KR20110105100A - Construction method for underground watertight wall - Google Patents

Construction method for underground watertight wall Download PDF

Info

Publication number
KR20110105100A
KR20110105100A KR1020100024163A KR20100024163A KR20110105100A KR 20110105100 A KR20110105100 A KR 20110105100A KR 1020100024163 A KR1020100024163 A KR 1020100024163A KR 20100024163 A KR20100024163 A KR 20100024163A KR 20110105100 A KR20110105100 A KR 20110105100A
Authority
KR
South Korea
Prior art keywords
casing
auxiliary
main casing
main
underground
Prior art date
Application number
KR1020100024163A
Other languages
Korean (ko)
Other versions
KR101153314B1 (en
Inventor
박정태
Original Assignee
홍지기술산업주식회사
박정태
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 홍지기술산업주식회사, 박정태 filed Critical 홍지기술산업주식회사
Priority to KR1020100024163A priority Critical patent/KR101153314B1/en
Publication of KR20110105100A publication Critical patent/KR20110105100A/en
Application granted granted Critical
Publication of KR101153314B1 publication Critical patent/KR101153314B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1607Shapes round, e.g. circle
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0021Mortar

Abstract

본 발명은 주케이싱(100) 및 상기 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)이 번갈아 설치되는 지중 차수벽 시공방법에 있어서, 상기 주케이싱(100)이 설치될 지반을 천공하여 천공 홀(101)을 형성하고 토사로 되메움하는 선천공 단계; 상기 천공 홀(101)의 사이 영역의 지반에 상기 보조케이싱(200)을 설치하는 보조케이싱 설치단계와; 상기 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 재천공하여 복수의 상기 주케이싱(100)을 설치하는 주케이싱 설치단계와; 상기 복수의 보조케이싱(200) 및 주케이싱(100)의 내부에 배근(300)을 설치하는 배근단계와; 상기 복수의 보조케이싱(200) 및 주케이싱(100) 내부에 콘크리트를 타설하는 콘크리트 타설단계와; 상기 콘크리트 타설단계에 의해 타설된 콘크리트의 양생 전, 상기 보조케이싱(200) 및 주케이싱(100)을 제거하는 케이싱 제거단계를; 포함하는 지중 차수벽 시공방법을 제시함으로써, 주열식 현장타설 말뚝공법의 장점인 충분한 강도를 확보할 수 있도록 하면서도, 높은 차수 효과를 얻을 수 있도록 한다.According to the present invention, the main casing 100 and the underground casing wall construction method in which a plurality of auxiliary casings 200 formed on both sides of the groove 210 for coupling with the main casing 100 are alternately installed, the main casing ( A perforation step of perforating the ground on which 100 is to be installed to form perforation holes 101 and backfilling with earth and sand; An auxiliary casing installation step of installing the auxiliary casing 200 on the ground between the drilling holes 101; A main casing installation step of installing a plurality of the main casings 100 by re-perforating the ground between the plurality of auxiliary casings 200 installed by the auxiliary casing installation step; A reinforcement step of installing the reinforcement 300 in the plurality of auxiliary casings 200 and the main casing 100; A concrete placing step of placing concrete in the plurality of auxiliary casings 200 and the main casing 100; A casing removal step of removing the auxiliary casing 200 and the main casing 100 before curing of the concrete poured by the concrete pouring step; By suggesting a method for constructing underground containment walls, it is possible to secure sufficient strength, which is an advantage of the cast-in-place casting pile method, and to obtain a high order effect.

Description

지중 차수벽 시공방법{CONSTRUCTION METHOD FOR UNDERGROUND WATERTIGHT WALL}Underground wall construction method {CONSTRUCTION METHOD FOR UNDERGROUND WATERTIGHT WALL}

본 발명은 토목분야에 관한 것으로서, 상세하게는, 흙막이 및 차수를 주된 목적으로 하는 지중 차수벽(遮水壁) 구조물의 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the field of civil engineering, and more particularly, to a construction method of underground water line wall structures whose main purpose is earthquakes and orders.

현재, 흙막이 및 차수를 목적으로 지중에 벽체를 형성하기 위한 공법으로서, C.I.P.(cast in place pile) 공법, S.C.W.(soil cement wall) 공법 등이 주로 사용되고 있다.At present, C.I.P. (cast in place pile) method, S.C.W. (soil cement wall) method and the like are mainly used as a method for forming walls in the ground for the purpose of soil barrier and order.

C.I.P.(cast in place pile) 공법은 일종의 주열식 현장타설 말뚝으로서, 소정 직경으로 천공 후 주입식 콘크리트에 의해 토류벽을 형성하는 공법을 말하며, 주열식 강성체를 형성하므로 강도가 우수하다는 장점을 가지나, 연결부에 누수현상발생가능성이 크다는 단점을 갖는다.The cast in place pile (CIP) method is a kind of cast-in-place casting pile, which is a method of forming a earth wall by injection-type concrete after drilling to a predetermined diameter, and has the advantage of excellent strength because it forms a cast-heated rigid body. It has the disadvantage that the possibility of water leakage is great.

S.C.W.(soil cement wall) 공법은 주열식 지중벽으로 계획심도까지 천공 후 주입제(soil cement)를 주입하여 벽체를 형성하고, H 파일을 응력재로 삽입하여 토류벽을 형성하는 공법을 말하며, 차수 효과가 우수한 반면, 강도가 떨어진다는 단점을 갖는다.The SCW (soil cement wall) method is a method of forming a wall by injecting oil cement after drilling to the planned depth as a main heat-based underground wall, and forming a earth wall by inserting an H file as a stress material. On the other hand, it has the disadvantage of low strength.

즉, 현장의 여건상 차수벽 구조물이 높은 강도를 요구하는 경우에는 상기 C.I.P. 공법과 같은 주열식 현장타설 말뚝공법이 적절하다 할 수 있는데, 이는 기본적으로 하나의 케이싱(casing)에 의해 하나의 현장타설 말뚝이 형성되는 방식을 취하므로, 각각 독립적으로 형성된 말뚝 사이로 흐르는 물을 차단하기가 곤란하다는 근본적인 문제점을 안고 있다.That is, when the order wall structure requires high strength due to the condition of the site, the C.I.P. A column-type cast-in-place pile method, such as a construction method, may be appropriate. This basically takes a way in which one cast-in-place pile is formed by one casing, so that water flowing between each independently formed pile is blocked. There is a fundamental problem that is difficult.

이러한 문제를 해소하기 위하여, 각 말뚝의 일부가 상호 겹치도록 시공하는 오버랩(overlap) 배열방법, 말뚝을 갈짓자 형상으로 배치하는 방법, 말뚝 사이에 소일 시멘트에 의한 벽체를 형성하거나 철근바구니 등에 의한 별도 구조물을 설치하는 방법 등이 고안되어 왔다.In order to solve such a problem, an overlap arrangement method in which parts of each pile are overlapped with each other, a method of arranging piles in a shape of a pile, a wall made of soil cement between piles, or a separate basket by reinforcing baskets, etc. A method of installing a structure has been devised.

그러나, 그 어느 것도 완벽한 차수 효과를 얻을 수는 없었으므로, 높은 강도 및 차수성이 요구되는 지중 흙막이 구조물에 적절히 적용될 수 있는 시공방법에 관한 고안이 절실히 요청되고 있는 실정이라 할 수 있다.However, since none of them can achieve a perfect order effect, it is an urgent need to devise a construction method that can be appropriately applied to underground earthquake structures requiring high strength and orderability.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 주열식 현장타설 말뚝공법의 장점인 충분한 강도를 확보할 수 있도록 하면서도, 높은 차수 효과를 얻을 수 있도록 하는 지중 차수벽의 시공방법을 제공함을 그 목적으로 한다.The present invention has been made to solve the above problems, and while providing a sufficient degree of strength, which is an advantage of the cast-in-place casting pile method, it provides a method of construction of the underground order wall to obtain a high order effect The purpose.

본 발명은 상술한 바와 같은 목적을 달성하기 위하여, 주케이싱(100) 및 상기 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)이 번갈아 설치되는 지중 차수벽 시공방법에 있어서, 상기 주케이싱(100)이 설치될 지반을 천공하여 천공 홀(101)을 형성하고 토사로 되메움하는 선천공 단계; 상기 천공 홀(101)의 사이 영역의 지반에 상기 보조케이싱(200)을 설치하는 보조케이싱 설치단계와; 상기 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 재천공하여 복수의 상기 주케이싱(100)을 설치하는 주케이싱 설치단계와; 상기 복수의 보조케이싱(200) 및 주케이싱(100)의 내부에 배근(300)을 설치하는 배근단계와; 상기 복수의 보조케이싱(200) 및 주케이싱(100) 내부에 콘크리트를 타설하는 콘크리트 타설단계와; 상기 콘크리트 타설단계에 의해 타설된 콘크리트의 양생 전, 상기 보조케이싱(200) 및 주케이싱(100)을 제거하는 케이싱 제거단계를; 포함하는 지중 차수벽 시공방법을 제시한다.In order to achieve the object as described above, the present invention, the main casing 100 and the ground casing alternately provided with a plurality of auxiliary casing 200 formed on both sides of the groove portion 210 for coupling with the main casing 100 In the order wall construction method, the perforated step of drilling the ground on which the main casing (100) is to be installed to form a punching hole (101) and backfills with earth and sand; An auxiliary casing installation step of installing the auxiliary casing 200 on the ground between the drilling holes 101; A main casing installation step of installing a plurality of the main casings 100 by re-perforating the ground between the plurality of auxiliary casings 200 installed by the auxiliary casing installation step; A reinforcement step of installing the reinforcement 300 in the plurality of auxiliary casings 200 and the main casing 100; A concrete placing step of placing concrete in the plurality of auxiliary casings 200 and the main casing 100; A casing removal step of removing the auxiliary casing 200 and the main casing 100 before curing of the concrete poured by the concrete pouring step; We present the method of construction of underground containment wall.

상기 주케이싱(100)의 설치를 위한 천공 홀(101)의 크기는 상기 보조케이싱(200)의 설치를 위한 천공 홀(102)의 크기에 비해 큰 것이 바람직하다.The size of the drilling hole 101 for the installation of the main casing 100 is preferably larger than the size of the drilling hole 102 for the installation of the auxiliary casing 200.

상기 주케이싱의 단면은 원형 구조이고, 상기 보조케이싱의 홈부의 단면은 만곡진 구조에 의해 구현될 수 있다.The cross section of the main casing is a circular structure, the cross section of the groove portion of the auxiliary casing may be implemented by a curved structure.

상기 보조케이싱 설치단계는 상기 주케이싱을 임시로 지반에 설치하는 주케이싱 임시설치단계와; 상기 주케이싱 내부에 상기 보조케이싱을 삽입하여 설치하는 보조케이싱 삽입단계와; 상기 보조케이싱 삽입단계에 의해 설치된 상기 보조케이싱은 지반에 설치된 상태를 유지하면서, 상기 주케이싱을 임시로 제거하는 주케이싱 임시제거단계를; 포함하는 것이 바람직하다.The auxiliary casing installation step includes a main casing temporary installation step of temporarily installing the main casing on the ground; An auxiliary casing insertion step of inserting and installing the auxiliary casing into the main casing; A main casing temporary removal step of temporarily removing the main casing while maintaining the state of the auxiliary casing installed by the auxiliary casing insertion step; It is preferable to include.

상기 보조케이싱 삽입단계는 상기 주케이싱의 내면과 상기 보조케이싱 외면 사이에 스페이서를 삽입함으로써, 상기 보조케이싱을 상기 주케이싱의 중앙부에 위치시키는 단계를 더 포함하는 것이 바람직하다.The auxiliary casing inserting step may further include positioning the auxiliary casing in the center of the main casing by inserting a spacer between the inner surface of the main casing and the outer surface of the auxiliary casing.

상기 보조케이싱 삽입단계는 상기 보조케이싱 삽입단계 이후, 상기 주케이싱과 상기 보조케이싱의 사이를 충전재의 되메움에 의해 충전하는 보조케이싱 측부 충전단계를 더 포함하는 것이 바람직하다.The auxiliary casing inserting step may further include an auxiliary casing side filling step of filling the gap between the main casing and the auxiliary casing by backfilling a filler after the auxiliary casing inserting step.

상기 보조케이싱 측부 충전단계에서 사용되는 상기 충전재는 모래 또는 저강도 몰탈인 것이 바람직하다.The filler used in the auxiliary casing side filling step is preferably sand or low strength mortar.

상기 콘크리트 타설단계에서 콘크리트의 타설 순서는 상기 복수의 보조케이싱 및 주케이싱 중 일단에 설치된 것으로부터 순차적으로 이루어지고, 상기 케이싱 제거단계에서 상기 보조케이싱 및 주케이싱의 제거 순서는 상기 콘크리트 타설단계에서 콘크리트의 타설 순서에 따라 순차적으로 이루어지는 것이 바람직하다.In the concrete pouring step, the concrete pouring order is sequentially made from one end of the plurality of auxiliary casing and the main casing, the removal order of the auxiliary casing and the main casing in the casing removal step is concrete in the concrete pouring step It is preferable to be made sequentially according to the pouring order of.

상기 보조케이싱 설치단계, 주케이싱 설치단계, 배근단계, 콘크리트 타설단계 및 케이싱 제거단계 이후, 상기 단계들에 따른 1차 작업에 의해 형성된 1차 지중 차수벽에 인접하여, 상기 단계들과 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 배근단계, 2차 콘크리트 타설단계 및 2차 케이싱 제거단계에 의한 2차 작업이 수행됨으로써, 2차 지중 차수벽을 연속적으로 형성하는 것이 바람직하다.After the auxiliary casing installation step, the main casing installation step, the reinforcement step, the concrete placing step and the casing removal step, adjacent to the primary underground order wall formed by the first operation according to the steps, according to the same configuration as the steps It is preferable to continuously form the secondary underground water order wall by performing the secondary work by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement step, the secondary concrete placing step, and the secondary casing removal step. Do.

상기 보조케이싱 설치단계 및 주케이싱 설치단계는 상기 1차 작업의 마감에 의한 종단부를 상기 보조케이싱이 설치된 상태에서 종료하는 종단부 보조케이싱 설치단계를 포함하고, 상기 배근단계, 콘크리트 타설단계 및 케이싱 제거단계는 상기 종단부 보조케이싱 내부에 배근 및 콘크리트 타설작업을 수행한 후, 상기 종단부 보조케이싱을 제거하는 1차 지중 차수벽의 종단부 형성단계를 포함하며, 상기 2차 보조케이싱 설치단계는 상기 1차 지중 차수벽의 종단부 측부에 상기 2차 주케이싱 설치단계에 의한 상기 주케이싱이 설치될 간격을 두고, 상기 복수의 보조케이싱 중 최초의 2차 보조케이싱을 설치하는 최초의 2차 보조케이싱 설치단계를 포함하고, 상기 2차 주케이싱 설치단계는 상기 1차 지중 차수벽의 종단부와 상기 최초의 2차 보조케이싱 사이에 상기 복수의 주케이싱 중 최초의 2차 주케이싱을 설치하는 최초의 2차 주케이싱 설치단계를 포함하는 것이 바람직하다.The auxiliary casing installation step and the main casing installation step includes a terminal auxiliary casing installation step of terminating the end by the end of the primary work in the state in which the auxiliary casing is installed, the reinforcement step, concrete pouring step and casing removal The step includes the step of forming the end of the primary underground order wall for removing the end auxiliary casing after performing the reinforcement and concrete pouring work in the end auxiliary casing, the second auxiliary casing installation step is the 1 First secondary auxiliary casing installation step of installing the first secondary auxiliary casing among the plurality of auxiliary casings at intervals at which the main casing by the second main casing installation step is installed on the side of the end portion of the vehicle underground order wall. Wherein the secondary main casing installation step includes an end portion of the primary underground order wall and the first secondary auxiliary casing. And the inclusion of the first secondary main casing installation step of installing the first secondary main casing of the plurality of the main casing is preferred.

상기 종단부 보조케이싱 설치단계는 상기 주케이싱을 임시로 지반에 설치하는 주케이싱 임시설치단계와; 상기 주케이싱 내부에 상기 종단부 보조케이싱을 삽입하여 설치하는 종단부 보조케이싱 삽입단계와; 상기 주케이싱과 상기 종단부 보조케이싱의 사이를 충전재의 되메움에 의해 충전하는 종단부 보조케이싱 측부 충전단계와; 상기 종단부 보조케이싱 삽입단계에 의해 설치된 상기 종단부 보조케이싱은 지반에 설치된 상태를 유지하면서, 상기 주케이싱을 임시로 제거하는 주케이싱 임시제거단계를; 포함하고, 상기 1차 지중 차수벽의 종단부 형성단계는 상기 종단부 보조케이싱 내부에 배근 및 콘크리트 타설작업을 수행한 후, 상기 종단부 보조케이싱을 제거함으로써, 상기 1차 지중 차수벽의 종단부와 상기 충전재가 접촉한 상태로 마감하는 것이 바람직하다.The terminal auxiliary casing installation step includes a main casing temporary installation step of temporarily installing the main casing on the ground; An end auxiliary casing insertion step of inserting and installing the end auxiliary casing inside the main casing; A terminal secondary casing side filling step of filling the gap between the main casing and the terminal auxiliary casing by backfilling a filler; A main casing temporary removal step of temporarily removing the main casing while the end auxiliary casing installed by the end auxiliary casing inserting step is installed on the ground; And the end portion forming step of the primary underground order wall includes removing the terminal auxiliary casing after performing reinforcement and concrete placing work in the terminal auxiliary casing. It is desirable to finish with the filler in contact.

상기 종단부 보조케이싱 측부 충전단계에서 사용되는 상기 충전재는 모래 또는 저강도 몰탈인 것이 바람직하다.The filler used in the terminal auxiliary casing side filling step is preferably sand or low strength mortar.

본 발명은 주열식 현장타설 말뚝공법의 장점인 충분한 강도를 확보할 수 있도록 하면서도, 높은 차수 효과를 얻을 수 있도록 하는 지중 차수벽의 시공방법을 제공한다.The present invention provides a method of construction of underground order walls to ensure a sufficient degree of strength, while ensuring sufficient strength, which is an advantage of the cast-in-place casting method.

도 1 이하는 본 발명의 실시예를 도시한 것으로서,
도 1은 선천공 작업에 관한 평면도.
도 2는 보조케이싱의 일실시예의 사시도.
도 3은 보조케이싱이 설치된 상태의 평면도.
도 4는 보조케이싱, 주케이싱 설치 및 배근작업이 완료된 상태의 평면도.
도 5는 콘크리트 타설 및 케이싱 제거작업이 완료된 상태의 평면도.
도 6은 주케이싱 내부에 보조케이싱이 삽입된 상태의 평면도.
도 7은 설치된 보조케이싱의 측부가 충전재에 의해 되메움된 상태의 평면도.
도 8은 2차 지중 차수벽의 형성을 위한 보조케이싱이 설치된 상태의 평면도.
도 9는 2차 지중 차수벽의 형성을 위한 보조케이싱, 주케이싱 설치 및 배근작업이 완료된 상태의 평면도.
도 10은 2차 지중 차수벽의 형성을 위한 콘크리트 타설 및 케이싱 제거작업이 완료된 상태의 평면도.
Figure 1 below shows an embodiment of the present invention,
1 is a plan view of a perforation work.
2 is a perspective view of one embodiment of an auxiliary casing;
3 is a plan view of the auxiliary casing is installed.
4 is a plan view of the auxiliary casing, the main casing installation and reinforcement work is completed.
5 is a plan view of the concrete pouring and casing removal work is completed.
6 is a plan view of the auxiliary casing is inserted into the main casing.
7 is a plan view of the side portion of the installed auxiliary casing backfilled with a filler.
8 is a plan view of a state in which an auxiliary casing for forming a secondary underground order wall is installed;
Figure 9 is a plan view of the secondary casing, the main casing installation and reinforcement work for the formation of the secondary underground water order wall is completed.
FIG. 10 is a plan view of a state in which concrete placing and casing removal work for forming secondary underground order walls are completed; FIG.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 이하에 도시된 바와 같이, 본 발명은 기본적으로, 주케이싱(100) 및 그 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)이 번갈아 설치되는 지중 차수벽 시공방법에 관한 것으로서, 다음과 같은 과정에 의해 구성된다.As shown below in Figure 1, the present invention basically, the main casing 100 and the plurality of auxiliary casings 200 formed on both sides of the groove portion 210 for coupling with the main casing 100 alternately installed The underground order wall construction method is to be constructed by the following process.

우선, 주케이싱(100)이 설치될 지반을 천공하여 천공 홀(101)을 형성하고 토사로 되메움하는 선천공 및 되메움 작업을 실시한다(도 1).First, perforating the ground on which the main casing 100 is to be installed to form a punching hole 101, and performs a pre-punching and backfilling work to fill the soil back (Fig. 1).

그 천공 홀(101)의 사이 영역의 지반에 보조케이싱(200)을 설치한다(도 2,3).The auxiliary casing 200 is provided in the ground between the drilling holes 101 (Figs. 2 and 3).

위 보조케이싱 설치단계에 의해 설치된 복수의 보조케이싱(200) 사이의 지반을 재천공하여 복수의 주케이싱(100)을 설치하고, 그 복수의 보조케이싱(200) 및 주케이싱(100)의 내부에 배근(300)을 설치한 후, 콘크리트를 타설한다(도 4).Re-punch the ground between the plurality of auxiliary casings 200 installed by the above-described auxiliary casing installation step to install a plurality of main casing 100, the plurality of auxiliary casing 200 and the inside of the main casing 100 After installing the reinforcement 300, the concrete is poured (Fig. 4).

타설된 콘크리트의 양생 전, 보조케이싱(200) 및 주케이싱(100)을 제거함으로써 차수벽 구조물(A)을 형성한다(도 5).Prior to curing of the poured concrete, the order wall structure A is formed by removing the auxiliary casing 200 and the main casing 100 (FIG. 5).

즉, 차수벽 구조물(A)의 거푸집 역할을 담당하는 보조케이싱(200) 및 주케이싱(100)을 상호 맞물리는 구조에 의해 설치하고, 이에 콘크리트를 타설한 후, 그 콘크리트의 양생 전 케이싱(100,200)을 제거하면, 양생이 진행되면서 보조케이싱(200) 내부에 타설된 콘크리트와 주케이싱(100) 내부에 타설된 콘크리트가 그 접합부(도 5의 점선)에서 상호 견고한 결합을 이루게 된다.That is, the auxiliary casing 200 and the main casing 100, which serve as formwork of the order wall structure A, are installed by mutually interlocking structures, and after the concrete is poured therein, casings before curing of the concrete (100,200). When removing, as the curing proceeds, the concrete placed inside the auxiliary casing 200 and the concrete placed inside the main casing 100 form a rigid bond with each other at their joints (dotted line in FIG. 5).

상술한 선천공 및 되메움 작업을 실시하지 않고, 보조케이싱(200)을 먼저 설치하고 주케이싱(100)의 설치를 위한 천공작업을 실시하는 경우, 천공장비와 보조케이싱(200)의 접촉에 의해 보조케이싱(200)의 파손이 발생할 수 있는데, 선천공 및 되메움 작업(양질의 토사에 의한)을 먼저 실시하는 경우 천공장비가 용이하게 재천공 작업을 수행할 수 있는 바, 보조케이싱(200)의 파손 우려를 방지할 수 있다는 효과가 있다.When the auxiliary casing 200 is installed first and the drilling operation for the installation of the main casing 100 is performed without performing the above-described drilling and backfilling operations, the contacting of the drilling equipment and the auxiliary casing 200 is performed. Breakage of the auxiliary casing 200 may occur, when the perforation and backfilling (by good quality earth and sand) are performed first, the perforation equipment can easily perform the re-punching operation, and the auxiliary casing 200. There is an effect that can prevent the risk of damage.

주케이싱(100)의 설치를 위한 천공 홀(101)의 크기가 보조케이싱(200)의 설치를 위한 천공 홀(102)의 크기에 비해 크도록 하는 경우, 상술한 효과를 더욱 안정적으로 얻을 수 있다(도 1,3).When the size of the drilling hole 101 for the installation of the main casing 100 is larger than the size of the drilling hole 102 for the installation of the auxiliary casing 200, the above-described effects can be obtained more stably. (Figures 1,3).

따라서, 본 발명에 의한 공법은 기본적으로 C.I.P. 공법과 같은 주열식 현장타설 말뚝공법의 구성을 취함에 따라 우수한 강도를 얻을 수 있도록 하면서도, 말뚝 사이로 흐르는 물을 완전히 차단할 수 있으므로, 높은 강도 및 우수한 차수 효과를 동시에 만족할 수 있는 차수벽 구조물을 얻을 수 있는 것이다.Therefore, the process according to the present invention is basically C.I.P. It is possible to obtain a high-strength wall structure that satisfies high strength and excellent ordering effect, since it is possible to completely block the water flowing between the piles while providing excellent strength by taking the construction of the column-type cast-in-place pile method such as the construction method. will be.

보조케이싱(200)에 주케이싱(100)과의 결합을 위한 홈부(210)가 형성됨으로써, 주케이싱(100) 및 보조케이싱(200)이 상기와 같은 요철 결합구조를 이룰 수 있는 구성은 다양한 실시예에 의해 구현될 수 있다.By forming the groove portion 210 for coupling with the main casing 100 in the auxiliary casing 200, the main casing 100 and the auxiliary casing 200 can form a concave-convex coupling structure as described above various implementations It may be implemented by example.

도 1 이하는 그 대표적인 실시예로서, 주케이싱(100)의 단면이 원형 구조에 의해 형성되고, 보조케이싱(200)의 홈부(210)의 단면이 만곡진 구조에 의해 구현된 경우를 도시한 것이고, 이하에서는 본 실시예의 케이싱(100,200)의 구조에 따른 시공방법의 실시예를 설명한다.Figure 1 is a representative embodiment, the cross-section of the main casing 100 is formed by a circular structure, the cross-sectional view of the groove portion 210 of the auxiliary casing 200 is shown by a curved structure Hereinafter, an embodiment of the construction method according to the structure of the casing (100,200) of the present embodiment.

보조케이싱(200)은 그 자체를 지반에 타입하거나, 천공 후 삽입하는 방식을 취할 수도 있으나, 오거와 같은 기존의 굴착장비를 그대로 활용하기 위해서는, 도 6에 도시된 바와 같이, 일단 주케이싱(100)을 임시로 지반에 설치하고, 그 주케이싱(100) 내부에 보조케이싱(200)을 삽입하여 설치한 후, 설치된 보조케이싱(200)은 지반에 설치된 상태를 유지하면서, 주케이싱(100)을 임시로 제거하는 방식을 취하는 것이 바람직하다.The auxiliary casing 200 may itself be typed into the ground or inserted after drilling, but in order to utilize the existing drilling equipment such as an auger as it is, as shown in FIG. ) Is temporarily installed on the ground, and after the auxiliary casing 200 is inserted into the main casing 100 to be installed, the installed auxiliary casing 200 maintains the state of the main casing 100 while being installed on the ground. It is desirable to take a temporary removal method.

주케이싱(100) 내부에 보조케이싱(200)을 삽입하는 작업 및 주케이싱(100)의 임시제거작업에 있어서, 보조케이싱(200)을 주케이싱(100)의 중앙부에 위치시키기 위해서는, 도 6에 도시된 바와 같이, 주케이싱(100)의 내면과 보조케이싱(200) 외면 사이에 스페이서(220)를 삽입하는 것이 바람직하다.In the operation of inserting the auxiliary casing 200 into the main casing 100 and the temporary removal of the main casing 100, the auxiliary casing 200 is located in the center of the main casing 100 in FIG. 6. As shown, it is preferable to insert the spacer 220 between the inner surface of the main casing 100 and the outer surface of the auxiliary casing 200.

도 7에 도시된 바와 같이, 보조케이싱(200) 삽입단계 이후, 주케이싱(100)과 보조케이싱(200)의 사이를 충전재(230)의 되메움에 의해 충전하는 경우, 주케이싱(100)의 설치를 위하여, 보조케이싱(200) 사이의 영역을 천공하는 작업을 보다 원활하게 할 수 있다는 장점이 있다.As shown in FIG. 7, after the insertion of the auxiliary casing 200, the main casing 100 and the auxiliary casing 200 are filled by the backfill of the filling material 230. For installation, there is an advantage that the operation of drilling the area between the auxiliary casing 200 can be more smoothly.

이를 위해서는 모래 또는 저강도 몰탈과 같이 천공작업이 용이한 충전재(230)를 사용하는 것이 바람직하다.For this purpose, it is preferable to use a filler 230 that is easy to punch, such as sand or low strength mortar.

실제에 있어서, 복수의 케이싱(100,200)에 대한 콘크리트 타설 및 그 케이싱(100,200)의 제거작업은 한번의 작업에 의해 수행되기 어려우므로, 일부 케이싱(100,200)으로부터 일정한 방향을 향하여 순차적으로 이루어지게 될 것인데, 이 경우, 콘크리트 타설작업은 복수의 보조케이싱(200) 및 주케이싱(100) 중 일단에 설치된 것으로부터 순차적으로 이루어지고, 보조케이싱(200) 및 주케이싱(100)의 제거 순서는 상기 콘크리트 타설단계에서 콘크리트의 타설 순서에 따라 순차적으로 이루어지도록 하는 것이 바람직하다.In practice, concrete casing for a plurality of casing (100,200) and the removal of the casing (100,200) is difficult to be performed by one operation, so it will be made sequentially from some casing (100,200) toward a certain direction In this case, the concrete pouring work is sequentially made from one of the plurality of auxiliary casings 200 and the main casing 100, and the removal order of the auxiliary casings 200 and the main casing 100 is the concrete pouring. It is preferable to be made sequentially according to the pouring order of the concrete in the step.

본 발명에 의한 시공방법에 있어서, 일체로 형성된 차수벽 구조물을 얻기 위해서는, 케이싱(100,200)에 타설된 콘크리트의 양생 전 그 케이싱(100,200)을 제거하는 것이 중요하기 때문이다.In the construction method according to the present invention, it is important to remove the casings 100 and 200 before curing of the concrete placed on the casings 100 and 200 in order to obtain the integrally formed wall structure.

차수벽 구조물의 규모가 큼에 따라 하루에 작업을 완료할 수 없는 경우, 전날에 작업한 부분과 그 다음날 작업할 부분 사이의 결합부에서 누수가 발생할 우려가 있다.If the work wall cannot be completed in one day due to the large size of the order wall structure, there is a risk of water leakage at the joint between the part worked on the previous day and the part to be worked on the next day.

이를 방지하기 위해서는 도 8에 도시된 바와 같이, 상기 단계들에 따른 1차 작업에 의해 형성된 1차 지중 차수벽(A)에 인접하여, 상기 단계들과 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 배근단계, 2차 콘크리트 타설단계 및 2차 케이싱 제거단계에 의한 2차 작업이 수행됨으로써, 2차 지중 차수벽(B)을 연속적으로 형성하는 것이 필요하다.To prevent this, as shown in FIG. 8, the secondary sub-casing installation step 2 according to the same configuration as the above steps is adjacent to the primary underground order wall A formed by the primary operation according to the steps. By performing the secondary work by the primary main casing installation step, the secondary reinforcement step, the secondary concrete placing step and the secondary casing removal step, it is necessary to continuously form the secondary underground order wall (B).

보다 구체적으로는, 도 7에 도시된 바와 같이, 상기 1차 작업의 마감에 의한 종단부를 보조케이싱(200a)이 설치된 상태에서 종료하고, 그 종단부 보조케이싱(200a) 내부에 배근 및 콘크리트 타설작업을 수행한 후, 종단부 보조케이싱(200a)을 제거함으로써, 도 8의 1차 지중 차수벽(A) 종단부와 같은 구조가 형성되도록 한다.More specifically, as shown in Figure 7, the end by the end of the primary work is terminated in the state in which the auxiliary casing 200a is installed, the reinforcement and concrete placement work inside the terminal auxiliary casing 200a After performing the step, by removing the terminal auxiliary casing (200a), a structure such as the first underground order wall (A) end of Figure 8 is formed.

다음날의 작업시, 1차 지중 차수벽(A)의 종단부 측부에 주케이싱(100)이 설치될 간격을 두고, 복수의 보조케이싱(200) 중 최초의 2차 보조케이싱(200b)을 설치한다.During the work of the next day, the first secondary auxiliary casing 200b among the plurality of auxiliary casings 200 is installed at intervals at which the main casing 100 is to be installed at the end side side of the primary underground order wall A. FIG.

이후, 도 9에 도시된 바와 같이, 1차 지중 차수벽(A)의 종단부와 최초의 2차 보조케이싱(200b) 사이에 복수의 주케이싱(100) 중 최초의 2차 주케이싱(100b)을 설치하고, 나머지 케이싱(100,200)은 상기 1차 지중 차수벽(A)의 경우와 동일한 방식에 의해 설치하며, 상술한 바와 같은 방식으로 배근, 콘크리트 타설, 케이싱(100,200) 제거작업을 진행함으로써, 2차 지중 차수벽(B)을 얻을 수 있다.Thereafter, as shown in FIG. 9, the first secondary main casing 100b of the plurality of main casings 100b is disposed between the end portion of the primary underground order wall A and the first secondary auxiliary casing 200b. The rest of the casing (100,200) is installed in the same manner as in the case of the primary underground water order wall (A), and by removing the reinforcement, concrete pouring, casing (100,200) in the manner described above, the secondary Underground order wall B can be obtained.

이와 같이 시공된 1차 지중 차수벽(A) 및 2차 지중 차수벽(B)은 도 10에 도시된 바와 같이, 전체적으로 연속적인 구조를 형성하므로, 수일에 걸쳐 작업이 진행됨에 불구하고 우수한 차수 효과를 얻을 수 있다는 장점이 있다.The primary underground order wall (A) and the secondary underground order wall (B) constructed as described above form a continuous structure as a whole, as shown in FIG. 10, so that an excellent order effect is obtained even though the work proceeds for several days. There is an advantage that it can.

도 8에 도시된 바와 같이, 1차 지중 차수벽(A)의 종단부와 충전재(230)가 접촉한 상태로 마감된 구성을 취하는 경우, 2차 지중 차수벽(B)의 형성을 위한 주케이싱(100) 중 최초의 2차 주케이싱(100b)의 설치를 위한 천공작업이 용이하다는 장점이 있으며, 이를 위해서는 1차 지중 차수벽(A)의 종단부 보조케이싱(200a)의 설치 및 콘크리트 타설 작업을 다음과 같이 진행하는 것이 필요하다.As shown in FIG. 8, when the terminal portion of the primary underground order wall A and the filler 230 are in contact with each other, the main casing 100 for forming the secondary underground order wall B is formed. ) Has the advantage of easy drilling for the installation of the first secondary main casing (100b), and for this purpose, the installation of the secondary auxiliary casing (200a) of the primary underground water order wall (A) and concrete pouring work as follows. It is necessary to proceed together.

주케이싱(100)을 임시로 지반에 설치하고, 그 주케이싱(100) 내부에 종단부 보조케이싱(200a)을 삽입하여 설치한 후, 주케이싱(100)과 종단부 보조케이싱(200a)의 사이를 충전재(230)의 되메움에 의해 충전한다.After the main casing 100 is temporarily installed on the ground, and the terminal auxiliary casing 200a is inserted into the main casing 100 and then installed, the main casing 100 is interposed between the main casing 100 and the terminal auxiliary casing 200a. Is filled by the backfill of the filler 230.

설치된 종단부 보조케이싱(200a)은 지반에 설치된 상태를 유지하면서, 주케이싱(100)을 임시로 제거하고, 종단부 보조케이싱(200a) 내부에 배근 및 콘크리트 타설작업을 수행한 후, 종단부 보조케이싱(200a)을 제거함으로써, 1차 지중 차수벽의 종단부와 충전재(230)가 접촉한 상태로 마감된 구성을 얻을 수 있다.The installed end auxiliary casing 200a temporarily removes the main casing 100 while maintaining the state of being installed on the ground, and performs the reinforcement and concrete pouring work in the end auxiliary casing 200a. By removing the casing 200a, it is possible to obtain a configuration in which the terminal portion of the primary underground order wall and the filler 230 are in contact with each other.

이 경우의 충전재(230)도 모래 또는 저강도 몰탈과 같이 천공작업이 용이한 것을 사용하는 것이 바람직하다.In this case, the filler 230 is also preferably used for easy drilling, such as sand or low strength mortar.

1차 지중 차수벽(A)과 2차 지중 차수벽(B)의 연결부의 차수를 보다 확실히 하기 위해서는 다음과 같은 구성을 취하는 것이 효과적이다.It is effective to take the following constitution to more secure the order of the connection portion between the primary underground order wall A and the secondary underground order wall B.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has been described only with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above It will be said that both the technical idea and the technical idea which together with the base are included in the scope of the present invention.

A : 1차 지중 차수벽 B : 2차 지중 차수벽
100 : 주케이싱 101 : 천공 홀
100b : 최초의 2차 주케이싱 200 : 보조케이싱
200a : 종단부 보조케이싱 200b : 최초의 2차 보조케이싱
210 : 홈부 220 : 스페이서
230 : 충전재 240 : 돌부
300 : 배근
A: Primary Underground Wall B: Second Underground Wall
100: main casing 101: punched hole
100b: first secondary main casing 200: auxiliary casing
200a: end secondary casing 200b: first secondary auxiliary casing
210: groove portion 220: spacer
230: filler 240: protrusion
300: reinforcement

Claims (12)

주케이싱(100) 및 상기 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)이 번갈아 설치되는 지중 차수벽 시공방법에 있어서,
상기 주케이싱(100)이 설치될 지반을 천공하여 천공 홀(101)을 형성하고 토사로 되메움하는 선천공 단계;
상기 천공 홀(101)의 사이 영역의 지반에 상기 보조케이싱(200)을 설치하는 보조케이싱 설치단계와;
상기 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 재천공하여 복수의 상기 주케이싱(100)을 설치하는 주케이싱 설치단계와;
상기 복수의 보조케이싱(200) 및 주케이싱(100)의 내부에 배근(300)을 설치하는 배근단계와;
상기 복수의 보조케이싱(200) 및 주케이싱(100) 내부에 콘크리트를 타설하는 콘크리트 타설단계와;
상기 콘크리트 타설단계에 의해 타설된 콘크리트의 양생 전, 상기 보조케이싱(200) 및 주케이싱(100)을 제거하는 케이싱 제거단계를;
포함하는 지중 차수벽 시공방법.
In the underground order wall construction method in which a plurality of auxiliary casings 200 formed on both sides of the main casing 100 and the groove portion 210 for coupling with the main casing 100 are alternately installed.
A perforation step of perforating the ground on which the main casing 100 is to be installed to form perforation holes 101 and backfilling with earth and sand;
An auxiliary casing installation step of installing the auxiliary casing 200 on the ground between the drilling holes 101;
A main casing installation step of installing a plurality of the main casings 100 by re-perforating the ground between the plurality of auxiliary casings 200 installed by the auxiliary casing installation step;
A reinforcement step of installing the reinforcement 300 in the plurality of auxiliary casings 200 and the main casing 100;
A concrete placing step of placing concrete in the plurality of auxiliary casings 200 and the main casing 100;
A casing removal step of removing the auxiliary casing 200 and the main casing 100 before curing of the concrete poured by the concrete pouring step;
Underground wall construction method including.
제1항에 있어서,
상기 주케이싱(100)의 설치를 위한 천공 홀(101)의 크기는 상기 보조케이싱(200)의 설치를 위한 천공 홀(102)의 크기에 비해 큰 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
Underground wall construction method characterized in that the size of the drilling hole 101 for the installation of the main casing (100) is larger than the size of the drilling hole (102) for the installation of the auxiliary casing (200).
제1항에 있어서,
상기 주케이싱(100)의 단면은 원형 구조이고, 상기 보조케이싱(200)의 홈부(210)의 단면은 만곡진 구조인 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
The cross section of the main casing (100) is a circular structure, the cross section of the groove portion 210 of the auxiliary casing (200) is an underground order wall construction method, characterized in that the curved structure.
제1항에 있어서,
상기 보조케이싱 설치단계는
상기 주케이싱(100)을 임시로 지반에 설치하는 주케이싱 임시설치단계와;
상기 주케이싱(100) 내부에 상기 보조케이싱(200)을 삽입하여 설치하는 보조케이싱 삽입단계와;
상기 보조케이싱 삽입단계에 의해 설치된 상기 보조케이싱(200)은 지반에 설치된 상태를 유지하면서, 상기 주케이싱(100)을 임시로 제거하는 주케이싱 임시제거단계를;
포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
The auxiliary casing installation step
A main casing temporary installation step of temporarily installing the main casing 100 on the ground;
An auxiliary casing insertion step of inserting and installing the auxiliary casing 200 into the main casing 100;
The main casing 200 installed by the auxiliary casing insertion step includes a main casing temporary removal step of temporarily removing the main casing 100 while maintaining the state installed in the ground;
Underground order wall construction method comprising a.
제4항에 있어서,
상기 보조케이싱 삽입단계는
상기 주케이싱(100)의 내면과 상기 보조케이싱(200) 외면 사이에 스페이서(220)를 삽입함으로써, 상기 보조케이싱(200)을 상기 주케이싱(100)의 중앙부에 위치시키는 단계를 더 포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 4, wherein
The auxiliary casing insertion step
And inserting the spacer 220 between an inner surface of the main casing 100 and an outer surface of the auxiliary casing 200, thereby positioning the auxiliary casing 200 in the center of the main casing 100. Underground order wall construction method characterized in that.
제4항에 있어서,
상기 보조케이싱 삽입단계는
상기 보조케이싱 삽입단계 이후, 상기 주케이싱(100)과 상기 보조케이싱(200)의 사이를 충전재(230)의 되메움에 의해 충전하는 보조케이싱 측부 충전단계를 더 포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 4, wherein
The auxiliary casing insertion step
After the sub-casing insertion step, the underground casing wall construction further comprises a secondary casing side filling step of filling the back of the filling material 230 between the main casing 100 and the auxiliary casing 200. Way.
제6항에 있어서,
상기 보조케이싱 측부 충전단계에서 사용되는 상기 충전재(230)는 모래 또는 저강도 몰탈인 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 6,
The filler 230 used in the secondary casing side filling step is a ground order wall construction method, characterized in that the sand or low strength mortar.
제1항에 있어서,
상기 콘크리트 타설단계에서 콘크리트의 타설 순서는
상기 복수의 보조케이싱(200) 및 주케이싱(100) 중 일단에 설치된 것으로부터 순차적으로 이루어지고,
상기 케이싱 제거단계에서 상기 보조케이싱(200) 및 주케이싱(100)의 제거 순서는
상기 콘크리트 타설단계에서 콘크리트의 타설 순서에 따라 순차적으로 이루어지는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
In the concrete pouring step, the concrete pouring order
It is sequentially made from one of the plurality of auxiliary casing 200 and the main casing 100 is installed,
The removal order of the auxiliary casing 200 and the main casing 100 in the casing removal step is
Underground order wall construction method characterized in that made in sequence according to the order of placing concrete in the concrete placing step.
제1항에 있어서,
상기 보조케이싱 설치단계, 주케이싱 설치단계, 배근단계, 콘크리트 타설단계 및 케이싱 제거단계 이후,
상기 단계들에 따른 1차 작업에 의해 형성된 1차 지중 차수벽(A)에 인접하여, 상기 단계들과 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 배근단계, 2차 콘크리트 타설단계 및 2차 케이싱 제거단계에 의한 2차 작업이 수행됨으로써, 2차 지중 차수벽(B)을 연속적으로 형성하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 1,
After the auxiliary casing installation step, main casing installation step, reinforcement step, concrete pouring step and casing removal step,
Adjacent to the primary underground order wall A formed by the primary operations according to the above steps, the secondary secondary casing installation step, the secondary main casing installation step, the secondary reinforcement step, 2 The secondary undercarriage wall construction method, characterized in that the secondary undercarriage wall (B) is continuously formed by performing the secondary work by the secondary concrete pouring step and the secondary casing removal step.
제9항에 있어서,
상기 보조케이싱 설치단계 및 주케이싱 설치단계는
상기 1차 작업의 마감에 의한 종단부를 상기 보조케이싱(200a)이 설치된 상태에서 종료하는 종단부 보조케이싱 설치단계를 포함하고,
상기 배근단계, 콘크리트 타설단계 및 케이싱 제거단계는
상기 종단부 보조케이싱(200a) 내부에 배근 및 콘크리트 타설작업을 수행한 후, 상기 종단부 보조케이싱(200a)을 제거하는 1차 지중 차수벽의 종단부 형성단계를 포함하며,
상기 2차 보조케이싱 설치단계는
상기 1차 지중 차수벽(A)의 종단부 측부에 상기 2차 주케이싱 설치단계에 의한 상기 주케이싱(100)이 설치될 간격을 두고, 상기 복수의 보조케이싱(200) 중 최초의 2차 보조케이싱(200b)을 설치하는 최초의 2차 보조케이싱 설치단계를 포함하고,
상기 2차 주케이싱 설치단계는
상기 1차 지중 차수벽(A)의 종단부와 상기 최초의 2차 보조케이싱(200b) 사이에 상기 복수의 주케이싱(100) 중 최초의 2차 주케이싱(100b)을 설치하는 최초의 2차 주케이싱 설치단계를 포함하는 것을 특징으로 하는 지중 차수벽 시공방법.
10. The method of claim 9,
The auxiliary casing installation step and the main casing installation step
And a terminal auxiliary casing installation step of terminating the terminal by the end of the primary work in the state in which the auxiliary casing 200a is installed.
The reinforcement step, concrete pouring step and casing removal step
After performing the reinforcement and concrete pouring work inside the end auxiliary casing (200a), and the step of forming the end of the primary underground order wall to remove the end auxiliary casing (200a),
The secondary auxiliary casing installation step
The first secondary auxiliary casing among the plurality of auxiliary casings 200 is spaced apart from each other at the terminal side of the primary underground order wall A by the second main casing installation step. The first secondary casing installation step of installing (200b),
The secondary main casing installation step
First secondary main to install the first secondary main casing 100b among the plurality of main casings 100b between the end of the primary underground order wall A and the first secondary auxiliary casing 200b. Underground order wall construction method comprising the step of installing the casing.
제10항에 있어서,
상기 종단부 보조케이싱 설치단계는
상기 주케이싱(100)을 임시로 지반에 설치하는 주케이싱 임시설치단계와;
상기 주케이싱(100) 내부에 상기 종단부 보조케이싱(200a)을 삽입하여 설치하는 종단부 보조케이싱 삽입단계와;
상기 주케이싱(100)과 상기 종단부 보조케이싱(200a)의 사이를 충전재(230)의 되메움에 의해 충전하는 종단부 보조케이싱 측부 충전단계와;
상기 종단부 보조케이싱 삽입단계에 의해 설치된 상기 종단부 보조케이싱(200a)은 지반에 설치된 상태를 유지하면서, 상기 주케이싱(100)을 임시로 제거하는 주케이싱 임시제거단계를; 포함하고,
상기 1차 지중 차수벽의 종단부 형성단계는
상기 종단부 보조케이싱(200a) 내부에 배근 및 콘크리트 타설작업을 수행한 후, 상기 종단부 보조케이싱(200a)을 제거함으로써, 상기 1차 지중 차수벽의 종단부와 상기 충전재(230)가 접촉한 상태로 마감하는 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 10,
The terminal auxiliary casing installation step is
A main casing temporary installation step of temporarily installing the main casing 100 on the ground;
An end auxiliary casing insertion step of inserting and installing the end auxiliary casing 200a in the main casing 100;
A terminal secondary casing side filling step of filling the back casing of the filler material 230 between the main casing 100 and the terminal auxiliary casing 200a;
A main casing temporary removal step of temporarily removing the main casing 100 while the terminal auxiliary casing 200a installed by the end auxiliary casing insertion step maintains the state of being installed on the ground; Including,
The end portion forming step of the primary underground order wall
After performing the reinforcement and concrete pouring work in the terminal auxiliary casing (200a), by removing the terminal auxiliary casing (200a), the end portion of the primary underground order wall and the filler 230 contacted Underground wall construction method characterized in that the finish.
제11항에 있어서,
상기 종단부 보조케이싱 측부 충전단계에서 사용되는 상기 충전재(230)는 모래 또는 저강도 몰탈인 것을 특징으로 하는 지중 차수벽 시공방법.
The method of claim 11,
The filling material 230 used in the terminal auxiliary casing side filling step is a ground order wall construction method, characterized in that the sand or low strength mortar.
KR1020100024163A 2010-03-18 2010-03-18 Construction method for underground watertight wall KR101153314B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100024163A KR101153314B1 (en) 2010-03-18 2010-03-18 Construction method for underground watertight wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100024163A KR101153314B1 (en) 2010-03-18 2010-03-18 Construction method for underground watertight wall

Publications (2)

Publication Number Publication Date
KR20110105100A true KR20110105100A (en) 2011-09-26
KR101153314B1 KR101153314B1 (en) 2012-06-07

Family

ID=44955555

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100024163A KR101153314B1 (en) 2010-03-18 2010-03-18 Construction method for underground watertight wall

Country Status (1)

Country Link
KR (1) KR101153314B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119218A (en) * 2019-12-23 2020-05-08 王君舫 Construction method for processing leading hole joint of ultra-deep plain diaphragm wall

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101777176B1 (en) 2016-07-25 2017-09-11 차수익 Construction method of cast-in-placed-pile using steel pipes having different shapes to each other
KR102560785B1 (en) * 2021-11-29 2023-07-26 백우열 A casing for drilling the ground and a method of constructing an underground continuous wall using the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4268192A (en) 1978-09-11 1981-05-19 Raymond International Builders, Inc. Concrete wall construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111119218A (en) * 2019-12-23 2020-05-08 王君舫 Construction method for processing leading hole joint of ultra-deep plain diaphragm wall

Also Published As

Publication number Publication date
KR101153314B1 (en) 2012-06-07

Similar Documents

Publication Publication Date Title
KR100752397B1 (en) Construction method for underground watertight wall and subsidiary casing used in the same
KR100910576B1 (en) Embed anchor and construction method of composite basement wall using the same
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
KR100862977B1 (en) Precast concrete file and method for constructing thereof
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
KR101842208B1 (en) Construction method of retaining wall
KR101840226B1 (en) The guide holes of the form for soil auger dredges
KR101153314B1 (en) Construction method for underground watertight wall
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
KR20110070188A (en) Construction method for underground watertight wall
WO2009005244A2 (en) Method for burying hume pipes and support block used in the method
KR101153313B1 (en) Subsidiary casing and construction method for underground watertight wall using the same
KR101567742B1 (en) PHC pile and construction method of underground structure using the same
KR101392995B1 (en) Construction method for retaining of earth
JP2013053465A (en) Construction method for underground structure, underground structure, and precast block
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
JP5367537B2 (en) Construction method and structure of steel pipe sheet pile
KR101219450B1 (en) Building structure using underground watertight wall and construction method thereof
KR101073975B1 (en) Joint structure and construction method for underground watertight wall using the same
JP5288356B2 (en) How to connect existing piping and new piping in the manhole
KR101047257B1 (en) Construction method of earth wall using composite sheet pile
KR101219452B1 (en) Concavo-convex member for wall structure and construction method for wall used in the same
KR101285987B1 (en) Improved Compound Roof Tunnel Method
KR101335578B1 (en) Molding for constructing perpendicular hall and construction method for perpendicular hall using it
KR101279618B1 (en) Construction method of underground structure

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150529

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee