KR20080062484A - Equal plastering for facilities and equalizing plaster reinforcement method using the same - Google Patents
Equal plastering for facilities and equalizing plaster reinforcement method using the same Download PDFInfo
- Publication number
- KR20080062484A KR20080062484A KR1020060138361A KR20060138361A KR20080062484A KR 20080062484 A KR20080062484 A KR 20080062484A KR 1020060138361 A KR1020060138361 A KR 1020060138361A KR 20060138361 A KR20060138361 A KR 20060138361A KR 20080062484 A KR20080062484 A KR 20080062484A
- Authority
- KR
- South Korea
- Prior art keywords
- reinforcement
- uniform thickness
- plastering
- spacer
- trowel
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
- E04F21/02—Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
- E04F21/16—Implements for after-treatment of plaster or the like before it has hardened or dried, e.g. smoothing-tools, profile trowels
- E04F21/161—Trowels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
Abstract
The present invention relates to a uniform plastering material and a uniform plastering reinforcement method using the same, in order to solve the problem that the plastering surface is not smooth and the plastering thickness is uneven, the uniform thickness by pressing the outer surface of the uniform thickness spacer and the uniform thickness spacer A combination of spacing trowels was used to construct equalizers for the facilities.
As an embodiment using the equalizer for the facility, after fixing the uniform thickness spacer according to the shape of the structure member of the facility to be repaired, the primer is applied, and the outer surface of the plurality of uniform thickness spacers is rubbed with a trowel for uniform thickness spacer. Plaster and harden at the height of the uniform thickness spacer, remove the uniform thickness spacer, apply primer in the demolition section, rub the inner filling reinforcement with a trowel for uniform thickness spacer, finish the plastering work, and then apply the finish coating material. A plaster reinforcement method was constructed.
In addition, the primer is applied in the removal of the equal thickness spacer and the reinforcement is inserted and inserted to complete the plastering work.In the case of the square facility or the circular facility, the spiral reinforcement can be used evenly and smoothly instead of the reinforcement. The facility was constructed to enhance the quality and workability by reinforcing the facilities.
Description
1 is a conceptual view of the present invention applied to a planar facility including the lower and side portions of the bridge.
2 is a conceptual diagram applying the present invention to a square facility including a culvert;
Figure 3 is a conceptual diagram applying the present invention to a curved facility including a tunnel.
4 is a conceptual diagram applying the present invention to a circular facility including a pipeline.
FIG. 5 is a cross-sectional view taken along AA of FIG. 1, BB of FIG. 2, CC of FIG. 3, and DD of FIG. 4, and a reinforcement design thickness of a reinforcing reinforcement designed after applying a primer to a base surface of a structural member having an equal thickness spacer is installed. Some cross-sectional conceptual view of the state filled with above.
FIG. 6 is a cross-sectional conceptual view of a state in which a part of the plasterer is smoothly rubbed with a trowel for uniform thickness spacers so as to contact the outer surfaces of the plurality of uniform thickness spacers in the state of FIG. 5.
7 is a cross-sectional view of a state in which a part of the plastering operation is smoothly carried out by rubbing with the trowel for uniform thickness spacer in contact with the outer surface of another even thickness spacer so as to overlap with the edge portion where the previous plastering work is completed in the state of FIG. 6. Conceptual diagram.
8 is a cross-sectional conceptual view of the last and current plastering work completed in the state of FIG.
Figure 9 is a cross-sectional conceptual view of the primer applied after removing the uniform thickness spacer in the state of FIG.
10 is a cross-sectional conceptual view of a state in which smooth plastering is performed by filling an inner filling reinforcement on the primer in the even-thickness spacer removal part of FIG. 9 more than a plastering reinforcement design thickness and then rubbing with a trowel for uniform-thickness spacer.
FIG. 11 is a cross-sectional conceptual view of a state in which a finish coating material is applied onto a finisher after finishing filling by filling the filling plastering material of FIG. 10; FIG.
12 is a cross-sectional conceptual view of a state in which a reinforcing bar is inserted into an even thickness spacer demolition part coated with a primer after removing the even thickness spacer of FIG. 9;
FIG. 13 is a cross-sectional conceptual view of a state in which the finish coating material is finished after filling and filling the filling filler in the uniform thickness spacer removal part around the reinforcing bar in the state of FIG.
14 is an enlarged cross-sectional conceptual view showing an adhesive portion of a uniform thickness spacer joint;
15 is an enlarged cross-sectional conceptual view of a state where an overlapping portion of a rebar is overlapped with a binding line.
Fig. 16 is a conceptual view of the case where the spiral uniform thickness spacer is installed in a circular facility as another embodiment of the uniform thickness spacer.
FIG. 17 is a conceptual view illustrating a case in which a spiral rebar is installed in a circular facility as another embodiment of the rebar; FIG.
* Explanation of symbols for main parts of the drawings
1: Plane facility 3: Structure member
5: reinforcement material 7: square facility
9: curved facility 11: circular facility
13: disheveled stiffener 15: plastering stiffener
17:
21, 21 ': Plastering
25: equal
29, 29 ':
33: reinforcing bar 35: adhesive portion
37: overlapping part 39: the binding line
41: spiral equal thickness spacer 43: spiral rebar
The present invention relates to an equal plastering facility and an equal plastering reinforcement method using the same, a flat facility including the lower and side portions of the bridge, a angular facility including a culvert and a waterway, a curved facility including a tunnel, a circular including a pipeline The entire facility including the facility was applied.
In the past, when repairing or reinforcing a facility, an experienced cementer directly uses an ordinary trowel using inorganic cement mortar or organic resin, and sprays cement mortar or resin on the surface to be repaired by spraying. A skilled plasterer may perform the plastering work using a conventional trowel directly. These methods commonly require that the degree of plastering at the bottom of the trowel and the pressure adjustment applied to the trowel depend only on the skill of the plasterer. In addition, there is no choice but to make a different surface every time, which inevitably leads to trowel marks, which not only reduces the flatness of the surface but also makes the thickness of the plaster uniform, so that the amount of material used is not constant or the strength reinforcement is not carried out as planned. The problem is that It was a situation.
In addition, in the case of the uniform thickness plastering trowel, which is improved by attaching a blade of a predetermined height to the planned plastering thickness on the base surface of the trowel for uniform plastering, the cement mortar adheres easily around the blade. In the process of removing the marks, there was a problem that the workability and quality were deteriorated, such as uneven thickness of plastering. On the other hand, there is a method of fixing the reinforcement to the structure to be reinforced in the conventional reinforcement method after the reinforcement by cement mortar or resin, but in the process of fixing the reinforcement to the structure to be reinforced, it is fixed by fixing the anchor after drilling In addition to structural damage to the facility, and after performing a manual plastering or spraying, the trowel is finally used to perform ordinary plastering work. Therefore, the plastering angle of the plasterer's bottom and the pressure adjustment applied to the trowel are applied only to the plasterer. Not only have to rely on the skill of the worker but also different every time, because the inevitable trowel marks inevitably had a problem that the finish is not smooth.
In addition, there is a method of attaching a sheet-type reinforcement containing glass fiber or carbon fiber as an adhesive material and then plastering it with cement mortar or resin in the conventional facility reinforcement method, but using a trowel after hand plastering or spraying In the end, the general plastering process is performed. Therefore, the plastering angle of the trowel holder and the pressure adjustment applied to the trowel is not only dependent on the skill of the plasterer but also different every time. There was no problem that the trowel marks could not be made and the beauty surface was not finished smoothly.
In particular, in the case of sewage facilities including sewer pipes or culverts, it is difficult to improve the excavation during the maintenance process, so non-excavation repair reinforcement is performed to repair the inner surface of the sewage structure without digging the ground. Since a large amount of sewage flows at one time, the surface of the unexcavated repair reinforcement inner surface is as smooth as FRP or plastic surface to secure the maximum passage surface. Repair reinforcement can be activated, but in the conventional method of plastering, the plastering angle of the trowel floor and the pressure adjustment applied to the trowel is not only dependent on the skill of the plasterer but also different every time. Inevitably, trowel marks will inevitably appear on the surface. There was a problem that the use of the repair method of the refining method is limited.
In order to solve the problem that the plastering surface is not smooth and the plastering thickness is uneven as described above, the present invention is used to attach to the base surface of the structure member of the repaired facility or to open and secure it, and the height corresponding to the predetermined width and the reinforcement design thickness. A plurality of uniform thickness spacers, which are temporary materials of linear cross-section, and the pressing force applied to the trowel only on the outer surface of the uniform thickness spacers to prevent the pressure from acting on the disheveled reinforcement including cement mortar and resin. For this purpose, a uniform plastering material was constructed in combination with a trowel for uniform thickness spacers, which was a little longer than the interval between even thickness spacers.
As an embodiment using the equality plastering material, a plurality of uniform thickness spacers, which are temporary materials of linear cross section having a height and a predetermined width corresponding to the thickness of the reinforcement design space at predetermined intervals in the shape of the structural member of the facility to be repaired. After fixing the material, apply primer on the structure member, fill the dished reinforcement with the thickness of the equal thickness spacer more than the thickness, and then rub the outer surface of the multiple thickness spacers with the trowel for uniform thickness spacer which is longer than the distance between the uniform thickness spacers. Plaster the dished reinforcement smoothly at the height of the uniform thickness spacer, remove the uniform thickness spacer, apply primer to the inner surface of the equal thickness spacer demolition section where the equal thickness spacer is removed, and fill the filling reinforcement with the above plaster height. Rub it with a trowel for even thickness spacers After performing the operation section it was constructed facilities equivalents plastering reinforcement method to be closed by applying a finish coating on the reinforcement plastering.
In addition, as another embodiment using the same uniform plastering material, to remove the even thickness spacer and to apply the primer to the inner surface of the equal thickness spacer demolition of the equal thickness spacer removed and inserting the reinforcing bar after the reinforcement Fill the inner reinforcement material in the demolition part of the surrounding thicknesses with the thickness of the surrounding plaster reinforcement more than the height of the surrounding plastering material and rub it with a trowel for uniform thickness spacing to perform the plastering work. Configured.
On the other hand, instead of the equal thickness spacer and reinforcing bar, in the case of a square facility or a circular facility, it was configured to include a spiral equal thickness spacer and a spiral reinforcing bar.
As described above, the pressure applied by the plasterer to the trowel is applied only to the outer surfaces of the plurality of uniform thickness spacers, and the length is greater than the interval between the uniform thickness spacers so that no pressure is applied to the dished reinforcement material including cement mortar and resin. Plastering using a rather long uniform thickness spacing trowel makes it possible to reinforce the facility evenly and smoothly according to the design thickness of plastering to improve quality and workability.
With reference to the accompanying drawings with respect to the configuration of the present invention will be described in detail in the order of facilities equalizer, facilities equalizer reinforcement method embodiment.
According to the present invention, in order to solve the problem that the surface of the plaster is not smooth and the thickness of the plaster is uneven, the
One embodiment using the equal amount of plastering materials described in the process order is as follows.
A plurality of
The
On the coated surface of the
Evenly spaced spacing
The
Plastering work by filling the inner filling reinforcement (29) on the coating surface of the
The facility uniform plaster reinforcement method was configured to finish by applying the
In addition, when another embodiment using the equality of the installation material described in the process order as follows.
Plastering work by filling the inner filling reinforcement (29) on the coating surface of the
Here, in the case of the
On the other hand, in the case of the square facility (7) or the circular facility (11) instead of the
In the construction process, the joint portion of the
As described above, according to the present invention, the pressure applied by the plasterer to the trowel is applied only to the outer surfaces of the plurality of uniform thickness spacers, and evenly spaced thickness so that no pressure acts on the dished reinforcement containing cement mortar and resin. Plastering with uniform thickness spacing trowel slightly longer than the spacing between ashes improves quality and workability by reinforcing the facilities evenly and smoothly according to the design thickness of the plastering reinforcement, and when using more reinforcing bars or spiral reinforcing bars. In addition, the strength is further increased, and the effect of further improving the quality, including workability, is expected.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060138361A KR20080062484A (en) | 2006-12-29 | 2006-12-29 | Equal plastering for facilities and equalizing plaster reinforcement method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060138361A KR20080062484A (en) | 2006-12-29 | 2006-12-29 | Equal plastering for facilities and equalizing plaster reinforcement method using the same |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20080062484A true KR20080062484A (en) | 2008-07-03 |
Family
ID=39814612
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020060138361A KR20080062484A (en) | 2006-12-29 | 2006-12-29 | Equal plastering for facilities and equalizing plaster reinforcement method using the same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20080062484A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018040116A (en) * | 2016-09-06 | 2018-03-15 | 株式会社大林組 | Repair method of concrete structure |
KR20210128647A (en) * | 2020-04-17 | 2021-10-27 | 아프로단디 주식회사 | Construction method of heat insulation for outer wall of building |
KR20220064031A (en) | 2020-11-11 | 2022-05-18 | 유병안 | When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks. |
-
2006
- 2006-12-29 KR KR1020060138361A patent/KR20080062484A/en not_active Application Discontinuation
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018040116A (en) * | 2016-09-06 | 2018-03-15 | 株式会社大林組 | Repair method of concrete structure |
KR20210128647A (en) * | 2020-04-17 | 2021-10-27 | 아프로단디 주식회사 | Construction method of heat insulation for outer wall of building |
KR20220064031A (en) | 2020-11-11 | 2022-05-18 | 유병안 | When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks. |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101014230B1 (en) | Method for reparing and reinforcing outer wall of building | |
US9476212B2 (en) | System and method for structural rehabilitation and enhancement | |
JP2014177766A (en) | Method for constructing concrete precast floor slab for bridge | |
KR101732669B1 (en) | Reinforcement member, concrete box reinforced with the same and the construction method thereof | |
KR100597175B1 (en) | The FRP-BAR RECOVERING SYSTEM, Concrete cover restoration and FRPfibre reinforced polymer-bar filling up system | |
KR20080062484A (en) | Equal plastering for facilities and equalizing plaster reinforcement method using the same | |
KR20100103038A (en) | Unequal tubular uniform plastering apparatus and internal plastering method using the same | |
KR101310580B1 (en) | Repair and reinforcement of large pipeline facilities including sewage culverts | |
KR20170126546A (en) | The inner surface of pipelines medium and large repair and reinforcement | |
CN107989398B (en) | Construction method for wall reinforcing structure | |
KR100935396B1 (en) | An anticorrosion lining method for the inside of the welded pipe by using film coatting nonwoven felt-ring | |
KR101625468B1 (en) | Expansion joint device for an aqueduct and construction method thereof | |
KR20050034978A (en) | Waterproof, repair and reinforcement of flat, curved and rectangular structures | |
KR100937312B1 (en) | The mold of non-dismantlement type and the process of structure for repair reinforcement therewith | |
KR20170040146A (en) | Maintenance method of detachment area by using a trowel combined with a trowel and a trowel brush for repairing a concrete detachment site on a building wall | |
JP4978171B2 (en) | New induced joint structure | |
CN114960978A (en) | Waterproof method for concrete abutted seam without reserved embedded structure in reconstruction and extension structure | |
KR20220064031A (en) | When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks. | |
KR101489227B1 (en) | lining method of tunnels using fiber rods, polymer mortar and adhesion waterproofer | |
KR101493190B1 (en) | Reinforcement method using reinforced bar | |
KR100820331B1 (en) | Method of repairing manhole and material for repairing manhole | |
JP2005155273A (en) | Repair/reinforcement method for narrow portions of old manhole | |
KR101428036B1 (en) | Equivalent Equipments for Equipping Reinforcement and Reinforcement Method | |
JPH07233620A (en) | Floor structure | |
KR20070079155A (en) | Non-excavation dry attachment media and reinforcement spraying method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E90F | Notification of reason for final refusal | ||
E601 | Decision to refuse application | ||
E801 | Decision on dismissal of amendment |