KR20120048152A - Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof - Google Patents

Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof Download PDF

Info

Publication number
KR20120048152A
KR20120048152A KR1020100109627A KR20100109627A KR20120048152A KR 20120048152 A KR20120048152 A KR 20120048152A KR 1020100109627 A KR1020100109627 A KR 1020100109627A KR 20100109627 A KR20100109627 A KR 20100109627A KR 20120048152 A KR20120048152 A KR 20120048152A
Authority
KR
South Korea
Prior art keywords
temporary
filler
tunnel
divided
pipe
Prior art date
Application number
KR1020100109627A
Other languages
Korean (ko)
Other versions
KR101312668B1 (en
Inventor
정근석
Original Assignee
대지종건(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대지종건(주) filed Critical 대지종건(주)
Priority to KR1020100109627A priority Critical patent/KR101312668B1/en
Publication of KR20120048152A publication Critical patent/KR20120048152A/en
Application granted granted Critical
Publication of KR101312668B1 publication Critical patent/KR101312668B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/20Special cross- sections, e.g. corrugated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE: A non-excavation type tunnel and a conduit using corrugated or rugged panels and a construction method thereof are provided to remarkably reduce construction time and costs by enabling the easy installation of pipe bodies. CONSTITUTION: A non-excavation type tunnel and a conduit using corrugated or rugged panels comprise corrugated or rugged panels(1). The corrugated or rugged panels are coupled to each other through multiple coupling units in a circular or arched shape. The coupled panels are inserted into an excavated hole. Pipe bodies are inserted into the coupled panels. A guide pipe(5) for a filler and reinforcement supply hose is installed on the top surface or bottom surface of the uppermost panel.

Description

분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로와 그의 시공공법{Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof}Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method

본 발명은 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로와 그의 시공공법에 관한 것으로 더욱 상세하게는 상수관로, 암거를 포함한 하수관로, 수로, 도로 및 철도용 횡 배수로 및 보?차도, 제방 횡단용 횡 배수로, 지하차도, 지하 저장고, 가스관로, 통신관로, 전력 관로, 지하 격납고, 에코 터널, 수직구 및 터널 등을 완전시공하기에 앞서 설치되는 비개착 가설 터널 및 관로를 분할 파형 또는 요철판으로 구축하되, 비개착 가설 터널 및 관로의 최상방부에 위치되는 분할 파형 또는 요철판의 내부 또는 외부에 채움재 겸 보강재 공급호스 안내관을 설치하여 가설 터널 및 관로의 외주면과 굴진공 사이의 틈새 또는 관체의 외주면과 비개착 가설 터널 및 관로의 내주면 사이에 형성되는 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 원활하고도 완벽하게 충진시킬 수 있도록 하고, 또 필요에 따라서는 최하방부에 위치되는 분할 파형 또는 요철판에는 일반 레일형 또는 철근 및 와이어 메쉬 삽입홈이 구비된 관체 받침 및 간격재 겸용 레일을 설치하여 비개착 가설 터널 및 관로를 설치한 후 그 내부로 각종 관체를 설치할 때 관체 자체가 원활히 미끄러져 삽입될 수 있도록 함은 물론 각종 관체의 외주면과 비개착 가설 터널 및 관로의 내주면 사이에 동일한 공간부가 구비되어 차후 이들 공간부에 채움재 겸 보강재를 원활히 충진시킬 수 있을 뿐만 아니라 이들 공간부에 설치되는 철근 또는 와이어 메쉬를 관체 받침 및 간격재 겸용 레일의 설치 여부에 무관하게 원활히 설치할 수 있도록 발명한 것이다.
The present invention relates to unattached temporary tunnels and pipelines using divided waveforms or irregularities and their construction methods. More particularly, the present invention relates to water pipes, sewer pipes including culverts, waterways, roads and rail transverse drainages and pavements, embankment crossings. Split corrugated or uneven plate for non-adjacent temporary tunnels and pipelines installed prior to complete construction of transverse drainage, underground roadway, underground storage, gas pipelines, communication pipelines, power pipelines, underground hangars, eco-tunnels, vertical tunnels and tunnels The gap between the outer circumference of the temporary tunnel and the pipeline and the hole is installed by installing the filler and reinforcement supply hose guide pipe inside or outside the divided wave or uneven plate located at the top of the unattached temporary tunnel and the pipeline. Filler, reinforcement or cast-in-place concrete in the space formed between the outer circumferential surface of the pipe and the inner circumferential surface of the unattached temporary tunnel and pipeline In order to ensure complete and complete filling, and if necessary, the split corrugation or uneven plate located at the lowermost part is provided with non-standard rail-type or spacer supporting rail with spacer and wire mesh insert groove. After installing the installation temporary tunnels and pipelines, the pipe itself slides smoothly when various pipes are installed into the interior, and the same space is provided between the outer circumferential surface of the various pipes and the inner circumferential surface of the non-attached temporary tunnels and pipelines. In the future, not only the filling material and reinforcing material can be filled in these spaces smoothly, but the reinforcing bars or wire meshes installed in these spaces are invented so as to be installed smoothly regardless of whether the pipe support and the spacer double rail are installed.

일반적으로, 상수관로, 암거를 포함한 하수관로, 수로, 도로 및 철도용 횡 배수로 및 보?차도, 제방 횡단용 횡 배수로, 지하차도, 지하 저장고, 가스관로, 통신관로, 전력 관로, 지하 격납고, 에코 터널, 수직구 및 터널 등의 터널 및 관로 구조물을 시공하기 위해서 다양한 터널 및 관로 구조물 시공방법이 사용되고 있다.Generally, water pipes, sewer pipes including culverts, waterways, road and rail transverse drains and pavements, embankment crossings, underground passages, underground storage, gas pipelines, communication pipelines, power pipelines, underground hangars, eco tunnels Various tunnel and pipeline structure construction methods are used to construct tunnels and pipeline structures such as vertical holes and tunnels.

이중 대표적인 터널 구조물 시공방법으로는 터널 구조물을 시공하고자 하는 곳의 땅을 완전히 개착(開鑿)하여 터널 구조물을 시공한 다음, 그 위에 개착된 흙을 덮어 터널 구조물을 시공하는 오픈 트렌치 공법(Open Trench Method ; 이하 O.T.M.)과 시공하고자 하는 곳의 땅을 개착(開鑿)하지 않고 쉴드 터널링 머신(Shield Tunneling Machine)을 사용한 비개착(非開鑿)하여 터널을 형성한 다음 형성된 터널 안에 터널 구조물을 시공하는 터널 보링 공법(Tunneling Boring Method ; 이하 T.B.M.)이 있다. Among the typical tunnel structure construction methods, the open trench method of constructing a tunnel structure by completely reattaching the ground where the tunnel structure is to be constructed, and then covering the soil deposited on the open trench method (Open Trench Method) Tunnel boring to form tunnels by non-attaching using the Shield Tunneling Machine without attaching the OTM) and the land to be constructed. Tunneling Boring Method (TBM).

그 외에 도로 또는 철도 레일 밑에 터널을 구축하는 방법으로 파이프를 이용하여 상부의 토층을 지지한 상태에서 그 아래 지하 구조물을 시공하는 파이프 루프 공법(Pipe Roof Method) 등이 있다.In addition, there is a pipe roof method for constructing tunnels under the road or railway rails and constructing underground structures under the upper ground using pipes.

이러한 오픈 트렌치 공법(O.T.M.)과 터널 보링 공법(T.B.M.)방법 중에서 현재 대표적으로 쓰이는 공법은 터널 보링 공법(T.B.M.)이다.Among the open trench method (O.T.M.) and tunnel boring method (T.B.M.) method, the currently used method is the tunnel boring method (T.B.M.).

이 터널 보링 공법은 주로 도시지역 및 토층이 암반층으로 이루어진 곳에서 많이 사용되는데, 이는 터널을 시공하는 과정에서 지상 건축 구조물(도로 및 건물 등)과 지하 건축 구조물(하수도 및 가스관 등) 및 지상 교통 흐름에 최소한의 영향을 끼치면서 터널을 시공할 수 있기 때문이다.This tunnel boring method is mainly used in urban areas and soil layers, which are composed of rock layers, which are ground construction structures (roads and buildings, etc.), underground construction structures (sewerage and gas pipes, etc.) and ground traffic flows. This is because tunnels can be constructed with minimal impact.

그러나, 이러한 오픈 트렌치 공법과 터널 보링 공법은 다음과 같은 터널 시공상의 문제점이 있다.However, the open trench method and the tunnel boring method have problems in tunnel construction as follows.

먼저, 오픈 트렌치 공법은 지하 구조물을 시공하기 위해 토층을 개착한 후 시공을 하는데 이는 지상의 건축 구조물에 의해 시공장소가 제약받으며, 지상의 교통흐름을 방해하는 문제점이 있다.First, in the open trench method, construction is performed after the soil layer is opened for construction of the underground structure, which is restricted by the construction site of the ground and interferes with the traffic flow on the ground.

그리고, 터널 보링 공법은 주로 암반층에 터널을 비개착(非開鑿)하여 시공하는 것으로 대부분의 터널 보링 머신은 원형 터널구조만을 구축할 수 있는 구조를 가지고 있으므로 원형 터널구조가 아닌 사각형태의 터널구조를 시공하기 위해서는 터널 구조물의 직경보다 큰 직경을 원형 또는 타원형 터널을 시공하여야하거나, 오픈 트렌치 공법 또는 파이프 루프 공법 등을 사용하여야 하므로 터널 구조물을 시공하는데 번거로움과 시공비용이 증가되는 문제점이 있다.In addition, the tunnel boring method is mainly constructed by attaching a tunnel to a rock layer. Since most tunnel boring machines have a structure in which only a circular tunnel structure can be constructed, a tunnel structure of a rectangular shape is used instead of a circular tunnel structure. In order to construct a circular or oval tunnel having a diameter larger than the diameter of the tunnel structure, or to use an open trench method or a pipe loop method, there is a problem in that the troublesome and construction cost is increased when constructing the tunnel structure.

이러한 문제점을 해결하기 위해 본원의 출원인은 특허 제 99-15875호 및 특허 제 99-18904호에서 지중에 비개착식으로 터널 구조물을 시공하기 위해 기술에서 터널 구조물을 지중 내부에 연속적으로 밀어 넣으면서 터널을 형성하는 것이 알려져 있다.In order to solve this problem, the applicant of the present application in the patents 99-15875 and 99-18904, in order to construct the tunnel structure non-adherent to the ground in the technique to continuously push the tunnel structure into the underground tunnel It is known to form.

이와 같은 비개착식으로 터널 구조물의 설치공법은, 통상 터널을 시공하고자 하는 지상을 일정깊이로 수직 굴착하여 수직 전진갱 및 도달갱을 형성하고, 상기 수직 전진갱의 일측 벽면에 버팀 반력벽을 설치한 다음 수직 전진갱 내부에 터널 굴착수단을 설치하고, 상기 터널 굴착수단의 선추진 프레임에 설치되어서 상기 버팀 반력벽에 지지된 선추진용 유압 실린더를 작동시켜 선추진 프레임을 최초로 상기 수직 전진갱의 수평방향으로 지중 내부로 압입시켜 터널 구축공간을 형성한 후 상기 선추진 프레임이 지중 내부로 모두 압입되면 터널 굴착공간으로 압입될 터널 구조물이 상기 선추진용 유압 실린더를 지지하도록 수직 전진갱 내부에 위치시킨다.In this non-adhesive installation method of the tunnel structure, the vertical ground and the reaching shaft are usually formed by vertically excavating the ground where the tunnel is to be constructed to a certain depth, and installing a supporting reaction wall on one wall of the vertical forward shaft. Then, a tunnel excavation means is installed inside the vertical forward shaft, and installed on the line propulsion frame of the tunnel excavation means to operate the line propulsion hydraulic cylinder supported by the propulsion reaction wall for the first time. After forming the tunnel construction space by press-fitting into the underground in the direction, when the line propulsion frames are all press-fitted into the underground, the tunnel structure to be press-fitted into the tunnel excavation space is positioned inside the vertical forward shaft to support the hydraulic cylinder for line propulsion.

이어서 터널 구조물을 연속적으로 터널 굴착공간으로 압입시키도록 압입 추진용 유압 실린더를 버팀 반력벽에 지지되게 설치하고, 터널 굴착공간 내부의 토사를 선추진 프레임 내에 설치된 굴삭기로 굴삭하며, 굴삭된 토사를 컨베이어로 이송시켜 운반 대차에 실어 수직 전진갱으로 이동시켜 배출하며, 이후 선추진 프레임 내부의 토사가 모두 굴착되면 선추진용 유압 실린더를 재작동시켜 선추진 프레임을 밀어 넣어 토사의 붕괴를 방지하여 터널 구축공간을 형성한 다음, 선추진 프레임이 터널 구축공간을 형성하면서 밀어 넣어지면 수직 전진갱에 설치된 압입 추진용 유압 실린더가 터널 구조물을 밀어 넣고, 선추진 프레임의 선추진과 압입 추진용 유압 실린더에 의한 터널 구조물 압입 과정을 반복하여 상기 지중에 연속적으로 터널 구조물을 형성하며, 선추진 프레임이 굴진하는 과정에서 상기 지중의 성질이 토사층에서 암반층으로 변화되면 선추진 프레임 내에 설치된 암반 보링기를 횡방향 회전 및 수평방향 이동시킨다.Subsequently, a pressurized propulsion hydraulic cylinder is installed to be supported on the support reaction wall to continuously press the tunnel structure into the tunnel excavation space, excavate the soil inside the tunnel excavation space with an excavator installed in the line propulsion frame, and excavate the excavated soil After transporting it to the transport truck, it is moved to the vertical forward shaft and discharged. After all the soil inside the linear propulsion frame is excavated, the hydraulic propulsion cylinder is reactivated to push the linear propulsion frame to prevent the collapse of the soil. After the thrust frame is pushed while forming the tunnel construction space, the pressurized propulsion hydraulic cylinder installed in the vertical forward shaft pushes the tunnel structure, and the tunnel by the thrust and the pressurized propulsion hydraulic cylinder of the thrust frame is pushed. By repeating the structure indentation process, tunnel structures are continuously formed in the ground. It said, the Soil When the nature of the changes in the rock layer tosacheung moving the rock boring provided in the wire pushing direction transverse frame rotation and the horizontal line in the course of the driving frame drilling.

이와 같이 횡방향 회전 및 수평 방향 이동되는 암반 보링기를 통해 암반층 전단면에 다수개의 굴착공을 형성하고, 이 굴착공을 유압 해머 또는 굴삭기로 파쇄시키며, 상기의 파쇄과정에서 굴착된 암반을 컨베어어를 통해 운반 대차로 상차시켜 수직 전진갱으로 이송시켜 외부로 배출하고, 상기 암반이 모두 파쇄되면 선추진용 유압 실린더가 작동하여 선추진 프레임을 밀어 넣으며, 선추진 프레임이 이동한 거리만큼 압입 추진용 유압 실린더로 상기 터널 구조물을 지중 내부로 압입시키며 상기 암반 보링기로 굴착공을 형성하는 과정을 반복하여 암반에 터널 굴착공간을 확보하면서 연속적으로 터널 구조물을 압입시켜 암반층이 끝나는 지점까지 형성하는 과정으로 이루어진다.As described above, a plurality of excavation holes are formed on the front end surface of the rock layer through rock boring machines which are horizontally rotated and horizontally moved, and the excavation holes are crushed by a hydraulic hammer or excavator, and the rock excavated in the above crushing process is carried out. The vehicle is transported to the vertical forward shaft to be discharged to the vertical forward shaft, and discharged to the outside. When all the rocks are broken, the linear propulsion hydraulic cylinder is operated to push the linear propulsion frame, and the hydraulic cylinder for pushing-in propulsion as far as the linear propulsion frame moves. The tunnel structure is pressurized into the underground and the excavation hole is formed by repeating the rock boring. The tunnel excavation space is secured to the rock while continuously tunneling the tunnel structure and forming the end point of the rock layer.

그런데 종래 대부분의 관로 구조물을 포함한 터널 구조물(상기 관로 구조물 역시 터널 구조물과 그 크기만 다를 뿐 동일하므로 이하에서는 "터널 구조물"을 중심으로 설명한다)은 단일 구조체로서 원형 터널구조 또는 아치형 터널구조로 구축하거나 또는 운반 및 조립성 등을 감안하여 시멘트 또는 발포성 합성수지 등으로 성형한 다분할 세그멘트를 사용하고 있으나, 이 경우 외부로부터 가해지는 토압 등에 대응하는 횡 방향 내력이 약하고 중량이 많이 나가는 단점이 있다.By the way, the tunnel structure including most of the conventional pipeline structure (the pipeline structure is also the same as the tunnel structure, but only different in size, hereinafter will be described with reference to the "tunnel structure" center) is constructed as a circular tunnel structure or arched tunnel structure as a single structure Or in order to transport and assembling, etc. in order to use a multi-part segment formed of cement or foamed synthetic resin, etc. In this case, there is a disadvantage in that the transverse strength corresponding to the earth pressure applied from the outside is weak and the weight is high.

따라서, 최근 들어서는 외부로부터 가해지는 토압 등에 대응하는 횡 방향 내력을 증가시키고 중량을 저감시키기 위해 요철을 포함하는 파형 형태로 절곡된 파형판 또는 요철판을 이용하여 수개의 호형 또는 판형 분할 파형 또는 요철판들을 제작하고 이를 굴진 지점으로 이송시켜 현장에서 원형이나 아치형 또는 그 밖의 다각형 모양의 비개착 가설 터널 및 관로구조로 직접 조립한 후 이를 지반의 굴진공에 압입 설치한 다음 가설 터널 및 관로의 외측과 굴진공 사이의 틈새를 토사나 모르타르 등과 같은 채움재 겸 보강재를 채우는 방식을 채택하고 있다.Therefore, in recent years, several arc-shaped or plate-shaped divided waveforms or irregularities are formed by using a wavy plate or irregularities that are bent in a wave form including irregularities to increase the lateral strength corresponding to earth pressure applied from the outside and reduce the weight. Fabricate and transport it to the excavation point, and then assemble it directly into the unattached temporary tunnel and pipeline structure of circular, arched or other polygonal shape on the site, and then press-install it into the ground cavity. The gap between vacuums is filled with fillers and reinforcements such as earth and mortar.

뿐만 아니라, 굴진공에 상기한 가설 터널 및 관로를 설치한 후에는 그 내부에 상수관로나, 암거를 포함한 하수관로, 수로, 도로 및 철도용 횡 배수로 및 보?차도, 제방 횡단용 횡 배수로, 지하차도, 지하 저장고, 가스관로, 통신관로, 전력 관로, 지하 격납고, 에코 터널, 수직구 및 터널(이하 "각종 관체"로 통칭함) 등을 설치하게 된다.In addition, after installing the above-mentioned temporary tunnels and pipelines in the drilling pit, water pipes, sewer pipes including culverts, waterways, road and rail transverse drainages and pavements, transverse drainages, and underground passages , Underground storage, gas pipelines, communication pipelines, electric power pipelines, underground hangars, echo tunnels, vertical holes and tunnels (hereinafter referred to as "various pipes") will be installed.

그런데 종래의 가설 터널 및 관로에는, 가설 터널 및 관로의 외주면과 굴진공 사이 및 가설 터널 및 관로의 내주면과 각종 관체의 외주면 사이에 형성되는 공간부에 채움재 겸 보강재를 완벽히 충진시킬 수 있도록 하는 채움재 겸 보강재 공급호스 안내관이 구비되어 있지 않아 가설 터널 및 관로의 외측과 굴진공 사이의 틈새 또는 관체의 외주면과 가설 터널 및 관로의 내주면 사이에 형성되는 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 채우는 작업이 매우 어려울 뿐만 아니라 이들 공간부에 채움재 겸 보강재가 밀실한 상태로 완벽히 채워지지 않아 구조물 자체의 강도가 전체적으로 동일하지 못하고 일부에서 약하게 되어 가설 터널 및 관로 상부의 지반 침하 또는 관체의 품질 및 안전도의 저하 등 여러 가지 문제점이 있다.However, in the conventional temporary tunnel and pipeline, the filler and reinforcement to completely fill the space formed between the outer circumferential surface of the temporary tunnel and the pipeline and the drilling hole and between the inner circumferential surface of the temporary tunnel and the pipeline and the outer circumferential surface of various pipes Filling filler and reinforcement or cast-in-place concrete in the space formed between the outer circumferential surface of the temporary tunnel and pipe or the outer circumferential surface of the pipe and the inner circumferential surface of the temporary tunnel and pipeline because the guide hose is not provided. Not only is this very difficult, but the filling and reinforcement of these spaces are not completely filled, so the strength of the structure itself is not the same, and the structure is weak in some places. There are several problems.

또한, 종래의 가설 터널 및 관로에는 상기한 각종 관체들을 가설 터널 및 관로의 내부에 설치할 때 이를 지지 또는 받쳐주기 위한 어떠한 구성품도 설치되어 있지 않을 뿐만 아니라 가설 터널 및 관로의 내주면과 각종 관체들의 외주면 사이의 공간부를 일정한 간격으로 유지시켜 주기 위한 어떠한 구성품도 설치되어 있지 않아 비개착 가설 터널 및 관로를 굴진공 내에 설치한 후 그 내부로 각종 관체를 설치할 때, 양자 사이에서 큰 마찰력이 발생하게 되어 중량체인 각종 관체 자체가 가설 터널 및 관로 내부로 원활히 삽입 설치되지 않을 뿐만 아니라, 각종 관체의 외면이 손상되어 품질이 저하되기도 하고, 각종 관체의 외면과 비개착 가설 터널 및 관로의 내주면 사이에 일정한 공간부가 계획대로 균등하게 형성되지 않게 되므로 차후 이들 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 충진시킬 때 가설 터널 및 관로의 내주면과 각종 관체의 외주면 사이에서 상방부가 넣고 저면부가 좁은 형태를 그대로 유지한 채 채움재 겸 보강재 또는 현장 타설 콘크리트가 충진되는 문제점 등도 있다.
In addition, the conventional temporary tunnels and pipelines are not provided with any components for supporting or supporting the above-mentioned various bodies when they are installed inside the temporary tunnels and pipelines, as well as between the inner circumferential surfaces of the temporary tunnels and pipelines and the outer circumferential surfaces of the various pipelines. Since no components are installed to maintain the space part at regular intervals, when the non-adhesive temporary tunnels and pipelines are installed in the cavity and various pipes are installed therein, a large friction force is generated between them. Not only the various pipes themselves are not easily inserted into the temporary tunnels and pipelines, but the external surfaces of the pipes are damaged and the quality is degraded, and a certain space is planned between the external surfaces of the various pipes and the inner circumferential surfaces of the non-attached temporary tunnels and pipelines. As it is not formed evenly as it is, When filling the reinforcement and reinforcement or cast-in-place concrete, there is a problem in that the upper part is inserted between the inner circumferential surface of the temporary tunnel and the pipeline and the outer circumferential surface of various pipes, and the filling material, reinforcement or in-place concrete is filled while the bottom part is kept in a narrow form.

본 발명은 이와 같은 종래의 제반 문제점을 해소하기 위하여 안출한 것으로, 상수관로나, 암거를 포함한 하수관로, 수로, 도로 및 철도용 횡 배수로 및 보?차도, 제방 횡단용 횡 배수로, 지하차도, 지하 저장고, 가스관로, 통신관로, 전력 관로, 지하 격납고, 에코 터널, 수직구 및 터널 등과 같은 각종 관체를 설치할 때 사용되는 비개착 가설 터널 및 관로를 분할 파형 또는 요철판으로 구축하되, 비개착 가설 터널 및 관로의 최상방부에 위치되는 분할 파형 또는 요철판의 내부 또는 외부에 채움재 겸 보강재 공급호스 안내관을 설치하여 가설 터널 및 관로의 외주면과 굴진공 사이의 틈새 또는 관체의 외주면과 비개착 가설 터널 및 관로의 내주면 사이에 형성되는 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 원활하고도 완벽하게 충진시킬 수 있도록 함으로써 가설 터널 및 관로의 외측과 굴진공 사이의 틈새 또는 관체의 외주면과 가설 터널 및 관로의 내주면 사이에 형성되는 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 채우는 작업이 간편하여 공사에 따른 시간과 인건비 등을 대폭 줄일 수 있을 뿐만 아니라 이들 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트가 완벽히 채워지게 되어 구조물 전체 강도를 균일하게 유지시킬 수 있음은 물론 강도 자체를 대폭 증대시킬 수 있는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로와 그의 시공공법을 제공하는데 그 목적이 있는 것이다.The present invention has been devised to solve such a conventional problem, such as water pipes, sewer pipes including culverts, waterways, road and rail transverse drainage and pavement, transverse drainage, underground roadway, underground storage The construction of non-adhesive temporary tunnels and conduits used in installing various pipes such as gas pipelines, communication pipelines, electric power pipelines, underground hangars, eco-tunnels, vertical openings and tunnels, etc. Filler and reinforcement supply hose guide pipes are installed inside or outside the split corrugation or uneven plate located at the top of the pipeline to provide clearance between the outer circumferential surface of the temporary tunnel and the pipeline and the hole or the outer circumferential surface of the pipeline and the unattached temporary tunnel and pipeline It is possible to fill the space formed between the inner circumferential surface of the filling and reinforcement or the cast-in-place concrete smoothly and completely. It is easy to fill the space formed between the gap between the outside of the temporary tunnel and the pipeline and the hole or the outer circumferential surface of the pipe and the inner circumferential surface of the temporary tunnel and the pipeline, so that the time required for construction In addition to drastically reducing labor costs, these spaces are completely filled with fillers, reinforcements, or on-site pouring concrete, so that the overall strength of the structure can be maintained uniformly. The purpose is to provide non-attached temporary tunnels and pipelines and construction methods thereof.

본 발명의 다른 목적은, 필요에 따라 최하방부에 위치되는 분할 파형 또는 요철판에는 정단면이 "ㅗ"자, "∧"자 및 "∩"자 형상을 갖는 관체 받침 및 간격재 겸용 레일을 길게 또는 정해진 간격을 두고 설치하고, 또 필요에 따라서는 길게 설치된 상기 관체 받침 및 간격재 겸용 레일의 상면에 철근 및 와이어 메쉬가 삽입될 수 있는 삽입홈을 정해진 간격을 두고 구비시켜 줌으로써 비개착 가설 터널 및 관로를 설치한 후 그 내부로 각종 관체를 설치할 때 관체 자체가 관체 받침 및 간격재 겸용 레일의 상면을 타고 원활히 미끄러져 삽입되게 되므로 각종 관체를 원활히 설치할 수 있어 공사시간 및 비용을 대폭 줄일 수 있고, 또 가설 터널 및 관로 내부에서 각종 관체를 받쳐주고 있는 관체 받침 및 간격재 겸용 레일에 의해 각종 관체의 외주면과 비개착 가설 터널 및 관로의 내주면 사이에 일정한 폭을 갖는 공간부가 구비되어 차후 이들 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 원활히 충진시킬 수 있으며, 또한 관체 받침 및 간격재 겸용 레일을 설치한 상태에서도 이들 공간부 사이에 철근 또는 와이어 메쉬를 원활히 설치할 수 있어 구조물의 강도를 전체적으로 대폭 증대시킬 수 있는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로와 그의 시공공법을 제공하는데 있다.
According to another object of the present invention, a split corrugated plate or a concave-convex plate positioned at the lowermost part of the present invention may have a long length of the tubular support and spacer having a cross section having a shape of “ㅗ”, “∧” and “∩”. Or install at regular intervals, and if necessary by providing a groove for inserting the reinforcing wire and the wire mesh on the upper surface of the pipe support and the spacer double rail provided at regular intervals, the non-adhesive temporary tunnel and When installing various pipes inside the pipe after installing the pipe line, the pipe itself slides smoothly through the upper surface of the pipe support and spacer rail so that various pipes can be installed smoothly, thus greatly reducing the construction time and cost. In addition, non-adhesion of the outer circumferential surface of various pipes by the pipe support and spacer rail supporting various pipes inside the temporary tunnel and pipeline A space having a constant width is provided between the inner circumferential surface of the tunnel and the pipeline so that these spaces can be smoothly filled with filler and reinforcement or cast-in-place concrete, and these spaces can be installed even when the pipe support and spacer are installed. The present invention provides a non-adhesive temporary tunnel and pipeline using a split waveform or uneven plate which can smoothly install reinforcing bars or wire meshes in between, and greatly increase the strength of the structure as a whole.

상기한 목적을 달성하기 위한 본 발명의 비개착 가설 터널 및 관로는, 파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성한 수개의 분할 파형 또는 요철판들을 수개의 결합수단을 통해 상호 결합시켜 원형이나 마제형, 아치형 또는 그 밖의 다각형의 모양으로 제작하여 굴진공 내에 설치하고, 그 내부에 각종 관체를 내설하는 비개착 가설 터널 및 관로에 있어서, 상기 분할 파형 또는 요철판들 중 가설 터널 및 관로의 최상단에 위치되는 분할 파형 또는 요철판의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관을 설치한 것을 특징으로 한다.In order to achieve the above object, the non-attached hypothetical tunnel and the conduit of the present invention, by using a corrugated plate or a concave-convex plate to combine several divided waveforms or concave-convex plate bent in an arc or plate shape through a plurality of coupling means In the non-attached temporary tunnels and pipelines, which are manufactured in the shape of a circle, a horseshoe, an arch, or other polygons, are installed in a hollow hole, and in which various pipes are installed. The filler and reinforcing material supply hose guide pipe perforated at predetermined intervals is installed on one or both of the central upper or lower surface of the divided waveform or uneven plate located at the top end.

이때, 상기 채움재 겸 보강재 공급호스 안내관은 용접을 통해 분할 파형 또는 요철판의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 직접 고정 설치하거나, 또는 수개의 "U" 고정볼트와 너트를 이용하여 착탈 가능하게 고정 설치한 것을 특징으로 한다.At this time, the filler and reinforcement supply hose guide tube is directly fixed to any one side or both sides of the middle or upper surface of the divided wave or concave-convex plate by welding, or detached using several "U" fixing bolts and nuts. It is characterized by being fixedly installed.

뿐만 아니라, 소정형상의 가설 터널 및 관로로 조립되는 수개의 분할 파형 또는 요철판 중 최하방부에 위치되는 분할 파형 또는 요철판의 내면에, 각종 관체를 가설 터널 및 관로 내부에 삽입 설치할 때 각종 관체의 저부 외주면을 지지해주며 미끄럼 이동되도록 하는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일을 부가 설치한 것을 특징으로 한다.In addition, when various pipes are inserted into and installed inside the temporary tunnels and pipes, various pipes may be installed on the inner surface of the divided waveforms or concave-convex plates located at the lowermost part among several divided waveforms or concave-convex plates that are assembled into temporary tunnels and conduits of a predetermined shape. Supporting the outer peripheral surface of the bottom and characterized in that the pair of one or more pipe support and spacer rails are installed to slide.

이때, 상기 관체 받침 및 간격재 겸용 레일은 정단면이 "ㅗ"자 형상이나 "∧"자 형상 또는 "∩"자 형상 중 어느 한 형상을 갖도록 압출 또는 절곡 성형한 것을 특징으로 한다.At this time, the pipe support and the spacer double rail is characterized in that the front end surface is extruded or bent molded so as to have any one of a "ㅗ" shape, "∧" shape or "∩" shape.

또한, 상기 관체 받침 및 간격재 겸용 레일은 분할 파형 또는 요철판들 중 가설 터널 및 관로의 최하방부에 위치되는 분할 파형 또는 요철판의 내면에 정해진 간격을 두고 설치하여 각각의 관체 받침 및 간격재 겸용 레일 사이에 철근 및 와이어 메쉬 삽입용 공간부가 형성되게 한 것을 특징으로 한다.In addition, the pipe support and spacer double rail is installed at regular intervals on the inner surface of the divided waveform or concave-convex plate located in the lowermost part of the temporary tunnel and conduit among the divided wave or concave-convex plate to combine the respective pipe support and spacer. The space between the rails and the wire mesh insert is formed between the rails.

또, 상기 관체 받침 및 간격재 겸용 레일의 상면에는 가설 터널 및 관로의 내면과 그 내부에 설치되는 각종 관체의 외면 사이에 형성되는 공간부에 채움재 겸 보강재를 충진시켜 구조물의 강도를 보강시킬 때 설치되는 철근 및 와이어 메쉬가 관체 받침 및 간격재 겸용 레일에 걸리지 않고 삽입될 수 있도록 하는 철근 및 와이어 메쉬 삽입홈을 정해진 간격을 두고 더 구비시킨 것을 특징으로 한다.In addition, the upper surface of the pipe support and spacer double rail is filled in the space formed between the inner surface of the temporary tunnel and the pipeline and the outer surface of the various pipes installed therein to be installed when reinforcing the strength of the structure Reinforcing bar and the wire mesh is characterized in that the reinforcing bar and the wire mesh insertion groove so as to be inserted without being caught by the pipe support and spacer double rail at regular intervals.

이때, 상기 관체 받침 및 간격재 겸용 레일은 분할 파형 또는 요철판들 중 가설 터널 및 관로의 최하방부에 위치되는 분할 파형 또는 요철판의 내면에 용접 고정하거나, 또는 수개의 볼트 및 너트를 통해 착탈 가능하게 설치한 것 중 어느 한 형태로 설치한 것을 특징으로 한다.At this time, the pipe support and spacer double rail is welded fixed to the inner surface of the divided waveform or concave-convex plate which is located at the lowermost part of the temporary tunnel and conduit among the divided waveform or concave-convex plate, or detachable through several bolts and nuts. It is characterized in that it is installed in any one form.

또한, 상기 결합수단은 걸림돌기와 삽입편 및 결합공을 구비하고 서로 인접된 분할 파형 또는 요철판들의 4면 결합판에 각각 천공된 결합구 체결공에 1개가 끼워져 결합된 상태에서 다른 하나가 상기 결합구 체결공에 결합되어 있는 쇄기형 결합구의 결합공에 끼워져 결합되는 형태를 갖고 서로 인접된 두 분할 파형 또는 요철판를 상호 일체로 결합시켜 주는 수 쌍의 쇄기형 결합구 또는 서로 인접된 분할 파형 또는 요철판들의 결합판에 각각 천공된 결합구 체결공에 끼워져 상호 나사 결합되는 수개의 볼트 및 너트로 구성된 것을 특징으로 한다.In addition, the coupling means is provided with a locking projection, the insertion piece and the coupling hole and the other one in the state in which one is inserted into the coupling hole fastening holes drilled in the four-side coupling plate of the divided waveform or concave-convex plates adjacent to each other Several pairs of wedge-shaped couplers or split wave-shaped or contiguous adjacent to each other that form two types of wedge-shaped couplings that are coupled to the spherical coupling holes and are coupled to each other. It is characterized by consisting of several bolts and nuts that are screwed into each other are fitted to the coupling hole fastening holes drilled in the coupling plate of the iron plate respectively.

한편, 상기한 목적을 달성하기 위한 본 발명 방법은, 굴진공의 내부에 설치되는 비개착 가설 터널 및 관로를 시공하는 공법에 있어서, 공장에서 파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성하고, 4면에는 수개의 결합구 체결공이 정해진 간격으로 천공된 결합판을 용접 설치하여 수개의 분할 파형 또는 요철판들을 제작하되, 일부 분할 파형 또는 요철판의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관을 설치하고, 또 일부 분할 파형 또는 요철판의 내면에는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일을 설치한 다음 이들을 현장으로 이송시키는 공정과; 현장의 지반 상에 굴진공을 뚫는 공정과; 상기 굴진공 내에 결합수단들을 이용하여 수개의 분할 파형 또는 요철판들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로로 조립 설치하되, 가설 터널 및 관로의 최상단에는 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 채움재 겸 보강재 공급호스 안내관이 설치되어 있는 분할 파형 또는 요철판을 위치시켜 조립하는 공정과; 상기 분할 파형 또는 요철판의 중앙 상면에 고정 설치된 채움재 겸 보강재 공급호스 안내관을 통해 채움재 겸 보강재 공급호스를 삽입시켜 굴진공과 가설 터널 및 관로의 외주면 사이에 형성된 공간부로 채움재 겸 보강재를 주입시켜 채워 주는 공정과; 채움재 겸 보강재의 양생 후 상기 가설 터널 및 관로의 내부로 각종 관체를 삽입 설치하는 공정과; 상기 분할 파형 또는 요철판의 중앙 하면 상면에 고정 설치된 채움재 겸 보강재 공급호스 안내관을 통해 채움재 겸 보강재 공급호스를 삽입시켜 상기 각종 관체의 삽입에 의해 형성된 가설 터널 및 관로의 내주면과 각종 관체의 외주면 사이에 형성된 공간부에 채움재 겸 보강재를 주입시켜 채워 주는 공정;으로 이루어진 것을 특징으로 한다.On the other hand, the method of the present invention for achieving the above object, in the construction method of the non-adhesive temporary tunnels and pipelines installed inside the excavation hole, bent to form an arc or plate using a corrugated plate or uneven plate at the factory On the four sides, several joining fasteners are welded and installed to the joining plate, which is drilled at predetermined intervals, to produce several divided waveforms or uneven plates, and one or both of the central upper surface or the lower surface of some divided waveforms or uneven plates Several fillers and reinforcement outlet hoses are provided with perforated filler and reinforcement supply hose guide tubes at predetermined intervals, and a pair or more pipe support and spacer rails are installed on the inner surface of some divided corrugations or irregularities. Then transferring them to the site; Drilling a hole in the ground of the site; Assemble and install several uneven temporary tunnels and pipelines having a predetermined shape by connecting several divided waveforms or irregularities in the longitudinal and transverse directions by using coupling means in the excavation hole. Locating and assembling the divided corrugated or uneven plate provided with a filler and reinforcing material supply hose guide tube on one or both surfaces of the lower surface; Filler and reinforcement supply hose is inserted through the filler and reinforcement supply hose guide tube fixedly installed on the central upper surface of the divided wave or uneven plate to inject and fill the filler and reinforcement into the space formed between the excavated hole and the temporary tunnel and the outer circumferential surface of the pipeline. Process; Inserting and installing various pipe bodies into the temporary tunnel and the pipeline after curing of the filler and reinforcing material; Inserting the filler and reinforcement supply hose through the filler and reinforcement supply hose guide tube fixedly installed on the upper surface of the center of the divided wave or uneven plate between the inner circumferential surface of the temporary tunnel and the pipe formed by the insertion of the various tubes and the outer peripheral surface of the various tubes Characterized in that it comprises a step of injecting the filling material and reinforcing material filled in the space portion formed in the.

또, 상기 굴진공 내에 결합수단들을 이용하여 수개의 분할 파형 또는 요철판들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로로 조립 설치할 때, 가설 터널 및 관로의 최하단에는 관체 받침 및 간격재 겸용 레일을 구비한 분할 파형 또는 요철판을 위치시켜 조립한 것을 특징으로 한다.In addition, when assembling and installing an unattached temporary tunnel and pipeline having a predetermined shape by connecting several divided waveforms or irregularities in the longitudinal and transverse directions by using coupling means in the excavation hole, the tube is arranged at the bottom of the temporary tunnel and pipeline. It is characterized by assembling the divided waveform or uneven plate provided with a support and spacer rail combined.

또한, 상기 가설 터널 및 관로의 내부로 각종 관체를 삽입 설치할 때, 상기 가설 터널 및 관로의 입구에 각종 관체를 위치시킨 후 최하단 분할 파형 또는 요철판의 내면에 설치되어 있는 관체 받침 및 간격재 겸용 레일을 따라 밀어넣어 가설 터널 및 관로의 내부로 각종 관체를 삽입 설치하는 것을 특징으로 한다.In addition, when inserting the various pipes into the interior of the temporary tunnel and the pipeline, after placing the various pipes at the entrance of the temporary tunnel and the pipeline pipe joints and spacers installed on the inner surface of the lowermost split waveform or uneven plate Pushed along the installation is characterized in that the installation of various pipe bodies into the interior of the temporary tunnel and pipe.

또, 상기 가설 터널 및 관로에 각종 관체를 삽입 설치하기에 앞서 상기 가설 터널 및 관로의 내부에 철근 또는 와이어 메쉬를 배근하는 공정을 더 실시하는 것을 특징으로 한다.The method may further include reinforcing the reinforcing wire or the wire mesh inside the temporary tunnel and the pipeline before inserting and installing various pipe bodies into the temporary tunnel and the pipeline.

또한, 상기 굴진공의 내면과 가설 터널 및 관로의 외주면 사이에 형성된 공간부 또는 상기 가설 터널 및 관로의 내주면과 각종 관체의 외주면 사이에 형성된 공간부에 채움재 겸 보강재를 주입시켜 채우기에 앞서, 상기 가설 터널 및 관로의 내부 또는 각종 관체의 내부에 수개의 진동발생기를 설치한 다음, 상기한 공간부 내로 채움재 겸 보강재를 주입할 때 진동발생기를 작동시켜 주는 공정을 더 실시하는 것을 특징으로 한다.In addition, the hypothesis prior to filling the space portion formed between the inner surface of the drilling hole and the outer circumferential surface of the temporary tunnel and the pipeline or the space formed between the inner circumferential surface of the temporary tunnel and pipeline and the outer circumferential surface of the various pipes, the hypothesis After the installation of several vibration generators in the tunnel and the interior of the pipe or the various pipe bodies, the process of operating the vibration generator when injecting the filler and reinforcement into the above-mentioned space portion is characterized in that it further performs.

이때, 상기 가설 터널 및 관로는 원형을 포함하여 마제형과 아치형, 5각, 6각 및 8각의 다각형 모양 중 어느 한 형상을 갖는 것을 특징으로 한다.In this case, the temporary tunnel and the pipe line is characterized in that it has a shape of one of the polygonal shape of the horseshoe and arched, 5, 6 and 8 angles, including a circular.

또, 상기 채움재 겸 보강재로는 시멘트 그라우트재, 모르타르, 수지 모르타르, 수지, 뿜칠재 및 현장 타설 콘크리트를 포함하는 것을 특징으로 한다.
In addition, the filler and reinforcing material is characterized in that it comprises a cement grout material, mortar, resin mortar, resin, swelling material and cast-in-place concrete.

이상에서 설명한 바와 같이 본 발명의 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로와 그의 시공공법에 의하면, 상수관로나, 암거를 포함한 하수관로, 수로, 도로 및 철도용 횡 배수로 및 보?차도, 제방 횡단용 횡 배수로, 지하차도, 지하 저장고, 가스관로, 통신관로, 전력 관로, 지하 격납고, 에코 터널, 수직구 및 터널 등과 같은 각종 관체를 설치할 때, 사용되는 비개착 가설 터널 및 관로를 분할 파형 또는 요철판으로 구축하되, 가설 터널 및 관로의 최상방부에 위치되는 분할 파형 또는 요철판의 내부나 외부 또는 양면 모두에 채움재 겸 보강재 공급호스 안내관을 설치하여 가설 터널 및 관로의 외주면과 굴진공 사이의 틈새 또는 관체의 외주면과 비개착 가설 터널 및 관로의 내주면 사이에 형성되는 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 원활하고도 완벽하게 충진시킬 수 있도록 함으로써 가설 터널 및 관로의 외측과 굴진공 사이의 틈새 또는 관체의 외주면과 가설 터널 및 관로의 내주면 사이에 형성되는 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트를 채우는 작업이 간편하여 공사에 따른 시간과 인건비 등을 대폭 줄일 수 있고, 특히 이들 공간부에 채움재 겸 보강재 또는 현장 타설 콘크리트가 완벽히 채워지게 되어 구조물 전체 강도를 균일하게 유지시킬 수 있음은 물론 강도 자체를 대폭 증대시킬 수 있는 것이다.As described above, according to the non-adhesive temporary tunnels and pipelines using the divided waveform or uneven plate of the present invention, and the construction method thereof, the water supply pipe, the sewer pipe including the culvert, the water channel, the road and rail transverse drainage and the roadway, Divided waveforms of non-adhesive temporary tunnels and pipelines used when installing various pipes such as transverse drainage, underground roadway, underground storage, gas pipeline, communication pipeline, power pipeline, underground hangar, eco tunnel, vertical tunnel and tunnel Or it is constructed of uneven plate, and installs the filler and reinforcement supply hose guide pipe in the inside, outside or both sides of the uneven plate or the uneven plate located in the uppermost part of the temporary tunnel and conduit, between the outer peripheral surface of the temporary tunnel and the conduit and the hole Filler and reinforcement or site in the space formed between the gap between the outer circumference of the pipe or the inner circumference of the non-adhesive temporary tunnel and pipeline Filling and reinforcement or site-pouring concrete in the space formed between the outer circumferential surface of the gap or pipe and the inner circumferential surface of the temporary tunnel and pipeline with the gap between the outside of the temporary tunnel and pipeline and the hollow hole to allow filling the poured concrete smoothly and completely. It is easy to fill the space, greatly reducing the time and labor cost according to the construction, especially the filling and reinforcing material or on-site concrete is completely filled in these spaces to maintain the overall strength of the structure uniformly, as well as the strength itself It can greatly increase.

또한, 본 발명에서는 가설 터널 및 관로의 최하방부에 위치되는 분할 파형 또는 요철판에는 정단면이 "ㅗ"자, "∧"자 및 "∩"자 형상을 갖는 관체 받침 및 간격재 겸용 레일을 설치하여 줌으로써, 비개착 가설 터널 및 관로를 설치한 후 그 내부로 각종 관체를 설치할 때 관체 자체가 관체 받침 및 간격재 겸용 레일의 상면을 타고 원활히 미끄러져 삽입되게 되므로 각종 관체를 원활히 설치할 수 있어 공사시간 및 비용을 대폭 줄일 수 있고, 또 가설 터널 및 관로 내부에서 각종 관체를 받쳐주고 있는 관체 받침 및 간격재 겸용 레일에 의해 각종 관체의 외주면과 비개착 가설 터널 및 관로의 내주면 사이에 일정한 폭을 갖는 공간부가 구비되어 차후 이들 공간부에 채움재 겸 보강재를 원활히 충진시킬 수 있다.In addition, in the present invention, the split wave or uneven plate located in the lowermost part of the temporary tunnel and the pipe line is provided with a pipe support and a spacer rail having a front end section having a shape of "ㅗ", "∧" and "∩". By installing the non-attached temporary tunnel and pipeline, the pipe itself slides smoothly through the upper surface of the pipe support and spacer rail when the various pipes are installed in the interior, so that various pipes can be installed smoothly. And a space with a constant width between the outer circumference of the various pipes and the inner circumference of the non-attached temporary tunnels and pipes by the pipe support and spacer rail which supports various pipes in the temporary tunnels and pipelines. Additional portions are provided to smoothly fill these spaces with filler and reinforcement in the future.

뿐만 아니라, 필요에 따라서는 상기 관체 받침 및 간격재 겸용 레일을 정해진 간격을 두고 설치하여 관체 받침 및 간격재 겸용 레일들 사이에 철근 및 와이어 메쉬 삽입용 공간부가 형성되게 하거나, 또는 상기 관체 받침 및 간격재 겸용 레일의 상면 자체에 철근 및 와이어 메쉬가 삽입될 수 있는 삽입홈을 정해진 간격을 두고 구비시켜 줌으로써 관체 받침 및 간격재 겸용 레일을 설치해 놓은 상태에서도 이들 공간부 사이에 철근 또는 와이어 메쉬를 원활히 설치할 수 있어 구조물의 강도를 전체적으로 대폭 증대시킬 수 있는 등 매우 유용한 발명인 것이다.
In addition, if necessary, the tubular support and the spacer double rail are installed at predetermined intervals so as to form a space for reinforcing wire and wire mesh insertion between the tubular support and the spacer double rail, or the tubular support and the gap. Reinforcement wires or wire meshes can be installed smoothly between the spaces even when the pipe support and spacer rail are installed by providing insertion grooves for reinforcing bars and wire meshes on the upper surface of the reusable rails at regular intervals. It is possible to greatly increase the strength of the structure as a whole is a very useful invention.

도 1은 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관이 설치된 분할 파형 또는 요철판을 적용하여 가설 터널 및 관로를 조립한 상태의 사시도.
도 2는 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관이 설치된 분할 파형 또는 요철판을 적용하여 가설 터널 및 관로를 조립한 상태의 정면도.
도 3의 (a)-(c)는 본 발명 중 채움재 겸 보강재 공급호스 안내관들의 설치 예들이 적용된 분할 파형 또는 요철판의 정면도.
도 4는 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관과 관체 받침 및 간격재 겸용 레일이 설치된 분할 파형 또는 요철판들을 적용하여 가설 터널 및 관로를 조립한 상태의 사시도.
도 5는 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관과 관체 받침 및 간격재 겸용 레일이 설치된 분할 파형 또는 요철판들을 적용하여 가설 터널 및 관로를 조립한 상태의 정면도.
도 6의 (a)(b)는 본 발명 중 관체 받침 및 간격재 겸용 레일의 다른 실시 예가 적용된 분할 파형 또는 요철판의 정면도.
도 7은 본 발명에서 사용된 분할 파형 또는 요철판과 결합수단의 일부 분해 사시도.
도 8은 본 발명 중 관체 받침 및 간격재 겸용 레일의 일 실시 예가 적용된 분할 파형 또는 요철판의 사시도.
도 9의 (a)-(c)는 철근 및 와이어 메쉬 삽입 공간부가 구비된 관체 받침 및 간격재 겸용 레일들을 정해진 간격을 두고 설치한 실시 예들이 적용된 분할 파형 또는 요철판의 사시도.
도 10의 (a)-(c)는 철근 및 와이어 메쉬 삽입홈가 구비된 관체 받침 및 간격재 겸용 레일들의 실시 예들이 적용된 분할 파형 또는 요철판의 사시도.
도 11은 굴진공 내에 본 발명이 작용된 가설 터널 및 관로과 각종 관체를 순차적으로 설치하고 공간부에 채움재 겸 보강재를 충진시킨 상태의 정 단면도.
도 12의 (a)(b)는 진동발생기를 작동시키면서 각각의 공간부에 채움재 겸 보강재를 충진시키는 상태를 보인 정 단면도.
도 13은 본 발명의 시공공법을 설명하기 위한 시공 순서도.
1 is a perspective view of a temporary tunnel and a pipe assembling state by applying a divided waveform or concave-convex plate installed with a filler and reinforcement supply hose guide tube according to an embodiment of the present invention.
Figure 2 is a front view of a state of assembling the temporary tunnel and the conduit by applying a divided waveform or concave-convex plate installed with a filler and reinforcement supply hose guide tube according to an embodiment of the present invention.
Figure 3 (a)-(c) is a front view of the divided waveform or uneven plate to which the installation examples of the filler and reinforcing material supply hose guide tubes of the present invention is applied.
Figure 4 is a perspective view of a state of assembling the temporary tunnel and the pipeline by applying the divided waveform or uneven plate installed with a filler and reinforcement supply hose guide tube and pipe support and spacer rail according to an embodiment of the present invention.
FIG. 5 is a front view of a state in which a temporary tunnel and a conduit are assembled by applying split waveforms or uneven plates provided with a filler and reinforcing material supply hose guide tube and a pipe support and spacer rail according to an embodiment of the present invention; FIG.
Figure 6 (a) (b) is a front view of the divided waveform or uneven plate to which another embodiment of the tubular support and spacer rail in the present invention is applied.
Figure 7 is an exploded perspective view of a portion of the divided waveform or uneven plate and the coupling means used in the present invention.
8 is a perspective view of a divided wave or uneven plate to which an embodiment of the tubular support and the spacer combined rail in the present invention is applied.
Figure 9 (a)-(c) is a perspective view of a divided waveform or uneven plate is applied to embodiments in which the pipe support and spacer rails provided with a reinforcing bar and the wire mesh insertion space is provided at predetermined intervals.
10 (a)-(c) is a perspective view of a divided wave or uneven plate to which embodiments of the tubular support and spacer double rail provided with reinforcing bars and wire mesh insertion grooves are applied;
11 is a cross-sectional view of the temporary tunnel and pipe line and the various pipes in which the present invention is applied to the excavation hole sequentially and filled with a filler and a reinforcement in the space.
Figure 12 (a) (b) is a sectional view showing a state of filling the filler and reinforcing material in each space portion while operating the vibration generator.
13 is a construction flow chart for explaining the construction method of the present invention.

이하, 첨부된 도면을 참조하여 본 발명에 따른 바람직한 실시 예를 상세히 설명하면 다음과 같다. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관이 설치된 분할 파형 또는 요철판을 적용하여 가설 터널 및 관로를 조립한 상태의 사시도이고, 도 2는 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관이 설치된 분할 파형 또는 요철판을 적용하여 가설 터널 및 관로를 조립한 상태의 정면도이며, 도 3의 (a)-(c)는 본 발명 중 채움재 겸 보강재 공급호스 안내관들의 설치 예들이 적용된 분할 파형 또는 요철판의 정면도이고, 도 4는 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관과 관체 받침 및 간격재 겸용 레일이 설치된 분할 파형 또는 요철판들을 적용하여 가설 터널 및 관로를 조립한 상태의 사시도이다.1 is a perspective view of a temporary tunnel and a pipeline assembled by applying a divided waveform or uneven plate provided with a filler and reinforcement supply hose guide tube according to an embodiment of the present invention, and FIG. 2 is an embodiment of the present invention. Filler and reinforcement supply hose according to the present invention is a front view of the assembly of the temporary tunnel and the pipeline by applying a divided wave or uneven plate installed guide pipe, Figure 3 (a)-(c) of the present invention the filler and reinforcement supply hose guide 4 is a front view of a split wave or uneven plate to which the installation examples of the pipes are applied, and FIG. 4 is a split wave or uneven plate installed with a filler and reinforcing material supply hose guide tube and a pipe support and spacer rail according to an embodiment of the present invention. Is a perspective view of a temporary tunnel and a pipeline assembled together.

또, 도 5는 본 발명의 일 실시 예에 따른 채움재 겸 보강재 공급호스 안내관과 관체 받침 및 간격재 겸용 레일이 설치된 분할 파형 또는 요철판들을 적용하여 가설 터널 및 관로를 조립한 상태의 정면도이고, 도 6의 (a)(b)는 본 발명 중 관체 받침 및 간격재 겸용 레일의 다른 실시 예가 적용된 분할 파형 또는 요철판의 정면도이며, 도 7은 본 발명에서 사용된 분할 파형 또는 요철판과 결합수단의 일부 분해 사시도이고, 도 8은 본 발명 중 관체 받침 및 간격재 겸용 레일의 일 실시 예가 적용된 분할 파형 또는 요철판의 사시도이며, 도 9의 (a)-(c)는 철근 및 와이어 메쉬 삽입 공간부가 구비된 관체 받침 및 간격재 겸용 레일들을 정해진 간격을 두고 설치한 실시 예들이 적용된 분할 파형 또는 요철판의 사시도이고, 도 10의 (a)-(c)는 철근 및 와이어 메쉬 삽입홈가 구비된 관체 받침 및 간격재 겸용 레일들의 실시 예들이 적용된 분할 파형 또는 요철판의 사시도이다.In addition, Figure 5 is a front view of a state of assembling the temporary tunnels and pipelines by applying the divided corrugated or uneven plate provided with a filler and reinforcement supply hose guide tube and pipe support and spacer rail according to an embodiment of the present invention, Figure 6 (a) (b) is a front view of the divided waveform or uneven plate to which another embodiment of the tubular support and spacer rail in the present invention is applied, Figure 7 is a divided waveform or uneven plate and coupling means used in the present invention 8 is a partially exploded perspective view of the present invention, FIG. 8 is a perspective view of a divided waveform or uneven plate to which an embodiment of a tubular support and spacer double rail according to the present invention is applied, and FIGS. 9 (a)-(c) are rebar and wire mesh insertion spaces. 10 is a perspective view of a divided wave shape or a concave-convex plate to which embodiments including additional pipe support and spacers provided with a predetermined interval are installed, and FIGS. 10 (a)-(c) show reinforcing bars and wire mesh insertion grooves. Embodiment of the tube support and spacing member comprising a rail Combination examples are applied is a perspective view of a divided waveform or yaw iron plate.

또한, 도 11은 굴진공 내에 본 발명이 작용된 가설 터널 및 관로과 각종 관체를 순차적으로 설치하고 공간부에 채움재 겸 보강재를 충진시킨 상태의 정 단면도이고, 도 12의 (a)(b)는 진동발생기를 작동시키면서 각각의 공간부에 채움재 겸 보강재를 충진시키는 상태를 보인 정 단면도를 나타낸 것이다.In addition, Figure 11 is a cross-sectional view of the installation of the temporary tunnel and the pipeline and the various pipes and the body is filled with a filler and reinforcing material in order to the present invention in the excavation hole, Figure 12 (a) (b) is a vibration The sectional view showing the state of filling the filler and reinforcement in each space while operating the generator is shown.

이에 따르면 본 발명의 비개착 가설 터널 및 관로는, According to this, the non-adhesive temporary tunnel and the conduit of the present invention,

파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성한 수개의 분할 파형 또는 요철판(1)들을 수개의 결합수단(2)을 통해 상호 결합시켜 원형이나 마제형, 아치형 또는 그 밖의 다각형의 모양으로 제작하여 굴진공(100) 내에 설치하고, 그 내부에 각종 관체(300)를 내설하는 비개착 가설 터널 및 관로(200)에 있어서, By using the corrugated plate or the concave-convex plate, several divided corrugated or concave-convex boards 1 bent into an arc or plate shape are joined together through a plurality of joining means 2 to form a circle, a horse, an arch, or another polygonal shape. In the non-attached temporary tunnel and the pipe line 200 which are manufactured and installed in the drilling hole 100 and in which various pipe bodies 300 are embedded therein,

상기 분할 파형 또는 요철판(1)들 중 가설 터널 및 관로의 최상단에 위치되는 분할 파형 또는 요철판(1)의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에, 수개의 채움재 겸 보강재 유출공(5a)이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관(5)을 설치한 것을 특징으로 한다.Several filling and reinforcing material outlet holes 5a on any one surface or both of the central upper surface or the lower surface of the divided waveform or uneven plate 1 located at the top of the temporary tunnel and conduit among the divided wave or uneven plate 1. ) Is characterized in that the installation of the filler and reinforcement supply hose guide pipe (5) perforated at a predetermined interval.

이때, 상기 채움재 겸 보강재 공급호스 안내관(5)은 용접을 통해 분할 파형 또는 요철판(1)의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 직접 고정 설치하거나, 또는 수개의 "U" 고정볼트(7c)와 너트(7a)를 이용하여 착탈 가능하게 고정 설치한 것을 특징으로 한다.At this time, the filler and the reinforcing material supply hose guide tube 5 is directly fixed to any one or both of the upper surface or the lower surface of the center or bottom of the corrugated plate 1 by welding, or several "U" fixing bolts It is characterized by fixedly attaching and detaching using 7c and the nut 7a.

뿐만 아니라, 소정형상의 가설 터널 및 관로(200)로 조립되는 수개의 분할 파형 또는 요철판(1) 중 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에, 각종 관체(300)를 가설 터널 및 관로(200) 내부에 삽입 설치할 때, 각종 관체(300)의 저부 외주면을 지지해주며 미끄럼 이동되도록 하는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일(3)을 부가 설치한 것을 특징으로 한다.In addition, various tubular bodies 300 are placed on the inner surface of the divided waveform or uneven plate 1 located at the lowermost part among several divided waveforms or uneven plate 1 assembled into a temporary tunnel and pipe 200 having a predetermined shape. When inserting and installing in the temporary tunnel and the pipe line 200, a pair of one or more pipe supports and spacers for supporting the outer circumferential surface of the various pipe bodies 300 and sliding them is additionally installed. It is done.

이때, 상기 관체 받침 및 간격재 겸용 레일(3)은 정단면이 "ㅗ"자 형상이나 "∧"자 형상 또는 "∩"자 형상 중 어느 한 형상을 갖도록 압출 또는 절곡 성형한 것을 특징으로 한다.At this time, the tubular base and the spacer rail (3) is characterized in that the front end surface is extruded or bent molded so as to have any shape of "ㅗ" shape, "∧" shape or "∩" shape.

또한, 상기 관체 받침 및 간격재 겸용 레일(3)은 분할 파형 또는 요철판(1)들 중 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 정해진 간격을 두고 설치하여 각각의 관체 받침 및 간격재 겸용 레일(3) 사이에 철근 및 와이어 메쉬 삽입용 공간부(3b)가 형성되게 한 것을 특징으로 한다.In addition, the pipe support and the spacer rail (3) is a predetermined interval of the divided waveform or uneven plate 1 located in the lowermost part of the temporary tunnel and the conduit 200 of the divided waveform or uneven plate (1) It is installed so as to be characterized in that the reinforcing bar and the wire mesh insert space portion (3b) is formed between each of the tubular support and the spacer rail (3).

또, 상기 관체 받침 및 간격재 겸용 레일(3)의 상면에는 가설 터널 및 관로(200)의 내면과 그 내부에 설치되는 각종 관체(300)의 외면 사이에 형성되는 공간부(S2)에 채움재 겸 보강재(6)를 충진시켜 구조물의 강도를 보강시킬 때 설치되는 철근 및 와이어 메쉬(4)가 관체 받침 및 간격재 겸용 레일(3)에 걸리지 않고 삽입될 수 있도록 하는 철근 및 와이어 메쉬 삽입홈(3a)을 정해진 간격을 두고 더 구비시킨 것을 특징으로 한다.In addition, the upper surface of the pipe support and the spacer rail (3) is filled in the space portion (S2) formed between the inner surface of the temporary tunnel and the pipeline 200 and the outer surface of the various pipe bodies 300 installed therein Reinforcing bars and wire mesh insertion grooves 3a for filling the reinforcing material 6 so that the reinforcing bars and wire meshes 4 installed when reinforcing the strength of the structure can be inserted without being caught by the tubular support and the spacer rail 3. ) Is further provided at a predetermined interval.

이때, 상기 관체 받침 및 간격재 겸용 레일(3)은 분할 파형 또는 요철판(1)들 중 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 용접 고정하거나, 또는 수개의 볼트(7b) 및 너트(7a)를 통해 착탈 가능하게 설치한 것 중 어느 한 형태로 설치한 것을 특징으로 한다.At this time, the pipe support and the spacer rail (3) is welded fixed to the inner surface of the divided waveform or uneven plate (1) located in the lowermost part of the temporary tunnel and the conduit 200 of the divided waveform or uneven plate (1) Or, it is characterized in that it is installed in any one form detachably installed through several bolts (7b) and nuts (7a).

또한, 상기 결합수단(2)은 걸림돌기(21a)와 삽입편(21b) 및 결합공(21c)을 구비하고 서로 인접된 분할 파형 또는 요철판(1)들의 4면 결합판(11)에 각각 천공된 결합구 체결공(11a)에 1개가 끼워져 결합된 상태에서 다른 하나가 상기 결합구 체결공(11a)에 결합되어 있는 쇄기형 결합구(21)의 결합공(21c)에 끼워져 결합되는 형태를 갖고 서로 인접된 두 분할 파형 또는 요철판(1)를 상호 일체로 결합시켜 주는 수 쌍의 쇄기형 결합구(21) 또는 서로 인접된 분할 파형 또는 요철판(1)들의 결합판(11)에 각각 천공된 결합구 체결공(11a)에 끼워져 상호 나사 결합되는 수개의 볼트(22a) 및 너트(22b)로 구성된 것을 특징으로 한다.In addition, the coupling means (2) has a locking projection (21a), the insertion piece (21b) and the coupling hole (21c) and each adjacent to the four-sided coupling plate 11 of the divided waveform or uneven plate (1) In the state in which one is inserted into and coupled to the perforated coupler fastening hole 11a, the other is inserted into the coupling hole 21c of the wedge-shaped coupler 21 coupled to the coupler fastening hole 11a. A pair of wedge-shaped couplers 21 for coupling the two divided waveforms or the uneven plate 1 adjacent to each other integrally with each other, or the coupling plate 11 of the divided waveforms or the uneven plate 1 adjacent to each other. It is characterized in that it consists of several bolts 22a and nuts 22b which are fitted into each of the perforated coupler fastening holes 11a and screwed together.

한편, 도 13은 본 발명의 시공공법을 설명하기 위한 시공 순서도를 나타낸 것이다.On the other hand, Figure 13 shows a construction flow chart for explaining the construction method of the present invention.

이에 따르면 본 발명의 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법은,According to the construction method of the non-adhesive temporary tunnels and pipes using the divided waveform or uneven plate of the present invention,

굴진공(100)의 내부에 설치되는 비개착 가설 터널 및 관로(200)를 시공하는 공법에 있어서,In the construction method of the non-adhesive temporary tunnel and pipe line 200 installed in the drilling hole 100,

공장에서 파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성하고, 4면에는 수개의 결합구 체결공(11a)이 정해진 간격으로 천공된 결합판(11)을 용접 설치하여 수개의 분할 파형 또는 요철판(1)들을 제작하되, 일부 분할 파형 또는 요철판(1)의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공(5a)이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관(5)을 설치하고, 또 일부 분할 파형 또는 요철판(1)의 내면에는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일(3)을 설치한 다음 이들을 현장으로 이송시키는 공정과;In the factory, using a corrugated plate or a concave-convex plate to bend to form an arc or a plate, and welded to the joining plate (11) in which four joining holes (11a) are drilled at predetermined intervals on the four sides of several divided waveforms or The uneven plate (1) is manufactured, but the filler and the reinforcing material perforated at a predetermined interval of several filler and reinforcing material outlet holes (5a) on any one side or both of the central upper surface or the lower surface of the partly divided waveform or uneven plate (1) Installing a supply hose guide pipe (5), and installing a pair or more pipe support and spacer rail (3) on the inner surface of the partly corrugated wave or uneven plate (1), and transferring them to the site; ;

현장의 지반 상에 굴진공(100)을 뚫는 공정과;Drilling a hole 100 on the ground of the site;

상기 굴진공(100) 내에 결합수단(2)들을 이용하여 수개의 분할 파형 또는 요철판(1)들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로(200)로 조립 설치하되, 가설 터널 및 관로(200)의 최상단에는 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 채움재 겸 보강재 공급호스 안내관(5)이 설치되어 있는 분할 파형 또는 요철판(1)을 위치시켜 조립하는 공정과;Assembling and installing as an unattached temporary tunnel and pipe line 200 having a predetermined shape by connecting several divided waveforms or uneven plates 1 in the longitudinal and transverse directions using coupling means 2 in the drilling hole 100. However, at the top of the temporary tunnel and the pipe line 200, the wave form or the uneven plate (1) having the filling material and the reinforcing material supply hose guide pipe (5) is installed on one or both of the upper and lower surfaces of the center to assemble Process;

상기 분할 파형 또는 요철판(1)의 중앙 상면에 설치되어 있는 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입시켜 굴진공(100)과 가설 터널 및 관로(200)의 외주면 사이에 형성된 공간부(S1)로 채움재 겸 보강재(6)를 주입시켜 채워 주는 공정과; Filler and reinforcement supply hose (8) is inserted through the filler and reinforcement supply hose guide pipe (5) installed on the central upper surface of the divided wave or uneven plate (1) by drilling hole 100, temporary tunnel and pipe ( Injecting and filling the filler and reinforcement 6 into the space S1 formed between the outer circumferential surfaces of the 200;

채움재 겸 보강재(6)의 양생 후 상기 가설 터널 및 관로(200)의 내부로 각종 관체(300)를 삽입 설치하는 공정과;Inserting and installing various pipe bodies (300) into the temporary tunnel and the conduit (200) after curing of the filler and reinforcement (6);

상기 분할 파형 또는 요철판(1)의 중앙 하면에 설치되어 있는 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입시켜 상기 각종 관체(300)의 삽입에 의해 형성된 가설 터널 및 관로(200)의 내주면과 각종 관체(300)의 외주면 사이에 형성된 공간부(S2)에 채움재 겸 보강재(6)를 주입시켜 채워 주는 공정;으로 이루어진 것을 특징으로 한다.Filler and reinforcement supply hose 8 is inserted through the filler and reinforcement supply hose guide tube 5 installed on the center lower surface of the divided wave or concave-convex plate 1 and formed by the insertion of the various pipe bodies 300. Characterized in that it comprises a step of injecting and filling the filler and reinforcing material 6 in the space (S2) formed between the inner circumferential surface of the temporary tunnel and the pipe line 200 and the outer circumferential surface of the various pipe bodies (300).

또, 상기 굴진공(100) 내에 결합수단(2)들을 이용하여 수개의 분할 파형 또는 요철판(1)들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로(200)로 조립 설치할 때, 가설 터널 및 관로(200)의 최하단에는 관체 받침 및 간격재 겸용 레일(3)을 구비한 분할 파형 또는 요철판(1)을 위치시켜 조립한 것을 특징으로 한다.In addition, by using the coupling means (2) in the drilling hole 100 to connect several divided waveforms or uneven plate (1) in the longitudinal and transverse direction to the non-attached temporary tunnel and pipe 200 having a predetermined shape When assembling and installing, it is characterized in that the lowermost end of the temporary tunnel and the pipe line 200 is assembled by placing a divided wave or uneven plate (1) provided with a pipe support and spacer rail (3).

또한, 상기 가설 터널 및 관로(200)의 내부로 각종 관체(300)를 삽입 설치할 때, 상기 가설 터널 및 관로(200)의 입구에 각종 관체(300)를 위치시킨 후 최하단 분할 파형 또는 요철판(1)의 내면에 설치되어 있는 관체 받침 및 간격재 겸용 레일(3)을 따라 밀어넣어 가설 터널 및 관로(200)의 내부로 각종 관체(300)를 삽입 설치하는 것을 특징으로 한다.In addition, when inserting the various pipe body 300 into the interior of the temporary tunnel and the pipe line 200, after placing the various pipe body 300 at the inlet of the temporary tunnel and pipe line 200, the lowermost divided waveform or uneven plate ( 1) It is characterized by inserting the various pipe bodies 300 into the interior of the temporary tunnel and the pipeline 200 by pushing along the pipe support and the spacer rail (3) installed on the inner surface.

또, 상기 가설 터널 및 관로(200)에 각종 관체(300)를 삽입 설치하기에 앞서, 상기 가설 터널 및 관로(200)의 내부에 철근 또는 와이어 메쉬(4)를 배근하는 공정을 더 실시하는 것을 특징으로 한다.Further, prior to inserting and installing the various pipe bodies 300 in the temporary tunnel and the pipeline 200, the step of reinforcing the reinforcement or wire mesh (4) in the interior of the temporary tunnel and pipeline 200 It features.

또한, 상기 굴진공(100)의 내면과 가설 터널 및 관로(200)의 외주면 사이에 형성된 공간부(S1) 또는 상기 가설 터널 및 관로(200)의 내주면과 각종 관체(300)의 외주면 사이에 형성된 공간부(S2)에 채움재 겸 보강재(6)를 주입시켜 채우기에 앞서, 상기 가설 터널 및 관로(200)의 내부 또는 각종 관체(300)의 내부에 수개의 진동발생기(9)를 설치한 다음, 상기한 공간부(S1)(S2) 내로 채움재 겸 보강재(6)를 주입할 때 진동발생기(9)를 작동시켜 주는 공정을 더 실시하는 것을 특징으로 한다.In addition, a space S1 formed between the inner surface of the drilling hole 100 and the outer circumferential surface of the temporary tunnel and the conduit 200 or between the inner circumferential surface of the temporary tunnel and the conduit 200 and the outer circumferential surface of the various tubular bodies 300. Prior to filling and filling the filler and reinforcement 6 into the space S2, after installing several vibration generators 9 inside the temporary tunnel and the conduit 200 or inside the various pipe bodies 300, When the filler and the reinforcing material 6 is injected into the spaces S1 and S2, the vibration generator 9 is operated.

이때, 상기 가설 터널 및 관로(200)는 원형을 포함하여 마제형과 아치형, 5각, 6각 및 8각의 다각형 모양 중 어느 한 형상을 갖는 것을 특징으로 한다.At this time, the temporary tunnel and the pipe line 200 is characterized in that it has a shape of a horseshoe and arch, including a circular shape, a polygonal shape of five, six and eight angles.

또, 상기 채움재 겸 보강재(6)로는 시멘트 그라우트재, 모르타르, 수지 모르타르, 뿜칠재 및 현장 타설 콘크리트를 포함하는 것을 특징으로 한다.In addition, the filler and reinforcing material (6) is characterized in that it comprises a cement grout material, mortar, resin mortar, spraying material and in-situ concrete.

이와 같은 구성 및 공정으로 이루어진 본 발명의 작용효과를 설명하면 다음과 같다.Referring to the effect of the present invention made of such a configuration and process as follows.

먼저, 본 발명의 비개착 가설 터널 및 관로(200)는, 가설 터널 및 관로(200) 자체를 구성하는 수개의 분할 파형 또는 요철판(1)들 중 가설 터널 및 관로(200)의 최상단에 위치되는 분할 파형 또는 요철판(1)의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공(5a)이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관(5)을 설치한 것을 주요기술 구성요지로 한다.First, the non-adhesive temporary tunnel and pipeline 200 of the present invention is located at the top of the temporary tunnel and pipeline 200 among several divided waveforms or uneven plates 1 constituting the temporary tunnel and pipeline 200 itself. Filler and reinforcing material supply hose guide pipe 5 having a plurality of filler and reinforcing material outlet holes 5a are provided at predetermined intervals on either or both of the central upper or lower surface of the divided waveform or uneven plate 1 to be formed. One of the main technical components is as follows.

이때, 상기 비개착 가설 터널 및 관로(200)는 파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성한 수개의 분할 파형 또는 요철판(1)들을 굴진공(100) 내에서 수개의 결합수단(2)을 통해 상호 결합시켜 원형이나 마제형, 아치형 또는 그 밖의 다각형의 모양으로 제작한 구조를 갖는다.At this time, the non-adhesive temporary tunnel and the conduit 200 is a number of coupling means in the drilling hole 100 of the divided wave or uneven plate (1) formed by bending the arc or plate using a corrugated plate or uneven plate (2) has a structure made in the shape of a circle, horseshoe, arches or other polygons by mutual coupling.

한편, 상기 채움재 겸 보강재 공급호스 안내관(5)은 분할 파형 또는 요철판(1)의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 용접을 통해 직접 고정 설치하거나, 또는 수개의 "U" 고정볼트(7c)와 너트(7a)를 이용하여 착탈 가능하게 고정 설치한 형태를 갖는다.On the other hand, the filler and reinforcing material supply hose guide pipe (5) is installed directly fixed by welding to any one or both of the upper surface or the lower surface of the center of the divided wave or uneven plate (1), or several "U" fixing bolts It has the form which fixedly attached and detachable using 7c and the nut 7a.

상기와 같이 가설 터널 및 관로(200)의 최상방부에 위치되는 분할 파형 또는 요철판(1)의 중앙 상면(외부; 도 3의 (b) 참조) 또는 하면(내부; 도 3의 (a) 참조) 또는 양면 모두(도 3의 (c) 참조)에 채움재 겸 보강재 공급호스 안내관(5)을 설치하여 주게 되면, 가설 터널 및 관로(200)의 외주면과 굴진공(100) 사이에 형성된 공간부(S1)에는 최상방부에 위치되는 분할 파형 또는 요철판(1)의 중앙 상면(외부)에 설치되어 있는 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입하여 채움재 겸 보강재(6)를 주입시킬 수 있고, 각종 관체(300)의 외주면과 가설 터널 및 관로(200)의 내주면 사이에 형성되는 공간부(S2)에는 최상방부에 위치되는 분할 파형 또는 요철판(1)의 중앙 하면(내부)에 설치되어 있는 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입하여 채움재 겸 보강재(6)를 주입시킬 수 있다.As described above, the central upper surface (outside; see FIG. 3 (b)) or the bottom surface (inside; FIG. 3 (a)) of the divided waveform or uneven plate 1 located at the uppermost part of the temporary tunnel and the conduit 200 ) Or both sides (see (c) of FIG. 3) when the filler and reinforcement supply hose guide tube 5 is installed, the space formed between the outer circumferential surface of the temporary tunnel and the conduit 200 and the drilling hole 100. Filler and reinforcement supply hose (8) is inserted into (S1) through a filler and reinforcement supply hose guide tube (5) installed on the upper part (outside) of the divided waveform or uneven plate (1) located in the uppermost portion Filler and reinforcement (6) can be injected, the space portion (S2) formed between the outer circumferential surface of the various tubular body 300 and the inner circumferential surface of the temporary tunnel and the conduit 200 is divided waveform or uneven plate ( Filler and reinforcement supply hose guide pipe (5) installed on the lower surface (inside) of 1) By inserting the filler Greater reinforcing supply hose (8) can be injected into fill material Greater reinforcing material (6).

따라서, 가설 터널 및 관로(200)와 굴진공 사이 또는 각종 관체(300)와 가설 터널 및 관로(200) 사이에 형성되는 공간부(S1)(S2)에 채움재 겸 보강재(6)를 채우는 작업이 간편하여 공사에 따른 시간과 인건비 등을 대폭 줄일 수 있고, 특히 이들 공간부(S1)(S2)에 채움재 겸 보강재(6)를 완벽히 채울 수 있어 구조물 전체 강도를 균일하게 유지시킬 수 있을 뿐만 아니라 강도 자체를 대폭 증대시킬 수 있는 것이다.Therefore, filling the reinforcing material and reinforcing material (6) in the space (S1) (S2) formed between the temporary tunnel and the conduit 200 and the drilling hole or between the various tubular body 300 and the temporary tunnel and the conduit (200) It is simple and can greatly reduce the time and labor cost according to the construction, and in particular, it is possible to completely fill the filling material and reinforcement (6) in these spaces (S1) (S2) can not only maintain the overall strength of the structure uniformly but also strength It can greatly increase itself.

또한, 본 발명은 소정형상을 갖는 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일(3)을 부가 설치하여, 각종 관체(300)를 가설 터널 및 관로(200) 내부에 삽입 설치할 때, 상기 관체 받침 및 간격재 겸용 레일(3)이 각종 관체(300)의 저부 외주면을 받쳐 지지해주면서 양자간 마찰력을 최대한 줄여 주어 각종 관체(300) 자체가 원활히 미끄러져 이동되며 가설 터널 및 관로(200)의 내부로 삽입 설치될 수 있도록 한 것을 또 다른 주요기술 구성요소로 한다.In addition, in the present invention, a pair of one or more pipe support and spacer double rails is added to the inner surface of the divided waveform or uneven plate 1 located at the lowermost portion of the temporary tunnel and the pipe 200 having a predetermined shape. When the various pipes 300 are inserted into and installed inside the temporary tunnel and the pipe line 200, the pipe support and the spacer double rail 3 support the outer peripheral surfaces of the bottoms of the pipes 300 to support friction between the two pipes. By reducing as much as possible the various pipes 300 itself to move smoothly and to be inserted into the installation of the temporary tunnel and the pipeline 200 is another major technology component.

이때, 상기 관체 받침 및 간격재 겸용 레일(3)은 각종 관체(300)들의 크기 및 중량에 대응하여 다양한 형태로 제작하여 설치할 수 있는데, 그 중 하나는 도 4 및 도 8에 도시한 바와 같이 일반 기차 레일과 같이 정 단면이 "ㅗ"자 형상을 갖도록 압출 성형할 수도 있고, 다른 형태로는 철판을 이용하여 도 6의 (a)와 같이 "∧"자 형상 또는 도 6의 (b)와 같이 "∩"자 형상을 갖도록 프레스를 통해 절곡 성형할 수도 있다.At this time, the pipe support and the spacer rail (3) can be manufactured and installed in various forms corresponding to the size and weight of the various pipe bodies 300, one of which is as shown in Figures 4 and 8 Like the train rail, the cross section may be extruded to have a "ㅗ" shape, and in another form, a steel plate may be used to form a "∧" shape as shown in FIG. 6A or FIG. 6B. It may be bent and molded through a press to have a "∩" shape.

상기와 같은 방식을 통해 성형한 관체 받침 및 간격재 겸용 레일(3) 중 전자의 경우는 각종 관체(300)들의 크기 및 중량이 크고 많이 나가는 경우 바람직하고, 후자의 경우는 관체들의 크기가 적고 중량도 적게 나가는 경우 바람직하며, 특히 정단면이 "∧"자 형상을 갖는 경우 각종 관체(300)와 관체 받침 및 간격재 겸용 레일(3) 사이의 마찰력을 최소한으로 줄일 수 있어 좋다.The former of the tubular support and the spacer combined rail (3) formed through the above-described method is preferable when the size and weight of the various tubular bodies 300 are large and outgoing, and the latter case is small in size and weight. It is preferable to go out even less, especially when the front end surface has a "∧" shape can be reduced to the minimum frictional force between the various tubular body 300 and the tubular support and the spacer rail (3).

이때, 상기 관체 받침 및 간격재 겸용 레일(3)은 생산 공장에서 분할 파형 또는 요철판(1)들 중 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 용접 고정하거나, 또는 수개의 볼트(7b) 및 너트(7a)를 통해 착탈 가능하게 설치하는 것이 바람직하나, 상기 관체 받침 및 간격재 겸용 레일(3)을 설치함으로 인해 분할 파형 또는 요철판(1)의 중량이 많이 나가 이동성이 좋지 않을 경우에는 가설 터널 및 관로(200) 시공현장에서 용접 또는 수개의 볼트(7b) 및 너트(7a)를 통해 착탈 가능하게 설치할 수도 있다.In this case, the pipe support and the spacer rail (3) is the inner surface of the divided waveform or uneven plate (1) located in the lowermost part of the temporary tunnel and the conduit 200 of the divided waveform or uneven plate (1) in the production plant It is preferable to install or detachably weld to or to be detachably installed through several bolts 7b and nuts 7a. If the weight of the) is not good mobility is not good in the construction of the temporary tunnel and pipeline 200 may be installed detachably through welding or several bolts (7b) and nuts (7a).

상기와 같이 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일(3)을 부가 설치하여, 각종 관체(300)를 가설 터널 및 관로(200) 내부에 삽입 설치할 때, 상기 관체 받침 및 간격재 겸용 레일(3)이 각종 관체(300)의 저부 외주면을 받쳐 지지해주면서 양자간의 마찰력을 크게 줄여주게 되므로 각종 관체(300) 자체가 관체 받침 및 간격재 겸용 레일(3)의 상면을 타고 원활히 미끄러져 삽입되게 되어 각종 관체를 원활히 설치할 수 있다.As described above, a pair of one or more pipe support and spacer rails 3 are additionally installed on the inner surface of the divided waveform or uneven plate 1 located at the lowermost part of the temporary tunnel and the pipe line 200 to provide various pipes ( When the 300 is inserted into the temporary tunnel and the pipeline 200, the tubular support and the spacer rail 3 support the outer peripheral surface of the bottom of the various tubular bodies 300, thereby greatly reducing the frictional force between the various tubular bodies. 300 itself slides smoothly on the upper surface of the tubular support and the spacer rail (3) can be inserted smoothly to install a variety of tubular.

뿐만 아니라, 공사시간 및 비용을 대폭 줄일 수 있고, 또한 별도의 간격 유지구 또는 스페이서 등을 설치하지 않아도 가설 터널 및 관로 내부에서 각종 관체를 받쳐주고 있는 관체 받침 및 간격재 겸용 레일(3)에 의해 도 11의 확대도와 같이 각종 관체(300)의 외주면과 가설 터널 및 관로(200)의 내주면 사이에 일정한 폭을 갖는 공간부(S2)가 구비되어 차후 이 공간부(S2)에 채움재 겸 보강재(6)를 원활히 충진시켜 줄 수 있음은 물론 이들 사이의 구조강도를 동일하게 유지시킬 수 있어, 구조물 자체의 강도를 전체적으로 동일하게 유지시킬 수 있으며, 또한 가설 터널 및 관로(200) 상부의 지반 침하를 완벽히 방지할 수 있고, 또 각종 관체(300)의 품질 및 안전도를 대폭 향상시킬 수 있다.In addition, construction time and cost can be significantly reduced, and also by the pipe support and spacer rail (3) that supports various pipes in the temporary tunnel and pipelines without installing a separate space holder or spacer, etc. As shown in the enlarged view of FIG. 11, a space S2 having a predetermined width is provided between the outer circumferential surface of the various pipe bodies 300 and the inner circumferential surface of the temporary tunnel and the conduit 200, thereby filling and reinforcing the space S2. ) Can be smoothly filled, as well as to maintain the same structural strength between them, it is possible to maintain the same strength of the structure itself as a whole, and also to completely settle the ground of the temporary tunnel and pipeline 200 It can prevent and also can significantly improve the quality and safety of the various pipe bodies 300.

한편, 가설 터널 및 관로(200)의 내부에 각종 관체(300)를 삽입 설치한 후 각종 관체(300)의 외주면과 가설 터널 및 관로(200)의 내주면 사이에 형성된 공간부(S2)에 시멘트 그라우트재나, 모르타르, 수지 모르타르, 뿜칠재 및 현장 타설 콘크리트 등의 채움재 겸 보강재(6)만 충진시킬 경우, 구조강도가 원하는 강도가 나타나지 않아 이들 공간부(S2) 사이에 철근 또는 와이어 메쉬(4)를 배근할 필요가 있을 수 있다.Meanwhile, after inserting and installing various pipe bodies 300 inside the temporary tunnel and the pipe line 200, cement grout is formed in the space S2 formed between the outer circumferential surface of the various pipe bodies 300 and the inner circumferential surface of the temporary tunnel pipe line and the pipe line 200. When only the filler and reinforcing material (6) such as ash, mortar, resin mortar, foaming material, and cast-in-place concrete is filled, the structural strength does not show the desired strength, and the reinforcing bar or wire mesh (4) is interposed between these spaces (S2). You may need to work out.

그런데, 상기와 같이 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 상면이 평탄한 형상을 갖는 관체 받침 및 간격재 겸용 레일(3)을 그대로 설치할 경우 철근 또는 와이어 메쉬(4)가 관체 받침 및 간격재 겸용 레일(3)의 상면에 올려지는 형태를 갖게 되어 철근 또는 와이어 메쉬(4) 자체가 각종 관체(300)를 가설 터널 및 관로(200)의 내부로 삽입 설치하는데 장애물로 작용하게 된다.However, when installing the pipe support and the spacer rail (3) having a flat upper surface as it is on the inner surface of the divided waveform or uneven plate (1) located in the lowermost part of the temporary tunnel and pipeline 200 as described above Alternatively, the wire mesh 4 may be formed on the upper surface of the pipe support and the spacer rail 3 so that the reinforcing wire or the wire mesh 4 itself may form various pipe bodies 300. It will act as an obstacle to the installation.

따라서, 본 발명에서는 필요에 따라 상기 관체 받침 및 간격재 겸용 레일(3)을 가설 터널 및 관로(200)의 최하방부에 위치되는 분할 파형 또는 요철판(1)의 내면에 설치할 때 전체에 걸쳐 길게 설치하지 않고 도 9의 (a)-(c)와 같이 관체 받침 및 간격재 겸용 레일(3)들을 작은 길이로 절단하여 정해진 간격을 두고 설치하여 각각의 관체 받침 및 간격재 겸용 레일(3) 사이에 철근 및 와이어 메쉬 삽입용 공간부(3b)가 형성되게 하거나, 또는 상기 관체 받침 및 간격재 겸용 레일(3)의 상면에 도 10의 (a)-(c)와 같이 정해진 간격(즉, 철근 및 와이어 메쉬(4)가 설치되는 간격)을 두고 철근 및 와이어 메쉬 삽입홈(3a)을 더 형성시켜 주었다.Therefore, in the present invention, when the pipe support and the spacer double rail (3) is installed on the inner surface of the divided waveform or uneven plate (1) located at the lowermost part of the temporary tunnel and the conduit (200) as necessary, the entire length is long. Without installing, as shown in (a)-(c) of FIG. 9, the tubular support and the spacer rail (3) are cut into small lengths and installed at predetermined intervals, respectively, between each tubular support and the spacer rail (3). Reinforcing bar and wire mesh insertion space (3b) is formed on the upper surface of the pipe support and the spacer rail (3), the interval defined as (a)-(c) of FIG. And a space between the wire mesh 4 is installed) to further form the reinforcing bars and the wire mesh insertion grooves 3a.

이에 따라, 상기 가설 터널 및 관로(200)의 내주면과 그 내부에 설치되는 각종 관체(300)의 외주면 사이에 형성되는 공간부(S2)에 채움재 겸 보강재(6)를 충진시켜 구조물의 강도를 보강시킬 때 설치되는 철근 및 와이어 메쉬(4)가 상기 관체 받침 및 간격재 겸용 레일(3)들 사이에 형성된 철근 및 와이어 메쉬 삽입용 공간부(3b) 또는 상기 관체 받침 및 간격재 겸용 레일(3)의 상면에 형성된 철근 및 와이어 메쉬 삽입홈(3a)에 삽입된 형태를 갖게 되므로 관체 받침 및 간격재 겸용 레일(3)의 설치 여부에 무관하게 상기 가설 터널 및 관로(200)의 내주면과 그 내부에 설치되는 각종 관체(300)의 외주면 사이에 형성되는 공간부(S2) 사이에 철근 또는 와이어 메쉬(4)를 원활히 설치할 수 있어 구조물의 강도를 전체적으로 증대시킬 수 있는 것이다.Accordingly, the filling material and the reinforcing material 6 is filled in the space S2 formed between the inner circumferential surface of the temporary tunnel and the pipeline 200 and the outer circumferential surfaces of the various pipe bodies 300 installed therein, thereby reinforcing the strength of the structure. Reinforcing bar and wire mesh (4) is installed when the reinforcement and wire mesh insertion space (3b) formed between the tubular support and spacer rails (3) or the tubular support and spacer rail (3) Since it has a shape inserted into the reinforcing bar and the wire mesh insertion groove (3a) formed on the upper surface of the irrespective of whether the pipe support and the spacer rail (3) is installed, the inner circumferential surface of the temporary tunnel and the pipe 200 and the inside Reinforcing bars or wire mesh 4 can be smoothly installed between the spaces S2 formed between the outer circumferential surfaces of the various pipe bodies 300 to be installed, thereby increasing the strength of the structure as a whole.

또한, 상기 결합수단(2)으로는 도 7과 같이 걸림돌기(21a)와 삽입편(21b) 및 결합공(21c)을 구비한 수 쌍의 쇄기형 결합구(21)로 구성할 수도 있고, 또한 도 11 등과 같이 수개의 볼트(22a) 및 너트(22b)로 구성할 수도 있는데, 쇄기형 결합구(21)의 경우 서로 인접된 분할 파형 또는 요철판(1)들의 4면 결합판(11)에 각각 천공된 결합구 체결공(11a)에 1개가 끼워져 결합된 상태에서 다른 하나가 상기 결합구 체결공(11a)에 결합되어 있는 쇄기형 결합구(21)의 결합공(21c)에 끼워 결합시켜 서로 인접된 두 분할 파형 또는 요철판(1)를 상호 일체로 결합시켜 주면 되고, 볼트(22a) 및 너트(22b)의 경우 서로 인접된 분할 파형 또는 요철판(1)들의 결합판(11)에 각각 천공된 결합구 체결공(11a)에 볼트(22a)를 끼운 다음 상기 볼트(22a)에 너트(22b)를 체결시켜 주면 된다.In addition, the coupling means 2 may be composed of a pair of wedge-shaped coupling sphere 21 having a locking projection 21a, an insertion piece 21b and a coupling hole 21c as shown in FIG. In addition, the bolt 22a and the nut 22b may be configured as shown in FIG. 11. In the case of the wedge-shaped coupling hole 21, the four-side coupling plate 11 of the divided waveforms or uneven plates 1 adjacent to each other is provided. In the state in which one is fitted into each of the coupling hole fastening hole (11a) perforated in the other one is fitted into the coupling hole (21c) of the wedge-shaped coupling sphere 21 is coupled to the coupling hole coupling hole (11a) The two divided waveforms or concave-convex plates 1 adjacent to each other may be integrally coupled to each other. In the case of the bolts 22a and the nut 22b, the joining plates 11 of the divided waveforms or concave-convex plates 1 adjacent to each other may be used. The bolt 22a may be inserted into the coupling hole coupling hole 11a respectively drilled into the bolt 22a, and then the nut 22b may be fastened to the bolt 22a.

이때, 도시는 생략하였으나 서로 인접된 분할 파형 또는 요철판(1)들의 결합판(11) 사이에 누수 방지용 고무판이나 실리콘 판 등을 더 설치해 주면 두 분할 파형 또는 요철판(1)들의 결합부에서 발생되는 틈새를 통해 지수가 가설 터널 및 관로(200) 내부로 누수되는 것을 방지할 수도 있다.At this time, although not shown, if a rubber plate or a silicon plate for preventing leakage is further installed between the adjacent joints 11 of the divided corrugations or the concave-convex plates 1, it is generated at the joining portion of the two divided corrugated or concave-convex plates 1. The gap may be prevented from leaking into the hypothesis tunnel and the pipeline 200.

뿐만 아니라, 상기 분할 파형 또는 요철판(1)들의 4면에 설치한 결합판(11)의 설치를 배제하고, 상기 분할 파형 또는 요철판(1)의 4 내주면을 따라 정해진 간격을 두고 수개의 볼트를 용접을 통해 고정 설치하고, 일정 폭으로 절단된 상태에서 양단부에서 길이방향으로 상기 볼트들의 간격에 대응하는 위치에 각각 볼트 통과공이 두 줄로 천공된 구성을 갖는 이음부 덧판을 서로 인접된 분할 파형 또는 요철판(1)의 결합부 내주면 일부에 겹쳐지는 형태로 설치한 다음 수개의 볼트들을 통해 상기 이음부 덧판들이 두 분할 파형 또는 요철판을 상호 일체로 결합되도록 할 수도 있다.In addition, several bolts are provided at predetermined intervals along the four inner circumferential surfaces of the divided waveform or the uneven plate 1, excluding the installation of the coupling plate 11 installed on the four surfaces of the divided waveform or the uneven plate 1. Is fixed by welding, and the joint plate having a configuration in which the bolt through-holes are formed in two rows at the positions corresponding to the gaps of the bolts in the longitudinal direction at both ends in a state of being cut to a predetermined width or adjacent to each other, It may be installed in a form overlapping a part of the inner peripheral surface of the coupling portion of the concave-convex plate 1, and then through the several bolts, the joint plate may be combined with the two divided waveforms or concave-convex plate integrally.

한편, 본 발명의 시공공법에서는 먼저 현장과 멀리 떨어진 공장에서 파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성하고, 4면에는 수개의 결합구 체결공(11a)이 정해진 간격으로 천공된 결합판(11)을 용접 설치하여 수개의 분할 파형 또는 요철판(1)들을 제작하되, 가설 터널 및 관로(200)의 최상방부에 설치할 일부 분할 파형 또는 요철판(1)의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공(5a)이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관(5)을 설치하고, 또 가설 터널 및 관로(200)의 최하방부에 설치할 일부 분할 파형 또는 요철판(1)의 내면에는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일(3)을 설치한 다음 이들을 현장으로 이송시키게 된다.On the other hand, in the construction method of the present invention, first bent to form an arc or plate using a corrugated plate or uneven plate in a factory far from the field, and the four coupling holes (11a) are drilled at predetermined intervals on four sides The plate 11 is welded to produce several divided waveforms or uneven plates 1, but the upper part or the lower surface of the center of the partial divided waveforms or uneven plates 1 to be installed at the uppermost part of the temporary tunnel and the conduit 200. Part of the filler and reinforcement supply hose guide pipe (5) perforated at a predetermined interval on the one side or both sides of the filler and reinforcement outflow hole (5a) is installed, and part to be installed at the lowermost part of the temporary tunnel and pipeline 200 On the inner surface of the divided waveform or uneven plate (1) is installed a pair of one or more pipe support and spacer rail (3) and then transport them to the site.

또, 공장에서 분할 파형 또는 요철판(1)을 제작하여 이송하는 공정과 별개로 현장에서는 지반 상에 굴진공(100)을 뚫고, 이어서 상기 굴진공(100) 내에서 결합수단(2)들을 이용하여 수개의 파형 또는 요철판(1)들을 종 방향 및 횡 방향으로 연결시켜 소정형상(예를 들어 원형이나, 마제형, 아치형, 5각, 6각 및 8각의 다각형 모양 중 어느 한 형상)의 비개착 가설 터널 및 관로(200)로 조립 설치하되, 가설 터널 및 관로(200)의 최상단에는 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 채움재 겸 보강재 공급호스 안내관(5)이 설치되어 있는 분할 파형 또는 요철판(1)을 위치시켜 조립하게 된다.In addition, apart from the process of manufacturing and transferring the divided waveform or uneven plate 1 in the factory, the drilling hole 100 is drilled on the ground in the field, and then the coupling means 2 are used in the drilling hole 100. By connecting several corrugated or uneven plates 1 in a longitudinal direction and a transverse direction so that a ratio of a predetermined shape (for example, a shape of a polygonal shape of a circular shape, a horseshoe shape, an arc shape, a pentagonal shape, a hexagonal shape, and an octagonal shape) is observed. Install and install as an installation temporary tunnel and pipeline 200, the top of the temporary tunnel and pipeline 200 is divided waveforms that the filler and reinforcement supply hose guide pipe (5) is installed on one or both sides of the central upper surface or lower surface Alternatively, the uneven plate 1 is placed and assembled.

이때, 상기 굴진공(100) 내에 결합수단(2)들을 이용하여 수개의 분할 파형 또는 요철판(1)들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로(200)로 조립 설치할 때, 필요에 따라서는 상기 가설 터널 및 관로(200)의 최하단에는 관체 받침 및 간격재 겸용 레일(3)을 구비한 분할 파형 또는 요철판(1)을 위치시켜 조립할 수도 있다.At this time, by using the coupling means (2) in the drilling hole (100) by connecting several divided waveforms or uneven plate (1) in the longitudinal and transverse direction to the non-attached temporary tunnel and pipe 200 having a predetermined shape When assembling and installing, if necessary, at the lower end of the temporary tunnel and the pipe line 200, the divided corrugation or the uneven plate 1 having the pipe support and the spacer double rail 3 may be placed and assembled.

이후, 상기 분할 파형 또는 요철판(1)의 중앙 상면에 설치되어 있는 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입시켜, 상기 굴진공(100)과 가설 터널 및 관로(200)의 외주면 사이에 형성된 공간부(S1)로 채움재 겸 보강재(6)를 주입시켜 채워 양생시킨 다음, 상기 가설 터널 및 관로(200)의 내부로 각종 관체(300)를 삽입 설치하게 된다.Subsequently, the filler and reinforcement supply hose 8 is inserted through the filler and reinforcement supply hose guide tube 5 installed on the center upper surface of the divided corrugation or the uneven plate 1, and the drilling hole 100 and the hypothesis are inserted. Fill and cure the filler and reinforcement 6 into the space S1 formed between the outer circumferential surface of the tunnel and the conduit 200 to cure it, and then insert and install various pipe bodies 300 into the temporary tunnel and the conduit 200. Done.

이때, 비개착 가설 터널 및 관로(200)의 최하단 분할 파형 또는 요철판(1)의 내면에 관체 받침 및 간격재 겸용 레일(3)이 구비된 경우, 상기 가설 터널 및 관로(200)의 내부로 각종 관체(300)를 삽입 설치할 때, 가설 터널 및 관로(200)의 입구에 각종 관체(300)를 위치시킨 후 관체 받침 및 간격재 겸용 레일(3)을 따라 밀어넣어 가설 터널 및 관로의 내부로 각종 관체(300)를 삽입 설치하면 더욱 쉽게 각종 관체(300)를 가설 터널 및 관로(200)의 내부로 삽입 설치할 수 있다.In this case, when the pipe support and the spacer double rail (3) is provided on the innermost surface of the lowermost divided waveform of the non-adhesive temporary tunnel and the conduit 200 or the uneven plate 1, the temporary tunnel and the conduit 200 into the interior of the temporary tunnel and the conduit 200 When inserting and installing the various pipe bodies 300, the various pipe bodies 300 are positioned at the inlet of the temporary tunnel and the pipe line 200, and then pushed along the pipe support and the spacer rail 3 to the inside of the temporary tunnel and pipe lines. Inserting and installing the various pipe bodies 300 can more easily insert the various pipe bodies 300 into the interior of the temporary tunnel and the pipe line 200.

이어서, 상기 분할 파형 또는 요철판(1)의 중앙 하면에 설치되어 있는 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입시켜, 상기 각종 관체(300)의 삽입에 의해 형성된 가설 터널 및 관로(200)의 내주면과 각종 관체(300)의 외주면 사이에 형성된 공간부(S2)에 채움재 겸 보강재(6)를 주입시켜 채워 주는 공정을 실시하게 된다.Subsequently, the filler and reinforcing material supply hose 8 is inserted through the filler and reinforcing material supply hose guide tube 5 provided on the center lower surface of the divided corrugation or the uneven plate 1 to insert the various pipe bodies 300. Injecting the filler and reinforcing material 6 into the space S2 formed between the inner circumferential surface of the temporary tunnel and the pipe line 200 and the outer circumferential surface of the various pipe bodies 300 formed by the filling process.

즉, 본 발명이 적용된 상기 가설 터널 및 관로(200)의 최상단에는 채움재 겸 보강재 공급호스 안내관(5)이 구비된 분할 파형 또는 요철판(1)이 설치되어 있으므로, 상기 굴진공(100)의 내면과 가설 터널 및 관로(200)의 외주면 사이에 형성된 공간부(S1) 또는 상기 가설 터널 및 관로(200)의 내주면과 각종 관체(300)의 외주면 사이에 형성된 공간부(S2)에 채움재 겸 보강재(6)를 주입시켜 채울 때, 도 12의 (a)(b)와 같이 상기 가설 터널 및 관로(200)의 최상단에 설치되어 있는 분할 파형 또는 요철판(1)에 고정 설치된 채움재 겸 보강재 공급호스 안내관(5)을 통해 채움재 겸 보강재 공급호스(8)를 삽입시켜 공간부(S1)(S2)들의 내측부터 채움재 겸 보강재(6)가 충진되도록 하면 된다.That is, since the divided waveform or uneven plate (1) having the filler and the reinforcing material supply hose guide pipe (5) is installed at the top of the temporary tunnel and the pipeline 200 to which the present invention is applied, Filler and reinforcement in the space portion S1 formed between the inner surface and the outer circumferential surface of the temporary tunnel and the conduit 200 or the space portion S2 formed between the inner circumferential surface of the temporary tunnel and the conduit 200 and the outer circumferential surfaces of the various pipe bodies 300. Filling material and reinforcing material supply hose fixed to the divided waveform or uneven plate (1) is installed at the top of the temporary tunnel and pipeline 200 as shown in (a) (b) of Figure 12 when filling the filling Filler and reinforcement supply hose (8) is inserted through the guide tube (5) to fill the filler and reinforcement (6) from the inside of the space (S1) (S2).

상기와 같이 가설 터널 및 관로(200)의 최상단에 채움재 겸 보강재 공급호스 안내관(5)이 구비된 분할 파형 또는 요철판(1)을 설치하여 채움재 겸 보강재(6)를 충진시킬 경우, 시멘트 그라우트재, 모르타르, 수지 모르타르, 뿜칠재 및 현장 타설 콘크리트 등을 포함하는 채움재 겸 보강재(6)를 각각의 공간부(S1)(S2)에 원활하고도 완벽하게 충진시킬 수 있어, 가설 터널 및 관로(200)과 굴진공(100) 사이 또는 각종 관체(300)와 가설 터널 및 관로(200) 사이에 형성되는 공간부(S1)(S2)에 채움재 겸 보강재(6)를 채우는 작업이 매우 간편하여 공사에 따른 시간과 인건비 등을 대폭 줄일 수 있을 뿐만 아니라 이들 공간부에 채움재 겸 보강재가 완벽히 채워지게 되어 구조물 전체 강도를 균일하게 유지시킬 수 있음은 물론 강도 자체를 대폭 증대시킬 수 있는 것이다.When filling the filler and reinforcement (6) to install the divided corrugated or uneven plate (1) provided with a filler and reinforcement supply hose guide pipe (5) at the top of the temporary tunnel and the pipeline 200 as described above, cement grout Filler and reinforcement (6), including ash, mortar, resin mortar, fuming material and cast-in-place concrete, can be smoothly and completely filled in each space (S1) (S2). Filling and reinforcing material (6) in the space portion (S1) (S2) formed between the 200 and the drilling hole 100 or between the various tubular body 300 and the temporary tunnel and the pipeline 200 is very easy construction Not only can greatly reduce the time and labor costs, but also the filling material and reinforcement in these spaces are completely filled to maintain the overall strength of the structure uniformly, as well as to significantly increase the strength itself.

또한, 상기 가설 터널 및 관로(200)에 각종 관체(300)를 삽입 설치하기에 앞서, 구조보강을 위해 상기 가설 터널 및 관로(200)의 내부에 도 11 및 도 12의 (a)(b)와 같이 철근 또는 와이어 메쉬(4)를 배근하는 공정을 더 실시할 수도 있다.In addition, prior to inserting and installing various pipe bodies 300 in the temporary tunnel and the pipeline 200, the interior of the temporary tunnel and the pipeline 200 for structural reinforcement (a) (b) of FIG. As described above, the step of reinforcing the reinforcing bars or the wire mesh 4 may be further performed.

한편, 상기 굴진공(100)의 내면과 가설 터널 및 관로(200)의 외주면 사이에 형성된 공간부(S1) 또는 상기 가설 터널 및 관로(200)의 내주면과 각종 관체(300)의 외주면 사이에 형성된 공간부(S2)에 채움재 겸 보강재(6)를 주입시켜 채울 때, 채움재 겸 보강재(6)의 자중에 의해서만 각 공간부로 채워지게 할 경우 많은 시간이 걸릴 우려가 있을 뿐만 아니라, 각각의 공간부에 채움재 겸 보강재(6)가 빈틈없이 채워지지 않을 우려가 있다.Meanwhile, a space S1 formed between the inner surface of the drilling hole 100 and the outer circumferential surface of the temporary tunnel and the conduit 200 or between the inner circumferential surface of the temporary tunnel and the conduit 200 and the outer circumferential surface of the various tubular bodies 300. When filling and filling the filler and reinforcement 6 into the space S2, when filling the space with only the self-weight of the filler and the reinforcement 6, it may take a lot of time. The filler and reinforcement 6 may not be filled tightly.

따라서, 본 발명에서는 상기 굴진공(100)의 내면과 가설 터널 및 관로(200)의 외주면 사이에 형성된 공간부(S1) 또는 상기 가설 터널 및 관로(200)의 내주면과 각종 관체(300)의 외주면 사이에 형성된 공간부(S2)에 채움재 겸 보강재(6)를 주입시켜 채우기에 앞서, 도 12의 (a)(b)와 같이 상기 가설 터널 및 관로(200)의 내부 또는 각종 관체(300)의 내부에 수개의 진동발생기(9)를 설치한 다음, 상기한 공간부(S1)(S2) 내로 채움재 겸 보강재(6)를 주입할 때 진동발생기(9)를 작동시켜 주는 공정을 더 실시할 수 있도록 함으로써 각 공간부에 채움재 겸 보강재(6)를 충진시키는데 걸리는 시간을 줄일 수 있을 뿐만 아니라, 각각의 공간부에 채움재 겸 보강재(6)가 빈틈 없이 채워지게 되어 구조물의 강도 역시 대폭 증대시킬 수 있다.
Therefore, in the present invention, the space S1 formed between the inner surface of the excavation hole 100 and the outer circumferential surface of the temporary tunnel and the conduit 200 or the inner circumferential surface of the temporary tunnel and the conduit 200 and the outer circumferential surface of the various tubular bodies 300. Before filling and filling the filler and reinforcement 6 into the space S2 formed therebetween, as shown in FIG. 12A and FIG. 12B, the interior of the temporary tunnel and the conduit 200 or various kinds of pipe bodies 300. After installing several vibration generators 9 therein, the step of operating the vibration generator 9 when injecting the filler and reinforcement 6 into the spaces S1 and S2 may be further performed. By not only reducing the time taken to fill the filler and reinforcement 6 in each space portion, but also filling the filler and reinforcement 6 in each space portion without gaps can greatly increase the strength of the structure. .

상술한 실시 예는 본 발명의 가장 바람직한 예에 대하여 설명한 것이지만, 상기 실시 예에만 한정되는 것은 아니며, 본 발명의 기술사상을 벗어나지 않는 범위 내에서 다양한 변형이 가능하다는 것은 당업자에게 있어서 명백한 것이다.
It should be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined in the appended claims.

1 : 분할 파형 또는 요철판
11 : 결합판 11a : 결합구 체결공
2 : 결합수단
21 : 쇄기형 결합구 21a : 걸림돌기
21b :삽입편 21c : 결합공
22a : 볼트 22b : 너트
3 : 관체 받침 및 간격재 겸용 레일
3a : 철근 및 와이어 메쉬 삽입홈
3b : 철근 및 와이어 메쉬 삽입용 공간부
4 : 철근 및 와이어 메쉬
5 : 채움재 겸 보강재 공급호스 안내관 5a : 채움재 겸 보강재 유출공
6 : 채움재 겸 보강재
7a : 너트 7b : 볼트
7c : "U" 고정볼트
8 : 채움재 겸 보강재 공급호스
9 : 진동발생기
100 : 굴진공
200 : 가설 터널 및 관로
300 : 각종 관체
S1, S2 : 공간부
1: split waveform or uneven plate
11 coupling plate 11a coupling hole
2: combining means
21: wedge-type coupling sphere 21a: the locking projection
21b: Insertion piece 21c: Joining hole
22a: bolt 22b: nut
3: pipe support and spacer
3a: Reinforcing Bar and Wire Mesh Insert
3b: space for inserting rebar and wire mesh
4: rebar and wire mesh
5: Filler and stiffener supply hose guide pipe 5a: Filler and stiffener outflow hole
6: Filler and Reinforcement
7a: Nut 7b: Bolt
7c: "U" fixing bolt
8: Filler and Stiffener Supply Hose
9: vibration generator
100: drilling hole
200: temporary tunnel and pipeline
300: various tubes
S1, S2: space part

Claims (13)

파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성한 수개의 분할 파형 또는 요철판들을 수개의 결합수단을 통해 상호 결합시켜 원형이나 마제형, 아치형 또는 그 밖의 다각형의 모양으로 제작하여 굴진공 내에 설치하고, 그 내부에 각종 관체를 내설하는 비개착 가설 터널 및 관로에 있어서,
상기 분할 파형 또는 요철판들 중 가설 터널 및 관로의 최상단에 위치되는 분할 파형 또는 요철판의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관을 설치한 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
Using several corrugated boards or concave-convex boards, each divided corrugated or concave-convex board is formed into a circular or majestic, arched, or other polygonal shape and installed in the cavity through several joining means. In the non-attached temporary tunnels and pipelines in which various pipes are installed therein,
Filler and reinforcing material perforated at intervals of several filler and reinforcing material outlet holes on one or both of the central upper or lower surface of the divided waveform or uneven plate among the split wave or uneven plate Non-adhesive temporary tunnel and pipeline using a split wave or uneven plate, characterized in that the supply hose guide pipe is installed.
청구항 1에 있어서,
상기 채움재 겸 보강재 공급호스 안내관은,
용접을 통해 분할 파형 또는 요철판의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 직접 고정 설치하거나, 또는 수개의 "U" 고정볼트와 너트를 이용하여 착탈 가능하게 고정 설치한 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
The method according to claim 1,
The filler and reinforcement supply hose guide tube,
Divided waveform, characterized in that the fixed waveform is directly fixed to one or both of the upper surface or the lower surface of the divided waveform or uneven plate by welding, or detachably fixed using a few "U" fixing bolts and nuts. Or unattached temporary tunnels and pipelines using uneven plate.
청구항 1에 있어서,
상기 분할 파형 또는 요철판들 중 가설 터널 및 관로의 최하방부에 위치되는 분할 파형 또는 요철판의 내면에는, 각종 관체를 가설 터널 및 관로 내부에 삽입 설치할 때 각종 관체의 저부 외주면을 지지해주며 미끄럼 이동되도록 하는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일을 부가 설치한 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
The method according to claim 1,
On the inner surface of the divided waveform or uneven plate which is located at the lowermost part of the temporary tunnel and conduit among the divided waveform or uneven plate, when the various pipes are inserted into the temporary tunnel and the conduit, the bottom circumferential surface of the bottom of the various pipes is supported and slides. A non-adhesive temporary tunnel and pipeline using a split corrugated or uneven plate further comprising a pair of one or more tube support and spacer rails.
청구항 3에 있어서,
상기 관체 받침 및 간격재 겸용 레일은,
정단면이 "ㅗ"자 형상이나 "∧"자 형상 또는 "∩"자 형상 중 어느 한 형상을 갖도록 압출 또는 절곡 성형한 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
The method according to claim 3,
The pipe support and the spacer combined rail,
A non-adhesive temporary tunnel and pipe line using a divided waveform or uneven plate characterized in that the front end surface is extruded or bent to have a shape of "ㅗ" shape, "∧" shape, or "자" shape.
청구항 3에 있어서,
상기 관체 받침 및 간격재 겸용 레일은,
상기 분할 파형 또는 요철판의 내면에 정해진 간격을 두고 설치하여 각각의 관체 받침 및 간격재 겸용 레일 사이에 철근 및 와이어 메쉬 삽입용 공간부가 형성되게 한 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
The method according to claim 3,
The pipe support and the spacer combined rail,
Non-adhesion using split waveforms or uneven plates, provided at intervals on the inner surface of the split waveforms or uneven plates to form a space for inserting reinforcing bars and wire mesh between respective pipe supports and spacers. Hypothetical tunnels and pipelines.
청구항 3에 있어서,
상기 관체 받침 및 간격재 겸용 레일의 상면에는,
철근 및 와이어 메쉬 삽입홈을 정해진 간격을 두고 더 구비시킨 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
The method according to claim 3,
On the upper surface of the pipe support and the spacer double rail,
Non-adhesive temporary tunnel and pipeline using a divided waveform or uneven plate characterized in that the reinforcing bars and wire mesh insertion grooves are further provided at predetermined intervals.
청구항 3에 있어서,
상기 관체 받침 및 간격재 겸용 레일은,
상기 분할 파형 또는 요철판들 중 가설 터널 및 관로의 최하방부에 위치되는 분할 파형 또는 요철판의 내면에 용접 고정하거나, 또는 수개의 볼트 및 너트를 통해 착탈 가능하게 설치한 것 중 어느 한 형태로 설치한 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로.
The method according to claim 3,
The pipe support and the spacer combined rail,
It is installed in any one of the divided waveform or uneven plate welded fixed to the inner surface of the divided waveform or uneven plate which is located at the lowermost part of the temporary tunnel and conduit, or detachably installed through several bolts and nuts. Non-adhesive temporary tunnels and pipelines using divided waveforms or irregularities.
굴진공의 내부에 설치되는 비개착 가설 터널 및 관로를 시공하는 공법에 있어서,
공장에서 파형판 또는 요철판을 이용하여 호형 또는 판형으로 절곡 형성하고, 4면에는 수개의 결합구 체결공이 정해진 간격으로 천공된 결합판을 용접 설치하여 수개의 분할 파형 또는 요철판들을 제작하되, 일부 분할 파형 또는 요철판의 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 수개의 채움재 겸 보강재 유출공이 정해진 간격을 두고 천공된 채움재 겸 보강재 공급호스 안내관을 설치한 다음 이들을 현장으로 이송시키는 공정과;
현장의 지반 상에 굴진공을 뚫는 공정과;
상기 굴진공 내에 결합수단들을 이용하여 수개의 분할 파형 또는 요철판들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로로 조립 설치하되, 가설 터널 및 관로의 최상단에는 중앙 상면 또는 하면 중 어느 한 면 또는 양면에 채움재 겸 보강재 공급호스 안내관이 설치되어 있는 분할 파형 또는 요철판을 위치시켜 조립하는 공정과;
상기 분할 파형 또는 요철판의 중앙 상면에 고정 설치된 채움재 겸 보강재 공급호스 안내관을 통해 채움재 겸 보강재 공급호스를 삽입시켜 굴진공과 가설 터널 및 관로의 외주면 사이에 형성된 공간부로 채움재 겸 보강재를 주입시켜 채워 주는 공정과;
채움재 겸 보강재의 양생 후 상기 가설 터널 및 관로의 내부로 각종 관체를 삽입 설치하는 공정과;
상기 분할 파형 또는 요철판의 중앙 하면 상면에 고정 설치된 채움재 겸 보강재 공급호스 안내관을 통해 채움재 겸 보강재 공급호스를 삽입시켜 상기 각종 관체의 삽입에 의해 형성된 가설 터널 및 관로의 내주면과 각종 관체의 외주면 사이에 형성된 공간부에 채움재 겸 보강재를 주입시켜 채워 주는 공정;으로 이루어진 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법.
In the construction method for constructing an unattached temporary tunnel and a pipe line installed inside the excavation hole,
In the factory, using the corrugated plate or concave-convex plate to bend to form an arc or plate, and to produce a number of divided corrugated or concave-convex plate by welding the coupling plate perforated at a predetermined interval on the four sides, Installing a filler and reinforcing material supply hose guide tube having a plurality of filler and reinforcing material outlet holes at predetermined intervals on either or both of the upper and lower surfaces of the divided waveform or the uneven plate;
Drilling a hole in the ground of the site;
Assemble and install several uneven temporary tunnels and pipelines having a predetermined shape by connecting several divided waveforms or irregularities in the longitudinal and transverse directions by using coupling means in the excavation hole. Locating and assembling the divided corrugated or uneven plate provided with a filler and reinforcing material supply hose guide tube on one or both surfaces of the lower surface;
Filler and reinforcement supply hose is inserted through the filler and reinforcement supply hose guide tube fixedly installed on the central upper surface of the divided wave or uneven plate to inject and fill the filler and reinforcement into the space formed between the excavated hole and the temporary tunnel and the outer circumferential surface of the pipeline. Process;
Inserting and installing various pipe bodies into the temporary tunnel and the pipeline after curing of the filler and reinforcing material;
Inserting the filler and reinforcement supply hose through the filler and reinforcement supply hose guide tube fixedly installed on the upper surface of the center of the divided wave or uneven plate between the inner circumferential surface of the temporary tunnel and the pipe formed by the insertion of the various tubes and the outer peripheral surface of the various tubes Injecting a filler and reinforcing material in the space portion formed in the filling step; Construction method of the non-adhesive temporary tunnels and pipes using a divided waveform or uneven plate.
청구항 8에 있어서,
공장에서 수개의 파형판 또는 요철판을 제작할 때 또는 현장에서 가설 터널 및 관로를 조립하기에 앞서 일부 분할 파형 또는 요철판의 내면에는 한 쌍 또는 그 이상의 관체 받침 및 간격재 겸용 레일을 설치하여, 굴진공 내에서 결합수단들을 이용하여 수개의 분할 파형 또는 요철판들을 종방향 및 횡방향으로 연결시켜 소정형상을 갖는 비개착 가설 터널 및 관로로 조립 설치할 때, 가설 터널 및 관로의 최하단에 관체 받침 및 간격재 겸용 레일을 구비한 분할 파형 또는 요철판을 위치시켜 조립하는 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법.
The method according to claim 8,
When manufacturing several corrugated or uneven plates in the factory, or before assembling temporary tunnels and conduits in the field, install a pair or more rails and spacer rails on the inner surface of some split corrugated or uneven plates. When supporting several split wave or uneven plate in the vacuum and connecting them in the longitudinal direction and the lateral direction to assemble and install them into an unattached temporary tunnel and pipeline having a predetermined shape, the pipe support and spacing at the bottom of the temporary tunnel and pipeline A method of constructing an unattached temporary tunnel and pipe line using a divided wave or uneven plate, wherein the divided wave or uneven plate having a reusable rail is positioned and assembled.
청구항 8 또는 청구항 9에 있어서,
상기 가설 터널 및 관로의 내부로 각종 관체를 삽입 설치할 때, 상기 가설 터널 및 관로의 입구에 각종 관체를 위치시킨 후 최하단 분할 파형 또는 요철판의 내면에 설치되어 있는 관체 받침 및 간격재 겸용 레일을 따라 밀어넣어 가설 터널 및 관로의 내부로 각종 관체를 삽입 설치하는 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법.
The method according to claim 8 or 9,
When inserting various types of pipes into the temporary tunnels and pipes, various pipes are placed at the entrances of the temporary tunnels and pipes, and then along the pipe support and spacer double rails installed on the innermost surface of the lowest divided waveform or uneven plate. A construction method of an unattached temporary tunnel and a pipeline using a divided waveform or a concave-convex plate characterized by pushing and inserting various tubes into the interior of the temporary tunnel and a pipeline.
청구항 8에 있어서,
상기 가설 터널 및 관로에 각종 관체를 삽입 설치하기에 앞서, 상기 가설 터널 및 관로의 내부에 철근 또는 와이어 메쉬를 배근하는 공정을 더 실시하는 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법.
The method according to claim 8,
Prior to inserting and installing various pipe bodies into the temporary tunnel and the conduit, the non-adhesive temporary tunnel using the divided waveform or uneven plate further comprising the step of reinforcing the reinforcing wire or wire mesh inside the temporary tunnel and the conduit. And construction method of pipeline.
청구항 8에 있어서,
상기 굴진공의 내면과 가설 터널 및 관로의 외주면 사이에 형성된 공간부 또는 상기 가설 터널 및 관로의 내주면과 각종 관체의 외주면 사이에 형성된 공간부에 채움재 겸 보강재를 주입시켜 채우기에 앞서, 상기 가설 터널 및 관로의 내부 또는 각종 관체의 내부에 수개의 진동발생기를 설치한 다음, 상기한 공간부 내로 채움재 겸 보강재를 주입할 때 진동발생기를 작동시켜 주는 공정을 더 실시하는 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법.
The method according to claim 8,
Prior to filling by filling the filler and reinforcement into the space formed between the inner surface of the drilling hole and the outer circumferential surface of the temporary tunnel and the pipe or the outer circumferential surface of the various tunnels and the temporary tunnel and the pipe, the temporary tunnel and After installing several vibration generators in the pipeline or the inside of various pipe bodies, the step of operating the vibration generator when injecting the filler and reinforcement into the above-mentioned space portion further divided wave or uneven plate Construction method of unattached temporary tunnel and pipeline using
청구항 9에 있어서,
상기 채움재 겸 보강재는 시멘트 그라우트재, 모르타르, 수지 모르타르, 수지, 뿜칠재 및 현장 타설 콘크리트를 포함하는 것을 특징으로 하는 분할 파형 또는 요철판을 이용한 비개착 가설 터널 및 관로의 시공공법.














The method according to claim 9,
The filling material and reinforcing material is cement grout material, mortar, resin mortar, resin, spraying material, and the construction method of the non-adhesive temporary tunnels and pipelines using the uneven plate, characterized in that the cast-in-place concrete.














KR1020100109627A 2010-11-05 2010-11-05 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof KR101312668B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100109627A KR101312668B1 (en) 2010-11-05 2010-11-05 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100109627A KR101312668B1 (en) 2010-11-05 2010-11-05 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof

Publications (2)

Publication Number Publication Date
KR20120048152A true KR20120048152A (en) 2012-05-15
KR101312668B1 KR101312668B1 (en) 2013-09-27

Family

ID=46266552

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100109627A KR101312668B1 (en) 2010-11-05 2010-11-05 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof

Country Status (1)

Country Link
KR (1) KR101312668B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101312663B1 (en) * 2010-11-05 2013-09-27 삼대건설 주식회사 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof
KR101392995B1 (en) * 2013-09-04 2014-05-27 장해동 Construction method for retaining of earth
WO2021203625A1 (en) * 2020-04-09 2021-10-14 山东建筑大学 Composite supporting structure, and construction system and method
CN115750995A (en) * 2022-11-08 2023-03-07 山东省地质矿产勘查开发局八〇一水文地质工程地质大队(山东省地矿工程勘察院) Device and method for in-situ trenchless treatment of karst collapse risk points

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101022505B1 (en) * 2008-09-19 2011-03-16 코오롱건설주식회사 Filling method for void space of lining concrete of top end tunnel
KR101068626B1 (en) * 2009-01-28 2011-09-28 대지종건(주) Undrilled laying method for pipeline and tunnel using complex excavator
KR100973770B1 (en) 2010-05-27 2010-08-04 대지종건(주) Non-excavation type constructed tunnels and conduits using arc-shaped divided segments and its construccting methods thereof
KR101312663B1 (en) * 2010-11-05 2013-09-27 삼대건설 주식회사 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101312663B1 (en) * 2010-11-05 2013-09-27 삼대건설 주식회사 Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof
KR101392995B1 (en) * 2013-09-04 2014-05-27 장해동 Construction method for retaining of earth
WO2021203625A1 (en) * 2020-04-09 2021-10-14 山东建筑大学 Composite supporting structure, and construction system and method
US11739639B2 (en) 2020-04-09 2023-08-29 Shandong Jianzhu University Composite support structure, construction system, and method
CN115750995A (en) * 2022-11-08 2023-03-07 山东省地质矿产勘查开发局八〇一水文地质工程地质大队(山东省地矿工程勘察院) Device and method for in-situ trenchless treatment of karst collapse risk points
CN115750995B (en) * 2022-11-08 2023-07-07 山东省地质矿产勘查开发局八〇一水文地质工程地质大队(山东省地矿工程勘察院) Device and method for in-situ trenchless treatment of karst collapse risk points

Also Published As

Publication number Publication date
KR101312668B1 (en) 2013-09-27

Similar Documents

Publication Publication Date Title
KR100973770B1 (en) Non-excavation type constructed tunnels and conduits using arc-shaped divided segments and its construccting methods thereof
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
KR101022382B1 (en) Precast horizontality tubular roof and tunnel construction method using the same
KR101179778B1 (en) Method for constructing underground structure
KR101312663B1 (en) Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof
KR20090100867A (en) The method construction work and unit metal tubing constructing system for the road underground driveway
KR100995384B1 (en) Parallelly connected iron tube assembly and construction method for underground structure using the same
KR100538272B1 (en) The methods of trenchless underway construction using pre-cast assembly concrete box
JP2009150165A (en) Tunnel interior structure and its construction method
KR101312668B1 (en) Non-excavation type constructed tunnels and conduits using arc-shaped divided segments or rugged panels and its constructing method thereof
KR100834076B1 (en) None open cut tunnelling method and tunnel
CN111379577B (en) Detachable U-shaped primary support method combined with shed cover construction
JP4634363B2 (en) Multiple arc tunnel construction method
KR20110132909A (en) Underpass using precast concrete pile and method for constructing the same
KR101029311B1 (en) Non-excavation laying method for pipeline and tunnel using temporary composite pipe
KR20050020451A (en) Shield tunneling construction method and tunnel structure
JP5688244B2 (en) Construction method for underground structures
KR20090126131A (en) Loop structure using precast concrete block and construction method thereof
KR101068616B1 (en) Trenchless tunnel and pipelines using guiding draining type divided rugged panels and hheir constructing method for tunnel and pipelines using the same thereof
KR101275468B1 (en) The structure assembly for building a tunnel and building method thereof
KR20070088172A (en) Steel pipe roof assembly and the construction method for tunnel using thereof
KR20070079675A (en) Method for construction of tunnel
KR100928566B1 (en) Roof assembly and constructing method thereof
KR100926501B1 (en) Roof and shield tunneling construction method (rsm) and tunnel structure
KR101835828B1 (en) Complex Steel Pipe Structure for Underground Wall and the Construction Method Using the Same

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170323

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170922

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180928

Year of fee payment: 6

R401 Registration of restoration