KR20080062484A - Equal plastering for facilities and equalizing plaster reinforcement method using the same - Google Patents

Equal plastering for facilities and equalizing plaster reinforcement method using the same Download PDF

Info

Publication number
KR20080062484A
KR20080062484A KR1020060138361A KR20060138361A KR20080062484A KR 20080062484 A KR20080062484 A KR 20080062484A KR 1020060138361 A KR1020060138361 A KR 1020060138361A KR 20060138361 A KR20060138361 A KR 20060138361A KR 20080062484 A KR20080062484 A KR 20080062484A
Authority
KR
South Korea
Prior art keywords
reinforcement
uniform thickness
plastering
spacer
trowel
Prior art date
Application number
KR1020060138361A
Other languages
Korean (ko)
Inventor
유정식
Original Assignee
유정식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유정식 filed Critical 유정식
Priority to KR1020060138361A priority Critical patent/KR20080062484A/en
Publication of KR20080062484A publication Critical patent/KR20080062484A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/16Implements for after-treatment of plaster or the like before it has hardened or dried, e.g. smoothing-tools, profile trowels
    • E04F21/161Trowels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Abstract

The present invention relates to a uniform plastering material and a uniform plastering reinforcement method using the same, in order to solve the problem that the plastering surface is not smooth and the plastering thickness is uneven, the uniform thickness by pressing the outer surface of the uniform thickness spacer and the uniform thickness spacer A combination of spacing trowels was used to construct equalizers for the facilities.

As an embodiment using the equalizer for the facility, after fixing the uniform thickness spacer according to the shape of the structure member of the facility to be repaired, the primer is applied, and the outer surface of the plurality of uniform thickness spacers is rubbed with a trowel for uniform thickness spacer. Plaster and harden at the height of the uniform thickness spacer, remove the uniform thickness spacer, apply primer in the demolition section, rub the inner filling reinforcement with a trowel for uniform thickness spacer, finish the plastering work, and then apply the finish coating material. A plaster reinforcement method was constructed.

In addition, the primer is applied in the removal of the equal thickness spacer and the reinforcement is inserted and inserted to complete the plastering work.In the case of the square facility or the circular facility, the spiral reinforcement can be used evenly and smoothly instead of the reinforcement. The facility was constructed to enhance the quality and workability by reinforcing the facilities.

Description

Equal plastering for facilities and equalizing plaster reinforcement method using the same

1 is a conceptual view of the present invention applied to a planar facility including the lower and side portions of the bridge.

2 is a conceptual diagram applying the present invention to a square facility including a culvert;

Figure 3 is a conceptual diagram applying the present invention to a curved facility including a tunnel.

4 is a conceptual diagram applying the present invention to a circular facility including a pipeline.

FIG. 5 is a cross-sectional view taken along AA of FIG. 1, BB of FIG. 2, CC of FIG. 3, and DD of FIG. 4, and a reinforcement design thickness of a reinforcing reinforcement designed after applying a primer to a base surface of a structural member having an equal thickness spacer is installed. Some cross-sectional conceptual view of the state filled with above.

FIG. 6 is a cross-sectional conceptual view of a state in which a part of the plasterer is smoothly rubbed with a trowel for uniform thickness spacers so as to contact the outer surfaces of the plurality of uniform thickness spacers in the state of FIG. 5.

7 is a cross-sectional view of a state in which a part of the plastering operation is smoothly carried out by rubbing with the trowel for uniform thickness spacer in contact with the outer surface of another even thickness spacer so as to overlap with the edge portion where the previous plastering work is completed in the state of FIG. 6. Conceptual diagram.

8 is a cross-sectional conceptual view of the last and current plastering work completed in the state of FIG.

Figure 9 is a cross-sectional conceptual view of the primer applied after removing the uniform thickness spacer in the state of FIG.

10 is a cross-sectional conceptual view of a state in which smooth plastering is performed by filling an inner filling reinforcement on the primer in the even-thickness spacer removal part of FIG. 9 more than a plastering reinforcement design thickness and then rubbing with a trowel for uniform-thickness spacer.

FIG. 11 is a cross-sectional conceptual view of a state in which a finish coating material is applied onto a finisher after finishing filling by filling the filling plastering material of FIG. 10; FIG.

12 is a cross-sectional conceptual view of a state in which a reinforcing bar is inserted into an even thickness spacer demolition part coated with a primer after removing the even thickness spacer of FIG. 9;

FIG. 13 is a cross-sectional conceptual view of a state in which the finish coating material is finished after filling and filling the filling filler in the uniform thickness spacer removal part around the reinforcing bar in the state of FIG.

14 is an enlarged cross-sectional conceptual view showing an adhesive portion of a uniform thickness spacer joint;

15 is an enlarged cross-sectional conceptual view of a state where an overlapping portion of a rebar is overlapped with a binding line.

Fig. 16 is a conceptual view of the case where the spiral uniform thickness spacer is installed in a circular facility as another embodiment of the uniform thickness spacer.

FIG. 17 is a conceptual view illustrating a case in which a spiral rebar is installed in a circular facility as another embodiment of the rebar; FIG.

* Explanation of symbols for main parts of the drawings

1: Plane facility 3: Structure member

5: reinforcement material 7: square facility

9: curved facility 11: circular facility

13: disheveled stiffener 15: plastering stiffener

17: Uniform thickness spacer 19, 19 ': Trowel for uniform thickness spacer

21, 21 ': Plastering member 23, 23': Handle

25: equal thickness spacer removal 27, 27 ': primer

29, 29 ': filling material 31, 31': finish coating material

33: reinforcing bar 35: adhesive portion

37: overlapping part 39: the binding line

41: spiral equal thickness spacer 43: spiral rebar

The present invention relates to an equal plastering facility and an equal plastering reinforcement method using the same, a flat facility including the lower and side portions of the bridge, a angular facility including a culvert and a waterway, a curved facility including a tunnel, a circular including a pipeline The entire facility including the facility was applied.

In the past, when repairing or reinforcing a facility, an experienced cementer directly uses an ordinary trowel using inorganic cement mortar or organic resin, and sprays cement mortar or resin on the surface to be repaired by spraying. A skilled plasterer may perform the plastering work using a conventional trowel directly. These methods commonly require that the degree of plastering at the bottom of the trowel and the pressure adjustment applied to the trowel depend only on the skill of the plasterer. In addition, there is no choice but to make a different surface every time, which inevitably leads to trowel marks, which not only reduces the flatness of the surface but also makes the thickness of the plaster uniform, so that the amount of material used is not constant or the strength reinforcement is not carried out as planned. The problem is that It was a situation.

In addition, in the case of the uniform thickness plastering trowel, which is improved by attaching a blade of a predetermined height to the planned plastering thickness on the base surface of the trowel for uniform plastering, the cement mortar adheres easily around the blade. In the process of removing the marks, there was a problem that the workability and quality were deteriorated, such as uneven thickness of plastering. On the other hand, there is a method of fixing the reinforcement to the structure to be reinforced in the conventional reinforcement method after the reinforcement by cement mortar or resin, but in the process of fixing the reinforcement to the structure to be reinforced, it is fixed by fixing the anchor after drilling In addition to structural damage to the facility, and after performing a manual plastering or spraying, the trowel is finally used to perform ordinary plastering work. Therefore, the plastering angle of the plasterer's bottom and the pressure adjustment applied to the trowel are applied only to the plasterer. Not only have to rely on the skill of the worker but also different every time, because the inevitable trowel marks inevitably had a problem that the finish is not smooth.

In addition, there is a method of attaching a sheet-type reinforcement containing glass fiber or carbon fiber as an adhesive material and then plastering it with cement mortar or resin in the conventional facility reinforcement method, but using a trowel after hand plastering or spraying In the end, the general plastering process is performed. Therefore, the plastering angle of the trowel holder and the pressure adjustment applied to the trowel is not only dependent on the skill of the plasterer but also different every time. There was no problem that the trowel marks could not be made and the beauty surface was not finished smoothly.

In particular, in the case of sewage facilities including sewer pipes or culverts, it is difficult to improve the excavation during the maintenance process, so non-excavation repair reinforcement is performed to repair the inner surface of the sewage structure without digging the ground. Since a large amount of sewage flows at one time, the surface of the unexcavated repair reinforcement inner surface is as smooth as FRP or plastic surface to secure the maximum passage surface. Repair reinforcement can be activated, but in the conventional method of plastering, the plastering angle of the trowel floor and the pressure adjustment applied to the trowel is not only dependent on the skill of the plasterer but also different every time. Inevitably, trowel marks will inevitably appear on the surface. There was a problem that the use of the repair method of the refining method is limited.

In order to solve the problem that the plastering surface is not smooth and the plastering thickness is uneven as described above, the present invention is used to attach to the base surface of the structure member of the repaired facility or to open and secure it, and the height corresponding to the predetermined width and the reinforcement design thickness. A plurality of uniform thickness spacers, which are temporary materials of linear cross-section, and the pressing force applied to the trowel only on the outer surface of the uniform thickness spacers to prevent the pressure from acting on the disheveled reinforcement including cement mortar and resin. For this purpose, a uniform plastering material was constructed in combination with a trowel for uniform thickness spacers, which was a little longer than the interval between even thickness spacers.

As an embodiment using the equality plastering material, a plurality of uniform thickness spacers, which are temporary materials of linear cross section having a height and a predetermined width corresponding to the thickness of the reinforcement design space at predetermined intervals in the shape of the structural member of the facility to be repaired. After fixing the material, apply primer on the structure member, fill the dished reinforcement with the thickness of the equal thickness spacer more than the thickness, and then rub the outer surface of the multiple thickness spacers with the trowel for uniform thickness spacer which is longer than the distance between the uniform thickness spacers. Plaster the dished reinforcement smoothly at the height of the uniform thickness spacer, remove the uniform thickness spacer, apply primer to the inner surface of the equal thickness spacer demolition section where the equal thickness spacer is removed, and fill the filling reinforcement with the above plaster height. Rub it with a trowel for even thickness spacers After performing the operation section it was constructed facilities equivalents plastering reinforcement method to be closed by applying a finish coating on the reinforcement plastering.

In addition, as another embodiment using the same uniform plastering material, to remove the even thickness spacer and to apply the primer to the inner surface of the equal thickness spacer demolition of the equal thickness spacer removed and inserting the reinforcing bar after the reinforcement Fill the inner reinforcement material in the demolition part of the surrounding thicknesses with the thickness of the surrounding plaster reinforcement more than the height of the surrounding plastering material and rub it with a trowel for uniform thickness spacing to perform the plastering work. Configured.

On the other hand, instead of the equal thickness spacer and reinforcing bar, in the case of a square facility or a circular facility, it was configured to include a spiral equal thickness spacer and a spiral reinforcing bar.

As described above, the pressure applied by the plasterer to the trowel is applied only to the outer surfaces of the plurality of uniform thickness spacers, and the length is greater than the interval between the uniform thickness spacers so that no pressure is applied to the dished reinforcement material including cement mortar and resin. Plastering using a rather long uniform thickness spacing trowel makes it possible to reinforce the facility evenly and smoothly according to the design thickness of plastering to improve quality and workability.

With reference to the accompanying drawings with respect to the configuration of the present invention will be described in detail in the order of facilities equalizer, facilities equalizer reinforcement method embodiment.

According to the present invention, in order to solve the problem that the surface of the plaster is not smooth and the thickness of the plaster is uneven, the structural member 3 of the repaired facility, for example, the flat facility 1 including the lower and side portions of the bridge, is straight. In the case of a square facility (7) including a culvert and a waterway with a haunch part, in the case of a curved facility (9) in consideration of the shape of the haunch, a circular facility including a curved shape and a pipeline in consideration of the curvature of the curved member In the case of (11), it is manufactured in a circular shape and used by attaching or detaching a conventional attachment material detachable to the inner surface of the structural member 3 to be reinforced, and having a predetermined width and raising the height corresponding to the design thickness of the plastering reinforcement. On the premise of having a shape, the structure to facilitate the removal of the uniform thickness spacer 17 from the plaster reinforcement 15 even after the plaster reinforcement 15 is cured A plasterer pushes and pushes the trowel only on the outer surfaces of a plurality of uniform thickness spacers 17 and linear equally spaced spacers 17 which are attached or fixed with a trapezoidal cross section on the base surface of the ashes 3. Trowels for even-thickness spacers (19, 19 ') somewhat longer in length than the gaps between the evenly-spaced spacers (17) in order to allow pressure to act and to prevent pressure from being applied to the dished reinforcement (13) containing cement mortar and resin at all. ) And evenly spaced trowels (19, 19 ') have a single or multiple handles (top or side) of conventional plate or rod-shaped plastering members (21, 21'). 23, 23 ') is configured to run.

One embodiment using the equal amount of plastering materials described in the process order is as follows.

A plurality of uniform thickness spacers 17 including a plastic material having a linear cross section having a height corresponding to a plaster reinforcement design thickness at predetermined intervals in the shape of the structural member 3 of the facility to be repaired use a conventional attachment material. It is fixed to the base surface of the structural member 3 in the form of a temporary member by attaching or spreading.

The primer 27 is applied to the base surface of the structure member 3 using a conventional brush or a spraying equipment.

On the coated surface of the uniform thickness spacer 17 and the primer 27, a dished reinforcement 13 containing a conventional cement mortar or resin is filled to the height of the equal thickness spacer 17 or more.

Evenly spaced spacing member 13 by rubbing the outer surface of the two or more uniform thickness spacers 17 with a trowel 19 for uniform thickness spacers longer in length than the gap between the uniform thickness spacers 17. Plastering smoothly to the height of (17) to sequentially plaster so that some edge area plastered at this time overlaps some edge area plastered last time to cure the plaster reinforcement (15).

The uniform thickness spacer 17 is removed and the primer 27 is applied to the inner surface of the uniform thickness spacer removal part 25 from which the uniform thickness spacer 17 is removed.

Plastering work by filling the inner filling reinforcement (29) on the coating surface of the primer 27 on the inner surface of the uniform thickness spacer removal section 25 more than the height of the surrounding plaster reinforcement (15) with a trowel for uniform thickness spacer (19 ') The curing of the plastering reinforcement 15 is performed.

The facility uniform plaster reinforcement method was configured to finish by applying the finish coating material 31 on the cured plaster reinforcement (15).

In addition, when another embodiment using the equality of the installation material described in the process order as follows.

Plastering work by filling the inner filling reinforcement (29) on the coating surface of the primer 27 on the inner surface of the uniform thickness spacer removal section 25 more than the height of the surrounding plaster reinforcement (15) with a trowel for uniform thickness spacer (19 ') The process of curing the plastering reinforcement 15 is performed by reinforcing bars including conventional reinforcing bars, FRP rods, and resin rods on the application surface of the primer 27 on the inner surface of the uniform thickness spacer removal section 25 ( 33) and further including the filling material in the uniform thickness spacer demolition section 25 around the reinforcing bar (33) to fill the reinforcing material (29) more than the height of the surrounding plaster reinforcement (15) trowel for uniform thickness spacer (19) ') To perform the plastering work to configure the process of curing the plastering reinforcement (15).

Here, in the case of the square facility 7 or the circular facility 11 in the process of inserting the reinforcing bar 33 on the primer 27 applied surface of the inner surface of the thickness spacer removal section 25, the rectangular or circular constrained shape Therefore, the overlapped portion in the open state can be fixed by overlapping the conventional bundling line (39), so there is no need for a separate fixing means, but in the case of the planar facility (1) including the lower portion of the bridge is not separately shown in the drawings. It was comprised so that it may fix using the adhesive material containing a fastened cement mortar conventionally at the predetermined | prescribed location of the reinforcing bar 33.

On the other hand, in the case of the square facility (7) or the circular facility (11) instead of the uniform thickness spacer 17, the spiral equal thickness spacer 41 is also included in the scope of the present invention, and used instead of the reinforcement (33) Spiral reinforcing bar 43 was also configured to be used within the scope of the present invention.

In the construction process, the joint portion of the uniform thickness spacer 17 has an adhesive portion 35 connected using a conventional adhesive material, and the overlapping portion 37 of the reinforcing bar 33 uses a conventional binding line 39. It was allowed to be layered.

As described above, according to the present invention, the pressure applied by the plasterer to the trowel is applied only to the outer surfaces of the plurality of uniform thickness spacers, and evenly spaced thickness so that no pressure acts on the dished reinforcement containing cement mortar and resin. Plastering with uniform thickness spacing trowel slightly longer than the spacing between ashes improves quality and workability by reinforcing the facilities evenly and smoothly according to the design thickness of the plastering reinforcement, and when using more reinforcing bars or spiral reinforcing bars. In addition, the strength is further increased, and the effect of further improving the quality, including workability, is expected.

Claims (3)

In plaster reinforcement of facilities, A plurality of uniform thickness spacers of linear cross section having a height corresponding to the thickness of the plastering reinforcement design, Equal plastering material, characterized in that consisting of a trowel for the uniform thickness spacing material longer than the interval between the even thickness spacing material. In plaster reinforcement of facilities, Attaching or spreading a plurality of uniform thickness spacers to fix the surface of the structure, Applying a primer to the base surface of the structure; Filling the reinforcing material scattered on the primer applied to the uniform thickness spacer and the base surface of the structure to a height greater than or equal to the thickness spacer; The outer surface of the plurality of even thickness spacers was rubbed with a trowel for equal thickness spacers longer than the distance between the equal thickness spacers, and the displaced reinforcement was laid at the height of the equal thickness spacers, and some edge areas plastered at this time were partially plastered. Curing the plaster reinforcement by sequentially plastering to overlap the edge area; Removing the uniform thickness spacer and applying a primer to an inner surface of the uniform thickness spacer removal portion; A process of curing the plaster reinforcement by filling the filling material on the primer-coated surface of the inner surface of the uniform thickness spacer demolition part more than the height of the surrounding plaster reinforcement and rubbing it with a trowel for uniform thickness spacer; Equalizing plaster reinforcement method for the facility, characterized in that the process consisting of applying a finish coating material on the cured plastering reinforcement. The method of claim 2, The process of hardening plastering reinforcement by filling the reinforcement material on the primer coating surface of the inner surface of the equal thickness spacer demolition part more than the height of the surrounding plaster reinforcement by rubbing it with a trowel for uniform thickness spacer material to harden the reinforcement member of the uniform thickness spacer Plaster reinforcement is further included on the inner surface of the primer coating, and then the inside of the reinforcement with equal thickness spacing material is filled in the reinforcement to fill the reinforcement above the height of the surrounding reinforcement and rub with a trowel for uniform thickness spacing to perform plastering Uniformity reinforcement method for the facility, characterized in that consisting of a step of curing the process.
KR1020060138361A 2006-12-29 2006-12-29 Equal plastering for facilities and equalizing plaster reinforcement method using the same KR20080062484A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060138361A KR20080062484A (en) 2006-12-29 2006-12-29 Equal plastering for facilities and equalizing plaster reinforcement method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060138361A KR20080062484A (en) 2006-12-29 2006-12-29 Equal plastering for facilities and equalizing plaster reinforcement method using the same

Publications (1)

Publication Number Publication Date
KR20080062484A true KR20080062484A (en) 2008-07-03

Family

ID=39814612

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060138361A KR20080062484A (en) 2006-12-29 2006-12-29 Equal plastering for facilities and equalizing plaster reinforcement method using the same

Country Status (1)

Country Link
KR (1) KR20080062484A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018040116A (en) * 2016-09-06 2018-03-15 株式会社大林組 Repair method of concrete structure
KR20210128647A (en) * 2020-04-17 2021-10-27 아프로단디 주식회사 Construction method of heat insulation for outer wall of building
KR20220064031A (en) 2020-11-11 2022-05-18 유병안 When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks.

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018040116A (en) * 2016-09-06 2018-03-15 株式会社大林組 Repair method of concrete structure
KR20210128647A (en) * 2020-04-17 2021-10-27 아프로단디 주식회사 Construction method of heat insulation for outer wall of building
KR20220064031A (en) 2020-11-11 2022-05-18 유병안 When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks.

Similar Documents

Publication Publication Date Title
KR101014230B1 (en) Method for reparing and reinforcing outer wall of building
US9476212B2 (en) System and method for structural rehabilitation and enhancement
JP2014177766A (en) Method for constructing concrete precast floor slab for bridge
KR101732669B1 (en) Reinforcement member, concrete box reinforced with the same and the construction method thereof
KR100597175B1 (en) The FRP-BAR RECOVERING SYSTEM, Concrete cover restoration and FRPfibre reinforced polymer-bar filling up system
KR20080062484A (en) Equal plastering for facilities and equalizing plaster reinforcement method using the same
KR20100103038A (en) Unequal tubular uniform plastering apparatus and internal plastering method using the same
KR101310580B1 (en) Repair and reinforcement of large pipeline facilities including sewage culverts
KR20170126546A (en) The inner surface of pipelines medium and large repair and reinforcement
CN107989398B (en) Construction method for wall reinforcing structure
KR100935396B1 (en) An anticorrosion lining method for the inside of the welded pipe by using film coatting nonwoven felt-ring
KR101625468B1 (en) Expansion joint device for an aqueduct and construction method thereof
KR20050034978A (en) Waterproof, repair and reinforcement of flat, curved and rectangular structures
KR100937312B1 (en) The mold of non-dismantlement type and the process of structure for repair reinforcement therewith
KR20170040146A (en) Maintenance method of detachment area by using a trowel combined with a trowel and a trowel brush for repairing a concrete detachment site on a building wall
JP4978171B2 (en) New induced joint structure
CN114960978A (en) Waterproof method for concrete abutted seam without reserved embedded structure in reconstruction and extension structure
KR20220064031A (en) When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks.
KR101489227B1 (en) lining method of tunnels using fiber rods, polymer mortar and adhesion waterproofer
KR101493190B1 (en) Reinforcement method using reinforced bar
KR100820331B1 (en) Method of repairing manhole and material for repairing manhole
JP2005155273A (en) Repair/reinforcement method for narrow portions of old manhole
KR101428036B1 (en) Equivalent Equipments for Equipping Reinforcement and Reinforcement Method
JPH07233620A (en) Floor structure
KR20070079155A (en) Non-excavation dry attachment media and reinforcement spraying method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E601 Decision to refuse application
E801 Decision on dismissal of amendment