at the bottom by the weight of the other steel column 100'.
33 (c) and 33 (d)
A guide plate GP is installed at both ends of the
At least one of the upper end of the
VIII. Steel - Concrete hybrid Construction method of PC structure
81 to 97 show an embodiment of a method of constructing a steel-concrete hybrid PC structure according to the present invention in order.
One. Pipe rack structure (pipe rack structure)
A method of constructing a steel-concrete hybrid PC structure of the present invention comprises:
A pipe rack structure that does not require a separate refractory coating by using the
(1) A base template preparing step (step (a)) of preparing a base template (BS) composed of a plurality of frames P connecting the plurality of template base nodes TN and the template base nodes TN as shown in ;
(2) a column installing step of installing a plurality of the
(3) As shown in FIGS. 84 and 85, a plurality of
(4) a pipe installation step of installing a plurality of
(5) a framing unit coupling step of coupling the completed
(6) As shown in FIGS. 64, 66, 92 and 93, the column end plate CF of the lower part of the
And a control unit,
The
85 (c) and 96, the
65,
A setting cone insertion hole CFH is formed in the column end plate CF of the lower part of the
The setting cone (CFC) is inserted into the setting cone insertion hole (CFH)
The lower end column end plate CF of the completed
66 and 67,
(6) The refractory mortar coating step,
(FPM) is covered with a die unit (FU) divided into a plurality of members.
90,
(5) joining the frame unit,
And a conveying step of conveying the combined frame unit (1000) and the base template (BS).
And a plurality of the
The
(3) installation and refractory covering step; And (4) the pipe installation step is repeated from the bottom to the top at the various stages.
2. General building structure
89 (b) is a general building structure using a base template (BS)
The present invention is characterized in that the
The end portion of the
The pipe installation step (4) is omitted,
(7) Slab concrete is laid so that the upper flange and the upper part of the web of the
Lt; / RTI >
A slab is formed on the upper portion of the
85 (c) and 96, the
A setting cone insertion hole CFH is formed in the column end plate CF of the lower part of the
The setting cone (CFC) is inserted into the setting cone insertion hole (CFH)
The lower end column end plate CF of the completed
As shown in Figs. 66 and 67,
(6) The refractory mortar coating step,
(FPM) is covered with a die unit (FU) divided into a plurality of members.
61,
(5) joining the frame unit,
And a conveying step of conveying the combined frame unit (1000) and the base template (BS).
A plurality of the
The
The step (3) of installing the beam and the step of coating the refractory is repeated from the bottom to the top at the various stages.
Hereinafter, a general building structure without a base template (BS) will be described.
The present invention is for the construction using pillars (100) and beams (200)
(1) a foundation installation step of excavating the ground and installing a plurality of bases (not shown);
(2) a column installation step of installing a plurality of the
(3) a beam installation step of installing a plurality of
(4) slab concrete pouring step for pouring slab concrete;
, ≪ / RTI >
The
94 and FIG. 25 (b), the ends of the
The slab concrete pouring step (4) includes placing the slab concrete over the web stop of the
A slab is formed on the upper portion of the
96, the
While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the invention.
It is therefore intended that the appended claims cover such modifications and variations as fall within the true scope of the invention.
N: Nut
BFN: Double-sided nut
B: Bolt
SB: Setting bolt
SH: Setting hole
GP: Guide plate
PP: anti-vibration pad
BS: Base template
TN: Template Foundation Node
NP: Node top plate
NP`: Node bottom plate
P: frame
P`: Fixed frame
P``: Length adjustment frame
CP: Brace
CF: Column end plate
CFC: Setting cone
CFH: Setting cone insertion hole
FU: Formwork unit
WD: Welding
SP: Spacer
100: Column
100`: Steel column
100`-1: Column flange
100`-2: Column web
110: column plate
112: vertical slot
114: horizontal slot
116:
118: double-sided nut buried steel
118-1: Straight
118-2: U-shaped
200: Bo
201: Reinforced concrete
202:
205: Beam concrete
207:
200`: steel frame
210:
300: girder
310: girder plate
312: vertical slot
400: beam
410: beam plate
500: Column bracket
520: Bracket plate
540: connecting plate
560: Support plate
580: Fixing plate
590: Column connection plate
1000: Frame unit
1100: Frame column unit
2000: Pipe
Claims (17)
A beam 200 optionally including a reinforcing bar and an end coupled to the beam plate 210;
, ≪ / RTI >
A vertical slot 112 having an open top and a closed bottom is formed in the column plate 110 so that a nut N protruding from the beam plate 210 is inserted into an open portion of the upper portion of the vertical slot 112 And,
Since the column plate 110 and the beam plate 210 are fastened with bolts,
Wherein the beam (200) is self leveling to the correct position of the column (100) by self weight.
The lower end of the beam plate 210 or the upper end of the column plate 110 may be cut obliquely,
The lower end of the beam plate 210 and the upper end of the column plate 110 are sloped in an interlocking manner,
And the lower end of the beam plate (210) contacts the upper end of the column plate (110) and then slides down to be lowered.
A beam 200 optionally including a reinforcing bar and an end coupled to the beam plate 210;
, ≪ / RTI >
A horizontal slot 114 is formed in the column plate 110 with one side opened and the other side closed to allow the nut N protruding from the beam plate 210 to be opened at one side of the horizontal slot 114 ≪ / RTI >
Since the column plate 110 and the beam plate 210 are fastened with bolts,
Wherein the beam (200) is self leveling to the correct position of the column (100).
The other end of the beam plate 210 or one end of the column plate 110 may be cut obliquely,
The other end of the beam plate 210 and one end of the column plate 110 are sloped in an interlocking manner,
Wherein the other end of the beam plate (210) contacts one end of the column plate (110) and then slides to move laterally.
A beam 200 optionally including a reinforcing bar and an end coupled to the beam plate 210;
, ≪ / RTI >
A setting bolt SB is installed to protrude below the column plate 110,
A setting hole (SH) is formed under the beam plate (210)
Since the beam 200 is lowered by its own weight and the setting hole SH is fixed to the setting bolt SB, the column plate 110 and the beam plate 210 are bolted together,
Wherein the beam (200) is self leveling to the correct position of the column (100) by self weight.
When two or more column plates 110 are coupled to the outer surface of one column 100 at different levels on the same level,
A plurality of bolts coupled to each of the two or more column plates 110 for connecting the beam plates 210 are fastened to the outer surface of the column 100 at different levels so that interference occurs between the plurality of bolts Wherein the rod-and-column hybrid structure comprises a plurality of columns.
When two or more column plates 110 are coupled to the outer surface of one column 100 at different levels on the same level,
A plurality of bolts coupled to each of the two or more column plates 110 for connecting the beam plates 210 are fastened to the outer surface of the column 100 at different levels so that interference occurs between the plurality of bolts Wherein the rod-and-column hybrid structure comprises a plurality of columns.
When two or more column plates 110 are coupled to the outer surface of one column 100 at different levels on the same level,
A plurality of bolts coupled to each of the two or more column plates 110 for connecting the beam plates 210 are fastened to the outer surface of the column 100 at different levels so that interference occurs between the plurality of bolts Wherein the rod-and-column hybrid structure comprises a plurality of columns.
A small beam of beam 400 optionally including a beam steel frame inside and a beam plate 410 coupled to the end;
, ≪ / RTI >
A vertical slot 312 is formed in the upper portion of the girder plate 310 and the lower portion of the girder plate 310 is closed so that a nut N protruding from the beam plate 410 is inserted into an upper portion of the vertical slot 312 And,
Since the girder plate 310 and the beam plate 410 are fastened with bolts,
Wherein the beam (400) is self-leveled and coupled to the correct position of the girder (300) by its own weight.
The lower end of the beam plate 410 or the upper end of the girder plate 310 may be cut obliquely,
The lower end of the beam plate 410 and the upper end of the girder plate 310 are slantingly cut into an interlocking shape,
Wherein the lower end of the beam plate (410) contacts the upper end of the girder plate (310), and then slides down to be lowered.
A small beam of beam 400 optionally including a beam steel frame inside and a beam plate 410 coupled to the end;
, ≪ / RTI >
A setting bolt (not shown) protrudes from the bottom of the girder plate 310,
A setting hole (not shown) is formed below the beam plate 410,
Since the beam 400 is lowered by its own weight and the girder plate 310 and the beam plate 410 are bolted together after the setting hole (not shown) is set in the setting bolt (not shown)
Wherein the beam (400) is self-leveled and coupled to the correct position of the girder (300) by its own weight.
A guide plate GP is installed at both ends of the column plate 110,
And the beam plate (210) is guided when the beam (200) descends.
A guide plate GP is installed at the upper and lower ends of the column plate 110,
And the beam plate (210) is guided when the beam (200) moves horizontally.
A guide plate GP is installed at both ends of the girder plate 310,
And the beam plate (410) is guided when the beam (400) descends.
A guide plate GP is installed at both ends of the girder plate 310,
And the beam plate (410) is guided when the beam (400) descends.
The nut plate (210) has a nut hole formed therein, the nut (N) is installed at the other end and the other end is protruded,
Since the thickness of the column plate 110 is the same as the protrusion length of one end of the nut N,
And the amount of steel material of the beam plate (210) and the column plate (110) is reduced.
The beam 200 encases the beam concrete,
Wherein the beam plate (210) is coupled to the beam concrete using stud bolts (not shown).
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR20150061529 | 2015-04-30 | ||
KR1020150061529 | 2015-04-30 |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20160130130A true KR20160130130A (en) | 2016-11-10 |
KR101675022B1 KR101675022B1 (en) | 2016-11-11 |
Family
ID=57484619
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150078696A KR101675022B1 (en) | 2015-04-30 | 2015-06-03 | the hybrid joint construction between column and beam, the hybrid joint construction between girder and beam |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101675022B1 (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05179702A (en) * | 1991-12-28 | 1993-07-20 | Daiwa House Ind Co Ltd | Column-beam connected structure |
JPH07238590A (en) * | 1994-02-28 | 1995-09-12 | Hitachi Zosen Corp | Beam coupling part structure of precast column |
KR100622300B1 (en) | 2005-02-02 | 2006-09-19 | 삼성물산 주식회사 | Pin connection structure of concrete beam and PC post, and construction method thereof |
KR20090126076A (en) * | 2008-06-03 | 2009-12-08 | 동국대학교 산학협력단 | Dry beam-column connection of precast concrete members within the extended limitation of construction tolerances |
JP2009299267A (en) * | 2008-06-10 | 2009-12-24 | Takenaka Komuten Co Ltd | Structure and method for joining precast concrete structural members together |
KR101289934B1 (en) | 2012-12-18 | 2013-07-25 | (주) 동양구조안전기술 | Connection of compressed joint using post-tension between pc-column and pc beam and it's construction method |
-
2015
- 2015-06-03 KR KR1020150078696A patent/KR101675022B1/en active IP Right Grant
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05179702A (en) * | 1991-12-28 | 1993-07-20 | Daiwa House Ind Co Ltd | Column-beam connected structure |
JPH07238590A (en) * | 1994-02-28 | 1995-09-12 | Hitachi Zosen Corp | Beam coupling part structure of precast column |
KR100622300B1 (en) | 2005-02-02 | 2006-09-19 | 삼성물산 주식회사 | Pin connection structure of concrete beam and PC post, and construction method thereof |
KR20090126076A (en) * | 2008-06-03 | 2009-12-08 | 동국대학교 산학협력단 | Dry beam-column connection of precast concrete members within the extended limitation of construction tolerances |
JP2009299267A (en) * | 2008-06-10 | 2009-12-24 | Takenaka Komuten Co Ltd | Structure and method for joining precast concrete structural members together |
KR101289934B1 (en) | 2012-12-18 | 2013-07-25 | (주) 동양구조안전기술 | Connection of compressed joint using post-tension between pc-column and pc beam and it's construction method |
Also Published As
Publication number | Publication date |
---|---|
KR101675022B1 (en) | 2016-11-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101030419B1 (en) | Joint structure of vertical member and horizontal member | |
CN107989228B (en) | Prefabricated steel reinforced concrete shear wall structure and preparation and installation methods thereof | |
KR101766806B1 (en) | the rigid connection structure between precast concrete column and precast concrete beam using the temporary bracket installing precast concrete column, the modular system using the same | |
KR102011412B1 (en) | Joint for Precast Beam and Columns | |
KR101962853B1 (en) | Joint for Precast Beam and Columns | |
KR101572926B1 (en) | the steel-concrete hybrid precast concrete beam connecting structure for a horizontal extending a building and the construction method thereof | |
KR101844344B1 (en) | the rigid connection structure between precast concrete column and precast concrete beam, the construction method of rigid connection structure using the same | |
CN108005264B (en) | Steel frame constraint precast reinforced concrete shear wall structure and preparation and installation methods | |
KR101751776B1 (en) | the hybrid self-positioning connecting structure of column and beam | |
KR101691635B1 (en) | the base template for the frame unit transportation and construction | |
JP4235079B2 (en) | Structure of joint between reinforced concrete column and steel beam | |
KR101665626B1 (en) | the construction method of the hybrid steel joint construction | |
KR101766805B1 (en) | the hybrid joint construction between column plate and column | |
KR101429137B1 (en) | PC Beam Unit Connection Structure For Expensive Space And Construction Method Thereof | |
KR101700950B1 (en) | the hybrid steel joint construction between column and beam | |
KR101665622B1 (en) | the construction method of steel-concrete hybrid precast concrete structure | |
JP5869717B1 (en) | Existing concrete structure reinforcement structure | |
KR101675022B1 (en) | the hybrid joint construction between column and beam, the hybrid joint construction between girder and beam | |
KR101665628B1 (en) | the construction method of hybrid precast concrete structure | |
JP5207078B2 (en) | Construction method for seismic control columns | |
KR101872274B1 (en) | the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure between precast concrete column and precast concrete beam | |
KR101548215B1 (en) | the deep composite precast beam, the connection structure between composite precast column and the deep composite precast beam | |
KR20180026286A (en) | Grid precast concrete structure and constructing method thereof | |
KR20170123370A (en) | the rigid connection structure without concrete between the upper precast concrete column and the lower precast concrete column and the rigid connection structure between precast concrete column and precast concrete beam | |
JP2001262586A (en) | Foundation structure of dwelling house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GRNT | Written decision to grant |