KR101219452B1 - Concavo-convex member for wall structure and construction method for wall used in the same - Google Patents

Concavo-convex member for wall structure and construction method for wall used in the same Download PDF

Info

Publication number
KR101219452B1
KR101219452B1 KR1020100093975A KR20100093975A KR101219452B1 KR 101219452 B1 KR101219452 B1 KR 101219452B1 KR 1020100093975 A KR1020100093975 A KR 1020100093975A KR 20100093975 A KR20100093975 A KR 20100093975A KR 101219452 B1 KR101219452 B1 KR 101219452B1
Authority
KR
South Korea
Prior art keywords
primary
continuous wall
concave
casing
auxiliary
Prior art date
Application number
KR1020100093975A
Other languages
Korean (ko)
Other versions
KR20120032371A (en
Inventor
노삼영
김승훈
김갑수
조용원
Original Assignee
홍지기술산업주식회사
동부건설 주식회사
현대산업개발 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 홍지기술산업주식회사, 동부건설 주식회사, 현대산업개발 주식회사 filed Critical 홍지기술산업주식회사
Priority to KR1020100093975A priority Critical patent/KR101219452B1/en
Publication of KR20120032371A publication Critical patent/KR20120032371A/en
Application granted granted Critical
Publication of KR101219452B1 publication Critical patent/KR101219452B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/14Sealing joints between adjacent sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 건설, 토목분야에 관한 것으로서, 상세하게는, 복수의 연속벽이 상호 인접되도록 연속 형성되는 연속벽구조물용 요철형성부재 및 이를 이용한 벽구조물 시공방법에 관한 것이다. 특히 본 발명은 상호 인접되어 연속 형성되는 복수의 연속벽(A,B) 사이에 설치되며 상기 상호 인접되는 연속벽(A,B) 의 종단면에 대응되게 형성되고, 상호 인접되는 두 연속벽(A,B) 중 후 시공되는 연속벽(B) 과 인접되는 면에 제1요철부(310)가 형성된 연속벽구조물용 요철형성부재(300) 및 이를 이용한 벽구조물 시공방법을 제시한다.The present invention relates to the field of construction and civil engineering, and more particularly, to a concave-convex forming member for a continuous wall structure which is continuously formed such that a plurality of continuous walls are adjacent to each other, and a method of constructing a wall structure using the same. In particular, the present invention is provided between a plurality of continuous walls (A, B) that are formed adjacent to each other continuously formed to correspond to the longitudinal section of the adjacent continuous walls (A, B), two continuous walls (A) adjacent to each other , B) proposes a concave-convex forming member 300 for a contiguous wall structure having a first concave-convex portion 310 formed on a surface adjacent to the contiguous continuous wall (B), and a wall construction method using the same.

Description

연속벽구조물용 요철형성부재 및 이를 이용한 벽구조물 시공방법{CONCAVO-CONVEX MEMBER FOR WALL STRUCTURE AND CONSTRUCTION METHOD FOR WALL USED IN THE SAME}Concave-convex forming member for continuous wall structure and construction method of wall structure using same {CONCAVO-CONVEX MEMBER FOR WALL STRUCTURE AND CONSTRUCTION METHOD FOR WALL USED IN THE SAME}

본 발명은 건설, 토목분야에 관한 것으로서, 상세하게는, 복수의 연속벽이 상호 인접되도록 연속 형성되는 연속벽구조물용 요철형성부재 및 이를 이용한 벽구조물 시공방법에 관한 것이다.The present invention relates to the field of construction and civil engineering, and more particularly, to a concave-convex forming member for a continuous wall structure which is continuously formed such that a plurality of continuous walls are adjacent to each other, and a method of constructing a wall structure using the same.

건축물의 구조벽, 내력벽은 물론, 토목분야에서도 흙막이 및 차수를 목적으로 현장타설에 의해 지중에 벽체, 벽구조물을 형성하기 위한 공법이 많이 사용되고 있다.In the civil engineering field, as well as structural walls, bearing walls of buildings, construction methods for forming walls and wall structures in the ground by site casting for the purpose of earthquake and order are widely used.

이와 같은 건설, 토목분야의 벽구조물은 그 규모가 매우 크기 때문에 한번의 작업에 의해 형성하기 어렵다. 따라서, 실질적으로는 1차 작업에 의해 벽구조물의 일부를 형성하고, 1차 형성 부분에 인접하여 2차 작업을 수행하여 벽구조물의 또 다른 일부를 연속적으로 형성하는 등 복수 작업에 걸쳐 공사를 진행한다.Such construction and civil engineering wall structures are very large and difficult to form in one operation. Therefore, the construction is carried out over a plurality of operations, such as forming a part of the wall structure substantially by the primary work, and performing a second operation adjacent to the primary forming part to continuously form another part of the wall structure. do.

그런데, 복수 작업에 걸쳐 벽구조물을 형성함에 따라서, 인접경계부분 사이로 흐르는 물을 완벽하게 차단하기 어려우며, 인접경계부분에서 상대적으로 구조적 안정성이 취약한 문제점이 있다.However, as the wall structure is formed over a plurality of operations, it is difficult to completely block the water flowing between adjacent boundary portions, and there is a problem in that structural stability is weak in the adjacent boundary portions.

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 복수의 연속벽 간 결합력이 매우 우수하며 높은 차수효과를 얻을 수 있는 연속벽구조물용 요철형성부재 및 이를 이용한 벽구조물 시공방법을 제공함을 그 목적으로 한다.The present invention has been made to solve the above problems, and provides a concave-convex forming member for a continuous wall structure and a method of constructing a wall structure using the same, which is excellent in the coupling force between a plurality of continuous walls and can obtain a high degree of effect. The purpose.

상기한 과제를 해결하기 위해 본 발명은 연속 형성되는 복수의 연속벽(A,B)이 상호 요철부에 의해 연접될 수 있도록, 상호 인접되는 두 연속벽(A,B) 사이에 개재되며 적어도 어느 한쪽 면에 요철부(310,320)가 형성된 연속벽구조물용 요철형성부재(300)를 제시한다. In order to solve the above problems, the present invention is interposed between two continuous walls (A, B) adjacent to each other, so that a plurality of continuous walls (A, B) to be continuously formed can be connected by the mutual uneven portion and at least any The concave-convex forming member 300 for the continuous wall structure in which the concave-convex portions 310 and 320 are formed on one surface is provided.

상기 상호 인접되는 두 연속벽 (A,B)중 후 시공되는 연속벽(B)에 인접되는 면에 제1요철부(310)가 형성되며, 제1요철부(310)는 복수의 제1홈(312)으로 형성될 수 있다.The first concave-convex portion 310 is formed on a surface adjacent to the continuous wall B, which is constructed later, among the two adjacent contiguous walls A and B, and the first concave-convex portion 310 includes a plurality of first grooves. 312.

상기 상호 인접되는 두 연속벽 (A,B)중 선 시공되는 연속벽(A)에 인접되는 면에도 제2요철부(320)가 형성될 수 있다.The second concave-convex portion 320 may be formed on a surface adjacent to the continuous wall A, which is a line construction among the two continuous walls A and B adjacent to each other.

상기 제2요철부(320)는 상기 선 시공되는 연속벽(A)을 향해 돌출 형성된 돌출부(322)로 형성될 수 있다.The second uneven portion 320 may be formed as a protrusion 322 protruding toward the continuous wall A to be constructed.

상기 돌출부(322)는 상기 상호 인접되는 두 연속벽(A,B) 중 후 시공되는 연속벽(B) 측에 제2홈(324)이 형성될 수 있도록 돌출 형성될 수 있다.The protrusion 322 may protrude so that the second groove 324 may be formed on the side of the continuous wall B which is later constructed among the two adjacent continuous walls A and B.

상기 돌출부(322)의 선 시공되는 연속벽 측 인접면 중 상기 제2홈(324)의 둘레면과 대응되는 부분 및, 상기 제2홈(324)의 개구부 반대쪽면인 바닥면에는 수팽창 지수재(330)가 도포될 수 있다.A water-expandable index member is provided on a portion of the adjacent wall side adjacent surface of the protruding portion 322 corresponding to the circumferential surface of the second groove 324 and a bottom surface opposite to the opening of the second groove 324. 330 may be applied.

또한 상기한 과제를 해결하기 위해 본 발명은 상기의 요철형성부재(300)에 의한 요철부를 갖는 1차 연속벽(A)을, 현장타설에 의해 형성하는 1차 연속벽형성단계; 상기 1차 연속벽(A)의 요철부에 인접하여 2차 연속벽(B)을 형성하는 2차 연속벽형성단계;를 포함하는 것을 특징으로 하는 차수벽구조물 시공방법을 제시한다.In addition, in order to solve the above problems, the present invention is a primary continuous wall forming step of forming a primary continuous wall (A) having an uneven portion by the above-mentioned convex-concave forming member 300 by spot casting; And a secondary continuous wall forming step of forming a secondary continuous wall (B) adjacent to the uneven portion of the primary continuous wall (A).

상기 1차 연속벽형성단계는, 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)을 지반에 설치하되, 그 복수의 보조케이싱(200) 사이에 상기 주케이싱(100)이 설치될 간격을 두고 설치하는 1차 보조케이싱 설치단계; 상기 요철형성부재(300)를 상기 복수의 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에 인접되도록 설치하는 요철형성부재설치단계; 상기 1차 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 천공하여 복수의 상기 주케이싱(100)을 설치하는 1차 주케이싱 설치단계; 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 콘크리트를 타설하고 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)를 제거하여 상기 요철형성부재(300)가 설치된 1차 연속벽(A)를 형성하는 1차 콘크리트작업단계;를 포함할 수 있다.In the first continuous wall forming step, a plurality of auxiliary casings 200 formed on both sides of the groove 210 for coupling with the main casing 100 are installed on the ground, and the plurality of auxiliary casings 200 are disposed between the plurality of auxiliary casings 200. A primary auxiliary casing installation step of installing the main casing 100 at intervals to be installed; An uneven forming member installing step of installing the uneven forming member 300 to be adjacent to the secondary continuous wall B side end casing 200a of the plurality of auxiliary casings 200; A primary main casing installation step of installing a plurality of the main casings 100 by drilling the ground between the plurality of auxiliary casings 200 installed by the primary auxiliary casing installation step; Placing concrete in the plurality of primary auxiliary casings 200 and primary main casings 100 and removing the plurality of primary auxiliary casings 200 and primary main casings 100 to remove the irregularities forming member. It may include; primary concrete work step to form a primary continuous wall (A) 300 is installed.

상기 2차 연속벽형성단계는 상기 1차 연속벽형성단계와 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체 설치단계, 2차 콘크리트작업단계에 의해 이루어지며; 상기 2차 연속벽(B)의 1차 연속벽(A) 반대쪽 종단부에 3차 차수벽이 연속 형성되는 경우에는, 상기 3차 차수벽과의 사이에 상기 요철형성부재(300)가 설치되도록 상기 1차 연속벽형성단계와 동일한 구성에 따른 요철형성부재설치단계가 포함될 수 있다.The secondary continuous wall forming step is made by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement installation step, the secondary concrete work step according to the same configuration as the primary continuous wall formation step ; In the case where tertiary order walls are continuously formed at the end portion opposite to the primary continuous wall A of the secondary continuous wall B, the unevenness forming member 300 is installed between the third order walls. The uneven forming member installation step according to the same configuration as the next continuous wall forming step may be included.

또는 상기 2차 연속벽형성단계는 상기 1차 연속벽형성단계와 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체 설치단계, 2차 콘크리트작업단계에 의해 이루어지며; 상기 복수의 2차 주케이싱(100) 중 1차 연속벽(A)에 인접 설치된 선단부 2차 주케이싱(100)을 임시 제거하여 상기 1차 연속벽(A)에 설치된 요철형성부재(300)를 제거한 후, 상기 임시 제거한 선단부 2차 주케이싱(100)을 재설치하는 요철형성부재 제거단계를 더 포함할 수 있다.Alternatively, the secondary continuous wall forming step is performed by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement installation step, and the secondary concrete work step according to the same configuration as the primary continuous wall formation step. ; Temporarily removing the tip secondary main casing 100 installed adjacent to the primary continuous wall A among the plurality of secondary main casings 100 to remove the unevenness forming member 300 installed on the primary continuous wall A. FIG. After removal, the step of removing the irregularities forming member for reinstalling the temporary main secondary casing 100 removed.

한편, 상기 1차 연속벽형성단계는 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)을 임시로 설치한 주케이싱(100)의 내부에 설치한 후 상기 임시 설치한 주케이싱(100)을 제거하는 1차 보조케이싱 설치단계; 상기 1차 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 천공하여, 복수의 상기 주케이싱(100)을 상기 보조케이싱(200)에 인접하도록 설치하는 1차 주케이싱 설치단계; 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 보강체(400)를 설치하는 1차 보강체 설치단계; 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 콘크리트를 타설하고 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)를 제거하여 1차 연속벽(A)를 형성하는 1차 콘크리트작업단계;를 포함하며, On the other hand, the first continuous wall forming step is provided in the interior of the main casing 100 temporarily installed a plurality of auxiliary casings 200 formed on both sides of the groove portion 210 for coupling with the main casing 100. After the first secondary casing installation step of removing the temporarily installed main casing (100); Primary primary casing installation for drilling the ground between the plurality of secondary casings 200 installed by the primary secondary casing installation step, and installing the plurality of main casings 100 adjacent to the secondary casings 200. step; A primary reinforcement installation step of installing a reinforcement member 400 in the plurality of primary auxiliary casings 200 and the primary main casing 100; Placing concrete in the plurality of primary auxiliary casings 200 and primary main casings 100 and removing the plurality of primary auxiliary casings 200 and primary main casings 100 to form a primary continuous wall. Includes (A) the first concrete work step;

상기 복수의 1차 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에는 상기 요철형성부재(300)가 인접 설치된 후 상기 요철형성부재(300) 측 천공 영역이 충전재(230)에 의해 되메워지며, 상기 요철형성부재(300)는 상기 1차 콘크리트작업단계에서 상기 종단부 보조케이싱(200a)과 함께 제거되며, 상기 1차 연속벽(A)에 상기 요철형성부재(300)에 의한 요철부가 형성될 수 있다.Of the plurality of primary auxiliary casings 200, the secondary continuous wall (B) side end portion auxiliary casing (200a) after the concave-convex forming member 300 is installed adjacent to the perforated region of the concave-convex forming member 300 is a filler It is backfilled by 230, the concave-convex forming member 300 is removed together with the end auxiliary casing 200a in the primary concrete working step, the concave-convex forming member on the primary continuous wall (A) Concave-convex portion by 300 may be formed.

또한 상기한 과제를 해결하기 위해 본 발명은 요철형성부재(300)에 의한 요철부를 갖는 1차 연속벽(A)을, 현장타설에 의해 형성하는 1차 연속벽형성단계; In addition, the present invention to solve the above problems is the primary continuous wall forming step of forming a primary continuous wall (A) having an uneven portion by the uneven forming member 300 by in-situ casting;

상기 1차 연속벽(A)의 요철부에 인접하여 2차 연속벽(B)을 형성하는 2차 연속벽형성단계;A secondary continuous wall forming step of forming a secondary continuous wall (B) adjacent to the uneven portion of the primary continuous wall (A);

를 포함하는 것을 특징으로 하는 탑다운공법의 지중연속벽 시공방법을 제시한다.It proposes the underground continuous wall construction method of the top-down method comprising a.

본 발명은 1차 연속벽과 2차 연속벽이 요철형성부재에 의한 요철부에 의해 보다 견고하게 연속적으로 형성될 수 있으며, 차수효과가 매우 우수하다.In the present invention, the first continuous wall and the second continuous wall can be formed more continuously by the uneven portion by the uneven portion, and the order effect is excellent.

도 1 내지 도 5는 본 발명에 따른 연속벽구조물에 관한 것으로서,
도 1은 제1실시예에 따른 연속벽구조물의 평면도.
도 2는 제1실시예에 따른 연속벽구조물의 평단면도.
도 3은 제1실시예에 따른 연속벽구조물의 요철형성부재 사시도.
도 4는 제2실시예에 따른 연속벽구조물의 평단면도.
도 5는 제2실시예에 따른 연속벽구조물의 요철형성부재 사시도.
도 6 이하는 본 발명에 따른 연속벽구조물의 시공방법에 관한 것으로서,
도 6은 주케이싱의 일실시예의 사시도.
도 7은 보조케이싱의 일실시예의 사시도.
도 8은 1차 연속벽의 보조케이싱 설치상태의 평면도.
도 9는 1차 연속벽의 보조케이싱, 주케이싱, 보강체 설치상태 평면도.
도 10은 1차 연속벽이 형성된 상태 평면도.
도 11은 주케이싱 내부에 보조케이싱이 삽입된 상태의 평면도.
도 12는 설치된 보조케이싱의 측부가 충전재에 의해 되메움된 상태의 평면도.
도 13은 2차 연속벽의 보조케이싱 설치상태 평면도.
도 14는 2차 연속벽의 보조케이싱, 주케이싱, 보강체 설치상태 평면도.
도 15 및 도 16은 종단면 보조케이싱 및 요철형성부재의 실시 예들을 도시한 평면도.
1 to 5 relates to a continuous wall structure according to the present invention,
1 is a plan view of a continuous wall structure according to the first embodiment.
2 is a plan sectional view of a continuous wall structure according to the first embodiment;
Figure 3 is a perspective view of the concave-convex forming member of the continuous wall structure according to the first embodiment.
4 is a plan sectional view of the continuous wall structure according to the second embodiment;
Figure 5 is a perspective view of the concave-convex forming member of the continuous wall structure according to the second embodiment.
6 and below relates to the construction method of the continuous wall structure according to the present invention,
6 is a perspective view of one embodiment of a main casing.
7 is a perspective view of one embodiment of the auxiliary casing.
8 is a plan view of the auxiliary casing installation state of the primary continuous wall.
9 is a plan view of the auxiliary casing, the main casing, and the reinforcement of the primary continuous wall.
10 is a plan view of a state in which a primary continuous wall is formed.
11 is a plan view of the auxiliary casing is inserted into the main casing.
12 is a plan view of a state where the side of the installed auxiliary casing is backfilled with a filler;
13 is a plan view of the auxiliary casing installation state of the secondary continuous wall;
14 is a plan view of the auxiliary casing, the main casing, the reinforcement of the secondary continuous wall;
15 and 16 are plan views showing embodiments of the longitudinal cross-section auxiliary casing and the uneven member.

이하, 첨부된 도 1 이하를 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 5에 도시된 바와 같이, 본 발명은 상호 인접되어 연속 형성되는 복수의 연속벽(A,B)을 형성함에 있어서, 상호 인접되는 연속벽(A,B)간의 결합력을 높이고 완벽한 차수효과를 기대할 수 있도록 요철부(310,320)가 형성된 요철형성부재(300)를 제시한다. As shown in Figures 1 to 5, in the present invention to form a plurality of continuous walls (A, B) that are formed adjacent to each other continuously, the coupling force between the adjacent continuous walls (A, B) to increase and perfect order The concave-convex forming member 300 having the concave-convex portions 310 and 320 is provided to expect the effect.

따라서, 본 발명은 요철형성부재(300)에 의한 요철결합에 의해 복수의 연속벽(A,B)의 결합력이 증대됨으로써 복수의 연속벽(A,B)이 전체적으로 연속적으로 거동할 수 있다는 효과를 얻을 수 있다.Therefore, the present invention has the effect that the coupling force of the plurality of continuous walls (A, B) by the uneven coupling by the uneven forming member 300 increases the overall continuous behavior of the plurality of continuous walls (A, B). You can get it.

또한, 본 발명은 요철형성부재(300)에 의한 요철결합에 의해 복수의 연속벽(A,B)의 결합력이 증대됨으로써 우수한 차수 효과를 얻을 수 있다.In addition, the present invention can obtain an excellent ordering effect by increasing the bonding force of the plurality of continuous walls (A, B) by the uneven coupling by the uneven forming member 300.

또한, 본 발명은 복수의 연속벽(A,B) 사이에 강성체인 요철형성부재(300)가 매립되는 경우, 복수의 연속벽(A,B)의 인접경계부분이 보강됨으로써 구조적 안정성이 보다 증대될 수 있다는 효과를 얻을 수 있다.In addition, in the present invention, when the concave-convex forming member 300, which is a rigid body, is embedded between the plurality of continuous walls A and B, structural stability is further increased by reinforcing adjacent boundary portions of the plurality of continuous walls A and B. Can be achieved.

이하, 설명의 편의를 위해 상호 인접되는 두 연속벽 중 선 시공되는 연속벽을 '1차 연속벽(A)'이라 하고, 후 시공되는 연속벽을 '2차 연속벽(B)'이라 한다. Hereinafter, for convenience of description, the continuous wall that is pre-constructed among two adjacent walls that are adjacent to each other will be referred to as a 'primary continuous wall A', and the subsequent continuous wall that will be constructed will be referred to as a 'secondary continuous wall B'.

요철형성부재(300)는 1차, 2차 연속벽(A,B)들에 각각 밀착될 수 있도록 1차, 2차 연속벽(A,B)의 종단면에 대응되게 형성될 수 있다. The concave-convex forming member 300 may be formed to correspond to the end surfaces of the primary and secondary continuous walls A and B so as to be in close contact with the primary and secondary continuous walls A and B, respectively.

요철형성부재(300)의 요철부(310, 320)는 1차, 2차 연속벽(A,B)에 인접되는 면 중 어느 한쪽 면에만 형성되거나, 양쪽 면에 모두 형성될 수 있다. 이하, 설명의 편의를 위해 요철형성부재(300)의 요철부(310, 320) 중 후 시공되는 2차 연속벽(B)에 인접되는 면에 형성된 요철부(310)를 제1요철부(310)라 하며, 그 나머지를 제2요철부(320)라 한다.Concave-convex portions 310 and 320 of the concave-convex forming member 300 may be formed on only one of the surfaces adjacent to the primary and secondary continuous walls A and B, or both surfaces. Hereinafter, for convenience of description, the uneven parts 310 formed on the surface of the uneven parts 310 and 320 of the uneven parts 310 and 320 adjacent to the secondary continuous wall B which are constructed later are first uneven parts 310. ), And the rest of the second uneven portion 320 is called.

요철형성부재(300)의 요철부(310, 320)는 다양한 형상으로 형성될 수 있다.Concave-convex portions 310 and 320 of the concave-convex forming member 300 may be formed in various shapes.

예컨대, 요철형성부재(300)의 제1요철부(310)는 후술하는 바와 같이 1차 연속벽(A) 시공 후 2차 연속벽(B) 시공을 위해 요철형성부재(300) 인접 지반이 천공될 때 간섭되지 않도록, 돌기보다는 복수의 제1홈(312)으로 형성될 수 있다. 복수의 제1홈(312)은 도시된 바와 같이 포인트(point)처럼 형성될 수 있으며, 도시하지 않았지만 선형, 메쉬형 등 여러가지로 형성될 수 있음은 물론이다. For example, the first concave-convex portion 310 of the concave-convex forming member 300 is perforated in the ground adjacent to the concave-convex forming member 300 for the construction of the second contiguous wall (B) after the construction of the first contiguous wall (A). The first groove 312 may be formed in a plurality of first grooves 312 rather than protrusions so that they do not interfere when they are made. The plurality of first grooves 312 may be formed as a point as shown, and although not shown, may be formed in various ways such as linear and mesh shapes.

나아가, 요철형성부재(300)는 1차 연속벽(A)에 인접되는 면에도 제2요철부(320)가 형성됨으로써, 1차 연속벽(A)에 보다 견고하게 일체로 설치될 수 있다. 제2요철부(320)는 도시된 바와 같이 하나의 돌출부(322)로 형성될 수 있으며, 이에 한정되지 않고 복수의 돌출부(322)로 형성될 수도 있고 복수의 홈으로 형성될 수도 있다.Furthermore, since the second uneven portion 320 is formed on the surface adjacent to the primary continuous wall A, the unevenness forming member 300 may be more firmly installed on the primary continuous wall A. As shown in FIG. 2, the second uneven portion 320 may be formed of one protrusion 322, but is not limited thereto, and may be formed of a plurality of protrusions 322 or a plurality of grooves.

돌출부(322)로 형성된 제2요철부(320)는 여러가지 형상으로 형성될 수 있으며, 특히 도시된 바와 같이 요철형성부재(300)가 2차 연속벽(B) 측에 제2홈(324)을 가질 수 있도록 형성될 수 있다. 즉 돌출부(322)로 형성된 제2요철부(320)는 요철형성부재(300)가 1차 연속벽(A) 측을 향해 눌려진 형상으로 형성될 수 있다.The second uneven portion 320 formed of the protrusion 322 may be formed in various shapes, and as shown in the drawing, the uneven forming member 300 may form the second groove 324 on the side of the second continuous wall B. It can be formed to have. That is, the second concave-convex portion 320 formed by the protrusion 322 may be formed in a shape in which the concave-convex forming member 300 is pressed toward the primary continuous wall A side.

이에 더 나아가서, 요철형성부재(300)는 수팽창 지수재(330)가 도포될 수 있는데, 특히 돌출부(322)로 형성된 제2요철부(320)는 1차 연속벽(A) 측 인접면 중 상기의 홈의 둘레면과 대응되는 부분 및, 상기 홈의 개구부 반대쪽면인 바닥면에 각각 수팽창 지수재(330)가 도포될 수 있다. In addition, the concave-convex forming member 300 may be coated with a water-expandable index member 330. In particular, the second concave-convex portion 320 formed of the protruding portion 322 is one of the adjacent surfaces of the primary continuous wall A side. The water-expandable index member 330 may be applied to a portion corresponding to the circumferential surface of the groove and a bottom surface opposite to the opening of the groove, respectively.

따라서, 1차 연속벽(A)과 요철형성부재(300) 사이 또는 2차 연속벽(B)과 요철형성부재(300) 사이로 물이 흐르더라도 이 물에 의해 수팽창 지수재(330)가 팽창하여 1차 연속벽(A)과 요철형성부재(300) 사이 틈새, 2차 연속벽(B)과 요철형성부재(300) 사이 틈새를 메워주기 때문에, 보다 완벽한 차수효과를 기대할 수 있다. 특히 요철형성부재(300)의 일부분에만 수팽창 지수재(330)를 도포하여도 효과적으로 차수 목적을 달성할 수 있다.Accordingly, even if water flows between the first continuous wall A and the uneven member 300, or between the second continuous wall B and the uneven member 300, the water-expanding index member 330 expands due to the water. By filling the gap between the primary continuous wall (A) and the concave-convex forming member 300, the gap between the secondary continuous wall (B) and the concave-convex forming member 300, a more perfect order effect can be expected. In particular, even if the water-expandable index member 330 is applied only to a portion of the unevenness forming member 300 can effectively achieve the degree of order.

요철형성부재(300)는 도트(dot) 형상, 라인(line) 형상 등 다양한 형상으로 형성될 수 있으며, 특히 제거형인 경우 제거가 용이하도록 천공을 따라 수직한 라인 형상으로 형성될 수 있다.The concave-convex forming member 300 may be formed in various shapes such as a dot shape, a line shape, and the like. In particular, in the case of the removal type, the concave-convex forming member 300 may be formed in a vertical line shape along the perforation to facilitate removal.

이와 같은 요철형성부재(300)는 합성수지 등 다양한 소재로 형성될 수 있으며, 특히 강성이 우수한 철강과 같은 금속재로 형성되는 것이 보다 바람직하다할 수 있다.The uneven forming member 300 may be formed of various materials such as synthetic resin, it may be more preferably formed of a metal material such as steel having excellent rigidity.

한편, 도 6 내지 도 16을 참조하는 바와 같이 요철형성부재(300)는 1차, 2차 연속벽(A,B) 사이에 매립될 수 있다. 또는 도 도시된 바와 같이 요철형성부재(300)는 1차, 2차 연속벽(A,B) 사이에 요철부를 형성한 후 제거될 수 있다.
On the other hand, as shown in Figures 6 to 16, the concave-convex forming member 300 may be buried between the primary, secondary continuous wall (A, B). Alternatively, as shown in FIG. 3, the unevenness forming member 300 may be removed after forming the uneven portion between the first and second continuous walls A and B. FIG.

첫째, 도 6 내지 도 16을 참조하여 요철형성부재(300)가 1차, 2차 연속벽(A,B) 사이에 매립되는 경우, 요철형성부재(300)를 이용한 연속벽의 시공방법을 설명하면 다음과 같다. First, referring to FIGS. 6 to 16, when the unevenness forming member 300 is embedded between the first and second continuous walls A and B, the construction method of the continuous wall using the unevenness forming member 300 will be described. Is as follows.

본 발명에 따른 연속벽의 시공방법은 기본적으로, 현장타설에 의해 1차 연속벽(A)을 형성하되, 1차 연속벽(A)의 2차 연속벽(B) 측 종단면에 요철형성부재(300)가 일체로 설치되도록 한 1차 연속벽형성단계와; 1차 연속벽(A)과의 사이에 요철형성부재(300)가 매립되도록 현장타설에 의해 1차 연속벽(A)에 인접되는 2차 연속벽(B)을 형성하는 2차 연속벽형성단계;를 포함하여 구성될 수 있다.In the method of constructing a continuous wall according to the present invention, the primary continuous wall (A) is basically formed by spot casting, and the unevenness forming member is formed on the longitudinal cross-section of the secondary continuous wall (B) side of the primary continuous wall (A). A primary continuous wall forming step of allowing 300 to be integrally installed; Secondary continuous wall forming step of forming a secondary continuous wall (B) adjacent to the primary continuous wall (A) by in-situ so that the uneven forming member 300 is embedded between the primary continuous wall (A) It can be configured to include.

1차 연속벽(A)은 다음과 같이 형성될 수 있다.The primary continuous wall A may be formed as follows.

우선, 도 8에 도시된 바와 같이, 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)을 지반에 설치하는데, 도 9에 도시된 바와 같이, 그 복수의 보조케이싱(200) 사이에 주케이싱(100)이 설치될 간격을 두고 설치한다.First, as shown in FIG. 8, a plurality of auxiliary casings 200 formed at both sides of the groove 210 for coupling with the main casing 100 are installed on the ground, as shown in FIG. 9. The main casing 100 is installed at intervals between the plurality of auxiliary casings 200.

그리고, 요철형성부재(300)를 복수의 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에 인접되도록 설치한다. 이때, 요철형성부재(300)는 종단부 보조케이싱(200a)과 함께 동시에 설치될 수도 있고, 종단부 보조케이싱(200a)의 설치 후 천공에 근입될 수도 있다.Then, the concave-convex forming member 300 is installed to be adjacent to the secondary casing 200a of the second continuous wall B side of the plurality of auxiliary casings 200. At this time, the concave-convex forming member 300 may be installed together with the terminal auxiliary casing 200a at the same time, or may be indented after the installation of the terminal auxiliary casing 200a.

이후, 도 9에 도시된 바와 같이, 복수의 보조케이싱(200) 사이의 지반을 천공하여 복수의 주케이싱(100)을 설치하고, 그 복수의 보조케이싱(200) 및 주케이싱(100)의 내부에 보강체(400)을 설치한다.Subsequently, as shown in FIG. 9, a plurality of main casings 100 are installed by drilling the ground between the plurality of auxiliary casings 200, and the plurality of auxiliary casings 200 and the interior of the main casing 100 are installed. Install the reinforcement 400 in the.

다음, 보조케이싱(200) 및 주케이싱(100)을 제거하고 콘크리트를 타설하여 양생함으로써, 도 10에 도시된 바와 같은 1차 연속벽(A)을 형성한다.Next, the secondary casing 200 and the main casing 100 are removed and concrete is poured to cure, thereby forming a primary continuous wall A as shown in FIG. 10.

즉, 1차 연속벽(A)의 거푸집 역할을 담당하는 보조케이싱(200) 및 주케이싱(100)을 상호 맞물리는 구조에 의해 설치하고, 이에 콘크리트를 타설한 후, 그 콘크리트의 양생 전 케이싱(100,200)을 제거하면, 양생이 진행되면서 보조케이싱(200) 내부에 타설된 콘크리트와 주케이싱(100) 내부에 타설된 콘크리트가 그 접합부(도 10의 점선)에서 상호 견고한 결합을 이루게 된다.That is, the auxiliary casing 200 and the main casing 100 which serve as the formwork of the primary continuous wall A are installed by interlocking structures, and after the concrete is poured, the casing before curing of the concrete ( Removing the 100,200, while the curing proceeds, the concrete placed inside the auxiliary casing 200 and the concrete placed inside the main casing 100 form a firm bond with each other at their joints (dotted line in FIG. 10).

따라서, 복수의 말뚝이 오버랩(overlap)된 형상을 취함에 따라 우수한 강도를 얻을 수 있도록 하면서도, 말뚝 사이로 흐르는 물을 완전히 차단할 수 있으므로, 높은 강도 및 우수한 차수 효과를 동시에 만족할 수 있는 구조물을 얻을 수 있는 것이다.Therefore, the plurality of piles may have an overlapped shape to obtain excellent strength while completely blocking the water flowing between the piles, thereby obtaining a structure that can satisfy both high strength and excellent ordering effect at the same time. .

보조케이싱(200)에 주케이싱(100)과의 결합을 위한 홈부(210)가 형성됨으로써, 주케이싱(100) 및 보조케이싱(200)이 상기와 같은 요철 결합구조를 이룰 수 있는 구성은 다양한 실시예에 의해 구현될 수 있다.By forming the groove portion 210 for coupling with the main casing 100 in the auxiliary casing 200, the main casing 100 and the auxiliary casing 200 can form a concave-convex coupling structure as described above various implementations It may be implemented by example.

도 6 및 도 7은 그 대표적인 실시예로서, 주케이싱(100)의 단면이 원형 구조에 의해 형성될 수 있다. 보조케이싱(200)은 하나의 원형이 양쪽 원형과 오버랩된 상태에서 양쪽 원형에 의해 오버랩되지 않은 부분과 대응된 단면 형상으로 형성될 수 있으며, 이에 따라 보조케이싱(200)의 홈부(210)의 단면이 만곡진 구조에 의해 구현될 수 있다. 이하에서는 본 실시예의 케이싱(100,200)의 구조에 따른 시공방법의 실시예를 설명한다.6 and 7 are representative embodiments, the cross section of the main casing 100 may be formed by a circular structure. The auxiliary casing 200 may be formed in a cross-sectional shape corresponding to a portion not overlapped by both circles in a state in which one circle overlaps with both circles, and thus the cross section of the groove portion 210 of the auxiliary casing 200 may be formed. It can be implemented by this curved structure. Hereinafter, an embodiment of the construction method according to the structure of the casing (100,200) of the present embodiment.

보조케이싱(200)은 그 자체를 지반에 타입하거나, 천공 후 삽입하는 방식을 취할 수도 있으나, 오거와 같은 기존의 굴착장비를 그대로 활용하기 위해서는, 도 11에 도시된 바와 같이, 일단 주케이싱(100)을 임시로 지반에 설치하고, 그 주케이싱(100) 내부에 보조케이싱(200)을 삽입하여 설치한 후, 설치된 보조케이싱(200)은 지반에 설치된 상태를 유지하면서, 주케이싱(100)을 임시로 제거하는 방식을 취하는 것이 바람직하다.The auxiliary casing 200 may itself be typed into the ground or inserted after drilling, but in order to utilize the existing drilling equipment such as auger as it is, as shown in FIG. ) Is temporarily installed on the ground, and after the auxiliary casing 200 is inserted into the main casing 100 to be installed, the installed auxiliary casing 200 maintains the state of the main casing 100 while being installed on the ground. It is desirable to take a temporary removal method.

주케이싱(100) 내부에 보조케이싱(200)을 삽입하는 작업 및 주케이싱(100)의 임시제거작업에 있어서, 보조케이싱(200)을 주케이싱(100)의 중앙부에 위치시키기 위해서는, 도 11에 도시된 바와 같이, 주케이싱(100)의 내면과 보조케이싱(200) 외면 사이에 스페이서(220)를 삽입하는 것이 바람직하다.In the operation of inserting the auxiliary casing 200 into the main casing 100 and the temporary removal of the main casing 100, the auxiliary casing 200 is located in the center of the main casing 100 in FIG. 11. As shown, it is preferable to insert the spacer 220 between the inner surface of the main casing 100 and the outer surface of the auxiliary casing 200.

도 12에 도시된 바와 같이, 보조케이싱(200) 삽입단계 이후, 주케이싱(100)과 보조케이싱(200)의 사이를 충전재(230)의 되메움에 의해 충전할 수 있으며, 이 경우 주케이싱(100)의 설치를 위하여 보조케이싱(200) 사이의 영역을 천공하는 작업을 보다 원활하게 할 수 있다는 장점이 있다.As shown in FIG. 12, after the insertion of the auxiliary casing 200, the main casing 100 and the auxiliary casing 200 may be filled by the backfill of the filler 230, and in this case, the main casing ( There is an advantage that the work for drilling the area between the auxiliary casing 200 can be more smoothly for the installation of 100).

이를 위해서는 모래 또는 저강도 몰탈과 같이 천공작업이 용이한 충전재(230)를 사용하는 것이 바람직하다.For this purpose, it is preferable to use a filler 230 that is easy to punch, such as sand or low strength mortar.

다음 2차 연속벽(B)은 다음과 같이 형성될 수 있다.Next secondary continuous wall (B) may be formed as follows.

도 13 및 도 14에 도시된 바와 같이, 상기 단계들에 따른 1차 작업에 의해 형성된 1차 연속벽(A)에 인접하여, 상기 1차 연속벽(A)시의 단계들과 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체설치단계, 2차 콘크리트작업단계에 의한 2차 작업이 수행됨으로써, 2차 연속벽(B)을 연속적으로 형성할 수 있다.As shown in Figs. 13 and 14, adjacent to the primary continuous wall A formed by the primary operation according to the above steps, according to the same configuration as the steps at the time of the primary continuous wall A By performing the secondary operation by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement installation step, the secondary concrete work step, it is possible to form a secondary continuous wall (B) continuously.

보다 구체적으로는, 도 9를 참조하는 바와 같이, 상기 1차 작업의 마감에 의한 종단부를 보조케이싱(200a)이 설치된 상태에서 종료하고, 그 종단부 보조케이싱(200a) 내부에 보강체 및 콘크리트 타설, 양생작업을 수행한 후, 종단부 보조케이싱(200a)을 제거함으로써, 도 13의 1차 연속벽(A) 종단부와 같은 구조가 형성되도록 한다.More specifically, as shown in Fig. 9, the terminal ends by the end of the primary work is finished in the state in which the auxiliary casing 200a is installed, and the reinforcement and concrete pouring in the terminal auxiliary casing 200a. , After performing the curing operation, by removing the terminal auxiliary casing (200a), the structure such as the primary continuous wall (A) end of Figure 13 is formed.

2차 연속벽(B)의 작업시, 도 13에 도시된 바와 같이 1차 연속벽(A)의 종단부 측부에 주케이싱(100)이 설치될 간격을 두고, 복수의 보조케이싱(200) 중 최초의 2차 보조케이싱(200b)을 설치한다.During operation of the secondary continuous wall B, as shown in FIG. 13, the main casing 100 is spaced apart from the end side of the primary continuous wall A, and among the plurality of auxiliary casings 200. The first secondary auxiliary casing 200b is installed.

이후, 도 14에 도시된 바와 같이, 1차 연속벽(A)의 종단부와 최초의 2차 보조케이싱(200b) 사이에 복수의 주케이싱(100) 중 최초의 2차 주케이싱(100b)을 설치하고, 나머지 케이싱(100,200)은 상기 1차 연속벽(A)의 경우와 동일한 방식에 의해 설치하며, 상술한 바와 같은 방식으로 보강체설치, 콘크리트 양생작업을 진행함으로써, 2차 연속벽(B)을 얻을 수 있다.Thereafter, as shown in FIG. 14, the first secondary main casing 100b among the plurality of main casings 100b is disposed between the end portion of the primary continuous wall A and the first secondary auxiliary casing 200b. After installation, the remaining casing (100,200) is installed in the same manner as in the case of the primary continuous wall (A), by the reinforcement installation, concrete curing work in the manner described above, the secondary continuous wall (B ) Can be obtained.

이와 같이 시공된 1차 연속벽(A) 및 2차 연속벽(B)은 전체적으로 연속적인 구조를 형성하므로, 수일에 걸쳐 작업이 진행됨에 불구하고 우수한 차수 효과를 얻을 수 있다는 장점이 있다.Since the primary continuous wall (A) and the secondary continuous wall (B) constructed as described above form a continuous structure as a whole, there is an advantage that an excellent ordering effect can be obtained despite the work proceeds over several days.

도 13에 도시된 바와 같이, 1차 연속벽(A)의 종단부와 충전재(230)가 접촉한 상태로 마감된 구성을 취하는 경우, 2차 연속벽(B)의 형성을 위한 주케이싱(100) 중 최초의 2차 주케이싱(100b)의 설치를 위한 천공작업이 용이하다는 장점이 있으며, 이를 위해서는 1차 연속벽(A)의 종단부 보조케이싱(200a)의 설치 및 콘크리트 타설 작업을 다음과 같이 진행하는 것이 필요하다. As shown in FIG. 13, in the case where the end portion of the primary continuous wall A and the filler 230 are in contact with each other in a closed state, the main casing 100 for forming the secondary continuous wall B is formed. ) Has the advantage of easy drilling for the installation of the first secondary main casing (100b), for this purpose, the installation of the secondary auxiliary casing (200a) of the primary continuous wall (A) and concrete pouring work as follows. It is necessary to proceed together.

주케이싱(100)을 임시로 지반에 설치하고, 그 주케이싱(100) 내부에 종단부 보조케이싱(200a)을 삽입하여 설치하며(도 11 참조), 종단부 보조케이싱(200a)과 충전재(230) 사이에 위치되도록 요철형성부재(300)를 설치한 후, 주케이싱(100)과 종단부 보조케이싱(200a)의 사이를 충전재(230)의 되메움에 의해 충전한다. The main casing 100 is temporarily installed on the ground, and the terminal auxiliary casing 200a is inserted and installed in the main casing 100 (see FIG. 11), and the terminal auxiliary casing 200a and the filler material 230 are installed. After installing the concave-convex forming member 300 to be positioned between the), the back of the filler 230 is filled between the main casing 100 and the terminal auxiliary casing (200a).

설치된 종단부 보조케이싱(200a)과 요철형성부재(300)는 지반에 설치된 상태를 유지하면서, 주케이싱(100)을 임시로 제거하고, 종단부 보조케이싱(200a) 내부에 보강체 및 콘크리트 타설작업을 수행한 후, 종단부 보조케이싱(200a)을 제거함으로써, 1차 연속벽(A)의 종단부와 충전재(230)가 접촉한 상태로 마감된 구성을 얻을 수 있다.The terminal auxiliary casing 200a and the concave-convex forming member 300 installed are temporarily removed from the main casing 100 while maintaining the state of being installed on the ground, and reinforcement and concrete pouring work is performed inside the terminal auxiliary casing 200a. After performing, by removing the end auxiliary casing (200a), it is possible to obtain a configuration in which the end portion of the primary continuous wall (A) and the filler material 230 is in contact with each other.

이 경우의 충전재(230)도 모래 또는 저강도 몰탈과 같이 천공작업이 용이한 것을 사용하는 것이 바람직하다.In this case, the filler 230 is also preferably used for easy drilling, such as sand or low strength mortar.

한편, 종단부 보조케이싱(200a)은 도 6 내지 도 14에 도시된 바와 같이 나머지 보조케이싱(200)들과 동일한 형상을 취할 수도 있으나, 도 15 내지 도 17에 도시된 바와 같이 요철형성부재(300)와의 결합관계를 위해 상이한 형상을 취할 수도 있다.Meanwhile, the terminal auxiliary casing 200a may have the same shape as the other auxiliary casings 200 as shown in FIGS. 6 to 14, but the concave-convex forming member 300 is illustrated in FIGS. 15 to 17. It may take a different shape for the coupling relationship with).

즉 도 15에 도시된 바와 같이, 요철형성부재(300)의 1차 연속벽 측 연접면(300A)도 요철형상을 취하고, 종단부 보조케이싱(200a) 또한 이에 대응되는 형상을 취함으로써, 종단부 보조케이싱(200a)과 요철형성부재(300)가 서로 요철형상에 의해 결합될 수 있다.That is, as shown in FIG. 15, the primary continuous wall side connecting surface 300A of the unevenness forming member 300 also has a concave-convex shape, and the terminal auxiliary casing 200a also has a shape corresponding thereto. The auxiliary casing 200a and the concave-convex forming member 300 may be combined with each other by the concave-convex shape.

이에 따라, 요철형성부재(300)와 1차 연속벽(A)도 요철형상에 의해 보다 견고하게 결합되며 보다 확실한 차수효과를 기대할 수 있다.Accordingly, the unevenness forming member 300 and the primary continuous wall A are also more firmly coupled by the uneven shape and a more reliable order effect can be expected.

이때, 요철형성부재(300)와 종단부 보조케이싱(200a) 간 요철형상은 콘크리트 양생시 종단부 보조케이싱(200a)의 제거를 위해 요철형성부재(300)와 종단부 보조케이싱(200a)이 상호 천공의 길이방향, 즉 상하방향을 따라 분리 가능토록 형성됨이 바람직하다. At this time, the concave-convex shape between the concave-convex forming member 300 and the terminal auxiliary casing (200a) is the concave-convex forming member 300 and the terminal auxiliary casing (200a) mutually to remove the terminal auxiliary casing (200a) during concrete curing It is preferable to be formed to be separable along the longitudinal direction of the perforation, that is, the vertical direction.

또한 도 5에 도시된 바와 같이 요철형성부재(300)가 상술한 돌출부(322)를 갖는 경우, 도 16에 도시된 바와 같이 종단부 보조케이싱(200a)은 요철형성부재(300)의 돌출부(322)가 관통될 수 있도록 돌부 관통홀(202)이 형성될 수 있다.In addition, when the concave-convex forming member 300 has the above-described protrusion 322 as shown in FIG. 5, as shown in FIG. 16, the terminal auxiliary casing 200a has the protrusion 322 of the concave-convex forming member 300. The protrusion through hole 202 may be formed to pass through).

이때, 콘크리트 양생시 종단부 보조케이싱(200a)의 제거를 위해, 종단부 보조케이싱(200a)의 돌부 관통홀(202)은 상하방향을 따라 개구된 것이 바람직하다.
At this time, in order to remove the terminal auxiliary casing 200a during concrete curing, the protrusion through hole 202 of the terminal auxiliary casing 200a is preferably opened along the vertical direction.

둘째, 도 17 내지 도 22를 참조하여 요철형성부재(300)에 의해 1차, 2차 연속벽(A,B) 사이에 요철부가 형성된 후 요철형성부재(300)를 제거하는 경우, 요철형성부재(300)를 이용한 연속벽의 시공방법을 설명하면 다음과 같다. 여기서, 요철형성부재(300)를 제거하는 것 이외는 도 6 내지 도 16을 참조하여 상술한 시공방법과 동일, 유사하므로 중복 설명은 생략한다.Second, when the unevenness forming member 300 is removed after the uneven portion is formed between the first and second continuous walls A and B by the uneven forming member 300 with reference to FIGS. 17 to 22, the uneven forming member 300. Referring to the construction method of the continuous wall using the (300) as follows. Here, except for removing the concave-convex forming member 300 is the same as, and similar to the construction method described above with reference to Figures 6 to 16, duplicate description will be omitted.

먼저, 일 실시 예로써 도 17 및 도 18을 참조하여 설명하면 다음과 같다.First, with reference to FIGS. 17 and 18 as an embodiment as follows.

1차 연속벽(A) 형성을 위해, 1차 보조케이싱 설치단계, 차 주케이싱 설치단계, 1차 보강체 설치단계, 1차 콘크리트작업단계를 진행한다. 다만, 도 17에 도시된 바와 같이 복수의 1차 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에는 요철형성부재(300)가 인접 설치된 후 요철형성부재(300) 측 천공 영역이 충전재(230)에 의해 되메워질 수 있다. 그리고, 이와 같이 설치된 요철형성부재(300)는 1차 콘크리트작업단계에서 종단부 보조케이싱(200a)과 함께 제거될 수 있다. In order to form the primary continuous wall (A), the primary auxiliary casing installation step, the primary casing installation step, the primary reinforcement installation step, the primary concrete work step is carried out. However, as shown in FIG. 17, after the concave-convex forming member 300 is installed adjacent to the secondary casing 200a of the second continuous wall B side of the plurality of primary auxiliary casings 200, the concave-convex forming member 300 is disposed. ) Perforation region may be backfilled by filler 230. In addition, the concave-convex forming member 300 installed as described above may be removed together with the terminal auxiliary casing 200a in the first concrete work step.

따라서, 도 18에 도시된 바와 같이 1차 연속벽(A)의 종단면에 요철형성부재(300)에 의한 요철부(A1)가 형성될 수 있으며, 이에 따라 요철형성부재(300)가 제거되더라도 1차 연속벽(A)과 2차 연속벽(B)이 상호 요철구조의 결합에 의해 견고하게 연결될 수 있다. 또한 요철형성부재(300)는 1차 연속벽(A)에 요철부(A1)를 형성한 후 제거됨에 따라, 재사용이 가능하다.Therefore, as shown in FIG. 18, the uneven portion A1 may be formed in the longitudinal cross-section of the primary continuous wall A by the unevenness forming member 300, and thus, even if the unevenness forming member 300 is removed 1. The primary continuous wall A and the secondary continuous wall B can be firmly connected by combining the uneven structure with each other. In addition, the concave-convex forming member 300 is removed after forming the concave-convex portion A1 on the primary continuous wall A, and thus can be reused.

한편, 요철형성부재(300)는 상술한 바와 같이 제거되는 요철형성부재(300)에 의해 1차 연속벽(A)의 종단면에 요철부(A1)가 형성될 수 있도록, 제1요철부(310)만을 갖도록 형성될 수 있다. 요철형성부재(300)의 제1요철부(310)는 요철형성부재(300)가 천공을 따라 제거 가능토록 상하방향으로 수직한 라인 형상으로 형성될 수 있다.On the other hand, the concave-convex forming member 300 is the first concave-convex portion 310 so that the concave-convex portion A1 can be formed in the longitudinal section of the primary continuous wall (A) by the concave-convex forming member 300 is removed as described above. It can be formed to have only. The first concave-convex portion 310 of the concave-convex forming member 300 may be formed in a line shape perpendicular to the vertical direction so that the concave-convex forming member 300 can be removed along the perforation.

이와 같은 요철형성부재(300)는 1차 보조케이싱 설치단계에서 설치될 수도 있고, 1차 주케이싱 설치단계 후 별도의 요철형성부재 설치단계에 의해 설치될 수도 있으며, 1차 연속벽(A)의 종단면에 요철부를 형성할 수 있다면 어떠한 단계에서 설치되든 무방하다.Such irregularities forming member 300 may be installed in the primary auxiliary casing installation step, or may be installed by a separate irregularities forming member installation step after the primary main casing installation step, of the primary continuous wall (A) As long as the uneven portion can be formed in the longitudinal section, it may be installed at any stage.

이후, 2차 연속벽(B)이 1차 연속벽(A)의 요철부에 인접하도록 설치될 수 있다.Thereafter, the secondary continuous wall B may be installed to be adjacent to the uneven portion of the primary continuous wall A. FIG.

또 다른 실시 예로써 도 19 내지 도 22를 참조하여 설명하면 다음과 같다.As another embodiment, the following description will be made with reference to FIGS. 19 to 22.

도 19에 도시된 바와 같이 1차 연속벽(A)의 종단면에 요철형성부재(300)가 설치된 상태로 1차 연속벽형성단계가 마무리되며, 2차 연속벽 형성단계는 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체 설치단계, 2차 콘크리트작업단계에 의해 이루어질 수 있다.As shown in FIG. 19, the first continuous wall forming step is completed with the unevenness forming member 300 installed on the end surface of the first continuous wall A, and the second continuous wall forming step is the secondary auxiliary casing installation step. It can be made by the secondary main casing installation step, the secondary reinforcement installation step, the secondary concrete work step.

다만, 2차 연속벽(B)을 형성하는 중에, 도 20 내지 도 22에 도시된 바와 같이 요철형성부재(300)를 제거하는 요철형성부재 제거단계가 실시될 수 있다.However, during the formation of the second continuous wall B, as shown in FIGS. 20 to 22, the uneven forming member removing step of removing the uneven forming member 300 may be performed.

즉, 요철형성부재 제거단계는 도 20에 도시된 바와 같이 복수의 2차 주케이싱(100) 중 1차 연속벽(A)에 인접 설치된 선단부 2차 주케이싱(100)을 임시로 제거한 후, 도 21에 도시된 바와 같이 1차 연속벽(A)에 설치된 요철형성부재(300)를 제거한다. 그리고, 도 22에 도시된 바와 같이 임시 제거한 선단부 2차 주케이싱(100)을 원래 자리에 재설치할 수 있다.That is, as shown in FIG. 20, the removing of the uneven-formed member temporarily removes the tip secondary main casing 100 installed adjacent to the primary continuous wall A among the plurality of secondary main casings 100. As shown in FIG. 21, the unevenness forming member 300 installed in the primary continuous wall A is removed. And, as shown in FIG. 22, the temporarily removed tip secondary main casing 100 may be reinstalled in its original position.

이때, 요철형성부재(300)는 1차 연속벽(A)의 종단면에 요철부(A1)를 형성할 수 있도록, 적어도 1차 연속벽(A)과 인접하는 면에 제2요철부(320)가 형성될 수 있다. 요철형성부재(300)의 제2요철부(320)는 요철형성부재(300)가 천공을 따라 제거 가능토록 상하방향으로 수직한 라인 형상으로 형성될 수 있다.At this time, the concave-convex forming member 300 has a second concave-convex portion 320 on a surface adjacent to at least the primary continuous wall (A) so that the concave-convex portion A1 can be formed on the longitudinal cross-section of the primary continuous wall (A). Can be formed. The second concave-convex portion 320 of the concave-convex forming member 300 may be formed in a line shape perpendicular to the vertical direction so that the concave-convex forming member 300 can be removed along the perforation.

이와 같은 요철형성부재 제거단계는 2차 주케이싱 설치단계 중에 이루어질 수도 있고, 2차 주케이싱 설치단계와 2차 보강체 설치단계 사이에 이루어질 수도 있으며, 선단부 2차 주케이싱(100)가 설치된 후라면 언제든지 가능하다.
The uneven forming member removing step may be performed during the secondary main casing installation step, or may be performed between the secondary main casing installation step and the secondary reinforcement installation step, and after the tip secondary main casing 100 is installed. It is possible at any time.

이와 같은 시공방법에 의한 형성되는 연속벽은 건설, 토목분야에서 여러가지 벽체, 벽구조물로 형성될 수 있다.Continuous wall formed by such a construction method may be formed of various walls, wall structures in the construction, civil engineering.

예컨대, 상술한 바와 같이 차수효과가 우수한 바, 본 발명에 따른 연속벽은 흙막이 및 차수를 목적으로 하는 차수벽구조물로서 형성될 수 있다.For example, as described above, the ordering effect is excellent, and the continuous wall according to the present invention may be formed as an ordering wall structure for the purpose of the soil barrier and the order.

또한 상술한 바와 같이 흙막이 및 차수를 동시에 충족할 수 있으며, 건축물의 내력벽으로 충분한 내력이 확보될 수 있는 바 최근 많이 이용되는 탑다운공법의 지중연속벽으로 형성될 수도 있다.
In addition, as described above, it is possible to satisfy the soil barrier and the order at the same time, and can be formed as a continuous continuous wall of the top-down method that is widely used in recent years as a sufficient strength can be secured as the bearing wall of the building.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다. It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

A; 1차 연속벽 B; 2차 연속벽
100; 주케이싱 200; 보조케이싱
300; 요철형성부재 310; 제1요철부
320; 제2요철부 322; 돌출부
400; 보강체
A; Primary continuous wall B; 2nd continuous wall
100; Main casing 200; Auxiliary casing
300; Irregularities forming member 310; First uneven part
320; Second uneven portion 322; projection part
400; Reinforcement

Claims (12)

요철형성부재(300)에 의한 요철부를 갖는 1차 연속벽(A)을 현장타설에 의해 형성하는 1차 연속벽형성단계와, 상기 1차 연속벽(A)의 요철부에 인접하여 2차 연속벽(B)을 형성하는 2차 연속벽형성단계를 포함하며;
상기 요철형성부재(300)는 연속 형성되는 복수의 연속벽(A,B)이 상호 요철부에 의해 연접될 수 있도록 상호 인접되는 두 연속벽(A,B) 사이에 개재되며 적어도 어느 한쪽 면에 요철부(310,320)가 형성되고;
상기 1차 연속벽형성단계는, 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)을 지반에 설치하되 그 복수의 보조케이싱(200) 사이에 상기 주케이싱(100)이 설치될 간격을 두고 설치하는 1차 보조케이싱 설치단계와, 상기 요철형성부재(300)를 상기 복수의 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에 인접되도록 설치하는 요철형성부재 설치단계와, 상기 1차 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 천공하여 복수의 상기 주케이싱(100)을 설치하는 1차 주케이싱 설치단계와, 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 보강체(400)를 설치하는 1차 보강체 설치단계와, 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 콘크리트를 타설하고 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)를 제거하여 상기 요철형성부재(300)가 설치된 1차 연속벽(A)를 형성하는 1차 콘크리트작업단계를 포함하며;
상기 2차 연속벽형성단계는 상기 1차 연속벽형성단계와 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체 설치단계, 2차 콘크리트작업단계에 의해 이루어지며, 상기 복수의 2차 주케이싱(100) 중 1차 연속벽(A)에 인접 설치된 선단부 2차 주케이싱(100)을 임시 제거하여 상기 1차 연속벽(A)에 설치된 요철형성부재(300)를 제거한 후, 상기 임시 제거한 선단부 2차 주케이싱(100)을 재설치하는 요철형성부재 제거단계를 더 포함하는 것을 특징으로 하는 차수벽구조물 시공방법.
The first continuous wall forming step of forming the primary continuous wall (A) having the uneven portion by the uneven portion 300 by spot casting, and the second continuous adjacent to the uneven portion of the primary continuous wall (A) A second continuous wall forming step of forming the wall (B);
The concave-convex forming member 300 is interposed between two continuous walls (A, B) adjacent to each other so that a plurality of continuous walls (A, B) that are continuously formed can be connected by the mutual concave-convex portion and at least on one side Uneven portions 310 and 320 are formed;
In the first continuous wall forming step, a plurality of auxiliary casings 200 formed on both sides of the grooves 210 for coupling with the main casing 100 are installed on the ground, and the plurality of auxiliary casings 200 are disposed between the plurality of auxiliary casings 200. Primary auxiliary casing installation step of installing the main casing (100) at intervals to be installed, and the concave-convex forming member (300) of the secondary casing (200) of the secondary continuous wall (B) side end auxiliary casing Installing a plurality of the main casing 100 by drilling the ground between the uneven forming member installation step of installing adjacent to (200a) and the plurality of auxiliary casing 200 installed by the primary auxiliary casing installation step A primary main casing installation step, a primary reinforcement installation step of installing a reinforcement 400 in the plurality of primary auxiliary casings 200 and the primary main casing 100, and the plurality of primary Concrete is poured into the auxiliary casing 200 and the primary main casing 100 Includes a primary concreting step of forming the roughening element 300 is the first continuous wall (A) provided by removing the plurality of first secondary housing 200 and the primary main casing 100, and;
The secondary continuous wall forming step is made by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement installation step, the secondary concrete work step according to the same configuration as the primary continuous wall formation step The temporary concave-convex forming member 300 installed in the primary continuous wall A by temporarily removing the tip secondary main casing 100 adjacent to the primary continuous wall A among the plurality of secondary main casings 100. After removing, the ordered wall structure construction method further comprising the step of removing the irregularities forming member for reinstalling the temporary main secondary casing (100) removed.
청구항 1에 있어서,
상기 요철형성부재(300)는 상기 상호 인접되는 두 연속벽 (A,B)중 후 시공되는 연속벽(B)에 인접되는 면에 제1요철부(310)가 형성되며, 제1요철부(310)는 복수의 제1홈(312)으로 형성된 것을 특징으로 하는 차수벽구조물 시공방법.
The method according to claim 1,
The concave-convex forming member 300 has a first concave-convex portion 310 is formed on a surface adjacent to the continuous wall (B) to be constructed later of the two contiguous continuous wall (A, B), the first concave-convex portion ( 310 is a method for constructing a wall structure, characterized in that formed with a plurality of first grooves (312).
청구항 1에 있어서,
상기 요철형성부재(300)는 상기 상호 인접되는 두 연속벽 (A,B)중 선 시공되는 연속벽(A)에 인접되는 면에도 제2요철부(320)가 형성된 것을 특징으로 하는 차수벽구조물 시공방법.
The method according to claim 1,
The concave-convex forming member 300 has a second concave-convex structure, characterized in that the second concave-convex portion 320 is formed on the surface adjacent to the continuous wall (A) of the two adjacent continuous wall (A, B) Way.
청구항 3에 있어서,
상기 요철형성부재(300)는 상기 제2요철부(320)는 상기 선 시공되는 연속벽(A)을 향해 돌출 형성된 돌출부(322)로 형성된 것을 특징으로 하는 차수벽구조물 시공방법.
The method according to claim 3,
The concave-convex forming member 300, the second concave-convex portion 320 is a projection wall structure construction method, characterized in that formed as a protrusion 322 protruding toward the continuous wall (A) to be constructed.
청구항 4에 있어서,
상기 요철형성부재(300)는 상기 돌출부(322)는 상기 상호 인접되는 두 연속벽(A,B) 중 후 시공되는 연속벽(B) 측에 제2홈(324)이 형성될 수 있도록 돌출 형성된 것을 특징으로 하는 차수벽구조물 시공방법.
The method of claim 4,
The irregularities forming member 300 is formed such that the protrusion 322 protrudes so that the second groove 324 is formed on the side of the continuous wall B which is later constructed among the two adjacent continuous walls A and B. Ordered wall structure construction method characterized in that.
청구항 5에 있어서,
상기 요철형성부재(300)는 상기 돌출부(322)의 선 시공되는 연속벽 측 인접면 중 상기 제2홈(324)의 둘레면과 대응되는 부분 및, 상기 제2홈(324)의 개구부 반대쪽면인 바닥면에는 수팽창 지수재(330)가 도포된 것을 특징으로 하는 차수벽구조물 시공방법.
The method according to claim 5,
The concave-convex forming member 300 is a portion corresponding to the circumferential surface of the second groove 324 among the adjacent wall side adjacent surfaces of the protrusion 322, and the surface opposite to the opening of the second groove 324. A water barrier wall construction method characterized in that the water-expandable index member 330 is applied to the bottom surface.
삭제delete 삭제delete 청구항 1에 있어서,
상기 2차 연속벽형성단계는 상기 1차 연속벽형성단계와 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체 설치단계, 2차 콘크리트작업단계에 의해 이루어지며;
상기 2차 연속벽(B)의 1차 연속벽(A) 반대쪽 종단부에 3차 차수벽이 연속 형성되는 경우에는, 상기 3차 차수벽과의 사이에 상기 요철형성부재(300)가 설치되도록 상기 1차 연속벽형성단계와 동일한 구성에 따른 요철형성부재설치단계가 더 포함될 수 있는 것을 특징으로 하는 차수벽구조물 시공방법.
The method according to claim 1,
The secondary continuous wall forming step is made by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement installation step, the secondary concrete work step according to the same configuration as the primary continuous wall formation step ;
In the case where tertiary order walls are continuously formed at the end portion opposite to the primary continuous wall A of the secondary continuous wall B, the unevenness forming member 300 is installed between the third order walls. A method for constructing a barrier wall structure, which may further include a step of installing a concave-convex forming member according to the same configuration as the step of forming a continuous wall.
삭제delete 요철형성부재(300)에 의한 요철부를 갖는 1차 연속벽(A)을 현장타설에 의해 형성하는 1차 연속벽형성단계와, 상기 1차 연속벽(A)의 요철부에 인접하여 2차 연속벽(B)을 형성하는 2차 연속벽형성단계를 포함하며;
상기 요철형성부재(300)는 연속 형성되는 복수의 연속벽(A,B)이 상호 요철부에 의해 연접될 수 있도록 상호 인접되는 두 연속벽(A,B) 사이에 개재되며 적어도 어느 한쪽 면에 요철부(310,320)가 형성되고;
상기 1차 연속벽형성단계는
주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)을 임시로 설치한 주케이싱(100)의 내부에 설치한 후 상기 임시 설치한 주케이싱(100)을 제거하는 1차 보조케이싱 설치단계와,
상기 1차 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 천공하여, 복수의 상기 주케이싱(100)을 상기 보조케이싱(200)에 인접하도록 설치하는 1차 주케이싱 설치단계와,
상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 보강체(400)를 설치하는 1차 보강체 설치단계와,
상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 콘크리트를 타설하고 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)를 제거하여 1차 연속벽(A)를 형성하는 1차 콘크리트작업단계를 포함하며,
상기 복수의 1차 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에는 상기 요철형성부재(300)가 인접 설치된 후 상기 요철형성부재(300) 측 천공 영역이 충전재(230)에 의해 되메워지며,
상기 요철형성부재(300)는 상기 1차 콘크리트작업단계에서 상기 종단부 보조케이싱(200a)과 함께 제거되며 상기 1차 연속벽(A)에 상기 요철형성부재(300)에 의한 요철부가 형성되는 것을 특징으로 하는 차수벽구조물 시공방법.
The first continuous wall forming step of forming the primary continuous wall (A) having the uneven portion by the uneven portion 300 by spot casting, and the second continuous adjacent to the uneven portion of the primary continuous wall (A) A second continuous wall forming step of forming the wall (B);
The concave-convex forming member 300 is interposed between two continuous walls (A, B) adjacent to each other so that a plurality of continuous walls (A, B) that are continuously formed can be connected by the mutual concave-convex portion and at least on one side Uneven portions 310 and 320 are formed;
The first continuous wall forming step
The main casing 100 temporarily installed after installing the plurality of auxiliary casings 200 formed on both sides of the groove 210 for coupling with the main casing 100 to the interior of the main casing 100 temporarily installed. The first secondary casing installation step to remove the;
Primary primary casing installation for drilling the ground between the plurality of secondary casings 200 installed by the primary secondary casing installation step, and installing the plurality of main casings 100 adjacent to the secondary casings 200. Steps,
A primary reinforcement installation step of installing a reinforcement member 400 in the plurality of primary auxiliary casings 200 and the primary main casing 100;
Placing concrete in the plurality of primary auxiliary casings 200 and primary main casings 100 and removing the plurality of primary auxiliary casings 200 and primary main casings 100 to form a primary continuous wall. (A) includes a primary concrete work step,
Of the plurality of primary auxiliary casings 200, the secondary continuous wall (B) side end portion auxiliary casing (200a) after the concave-convex forming member 300 is installed adjacent to the perforated region of the concave-convex forming member 300 is a filler Backfilled by 230,
The concave-convex forming member 300 is removed together with the end auxiliary casing 200a in the first concrete work step, and the concave-convex portion formed by the concave-convex forming member 300 is formed in the first continuous wall A. A method for constructing a wall structure, characterized in that.
요철형성부재(300)에 의한 요철부를 갖는 1차 연속벽(A)을 현장타설에 의해 형성하는 1차 연속벽형성단계와, 상기 1차 연속벽(A)의 요철부에 인접하여 2차 연속벽(B)을 형성하는 2차 연속벽형성단계를 포함하며;
상기 요철형성부재(300)는 연속 형성되는 복수의 연속벽(A,B)이 상호 요철부에 의해 연접될 수 있도록 상호 인접되는 두 연속벽(A,B) 사이에 개재되며 적어도 어느 한쪽 면에 요철부(310,320)가 형성되고;
상기 1차 연속벽형성단계는, 주케이싱(100)과의 결합을 위한 홈부(210)가 양측에 형성된 복수의 보조케이싱(200)을 지반에 설치하되 그 복수의 보조케이싱(200) 사이에 상기 주케이싱(100)이 설치될 간격을 두고 설치하는 1차 보조케이싱 설치단계와, 상기 요철형성부재(300)를 상기 복수의 보조케이싱(200) 중 2차 연속벽(B) 측 종단부 보조케이싱(200a)에 인접되도록 설치하는 요철형성부재 설치단계와, 상기 1차 보조케이싱 설치단계에 의해 설치된 상기 복수의 보조케이싱(200) 사이의 지반을 천공하여 복수의 상기 주케이싱(100)을 설치하는 1차 주케이싱 설치단계와, 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 보강체(400)를 설치하는 1차 보강체 설치단계와, 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)의 내부에 콘크리트를 타설하고 상기 복수의 1차 보조케이싱(200) 및 1차 주케이싱(100)를 제거하여 상기 요철형성부재(300)가 설치된 1차 연속벽(A)를 형성하는 1차 콘크리트작업단계를 포함하며;
상기 2차 연속벽형성단계는 상기 1차 연속벽형성단계와 동일한 구성에 따른 2차 보조케이싱 설치단계, 2차 주케이싱 설치단계, 2차 보강체 설치단계, 2차 콘크리트작업단계에 의해 이루어지며, 상기 복수의 2차 주케이싱(100) 중 1차 연속벽(A)에 인접 설치된 선단부 2차 주케이싱(100)을 임시 제거하여 상기 1차 연속벽(A)에 설치된 요철형성부재(300)를 제거한 후, 상기 임시 제거한 선단부 2차 주케이싱(100)을 재설치하는 요철형성부재 제거단계를 더 포함하는 것을 특징으로 하는 탑다운공법의 지중연속벽 시공방법.
The first continuous wall forming step of forming the primary continuous wall (A) having the uneven portion by the uneven portion 300 by spot casting, and the second continuous adjacent to the uneven portion of the primary continuous wall (A) A second continuous wall forming step of forming the wall (B);
The concave-convex forming member 300 is interposed between two continuous walls (A, B) adjacent to each other so that a plurality of continuous walls (A, B) that are continuously formed can be connected by the mutual concave-convex portion and at least on one side Uneven portions 310 and 320 are formed;
In the first continuous wall forming step, a plurality of auxiliary casings 200 formed on both sides of the grooves 210 for coupling with the main casing 100 are installed on the ground, and the plurality of auxiliary casings 200 are disposed between the plurality of auxiliary casings 200. Primary auxiliary casing installation step of installing the main casing (100) at intervals to be installed, and the concave-convex forming member (300) of the secondary casing (200) of the secondary continuous wall (B) side end auxiliary casing Installing a plurality of the main casing 100 by drilling the ground between the uneven forming member installation step of installing adjacent to (200a) and the plurality of auxiliary casing 200 installed by the primary auxiliary casing installation step A primary main casing installation step, a primary reinforcement installation step of installing a reinforcement 400 in the plurality of primary auxiliary casings 200 and the primary main casing 100, and the plurality of primary Concrete is poured into the auxiliary casing 200 and the primary main casing 100 Includes a primary concreting step of forming the roughening element 300 is the first continuous wall (A) provided by removing the plurality of first secondary housing 200 and the primary main casing 100, and;
The secondary continuous wall forming step is made by the secondary auxiliary casing installation step, the secondary main casing installation step, the secondary reinforcement installation step, the secondary concrete work step according to the same configuration as the primary continuous wall formation step The temporary concave-convex forming member 300 installed in the primary continuous wall A by temporarily removing the tip secondary main casing 100 adjacent to the primary continuous wall A among the plurality of secondary main casings 100. After removing, the method for removing the continuous continuous wall of the top down method characterized in that it further comprises the step of removing the irregularities forming member for reinstalling the secondary main casing (100).
KR1020100093975A 2010-09-28 2010-09-28 Concavo-convex member for wall structure and construction method for wall used in the same KR101219452B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100093975A KR101219452B1 (en) 2010-09-28 2010-09-28 Concavo-convex member for wall structure and construction method for wall used in the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100093975A KR101219452B1 (en) 2010-09-28 2010-09-28 Concavo-convex member for wall structure and construction method for wall used in the same

Publications (2)

Publication Number Publication Date
KR20120032371A KR20120032371A (en) 2012-04-05
KR101219452B1 true KR101219452B1 (en) 2013-01-11

Family

ID=46135501

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100093975A KR101219452B1 (en) 2010-09-28 2010-09-28 Concavo-convex member for wall structure and construction method for wall used in the same

Country Status (1)

Country Link
KR (1) KR101219452B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102283588B1 (en) * 2020-12-18 2021-07-30 김기남 File for cut-off wall with bended connection parts and the construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5738835U (en) * 1980-08-18 1982-03-02
KR20050092144A (en) * 2004-03-15 2005-09-21 이은숙 Arch steel pipe sheet piles use of arching effect and its wall
KR100752397B1 (en) * 2006-02-13 2007-08-28 홍지기술산업주식회사 Construction method for underground watertight wall and subsidiary casing used in the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5738835U (en) * 1980-08-18 1982-03-02
KR20050092144A (en) * 2004-03-15 2005-09-21 이은숙 Arch steel pipe sheet piles use of arching effect and its wall
KR100752397B1 (en) * 2006-02-13 2007-08-28 홍지기술산업주식회사 Construction method for underground watertight wall and subsidiary casing used in the same

Also Published As

Publication number Publication date
KR20120032371A (en) 2012-04-05

Similar Documents

Publication Publication Date Title
KR101314081B1 (en) Retaining wall and upeer structure connection method for rahmen structure
KR100864110B1 (en) Inserting method for casing and construction method for continuous wall thereof
KR100752397B1 (en) Construction method for underground watertight wall and subsidiary casing used in the same
KR100862977B1 (en) Precast concrete file and method for constructing thereof
KR101777176B1 (en) Construction method of cast-in-placed-pile using steel pipes having different shapes to each other
KR101572561B1 (en) Steel assembly for Pile
KR102009077B1 (en) Earth retaining wall construction method using castinplace concrete pile of impermeable peristyle type
JP5686693B2 (en) Invert construction method and precast member
KR101842208B1 (en) Construction method of retaining wall
KR101524303B1 (en) The wall members and underground wall, underground wall construction method using the same
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
JP2008223339A (en) Pile head strengthening method for hollow pile and pile head strengthening reinforcement material
KR20110070188A (en) Construction method for underground watertight wall
KR101521556B1 (en) Underground wall construction method using wall members
KR101219452B1 (en) Concavo-convex member for wall structure and construction method for wall used in the same
KR101153314B1 (en) Construction method for underground watertight wall
KR101153313B1 (en) Subsidiary casing and construction method for underground watertight wall using the same
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
JP6785591B2 (en) Construction method of the end structure of the leading element and the continuous underground wall
KR101017127B1 (en) Connecting Structure between Foundation and Pier, and Construction Method thereof
KR102062534B1 (en) Structure for grid join
KR101219450B1 (en) Building structure using underground watertight wall and construction method thereof
KR20190142492A (en) PHC pile to facilitate soil guard and construction method of soil guard structure using the same
KR101279618B1 (en) Construction method of underground structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170103

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190103

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20200114

Year of fee payment: 8