KR20120078807A - Method using double-acting pile hydraulic hammer - Google Patents

Method using double-acting pile hydraulic hammer Download PDF

Info

Publication number
KR20120078807A
KR20120078807A KR1020110000063A KR20110000063A KR20120078807A KR 20120078807 A KR20120078807 A KR 20120078807A KR 1020110000063 A KR1020110000063 A KR 1020110000063A KR 20110000063 A KR20110000063 A KR 20110000063A KR 20120078807 A KR20120078807 A KR 20120078807A
Authority
KR
South Korea
Prior art keywords
compaction
hydraulic hammer
ground
double
compaction plate
Prior art date
Application number
KR1020110000063A
Other languages
Korean (ko)
Inventor
박춘민
천유출
이보원
Original Assignee
주식회사 엑스포
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 엑스포 filed Critical 주식회사 엑스포
Priority to KR1020110000063A priority Critical patent/KR20120078807A/en
Publication of KR20120078807A publication Critical patent/KR20120078807A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
    • E02D3/068Vibrating apparatus operating with systems involving reciprocating masses
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B06GENERATING OR TRANSMITTING MECHANICAL VIBRATIONS IN GENERAL
    • B06BMETHODS OR APPARATUS FOR GENERATING OR TRANSMITTING MECHANICAL VIBRATIONS OF INFRASONIC, SONIC, OR ULTRASONIC FREQUENCY, e.g. FOR PERFORMING MECHANICAL WORK IN GENERAL
    • B06B1/00Methods or apparatus for generating mechanical vibrations of infrasonic, sonic, or ultrasonic frequency
    • B06B1/10Methods or apparatus for generating mechanical vibrations of infrasonic, sonic, or ultrasonic frequency making use of mechanical energy
    • B06B1/12Methods or apparatus for generating mechanical vibrations of infrasonic, sonic, or ultrasonic frequency making use of mechanical energy operating with systems involving reciprocating masses
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods

Abstract

PURPOSE: A rammed earth method using a reciprocating hydraulic hammer is provided to improve Depth of Improvement of the ground by repeating the process of filling fillers after drawing out a compaction plate. CONSTITUTION: A rammed earth method using a reciprocating hydraulic hammer is as follows. A compaction plate(250) is heated using the reciprocating hydraulic hammer(210), and one spot is firstly tamped. The compaction plate is tamped until the depth, in which the compaction plate is capable of being drawn out. The reciprocating hydraulic hammer comprises an upper hydraulic unit(240) and a lower hydraulic unit(241). The upper hydraulic unit lifts a ram(230). The lower hydraulic unit drops the lifted ram at more than a free falling speed. The compaction plate is drawn out. Filers(510) are filled in a compaction hole(500), and the one spot is secondary tamped. The Depth of Improvement of the ground increases by repeating the process of tamping the one spot.

Description

복동 유압해머를 이용한 다짐공법{Method using double-acting pile hydraulic hammer} Method using double-acting pile hydraulic hammer

본 발명은 복동 유압해머를 이용한 다짐공법에 관한 것으로, 복동유압해머를 통해 다짐판을 타격하는 램의 타격속도를 증속시켜줌으써 램이 다짐판을 타격하는 에너지가 증가되어 짧은 낙하고도로도 큰 개량심도를 얻을 수 있도록 하는 복동 유압해머를 이용한 다짐공법에 관한 것이다.
The present invention relates to a compaction method using a double-acting hydraulic hammer, by increasing the energy of the ram hitting the compaction plate by increasing the blow speed of the ram hitting the compaction plate through the double-acting hydraulic hammer, a short improved depth even at a short drop It relates to a compaction method using a double-acting hydraulic hammer to obtain a.

일반적으로 연약지반은 평야지대, 삼각주, 골짜기 등을 형성하고 있는 충적지로 건조물의 기초가 되는 바닥이 지지력이 없는 지반을 말한다. In general, soft ground is an alluvial ground that forms plains, deltas, valleys, etc., and refers to the ground where the ground on which the building is based has no bearing capacity.

이러한 연약지반 위에 건축물을 지으면 건물의 하중에 의해 지반이 파괴되거나 압밀침하가 발생 되는데 이를 방지하도록 지반을 직접 또는 간접적으로 강화, 안정화시키는 지반개량을 하게 된다.If the building is built on such a soft ground, the ground is destroyed or consolidation settled by the load of the building, and ground improvement is performed to directly strengthen or stabilize the ground directly or indirectly to prevent it.

이와 같은 지반을 개량하기 위한 공법으로는 유압해머다짐공법과 동다짐공법 등 다양한 공법이 있다.As a method for improving such a ground, there are various methods such as hydraulic hammer compaction method and dynamic compaction method.

상기 유압해머다짐공법이란 진동판(Tamper)을 이용하여 지반을 다지는 공법으로 유압헤머에 장착된 중량 10~13ton의 램이가 낙하고 1~1.5m에서 자유낙하속도로 다짐판을 40~60회 타격하여 지반을 다지게 되며 개량심도는 토질에 따라 4m 전후이다.The hydraulic hammer compaction method is a method of compacting the ground by using a diaphragm (Tamper) by a ram fall of 10 ~ 13 tons mounted on the hydraulic hammer falls and hits the compaction plate 40 ~ 60 times at a free fall speed at 1 ~ 1.5m The ground will be compacted and the depth of improvement will be around 4m depending on the soil.

이러한 유압해머다짐공법은 신속한 타격이 가능하고, 비교적 얕은 심도에서 다짐효율이 좋고, 다짐시 인접한 구조물에 피해를 주지 않으며, 진동이 적어 민원발생소지가 적고, 간단한 시공으로 공기를 단축할 수 있으나, 개량심도의 한계로 5m 이상의 깊은 심도에서는 적용하기가 어려운 문제점이 있다.This hydraulic hammer compaction method is capable of rapid blow, good compaction efficiency at a relatively shallow depth, does not damage adjacent structures when compacted, less vibration, less civil complaints, and can shorten the air by simple construction, There is a problem that it is difficult to apply at a depth of more than 5m due to the limit of the improved depth.

한편 상기 동다짐공법은 약 20ton 전후의 중량물(Pounder)을 크레인 등으로 소정의 높이까지 들어올린 후 자유낙하시켜 떨어지는 낙하에너지를 이용하여 지반을 개량시키는 공법이며 비교적 깊은 심도까지 개량 가능한 공법으로 국내에서는 통상 심도 8m 전후까지의 개량에 적용하고 있다.On the other hand, the compaction method is a method of improving the ground using the falling energy by lifting the weight under about 20 tons (Pounder) to a predetermined height with a crane or the like and freely falling, and can be improved to a relatively deep depth in Korea. Usually, it is applied to the improvement to around 8m depth.

이러한 동다짐공법은, 공사비가 저렴하고, 적용범위가 넓어 공사기간이 단축되며, 깊은 심도까지 개량이 가능하나, 표면진동의 영향으로 인근 구조물에 구조적인 영향을 주며, 분진, 소음 등으로 민원 소지가 있는 지역은 적용하기 어렵고, 유압해머다짐공법에 비해 시공가격이 비싸고 시공속도가 느린 문제점이 있다.Such compaction method is cheaper in construction cost, wider scope of application, shorten construction period, and can be improved to deep depth, but it has structural influence on nearby structures due to surface vibration, and has a complaint about dust, noise, etc. There is a problem that the area is difficult to apply, and construction cost is high and construction speed is slow compared to the hydraulic hammer compaction method.

또한 중량물의 낙하고는 높으나 낙하지점에 중량물이 타격되는 순간 타격지점과 타격각도가 매회 타격시 마다 다르기 때문에 큰 에너지로 타격하더라도 우수한 타격효과를 얻기 어려운 문제점이 있다.In addition, even if the weight of the heavy fall, but the impact point and the angle of blow is different every time the heavy hits the falling point, there is a problem that it is difficult to obtain an excellent hitting effect even when hitting with a large energy.

한편 지반개량지역의 지하수위가 1.5m 이내 일 경우에는 유압해머를 통한 타격에너지의 효율이 저하되기 때문에 요구지지력을 얻을 수 없게 되고, 이로 인해 지하수위를 낮춘 후 지반개량지역을 시공해야 한다. On the other hand, if the groundwater level in the ground improvement area is within 1.5m, the required bearing capacity cannot be obtained because the efficiency of the blow energy through the hydraulic hammer is lowered. Therefore, the ground improvement area should be constructed after lowering the groundwater level.

종래에는 상기 지반개량지역의 내부 수위는 Deep Well 공법을 적용하여 배수하나 외부의 지하수유입이 왕성할 경우에는 지하수 유입을 차단하기 위해 그라우팅 공법을 적용한다.Conventionally, the internal water level of the ground improvement area is drained by applying the Deep Well method, but when the groundwater inflow is strong, a grouting method is applied to block the groundwater inflow.

그러나 이러한 그라우팅 공법은 시공비용이 매우 높아 전체적인 비용 및 공기가 늦어지는 문제점이 있다.
However, such a grouting method has a problem in that the construction cost is very high and the overall cost and air are late.

상기와 같은 문제점을 해결하기 위한 본 발명의 목적은, 복동 유압해머를 이용하여 자유낙하되는 램의 낙하속도를 자유낙하속도 이상으로 증속시켜 램이 다짐판을 타격하는 타격에너지를 증가시켜줌으로써 짧은 낙하고도로도 깊은 개량심도를 얻을 수 있도록 하고, 다짐판의 인발이 용이한 깊이까지만 다짐판을 타격한 후 채움재를 채우는 과정을 반복하면서 지반을 다져줌으로써 다짐판의 인발 작업이 간편하도록 하며, 개량하고자 하는 지반의 외곽으로 차수벽을 형성함으로써 개량하고자 하는 지반으로 지하수가 유입되는 것을 차단해줄 수 있도록 하는 복동 유압해머를 이용한 다짐공법을 제공함에 있다.
An object of the present invention for solving the above problems, by using a double-acting hydraulic hammer to increase the falling energy of the ram falling freely more than the free falling speed to increase the impact energy hitting the compaction plate short drop It is possible to obtain a deeper depth of improvement, and to make the drawing work of the compaction board simple by striking the ground while repeating the process of filling the filling material after hitting the compaction plate only to the depth where the compaction board can be easily drawn out. It is to provide a compaction method using a double-acting hydraulic hammer to block the groundwater flow into the ground to be improved by forming a barrier wall to the outside of the ground.

상기한 바와 같은 목적을 달성하고 종래의 결점을 제거하기 위한 과제를 수행하는 본 발명은, 유압해머의 램을 상승시킨 후 자유 낙하시켜 다짐판을 타격함으로써 개량하고자 하는 지반을 다져주는 유압해머다짐장치를 이용한 유압해머다짐공법에 있어서, 상기 램을 상승시키는 상부유압수단과, 상승된 램을 자유낙하속도 이상으로 하강시키는 하부유압수단이 구비된 복동 유압해머를 이용하여 다짐판을 타격함으로써 일 지점을 1차적으로 다져주되, 인발이 가능한 깊이까지만 다짐판이 매립되도록 다짐판을 타격하여 다져주는 단계(S100); 이후 상기 일 지점에 매립된 다짐판을 인발하고 다짐판의 매립에 의해 형성된 다짐홀에 채움재를 채워 넣어 일 지점의 2차 다짐이 가능하도록 하는 단계(S110); 이후 상기 (S100)단계와 (S110)단계를 수회 반복하여 일 지점을 다수 번 다져 줌으로써 지반의 개량심도를 향상시키는 단계(S120); 이후 (S100),(S110),(S120) 단계를 반복 시행하여 개량하고자 하는 지반의 타 지점들을 연속적으로 다져주는 단계(S130);를 포함하여 이루어진 것을 특징으로 한다.The present invention, which achieves the object as described above, and performs the problem for eliminating the conventional defects, hydraulic hammer compaction apparatus for compacting the ground to be improved by hitting the compaction plate after raising the ram of the hydraulic hammer freely In the hydraulic hammer compaction method using a double-acting hydraulic hammer equipped with an upper hydraulic means for raising the ram, and a lower hydraulic means for lowering the raised ram above the free fall speed by hitting the compaction plate. Firstly chopped, but striking the compaction plate to be compacted so that the compaction plate is embedded only up to the depth possible (S100); After drawing the compaction plate embedded in the one point and filling the filling material in the compaction hole formed by the filling of the compaction plate to enable a second compaction of one point (S110); Thereafter, the steps S100 and S110 are repeated several times, thereby improving the depth of improvement of the ground by compacting one point a plurality of times (S120). After (S100), (S110), (S120) by repeatedly performing the steps to stiffen the other points of the ground to be improved (S130); characterized in that it comprises a.

또한 본 발명은 상기 유압해머의 램을 상승시킨 후 자유 낙하시켜 다짐판을 타격함으로써 개량하고자 하는 지반을 다져주는 유압해머다짐장치를 이용한 유압해머다짐공법에 있어서, 상기 램을 상승시키는 상부유압수단과, 상승된 램을 자유낙하속도 이상으로 하강시키는 하부유압수단이 구비된 복동 유압해머를 이용하여 다짐판을 타격함으로써 일 지점을 1차적으로 다져주되, 인발이 가능한 깊이까지만 다짐판이 매립되도록 다짐판을 타격하여 다져주는 단계(S200); 이후 상기 일 지점에 매립된 다짐판을 인발하고 유압해머다짐장치를 타 지점으로 이동시킨 후 상기 (S200)단계와 같은 방법으로 타 지점을 다져주는 단계(S210); 이후 상기 (S210) 단계에서 다짐판의 매립시 형성된 다짐홀에 채움재를 채워 넣는 단계(S220); 이후 (S200), (S210), (S220)단계를 반복하면서 개량하고자 하는 지역의 타 지점들을 순차적으로 다져주는 단계(S230); 이후 상기 (S230) 단계를 통해 1차적으로 다짐된 모든 지점들을 상기 (S200),(S210),(S220),(S230)과 같은 단계로 2~3회 반복 다짐하여 개량심도를 향상시켜주는 단계를 포함하여 구성되는 것을 특징으로 한다.In another aspect, the present invention provides a hydraulic hammer compaction method using a hydraulic hammer compaction apparatus for compacting the ground to be improved by raising the ram of the hydraulic hammer to free fall by hitting the compaction plate, the upper hydraulic means for raising the ram; Using a double-acting hydraulic hammer equipped with a lower hydraulic means for lowering the raised ram above the free fall speed, the compaction plate is primarily compacted by hitting the compaction plate, but the compaction plate is embedded only to the depth where drawing is possible. Strike to chop (S200); After drawing the compaction plate embedded in the one point and moving the hydraulic hammer compaction device to another point step (S200) and the other step to compact the other point (S210); After the step (S210) step of filling the filling material into the compaction hole formed when the compaction plate (S220); After the step (S200), (S210), (S220) and repeating the step of sequentially compacting the other points of the region to be improved (S230); After the step (S230) to compact all the points that were primarily compacted to the same step (S200), (S210), (S220), (S230) repeated 2-3 times to improve the depth of improvement Characterized in that comprises a.

또한 상기 일 지점을 1차적으로 다져주기 전에 개량하고자 하는 지반의 외곽으로 차수벽을 더 형성하여 개량하고자 하는 지반으로 지하수가 유입되는 것을 차단해주는 것을 특징으로 한다.In addition, it is characterized in that the groundwater to prevent the inflow of groundwater to the ground to further improve by forming a water barrier to the outside of the ground to be improved before the first point to compact.

또한 상기 차수벽은 개량하고자 하는 지반의 외곽을 따라 지반을 굴착하고, 굴착된 지반의 내부에 방수포를 포설한 후 굴착된 토사를 되메움으로써 형성되는 것을 특징으로 한다.In addition, the order wall is characterized in that it is formed by excavating the ground along the outer periphery of the ground to be improved, by installing a tarpaulin in the interior of the excavated ground and backfill the excavated soil.

또한 상기 복동 유압해머의 램과 다짐판의 타격지점에 위치하도록 복동 유압해머와 다짐판의 외부에 주름관 형태의 소음차단관을 더 설치하여 복동 유압해머의 타격시 소음 발생을 줄여주는 것을 특징으로 한다.
In addition, by installing a noise shield tube of the corrugated pipe shape to the outside of the double-acting hydraulic hammer and the compaction plate to be located at the impact point of the ram and the compaction plate of the double-acting hydraulic hammer characterized in that to reduce the noise generated when the double-acting hydraulic hammer hit. .

이상에서 설명한 바와 같이 본 발명에 의하면, 복동 유압해머를 이용하여 자유낙하되는 유압해머의 낙하속도를 자유낙하속도 이상으로 증속시켜 램이 다짐판을 타격하는 타격에너지를 증가시켜줌으로써 짧은 낙하고도로도 큰 개량심도를 얻을 수 있어, 진동, 분진, 소음에 따른 민원을 해소하면서 동다짐공법을 적용해야 하는 지역에서도 적용이 가능하고, 다짐판의 인발이 용이한 깊이까지만 다진 후 다짐판을 인발하고 채움재를 채우면서 다시 다짐 작업을 반복 함으로써 다짐판의 인발시 크레인에 부하가 발생하지 않으며 치환다짐의 효과를 얻어 보다 우수한 품질의 지지력을 얻을 수 있고, 개량하고자 하는 지반의 외곽으로 방수포를 이용한 차수벽을 설치하여 외부지하수 유입을 차단해줌으로써 지반 다짐시 원하는 지지력을 얻을 수 있고, 시공 비용이 저렴하고 시공속도가 향상되는 매우 유용한 발명이다.
As described above, according to the present invention, by using the double-acting hydraulic hammer to increase the falling energy of the hydraulic hammer falling freely more than the free falling speed to increase the impact energy of the ram hitting the compaction plate is short Improved depth can be obtained, and it can be applied even in areas where the compaction method should be applied while eliminating complaints caused by vibration, dust, and noise. By repeating the compaction operation while filling, no load is generated on the crane when the compaction plate is pulled out, and it is possible to obtain a better quality of bearing capacity by obtaining the effect of replacement compaction. By blocking the external groundwater inflow, it is possible to obtain the desired bearing capacity when compacting the ground. It is a very useful invention that the cost is low and the construction speed is improved.

도 1 은 본 발명에 의한 유압해머 다짐장치를 나타낸 예시도,
도 2 는 본 발명에 의한 유압해머 다짐장치를 이용하여 지반 다짐 시공 상태를 나타낸 예시도,
도 3 은 본 발명에 의한 유압해머 다짐장치를 이용하여 지반의 분할다짐 과정을 나타낸 예시도,
도 4 는 본 발명의 일실시예에 의한 다짐공법의 흐름도,
도 5 는 본 발명의 다른 실시예에 의한 다짐공법의 흐름도,
도 6 은 본 발명에 의한 차수벽의 시공과정을 나타낸 예시도,
도 7 은 본 발명에 의한 유압해머다짐장치에 소음차단관를 설치하는 과정을 나타낸 예시도,
도 8 은 본 발명에 의한 유압해머다짐장치에 소음차단관의 설치상태를 나타낸 예시도,
도 9 는 본 발명에 의한 유압해머다짐창치에 소음차단관을 설치하여 시공하는 상태를 나타낸 예시도,
1 is an exemplary view showing a hydraulic hammer compaction apparatus according to the present invention,
2 is an exemplary view showing a ground compaction construction state using the hydraulic hammer compaction apparatus according to the present invention,
3 is an exemplary view showing a process for splitting compaction of ground using a hydraulic hammer compaction apparatus according to the present invention;
4 is a flow chart of the compaction method according to an embodiment of the present invention,
5 is a flowchart of a compaction method according to another embodiment of the present invention;
6 is an exemplary view showing a construction process of the order wall according to the present invention,
7 is an exemplary view showing a process of installing a noise barrier pipe in the hydraulic hammer compaction apparatus according to the present invention,
8 is an exemplary view showing an installation state of the noise barrier pipe in the hydraulic hammer compaction apparatus according to the present invention,
9 is an exemplary view showing a state in which the installation of the noise barrier pipe in the hydraulic hammer compaction window according to the present invention,

이하 본 발명의 실시 예인 구성과 그 작용을 첨부도면에 연계시켜 상세히 설명하면 다음과 같다. 또한 본 발명을 설명함에 있어서, 관련된 공지기능 혹은 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명은 생략한다.Hereinafter, the configuration and the operation of the embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the following description of the present invention, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the subject matter of the present invention rather unclear.

도 1 은 본 발명에 의한 유압해머 다짐장치를 나타낸 예시도, 도 2 는 본 발명에 의한 유압해머 다짐장치를 이용하여 지반 다짐 시공 상태를 나타낸 예시도, 도 3 은 본 발명에 의한 유압해머 다짐장치를 이용하여 지반의 분할다짐 과정을 나타낸 예시도로서,1 is an exemplary view showing a hydraulic hammer compaction apparatus according to the present invention, Figure 2 is an exemplary view showing a ground compaction construction state using the hydraulic hammer compaction apparatus according to the present invention, Figure 3 is a hydraulic hammer compaction apparatus according to the present invention As an illustration showing the process of compaction of the ground using

본 발명은 복동 유압해머(210)와, 상기 복동 유압해머(210)에 의해 가격됨으로서 지반을 다져주는 다짐판(250)을 포함하여 구성되는 유압해머다짐장치(200)를 이용하여 지반개량지역을 다져주는 것이다.The present invention utilizes a hydraulic hammer compaction apparatus 200 including a double-acting hydraulic hammer 210 and a compaction plate 250 to compact the ground by being priced by the double-acting hydraulic hammer 210. It is to chop.

상기 이러한 유압해머다짐장치(200)는 크레인(100)의 일측에 설치되는 리더(120)에 안내되어 원하는 위치에 위치하게 된다.The hydraulic hammer compaction apparatus 200 is guided to the leader 120 installed on one side of the crane 100 is positioned in a desired position.

상기 복동 유압해머(210)의 상단에는 와이어(130)가 연결되어 유압해머다짐장치를(200)를 리더(120) 상에서 이동시킬 수 있도록 한다.A wire 130 is connected to the upper end of the double-acting hydraulic hammer 210 to move the hydraulic hammer compaction apparatus 200 on the leader 120.

한편 상기 복동 유압해머(210)는 상기 리더(120)에 안내되도록 설치되고 상기 와이어(130)가 상부에 연결되는 케이싱(220)과, 상기 케이싱(220)의 내부에 설치되어 유압에 의해 작동됨으로써 상기 다짐판(250)을 타격해주는 램(230)과, 상기 케이싱(220)의 상부에 설치되어 상기 램(230)을 상부로 들어 올려주는 상부유압수단(240)과, 상기 케이싱(220)의 하부에 설치되어 상기 상부유압수단(240)에 의해 상승된 램(230)이 낙하될 경우 램(230)을 자유낙하속도 이상의 속도로 하강시켜 램(230)에 의한 다짐판(250)의 타격에너지가 증가될 수 있도록 하는 하부유압수단(241)을 포함하여 구성된다.On the other hand, the double-acting hydraulic hammer 210 is installed to be guided to the leader 120 and the wire 130 is connected to the upper and the casing 220 is installed inside the casing 220 is operated by hydraulic pressure Ram 230 that strikes the compaction plate 250, the upper hydraulic means 240 is installed on the upper portion of the casing 220 to lift the ram 230, and the casing 220 When the ram 230 raised by the upper hydraulic means 240 is installed in the lower portion falls down the ram 230 at a speed more than the free fall speed to hit the energy of the compaction plate 250 by the ram 230 It is configured to include a lower hydraulic means 241 to be increased.

상기 하부유압수단(241)은 램(230)이 상승된 후 낙하되는 낙하시작지점에서 램(230)을 하부방향으로 자유낙하속도 이상의 속도로 가속시켜주는 것이다. The lower hydraulic means 241 is to accelerate the ram 230 in the downward direction at a speed of more than the free fall speed at the drop start point where the ram 230 is raised after falling.

이러한 본 발명의 복동 유압해머(210)는 주지관용의 공지된 유압해머로서 더 이상의 상세한 설명은 생략한다.The double-acting hydraulic hammer 210 of the present invention is a known hydraulic hammer for the main pipe, and further detailed description thereof will be omitted.

도 4 는 본 발명의 일실시예에 의한 다짐공법의 흐름도로서, 상기와 같이 구성되는 유압해머다짐장치(200)를 이용하여 일실시예에 의한 다짐공법을 설명하면, 먼저 램(230)을 상승시키는 상부유압수단(240)과, 상승된 램(230)을 자유낙하속도 이상으로 하강시키는 하부유압수단(241)이 구비된 복동 유압해머(210)를 이용하여 다짐판(250)을 타격함으로써 일 지점을 1차적으로 다져주되, 인발이 가능한 깊이까지만 다짐판(250)이 매립되도록 다짐판(250)을 타격하여 다져주는 단계와(S100), 이후 상기 일 지점에 매립된 다짐판(250)을 인발하고 복동 유압해머(210)의 램(230) 타격에 의해 다짐판(250)이 일 지점에 매립됨으로써 형성되는 다짐홀(500)에 채움재(510)를 채워 넣어 일 지점의 2차 다짐이 가능하도록 하는 단계(S110)와, 이후 상기 (S100)단계와 (S110) 단계를 수회 반복하여 일 지점을 다수 번 다져줌으로써 지반의 개량심도가 향상될 수 있도록 하는 단계(S120)와, 이후 상기 (S100),(S110),(S120) 단계를 반복 시행하여 개량하고자 하는 지반의 타 지점들을 연속적으로 다져주는 단계(S130);를 포함하여 이루어진 진다.Figure 4 is a flow chart of the compaction method according to an embodiment of the present invention, when using the hydraulic hammer compaction apparatus 200 configured as described above describes the compaction method according to an embodiment, first raise the ram 230 By hitting the compaction plate 250 using the double-acting hydraulic hammer 210 is provided with the upper hydraulic means 240 to lower, and the lower hydraulic means 241 for lowering the raised ram 230 above the free fall speed. The first step is to chop the compaction, hitting the compaction plate 250 so that the compaction plate 250 is embedded only to the depth possible to draw (S100), and then the compaction plate 250 embedded in the one point Drawing and filling the filling material 510 in the compaction hole 500 is formed by the compaction plate 250 is buried at one point by the ram 230 hit by the double-acting hydraulic hammer 210, the second compaction of one point is possible. Step (S110), and then repeat the steps (S100) and (S110) several times. Step (S120) to improve the improved depth of the ground by compacting one point a number of times, and then repeats the steps (S100), (S110), (S120) to the other points of the ground to be improved continuously Comprising the step (S130); is made, including.

이와 같은 본 발명의 일실시예에 의한 유압해머 다짐공법은 개량하고자 하는 지반의 일 지점의 다짐이 완료된 후 인접하는 타 지점들을 연속적으로 다져주는 공법이다.The hydraulic hammer compacting method according to an embodiment of the present invention as described above is a method of continuously compacting the other adjacent points after the compaction of one point of the ground to be improved.

한편 도 5 는 본 발명의 다른 실시예에 의한 다짐공법의 흐름도로서, 본 발명의 다른 실시예에 의한 유압해머 다짐공법은, 상기 램(230)을 상승시키는 상부유압수단(240)과, 상승된 램(230)을 자유낙하속도 이상으로 하강시키는 하부유압수단(241)이 구비된 복동 유압해머(210)를 이용하여 다짐판(250)을 타격함으로써 일 지점을 1차적으로 다져주되, 인발이 가능한 깊이까지만 다짐판(250)이 매립되도록 다짐판(250)을 타격하여 다져주는 단계(S200)와, 이후 상기 일 지점에 매립된 다짐판(250)을 인발하고 유압해머다짐장치(200)를 타 지점으로 이동시킨 후 상기 (S200)단계와 같은 방법으로 타 지점을 다져주는 단계(S210)와, 이후 상기 (S210)단계에서 다짐판(250)이 타격되어 지반에 매립됨으로써 형성되는 다짐홀에 채움재를 채워 넣어 유압해머다짐장치(200)를 이용 한 재 다짐이 가능하도록 하는 단계(S220)와, 이후 상기 (S200), (S210), (S220)단계를 반복하면서 개량하고자 하는 지역의 타 지점들을 순차적으로 연속하여 다져주는 단계(S230)와, 이후 상기 (S230) 단계를 통해 1차적으로 다짐되고 채움재(510)가 채워진 모든 지점들을 상기 (S200), (S210), (S220), (S230)과 같은 단계로 2~3회 반복 다짐하여 개량심도를 향상시켜주는 단계(S240)를 포함하여 이루어진다.5 is a flow chart of the compaction method according to another embodiment of the present invention, the hydraulic hammer compaction method according to another embodiment of the present invention, the upper hydraulic means 240 for raising the ram 230, and By hitting the compaction plate 250 by using the double-acting hydraulic hammer 210 provided with the lower hydraulic means 241 for lowering the ram 230 above the free fall speed, it is possible to squeeze a single point first, Step to hit the compaction plate 250 so that the compaction plate 250 is embedded only to the depth (S200), and then drawing up the compaction plate 250 embedded in the one point and hit the hydraulic hammer compaction apparatus 200 After moving to a point (S210) and the other step in the same way as the step (S210), and then in the step (S210) the compaction plate 250 is filled in the compaction hole formed by hitting the ground Filling the ash using the hydraulic hammer compactor (200) Step (S220) to enable the compaction, and then sequentially (S230) to sequentially compact other points of the region to be improved while repeating the steps (S200), (S210), (S220), and then The first step through the (S230) and the filling material 510 is filled all the points filled with (510) repeatedly repeated 2-3 times in the same step (S200), (S210), (S220), (S230) to improve the depth Improving step (S240) is made.

이와 같은 다른 실시예에 의한 본 발명은 일 지점의 다짐을 완료하고 타 지점을 다짐 하는 동안 일 지점에 형성된 다짐홀(500)에 채움재(510)를 채워넣음으로써 채움재(510)를 채워 넣는 동안에 유압해머다짐장치(200)를 이용하여 타 지점을 다져줌으로써 작업의 대기 시간이 적어 작업 효율이 매우 향상된다.
According to another embodiment of the present invention, while filling the filling material 510 by filling the filling material 510 in the compaction hole 500 formed at one point while completing the compaction of one point and compacting the other point. By using the hammer compaction apparatus 200 to compact other points, the waiting time of the work is reduced, and the work efficiency is greatly improved.

한편 상기 각 실시예에 의한 본 발명의 다짐공법은, 상기 하부유압수단(241)을 이용하여 자유낙하속도로 낙하되는 램(230)의 낙하속도를 자유낙하속도의 이상으로(1.8~2.4배) 증속시켜 줌으로써 램(230)이 다짐판(250)을 타격할 경우 타격에너지 또한 증가되어 짧은 낙하고도로도 낙하속도 증가에 의해 타격에너지가 향상되어 보다 큰 깊은 개량심도를 얻을 수 있게 되는 것이다.On the other hand, the compaction method of the present invention according to the embodiments, the falling speed of the ram 230 falling at the free fall speed using the lower hydraulic means 241 or more (1.8 ~ 2.4 times) the free fall speed When the ram 230 hits the compaction plate 250 by increasing the speed, the impact energy is also increased, and the impact energy is improved by increasing the falling speed even in a short drop.

또한 동일한 지점에 반복 타격이 가능하여 작은 에너지로도 우수한 타격효과를 얻을 수 있다.In addition, it is possible to repeatedly hit the same point, it is possible to obtain an excellent hitting effect even with a small energy.

한편 상기 다짐판(250)의 인발이 용이한 깊이는 대략 1m 정도로써, 1m 이상으로 다짐판(250)이 매립될 경우에는, 다짐판(250)이 너무 깊게 매립되어 인발하지 못하거나, 다짐판(250)을 인발하기 위한 크레인에 부하가 발생되어 다짐판(250)을 인발하기 위한 장비가 파손되는 문제점이 있다.On the other hand, the depth at which the compaction plate 250 is easy to draw is about 1 m, and when the compaction plate 250 is embedded at 1 m or more, the compaction plate 250 is embedded so deeply that it cannot be drawn out, or the compaction plate A load is generated in the crane for drawing the 250, there is a problem that the equipment for drawing the compaction plate 250 is broken.

즉 본 발명은 하부유압수단(241)에 의해 램(230)이 다짐판(250)을 타격하는 타격에너지가 증가되어 종래의 유압해머다짐공법에서와 같이 한 지점에 40~60회 타격하게 되면 다짐판(250)이 2m 이상 지중으로 매몰되어 다짐판(250)을 인발하는데 큰 무리가 따르거나 불가능하기 때문에, 상기 다짐하고자 하는 지점을 타격하는 횟수는 13~20회 정도로 하고 다짐판(250)의 매몰 깊이가 1m 정도로 유지될 수 있도록 한 후 다짐판(250)을 인발함으로써 다짐판(250)의 인발이 용이하게 이루어질 수 있도록 한다.That is, in the present invention, the ram energy of the ram 230 hitting the compaction plate 250 is increased by the lower hydraulic means 241, and then compacted when hitting 40 to 60 times at one point as in the conventional hydraulic hammer compacting method. Since the plate 250 is buried in the ground for 2m or more and a large crowd follows or is impossible to draw the compaction plate 250, the number of hitting points to be compacted is about 13 to 20 times and the compaction plate 250 is After the investment depth is maintained at about 1m, the compaction plate 250 is drawn out so that the compaction plate 250 can be easily drawn out.

이와 같은 본 발명은 다짐판(250)이 인발이 용이한 깊이인 1m 정도로 침하될 정도의 타격횟수로 타격하고, 다짐에 의해 형성된 다짐홀(500) 내부에 양질토나 쇄석 등의 채움재(510)를 채워서 2차 또는 3차 다짐이 가능하도록 함으로써 다짐판(250)의 인발시 크레인(100)의 붐(110)이 파손되거나, 무리한 인발에 의해 와이어(130)가 절단되어 유압해머(210)와 다짐판(250)이 분리 파손되지 않도록 하고, 주위의 양질토 또는 쇄석 등의 채움재(510)가 채워짐으로서 치환 다짐의 효과를 얻어 보다 우수한 품질의 지지력을 얻을 수 있게 된다.In the present invention as described above, the compaction plate 250 strikes at a number of hits such as to be settled down to about 1m, which is easy to pull out, and the filling material 510 such as high-quality soil or crushed stone in the compaction hole 500 formed by the compaction. By filling the secondary or tertiary compaction is possible, the boom 110 of the crane 100 is broken when the compaction plate 250 is pulled out, or the wire 130 is cut by the excessive pulling to compact with the hydraulic hammer 210. The plate 250 is not separated and damaged, and the filling material 510 such as high quality soil or crushed stone is filled, thereby obtaining the effect of replacement compaction, thereby obtaining support of higher quality.

도 6 은 본 발명에 의한 차수벽의 시공과정을 나타낸 예시도로서, 본 발명은 상기 각 실시예에서 일 지점을 1차적으로 다져주는 작업을 하기 전에 개량하고자 하는 지반의 외곽으로 차수벽(300)을 더 형성하여 개량하고자 하는 지반으로 지하수가 유입되는 것을 차단해줄 수 있다.
Figure 6 is an exemplary view showing the construction process of the order wall according to the present invention, the present invention is further added to the order wall 300 to the outside of the ground to be improved before the operation to first compact the point in each of the above embodiments It can block groundwater from entering the ground to be formed and improved.

이러한 차수벽(300)은, 개량하고자 하는 지반의 외곽을 따라 굴삭기를 이용하여 4m 전후의 깊이로 굴삭하여 굴삭홈(310)을 형성하고, 상기 굴삭홈(310) 내부의 바닥까지 닿게 방수포(320)를 펼쳐지도록 포설한 후 굴삭된 토사를 되메워 줌으로써 완료된다.The order wall 300 is excavated to a depth of about 4m using an excavator along the outer periphery of the ground to be improved to form an excavation groove 310, the tarpaulin 320 to reach the bottom inside the excavation groove 310 This is done by laying out to unfold and then backfilling the excavated soil.

한편 상기 굴삭홈(310)의 내부에는 방수포(320) 이외에도 비닐 등의 물의 흐름을 차단할 수 있는 재질의 차단막을 설치할 수 있다.On the other hand, in addition to the waterproof cloth 320, the excavation groove 310 may be provided with a blocking film of a material that can block the flow of water, such as vinyl.

이러한 본 발명은 개량하고자 하는 지반의 외곽에서 유입되는 4m이내 깊이의 지하수는 매립된 토사의 압력과 비밀 또는 방수포(320)에 설치작용에 의해 차단되고, 4m 이상 깊이를 통해 유입되는 지하수는 유입속도가 매우 느려 지반개량지역을 다짐하는데 있어, 유입되는 지하수를 차단함으로써 액상화 방지 및 다짐효율을 극대화 할 수 있다. The present invention is ground water of less than 4m depth flowing from the ground to be improved by the action of the buried soil and the installation or secret or tarpaulin 320, groundwater flowing through more than 4m depth is the inflow rate Is very slow in compacting the ground improvement area, by blocking the incoming ground water can maximize the prevention of liquefaction and compaction efficiency.

또한 종래와 같이 그라우팅 공법을 적용하는 것에 비하여 매우 저렴하게 지하수 유입을 차단할 수 있고 영구적인 차단이 아닌 지반개량지역의 공사기간 동안만의 차단효과를 얻는데 매우 용이하다.In addition, compared to the conventional grouting method applied to the groundwater can be blocked at a very low cost and it is very easy to obtain the blocking effect only during the construction period of the ground improvement area, not permanent blockage.

도 7 은 본 발명에 의한 유압해머다짐장치에 소음차단관를 설치하는 과정을 나타낸 예시도, 도 8 은 본 발명에 의한 유압해머다짐장치에 소음차단관의 설치상태를 나타낸 예시도, 도 9 는 본 발명에 의한 유압해머다짐창치에 소음차단관을 설치하여 시공하는 상태를 나타낸 예시도로서,Figure 7 is an exemplary view showing a process of installing a noise barrier pipe in the hydraulic hammer compaction apparatus according to the present invention, Figure 8 is an exemplary view showing an installation state of the noise shield pipe in the hydraulic hammer compaction apparatus according to the present invention, Figure 9 As an exemplary view showing a state in which a noise barrier pipe is installed and installed in a hydraulic hammer compaction window according to the present invention,

본 발명은 복동 유압해머(210)의 램(230)이 다짐판(250)을 타격하는 지점에 위치하도록 복동 유압해머(210)와 다짐판(250)의 외부에 끼워지도록 설치되어 램(230)이 다짐판(250)을 타격할 경우에 발생되는 소음을 줄여줄 수 있는 소음차단관(400)을 더 포함하여 구성된다.The present invention is installed so as to be fitted to the outside of the double-acting hydraulic hammer 210 and the compaction plate 250 so that the ram 230 of the double-acting hydraulic hammer 210 hits the compaction plate 250, the ram 230 It further comprises a noise blocking tube 400 that can reduce the noise generated when hitting the compaction plate 250.

상기 소음차단관(400)은 요부(410)와 철부(420)가 교번적으로 형성되어 신축이 가능하도록 구성되는 주름관 형태로 구성한다.The noise blocking tube 400 is configured in the form of a corrugated pipe formed so that the concave portion 410 and the convex portion 420 are alternately formed.

이러한 소음차단관(400)은 유압해머(210)의 타격에 의해 다짐판(250)이 지표면 이하로 침하될 경우, 신축되어 손상되지 않게 된다.The noise barrier tube 400 is stretched and damaged when the compaction plate 250 is settled below the ground surface by the impact of the hydraulic hammer 210.

즉 다짐판(250)이 침하되더라도 주름관 형태의 소음차단관(400)이 다짐판(250)의 침하와 함께 접혀지게 되어 파손되지 않게 된다.
That is, even when the compaction plate 250 is settled, the noise blocking tube 400 of the corrugated pipe form is folded together with the settlement of the compaction plate 250 so as not to be damaged.

이와 같이 본 발명은 짧은 낙하고도로도 낙하속도 증가에 의해 큰 개량심도를 얻을 수 있게 되어, 진동, 분진, 소음에 따른 민원은 해소하면서 동다짐공법을 적용해야 하는 지역에서도 적용이 가능하고, 가격이 저렴하며, 시공속도가 향상된다.
In this way, the present invention can obtain a large depth of improvement by increasing the falling speed even on a short drop road, and can be applied even in areas where the compaction method should be applied while eliminating complaints due to vibration, dust, and noise. It is inexpensive and construction speed is improved.

본 발명은 상술한 특정의 바람직한 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.
It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined in the appended claims and their equivalents. Of course, such modifications are within the scope of the claims.

(100) : 크레인 (110) : 붐
(120) : 리더 (130) : 와이어
(200) : 유압해머다짐장치 (210) : 복유압해머
(220) : 케이싱 (230) : 램
(240) : 상부유압수단 (241) : 하부유압수단
(250) : 다짐판 (300) : 차수벽
(310) : 굴삭홈 (320) : 방수포
(400) : 소음차단관 (410) : 요부
(420) : 철부 (500) : 다짐홀
(510) : 채움재
100: crane 110: boom
120: leader 130: wire
(200): hydraulic hammer compaction device (210): double hydraulic hammer
220: Casing 230: Ram
240, upper hydraulic means 241: lower hydraulic means
250: compaction plate 300: order wall
(310): excavation groove (320): tarpaulin
(400): sound insulation pipe (410): main part
(420): iron part 500: compaction hole
(510): Filler

Claims (5)

유압해머의 램을 상승시킨 후 자유 낙하시켜 다짐판을 타격함으로써 개량하고자 하는 지반을 다져주는 유압해머다짐장치를 이용한 유압해머다짐공법에 있어서,
상기 램을 상승시키는 상부유압수단과, 상승된 램을 자유낙하속도 이상으로 하강시키는 하부유압수단이 구비된 복동 유압해머를 이용하여 다짐판을 타격함으로써 일 지점을 1차적으로 다져주되, 인발이 가능한 깊이까지만 다짐판이 매립되도록 다짐판을 타격하여 다져주는 단계(S100);
이후 상기 일 지점에 매립된 다짐판을 인발하고 다짐판의 매립에 의해 형성된 다짐홀에 채움재를 채워 넣어 일 지점의 2차 다짐이 가능하도록 하는 단계(S110);
이후 상기 (S100)단계와 (S110)단계를 수회 반복하여 일 지점을 다수 번 다져 줌으로써 지반의 개량심도를 향상시키는 단계(S120);
이후 (S100),(S110),(S120) 단계를 반복 시행하여 개량하고자 하는 지반의 타 지점들을 순차적으로 다져주는 단계(S130);를 포함하여 이루어진 것을 특징으로 하는 복동 유압해머를 이용한 다짐공법.
In the hydraulic hammer compacting method using the hydraulic hammer compacting device to compact the ground to be improved by raising the ram of the hydraulic hammer and then freely falling and hitting the compaction plate.
Using a double-acting hydraulic hammer equipped with an upper hydraulic means for raising the ram and a lower hydraulic means for lowering the raised ram above a free fall speed, it is possible to squeeze the compaction plate primarily to draw a point. Hitting the compaction plate so that the compaction plate is embedded only up to the depth (S100);
After drawing the compaction plate embedded in the one point and filling the filling material in the compaction hole formed by the filling of the compaction plate to enable a second compaction of one point (S110);
Thereafter, the steps S100 and S110 are repeated several times, thereby improving the depth of improvement of the ground by compacting one point a plurality of times (S120).
Then (S100), (S110), (S120) by repeatedly performing the step of stepping the other points of the ground to be improved (S130); compaction method using a double-acting hydraulic hammer, characterized in that it comprises a.
유압해머의 램을 상승시킨 후 자유 낙하시켜 다짐판을 타격함으로써 개량하고자 하는 지반을 다져주는 유압해머다짐장치를 이용한 유압해머다짐공법에 있어서,
상기 램을 상승시키는 상부유압수단과, 상승된 램을 자유낙하속도 이상으로 하강시키는 하부유압수단이 구비된 복동 유압해머를 이용하여 다짐판을 타격함으로써 일 지점을 1차적으로 다져주되, 인발이 가능한 깊이까지만 다짐판이 매립되도록 다짐판을 타격하여 다져주는 단계(S200);
이후 상기 일 지점에 매립된 다짐판을 인발하고 유압해머다짐장치를 타 지점으로 이동시킨 후 상기 (S200)단계와 같은 방법으로 타 지점을 다져주는 단계(S210);
이후 상기 (S210) 단계에서 다짐판의 매립시 형성된 다짐홀에 채움재를 채워 넣는 단계(S220);
이후 (S200), (S210), (S220)단계를 반복하면서 개량하고자 하는 지역의 타 지점들을 순차적으로 다져주는 단계(S230);
이후 상기 (S230) 단계를 통해 1차적으로 다짐된 모든 지점들을 상기 (S200),(S210),(S220),(S230)과 같은 단계로 2~3회 반복 다짐하여 개량심도를 향상시켜주는 단계;를 포함하여 구성되는 것을 특징으로 하는 복동 유압해머를 이용한 다짐공법.
In the hydraulic hammer compacting method using the hydraulic hammer compacting device to compact the ground to be improved by raising the ram of the hydraulic hammer and then freely falling and hitting the compaction plate.
Using a double-acting hydraulic hammer equipped with an upper hydraulic means for raising the ram and a lower hydraulic means for lowering the raised ram above a free fall speed, it is possible to squeeze the compaction plate primarily to draw a point. Hitting the compaction plate so that the compaction plate is embedded only up to the depth (S200);
After drawing the compaction plate embedded in the one point and moving the hydraulic hammer compaction device to another point step (S200) and the other step to compact the other point (S210);
After the step (S210) step of filling the filling material into the compaction hole formed when the compaction plate (S220);
After the step (S200), (S210), (S220) and repeating the step of sequentially compacting the other points of the region to be improved (S230);
After the step (S230) to compact all the points that were primarily compacted to the same step (S200), (S210), (S220), (S230) repeated 2-3 times to improve the depth of improvement Compaction method using a double-acting hydraulic hammer, characterized in that comprising a.
제 1 항 또는 제 2 항에 있어서,
상기 일 지점을 1차적으로 다져주기 전에 개량하고자 하는 지반의 외곽으로 차수벽을 더 형성하여 개량하고자 하는 지반으로 지하수가 유입되는 것을 차단해줌으로써 액상화 방지 및 다짐효율을 극대화 할 수 있는 것을 특징으로 하는 복동 유압해머를 이용한 다짐공법.
The method according to claim 1 or 2,
Double acting to prevent liquefaction and maximize compaction efficiency by blocking the inflow of groundwater to the ground to be improved by further forming a barrier wall outside the ground to be improved before first compacting the one point. Compaction method using hydraulic hammer.
제 3 항에 있어서,
상기 차수벽은 개량하고자 하는 지반의 외곽을 따라 지반을 굴착하여, 굴착된 지반의 내부에 방수포를 포설한 후 굴착된 토사를 되메움으로써 형성되는 것을 특징으로 하는 복동 유압해머를 이용한 다짐공법.
The method of claim 3, wherein
The order wall is a compaction method using a double-acting hydraulic hammer characterized in that the excavation of the ground along the outer periphery of the ground to be improved, by installing a tarpaulin inside the excavated ground and backfill the excavated soil.
제 1 항 또는 제 2 항에 있어서,
상기 복동 유압해머의 램과 다짐판의 타격지점에 위치하도록 복동 유압해머와 다짐판의 외부에 주름관 형태의 소음차단관을 더 설치하여 복동 유압해머의 타격시 소음 발생을 줄여주는 것을 특징으로 하는 복동 유압해머를 이용한 다짐공법.
The method according to claim 1 or 2,
Double acting hydraulic hammer and the compaction plate to the outside of the double-acting hydraulic hammer and the compaction plate to be located at the impact point of the double-acting hydraulic hammer to reduce the noise generated when hitting the double-acting hydraulic hammer Compaction method using hydraulic hammer.
KR1020110000063A 2011-01-03 2011-01-03 Method using double-acting pile hydraulic hammer KR20120078807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110000063A KR20120078807A (en) 2011-01-03 2011-01-03 Method using double-acting pile hydraulic hammer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110000063A KR20120078807A (en) 2011-01-03 2011-01-03 Method using double-acting pile hydraulic hammer

Publications (1)

Publication Number Publication Date
KR20120078807A true KR20120078807A (en) 2012-07-11

Family

ID=46712014

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110000063A KR20120078807A (en) 2011-01-03 2011-01-03 Method using double-acting pile hydraulic hammer

Country Status (1)

Country Link
KR (1) KR20120078807A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351204A (en) * 2016-09-08 2017-01-25 河海大学 Shallow soft soil solidifying device and solidifying method thereof
CN107489138A (en) * 2017-08-28 2017-12-19 中化岩土集团股份有限公司 A kind of stable dynamic compaction machinery of centre of gravity structural behaviour
KR20230152190A (en) * 2022-03-29 2023-11-03 안신환 Ground compaction apparatus and method using cylindrical penetration body

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351204A (en) * 2016-09-08 2017-01-25 河海大学 Shallow soft soil solidifying device and solidifying method thereof
CN106351204B (en) * 2016-09-08 2018-02-23 河海大学 A kind of shallow layer soft soil solidification equipment and its curing
CN107489138A (en) * 2017-08-28 2017-12-19 中化岩土集团股份有限公司 A kind of stable dynamic compaction machinery of centre of gravity structural behaviour
KR20230152190A (en) * 2022-03-29 2023-11-03 안신환 Ground compaction apparatus and method using cylindrical penetration body

Similar Documents

Publication Publication Date Title
CN111335306A (en) Rapid construction method for deep and thick hard rock section drilled pile
CN110055948A (en) A kind of big Treatment Methods of Karst Foundation of depth and device
CN110258538A (en) A kind of soil nailing reinforces buffer-type artificial digging pile and its construction method
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN107964971A (en) A kind of precipitation method of subway station using the construction of PBA engineering methods
KR20120078807A (en) Method using double-acting pile hydraulic hammer
CN107780407B (en) Secondary precipitation union dynamic consolidation soft base processing method
CN112227337A (en) Device for tamping and leveling asphalt concrete cushion between pile foundations of soft land and construction method
CN112921947A (en) Foundation construction method in house building construction
CN102787608B (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN114961336B (en) Protective demolition construction method for foundation pile of basement close to existing subway line
CN204225101U (en) The construction equipment of concrete pile
CN104153355B (en) The constructing device of concrete-pile and construction method thereof
CN104110034B (en) The construction of Static Pressure Pile method of casting and penetrating resistance can be reduced
CN102635044B (en) Treating method of dynamic compacter for excavation roadbed
RU170995U1 (en) Rammed foundation
CN205776209U (en) The construction equipment of concrete-pile
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED
CN101709582A (en) Protection method for reducing soil extrusion in construction of prefabricated piles
CN112854198B (en) Construction method for treating old foundation of underground diaphragm wall
CN211080248U (en) Deep foundation pit supporting structure of adjacent road under complex geological condition
CN212026271U (en) Supporting construction of weak soil foundation ditch
CN204982857U (en) Three -dimensional multichannel drainage combination tamping unit of low level negative pressure
JP2015148105A (en) Ground improving method and ground improving system
CN113957874A (en) Construction method for constructing road on soft soil foundation

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal