KR20130090596A - Eco-composite type steel temporary construction and construction method thereof - Google Patents

Eco-composite type steel temporary construction and construction method thereof Download PDF

Info

Publication number
KR20130090596A
KR20130090596A KR1020120011847A KR20120011847A KR20130090596A KR 20130090596 A KR20130090596 A KR 20130090596A KR 1020120011847 A KR1020120011847 A KR 1020120011847A KR 20120011847 A KR20120011847 A KR 20120011847A KR 20130090596 A KR20130090596 A KR 20130090596A
Authority
KR
South Korea
Prior art keywords
eco
sheet pile
support
friendly
order wall
Prior art date
Application number
KR1020120011847A
Other languages
Korean (ko)
Other versions
KR101380782B1 (en
Inventor
박기경
Original Assignee
지더블유이엔씨 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 지더블유이엔씨 주식회사 filed Critical 지더블유이엔씨 주식회사
Priority to KR1020120011847A priority Critical patent/KR101380782B1/en
Publication of KR20130090596A publication Critical patent/KR20130090596A/en
Application granted granted Critical
Publication of KR101380782B1 publication Critical patent/KR101380782B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0051Including fibers
    • E02D2300/0065Including fibers made from textile
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0051Including fibers
    • E02D2300/0067Including fibers made from cellulose

Abstract

PURPOSE: An environmentally friendly riverside structure and a construction method thereof are provided to prevent environmental contamination without using cement and to construct the nature friendly structure using red clay. CONSTITUTION: An environmentally friendly riverside structure comprises struts (100), sheet piles (200), and cutoff collars. The struts are embedded into a bedrock layer (R). The sheet piles are embedded to the top of the bedrock layer or into a weathered rock layer and are arranged in front of the struts. The cutoff collars are installed between the struts on the bottom of the sheet piles and are composed of cementless red clay composites. The cementless red clay composites are composed of red clay powder, quicklime, and granite soil.

Description

친환경 복합형 강가시설 및 그 시공방법 {ECO-COMPOSITE TYPE STEEL TEMPORARY CONSTRUCTION AND CONSTRUCTION METHOD THEREOF}Eco-friendly complex riverside facility and construction method {ECO-COMPOSITE TYPE STEEL TEMPORARY CONSTRUCTION AND CONSTRUCTION METHOD THEREOF}

본 발명은 교각기초, 지하차도, 완충저류조시설등의 지하구조물을 축조하기 위하여 임시로 설치하는 가시설에 관한 것으로서, 구체적으로는 시멘트 콘크리트를 전혀 첨가하지 않아서 환경 오염을 방지하고, 견고하며, 토사 누출 또는 누수를 예방할 수 있는 차수벽을 가진 강가시설을 구축할 수 있도록 하는 친환경 복합형 강가시설 및 그 시공방법에 관한 것이다.
The present invention relates to temporary installations for temporarily constructing underground structures such as bridge foundations, underground roadways, and buffer storage tank facilities. The present invention also relates to an environment-friendly complex riverside facility and a construction method for constructing a riverside facility having a water barrier to prevent leakage.

흙막이벽은 교각의 기초 및 각종 구조물 등의 지반을 건설하기 위하여 터파기한 내부로 물 및 토사 등이 침투되는 것을 막기 위해 설치되는 것으로, 목조를 이용한 토류판을 설치하여 흙막이벽을 형성하는 것이 일반적이었다. 그러나 상기 목조에 의한 토류판은 목조가 시간이 지나면서 물에 의한 부식 및 변형 등의 문제가 발생함에 따라 흙막이벽의 붕괴 또는 물 등의 누수가 발생하는 문제가 있었고, 이를 위해 시트파일을 이용하여 흙막이벽을 형성하는 기술이 개발되었다.The retaining wall is installed to prevent the penetration of water and earth and sand into the excavated interior in order to construct foundations of piers and various structures, and it is common to form a retaining wall by installing earthen boards using wooden blocks. However, the earthen board made of wood had problems such as collapse of soil wall or leakage of water as problems such as corrosion and deformation caused by water occurred over time. Techniques for forming walls have been developed.

상기 시트파일을 이용한 흙막이벽은 벽체가 견고하고 재사용에 적합하며, 다수개의 시트파일이 간단한 결합구조에 의해 연속적으로 연결되어 설치될 수 있어 제작 및 설치가 용이하다는 장점이 있다. 그러나 시트파일은 강성이 취약한 판상구조라는 한계점 때문에 경암 등의 단단한 지층까지 항타하기 곤란한 문제점이 있다.The wall wall using the sheet pile has the advantage that the wall is solid and suitable for reuse, and that a plurality of sheet piles can be continuously connected and installed by a simple coupling structure, making it easy to manufacture and install. However, the sheet pile has a problem in that it is difficult to hit hard strata such as hard rock due to the limitation of weak stiffness.

이에 본 발명인은 2004년 '교각 직접 기초 가시설 및 그 시공방법(특허 제637899호)'을 개발한 바 있다. 상기의 선행기술은 암반의 표면 내지는 풍화암의 일정부분까지만 시트파일을 근입시키고, 상기 시트파일의 전면에서 지지층인 암반의 일정 깊이까지 H 파일 등의 지주를 근입시켜 상기 시트파일을 지지토록 하며, 상기 시트파일의 하단면을 중심으로 차수벽을 설치하는 것을 특징으로 한다.Accordingly, the present inventors have developed the 'pier direct foundation temporary installation and construction method thereof (Patent No. 637899) in 2004. The prior art is to infiltrate the sheet pile only up to a certain portion of the surface of the rock or weathered rock, and to support the sheet pile by incorporating a strut such as an H file from the front of the sheet pile to a predetermined depth of the rock, which is a supporting layer. Characterized in that the order wall is installed around the bottom surface of the sheet pile.

이로 인하여 상기 선행기술은 종래의 재래식 공법보다 공기를 대폭 단축시킬 수 있어 공사비용을 60%이상 절감시키는 효과를 발휘하였으나, 시공상 시트파일과 지주 사이에 간격이 발생하게 되고, 이러한 간격은 시트파일과 지주가 토압 등에 대하여 일체로 거동하지 못하고 개별적으로 거동함에 따라 구조적인 안정성에 한계가 있었다. Due to this, the prior art can significantly shorten the air compared to the conventional method, thereby reducing the cost of construction by more than 60%, but there is a gap between the seat pile and the prop in construction, such a gap is the seat pile There was a limit in the structural stability as the and landlords did not behave at all against earth pressure, but individually.

상기 문제를 해결하기 본 발명인은 또다시 '복합형 강가시설 및 그 시공방법(특허 제0884289호)'를 개발한 바 있다. 상기 선행기술은 도 1에 도시된 바와 같이, 지주와 시트파일 간에 띠장을 설치하여, 지주가 시트파일을 견고하게 지지할 수 있는 방법을 제시하고 있다. 구체적으로 상기 시트파일과 지주간의 결합을 견고히 하기 위하여, 시트파일과 띠장을 지지부재로 결합하고, 지주와 시트파일을 합성연결부재로 결합함으로써 시트파일, 띠장 및 지주가 하나의 구조체로써 거동하게 하여 구조적인 강성을 극대화시키고 있다. 다른 한편으로 시트파일의 하단부와 암반층의 상단 사이에 토류판(62)을 설치하고 상기 시트파일과 토류판 사이에 시멘트 몰탈(64)을 타설하여 차수벽을 형성시킴으로써, 시트파일 하단부에 대한 차수기능을 갖도록 함과 아울러 시멘트 몰탈의 강도를 이용하여 시트파일의 하단부가 토압에 의해 앞으로 밀리는 것을 방지하도록 하고 있다.In order to solve the above problems, the present inventors have again developed a 'composite river construction facility and its construction method (Patent No. 0884289)'. As shown in FIG. 1, the prior art proposes a method in which a belt is installed between the support post and the seat pile so that the support pillar can firmly support the seat pile. Specifically, in order to secure the coupling between the sheet pile and the support, the seat pile and the belt are combined with the supporting member, and the support and the sheet pile are combined with the synthetic connecting member so that the sheet file, the belt and the support behave as a single structure. The structural rigidity is maximized. On the other hand, by installing a soil plate 62 between the lower end of the sheet pile and the upper end of the rock layer and the cement mortar 64 is formed between the sheet pile and the soil plate to form a water barrier wall, to have the order function for the lower portion of the sheet pile In addition, by using the strength of the cement mortar to prevent the lower end of the sheet pile is pushed forward by the earth pressure.

그러나 상기 시멘트 또는 콘크리트를 이용하여 차수벽을 형성하는 방식은 시멘트 몰탈 또는 콘크리트에서 발생하는 6가 크롬, 암모니아, 라돈 및 기타 환경오염 물질로 인한 환경문제를 유발한다는 문제가 있다. 시멘트 몰탈 또는 콘크리트를 차수벽으로 이용하는 경우에는 차수벽의 해체가 용이하지 않아 내부 구조 공사 후 상기 가시설을 그대로 토사로 매립하는 경우가 많은데, 이 때 상기 시멘트 또는 콘크리트에 의한 환경문제가 발생되고, 많은 비용을 들여 상기 차수벽을 철거하더라도 시멘트 등을 폐기하는데 따른 환경오염의 문제가 여전히 존재하게 된다.
However, the method of forming the order wall using the cement or concrete has a problem that causes environmental problems due to hexavalent chromium, ammonia, radon and other environmental pollutants generated in the cement mortar or concrete. When cement mortar or concrete is used as the order wall, it is not easy to dismantle the order wall, so the temporary facility is often landfilled with earth and sand after the internal structure construction. Even if the order wall is removed, there is still a problem of environmental pollution due to the disposal of cement.

본 발명은 상기 종래기술이 가지는 문제점을 해결하기 위한 것으로서, 시멘트 콘크리트 몰탈을 사용함으로써 발생할 수 있는 환경오염을 예방하기 위해, 시멘트를 전혀 사용하지 않고, 황토를 주재료로 사용한 친환경 복합형 강가시설의 구조 및 그 시공방법을 제공하고자 한다.The present invention is to solve the problems of the prior art, in order to prevent the environmental pollution that can occur by using cement concrete mortar, without the use of cement at all, the structure of the eco-friendly composite steel structure using the clay as the main material And to provide a construction method thereof.

또한 차수벽에 시멘트를 사용하지 않음에 따라 약해질 수 있는 시트파일 하단부 밀림에 대한 저항성을 보강할 수 있는 수단을 제공하고자 한다.In addition, it is intended to provide a means to reinforce the resistance to the lower edge of the sheet pile that can be weakened by not using cement in the order wall.

아울러 무시멘트 황토에 의한 차수벽의 기능을 향상시킬 수 있도록 시트파일과 차수벽간의 밀착성 및 황토조성물간의 결합력을 향상시킬 수 있는 수단을 제공하고자 한다..
In addition, it is intended to provide a means for improving the adhesion between the sheet pile and the order wall and the cohesion between the ocher composition in order to improve the function of the order wall due to cement ocher.

상기의 과제를 해결하기 위한 본 발명의 가장 바람직한 실시예에 따르면, 암반층까지 근입되는 복수 개의 지주와, 상기 지주의 전면에서 암반층의 상면 또는 풍화암의 일부 깊이까지 근입되는 시트파일, 상기 지주와 지주 사이에서 시트파일의 하단부를 중심으로 하여 설치되는 차수벽으로 구성되는 복합형 강가시설에 있어서, 상기 차수벽은 무시멘트 황토 조성물로 이루어지는 것을 특징으로 하는 친환경 복합형 강가시설이 제공된다.According to the most preferred embodiment of the present invention for solving the above problems, a plurality of struts to be entered into the rock layer, the sheet pile to be entered to the upper surface of the rock layer or a part of the weathered rock from the front of the pillar, between the strut and the strut In the composite steel structure consisting of the order wall is installed around the lower end of the sheet pile, the order wall is provided with an eco-friendly composite river facility, characterized in that the cement ocher composition.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 무시멘트 황토 조성물은 소성가공된 황토분말에 생석회, 마사토가 포함되어 이루어지되, 시멘트가 포함되지 않는 것을 특징으로 하는 친환경 복합형 강가시설이 제공된다.According to another preferred embodiment of the present invention, the cementless loess composition is made of calcined lime, masato is included in the plastic processed ocher powder, eco-friendly composite steel is provided, characterized in that it does not contain cement.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 차수벽에는 와이어메쉬 또는 강섬유, 철근 등의 강재나 면섬유, 나일론사, 플라스틱 섬유 또는 볏짚, 닥나무펄프 등의 단섬유 내지는 절단된 조각들의 어느 하나 이상으로 된 보강부재가 더 포함되는 것을 특징으로 하는 친환경 복합형 강가시설이 제공된다.According to another preferred embodiment of the present invention, the order wall is made of any one or more of the wire mesh or steel fibers, such as steel fibers, rebar, cotton fibers, nylon yarn, plastic fibers or short fibers or cut pieces such as straw, mulberry pulp, etc. It is provided with an eco-friendly composite river, characterized in that the reinforcement member is further included.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 무시멘트 황토 조성물에는 황토점착액이 더 포함되는 것을 특징으로 하는 친환경 복합형 강가시설이 제공된다.According to another preferred embodiment of the present invention, the cementless ocher composition is provided with an eco-friendly complex steel structure, characterized in that the ocher adhesive is further included.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 황토점착액은 소성가공된 황토분말과; 옻 추출액, 계란껍질, 송진, 아마인유, 녹말, 아교, 부레, 자작나무 등의 타르, 에폭시, 아크릴, 에틸렌비닐 아세테이트, 폴리염화비닐, 폴리비닐아세테이트, 폴리부타디엔, 폴리염화비닐리덴, 폴리우레탄 수지 중 어느 하나 또는 둘 이상을; 혼합하여 형성되는 것을 특징으로 하는 친환경 복합형 강가시설이 제공된다.According to another preferred embodiment of the present invention, the ocher adhesive is plastic processed ocher powder; Lacquer extract, eggshell, rosin, linseed oil, starch, glue, briquette, tar, epoxy, acrylic, ethylene vinyl acetate, polyvinyl chloride, polyvinylacetate, polybutadiene, polyvinylidene chloride, polyurethane resin Any one or more than two; Provided is an eco-friendly complex riverside facility, characterized in that formed by mixing.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 시트파일의 하단부와 지주 사이에는 합성연결부재가 설치되는 것을 특징으로 하는 친환경 복합형 강가시설이 제공된다.According to another preferred embodiment of the present invention, there is provided an environment-friendly composite steel structure, characterized in that the composite connecting member is installed between the lower end and the support of the sheet pile.

본 발명의 바람직한 또 다른 실시예에 따르면, 교각 기초 등의 지중 구조물을 구축하기 위한 강가시설 시공방법에 있어서, a) 흙막이벽의 기둥이 되는 지주를 암반층까지 근입시키는 단계; b) 지주의 일측면에 시트파일을 항타하여 암반층의 상면 또는 풍화암의 일부 깊이까지 근입시키는 단계; c) 상기 지주의 가로방향으로 띠장을 설치하는 단계; d) 상기 시트파일과 띠장 사이에 일정한 간격으로 지지부재를 설치하고, 상기 시트파일과 지주 사이에 일정한 간격으로 합성연결부재를 설치하는 단계, e) 상기 시트파일의 하단부를 중심으로 하여 지주와 지주 사이에 무시멘트 황토 조성물로 이루어진 차수벽을 설치하는 단계; 를 포함하여 이루어지는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법이 제공된다.According to still another preferred embodiment of the present invention, a method for constructing a steel structure for constructing underground structures such as a pier foundation, the method comprising: a) incorporating a pillar, which is a pillar of a retaining wall, to a rock layer; b) driving a sheet pile on one side of the strut to access the top of the rock layer or some depth of the weathered rock; c) installing a strip in the transverse direction of the support; d) installing a support member at regular intervals between the sheet pile and the strip, and installing a composite connecting member at regular intervals between the sheet pile and the support, e) the support and support for the lower end of the seat pile Installing a barrier wall made of cementless ocher composition therebetween; Provided is a construction method of an environment-friendly composite river structure, characterized in that comprises a.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 d)단계에서 시트파일과 지주 사이에 합성연결부재를 설치함에 있어서, 상기 합성연결부재는 시트파일의 하단부와 이에 대응하는 지주 사이에는 반드시 설치되는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법이 제공된다.According to another preferred embodiment of the present invention, in installing the composite connecting member between the seat pile and the support in step d), the composite connecting member is necessarily installed between the lower end of the seat pile and the corresponding support Provided is a construction method of an eco-friendly complex riverside facility.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 차수벽은 무시멘트 황토 조성물을 분사식으로 타설하여 형성시키는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법이 제공된다.According to another preferred embodiment of the present invention, the order wall is provided with a construction method of the environment-friendly composite steel structure, characterized in that by forming the cement cement loess composition by spraying.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 차수벽 내부에는 와이어메쉬 보강부재를 더 설치하는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법이 제공된다.According to another preferred embodiment of the present invention, there is provided a construction method of an environment-friendly composite steel structure, characterized in that the wire mesh reinforcement member further installed in the order wall.

본 발명의 바람직한 또 다른 실시예에 따르면, 상기 차수벽을 설치하기 전에 차수벽이 설치될 시트파일의 하단면과 암반의 굴착면에는 황토점착액이 미리 도포되는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법이 제공된다.
According to another preferred embodiment of the present invention, before installation of the order wall, construction of an eco-friendly composite steel structure, characterized in that the ocher adhesive is applied in advance to the bottom surface of the sheet pile to be installed the order wall and the excavation surface of the rock A method is provided.

본 발명은 시멘트를 전혀 사용하지 않음으로써 시멘트 등에서 발생할 수 있는 환경오염 등의 문제가 없고, 황토를 사용함으로써 인체 및 환경에 유익한 자연친화적 구조체를 형성할 수 있으며, 황토점착액을 사용하여 보다 높은 차수기능을 확보할 수 있는 효과를 기대할 수 있다.
The present invention does not use the cement at all, there is no problem such as environmental pollution that can occur in the cement, etc., by using the yellow soil can form a natural friendly structure beneficial to the human body and the environment, using a higher order using ocher adhesive You can expect the effect to secure the function.

도 1은 종래의 복합형 강가시설 구조에 관한 사시단면도이다.
도 2는 본 발명의 친환경 복합형 강가시설의 일 실시예에 따른 시공방법의 흐름도이다. (a)는 지주의 근입단계, (b)는 시트파일의 근입단계, (c)는 굴착하면서 띠장, 지지부재 및 합성연결부재를 설치하는 단계, (d)는 토류판을 설치하여 차수벽을 설치하는 단계, (e)는 터파기를 완료한 단계를 각 도시하고 있다.
도 3은 본 발명의 친환경 복합형 강가시설에서 시트파일 하단부에 지주와 연결되는 합성연결부재를 설치시킨 사시단면도이다.
도 4는 본 발명의 친환경 복합형 강가시설에서 판재를 적층하여 고정시킨 형태의 토류판을 이용한 실시예의 사시단면도이다.
도 5는 본 발명의 친환경 복합형 강가시설에서 향후 제거할 수 있는 토류판의 구조를 이용한 실시예의 사시단면도이다.
도 6은 본 발명의 친환경 복합형 강가시설에서 판상 보강부재를 차수벽의 내면에 설치한 실시예의 사시단면도이다.
1 is a perspective cross-sectional view of a conventional composite river structure.
Figure 2 is a flow chart of the construction method according to an embodiment of the environment-friendly composite steel structure of the present invention. (a) is the step of entering the strut, (b) is the step of entering the sheet pile, (c) is excavating and installing the band, the support member and the composite connecting member, (d) is to install the earth plate Step (e) shows each step of completing the trench.
Figure 3 is a perspective cross-sectional view of the composite connecting member installed in the lower end of the seat pile in the environment-friendly composite river installation of the present invention.
Figure 4 is a perspective cross-sectional view of the embodiment using the earth plate of the form of the laminated board fixed in the environment-friendly composite river installation of the present invention.
Figure 5 is a perspective cross-sectional view of an embodiment using the structure of the earth plate that can be removed in the future environment-friendly composite river installation of the present invention.
Figure 6 is a perspective cross-sectional view of an embodiment in which the plate-shaped reinforcement member is installed on the inner surface of the order wall in the environment-friendly composite river installation of the present invention.

이하에서는 본 발명의 실시 예를 첨부된 도면을 참조하여 상세히 설명한다. 그러나 본 발명을 설명함에 있어 공지의 구성을 구체적으로 설명함으로 인하여 본 발명의 기술적 사상을 흐리게 하거나 불명료하게 하는 경우에는 위 공지의 구성에 관하여는 그 설명을 생략하기로 한다.
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the following description of the present invention, however, it is to be understood that the present invention is not limited to the disclosed embodiments.

본 발명의 친환경 복합형 강가시설은, 암반층까지 근입되는 복수 개의 지주(100), 상기 지주(100)의 전면에서 암반층의 상면 또는 풍화암의 일부 깊이까지 근입되는 시트파일(200), 상기 지주(100)의 가로방향으로 설치되는 띠장(300), 상기 시트파일(200)과 띠장(300) 사이에 설치되는 지지부재(250), 상기 시트파일(200)과 지주(100) 사이에 설치되는 합성연결부재(150), 및 상기 지주(100)와 지주(100) 사이에서 시트파일(200)의 하단부를 중심으로 하여 설치되는 차수벽(400)으로 구성되는 복합형 강가시설에 있어서, 상기 차수벽(400)은 무시멘트 황토조성물로 이루어지는 것을 특징으로 한다.Eco-friendly composite river according to the present invention, a plurality of struts (100) to be entered into the rock layer, the sheet pile 200 to be entered to the upper surface of the rock bed or a part of the weathered rock from the front of the pillar (100), the support (100) Belt strip 300 is installed in the horizontal direction of the support, the support member 250 is installed between the sheet pile 200 and the belt sheet 300, the composite connection is installed between the sheet pile 200 and the support (100) In the composite riverbed facility consisting of a member 150, and the order wall 400 which is installed between the support post 100 and the support post 100 about the lower end of the sheet pile 200, the order wall 400 Is characterized by consisting of cementless ocher composition.

이러한 친환경 복합형 강가시설은 도 2에 도시된 바와 같이, a) 흙막이벽의 기둥이 되는 지주(100)를 암반층까지 근입시키는 단계; b) 지주(100)의 일측면에 시트파일(200)을 항타하여 암반층의 상면 또는 풍화암의 일부 깊이까지 근입시키는 단계; c) 상기 지주(100)의 가로방향으로 띠장(300)을 설치하는 단계; d) 상기 시트파일(200)과 띠장(300) 사이에 일정한 간격으로 지지부재(250)를 설치하고, 상기 시트파일(200)과 지주(100) 사이에 일정한 간격으로 합성연결부재(150)를 설치하는 단계, e) 상기 시트파일(200)의 하단부를 중심으로 하여 지주(100)와 지주(100) 사이에 무시멘트 황토조성물로 이루어진 차수벽(400)을 설치하는 단계; 를 포함하여 이루어진다. 상기 a)단계에서의 '지주(100)를 근입시키는 단계'와 b)단계에서의 '시트파일(200)을 근입시키는 단계'는 현장의 여건에 따라 그 순서를 달리 할 수도 있다.As shown in Figure 2, the eco-friendly complex riverfront facility, a) the step of incorporating the strut 100 to be a pillar of the earth wall to the rock layer; b) driving the sheet pile 200 on one side of the support 100 to access the upper surface of the rock layer or a part of the weathered rock; c) installing the strip 300 in the horizontal direction of the support (100); d) Install the support member 250 at regular intervals between the sheet pile 200 and the strip 300, and the synthetic connecting member 150 at regular intervals between the sheet pile 200 and the support (100) Step of installing, e) installing the order wall 400 made of cementless ocher composition between the strut 100 and the strut 100 around the lower end of the sheet pile 200; It is made, including. In the step a), the step of incorporating the holding 100 and the step of incorporating the sheet pile 200 in step b) may be changed in order according to the conditions of the site.

상기 지주(100)는 시트파일(200)을 지지함은 물론, 전체적인 강가시설을 지지할 수 있도록 암반을 일정부분 이상의 깊이로 깊게 파고들어 단단히 고정되도록 하는데, 지주(100)가 설치될 부분을 미리 천공한 후 지주(100)를 삽입하고 이를 타격하여 설치한다. 상기 지주(100)는 H형강으로 하는 것이 바람직하나 토압에 대한 구조적인 강도를 유지, 형성할 수 있는 다른 자재의 사용도 가능하다.The support 100 is not only to support the seat pile 200, but also to dig deep into the rock to a certain portion or more depth so as to support the entire river installation, so that the support 100 is installed in advance After drilling, insert the strut 100 and install it by hitting it. The post 100 is preferably made of H-shaped steel, but other materials capable of maintaining and forming structural strength against earth pressure may be used.

다음으로 상기 지주(100)의 외부측면(교각 등의 구조물을 설치하는 내부 공사가 진행되는 부분을 내부측이라 한다)에는 시트파일(200)을 설치하는데, 상기 시트파일(200)은 두께가 얇고, 면적이 넓어 암반을 천공하고 시트파일(200)을 설치하는 것이 어려우므로, 암반의 일정 깊이까지 항타하여 설치하는 것이 바람직하지만, 암반 깊숙히 시트파일(200)이 삽입되기에는 강도가 낮아 암반에 살짝 끼워지는 정도로 설치한다. 상기 암반에 일정 깊이 이상으로 삽입된 지주(100)는 후술하는 터파기에 의해 시트파일(200)의 외부측의 토압을 받아서 흙막이벽이 내부측으로 붕괴되지 않도록 지지하는 역할을 한다.Next, a seat pile 200 is installed on an outer side surface of the support 100 (a portion where an internal construction for installing a structure such as a pier proceeds is called an inner side), and the sheet pile 200 has a thin thickness. Since the area is wide, it is difficult to perforate the rock and install the seat pile 200, but it is preferable to drive the rock to a predetermined depth, but the strength is low enough to insert the seat pile 200 deep into the rock. Install to the extent that it fits in. The strut 100 inserted into the rock more than a predetermined depth serves to support the earth wall so as not to collapse to the inner side by receiving earth pressure from the outer side of the sheet pile 200 by a trench to be described later.

상기 시트파일(200) 설치 후 시트파일(200)의 내부측면을 일정 깊이로 터파기를 한다. 상기 터파기로 인해 시트파일(200)의 내부측을 지지하던 토사층이 사라진 시트파일(200)이 시트파일(200) 배면의 토압등 수평하중에 의해 내부측으로 밀려 나오지 않도록 지주(100)와 시트파일(200)을 견고하게 고정하는 것이 필요하며, 이를 위해 지주(100)의 가로방향으로 띠장(300)을 설치하고, 시트파일(200)과 띠장(300) 사이에는 지지부재(250)를 설치한다.After the sheet pile 200 is installed, the inner side surface of the sheet pile 200 is excavated to a predetermined depth. The support pile 100 and the sheet pile (not to be pushed out to the inner side by the horizontal load such as the earth pressure of the back of the sheet pile 200 disappears the soil pile layer supporting the inner side of the sheet pile 200 due to the trench) It is necessary to firmly fix the 200, for this purpose to install a strip 300 in the horizontal direction of the support 100, and install the support member 250 between the sheet pile 200 and the strip 300.

상기 시트파일(200)이 토압에 의해 밀리지 않도록 하기 위해서는 지주(100)와 시트파일(200) 사이에 간격을 두지 않고 시공함이 바람직 하나, 지주(100)와 시트파일(200)을 밀착 정밀시공하는 것은 그다지 쉽지 아니하여 공사 진행을 원활하게 진행시킬 수 없으므로, 시공의 편의상 지주(100)와 시트파일(200)간에 일정한 간격을 두어 시공하는 것이 공사 진행상 바람직하다. 이로 인하여 상기 지주(100)가 시트파일(200)을 견고하게 지지할 수 없다는 문제가 있으나, 지주(100)와 시트파일(200)간에 합성연결부재(150)를 설치함으로써 상기 지주(100)가 시트파일(200)을 견고히 지지하도록 할 수 있다. 즉 지지부재(250)와 합성연결부재(150)는 시트파일(200), 지주(100) 및 띠장(300)을 일체로 거동하게 하여 시트파일(200) 배면의 토압 등에 의한 수평하중을 충분히 지지할 수 있도록 한다는 것은 특허 제884289호의 복합형 강가시설과 다르지 않다. 그러나 본 발명은 시트파일(200)의 하단부와 지주(100) 사이에는 상기 합성연결부재(150)가 반드시 설치되는 것을 중요한 기술적 특징으로 하고 있다.In order to prevent the sheet pile 200 from being pushed by earth pressure, it is preferable that the construction without spaces between the pillar 100 and the sheet pile 200 is carried out. However, the pillar pile 100 and the sheet pile 200 are in close contact with each other. It is not so easy to proceed with the construction smoothly, it is preferable to construct at regular intervals between the prop 100 and the seat pile 200 for the convenience of construction. Due to this, there is a problem that the support 100 cannot firmly support the seat pile 200, but the support 100 is installed by installing the synthetic connection member 150 between the support 100 and the seat pile 200. The sheet pile 200 may be firmly supported. That is, the support member 250 and the synthetic connecting member 150 integrally operate the sheet pile 200, the support 100, and the strip 300 to fully support the horizontal load by the earth pressure or the like on the back of the sheet pile 200. Making it possible is no different from the complex riverbed of patent 888489. However, the present invention has an important technical feature that the synthetic connecting member 150 is necessarily installed between the lower end of the seat pile 200 and the support 100.

앞서 본 바와 같이, 위 특허 제884289호의 복합형 강가시설은 지주(100)와 시트파일(200)간에 일정한 간격을 두고 합성연결부재(150)를 설치하여 시트파일(200)의 배면 토압 등을 지주(100)에 전달할 수 있도록 하고 있으나, 시트파일(200)의 하단부의 전면에 차수벽(400)이 설치되고 상기 차수벽(400)은 압축강도가 큰 시멘트 몰탈 내지 콘크리트로 형성되기 때문에 상기 시트파일(200) 하단부에는 합성연결부재(150)가 설치되지 않는다. 이에 반하여 본 발명은 도 3에 도시되어 있는 바와 같이, 차수벽(400)이 설치되는 시트파일(200)의 하단부에 지주(100)와 연결되는 합성연결부재(150)를 반드시 설치함으로써 차수벽(400)이 시트파일(200)의 배면토압을 지지할 수 있는 지지력이 없더라도 시트파일(200)의 하단면이 배면토압 등에 의하여 밀려 나오는 현상이 발생되지 않도록 한다. 이러한 시트파일(200) 하단부에 설치되는 합성연결부재(150)는, 향후 타설되는 차수벽(400)에 매립되어 시트파일(200)의 수평하중 지지기능을 전담하므로 상기 차수벽(400)은 수밀성만을 고려하여 그 재질을 광범위한 친환경 소재로 사용할 수 있도록 한다는 작용효과를 발휘한다.As previously seen, the composite river structure of the above patent No. 888489 has a fixed distance between the support 100 and the seat pile 200 to install a synthetic connection member 150 to support the back earth pressure of the seat pile 200, etc. Although it is possible to transmit to the 100, the order wall 400 is installed on the front of the lower end of the sheet pile 200 and the order wall 400 is formed of cement mortar or concrete with a high compressive strength, the sheet pile 200 ) Synthetic connecting member 150 is not installed at the lower end. On the contrary, in the present invention, as shown in FIG. 3, the order wall 400 is provided by necessarily installing a synthetic connection member 150 connected to the support 100 at the lower end of the seat pile 200 on which the order wall 400 is installed. Even if there is no support force capable of supporting the back soil pressure of the sheet pile 200, the phenomenon that the bottom surface of the sheet pile 200 is pushed out by the back soil pressure is not generated. The composite connecting member 150 installed at the lower end of the sheet pile 200 is buried in the ordered wall 400 to be placed in the future, and is dedicated to the horizontal load supporting function of the sheet pile 200, so that the order wall 400 considers only watertightness. It has the effect of using the material as a wide range of eco-friendly materials.

상기 친환경 소재의 차수벽(400)은 무시멘트 황토 조성물로 이루어지는 것이 바람직하다. 상기 무시멘트 황토 조성물은 시멘트를 전혀 첨가하지 않는 것으로 소성 가공된 황토에 생석회, 마사토 등을 혼합하여 제조된다.The order wall 400 of the eco-friendly material is preferably made of cementless ocher composition. The cementless ocher composition is prepared by mixing quicklime, masato, and the like with calcined ocher, which does not add any cement.

상기 황토조성물은 입자간의 결합력을 높이기 위해 황토점착액이 더 포함될 수 있다. 상기 황토점착액은 소성가공된 황토분말과; 옻 추출액, 계란껍질, 송진, 아마인유, 녹말, 아교, 부레, 자작나무 등의 타르, 에폭시, 아크릴, 에틸렌비닐 아세테이트, 폴리염화비닐, 폴리비닐아세테이트, 폴리부타디엔, 폴리염화비닐리덴, 폴리우레탄 수지 중 어느 하나 또는 둘 이상을; 혼합하여 형성한다. 상기 옷 추출액, 계란껍질, 송진, 아마인유, 녹말, 아교, 부레, 자작나무 등의 타르는 전통적으로 접착을 위해 사용되었던 재료이고, 에폭시, 아크릴, 에틸렌비닐 아세테이트, 폴리염화비닐, 폴리비닐아세테이트, 폴리부타디엔, 폴리염화비닐리덴, 폴리우레탄 수지는 공업적으로 합성되는 접착성분인데, 특히 옻 추출액, 송진, 아마인유 등은 친환경적이면서도 발수성을 높이면서 접착제 효과를 동시에 얻을 수 있어 본 발명의 황토점착액 성분으로 바람직하다.The ocher composition may further include an ocher adhesive to increase the binding force between the particles. The ocher adhesive is plastic processed ocher powder; Lacquer extract, eggshell, rosin, linseed oil, starch, glue, briquette, tar, epoxy, acrylic, ethylene vinyl acetate, polyvinyl chloride, polyvinylacetate, polybutadiene, polyvinylidene chloride, polyurethane resin Any one or more than two; Form by mixing. The tar, such as clothes extract, eggshell, rosin, linseed oil, starch, glue, briquettes, and birch, is a material that has traditionally been used for adhesion, and includes epoxy, acrylic, ethylene vinyl acetate, polyvinyl chloride, polyvinylacetate, Polybutadiene, polyvinylidene chloride, and polyurethane resins are industrially synthesized adhesive components. Especially, lacquer extract, rosin, linseed oil, etc. are eco-friendly and can improve the water repellency and at the same time obtain the adhesive effect. Preferred as a component.

상기 황토조성물로 이루어진 차수벽(400)은 강도를 향상시키기 위해 그 내부에 보강부재(450)를 삽입시킬 수 있다. 상기 보강부재(450)로는 와이어 메쉬 등의 판상부재를 사용할 수 있고, 강섬유, 철사 등의 조각, 면섬유, 나일론사, 플라스틱 섬유 등의 섬유보강재 또는 볏짚, 닥나무펄프 등의 단섬유 내지는 절단된 조각들이 사용될 수 있다.The order wall 400 made of the ocher composition may insert a reinforcement member 450 therein to improve strength. The reinforcing member 450 may be a plate-like member such as wire mesh, a fiber reinforcement such as steel fiber, wire, pieces, cotton fiber, nylon yarn, plastic fiber, or short fibers or cut pieces such as rice straw, mulberry pulp Can be used.

상기 차수벽(400)은 지주(100)의 돌출면 부분에 부직포(600)를 깔고 상기 부직포(600)의 상면에 토류판(500)을 설치하여 상기 토류판(500)과 시트파일(200), 토류판(500)과 암반의 굴착면 사이에 공간을 형성시킨 후 상기 공간에 무시멘트 황토 조성물을 타설함으로써 구축된다. 상기 보강부재(450)중 와이어 메쉬 등의 판상부재는 무시멘트 황토 조성물을 타설하기 전에 미리 설치하고 강섬유 조각 등의 절단된 조각들은 무시멘트 황토 조성물의 타설 전에 미리 혼합하여 사용하는 것이 바람직하다.The order wall 400 is a non-woven fabric 600 is laid on the protruding surface portion of the support 100 and the earth plate 500 is installed on the upper surface of the nonwoven fabric 600, the earth plate 500 and the sheet pile 200, earth plate ( 500) and by forming a space between the excavation surface of the rock and then pouring the cement ocher composition into the space. In the reinforcing member 450, a plate-like member such as a wire mesh is installed in advance before placing the cementless ocher composition, and the cut pieces such as steel fiber pieces are preferably mixed in advance before the cementing ocher composition is poured.

상기 지주(100)의 돌출면 부분에 설치되는 토류판(500)은 고정형일 수도 있고, 본 공사가 완료된 후 이를 제거할 수 있는 조립식일 수도 있으며, 판재를 적층하여 형성될 수도 있고, 전체가 하나로 된 판상부재일 수도 있다. 도 4는 판재를 적층하여 고정시킨 형태의 토류판(500)을 이용한 실시예를 나타내고, 도 5는 향후 제거할 수 있는 토류판(500)의 구조를 이용한 실시예를 나타내고 있다. The earth plate 500 installed on the protruding surface portion of the support 100 may be a fixed type, may be a prefabricated type that can be removed after the completion of the construction, may be formed by stacking the plate, the whole It may be a plate member. Figure 4 shows an embodiment using the earth plate 500 of the form in which the plate is laminated and fixed, Figure 5 shows an embodiment using the structure of the earth plate 500 that can be removed in the future.

상기 차수벽(400)은 무시멘트 황토 조성물을 분사식으로 시공함으로써 구축시킬 수도 있다. 차수벽(400)을 분사식 시공하는 경우 차수벽(400)이 설치될 시트파일(200)의 하단면과 암반의 굴착면에는 무시멘트 황토 조성물과의 접착력을 증대시키기 위해 황토점착액을 미리 도포시킬 수 있다. 물론 상기 분사식 타설방법이 아닌 경우에도 상기 황토점착액을 미리 도포시킬 수 있음은 당연하다. 상기 황토점착액에는 방수재를 혼합함으로써 향후 차수벽(400)의 차수기능을 더욱 높일 수 있다.The order wall 400 may be constructed by spraying a cementless ocher composition. When spraying the order wall 400, the bottom surface of the sheet pile 200 on which the order wall 400 is to be installed and the excavation surface of the rock can be applied in advance to the ocher adhesive to increase the adhesive force with the cement ocher composition. . Of course, even if the spraying method is not the ocher adhesive can be applied in advance. By mixing the waterproofing material with the ocher adhesive may further increase the order function of the order wall 400 in the future.

상기 분사식으로 시공되는 차수벽(400)에는 도 6에 도시된 바와 같이, 와이어메쉬 등의 판상 보강부재(450)를 그 내면에 설치하는 것이 바람직하다. 상기 와이어메쉬 등의 보강 부재는 무시멘트 황토 조성물의 시공전에 미리 설치될 수 있고, 수차 나누어 분사시공되는 단계의 사이에 설치될 수도 있다. 이와 같이 분사식으로 차수벽(400)을 시공하는 경우에는 토류판(500)의 구성이 불필요할 것임은 당연하다.As shown in FIG. 6, it is preferable to install a plate-shaped reinforcement member 450, such as a wire mesh, on the inner surface of the order wall 400. The reinforcing members such as wire mesh may be installed in advance before the construction of the cementless ocher composition, or may be installed between the steps of spraying. As such, when the order wall 400 is constructed by spraying, the configuration of the earth plate 500 may be unnecessary.

상기 차수벽(400)을 설치하기 전에 시트파일(200)의 배면토사에 대하여 그라우팅함으로써 지반을 보강함과 아울러 후면차수벽(400)을 형성시킬 수도 있으며, 이 경우 후면차수벽(400)이 시트파일(200) 배면의 토압 및 수압을 1차적으로 대응하게 되므로, 상기 무시멘트 황토 조성물에 의한 시트파일(200) 전면의 차수벽(400) 시공은 보다 용이하고 정밀하게 실시할 수 있다.It is also possible to reinforce the ground and form the rear order wall 400 by grouting the back soil of the sheet pile 200 before installing the order wall 400. In this case, the rear order wall 400 is the sheet pile 200. Since the earth pressure and the water pressure of the back side correspond primarily, the construction of the order wall 400 on the front of the sheet pile 200 by the cementless ocher composition can be carried out more easily and precisely.

이와 같이 본 발명의 친환경 복합형 강가시설은 매립되는 차수벽(400)을 독성이 강한 시멘트를 전혀 사용하지 않음으로써 지하수 등이 오염되지 않도록 한다는 점에서 지하환경보전에 매우 유익한 구조라고 할 수 있다.
As described above, the eco-friendly complex riverfront facility of the present invention is a very beneficial structure in that the underground water is not contaminated by not using cement having strong toxicity to the buried car wall 400 at all.

이상에서 본 발명은 구체적인 실시 예를 참조하여 상세히 설명하였으나, 상기 실시 예는 본 발명을 이해하기 쉽도록 하기 위한 예시에 불과한 것이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 하기의 특허청구범위에 의하여 정해지는 본 발명의 보호범위에 속한다고 할 것이다.
The present invention has been described in detail above with reference to specific embodiments, but the above embodiments are merely examples for easy understanding of the present invention, and therefore, substitutions, additions, and modifications within the scope do not depart from the spirit of the present invention. Embodiments will also belong to the protection scope of the present invention as defined by the claims below.

100: 지주 150: 합성연결부재
200: 시트파일 250: 지지부재
300: 띠장 400: 차수벽
450: 보강부재 500: 토류판
600: 부직포 S: 토사층
R: 암반층
100: prop 150: synthetic connecting member
200: sheet pile 250: support member
300: Belt 400: Order Wall
450: reinforcing member 500: earth plate
600: nonwoven fabric S: soil layer
R: rock bed

Claims (11)

암반층까지 근입되는 복수 개의 지주(100)와, 상기 지주(100)의 전면에서 암반층의 상면 또는 풍화암의 일부 깊이까지 근입되는 시트파일(200), 상기 지주(100)와 지주(100) 사이에서 시트파일(200)의 하단부를 중심으로 하여 설치되는 차수벽(400)으로 구성되는 복합형 강가시설에 있어서, 상기 차수벽(400)은 무시멘트 황토 조성물로 이루어지는 것을 특징으로 하는 친환경 복합형 강가시설A plurality of struts 100 entered to the rock bed, the sheet pile 200 to be entered from the front of the strut 100 to the upper surface of the rock layer or a part of the weathered rock, between the strut 100 and the strut 100 In the composite steel structure consisting of a water order wall 400 is installed around the lower end of the pile 200, the water order wall 400 is an environmentally friendly composite steel structure, characterized in that consisting of cementless loess composition 제1항에 있어서, 상기 무시멘트 황토 조성물은 소성가공된 황토분말에 생석회, 마사토가 포함되어 이루어지되, 시멘트가 포함되지 않는 것을 특징으로 하는 친환경 복합형 강가시설According to claim 1, The cement cement loess composition is an eco-friendly composite steelwork facility characterized in that the calcined ocher powder is made of quicklime, masato is included, but does not contain cement 제1항에 있어서, 상기 차수벽(400)에는 와이어메쉬 또는 강섬유, 철근 등의 강재나 면섬유, 나일론사, 플라스틱 섬유 또는 볏짚, 닥나무펄프 등의 단섬유 내지는 절단된 조각들의 어느 하나 이상으로 된 보강부재(450)가 더 포함되는 것을 특징으로 하는 친환경 복합형 강가시설The reinforcement member according to claim 1, wherein the order wall 400 includes at least one of steel or cotton fibers such as wire mesh or steel fiber, rebar, cotton fiber, nylon yarn, plastic fiber, or short fibers or cut pieces such as rice straw or mulberry pulp. Eco-friendly composite river facilities, characterized in that further comprises 450 제2항에 있어서, 상기 무시멘트 황토 조성물에는 황토점착액이 더 포함되는 것을 특징으로 하는 친환경 복합형 강가시설According to claim 2, The cement cement loess composition Eco-friendly complex river facility characterized in that it further comprises an ocher adhesive liquid 제4항에 있어서, 상기 황토점착액은 소성가공된 황토분말과; 옻 추출액, 계란껍질, 송진, 아마인유, 녹말, 아교, 부레, 자작나무 등의 타르, 에폭시, 아크릴, 에틸렌비닐 아세테이트, 폴리염화비닐, 폴리비닐아세테이트, 폴리부타디엔, 폴리염화비닐리덴, 폴리우레탄 수지 중 어느 하나 또는 둘 이상을; 혼합하여 형성되는 것을 특징으로 하는 친환경 복합형 강가시설According to claim 4, wherein the ocher adhesive liquid is processed ocher powder; Lacquer extract, eggshell, rosin, linseed oil, starch, glue, briquette, tar, epoxy, acrylic, ethylene vinyl acetate, polyvinyl chloride, polyvinylacetate, polybutadiene, polyvinylidene chloride, polyurethane resin Any one or more than two; Eco-friendly complex riverside facility characterized in that formed by mixing 제1항 내지 제5항 중 어느 한 항에 있어서, 상기 시트파일(200)의 하단부와 지주(100) 사이에는 합성연결부재(150)가 설치되는 것을 특징으로 하는 친환경 복합형 강가시설According to any one of claims 1 to 5, Eco-friendly composite steel structure, characterized in that the synthetic connecting member 150 is installed between the lower end of the seat pile 200 and the support 100. 교각 기초 등의 지중 구조물을 구축하기 위한 강가시설 시공방법에 있어서,
a) 흙막이벽의 기둥이 되는 지주(100)를 암반층까지 근입시키는 단계;
b) 지주(100)의 일측면에 시트파일(200)을 항타하여 암반층의 상면 또는 풍화암의 일부 깊이까지 근입시키는 단계;
c) 상기 지주(100)의 가로방향으로 띠장(300)을 설치하는 단계;
d) 상기 시트파일(200)과 띠장(300) 사이에 일정한 간격으로 지지부재(250)를 설치하고, 상기 시트파일(200)과 지주(100) 사이에 일정한 간격으로 합성연결부재(150)를 설치하는 단계,
e) 상기 시트파일(200)의 하단부를 중심으로 하여 지주(100)와 지주(100) 사이에 무시멘트 황토 조성물로 이루어진 차수벽(400)을 설치하는 단계; 를 포함하여 이루어지는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법
In the method of construction of a riverfront facility for building underground structures such as bridge foundations,
a) accessing the strut 100, which is a pillar of the retaining wall, to the rock layer;
b) driving the sheet pile 200 on one side of the support 100 to access the upper surface of the rock layer or a part of the weathered rock;
c) installing the strip 300 in the horizontal direction of the support (100);
d) Install the support member 250 at regular intervals between the sheet pile 200 and the strip 300, and the synthetic connecting member 150 at regular intervals between the sheet pile 200 and the support (100) Installation steps,
e) installing an order wall 400 made of cementless ocher composition between the strut 100 and the strut 100 about the lower end of the sheet pile 200; Construction method of the eco-friendly complex riverside facility characterized in that it comprises a
제7항에 있어서, 상기 d)단계에서 시트파일(200)과 지주(100) 사이에 합성연결부재(150)를 설치함에 있어서, 상기 합성연결부재(150)는 시트파일(200)의 하단부와 이에 대응하는 지주(100) 사이에는 반드시 설치되는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법The method of claim 7, wherein in the step d) in installing the composite connecting member 150 between the seat pile 200 and the support 100, the composite connecting member 150 and the lower end of the sheet pile 200 Construction method of an eco-friendly composite steel structure, characterized in that the installation is necessarily between the corresponding support (100) 제7항에 있어서, 상기 차수벽(400)은 무시멘트 황토 조성물을 분사식으로 타설하여 형성시키는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법The method of claim 7, wherein the order wall 400 is a construction method of eco-friendly composite steel structure, characterized in that by forming a cement cement composition by spraying 제7 내지 제9항중 어느 한 항에 있어서, 상기 차수벽(400) 내부에는 와이어메쉬 보강부재(450)를 더 설치하는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법 10. The construction method according to any one of claims 7 to 9, wherein a wire mesh reinforcement member 450 is further installed inside the order wall 400. 제10항에 있어서, 상기 차수벽(400)을 설치하기 전에 차수벽(400)이 설치될 시트파일(200)의 하단면과 암반의 굴착면에는 황토점착액이 미리 도포되는 것을 특징으로 하는 친환경 복합형 강가시설의 시공방법
According to claim 10, Eco-friendly complex type, characterized in that the ocher adhesive is applied in advance to the bottom surface of the sheet pile 200 to be installed in the order wall 400 and the excavation surface of the rock before installing the order wall 400 Construction method of riverside facility
KR1020120011847A 2012-02-06 2012-02-06 Eco-composite type steel temporary construction and construction method thereof KR101380782B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120011847A KR101380782B1 (en) 2012-02-06 2012-02-06 Eco-composite type steel temporary construction and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120011847A KR101380782B1 (en) 2012-02-06 2012-02-06 Eco-composite type steel temporary construction and construction method thereof

Publications (2)

Publication Number Publication Date
KR20130090596A true KR20130090596A (en) 2013-08-14
KR101380782B1 KR101380782B1 (en) 2014-04-02

Family

ID=49216150

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120011847A KR101380782B1 (en) 2012-02-06 2012-02-06 Eco-composite type steel temporary construction and construction method thereof

Country Status (1)

Country Link
KR (1) KR101380782B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101859440B1 (en) * 2017-08-30 2018-05-21 유한회사 강남이앤씨 Construction method of contemporary facility of complex steel using connecting means between cofferdam walls

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101625101B1 (en) * 2016-01-26 2016-05-27 원남토건 주식회사 Steel pipe wall temporary construction method
KR101649210B1 (en) * 2016-01-26 2016-08-22 원남토건 주식회사 Steel pipe wall temporary construction
KR101753095B1 (en) * 2016-02-04 2017-08-04 원남토건 주식회사 Considering environmental pollution Eco-friendly construction methods based structures

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100285691B1 (en) * 1999-05-31 2001-03-15 허권 Method for manufacturing a building materials using a ocher
KR100884289B1 (en) * 2008-06-23 2009-02-17 가원이엔씨 주식회사 Composite type steel temporary construction and construction method thereof
KR20100117470A (en) * 2009-04-25 2010-11-03 이주형 Eco landfill facility structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101859440B1 (en) * 2017-08-30 2018-05-21 유한회사 강남이앤씨 Construction method of contemporary facility of complex steel using connecting means between cofferdam walls

Also Published As

Publication number Publication date
KR101380782B1 (en) 2014-04-02

Similar Documents

Publication Publication Date Title
US8974152B2 (en) Polymer grouting method for constructing vertical supporting system
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN102433876B (en) Multi-compartment casing composite pile and construction method thereof
CN201883438U (en) Pit-in-foundation-pit steel sheet pile foundation pit supporting structure
CN103422501B (en) Anti-floating anchor rod structure in sand seam geology and construction method thereof
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN101250886B (en) Method for reinforcing masonry structure building base
CN106948340B (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
KR101545307B1 (en) Construction method of complex temporary facility with bottom grouting for weak ground
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN102877470B (en) Combined soil nailing construction method for supporting
KR101380782B1 (en) Eco-composite type steel temporary construction and construction method thereof
CN103233444A (en) Underwater riprap foundation bed and side slope erosion resisting structure and construction method thereof
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN102220764B (en) Construction method of deep foundation pit bracing system
CN104164895A (en) Basement generating no water buoyant force
CN100355991C (en) Method for constructing composite foundation of piles and ground interactive slurry bonded dispersed body material
CN102296620B (en) Curtain water-stop slope wall and construction method thereof
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN203475486U (en) Basement producing no water buoyancy
CN207228173U (en) A kind of underground project waterproof structure
KR101267688B1 (en) The shore protection construction method using a precast finish panel
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN105951670B (en) A kind of raising sea wall mask foundation bearing capacity construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
N231 Notification of change of applicant
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170323

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180323

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190326

Year of fee payment: 6