KR20150130099A - Steel and concrete composite segment for through bridge, and bridge construction method using the same - Google Patents

Steel and concrete composite segment for through bridge, and bridge construction method using the same Download PDF

Info

Publication number
KR20150130099A
KR20150130099A KR1020140057240A KR20140057240A KR20150130099A KR 20150130099 A KR20150130099 A KR 20150130099A KR 1020140057240 A KR1020140057240 A KR 1020140057240A KR 20140057240 A KR20140057240 A KR 20140057240A KR 20150130099 A KR20150130099 A KR 20150130099A
Authority
KR
South Korea
Prior art keywords
bridge
steel composite
segment
box body
hollow
Prior art date
Application number
KR1020140057240A
Other languages
Korean (ko)
Inventor
이연철
Original Assignee
주식회사 제이케이브릿지
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 제이케이브릿지 filed Critical 주식회사 제이케이브릿지
Priority to KR1020140057240A priority Critical patent/KR20150130099A/en
Publication of KR20150130099A publication Critical patent/KR20150130099A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Disclosed is a steel composite hollow segment for a through bridge and a construction method of a bridge using the same comprising: both side beams manufactured in a box-shape by assembling bent steel plates to form a hollow part(s), including a bent hollow box body and longitudinal tendons arranged around the bent hollow box body, and manufactured using concrete; and a transverse slab formed between a bottom inner sides of the side beams to be extended in a transverse direction, including a bent hollow box body arranged to be extended in a longitudinal direction and a longitudinal steel beam arranged between the bent hollow box bodies, and manufactured using concrete. As such, the present invention enables rapid and efficient construction by minimizing a weight of the segment.

Description

하로교용 강합성 중공세그먼트 및 이를 이용한 교량시공공법{STEEL AND CONCRETE COMPOSITE SEGMENT FOR THROUGH BRIDGE, AND BRIDGE CONSTRUCTION METHOD USING THE SAME}STEEL AND CONCRETE COMPOSITE SEGMENT FOR THROUGH BRIDGE, AND BRIDGE CONSTRUCTION METHOD USING THE SAME BACKGROUND OF THE INVENTION [0001]

본 발명은 하로교용 강합성 중공세그먼트 및 이를 이용한 교량시공공법에 관한 것이다. 더욱 구체적으로 양 측면빔과 슬래브를 포함하는 하로교용 세그먼트를 보다 장경간으로 제작할 수 있으면서도 자중이 크지 않아 시공성이 뛰어난 하로교용 강합성 중공세그먼트 및 이를 이용한 교량시공공법에 관한 것이다.The present invention relates to a steel composite hollow segment for hanging and a bridge construction method using the same. More particularly, the present invention relates to a steel composite hollow segment for a hanging bridge, which can be manufactured by a long span of segments including both side beams and slabs and has a small weight, and is excellent in workability, and a bridge construction method using the hollow segment.

하로교(THROUGH BRIDGE)는 슬래브의 위치에 따른 교량형식이다.THROUGH BRIDGE is the bridge type according to the location of the slab.

즉 하로교는 슬래브(노면)가 종방향 거더 하부에 위치되도록 한 교량이다.In other words, the lower bridge is a bridge in which the slab (road surface) is positioned below the longitudinal girder.

이러한 하로교 방식으로 최근 적용된 교량이 경전철 시공에 사용된 바 있는 UCB(U-TYPE CHANNEL BRIDGE, 채널브리지)이다.Recently, the bridges that have been applied in this way are the U-type bridge bridges (UCBs) used in light rail construction.

도 1a는 상기 하로교인 채널브리지(10,UCB)와 PSC 거더교(20)의 시공단면도를 비교 도시한 것인데, PSC 거더교 보다 형고가 낮아 주행 중 시야확보에 유리하고, 슬래브 접속구간의 토공량 감소에 의하여 시공성 및 공사비가 절감될 수 있다는 장점이 있다.(하로교의 형고가 낮아 형하고는 상로교인 거더교와 대비하여 매우 커질 수 있음을 알 수 있다.)1A is a cross-sectional view of the PSC girder bridge 20 in comparison with the lower cross-sectional channel bridge 10 (UCB). The lower cross-sectional shape of the PSC girder bridge is advantageous for securing visibility while traveling, There is an advantage that construction work and construction cost can be reduced. (It can be seen that the shape of the lower bridge is very low, so it can be very big compared to the girder bridge which is a sagittal bridge.)

이러한 채널브리지의 종래 시공공법으로서 채널브리지용 U형 세그먼트를 풀-스테이징 방법으로 설치할 수 있는데 이럴 경우 동바리와 같은 가시설 시스템을 반드시 설치해야 하므로 현장여건상 이를 설치할 수 없는 경우도 있고, 가시설 시스템의 시공비가 너무 큰 비중을 차지하는 경우가 많았다.As a conventional construction method of such a channel bridge, a U-shaped segment for a channel bridge can be installed as a full-staging method. In such a case, it is necessary to install a provisional system such as a horseshoe, Were often too large.

도 1b는 다른 종래 하로교의 제작방법을 도시한 것인데, 특히 프리플렉스 빔(40)을 제작하되, 하부플랜지 콘크리트(41) 각 내측면 하부에 수평으로 돌출된 돌출부(42)를 형성시키고, 상기 돌출부(42)에 프리캐스트 콘크리트 슬래브(50)가 얹어지도록 설치한 다음,In particular, the preflex beam 40 is manufactured by forming a protruding portion 42 horizontally protruding from the bottom of each inner side of the lower flange concrete 41, The precast concrete slab 50 is placed on the slab 42,

상기 프리캐스트 콘크리트 슬래브(50)와 프리플렉스 빔(40)은 돌출철근(43,44)들에 의하여 서로 연결되도록 하고, 상기 돌출철근(43,44)이 연결되는 부위를 콘크리트(45)로 마감하도록 하로교를 제작하는 방법이 소개되어 있다.The pre-cast concrete slab 50 and the pre-flex beam 40 are connected to each other by the projecting reinforcing bars 43 and 44, and a portion to which the projecting reinforcing bars 43 and 44 are connected is finished with concrete 45 And how to make a halos bridge.

이러한 하로교 제작은 종래 종방향으로 서로 연결되는 프리캐스트 방식의 U형 세그먼트(10)를 제작하는 방식과는 차별화되지만 상기 돌출부(42)에 슬래브의 자중 및 활하중이 작용할 경우 자칫 구조적으로 취약할 수밖에 없었다.Such a hanging bridge manufacturing is distinguished from the conventional method of manufacturing the pre-cast type U-shaped segment 10 connected to each other in the longitudinal direction. However, when the weight of the slab and the live load act on the protruding portion 42, .

이에 도 1c와 같은 하로교도 소개된 바 있다.In this case, a halo bridge as shown in FIG. 1C has been introduced.

즉, 양 측면빔(60)을 횡방향으로 이격시켜 설치하고, 일정 횡방향길이를 가진 횡방향 슬래브(70)를 종방향으로 다수 연속하여 설치되도록 한 것이다.That is, the both side beams 60 are disposed in the lateral direction, and a plurality of the lateral slabs 70 having a predetermined transverse length are installed in the longitudinal direction.

이에 횡방향 슬래브(70)의 하중을 측면빔(60)이 부담하도록 하기 위하여 측면빔(60)은 상부지지체(61)와 횡방향 슬래브(70)의 양 단부가 지지될 수 있도록 상부지지체(61) 하부에 내측으로 더 연장되어 지지턱(63)이 형성되도록 하게 된다.In order to allow the side beams 60 to bear the load of the transverse slab 70, the side beams 60 are arranged such that both ends of the upper support 61 and the transverse slab 70 are supported by the upper supports 61 So as to form the support step 63. [0053] As shown in FIG.

이에 상기 측면빔(60)의 하부지지체(62)의 높이는 횡방향 슬래브(70)의 하중을 지지할 수 있을 정도로 소정의 높이(H1)를 확보하여야 하고, 횡방향 슬래브(70)의 하중 대부분을 측면빔(60)이 부담하게 되므로 측면빔(60)의 높이(H2)도 상당 정도 확보할 수밖에 없었다.The height of the lower support 62 of the side beam 60 should be set to a predetermined height H1 so as to support the load of the lateral slab 70 and the load of the lateral slab 70 Since the side beams 60 are burdened, the height H2 of the side beams 60 has to be secured to a considerable extent.

또한 측면빔(60)의 단면을 최적화하기 위하여 종방향으로 연장된 긴장재(80)를 배치하고 자중을 줄이기 위하여 내부는 EPS 블럭(64)을 매립 설치하는 등의 측면빔(60) 제작이 매우 중요하게 됨을 알 수 있다.In order to optimize the cross-section of the side beam 60, it is very important to arrange the tension member 80 extending in the longitudinal direction and to construct the side beam 60 such as embedding the EPS block 64 in order to reduce its own weight .

이러한 측면빔(60)과 횡방향 슬래브(70)를 이용한 하로교는 현장여건에 따라서는 1경간이기는 하지만 횡방향으로 폭이 넓게 형성되어야 하는 경우도 있다.The downshifting using the side beams 60 and the lateral slabs 70 may be one span depending on the site conditions, but may be formed to be wide in the lateral direction.

이에 횡방향 슬래브(70)의 횡방향 길이(L4)도 커져야 하는데 이러한 횡방향 슬래브(70)의 길이(L4)를 개략 15m이상 형성시켜야 할 경우 그 자중이 너무 크게 늘어나기 때문에 측면빔(60)의 단면크기가 함께 커질 수밖에 없게 된다.The lateral length L4 of the transverse slab 70 must also be large. When the length L4 of the transverse slab 70 needs to be approximately 15 m or more, the weight of the side slab 70 is excessively increased, The cross-sectional size of the cross-sectional area of the cross-sectional area of the cross-

말하자면, 횡방향 슬래브(7)의 횡방향 길이(L4)이 커지면 커질수록 측면빔(60)의 높이(H2)와 측면빔(60)의 하부지지체(62)의 높이(H1)도 함께 증가시켜야 하다보니 하로교의 형고도 함께 증가될 수밖에 없어 하로교의 장점이 없어진다는 문제점이 발생하게 되었다.The height H2 of the side beam 60 and the height H1 of the lower support 62 of the side beam 60 must also be increased as the lateral length L4 of the lateral slab 7 becomes larger As a result, there is a problem that the merit of the Halo Bridge can not be increased.

따라서 횡방향폭이 넓게 시공되어야 하는 하로교에 있어서는 측면빔(60)의 단면을 최소화시켜야 하는데 하로교의 특성상 측면빔의 단면을 최소화 하는데는 한계가 있을 수밖에 없었다.Therefore, the cross-section of the side beam 60 must be minimized in the lower bridge where the horizontal width should be widened. However, there is a limit in minimizing the cross-section of the side beam due to the characteristics of the lower bridge.

또한 교각과 교각 사이에 걸쳐 측면빔(60)과 횡방향 슬래브(70)가 일체로 제작된 하로교용 세그먼트(1개의 세그먼트)를 이용함에 있어서는 그 자중이 너무 커지기 때문에 가설장비도 문제이지만 횡방향 슬래브(70)의 두께와 측면빔(60)의 단면높이가 너무 증대되어 하로교용 세그먼트를 이용한 교량시공이 사실상 어렵다는 문제점이 있었다.In addition, in the case of using the downhill segment (one segment) in which the side beam 60 and the lateral slab 70 are integrally formed between the bridge piers and the bridge piers, the self weight is excessively large, The thickness of the side wall beam 70 and the height of the cross section of the side beam 60 are excessively increased, so that it is practically difficult to construct a bridge using the downhill segment.

이에 본 발명은 측면빔과 횡방향 슬래브를 별도로 제작하지 않고 1개의 세그먼트로 장경간에 걸쳐 설치할 수 있으면서도 자중을 최소화시킬 수 있어 보다 신속하고 효율적으로 시공이 가능한 하로교용 강합성 중공세그먼트 및 이를 이용한 교량시공공법 제공을 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention can minimize the weight of the steel rod by installing the side beam and the lateral slab in a single segment, and can minimize the weight of the steel rod. Therefore, a steel composite hollow segment for a hanging bridge can be constructed more quickly and efficiently, It is a technical task to solve the provision of public law.

상기 과제를 달성하기 위하여 본 발명은In order to achieve the above object,

첫째, 하로교용 세그먼트를 강합성 중공세그먼트로 제작하게 된다. 말하자면 장경간에 설치되는 관계로 콘크리트에 의한 자중 증가요인을 최소화시키면서 소요의 휨강성을 충분히 확보할 수 있도록 내부에 중공부를 다수 형성시켜 제작하게 되며 휨 강성을 ?보하기 위하여 횡방향 슬래브에는 강재빔이 매립되도록 하고, 양 측면빔에는 PC강연선을 중공부 주위에 배치하여 프리스트레스가 도입되도록 하게 된다. 이에 본 발명의 하로교용 세그먼트를 하로교용 강합성 중공세그먼트로 지칭하게 된다.First, the segment for the downhole is made of a steel composite hollow segment. In other words, since it is installed between the long slopes, a large number of hollow parts are formed in order to secure sufficient bending stiffness while minimizing the increase of self weight due to concrete. In order to show the flexural rigidity, steel beams are buried in the lateral slab And the PC stranded wire is arranged around the hollow portion in the both side beams so that the prestress is introduced. Accordingly, the segment for off-shoring of the present invention is referred to as a steel-synthesized hollow segment for hanging.

이에 하로교용 강합성 중공세그먼트는 U형 단면으로 교각, 교대 사이에 일체로 거치되도록 시공되며 양 측면빔을 먼저 설치하고 양 측면빔 사이에 횡방향 슬래브를 별도 시공하지 않고 완성된 1경간의 하로교용 강합성 중공세그먼트로서 런칭에 의한 시공에 의하여 설치되도록 하게 된다.Therefore, the steel composite hollow segment for downhole is constructed so as to be integrally mounted between the bridge piers and the alternating beams in a U-shaped section, and both side beams are installed first, and a horizontal slab is not separately installed between the side beams, As a steel composite hollow segment, by installation by launching.

둘째, 상기 측면빔 및 횡방향 슬래브 내부에는 중공부(S)가 형성되는데 종래에는 타설되는 콘크리트 배제를 위하여 ESP 블록이 매립시키는 방식으로 상기 중공부(S)가 형성되도록 하였지만 이러한 ESP 블록은 구조적인 하중 분담을 전제로 하여 설치되는 것은 아니므로 콘크리트 배제 기능을 가진 것에 불과하다.Secondly, a hollow portion S is formed inside the side beam and the lateral slab. In the past, the hollow portion S was formed by embedding an ESP block in order to exclude concrete to be laid. Since it is not installed on the assumption of load sharing, it has merely a function of excluding concrete.

이에 본 발명은 상기 중공부(S)가 구조재로서 기능할 수 있도록 중공박스체로 형성시키게 된다. 나아가 중공박스체는 강판을 이용하지 않고 파형강판 또는 데크용강판을 이용하여 절곡 또는 엠보싱된 강판을 조립하여 박스체(이하 절곡 중공박스체)로 제작하게 된다.Accordingly, the hollow part S is formed as a hollow box so that the hollow part S can function as a structural member. Further, the hollow box body is formed by using a corrugated steel plate or a steel plate for a deck without assembling a steel plate, and assembling the bent or embossed steel plate to form a box body (hereinafter referred to as a bending hollow box body).

이에 본 발명의 측면빔 및 횡방향슬래브는 내부에 절곡 중공박스체가 매립되도록 하고 상기 절곡 중공박스체 주위에 길이방향 긴장재가 배치되도록 하여 프리스트레스가 도입되도록 함으로서 단면을 최적화시킴과 더불어 이에 따라 자중이 최소화되도록 하게 된다.The side beams and the lateral slabs of the present invention are designed such that the folded hollow box body is embedded therein and the longitudinal torsion material is disposed around the folded hollow box body so that the prestress is introduced to optimize the cross section, .

셋째, 본 발명은 상기 절곡 중공박스체가 양 측면빔과 횡방향 슬래브 내부에 위치하도록 하고, 서로가 브레이싱재에 의하여 구속되도록 한 상태에서 콘크리트 타설에 의하여 제작되면 종방향 연장길이는 하로교의 경간에 맞추어 제작하고 횡방향 폭은 하로교의 차선 등을 고려하여 1개의 U형 단면 세그먼트로서 이용할 수 있도록 하게 된다. 이때 상기 브레이싱재, 절곡 중공박스체는 모두 강재로 제작되기 때문에 본 발명에 의한 하로교용 강합성 중공세그먼트는 내부철근을 배근하지 않도록 하여 보다 신속하고 효율적인 제작이 가능하도록 하였다.Third, according to the present invention, when the bent hollow box body is positioned inside both side beams and the transverse slab and is constructed by pouring concrete in a state where they are constrained by a bracing member, the longitudinal extension length is adjusted to the span of the lower bridge And the lateral width can be used as one U-shaped cross-section segment in consideration of the lane of the lower bridge. At this time, since the bracing member and the bending hollow box body are all made of steel, the steel composite hollow segment for hanging according to the present invention does not include the inner reinforcing bars, thereby enabling quick and efficient manufacture.

본 발명은 하로교용 강합성 중공세그먼트로서 자중을 최소화시킴에 있어 콘크리트와 내부철근을 배제할 수 있으면서도 절곡 중공박스체 및 PC 강연선(종방향 긴장재)에 의하여 소요의 휨강성을 충분히 확보할 수 있게 되므로 제작도 용이하고 신속한 장경간 교량시공이 가능하게 된다.The present invention is a steel composite hollow segment for downhole that minimizes its own weight and can eliminate the concrete and the inner reinforcing bars, but can sufficiently secure the required bending stiffness by the bent hollow box and the PC stranded wire It is possible to construct a long-span bridge easily and quickly.

이에 장경간용이 아니라면 크레인등을 이용하여 교각, 교대 사이에 거치하여 시공할 수도 있고, 장경간용 이라면 런칭장비를 이용하여 1경간씩 시공하는 방식(일종의 ILM 방식)으로 시공할 수 있게 된다.If it is not long-span, it can be installed between piers and alternations by using a crane, etc. If it is for long-span, it can be installed by one span (one kind of ILM system) using launching equipment.

도 1a는 종래 하로교와 거더교의 비교도
도 1b는 종래 하로교용 강합성 세그먼트의 단면도,
도 1c는 종래 양 측면빔과 횡방향 슬래브로 분리되어 제작되는 하로교 시공사시도,
도 2a와 도 2b는 본 발명의 하로교용 강합성 중공세그먼트의 구성사시도 및 완성사시도,
도 3a 및 도 3b는 본 발명의 실시예 1에 의한 하로교용 강합성 중공세그먼트의 시공순서도,
도 4a 내지 도 4j는 본 발명의 실시예 2에 의한 하로교용 강합성 중공세그먼트의 시공순서도,
도 5a 및 도 5b는 실시예 2에 사용되는 본 발명의 세그먼트 런칭장치의 사시도 및 시공단면도이다.
FIG. 1A shows a comparison between a conventional lower bridge and a girder bridge
1B is a cross-sectional view of a conventional steel composite segment for downhole,
FIG. 1C is a perspective view of a conventional halos, which is manufactured by separating the two side beams and the lateral slab,
FIGS. 2A and 2B are a perspective view and a completed perspective view of a steel composite hollow segment for hanging,
FIGS. 3A and 3B are views showing a construction sequence of a steel composite hollow segment for downhole according to Embodiment 1 of the present invention,
Figs. 4A to 4J are views showing a construction sequence of a steel composite hollow segment for downhole according to Embodiment 2 of the present invention, Fig.
5A and 5B are a perspective view and a construction cross-sectional view of the segment launching apparatus of the present invention used in the second embodiment.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings, which will be readily apparent to those skilled in the art. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In order to clearly illustrate the present invention, parts not related to the description are omitted, and similar parts are denoted by like reference characters throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when an element is referred to as "comprising ", it means that it can include other elements as well, without excluding other elements unless specifically stated otherwise.

[ 하로교용 강합성 중공세그먼트(400) ][Steel Composite Hollow Segment for Halo Bridge (400)]

도 2a는 하로교용 강합성 중공세그먼트(400)의 구성사시도, 도 2b는 하로교용 강합성 중공세그먼트(400)의 완성사시도이다.FIG. 2 (a) is a perspective view of a steel composite hollow segment 400 for a downhill bridge, and FIG. 2 (b) is a completed perspective view of a steel composite hollow segment 400 for a downhill bridge.

먼저 상기 하로교용 강합성 중공세그먼트(400)는 양 측면빔(410)과 횡방향 슬래브(420)가 서로 일체로 제작되어 전체적으로 U형 단면으로 일정한 종방향 길이(L)를 가지도록 제작된다.The steel composite hollow segment 400 for downhole is manufactured such that the both side beams 410 and the lateral slabs 420 are integrally formed with each other to have a U-shaped cross section and a constant longitudinal length L as a whole.

상기 측면빔(410)은 수직빔 형태로서 단면높이(H2)를 가지게 되면 횡방향폭 (W2)를 가지는 콘크리트 빔이다. 이러한 측면빔(410)의 내부에는 종방향으로 연장되는 절곡 중공박스체(430)가 형성되는데 중공부(S)가 형성되어 콘크리트가 상기 중공부에 의하여 배제되어 측면빔(410)의 자중을 감소시키게 된다.The side beam 410 is a vertical beam and is a concrete beam having a lateral width W2 when it has a sectional height H2. In the inside of the side beam 410, a hollow hollow box body 430 extending in the longitudinal direction is formed. A hollow portion S is formed to exclude the concrete by the hollow portion to reduce the weight of the side beam 410 .

이러한 절곡 중공박스체(430)는 사각박스체 형태로 제작할 수 있는데 일반 강판이 아닌 절곡부가 다수 수직방향으로 형성된 절곡 중공박스체로 형성된 것을 이용하게 된다.The bent hollow box body 430 may be formed in the form of a rectangular box body, which is formed of a folded hollow box body formed in a plurality of vertical directions rather than a general steel plate.

이와 같이 절곡부가 형성되면 절곡부에 의하여 휨 강성이 일반 강판보다 더 증가하기 때문에 동일한 강재량을 사용하더라도 휨 강성 확보에 유리하므로 측면빔(410)의 단면을 최적화시킬 수 있게 된다.Since the bending stiffness is increased more than the general steel plate by the bending portion when the bending portion is formed as described above, it is possible to optimize the cross section of the side beam 410 because it is advantageous in securing the bending stiffness even if the same amount of steel is used.

또한 절곡강판으로 제작되기 때문에 그 자체로서 내부철근의 역할도 하기 때문에 측면빔에 복잡하고 시공성이 저하되는 내부철근의 배근작업도 배제할 수 있게 된다.In addition, because it is made of bended steel plate, it also acts as an inner reinforcing bar itself, so that it is possible to exclude the work of laying an inner reinforcing bar, which is complicated and poor in workability, in the side beam.

또한 주위에 배치된 종방향 긴장재(440)에 의한 정착부위의 국부응력에도 저항할 수 있기 때문에 종방향 긴장재(440)를 절곡 중공박스체(430) 전체 주위를 따라 배치할 수 있어 보다 효율적인 종방향 긴장재(440)의 이용이 가능하게 된다.The longitudinal torsion members 440 can be disposed along the entire circumference of the folded hollow box body 430 because they can resist the local stress at the fixing site by the longitudinal torsion members 440 disposed around the longitudinal torsion members 440, The use of the tension member 440 becomes possible.

이로서 절곡 중공박스체(430)를 사용하더라도 경제성을 충분히 확보할 수 있게 됨을 알 수 있다.Therefore, even if the hollow hollow box body 430 is used, the economical efficiency can be sufficiently secured.

상기 측면빔(410)은 서로 횡방향으로 이격된 위치에 형성되며 하단부 내측 사이에 횡방향 슬래브(420)가 일정한 두께로 형성된다.The side beams 410 are formed at positions spaced apart from each other in a transverse direction, and a transverse slab 420 is formed between the inside of the lower ends to have a constant thickness.

상기 횡방향 슬래브(420)는 교량에 있어 차량 등에 의한 활하중이 작용하게 되므로 일정한 두께(T)를 확보해야 하는데 열차에 의한 활하중은 반복적이고 충격등이 가해지기 때문에 특히 종방향 강재빔(440)이 매립되도록 하게 되며 이러한 종방향 강재빔(450)은 횡방향 슬래브(420)의 내부에 횡방향으로 서로 이격되어 종방향으로 연장되도록 배치하게 된다.Since the lateral slab 420 is subjected to a live load by a vehicle or the like in the bridge, a certain thickness T must be secured. The live load caused by the train is repetitively applied, And these longitudinal steel beams 450 are arranged to extend longitudinally apart from one another transversely to the interior of the transverse slabs 420.

상기 종방향 강재빔(450)은 I형강을 이용하여 콘크리트에 의하여 매립되는 방식으로 설치된다. The longitudinal steel beams 450 are installed in a manner that they are filled with concrete using I-shaped steel.

이때 횡방향 슬래브(420)의 내부에도 종방향으로 연장되는 절곡 중공박스체(430)가 종방향 강재빔(450) 사이 사이에 배치되도록 하게 된다.At this time, a longitudinally extending hollow box body 430 extending in the longitudinal direction is also disposed between the longitudinal steel beams 450 inside the lateral slabs 420.

장경간용의 경우 횡방향 슬래브(420)의 횡방향폭(W1)은 증가되므로 타설되는 콘크리트의 무게 때문에 자중이 크게 늘어날 수밖에 없는데 본 발명은 이러한 자중 증가 요인을 상쇄시키면서 휨 강성을 확보하기 위하여 절곡 중공박스체(430)를 배치하게 된다.The longitudinal width W1 of the transverse slab 420 is increased to increase the weight of the concrete due to the weight of the concrete being laid. In order to secure the flexural rigidity of the present invention, The hollow box body 430 is disposed.

이러한 절곡 중공박스체(430) 역시 일반 강판이 아닌 절곡부가 다수 수직방향으로 형성된 것을 이용하게 된다.The bent hollow box body 430 may be formed of a plurality of bent portions formed in a vertical direction rather than a general steel plate.

단지 횡방향 슬래브(420) 내부에 배치되는 것이므로 높이보다 폭이 큰 형태로 형성되도록 하는 것이 측면빔(410)의 절곡 중공박스체(430)와 차이가 있음을 알 수 있다.It can be seen that the hollow box body 430 of the side beam 410 is different from the hollow box body 430 of the side beam 410 in that the hollow box body 430 is formed in a shape larger than the height since it is disposed only inside the lateral slab 420.

이에 상기 절곡 중공박스체(430)의 형태는 사각박스체 형태로 형성되는데 내부는 중공부로 형성되도록 하되 미도시 하였지만 내부 브레이싱재등을 더 형성시켜 장경간용에 더욱 적합하도록 할 수도 있다.Accordingly, the bending hollow box body 430 is formed in the shape of a rectangular box body. The hollow box body 430 may be formed as a hollow body, but it may be further formed of an internal bracing material to be more suitable for long span.

또한 도 2a 및 도 2b에 의하면 횡방향 슬래브(420)의 중앙부에 폭보다 높이가 더 큰 절곡 중공박스체(430)가 형성되어 있음을 알 수 있는데 횡방향 슬래브(420)의 횡방향 폭이 커질 경우 중간에 단면높이가 큰 중앙빔(460)이 더 형성되도록 함으로서 횡방향 슬래브(420)의 휨 강성을 보다 효과적으로 확보할 수 있도록 하게 된다.2A and 2B, it can be seen that a folded hollow box body 430 having a height greater than the width is formed at the center of the lateral slab 420, and the lateral width of the lateral slab 420 is increased The central beam 460 having a larger cross-sectional height is formed in the middle, so that the flexural rigidity of the lateral slab 420 can be more effectively secured.

이에 상기 중앙빔(460)은 양 측면빔보다는 단면높이가 작게 형성됨을 알 수 있으며 상기 절곡 중공박스체(430)의 주위에 종방향 긴장재(440)가 역시 배치되어 있음을 알 수 있다.It can be seen that the center beam 460 is formed to have a smaller sectional height than the both side beams and that the longitudinal tension member 440 is also arranged around the folded hollow box body 430.

또한 상기 중앙빔(460)은 교량에 있어 중앙분리부 역할을 하게 되며 양 측면빔(410)과 중앙빔(460)의 사이에 차량등이 통행하게 된다.In addition, the center beam 460 serves as a central separating part in the bridge, and a vehicle or the like passes between the side beams 410 and the center beam 460.

이에 본 발명의 하로교용 강합성 중공세그먼트(400)는 횡방향 슬래브가 양 측면빔의 하부에 위치하게 되므로 하로교용임을 알 수 있으며 경간 사이에 1개의 하로교용 강합성 중공세그먼트(400)가 거치 또는 압출시키는 방식으로 시공하게 된다.Therefore, it can be seen that the steel composite hollow segment 400 for downhole according to the present invention is for downhole since the horizontal slab is located below the both side beams, and one steel composite hollow segment 400 for hang- The construction is carried out by extrusion.

또한 본 발명의 하로교용 강합성 중공세그먼트(400)는 미리 현장에서 제작되는데 각 절곡 중공박스체(430)를 서로 연결 및 구속시켜 주기 위하여 프레임 연결플레이트(470)를 사용하게 된다.In addition, the steel composite hollow segment 400 for downhole according to the present invention is manufactured in advance in the field, and the frame connection plate 470 is used to connect and constrain each of the hollow hollow box bodies 430 to each other.

이러한 프레임 연결플레이트(470)는 절곡 중공박스체(430), 종방향 강재빔(440)과 함께 횡방향 슬래브(420)에 있어 역시 내부철근 역할을 분담하여 본 발명은 횡방향 슬래브(420)와 측면빔(410)에 있어 내부철근의 배근작업을 배제시킬 수 있게 된다.This frame connection plate 470 also plays the role of an inner reinforcement in the transverse slab 420 together with the bending hollow box body 430 and the longitudinal steel beam 440, It is possible to exclude the operation of placing the inner reinforcement in the side beam 410.

이로서 본 발명의 하로교용 강합성 중공세그먼트(400)는 경간 사이에 1개의 세그먼트로 시공함에 따른 자중 감소를 위한 단면 구성으로 최적화 됨에도 휨 강성등을 충분히 확보할 수 있고, 내부철근이 필요 없어 제작도 용이하게 됨을 알 수 있다.Thus, the steel composite hollow segment 400 for downhole according to the present invention is optimized to have a sectional configuration for reducing the weight due to the construction of one segment between the spans, but it is possible to sufficiently secure the flexural rigidity and the like, .

[ 하로교용 강합성 중공세그먼트를 이용한 교량시공공법 ][Bridge Construction Method Using Steel Composite Hollow Segment for Halo Bridge]

도 3a 및 도 3b는 실시예 1에 의한 하로교용 강합성 중공세그먼트(400)를 이용한 교량시공공법의 순서도를 도시한 것이고, 3A and 3B are flowcharts of a bridge construction method using a steel composite hollow segment 400 for downhole according to the first embodiment,

도 4a 및 도 4b는 실시예 2에 의한 하로교용 강합성 중공세그먼트(400)를 이용한 교량시공공법의 순서도를 도시한 것이고,4A and 4B are flowcharts of a bridge construction method using a steel composite hollow segment 400 for downhole according to the second embodiment,

도 5a 및 도 5b는 상기 실시예 2에 있어서 본 발명의 세그먼트 런칭장치의 사시도 및 시공단면도를 도시한 것이다.5A and 5B are a perspective view and a construction sectional view of the segment launching apparatus according to the second embodiment of the present invention.

실시예 1과 실시예 2의 차이는 하로교용 하로교용 강합성 중공세그먼트(400)를 교대, 교각 사이에 인양 및 압출방식을 이용하는 가 여부에 따른 구분이다.The difference between Example 1 and Example 2 is that the steel composite hollow segments 400 for the lowering for the lowering are alternately alternated, and the lifting and pumping method is used between the bridge portions.

[ 실시예 1: 하로교용 강합성 중공세그먼트를 이용한 교량시공공법][Example 1: Construction method of a bridge using a steel composite hollow segment for a hanging bridge]

이에 실시예 1에 의한 시공공법을 살펴보면,In the construction method according to the first embodiment,

먼저 도 3a와 같이 교각(320), 교대(330)를 먼저 시공하고, 인근에서 앞서 살펴본 하로교용 강합성 중공세그먼트(400)를 제작하게 된다.First, as shown in FIG. 3A, a pier bridge 320 and an alternation 330 are first constructed, and the steel composite hollow segment 400 for a hanging bridge as described above is fabricated.

다음으로는 도 3b와 같이 크레인과 같은 인양수단을 이용하여 교각(320), 교대(330) 사이에 거치하는 방식으로 거더교 형태로 시공하게 됨을 알 수 있다.Next, as shown in FIG. 3B, it can be seen that the girder bridge type construction is implemented by mounting the bridge between the bridge pier 320 and the alternation 330 using a lifting means such as a crane.

이러한 방식으로 하로교용 강합성 중공세그먼트(400)를 거치한 후에는 포장층 등을 형성시켜 최종 하로교 시공이 간단하게 완료되도록 하게 된다.After the steel composite hollow segment 400 for hanging is placed in this way, a packing layer or the like is formed to complete the final hanging installation.

[ 실시예 2: 하로교용 강합성 중공세그먼트를 이용한 교량시공공법 ][Example 2: Construction method of a bridge using a steel composite hollow segment for a hanging bridge]

다음으로 실시예 2에 의하면 하로교용 강합성 중공세그먼트(400)를 인양하여 거치할 수 없는 경우로서 교대 등의 작업장에서 미리 하로교용 강합성 중공세그먼트(400)를 제작하고, 교대, 교각 상부로 하로교용 강합성 중공세그먼트(400)를 압출시키는 방식이다.Next, according to the second embodiment, when the steel composite hollow segment 400 for downhole can not be hoisted and can not be mounted, a steel composite hollow segment 400 for a hanging bridge is prepared in advance at a work site such as an alternate, The steel composite hollow segment 400 is extruded.

이에 도 4a와 같이 역시 교각(320), 교대(330)를 먼저 시공하고 교대(330) 후방의 제작장에서 본 발명의 하로교용 강합성 중공세그먼트(400)를 제작하게 된다.As shown in FIG. 4A, the bridge 320 and the alternation 330 are first constructed and the steel composite hollow segment 400 for a hanging bridge according to the present invention is manufactured in the manufacturing site behind the alternation 330.

도 4a와 같이, 교대 후방의 제작장의 업다운 유압실린더(350)는 상기 교대(320) 및 교각(330)의 모서리 부위에 각각 설치되고, 상기 교각(330)의 상부 방향으로 상승시킨다.As shown in FIG. 4A, the up-down hydraulic cylinders 350 at the back of the alternator are respectively installed at the corners of the alternation 320 and the bridge 330 and are raised upward in the bridge 330.

후속적으로, 상기 업다운 유압실린더(350)는 하로교용 강합성 중공세그먼트(400)를거치한 후 하강하여 상기 하로교용 강합성 중공세그먼트(400)를 상기 교각(330) 상의 교좌받침 상에 거치할 수 있다.Subsequently, the up-down hydraulic cylinder 350 receives the steel composite hollow segment 400 for descending and then descends to mount the steel composite hollow segment 400 for descending to the upper surface of the bridge on the bridge 330 .

또한, 상기 업다운 유압실린더(350)는 상기 하로교용 강합성 중공세그먼트(400)가 런칭되기 전에 상기 교대(320) 또는 교각(330)의 모서리 부위에 각각 일시적으로 설치되고, 상기 하로교용 강합성 중공세그먼트(400)가 상기 교각(330)에 모두 설치된 후에 해체되어 회수될 수 있다.The up-down hydraulic cylinder 350 is temporarily installed at the corners of the alternation 320 or the pier 330 before the steel composite hollow segment 400 for the lowering is launched, The segments 400 can be disassembled and recovered after all the bridge columns 330 are installed.

다음으로, 상기 세그먼트 런칭장치(100)를 제1 교각(330a)상에 이송하여 설치한다. 보다 구체적으로, 도 4b에 도시된 바와 같이, 상기 세그먼트 런칭장치(100)는 상기 제작장(500)을 기점으로 하여 상기 교대(320) 또는 교각(330) 상에서 이격된 상태로 전진하여 제1 교각(330a)상으로 이송되어 설치된다. 후술하는 바와 같이, 상기 세그먼트 런칭장치(100)는 전진 및 후진을 반복하면서 적어도 하나 이상의 하로교용 강합성 중공세그먼트(400a, 400b)를 순차적으로 상기 교각(330a, 330b) 상으로 런칭하게 된다.Next, the segment launching apparatus 100 is installed on the first pier 330a. More specifically, as shown in FIG. 4B, the segment launcher 100 advances in a state where it is spaced on the alternate 320 or pier 330 starting from the manufacturing site 500, (330a). As described later, the segment launching apparatus 100 sequentially launches at least one steel composite hollow segment 400a, 400b for descending over the bridge columns 330a, 330b while repeating forward and backward movement.

다음으로, 도 4c에 도시된 바와 같이, 상기 세그먼트 런칭장치(100)의 교량 이송대차(160)를 이용하여 제1 하로교용 강합성 중공세그먼트(400a)를 상기 제1 교각(330a)상으로 이송시킨다.Next, as shown in FIG. 4C, the steel composite hollow segment 400a for the first lowering bridge is transferred onto the first bridge pier 330a by using the bridge transfer bogie 160 of the segment launching apparatus 100 .

다음으로, 상기 업다운 유압실린더(350)를 상승시켜 상기 제1 하로교용 강합성 중공세그먼트(400a)를 거치한 후, 상기 세그먼트 런칭장치(100)를 상기 제작장(500)으로 후진시킨다. 구체적으로, 도 4d에 도시된 바와 같이, 상기 업다운 유압실린더(350)를 상승시켜 상기 제1 하로교용 강합성 중공세그먼트(400a)을 거치한 후, 상기 세그먼트 런칭장치(100)를 상기 제작장(500)으로 후진시킨다.Next, the up-down hydraulic cylinder 350 is raised to place the steel composite hollow segment 400a for first lowering down, and then the segment launching apparatus 100 is moved back to the fabrication site 500. [ 4D, after the up-down hydraulic cylinder 350 is lifted to mount the steel composite hollow segment 400a for the first lowering, the segment launching apparatus 100 is moved to the manufacturing site 500).

즉, 상기 세그먼트 런칭장치(100)는 상기 하로교용 강합성 중공세그먼트(400)가 거치되지 않은 상태에서 상기 교각(330)까지 전진하여 고정되고, 상기 교량 이송대차(160)를 통해 상기 하로교용 강합성 중공세그먼트(400)를 운반하며, 상기 하로교용 강합성 중공세그먼트(400)가 상기 교각(330) 상에 설치된 후에 상기 제작장(500)으로 후진하게 된다.That is, the segment launching apparatus 100 advances to and is fixed to the pier 330 in a state where the steel composite hollow segment 400 for hanging is not mounted, The composite hollow segment 400 is moved back to the fabrication site 500 after the steel composite hollow segment 400 for hanging is installed on the bridge 330.

도 5a 및 도 5b를 참조하면, 상기 세그먼트 런칭장치(100)는, 프레임(110), 구동부(120), 런칭장비 고정장치(130), 런칭장비 운전장치(140), 구동엔진(150), 교량 이송대차(160), 유압실린더 취부장치(170), 통로용 사다리(180), 대차 구동장치(190), 런칭장비 이송장치(210), 대차 정지 스토퍼(220), 교량 정착부(230), 유압실린더 취부장치 회전체(240), 호이스트 크레인(250) 및 프레임 연결부(260)를 포함할 수 있다.5A and 5B, the segment launching apparatus 100 includes a frame 110, a driving unit 120, a launching equipment fixing unit 130, a launching equipment operation unit 140, a driving engine 150, The bridge conveyance truck 160, the hydraulic cylinder mounting apparatus 170, the passageway ladder 180, the truck driving apparatus 190, the launching equipment conveying apparatus 210, the bogie stopper 220, the bridge fixing unit 230, A hydraulic cylinder mounting device rotation body 240, a hoist crane 250, and a frame connection portion 260. [

상기 프레임(110)은 상기 제작장(500)으로부터 전진 및 후진이 가능하도록 연장 설치되고, 구동부(120)는 상기 프레임(110) 상에 설치된다.The frame 110 is extended and extended from the fabrication site 500 to be movable forward and backward and the driving unit 120 is installed on the frame 110.

상기 런칭장비 고정장치(130)는 상기 프레임(110)의 전단에 설치되고, 유압실린더에 의해 구동되어 상기 프레임(110)을 상기 교각(330)상에 고정시킨다.The launching equipment fixing device 130 is installed at a front end of the frame 110 and is driven by a hydraulic cylinder to fix the frame 110 on the bridge 330.

상기 구동엔진(150)은 상기 프레임(110)의 양단에 설치되고, 런칭장비 운전장치(140)는 상기 프레임(110)의 전단에 설치되어 상기 프레임(110)이 상기 구동엔진(150)에 의해 상기 제작장(500)으로부터 전진 및 후진할 수 있도록 운전을 제어한다. The driving engine 150 is installed at both ends of the frame 110 and the launching equipment operation device 140 is installed at a front end of the frame 110 so that the frame 110 is rotated by the driving engine 150 And controls operation so as to move forward and backward from the fabrication site 500.

상기 교량 이송대차(160)는 상기 세그먼트 런칭장치(100) 상부에 설치되어 상기 하로교용 강합성 중공세그먼트(400)를 상기 교각(330) 상으로 운반하며, 대차 구동장치(190)는 상기 프레임(110) 상에서 상기 교량 이송대차(160)가 이송될 수 있도록 구동하고, 이때, 대차 정지 스토퍼(220)는 상기 프레임(110) 상에 설치되어 상기 교량 이송대차(160)를 소정 위치에서 정지시키는 역할을 하고, 교량 정착부(230)는 상기 하로교용 강합성 중공세그먼트(400)가 상기 교량 이송대차(160) 상에 정착되도록 상기 교량 이송대차(160)의 상측 단부에 형성된다.The bridge conveying bogie 160 is installed on the segment launching apparatus 100 to convey the steel composite hollow segment 400 for hanging onto the pier 330. The balancer driving device 190 is installed on the frame The bridge stopper stopper 220 is installed on the frame 110 to stop the bridge conveyance truck 160 at a predetermined position so as to stop the bridge conveyance truck 160. [ And the bridge fixing unit 230 is formed at the upper end of the bridge conveyance truck 160 so that the steel composite hollow segment 400 for the lowering is fixed on the bridge conveyance truck 160. [

상기 유압실린더 취부장치(170)는 상기 런칭장비 고정장치(130)를 상승 및 하강시키는 유압실린더가 취부되고, 유압실린더 취부장치 회전체(240)는 상기 유압실린더 취부장치(170)를 회전시키는 역할을 한다.The hydraulic cylinder attaching device 170 is mounted with a hydraulic cylinder for raising and lowering the launching equipment fixing device 130 and the hydraulic cylinder attaching device rotation body 240 rotates the hydraulic cylinder attaching device 170 .

또한, 세그먼트 런칭장치(100)의 하부에 런칭장비 이송장치(210), 호이스트 크레인(250) 및 프레임 연결부(260)가 형성될 수 있다.Further, a launching equipment transfer device 210, a hoist crane 250 and a frame connecting part 260 may be formed below the segment launching device 100.

다음으로, 도 4e에 도시된 바와 같이, 상기 제1 하로교용 강합성 중공세그먼트(400a)를 거치하고 있는 상기 업다운 유압실린더(350)를 하강시킨다.Next, as shown in FIG. 4E, the up-down hydraulic cylinder 350, which rests on the steel composite hollow segment 400a for downhole, is lowered.

다음으로, 도 4f에 도시된 바와 같이, 상기 제1 하로교용 강합성 중공세그먼트(400a)를 상기 제1 교각(330a)상에 설치한다.Next, as shown in FIG. 4F, the steel composite hollow segment 400a for the first lowering hanging is installed on the first bridge pier 330a.

다음으로, 도 4g에 도시된 바와 같이, 상기 제작장(500)으로부터 상기 세그먼트 런칭장치(100)를 제2 교각(330b)상으로 이송하여 설치한다. Next, as shown in FIG. 4G, the segment launching apparatus 100 is transferred from the manufacturing site 500 onto the second pier 330b.

다음으로, 도 4h에 도시된 바와 같이, 상기 세그먼트 런칭장치(100)의 교량 이송대차(160)를 이용하여 제2 하로교용 강합성 중공세그먼트(400b)를 상기 제2 교각(330b)으로 이송한다. Next, as shown in FIG. 4H, the steel composite hollow segment 400b for second lowering is transferred to the second bridge 330b using the bridge conveyance truck 160 of the segment launching apparatus 100 .

다음으로, 도 4i에 도시된 바와 같이, 상기 세그먼트 런칭장치(100)를 상기 제작장(500)으로 후진시킨다.Next, as shown in FIG. 4I, the segment launching apparatus 100 is moved back to the fabrication site 500.

다음으로, 도 4j에 도시된 바와 같이, 상기 제2 하로교용 강합성 중공세그먼트(400b)를 거치하고 있는 업다운 유압실린더(350)를 하강하여 상기 제2 하로교용 강합성 중공세그먼트(400b)를 상기 제2 교각(330b) 상에 설치한다.Next, as shown in FIG. 4J, the up-down hydraulic cylinder 350 on which the steel composite hollow segment 400b for downhole is placed is lowered to remove the steel composite hollow segment 400b for the second fall- And is installed on the second pier 330b.

결국, 본 발명의 실시예 2에 따르면, 업다운 유압실린더가 하로교용 강합성 중공세그먼트를 교각 상에 거치하고, 세그먼트 런칭장치가 교량 제작장으로부터 전진 및 후진을 반복하면서 적어도 하나 이상의 하로교용 강합성 중공세그먼트를 순차적으로 교각 상으로 간편하게 런칭할 수 있고, 이에 따라 종래의 기술에 따른 가설벤트 또는 대형 빔 런처를 사용하지 않아도 되며, 특히, 경간의 수가 적은 소형 또는 중형 교량의 시공에 유용하게 적용할 수 있다.As a result, according to the second embodiment of the present invention, the up-down hydraulic cylinder mounts the steel composite hollow segment for the downhill on the bridge pier, and the segment launching device repeatedly advances and reverses from the bridge production site, It is possible to easily launch the segments sequentially in the form of a pier, thereby avoiding the use of a conventional venting vent or a large beam launcher according to the prior art. In particular, the present invention can be applied to the construction of a small- or medium- have.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.It will be understood by those skilled in the art that the foregoing description of the present invention is for illustrative purposes only and that those of ordinary skill in the art can readily understand that various changes and modifications may be made without departing from the spirit or essential characteristics of the present invention. will be. It is therefore to be understood that the above-described embodiments are illustrative in all aspects and not restrictive. For example, each component described as a single entity may be distributed and implemented, and components described as being distributed may also be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is defined by the appended claims rather than the detailed description and all changes or modifications derived from the meaning and scope of the claims and their equivalents are to be construed as being included within the scope of the present invention do.

100: 세그먼트 런칭장치
110: 프레임 120: 구동부
130: 런칭장비 고정장치 140: 런칭장비 운전장치
150: 구동엔진 160: 교량 이송대차
170: 유압실린더 취부장치 180: 통로용 사다리
190: 대차 구동장치
210: 런칭장비 이송장치 220: 대차 정지 스토퍼
230: 교량 정착부 240: 유압실린더 취부장치 회전체
250: 호이스트 크레인 260: 프레임 연결부
400: 하로교용 강합성 중공세그먼트
400a: 제1 하로교용 강합성 중공세그먼트
400b: 제2 하로교용 강합성 중공세그먼트
410: 측면빔 420: 횡방향 슬래브
430: 절곡 중공박스체 440: 종방향 긴장재
450: 종방향 강재빔 460: 중앙빔
470: 프레임 연결플레이트 500: 제작장
100: Segment launching device
110: frame 120:
130: launching equipment fixing device 140: launching equipment operation device
150: drive engine 160: bridge conveyance truck
170: hydraulic cylinder mounting device 180: ladder for passage
190: Balance drive device
210: launching equipment feeder 220: bogie stopper
230: bridge fixing part 240: hydraulic cylinder mounting device rotation body
250: Hoist crane 260: Frame connection
400: steel composite hollow segment for hanging
400a: Steel composite hollow segment for first lowering
400b: Steel composite hollow segment for second lowering
410: side beam 420: transverse slab
430: Bent hollow box body 440: Longitudinal tension member
450: longitudinal steel beam 460: center beam
470: Frame connection plate 500: Production line

Claims (9)

절곡된 강판을 조립하여 중공부(S)가 형성되도록 제작된 박스체로서 종방향으로 연장되도록 배치된 절곡 중공박스체(430); 및 상기 절곡 중공박스체(430) 주위에 배치된 종방향 긴장재(440);를 포함하여 콘크리트로 제작된 양 측면빔(410); 및
상기 양 측면빔(410) 하부 내측 사이에 횡방향으로 연장되도록 형성된 것으로서 종방향으로 연장되도록 배치된 절곡 중공박스체(430); 상기 절곡 중공박스체(430) 사이 사이에 배치된 종방향 강재빔(450);을 포함하여 콘크리트로 제작된 횡방향 슬래브(420);을 포함하는 하로교용 강합성 중공세그먼트.
A folded hollow box body 430 arranged to extend in a longitudinal direction as a box body manufactured to form a hollow portion S by assembling a bent steel plate; And a longitudinal tensional material (440) disposed about the folded hollow box body (430); And
A bending hollow box body 430 formed to extend in the transverse direction between the lower inside of the both side beams 410 and to extend in the longitudinal direction; And a transverse slab (420) made of concrete including a longitudinal steel beam (450) disposed between the folded hollow box bodies (430).
제 1항에 있어서,
상기 콘크리트로 제작된 양 측면빔과 횡방향 슬래브 내부에 형성되는 것으로서 절곡 중공박스체(430)의 위치를 구속하도록 절곡 중공박스체(430) 사이사이에 브레이싱재를 포함하는 프레임 연결플레이트(470)가 더 설치되도록 하는 하로교용 강합성 중공세그먼트.
The method according to claim 1,
A frame connecting plate 470 including a bracing material is disposed between the bent hollow box body 430 and the bending hollow box body 430 to constrain the positions of the bent hollow box body 430, To be installed on the upper surface of the hollow synthetic rubber sheet.
제 1항에 있어서,
상기 횡방향 슬래브(420) 중간에는 절곡된 강판을 조립하여 중공부(S)가 형성되도록 제작된 박스체로서 종방향으로 연장되도록 배치된 절곡 중공박스체(430); 및 상기 절곡 중공박스체(430) 주위에 배치된 종방향 긴장재(440);를 포함하여 콘크리트로 제작된 중앙빔(460)이 더 형성되도록 하는 하로교용 강합성 중공세그먼트.
The method according to claim 1,
A folded hollow box body 430 arranged to extend in the longitudinal direction as a box body manufactured to form a hollow portion S by assembling a bent steel plate in the middle of the lateral slab 420; And a longitudinal tensional material (440) disposed about the folded hollow box body (430) to form a central beam (460) made of concrete.
절곡된 강판을 조립하여 중공부(S)가 형성되도록 제작된 박스체로서 종방향으로 연장되도록 배치된 절곡 중공박스체(430);와 상기 절곡 중공박스체(430) 주위에 배치된 종방향 긴장재(440);를 포함하여 콘크리트로 제작된 양 측면빔(410); 상기 양 측면빔(410) 하부 내측 사이에 횡방향으로 연장되도록 형성된 것으로서 종방향으로 연장되도록 배치된 절곡 중공박스체(430); 상기 절곡 중공박스체(430) 사이사이에 배치된 종방향 강재빔(450);과 상기 콘크리트로 제작된 양 측면빔과 횡방향 슬래브 내부에 형성되는 것으로서 절곡 중공박스체(430)의 위치를 구속하도록 절곡 중공박스체(430) 사이사이에 브레이싱재를 포함하는 프레임 연결플레이트(470);를 포함하는 횡방향슬래브(420);를 포함하도록 하로교용 강합성 중공세그먼트(400)를 제작하는 단계; 및
상기 제작된 하로교용 강합성 중공세그먼트(400)를 교각과 교대에 거치하여 서로 종방향으로 연결하는 단계를 포함하는 하로교용 강합성 중공세그먼트를 이용한 교량시공공법.
A folded hollow box body 430 arranged to extend in the longitudinal direction as a box body manufactured by assembling a bent steel plate to form a hollow portion S and a vertical tension member 430 disposed around the folded hollow box body 430, Side beam 410 made of concrete including the beam 440; A bending hollow box body 430 formed to extend in the transverse direction between the lower inside of the both side beams 410 and to extend in the longitudinal direction; A longitudinal steel beam 450 disposed between the folded hollow box bodies 430, and both side beams made of the concrete, and a hollow hollow box body 430 formed inside the lateral slabs, Fabricating a steel composite hollow segment (400) for downhole to include a horizontal slab (420) including a frame connection plate (470) including a bracing material between the folded hollow box bodies (430); And
And a step of vertically connecting the prepared steel composite hollow segments for hanging bridge 400 with the piers at alternate angles to each other in a longitudinal direction.
하로교용 강합성 중공세그먼트(400)를 교각(330) 상에 런칭(Launching)시키는 교량 런칭장비를 이용한 하로교 시공공법에 있어서,
a) 업다운 유압실린더(350)를 제1 및 제2 교각(330a, 330b)에 설치하고, 교량 제작장(500)으로부터 교량 런칭장비(100)를 투입하는 단계;
b) 상기 교량 런칭장비(100)를 제1 교각(330a)상에 이송하여 설치하는 단계;
c) 상기 교량 런칭장비(100)의 교량 이송대차(160)를 이용하여 상기 하로교용 강합성 중공세그먼트(400)에서 제1 하로교용 강합성 중공세그먼트(400a)을 상기 제1 교각((330a)상으로 이송하는 단계;
d) 상기 업다운 유압실린더(350)를 상승시켜 상기 제1 하로교용 강합성 중공세그먼트(400a)을 거치한 후, 상기 교량 런칭장비(100)를 상기 제작장(500)으로 후진시키는 단계;
e) 상기 제1 하로교용 강합성 중공세그먼트(400a)을 거치하고 있는 상기 업다운 유압실린더(350)를 하강시키는 단계;
f) 상기 제1 하로교용 강합성 중공세그먼트(400a)을 상기 제1 교각(330a)상에 설치하는 단계;
g) 상기 제작장(500)으로부터 상기 교량 런칭장비(100)를 제2 교각(330b)상으로 이송하여 설치하는 단계;
h) 상기 교량 런칭장비(100)의 교량 이송대차(160)를 이용하여 상기 하로교용 강합성 중공세그먼트(400) 중에서 제2 하로교용 강합성 중공세그먼트(400b)을 상기 제2 교각(330b)으로 이송하는 단계;
i) 상기 교량 런칭장비(100)를 상기 제작장(500)으로 후진시키는 단계; 및
j) 상기 제2 하로교용 강합성 중공세그먼트(400b)을 거치하고 있는 업다운 유압실린더(350)를 하강하여 상기 제2 하로교용 강합성 중공세그먼트(400b)을 상기 제2 교각(330b) 상에 설치하는 단계
를 포함하되,
상기 교량 런칭장비(100)는 상기 제작장(500)을 기점으로 하여 상기 교대(320) 또는 교각(330) 상에서 이격된 상태로 전진 및 후진을 반복하면서 적어도 하나 이상의 하로교용 강합성 중공세그먼트(400a, 400b)을 순차적으로 상기 교각(330a, 330b) 상으로 런칭 하는 하로교용 강합성 중공세그먼트를 이용한 교량시공공법.
In a hanging bridge construction method using a bridge launching equipment for launching a steel composite hollow segment for a hanging bridge (400) on a bridge pier (330)
a) installing the up-down hydraulic cylinder 350 at the first and second bridge columns 330a and 330b and inputting the bridge launching equipment 100 from the bridge manufacturing site 500;
b) transferring and installing the bridge launching equipment (100) on the first pier (330a);
c) using the bridge conveyance truck 160 of the bridge launching equipment 100, the steel composite hollow segment 400a for the first lowering bridging is transferred from the steel composite hollow segment 400 for the lowering bridge to the first bridge pier 330a, Lt; / RTI >
d) moving the up-down hydraulic cylinder 350 up to the steel composite hollow segment 400a for the first lowering and then backing the bridge launching equipment 100 to the fabrication site 500;
e) lowering the up-down hydraulic cylinder (350) resting on the steel composite hollow segment (400a) for the first lowering down;
f) installing the steel composite hollow segment (400a) for the first lowering over the first bridge pier (330a);
g) transferring the bridge launching equipment (100) from the fabrication site (500) onto a second bridge pier (330b) and installing it;
h) Using the bridge conveyance truck 160 of the bridge launching equipment 100, the steel composite hollow segment 400b for the second lowering bridge among the steel composite hollow segments 400 for the lowering is connected to the second bridge pier 330b ;
i) backing the bridge launching equipment (100) to the fabrication site (500); And
j) The up-down hydraulic cylinder 350 on which the steel composite hollow segment 400b for downhole is placed is lowered so that the steel composite hollow segment 400b for the second lowering down is installed on the second bridge 330b Step
, ≪ / RTI &
The bridge launching equipment 100 is configured to move at least one steel composite hollow segment 400a for downhole while repeatedly advancing and retreating in a state of being separated on the alternate 320 or bridge 330 starting from the manufacturing site 500 , And 400b are sequentially launched onto the bridge columns (330a, 330b) using a steel composite hollow segment for downhole.
제5항에 있어서,
상기 a) 단계의 업다운 유압실린더(350)는 상기 교각(330)의 모서리 부위에 각각 설치되고, 상기 교각(330)의 상부 방향으로 상승하여 하로교용 강합성 중공세그먼트(400)을 거치한 후 하강하여 상기 하로교용 강합성 중공세그먼트(400)을 상기 교각(330) 상의 교좌받침(340) 상에 거치하는 하로교용 강합성 중공세그먼트를 이용한 교량시공공법.
6. The method of claim 5,
The up-down hydraulic cylinder 350 in the step a) is installed at each corner of the bridge pier 330 and rises upward in the bridge pier 330 to mount the steel composite hollow segment 400 for down- And a steel composite hollow segment for hanging is mounted on the concrete support base 340 on the bridge pier 330. [
제6항에 있어서,
상기 업다운 유압실린더(350)는 상기 하로교용 강합성 중공세그먼트(400)가 런칭되기 전에 상기 교대(320) 또는 교각(330)의 모서리 부위에 각각 일시적으로 설치되고, 상기 하로교용 강합성 중공세그먼트(400)가 상기 교각(330)에 모두 설치된 후에 해체되어 회수되는 하로교용 강합성 중공세그먼트를 이용한 교량시공공법.
The method according to claim 6,
The up-down hydraulic cylinder 350 is temporarily installed at each of the corners of the alternate 320 or pier 330 before the steel composite hollow segment 400 for lowering is launched, and the steel composite hollow segment for down- 400 are installed in the bridge pier 330 and then disassembled and recovered, the bridging construction method using the steel composite hollow segment for downhole.
제5항에 있어서,
상기 교량 런칭장비(100)는 상기 하로교용 강합성 중공세그먼트(400)이 거치되지 않은 상태에서 상기 교각(330)까지 전진하여 고정되고, 상기 교량 이송대차(160)를 통해 상기 하로교용 강합성 중공세그먼트(400)을 운반하며, 상기 하로교용 강합성 중공세그먼트(400)이 상기 교각(330) 상에 설치된 후에 상기 제작장(500)으로 후진하는 하로교용 강합성 중공세그먼트를 이용한 교량시공공법.
6. The method of claim 5,
The bridge launching equipment 100 is advanced and fixed to the pier 330 in a state where the steel composite hollow segment 400 for hanging is not mounted, A method of constructing a bridge using a steel composite hollow segment for hauling that carries a segment (400) and moves back to the fabrication site (500) after the steel composite hollow segment (400) for hanging is installed on the bridge pier (330).
제 4항 또는 제 5항에 있어서,
상기 하로교용 강합성 중공세그먼트(400)는 횡방향 슬래브(420) 중간에 절곡된 강판을 조립하여 중공부(S)가 형성되도록 제작된 박스체로서 종방향으로 연장되도록 배치된 절곡 중공박스체(430); 및 상기 절곡 중공박스체(430) 주위에 배치된 종방향 긴장재(440);를 포함하여 콘크리트로 제작된 중앙빔이 더 형성된 되도록 제작된 것인 하로교용 강합성 중공세그먼트를 이용한 교량시공공법.
The method according to claim 4 or 5,
The steel composite hollow segment 400 for downhole is formed by assembling a steel plate bent in the middle of the transverse slab 420 to form a hollow portion S and a bent hollow box body 430); And a longitudinal tensional material (440) disposed around the folded hollow box body (430). The bridge construction method using the steel composite hollow segment for downhole, wherein the central beam is made of concrete.
KR1020140057240A 2014-05-13 2014-05-13 Steel and concrete composite segment for through bridge, and bridge construction method using the same KR20150130099A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140057240A KR20150130099A (en) 2014-05-13 2014-05-13 Steel and concrete composite segment for through bridge, and bridge construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140057240A KR20150130099A (en) 2014-05-13 2014-05-13 Steel and concrete composite segment for through bridge, and bridge construction method using the same

Publications (1)

Publication Number Publication Date
KR20150130099A true KR20150130099A (en) 2015-11-23

Family

ID=54844618

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140057240A KR20150130099A (en) 2014-05-13 2014-05-13 Steel and concrete composite segment for through bridge, and bridge construction method using the same

Country Status (1)

Country Link
KR (1) KR20150130099A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507146A (en) * 2015-11-27 2016-04-20 中铁大桥勘测设计院集团有限公司 Glass bridge floor stiffening girder used for pedestrian suspension bridge
CN105625193A (en) * 2016-03-14 2016-06-01 中铁二十四局集团安徽工程有限公司 Whole-span cast-in-place beam inverted-triangle formwork supporting frame and construction method thereof
CN109853358A (en) * 2019-01-24 2019-06-07 西安公路研究院 A kind of Very Low Clearance precast assembly integration UHPC spill beam bridge and its construction method
CN110373997A (en) * 2019-04-19 2019-10-25 中铁宝桥集团有限公司 The production method and moulding bed of curve plate girder segment
CN110409319A (en) * 2019-08-16 2019-11-05 中铁十四局集团第三工程有限公司 A kind of cast-in-place floorings bracket of large span steel reinforced concrete combination beam and construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105507146A (en) * 2015-11-27 2016-04-20 中铁大桥勘测设计院集团有限公司 Glass bridge floor stiffening girder used for pedestrian suspension bridge
CN105625193A (en) * 2016-03-14 2016-06-01 中铁二十四局集团安徽工程有限公司 Whole-span cast-in-place beam inverted-triangle formwork supporting frame and construction method thereof
CN109853358A (en) * 2019-01-24 2019-06-07 西安公路研究院 A kind of Very Low Clearance precast assembly integration UHPC spill beam bridge and its construction method
CN110373997A (en) * 2019-04-19 2019-10-25 中铁宝桥集团有限公司 The production method and moulding bed of curve plate girder segment
CN110409319A (en) * 2019-08-16 2019-11-05 中铁十四局集团第三工程有限公司 A kind of cast-in-place floorings bracket of large span steel reinforced concrete combination beam and construction method
CN110409319B (en) * 2019-08-16 2021-02-23 中铁十四局集团第三工程有限公司 Bracket for large-span steel-concrete composite beam cast-in-place bridge deck and construction method

Similar Documents

Publication Publication Date Title
KR101394193B1 (en) Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type
KR101654742B1 (en) Movable scaffolding system mounted upper-structure of bridge and bridge construction method therewith
KR20150130099A (en) Steel and concrete composite segment for through bridge, and bridge construction method using the same
CA2594158A1 (en) Bridge construction system and method
KR101214602B1 (en) Incremental launching apparatus for constructing rail-type concrete slab of composite bridge using shearing connector rail, and method for the same
KR20180009902A (en) Railcar travelling on bridge girders for carrying precast slabs and construction method for placing precast slabs using the railcar
CN105735101A (en) High-speed railway rush repair beam capable of being converted into permanent bridge structure, and rush repair method of high-speed railway rush repair beam
KR101228593B1 (en) Composite girder using inner molding member and bridge construction method therwith
KR101347113B1 (en) Incremental launching apparatus for constructing shearing pocket-type concrete slab of composite bridge
KR101551451B1 (en) Steel plate girder improved coner fixing capacity and rahmen or box type structure construction method using the same
JPH0841826A (en) Erection method of bridge and equipment thereof and main girder unit
KR101104298B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
CN110761185A (en) Prestress assembly type track beam for station and construction method thereof
KR101230049B1 (en) Incremental launching apparatus for launching concrete slab for bridge using form and rail, and constructing method for the same
KR101219788B1 (en) Method for constructing precast concrete floor plate for bridge with introducing compressive force using hydraulic jack
KR100981982B1 (en) Precast coping lifting system
KR101527752B1 (en) Construction method of prestressed composite girder bridge
KR101223753B1 (en) Incremental launching apparatus for launching concrete slab of tunnel type for composite bridge, and constructing method for the same
KR101607485B1 (en) Curved-psc girder with outrigger and curved-psc girder bridge construction method therewith
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
KR101958862B1 (en) Continuous concrete girder and bridge structure using the same
KR101043710B1 (en) Through bridge construction method by side beam and slab by box structure without lateral prestressing
KR100889140B1 (en) The assembly type hollow slab
KR20120054832A (en) Fcm construction method using i-girder
KR20190018775A (en) Railcar travelling on bridge girders for carrying precast slabs and construction method for placing precast slabs using the railcar

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right