KR20100002547A - The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure - Google Patents

The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure Download PDF

Info

Publication number
KR20100002547A
KR20100002547A KR1020080062476A KR20080062476A KR20100002547A KR 20100002547 A KR20100002547 A KR 20100002547A KR 1020080062476 A KR1020080062476 A KR 1020080062476A KR 20080062476 A KR20080062476 A KR 20080062476A KR 20100002547 A KR20100002547 A KR 20100002547A
Authority
KR
South Korea
Prior art keywords
underground
bending moment
wall
forming
excavation
Prior art date
Application number
KR1020080062476A
Other languages
Korean (ko)
Inventor
구자갑
Original Assignee
주식회사 코아이엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 코아이엔씨 filed Critical 주식회사 코아이엔씨
Priority to KR1020080062476A priority Critical patent/KR20100002547A/en
Publication of KR20100002547A publication Critical patent/KR20100002547A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions

Abstract

The present invention relates to a method for constructing underground structures and structures constructed thereby, in particular by increasing the efficiency of construction and construction of soil by sloped or curved floor slabs of reinforced concrete structures installed underground. The present invention relates to a method of constructing an underground structure and a structure constructed thereby, which reduce and reduce slab materials and reduce bending moments. The structure is constructed by using H-pile and earth plate method, heating method, or diaphragm wall method to construct a wall, which is a fixture, along the excavation interface, and to maintain the angle of repose as planned based on the wall and reinforcement structure. In the underground structure construction method consisting of a step of forming an excavation portion by excavating, a step of forming a reinforcing structure to stabilize the wall, a step of forming an underground structure of reinforced concrete in the excavation portion, and a step of finishing , When forming the underground structure, the floor slab of the structure is characterized in that formed in a structure in which the bending moment is reduced.

Description

The underground infrastructure construction work method for the bending moment reduction using the same, and infrastructure}

The present invention relates to a method for constructing underground structures and structures constructed thereby, in particular by increasing the efficiency of construction and construction of soil by sloped or curved floor slabs of reinforced concrete structures installed underground. The present invention relates to a method of constructing an underground structure and a structure constructed thereby, which can reduce the amount of slab material and reduce the bending moment and reduce the entry of temporary facilities.

Recently, with the development of redevelopment and reconstruction of downtown areas, the excavation construction site with a large depth is increasing.

In particular, in urban areas, excavation work is often performed near adjacent land boundaries in order to increase land utilization.

For example, when looking at the construction method of the subway station, which is one of the underground structures generally constructed in Korea, as shown in FIGS. 1A to 1D, a heat-treating method or a diaphragm for digging along the excavation interface on the ground 110 is shown. The wall 120, which is a temporary facility, is constructed by a fram wall construction method.

The excavation portion 111 is formed by digging the center to a flat bottom 111a with an excavator or the like while maintaining the angle of repose as the reference section of the wall 120.

The wall 120 is formed to form a reinforcing structure 130 made of a strip or anchor so as to stabilize.

The station structure 140 is formed of reinforced concrete on the bottom 111a of the excavation 111, and finishes.

However, in the conventional underground structure construction method, since the cross section of the bottom slab 141 of the station structure 140 constructed underground is formed into a quadrangle, the bending moment is increased and the tensile stress is increased by the tensile stress. There was a problem that the cross section of the bottom slab 141 is larger.

In addition, there is a problem that the excavation amount is unnecessarily increased to the lower space of the bottom slab 141 in a square, and the waste material such as reinforced concrete for constructing the bottom slab 141 is wasted more.

Therefore, in the case of the conventional underground structure construction method of forming a square cross section of the floor slab 141 has a disadvantage that the material consumption is enormous and requires a lot of construction costs, because the construction period is also long, the construction efficiency and economic efficiency is low There is a problem.

Thus, the present invention was created to solve the above problems, an object of the present invention is to be formed to be inclined or curved in the bottom slab of the structure installed underground, the amount of excavation of the soil and slab material is reduced, It is to provide an underground structure construction method for reducing the bending moment to reduce the bending moment, and thereby a structure constructed.

In order to achieve the above object, the present invention constructs a wall along the excavation boundary using a temporary construction method, and excavates the center by excavating the center while maintaining an angle of repose as long as the cross-section planned based on the wall and the reinforcing structure. And a step of forming a reinforcing structure to stabilize the wall, a step of forming an underground structure with reinforced concrete in the excavation part, and a finishing process. , The floor slab of the structure is characterized in that to form a structure in which the bending moment is reduced.

Optionally, the structure in which the bottom slab bending moment of the structure is reduced is characterized in that it is either inclined or made of a curved surface.

In addition, the present invention provides a structure constructed by the underground structure construction method for reducing the bending moment described above.

As described above, the present invention may achieve an excellent effect of preventing deformation by reducing the bending moment acting on the floor slab by forming the floor slab of the underground structure to be inclined or curved.

In addition, while reducing the amount of excavation of soil for the construction of underground structures, there is an effect that can reduce the material when building the floor slab of the structure.

Hereinafter, preferred embodiments of the present invention will be described in more detail with reference to the accompanying drawings.

Here, the components having the same function in all the following drawings are omitted by repeated reference to the same reference numerals, and the following terms are defined in consideration of functions in the present invention, which is a unique commonly used meaning It should be interpreted as.

2a to 2d is a diagram schematically illustrating a method for constructing an underground structure for reducing a bending moment according to an embodiment of the present invention. First, as shown in FIG. The diaphragm wall method is used to build a wall 220 that is a temporary fixture along the excavation interface.

Next, the excavation part 211 is formed using an excavator or the like as long as the end face is planned in the wall 220.

Here, the excavation of the excavation part 211 is formed to form an inclined or curved surface to the bottom edge portion 211b.

At this time, since only the bottom center portion 211a of the excavation portion 211 is excavated deeper than the edge portion 211b, the excavation amount of the soil is reduced.

Next, the reinforcing structure 230 is formed using a belt or an anchor to stabilize the wall 220.

Here, the reinforcing structure 230 serves as a transverse steel that transmits the force (moment or shear force) of the wall 220 to the axial force (AXIAL FORCE) as one of the members during the force transmission process.

Next, the bottom slab 241 is formed of reinforced concrete in the excavation portion 211, and subsequently, the underground structure 240 is constructed by constructing the first basement slab 242 and the second basement slab 243, etc. as necessary. To complete.

In this case, the bending moment of the bottom slab 241 of the underground structure 240 is reduced as the bottom edge portion 211b of the excavating portion 211 forming the underground structure 240 is formed to be inclined or curved. It can be easily constructed to form an inclined or curved surface which is a structure.

Subsequently, after completion of the underground structure 240, the outer wall is constructed, and other finishes are arranged to complete the entire underground structure.

On the other hand, the underground structure construction method may be a bottom-up construction (bottom-up) or a top-down construction (top-down) construction from the top to the bottom.

The present invention described above is not limited to the above-described embodiments and the accompanying drawings, and various changes, modifications, and equivalent changes to other embodiments may be made without departing from the technical spirit of the present invention. It will be apparent to those skilled in the art to which the invention pertains.

1A to 1D are cross-sectional views schematically illustrating a conventional underground structure construction method.

2A to 2D are cross-sectional views schematically illustrating a method for constructing an underground structure having a structure in which a bending moment is reduced according to the present invention.

※ Explanation of code about main part of drawing ※

210: ground 211: drilling portion

211a: bottom center portion 211b: edge portion

220: wall 230: reinforcement structure

240: structure 241: floor slab

242: 1st floor slab 243: 2nd floor slab

Claims (3)

Constructing a wall which is a temporary fixture along an excavation boundary by a temporary construction method, excavating a center by a predetermined section based on the wall and the reinforcing structure, and forming an excavation section; forming a reinforcing structure to stabilize the wall; and In the underground structure construction method consisting of the step of forming the structure of reinforced concrete in the excavation portion and the step of finishing the finishing process, When the structure is formed of the reinforced concrete, the floor slab of the structure underground structure construction method for reducing the bending moment, characterized in that to form a structure in which the bending moment is reduced. The method of claim 1, wherein the bottom slab bending moment of the structure is reduced structure of the underground structure for reducing the bending moment, characterized in that any one of the inclined or made of a curved surface. The structure characterized in that constructed by the underground structure construction method for reducing the bending moment of any one of claims 1 and 2.
KR1020080062476A 2008-06-30 2008-06-30 The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure KR20100002547A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080062476A KR20100002547A (en) 2008-06-30 2008-06-30 The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080062476A KR20100002547A (en) 2008-06-30 2008-06-30 The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure

Publications (1)

Publication Number Publication Date
KR20100002547A true KR20100002547A (en) 2010-01-07

Family

ID=41812569

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080062476A KR20100002547A (en) 2008-06-30 2008-06-30 The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure

Country Status (1)

Country Link
KR (1) KR20100002547A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967051A (en) * 2014-04-22 2014-08-06 北京工业大学 Arch scaffolding shearing force wall type double-layer three-span subway station structure and construction method
CN108277823A (en) * 2018-02-02 2018-07-13 北京市政建设集团有限责任公司 A kind of construction method of subway platform layer totality
CN108316344A (en) * 2018-02-02 2018-07-24 北京市政建设集团有限责任公司 A kind of construction method of subway station hall layer
CN108678011A (en) * 2018-06-07 2018-10-19 深圳市市政设计研究院有限公司 A kind of high hydraulic pressure of seabed depth earthing secretly buries tunnel structure across open cut greatly
CN108951701A (en) * 2018-07-26 2018-12-07 上海市机械施工集团有限公司 Wind pavilion and subway main body connection construction technique

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967051A (en) * 2014-04-22 2014-08-06 北京工业大学 Arch scaffolding shearing force wall type double-layer three-span subway station structure and construction method
CN103967051B (en) * 2014-04-22 2016-01-13 北京工业大学 A kind of bow member shearing wall-bilayer three is across the construction method of Metro Station Structure
CN108277823A (en) * 2018-02-02 2018-07-13 北京市政建设集团有限责任公司 A kind of construction method of subway platform layer totality
CN108316344A (en) * 2018-02-02 2018-07-24 北京市政建设集团有限责任公司 A kind of construction method of subway station hall layer
CN108316344B (en) * 2018-02-02 2020-01-07 北京市政建设集团有限责任公司 Construction method of subway station hall layer
CN108678011A (en) * 2018-06-07 2018-10-19 深圳市市政设计研究院有限公司 A kind of high hydraulic pressure of seabed depth earthing secretly buries tunnel structure across open cut greatly
CN108951701A (en) * 2018-07-26 2018-12-07 上海市机械施工集团有限公司 Wind pavilion and subway main body connection construction technique

Similar Documents

Publication Publication Date Title
CN109723085B (en) Deep foundation pit division construction rib wall support replacing structure and construction method thereof
CN110485473A (en) Rectangle active well and its construction method can be recycled in a kind of assembled that presetting detachable door opening
CN101250886B (en) Method for reinforcing masonry structure building base
CN107190752B (en) The design and construction method of rectangular section Row Piles Supporting Structure can be recycled in a kind of flexible compound antiseepage assembled
CN103758123A (en) Method for constructing protecting wall lining of cast-in-place manual hole digging pile
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN110593308B (en) Open excavation back pressure construction method for foundation pit of overhead operation subway underground comprehensive pipe gallery
KR20100002547A (en) The underground infrastructure construction work method for the bending moment reduction usingthe same, and infrastructure
CN109898521A (en) A kind of anchored pile supporting and construction method for foundation pit external corner
KR100313720B1 (en) Composite Underground Structure Construction Method
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR20090050042A (en) Connection method h pile and wide sheet pile
JP2000352296A (en) Method o constructing passage just under underground structure
CN111779004A (en) Construction process for fast supporting high slope of broken rock by strong unloading
KR20080025219A (en) Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall
KR101032408B1 (en) Method of reinforced earth retaining wall for cutting face through reinforcing execution and concrete block
CN106988337B (en) It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement
CN210827565U (en) Upper-span operation subway underground comprehensive pipe gallery foundation pit open excavation back pressure structure
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
CN102392459A (en) Construction method for straight manhole
KR100432782B1 (en) Supporting structure for tunnel and underground tunnel construction method using the same
CN111733855A (en) Construction method of underground continuous wall and underground continuous wall
CN110485471A (en) It is a kind of sliding rear by the recyclable rectangle active well of the integrated assembled of wall and its construction method
KR100637899B1 (en) Pier foundation temporarily structure and method for constructing it
CN109083125A (en) Temporary drainage ditch construction method under the conditions of a kind of subgrade

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E601 Decision to refuse application