KR101310580B1 - Repair and reinforcement of large pipeline facilities including sewage culverts - Google Patents

Repair and reinforcement of large pipeline facilities including sewage culverts Download PDF

Info

Publication number
KR101310580B1
KR101310580B1 KR1020130007253A KR20130007253A KR101310580B1 KR 101310580 B1 KR101310580 B1 KR 101310580B1 KR 1020130007253 A KR1020130007253 A KR 1020130007253A KR 20130007253 A KR20130007253 A KR 20130007253A KR 101310580 B1 KR101310580 B1 KR 101310580B1
Authority
KR
South Korea
Prior art keywords
reinforcement
large pipeline
wheel
repair
facility
Prior art date
Application number
KR1020130007253A
Other languages
Korean (ko)
Inventor
김정호
유정식
Original Assignee
(주)경동엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)경동엔지니어링 filed Critical (주)경동엔지니어링
Priority to KR1020130007253A priority Critical patent/KR101310580B1/en
Application granted granted Critical
Publication of KR101310580B1 publication Critical patent/KR101310580B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/13Geometrical or physical properties having at least a mesh portion
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0021Mortar

Abstract

PURPOSE: A repair and reinforcing method of a large pipe conduit facility including a sewage duct is provided to improve repairmen quality by performing reinforcement and repairmen while combining circulating inner water with a wheel attachment type inner water circulating pipe. CONSTITUTION: A repair and reinforcing method of a large pipe conduit facility including a sewage duct comprises as follows. Circulating the inner water is performed by using a wheel attachment type inner water circulating pipe and performing chipping of the large pipe conduit facility. A chipping unit is washed, and a wheel attachment type movable temporary plate is applied. An upper reinforcing member is mounted on an exterior of the wheel attachment type movable temporary plate. The upper reinforcing member and the wheel attachment type movable temporary plate are moved to a repair object position. After the upper reinforcing member and a lower reinforcing member are installed in the large pipe conduit facility, the primer and repairing mortar are placed. [Reference numerals] (AA) Circulating water inside; (BB) Chipping; (CC) Washing; (DD) Installing a movable installation board where wheels are attached; (EE) Mounting an upper reinforcing member; (FF) Move the upper reinforcing member and the installation board where wheels are attached; (GG) Installing the upper reinforcing member; (HH) Moving and installing a lower reinforcing member; (II) Covering a pipe for circulating water inside, which wheels are attached to, with a wheel cap; (JJ) Coating the members with primer; (KK) Placing repairing mortar; (LL) Curing the repairing mortar; (MM) Coating the members with a finishing coating material

Description

하수암거를 포함한 대형 관로 시설물 보수 보강공법{omitted}Repair and reinforcement of large pipeline facilities including sewage culverts

본 발명은 하수암거를 포함한 대형 관로 시설물 보수 보강공법에 관한 것으로, 더욱 상세하게는 하수암거, 수로를 포함한 대형 관로 시설물 내에서 바퀴 부착형 내부 물돌리기관을 통해 하수 또는 유수가 흐르는 상태에서 대형 관로 시설물이 노후화되거나 또는 특정 부위에 이상이 있는 경우 이를 내면에서 효율적으로 보수 보강할 수 있도록 발명한 것이다.The present invention relates to a reinforcement method for repairing large pipeline facilities including sewage culverts, and more specifically, a large pipeline in a state in which sewage or runoff flows through a wheel-mounted internal waterway engine in a large pipeline facility including sewage culverts and waterways. If the facility is aging or there is an abnormality in a specific site it was invented to efficiently repair and reinforce the inside.

일반적으로 하수암거, 수로를 포함한 대형 관로 시설물의 경우 주로 도심지의 도로 하부 등의 지하에 매설되어 있어서 지상 도로의 차량 통행을 제한하거나 보수 보강을 위하여 지상 도로에 물돌리기 호스를 포함한 가시설을 설치하는 것이 현실적으로 어려운 실정으로서 대형 관로 시설물이 노후화되거나 또는 특정 부위에 이상이 생기는 경우가 발생되어 이를 굴착하지 않고 내면에서 보수해야 되는 상황이 발생하게 된다.In general, large pipeline facilities including sewage culverts and waterways are usually buried underground, such as the lower part of urban roads. Therefore, it is advisable to install temporary facilities including water hoses on ground roads to limit vehicle traffic on ground roads or to reinforce repairs. As a situation that is difficult in reality, there are cases in which large pipeline facilities become obsolete or abnormalities occur in specific parts, and thus a situation that requires repairing from the inside without excavation occurs.

또한, 종래에는 하수암거, 수로를 포함한 대형 관로 시설물 내에서 물돌리기와 병행하여 보수 보강을 실시하는 경우에는 하수나 유수의 양도 비교적 많을뿐더러 흐름을 중단시킬 수 없어서 하수 암거 및 수로 바닥의 보수 보강시 종방향으로 2개의 부분으로 분리하여 물돌리기를 실시하면서 한쪽편의 보수 보강을 1차로 실시한 후에 2차로 다른 한쪽의 보수 보강을 실시할 수밖에 없고, 이로 인해 하수 또는 유수가 흐르는 상황하에서 불가피한 시공이음부의 발생으로 인하여 시공이음부의 품질이 저하됨은 물론 시공성도 저하되어 공사비도 증가하게 되는 문제점이 있는 실정이었다.In addition, in the past, when the water reinforcement is performed in parallel with the water running in a large pipeline facility including a sewage culvert and a water channel, the amount of sewage or running water is relatively high and the flow cannot be stopped. The water reinforcement of one side is performed firstly while the water revolving is separated into two parts in the longitudinal direction, and the other one must be reinforcement of the other side secondly. Due to the occurrence, the quality of the construction joints is deteriorated, as well as the workability is reduced, there is a problem that the construction cost increases.

한편, 종래에는 하수암거 및 수로의 상부와 하부를 구분하여 시공하는 경우에도 보강재를 포함한 관련 자재를 작업원이 낱개 또는 한 묶음 단위로 일일이 시점부에서 보수 보강 대상 지점까지 운반하여 시공함으로써 작업원이 상대적으로 많이 소요되어 시공성이 저하됨은 물론 공사비도 증가되는 문제점이 있는 실정이었다.Meanwhile, even when the sewage culvert and the upper and lower parts of the waterway are separately installed, the worker transports the related materials including the reinforcement material from the time point to the point of the reinforcement of the reinforcement one by one or in a bundle unit, thereby constructing the worker. Due to the relatively high cost of construction, as well as the construction cost was a problem that increases.

또한, 종래에는 하수암거 및 수로를 포함한 대형 관로 시설물의 노후화 정도를 감안하면 보수만 필요한 구간과 보강이 필요한 구간이 한 개의 현장 내에 혼재하여 있고, 보강이 필요한 구간에도 보강재의 종류를 현장 부위별 여건에 맞게 맞춤식으로 적용하는 것이 효율적이고 경제적임에도 불구하고 종래에는 일률적으로 보강재를 사용함으로써 비효율적이고 비경제적인 보수 보강이 실시되는 문제점이 있는 실정이었다.In addition, conventionally, considering only the degree of aging of large pipeline facilities including sewage culverts and waterways, sections requiring only repairs and sections requiring reinforcement are mixed in one site. Although it is efficient and economical to apply a custom fit according to the prior art, there has been a problem in that inefficient and inexpensive repair reinforcement is performed by uniformly using reinforcement materials.

본 발명은 이와 같은 종래의 제반 문제점을 해소하기 위하여 안출한 것으로, 하수암거 및 수로를 포함한 대형 관로 시설물의 하수 또는 유수가 흐르는 바닥면에는 상류부의 물막이 시점부터 계획된 보수 보강 구간 내의 종점까지 바퀴 부착형 내부 물돌리기관을 사용하여 내부 물돌리기를 병행하면서 보수 보강을 실시하도록 하여 보수 품질을 향상시키고, 시공성도 향상시키며, 공사비도 감소시키는데 그 목적이 있다.The present invention has been devised to solve such a conventional problem, the bottom surface of the sewage culverts and flowing water of large pipeline facilities including sewage culverts and waterways flowing on the bottom surface of the upstream to the end point within the planned maintenance reinforcement section The purpose is to improve the quality of repair, improve the constructability, and reduce the cost of construction by performing the internal reinforcement while performing internal reinforcement by using the internal divert engine.

또한, 하수암거 및 수로를 포함한 대형 관로 시설물의 상부와 하부의 보강재 설치를 별도로 구분하여 상부 시공시에는 바퀴 부착형 이동식 가설대를 사용하여 견인식 또는 추력식 중에서 한가지로 이동시켜 인접한 대형 관로 시설물의 내면에 인체공학적으로 상부 보강재의 운반거리를 감소시켜 설치하고, 하부 시공시에는 바퀴 부착형 내부 물돌리기관을 사용하면서 보강재의 이동 설치를 위한 2개 이상의 별도로 설치된 견인용 레일을 종방향으로 설치하여 물돌리기가 설치된 상태 하에서 하부 보강재를 견인식 또는 추력식 중에서 한가지와 미끄럼식을 혼용하여 이동시킨 후 제자리에서 설치할 수 있도록 하여 시공함으로써 하부 보강재의 운반거리를 감소시켜 설치함은 물론 소요 작업원의 수가 상대적으로 적게 소요되어 보수 품질을 향상시킴은 물론 시공성도 향상시키며, 공사비도 감소시키는데 그 목적이 있다.In addition, separate the installation of the reinforcement of the upper and lower parts of large pipeline facilities including sewage culverts and waterways, and when using the upper construction, move to one of the traction type or thrust type by using a wheel-mounted mobile temporary platform to the inner surface of the adjacent large pipeline facilities Ergonomically reduce the transport distance of the upper reinforcement, and install the two or more separately installed towing rails for the mobile installation of the reinforcement in the longitudinal direction when using the wheel-mounted internal pivoting engine for the lower construction. Under the condition of turning, the lower reinforcement can be installed by moving one of the traction or thrust type and sliding type to install it in place. It takes less time, improving repair quality Ron workability also improves, sikineunde reduced cost of construction it is an object.

한편, 하수암거 및 수로를 포함한 대형 관로 시설물의 상태를 감안하여 보수만 필요한 구간과 보강이 필요한 구간으로 구분하여 보수만 필요한 구간에는 보강재의 사용을 생략하여 구성함으로써 효율적이고 경제적인 보수 보강을 실시하는데 그 목적이 있다.On the other hand, considering the condition of large pipeline facilities including sewage culverts and waterways, it is divided into sections requiring only repair and sections requiring reinforcement. The purpose is.

또한, 보강이 필요한 구간에도 보강재의 종류를 현장 부위별 여건에 맞게 맞춤식으로 세분하여 사용함으로써 효율적이고 경제적인 보수 보강을 실시하는데 그 목적이 있다.In addition, the purpose of the reinforcement for the efficient and economical maintenance by using the subdivision of the reinforcement in the customized section to suit the conditions for each site site even in the section that needs reinforcement.

상기한 문제점을 해결하기 위한 본 발명은, 하수암거 및 수로를 포함한 하수 또는 유수가 흐르는 대형 관로 시설물의 보수 보강에 있어서, 바퀴 부착형 내부 물돌리기관을 사용하여 내부 물돌리기를 실시하는 공정과, 상기 바퀴 부착형 내부 물돌리기관을 사용하여 내부 물돌리기를 실시하는 공정 후 대형 관로 시설물의 치핑을 실시하는 공정과, 상기 대형 관로 시설물의 치핑을 실시하는 공정 후 치핑부를 세척하는 공정과, 상기 치핑부를 세척하는 공정 후 상부 시공시에는 바퀴 부착형 이동식 가설대를 설치하는 공정과, 상기 상부 시공시에는 바퀴 부착형 이동식 가설대를 설치하는 공정 후 바퀴 부착형 이동식 가설대의 외면에 상부 보강재를 거치하는 공정과, 상기 바퀴 부착형 이동식 가설대의 외면에 상부 보강재를 거치하는 공정 후 상부 보강재와 바퀴 부착형 이동식 가설대를 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시키는 공정과, 상기 상부 보강재와 바퀴 부착형 이동식 가설대를 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시키는 공정 후 대형 관로 시설물의 상부에 상부 보강재를 설치하는 공정과, 상기 대형 관로 시설물의 상부에 상부 보강재를 설치하는 공정 후 대형 관로 시설물의 하부에 하부 보강재를 이동 설치하는 공정과, 상기 대형 관로 시설물의 하부에 하부 보강재를 이동 설치하는 공정 후 바퀴 부착형 내부 물돌리기관의 바퀴용 캡을 씌우는 공정과, 상기 바퀴 부착형 내부 물돌리기관의 바퀴용 캡을 씌우는 공정 후 대형 관로 시설물의 내면에 프라이머를 도포하는 공정과, 상기 대형 관로 시설물의 내면에 프라이머를 도포하는 공정 후 프라이머 상에 보수 몰탈을 타설하는 공정과, 상기 프라이머상에 보수 몰탈을 타설하는 공정 후 보수 몰탈을 양생시키는 공정과, 상기 보수 몰탈을 양생시키는 공정 후 양생된 보수 몰탈 상에 마감코팅제를 도포하는 공정으로 구성된 것을 특징으로 한다.The present invention for solving the above problems, in the repair and reinforcement of the large pipeline facility flowing sewage or runoff, including sewage culverts and waterways, the process of performing internal water turning using a wheel-mounted internal waterway engine, Performing chipping of the large pipeline facility after the step of performing the internal spin using the wheel-mounted internal spinneret, and washing the chipping unit after the chipping of the large pipeline facility, and the chipping. When the upper construction after the process of washing the part, the process of installing a wheel-mounted removable temporary stand, and the process of installing the wheel-mounted removable temporary stand during the upper construction is to mount the upper reinforcement on the outer surface of the wheel-mounted movable temporary tent Upper reinforcing material after the process and the step of mounting the upper reinforcing material on the outer surface of the wheel-mounted movable temporary placing table After the process of moving the wheel-mounted mobile temporary platform to the maintenance target position in one of traction or thrust, and the process of moving the upper reinforcement and the wheel-mounted mobile temporary platform to the repair target position in one of the traction or thrust. Installing the upper reinforcement on the upper part of the pipeline facility, and installing the upper reinforcement on the upper part of the large pipeline facility, moving the lower reinforcement to the lower part of the large pipeline facility, and lowering the lower part of the large pipeline facility. After the process of moving and installing the reinforcing material, the process of covering the wheel cap of the wheel-mounted internal water wheel engine and the process of covering the wheel cap of the wheel-mounted internal water wheel engine after applying the primer to the inner surface of the large pipeline facility And, after the process of applying a primer on the inner surface of the large pipeline facility A process of pouring a repair mortar on the emmer, a process of curing the repair mortar after the process of pouring the repair mortar on the primer, and a process of applying a finish coating agent on the cured repair mortar after the process of curing the repair mortar. Characterized in that consisting of.

또한, 대형 관로 시설물의 보수 구간에는 상기 상부 보강재와 하부 보강재의 사용을 각각 삭제하여 구성된 것을 특징으로 한다.In addition, the repair section of the large pipeline facility is characterized in that the configuration by removing the use of the upper reinforcement and the lower reinforcement, respectively.

한편, 상기 상부 보강재와 하부 보강재는 각각 선재형 보강재로 구성된 것을 특징으로 한다.On the other hand, the upper reinforcement and the lower reinforcement is characterized in that each consisting of a wire-shaped reinforcement.

또한, 상기 선재형 보강재는 망형 보강재로 치환하여 구성된 것을 특징으로 한다.In addition, the wire rod reinforcement is characterized in that configured by replacing with a mesh reinforcement.

한편, 상기 선재형 보강재는 복합형 보강재로 치환하여 구성된 것을 특징으로 한다.On the other hand, the wire rod reinforcement is characterized in that configured by replacing the composite reinforcement.

이상에서 설명한 바와 같이 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법에 의하면, 하수암거 및 수로를 포함한 대형 관로 시설물의 하수 또는 유수가 흐르는 바닥면에는 상류부의 물막이 시점부터 계획된 보수 보강 구간 내의 종점까지 바퀴 부착형 내부 물돌리기관을 사용하여 내부 물돌리기를 병행하면서 보수 보강을 실시하도록 하여 보수 품질을 향상시키고, 시공성도 향상시키며, 공사비도 감소시키는 매우 유용한 발명인 것이다.As described above, according to the repairing and reinforcing method of a large pipeline facility including a sewage culvert according to the present invention, the end point within the planned reinforcement reinforcement section from the water barrier part of the upstream portion on the bottom surface of the sewage culvert and the flowing water of the large pipeline facility including the sewage culvert and the water channel. It is a very useful invention that improves the quality of repair, improves the constructability, and reduces the construction cost by performing repair reinforcement while using the internal spinneret attached to the wheel.

또한, 하수암거 및 수로를 포함한 대형 관로 시설물의 상부와 하부의 보강재 설치를 별도로 구분하여 상부 시공시에는 바퀴 부착형 이동식 가설대를 사용하여 견인식 또는 추력식 중에서 한가지로 이동시켜 인접한 대형 관로 시설물의 내면에 인체공학적으로 보강재의 운반거리를 감소시켜 설치하고, 하부 시공시에는 바퀴 부착형 내부 물돌리기관을 사용하면서 보강재의 이동 설치를 위한 2개 이상의 별도로 설치된 견인용 레일을 종방향으로 설치하여 물돌리기가 설치된 상태 하에서 보강재를 견인식 또는 추력식 중에서 한가지와 미끄럼식을 혼용하여 이동시킨 후 제자리에서 설치할 수 있도록 하여 시공함으로써 하부 보강재의 운반거리를 감소시켜 설치함은 물론 소요 작업원의 수가 상대적으로 적게 소요되어 보수 품질을 향상시킴은 물론 시공성도 향상시키며, 공사비도 감소시키는 매우 유용한 발명인 것이다.In addition, separate the installation of the reinforcement of the upper and lower parts of large pipeline facilities including sewage culverts and waterways, and when using the upper construction, move to one of the traction type or thrust type by using a wheel-mounted mobile temporary platform to the inner surface of the adjacent large pipeline facilities Ergonomically reduce the transport distance of the reinforcement and install it at the bottom of the installation by using two wheeled internal throttle engines to install two or more separately installed towing rails for longitudinal movement of the reinforcement. Under the installed condition, the reinforcement can be installed by moving one of the traction or thrust type and sliding type, and then installed in place to reduce the transport distance of the lower reinforcement and install relatively less number of workers. To improve the quality of repair Also it improves, which is very useful inventions construction cost is reduced.

한편, 하수암거 및 수로를 포함한 대형 관로 시설물의 상태를 감안하여 보수만 필요한 구간과 보강이 필요한 구간으로 구분하여 보수만 필요한 구간에는 보강재의 사용을 삭제하여 구성함으로써 효율적이고 경제적인 보수 보강을 실시하는 매우 유용한 발명인 것이다.On the other hand, considering the condition of large pipeline facilities including sewage culverts and waterways, it is divided into sections requiring only repair and sections requiring reinforcement. It is a very useful invention.

또한, 보강이 필요한 구간에도 보강재의 종류를 현장 부위별 여건에 맞게 맞춤식으로 세분하여 사용함으로써 효율적이고 경제적인 보수 보강을 실시하는 매우 유용한 발명인 것이다.In addition, it is a very useful invention to carry out efficient and economical maintenance reinforcement by using the subdivision of the reinforcement in a customized manner according to the site-specific conditions even in the section that requires reinforcement.

도 1은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 상부 단면도.
도 2는 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 하부 단면도.
도 3은 도 1의 B, B' 에 대한 상세도.
도 4는 도 1의 A에 대한 상세도.
도 5는 도 2의 C에 대한 상세도.
도 6은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 보수 보강 후 단면도.
도 7은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 상부 보강재 단면도.
도 8은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 하부 보강재 단면도.
도 9는 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 D-D 및 D' -D' 에 따른 단면도로서 제 1 및 2 실시예의 배열도.
도 10은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 D-D 및 D' -D' 에 따른 단면도로서 제 3 실시예의 배열도.
도 11은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 공정도.
1 is a cross-sectional view of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention.
Figure 2 is a bottom cross-sectional view of the repair and reinforcement method of large pipelines including sewage culvert of the present invention.
3 is a detailed view of B, B 'of FIG.
4 is a detailed view of A of FIG. 1.
FIG. 5 is a detailed view of C of FIG. 2; FIG.
Figure 6 is a cross-sectional view after the reinforcement of the repair and reinforcement method of large pipeline facilities including sewage culvert of the present invention.
Figure 7 is a cross-sectional view of the upper reinforcing material of the rehabilitation method for large pipeline facilities including sewage culvert of the present invention.
Figure 8 is a cross-sectional view of the lower reinforcing material of the repair construction reinforcement method for large pipelines including sewage culvert of the present invention.
9 is a cross-sectional view according to DD and D'-D 'of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention.
10 is a cross-sectional view according to DD and D'-D 'of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention.
Figure 11 is a process diagram of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention.

이하, 첨부된 도면을 참조하여 본 발명에 따른 바람직한 실시 예를 상세히 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 상부 단면도이고, 도 2는 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 하부 단면도이며, 도 3은 도 1의 B, B' 에 대한 상세도이고, 도 4는 도 1의 A에 대한 상세도이며, 도 5는 도 2의 C에 대한 상세도이고, 도 6은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 보수 보강 후 단면도이며, 도 7은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 상부 보강재 단면도이고, 도 8은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 하부 보강재 단면도이며, 도 9는 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 D-D 및 D' -D' 에 따른 단면도로서 제 1 및 2 실시예의 배열도이며, 도 10은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 D-D 및 D' -D' 에 따른 단면도로서 제 3 실시예의 배열도이고, 도 11은 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법의 공정도를 나타낸 것이다.1 is a cross-sectional view of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention, Figure 2 is a bottom cross-sectional view of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention, Figure 3 is B, B 'is a detailed view, FIG. 4 is a detailed view of A of FIG. 1, FIG. 5 is a detailed view of C of FIG. 2, and FIG. 6 is a repair and reinforcement method for repairing a large pipeline facility including a sewage culvert of the present invention. Figure 7 is a cross-sectional view after the reinforcement of the repair, and Fig. 7 is a cross-sectional view of the upper reinforcement of the large pipeline facility repair reinforcement method including the sewage culvert of the present invention, Figure 8 is a cross-sectional view of the bottom reinforcement of a large pipeline facility repair reinforcement method including the sewage culvert of the present invention. 9 is a cross-sectional view according to DD and D'-D 'of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention, and is an arrangement diagram of the first and second embodiments, and FIG. 10 includes a sewage culvert of the present invention. Sectional view according to D-D and D'-D 'of a large pipeline facility repair reinforcement method, and the arrangement of the third embodiment, Figure 11 shows a process diagram of a large pipeline facility repair reinforcement method including a sewage culvert of the present invention.

이에 따르면 도 1 내지 도 11에 도시된 바와 같이 하수암거를 포함한 대형 관로 시설물의 보수 보강에 있어서, 본 발명의 하수암거를 포함한 대형 관로 시설물 보수 보강공법은 대형 관로 시설물(1, 1' )의 하수 또는 유수(13)가 흐르는 바닥면에는 상류부의 물막이 시점부터 계획된 보수 보강 구간 내의 종점까지 바퀴 부착형 내부 물돌리기관(5)을 사용하여 내부 물돌리기를 실시하는 공정을 병행하면서 보수 보강을 실시하도록 도 1 내지 도 2에 도시된 바와 같이 대형 관로 시설물(1, 1' )을 각각 상부와 하부로 구분하여 시공하도록 구성하였다.According to this, in the repair reinforcement of a large pipeline facility including a sewage culvert, as shown in Figures 1 to 11, the reinforcement method for repairing a large pipeline facility including a sewage culvert of the present invention is the sewage of large pipeline facilities (1, 1 ') Alternatively, the reinforcement may be performed on the bottom surface of the flowing water 13 while performing an internal turning process using a wheel-mounted internal oscillation engine 5 from the upstream portion of the upstream portion to the end point in the planned maintenance reinforcement section. As shown in Fig. 1 to 2, large pipeline facilities (1, 1 ') were configured to be divided into the upper and lower constructions, respectively.

여기서, 상기 바퀴 부착형 내부 물돌리기관(5)은 통형관이나 개수로를 사용하며, 통형관이나 개수로의 하부에는 받침대(23)가 소정의 간격으로 설치되고 받침대(23)의 하단부에는 통상적인 바퀴(9)가 설치되도록 구성하여 바퀴(9)가 구르면서 바퀴 부착형 내부 물돌리기관(5)의 하부를 통해 하부 보강재(8)를 견인식 또는 추력식 중에서 한가지와 미끄럼식을 혼용하여 이동 설치할 수 있도록 하였다.In this case, the wheel-mounted inner circumferential engine (5) uses a tubular pipe or channel, the lower portion of the cylindrical tube or channel is provided with a pedestal 23 at a predetermined interval and the lower end of the pedestal 23 Inner wheel (9) is configured to be installed so that the wheel (9) rolls and moves the lower reinforcement (8) mixed with one of the traction or thrust type through the lower portion of the wheel-mounted internal spinneret (5) You can install it.

상기 바퀴 부착형 내부 물돌리기관(5)을 사용하여 내부 물돌리기를 실시하는 공정 후 대형 관로 시설물(1, 1' )이 노후화된 부분이나 파손 부위의 치핑부(32)를 대상으로 통상적인 브레이커나 워터젯을 사용하여 치핑을 실시하는 공정과, 상기 대형 관로 시설물(1, 1' )의 치핑을 실시하는 공정 후 치핑부(32)를 통상적인 고압세정장치를 사용하여 세척하는 공정으로 구성하였다.A conventional breaker for the chipping part 32 of an old part or a damaged part of a large pipeline facility (1, 1 ') after the process of performing the internal spin using the wheel-mounted internal spinneret (5). B was chipped using a water jet, and the chipping part 32 was washed with a conventional high pressure cleaning device after the chipping of the large pipeline facilities 1 and 1 '.

상기 치핑부(32)를 세척하는 공정 후 도 1에 도시된 바와 같이 대형 관로 시설물(1, 1' )의 상부 시공시에는 바퀴 부착형 이동식 가설대(3)를 설치하는 공정으로 구성하였다.After the process of washing the chipping portion 32, as shown in Figure 1 when the upper construction of the large pipeline facilities (1, 1 ') was configured to install a wheel-mounted removable temporary stand (3).

여기서, 상기 바퀴 부착형 이동식 가설대(3)는 도 1 및 도 3 내지 도 5와 같이 "

Figure 112013500241752-pat00012
" 자형으로 도시하였으나, 대형 관로 시설물(1, 1' )의 상부 형태에 따라서 형상은 변경하여 적용할 수 있도록 구성하였고, 통상적인 앵글이나 봉 또는 각형 빔 등으로 소정의 간격으로 배열하여 간격 사이의 틈새를 통해 상부 보강재(7)를 대형 관로 시설물(1, 1' )의 내면에 작업원이 통상적인 고정용 앵커를 사용하여 고정시키거나 또는 기존 철근에 결속선으로 묶어 고정시킬 수 있도록 하였으며, 대형 관로 시설물(1, 1' )의 단면 크기보다는 다소 작게 유격이 있도록 축소시켜 구성하되, "
Figure 112013500241752-pat00013
" 자형의 각각의 직선 부재의 일부분에는 길이 조정부(15)를 두어 끝단부에 관통공이 설치된 길이 조정캡(19) 내에 다수의 관통공이 설치된 길이 조정봉(17)이 삽입된 상태로 필요한 길이로 조정하여 맞춘 후 각각의 일치된 관통공 내에 고정나사(21)를 끼워 고정함으로써 바퀴 부착형 이동식 가설대(3)의 크기를 조정할 수 있도록 하였으며, 도면상에서 입체적인 형상의 도시는 생략하였으나 길이 방향으로 입체적인 형태를 유지하면서 설치 및 해체가 용이하여 반복 사용하도록 가설재로 제작하고 통상적인 고정나사로 조립하여 바퀴 부착형 이동식 가설대(3)를 구성하였고, 도면상에서 별도의 도시는 생략하였으나 필요시에는 바퀴 부착형 이동식 가설대(3)의 외면 양쪽 측면에는 대형 관로 시설물(1, 1' )과의 일정한 간격 유지를 위한 바퀴 부착형 간격 유지재를 소정의 간격으로 설치하도록 하였으며, 상기 바퀴 부착형 이동식 가설대(3) 상에 상부 보강재(7)를 얹은 상태로 대형 관로 시설물(1, 1' )의 보수 대상 위치로 이동시킬 수 있도록 하였다.Here, the wheel-mounted movable hypothesis 3 is as shown in FIGS. 1 and 3 to 5.
Figure 112013500241752-pat00012
"Although it is shown as a shape, according to the upper shape of the large pipeline facility (1, 1 ') is configured to be applied to change the shape, and arranged at a predetermined interval with a regular angle, rod or square beam, etc. Through the gap, the upper reinforcement (7) can be fixed to the inner surface of the large pipeline facility (1, 1 ') using a conventional anchoring anchor, or tied to the existing reinforcement bar by a binding line. It is configured to be reduced to have a smaller gap than the cross-sectional size of the pipeline facility (1, 1 '),
Figure 112013500241752-pat00013
"The length adjustment part 15 is provided in a part of each linear member of the shape, and it adjusts to the required length in the state which the length adjustment rod 17 in which many through-holes were installed in the length adjustment cap 19 in which the through-hole is installed in the end part is inserted, After fitting, the size of the wheel-mounted movable temporary placing table 3 can be adjusted by inserting and fixing the fixing screw 21 in each matched through hole. In the drawing, the three-dimensional shape is omitted, but the three-dimensional shape in the longitudinal direction is omitted. It is easy to install and dismantle while maintaining it, making it as a temporary material and assembling it with a conventional fixing screw to construct a wheel-mountable movable temporary stand (3). On both sides of the outer surface of the stand (3), wheel-mounted spacing is maintained to maintain a constant distance from the large pipeline facility (1, 1 ') The ashes were installed at predetermined intervals, and the upper reinforcement material 7 was placed on the wheel-mounted movable temporary stand 3 so that the ashes could be moved to the repaired position of the large pipeline facility 1, 1 ′. .

상기 대형 관로 시설물(1, 1' )의 상부 시공시에는 도 1에 도시된 바와 같이 바퀴 부착형 이동식 가설대(3)를 설치하는 공정 후 바퀴 부착형 이동식 가설대(3)의 외면에 상부 보강재(7)를 거치하는 공정으로 구성하였다.The upper reinforcement on the outer surface of the wheel-mounted mobile temporary platform 3 after the process of installing the wheel-mounted mobile temporary platform 3 as shown in Figure 1 during the upper construction of the large pipeline facility (1, 1 ') It consisted of the process of passing through (7).

상기 바퀴 부착형 이동식 가설대(3)의 외면에 상부 보강재(7)를 거치하는 공정 후 상부 보강재(7)와 바퀴 부착형 이동식 가설대(3)를 통상적인 밧줄이나 견인선을 사용하여 작업원이 인력으로 당기고 밀거나 또는 윈치를 사용하여 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시키는 공정과, 상기 상부 보강재(7)와 바퀴 부착형 이동식 가설대(3)를 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시키는 공정 후 대형 관로 시설물(1, 1' )의 상부에 상부 보강재(7)를 인접한 내면에 인체공학적으로 운반거리를 감소시켜 설치하는 공정으로 구성하였다.After the process of mounting the upper reinforcing material (7) on the outer surface of the wheel-mounted mobile temporary construction (3), the worker using a conventional rope or traction line the upper reinforcement (7) and the wheel-mounted mobile temporary platform (3) Pulling and pushing with this manpower or using a winch to move to the position to be repaired, either by traction or thrust, and by moving the upper reinforcement (7) and the wheel-mounted movable temporary platform (3) into one of traction or thrust. After the process of moving to the target location of the furnace repair, the upper reinforcing material (7) on the upper portion of the large pipeline facility (1, 1 ') was configured to the process of installing the ergonomically reduced transport distance on the adjacent inner surface.

여기서, 상기 상부 보강재(7)의 설치시에는 상부 보강재(7)로 사용되는 선재형 보강재(27)의 경우 간격 유지를 위한 배력근을 소정의 간격으로 고정 설치하는 경우도 본 선재형 보강재(27)의 범위에 포함시키도록 하였고, 선재형 보강재(27)와 망형 보강재(29) 및 복합형 보강재(31)의 경우 공히 대형 관로 시설물(1, 1' )에 고정시키기 위한 수단으로 통상적인 고정용 앵커를 사용하여 고정시키거나 또는 기존 철근에 결속선으로 묶어 고정시키도록 하였다.Here, in the case of the wire rod reinforcement 27 used as the upper reinforcement (7) when the upper reinforcement (7) is installed, the wire rod reinforcement (27) is also fixed in a predetermined interval to install the reinforcement muscles for maintaining the interval. In the case of the wire type reinforcement 27, the mesh reinforcement 29 and the composite reinforcement 31, it is a means for fixing to large pipeline facilities (1, 1 '). Anchors can be used to fix or tie to existing rebars.

또한, 상기 상부 보강재(7)가 필요한 보강 구간에는 도 7 및 도 9에 도시된 바와 같이 제 1 실시예로서 선재형 보강재(27)를 설치하되, 직선부용 보강재(39)와 헌치부용 보강재(41)로 구분한 후 규격화하고 조합하여 통상적인 결속선이나 결속구를 포함하는 결속재(43)를 사용하여 결속시키도록 하였다.In addition, in the reinforcement section in which the upper reinforcement member 7 is required, as shown in FIGS. 7 and 9, the wire-shaped reinforcement member 27 is installed as the first embodiment, but the reinforcement member 39 for the straight portion and the reinforcement member for the haunting part ( 41) and then standardized and combined to bind using a binding material 43 including a conventional binding line or a binding port.

한편, 상기 선재형 보강재(27)는 제 2 실시예로서 도 7 및 도 9에 도시된 바와 같이 망형 보강재(29)로 치환하여 통상적인 간격재를 사용하여 평면상으로 설치하되, 직선부용 보강재(39)와 헌치부용 보강재(41)로 구분한 후 규격화하고 조합하여 결속재(43)를 사용하여 결속시키도록 구성하였다.On the other hand, the wire rod reinforcement 27 is replaced with a mesh reinforcement (29) as shown in Figure 7 and 9 as a second embodiment is installed in a plane using a conventional spacer, but the reinforcement for the straight portion ( 39) and the reinforcing material for haunchi (41) and then standardized and configured to bind using the binding material (43).

또한, 상기 선재형 보강재(27)는 도 7 및 도 10에 도시된 바와 같이 제 3 실시예로서 선재형 보강재(27)와 망형 보강재(29)를 결속재(43)로 결합한 복합형 보강재(31)로 치환하여 통상적인 간격재를 사용하여 평면상으로 설치하되, 직선부용 보강재(39)와 헌치부용 보강재(41)로 구분한 후 규격화하고 조합하여 결속재(43)를 사용하여 결속시키도록 구성하였다.In addition, the wire-shaped reinforcement 27 is a composite reinforcement 31 is a combination of the wire-shaped reinforcement 27 and the mesh-shaped reinforcement 29 as a binding member 43 as a third embodiment as shown in Figs. To be installed in a planar shape using a conventional spacer material, and then divided into a straight portion reinforcement member 39 and a haunting portion reinforcement member 41, and then standardized and combined to bind using a binding member 43. Configured.

한편, 상기 선재형 보강재(27)의 경우 간격 유지를 위한 배력근을 소정의 간격으로 고정 설치하는 경우도 본 선재형 보강재(27)의 범위에 포함시키도록 하였고, 선재형 보강재(27)와 망형 보강재(29) 및 복합형 보강재(31)의 경우 공히 대형 관로 시설물(1, 1' )에 고정시키기 위한 수단으로 통상적인 고정용 앵커를 사용하여 고정시키거나 또는 기존 철근에 결속선으로 묶어 고정시키도록 하였다.On the other hand, in the case of the wire rod reinforcement 27 is also included in the range of the wire rod reinforcement 27, the case of fixed installation of the reinforcement for maintaining the spacing at a predetermined interval, the wire rod reinforcement 27 and the mesh In the case of the reinforcement 29 and the composite reinforcement 31, it is fixed by using a conventional anchoring anchor as a means for fixing to the large pipeline facilities (1, 1 '), or tied to the existing reinforcing bar by tie It was made.

상기 대형 관로 시설물(1, 1' )의 상부에 상부 보강재(7)를 설치하는 공정 후 도 2 및 도 8에 도시된 바와 같이 대형 관로 시설물(1, 1' )의 하부에 하부 보강재(8)를 이동 설치하는 공정으로 구성하였다.After the process of installing the upper reinforcing material (7) in the upper portion of the large pipeline facility (1, 1 ') as shown in Figure 2 and 8, the lower reinforcement (8) in the lower portion of the large pipeline facility (1, 1') It consisted of the process of moving installation.

여기서, 상기 하부 보강재(8)를 횡방향으로 소정의 간격으로 배열시키거나 또는 평면상으로 배열시킨 상태로 대형 관로 시설물(1, 1' )의 하부에 설치한 견인용 레일(11) 위에 미끄러지도록 통상적인 밧줄을 사용하여 작업원이 인력으로 당기고 밀거나 또는 밧줄이나 윈치를 사용하여 견인식 또는 추력식 중에서 한가지와 미끄럼식을 혼용하여 이동시켜 제자리에서 설치하거나 또는 작업원이 인력으로 운반하여 해당 부분에 직접 설치하도록 하였다.Here, the lower reinforcing material (8) is arranged to slide on the towing rail (11) installed in the lower portion of the large pipeline facilities (1, 1 ') in a state arranged in the horizontal direction at a predetermined interval or in a plane arrangement. Using a conventional rope, the worker pulls and pushes by the manpower, or by using a rope or winch to move one of the traction or thrust type and sliding type to install it in place, or the worker carries it to the part It was installed directly.

또한, 상기 하부 보강재(8)의 끝단부는 대형 관로 시설물(1, 1' )의 횡방향으로 상부 보강재(7)의 끝단부와 겹이음부가 생기도록 구성하며, 상기 겹이음부에 통상적인 결속선(43)을 사용하여 일체화시키도록 하였다.In addition, the end of the lower reinforcement (8) is configured such that the end of the upper reinforcement (7) and the lap joint in the transverse direction of the large pipeline facility (1, 1 '), and the normal binding to the lap joint The line 43 was used for integration.

또한, 상기 하부 보강재(8)가 필요한 보강 구간에는 도 8 및 도 9에 도시된 바와 같이 제 1 실시예로서 선재형 보강재(27)를 횡방향으로 소정의 간격으로 인력으로 운반하여 설치하되, 직선부용 보강재(39)와 헌치부용 보강재(41)로 구분한 후 규격화하고 조합하여 결속재(43)를 사용하여 결속시키도록 하였다.In addition, in the reinforcement section in which the lower reinforcement member 8 is required, as shown in FIGS. 8 and 9, the wire-shaped reinforcement member 27 is installed to be transported by a manpower at predetermined intervals in the transverse direction, but is installed in a straight line. After the bouillon reinforcement (39) and the haunbu reinforcement (41) was divided into standardized and combined to bind using the binding material (43).

여기서, 상기 상부 보강재(7)와 하부 보강재(8)로 사용되는 선재형 보강재(27)는 공히 철근, 강선, 탄소봉, 아라미드봉, 에프알피(F.R.P.)봉을 포함하는 각종 선재와 상기 각각의 선재에 탄소섬유, 아라미드섬유, 유리섬유를 포함한 토목섬유를 감싸서 보강한 복합선재를 전부 포함시키도록 구성하였다.Here, the wire rod type reinforcement 27 used as the upper reinforcing material (7) and the lower reinforcing material (8) is a variety of wires and steel wires, including the reinforcing rod, steel wire, carbon rod, aramid rod, FRP rods and the respective wire rods It was configured to include all the composite wire reinforced by wrapping the civil fiber including carbon fiber, aramid fiber, glass fiber.

한편, 상기 선재형 보강재(27)는 제 2 실시예로서 도 8 및 도 9에 도시된 바와 같이 망형 보강재(29)로 치환하여 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시킨 후 통상적인 간격재를 사용하여 평면상으로 설치하되, 직선부용 보강재(39)와 헌치부용 보강재(41)로 구분한 후 규격화하고 조합하여 결속재(43)를 사용하여 결속시키도록 구성하였다.On the other hand, the wire rod stiffener 27 is replaced with a net stiffener 29 as shown in Figs. It was installed in the plane using the ash, but divided into a straight portion reinforcement (39) and the haunting portion reinforcement (41) and then standardized and configured to bind using the binding material (43).

여기서, 상기 망형 보강재(29)는 와이어메쉬, 용접철망, 용접철근망, 용접철망과 용접철근망의 복합망, 메탈라스 및 타공판을 포함하는 망형재를 전부 포함시키도록 하였다.Here, the mesh reinforcement 29 is to include all the mesh material including the wire mesh, welded wire mesh, welded rebar mesh, composite mesh of welded wire mesh and welded rebar mesh, metal lath and perforated plate.

또한, 상기 선재형 보강재(27)는 도 8 및 도 10에 도시된 바와 같이 제 3 실시예로서 선재형 보강재(27)와 망형 보강재(29)를 결속재(43)로 결합한 복합형 보강재(31)로 치환하여 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시킨 후 통상적인 간격재를 사용하여 평면상으로 설치하도록 구성하였다.In addition, the wire-shaped reinforcement 27 is a composite reinforcement 31 which combines the wire-shaped reinforcement 27 and the mesh reinforcement 29 as the binding material 43 as a third embodiment as shown in Figs. Substituting) to move to the maintenance target position in one of the traction or thrust formula was configured to install in a plane using a conventional spacer.

한편, 상기 선재형 보강재(27)의 경우 간격 유지를 위한 배력근을 소정의 간격으로 고정 설치하는 경우도 본 선재형 보강재(27)의 범위에 포함시키도록 하였고, 선재형 보강재(27)와 망형 보강재(29) 및 복합형 보강재(31)의 경우 공히 대형 관로 시설물(1, 1' )에 고정시키기 위한 수단으로서 대형 관로 시설물(1, 1' )에 소정의 간격으로 천공한 후 천공부의 내면에 통상적인 고정용 앵커와 접착수지를 사용하여 고정시키거나 또는 기존 철근에 결속선으로 묶어 고정시키도록 하였다.On the other hand, in the case of the wire rod reinforcement 27 is also included in the range of the wire rod reinforcement 27, the case of fixed installation of the reinforcement for maintaining the spacing at a predetermined interval, the wire rod reinforcement 27 and the mesh In the case of the reinforcement 29 and the composite reinforcement 31, the inner surface of the perforated part after perforating the large pipeline facilities 1 and 1 'at predetermined intervals as a means for fixing them to the large pipeline facilities 1 and 1'. To fix it using a conventional fixing anchor and adhesive resin or to bind to the existing reinforcing bar tied with a tie.

한편, 상기 대형 관로 시설물(1, 1' )의 하부에 하부 보강재(8)를 이동 설치하는 공정 후 도 5에 도시된 바와 같이 대형 관로 시설물(1, 1' )의 길이 방향으로 소정의 간격으로 설치되는 바퀴 부착형 내부 물돌리기관(5)의 받침대(23)의 하단부에 바퀴용 캡(25)을 씌우는 공정으로 구성하였다.On the other hand, after the process of moving the lower reinforcement (8) to the lower portion of the large pipe facility (1, 1 ') as shown in Figure 5 at a predetermined interval in the longitudinal direction of the large pipe facility (1, 1'). It was composed of a process of covering the cap 25 for the wheel to the lower end of the pedestal 23 of the wheel-mounted inner spinneret (5) to be installed.

여기서, 상기 바퀴용 캡(25)은 보수 몰탈(35) 타설시 받침대(23)의 하단부가 보수 몰탈(35)에 매립되어 경화되지 않도록 하기 위해 사용하며, 통상적인 플라스틱제 파이프의 하단부를 밀폐시킨 한쪽 밀폐형 파이프나 플라스틱컵 등을 사용함이 경제적이고 바람직하며, 받침대(23)의 하단부를 보수 몰탈(35)에 매립시켜 보수 보강을 실시한 후 보수 몰탈(35)의 마감면에 맞춰 받침대(23)의 하단부를 절단시키는 방법도 도면상의 도시는 생략하였으나 또 다른 한가지 실시예로서 본 특허의 범위에 포함시키도록 하였다.Here, the wheel cap 25 is used to prevent the lower end of the pedestal 23 to be embedded in the repair mortar 35 and harden when pouring the repair mortar 35, and to seal the lower end of a conventional plastic pipe. It is economical and preferable to use one hermetic pipe or plastic cup, and the lower end of the pedestal 23 is embedded in the repair mortar 35 to perform repair reinforcement, and then to the finishing surface of the repair mortar 35. The method of cutting the lower end is also omitted from the drawings, but as another embodiment to be included in the scope of the present patent.

또한, 상기 소정의 간격으로 설치되는 바퀴 부착형 내부 물돌리기관(5)의 받침대(23)의 하단부에 바퀴용 캡(25)을 씌우는 공정 후 대형 관로 시설물(1, 1' )의 내면에 통상적인 접착제인 프라이머(33)를 통상적인 붓이나 뿜칠 방식으로 도포하는 공정과, 상기 대형 관로 시설물(1, 1' )의 내면에 통상적인 접착제인 프라이머(33)를 붓이나 뿜칠 방식으로 도포하는 공정 후 프라이머(33) 상에 보수 몰탈(35)을 통상적인 미장이나 뿜칠 방식으로 타설하는 공정과, 상기 프라이머(33) 상에 보수 몰탈(35)을 통상적인 미장이나 뿜칠 방식으로 타설하는 공정 후 보수 몰탈(35)을 소정의 시간동안 양생시키는 공정과, 상기 보수 몰탈(35)을 소정의 시간동안 양생시키는 공정 후 양생된 보수 몰탈(35) 상에 통상적인 표면 마감제인 마감코팅제(37)를 도포하는 공정으로 구성된 것을 특징으로 한다.In addition, after the process of covering the wheel cap 25 to the lower end of the pedestal 23 of the wheel-mounted internal waterway engine 5 installed at the predetermined intervals, it is common to the inner surface of the large pipeline facility (1, 1 '). A process of applying a primer 33, which is a phosphorus adhesive, by a conventional brush or a spraying method, and a process of applying a primer 33, which is a conventional adhesive, by a brush or a spraying method, on the inner surface of the large pipeline facility (1, 1 '). After the process of pouring the repair mortar 35 in a conventional plastering or spraying method on the primer 33, and the process of pouring the repair mortar 35 in the usual plastering or spraying method on the primer 33 After the process of curing the mortar (35) for a predetermined time, and after the process of curing the maintenance mortar (35) for a predetermined time, a coating finish 37 of the conventional surface finish agent which is a conventional surface finishing agent That consists of And a gong.

또한, 대형 관로 시설물(1, 1' )의 보수 구간에는 상기 상부 보강재(7)와 하부 보강재(8)의 사용을 삭제하여 구성된 것을 특징으로 한다.In addition, the repair section of the large pipeline facility (1, 1 ') is characterized in that the configuration by eliminating the use of the upper reinforcement (7) and lower reinforcement (8).

한편, 상기 상부 보강재(7)와 하부 보강재(8)는 각각 선재형 보강재(27)로 구성된 것을 특징으로 한다.On the other hand, the upper reinforcing material (7) and the lower reinforcing material (8) is characterized in that each consisting of a wire rod type reinforcing material (27).

또한, 상기 선재형 보강재(27)는 망형 보강재(29)로 치환하여 구성된 것을 특징으로 한다.In addition, the wire-shaped reinforcement 27 is characterized in that it is configured by replacing the mesh reinforcement (29).

한편, 상기 선재형 보강재(27)는 선재형 보강재(27)와 망형 보강재(29)가 통상적인 결속재(43)로 결속된 복합형 보강재(31)로 치환하여 구성된 것을 특징으로 한다.On the other hand, the wire-shaped reinforcement 27 is characterized in that the wire-shaped reinforcement 27 and the mesh-shaped reinforcement 29 is replaced by a composite reinforcement 31 bound with a conventional binding material 43.

또한, 상기 실시예는 대형 관로 시설물(1, 1' )의 4면을 전체적으로 보수 보강하는 경우에 해당되지만 현장 여건상 어느 특정한 면만을 대상으로 보수 보강을 실시하는 경우도 전부 본 발명의 범위에 포함시키도록 구성하였다.In addition, the above embodiment corresponds to the case where the overall reinforcement of the four sides of the large pipeline facilities (1, 1 ') as a whole, but the case of performing the reinforcement for any specific surface only on the site conditions are included in the scope of the present invention. It was configured to.

상술한 실시 예는 본 발명의 가장 바람직한 예에 대하여 설명한 것이지만, 상기 실시 예에만 한정되는 것은 아니며, 본 발명의 기술사상을 벗어나지 않는 범위 내에서 다양한 변형이 가능하다는 것은 당업자에게 있어서 명백한 것이다.It should be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined in the appended claims.

1, 1' : 대형 관로 시설물 3 : 바퀴 부착형 이동식 가설대
5 : 바퀴 부착형 내부 물돌리기관 7 : 상부 보강재
8 : 하부 보강재 9 : 바퀴
11 : 견인용 레일 13 : 하수 또는 유수
15 : 길이 조정부 17 : 길이 조정봉
19 : 길이 조정캡 21 : 고정나사
23 : 받침대 25 : 바퀴용 캡
27 : 선재형 보강재 29 : 망형 보강재
31 : 복합형 보강재 32 : 치핑부
33 : 프라이머 35 : 보수 몰탈
37 : 마감코팅제 39 : 직선부용 보강재
41 : 헌치부용 보강재 43 : 결속재
1, 1 ': large pipeline facility 3: wheel-mounted mobile tent
5: wheel attachment type internal pivot body 7: upper reinforcement
8: lower reinforcement 9: wheels
11: towing rail 13: sewage or running water
15: length adjusting unit 17: length adjusting rod
19: length adjusting cap 21: fixing screw
23: base 25: wheel cap
27: wire rod reinforcement 29: mesh reinforcement
31: composite reinforcement 32: chipping part
33: primer 35: repair mortar
37: finish coating agent 39: reinforcing material for the straight portion
41: reinforcing material for haunchi part 43: binding material

Claims (5)

하수 또는 유수가 흐르는 하수암거를 포함한 대형 관로 시설물의 보수 보강에 있어서,
바퀴 부착형 내부 물돌리기관을 사용하여 내부 물돌리기를 실시하는 공정과,
상기 바퀴 부착형 내부 물돌리기관을 사용하여 내부 물돌리기를 실시하는 공정 후 대형 관로 시설물의 치핑을 실시하는 공정과,
상기 대형 관로 시설물의 치핑을 실시하는 공정 후 치핑부를 세척하는 공정과,
상기 치핑부를 세척하는 공정 후 상부 시공시에는 바퀴 부착형 이동식 가설대를 설치하는 공정과,
상기 상부 시공시에는 바퀴 부착형 이동식 가설대를 설치하는 공정 후 바퀴 부착형 이동식 가설대의 외면에 상부 보강재를 거치하는 공정과,
상기 바퀴 부착형 이동식 가설대의 외면에 상부 보강재를 거치하는 공정 후 상부 보강재와 바퀴 부착형 이동식 가설대를 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시키는 공정과,
상기 상부 보강재와 바퀴 부착형 이동식 가설대를 견인식 또는 추력식 중에서 한가지로 보수 대상 위치로 이동시키는 공정 후 대형 관로 시설물의 상부에 상부 보강재를 설치하는 공정과,
상기 대형 관로 시설물의 상부에 상부 보강재를 설치하는 공정 후 대형 관로 시설물의 하부에 하부 보강재를 이동 설치하는 공정과,
상기 대형 관로 시설물의 하부에 하부 보강재를 이동 설치하는 공정 후 바퀴 부착형 내부 물돌리기관의 바퀴용 캡을 씌우는 공정과,
상기 바퀴 부착형 내부 물돌리기관의 바퀴용 캡을 씌우는 공정 후 대형 관로 시설물의 내면에 프라이머를 도포하는 공정과,
상기 대형 관로 시설물의 내면에 프라이머를 도포하는 공정 후 프라이머 상에 보수 몰탈을 타설하는 공정과,
상기 프라이머 상에 보수 몰탈을 타설하는 공정 후 보수 몰탈을 양생시키는 공정과,
상기 보수 몰탈을 양생시키는 공정 후 양생된 보수 몰탈 상에 마감코팅제를 도포하는 공정으로 구성된 것을 특징으로 하는 하수암거를 포함한 대형 관로 시설물 보수 보강공법.
In the maintenance reinforcement of the large pipeline facility including the sewage culvert which the sewage or the flowing water flow,
A step of performing an internal spin using a wheel-mounted internal spinneret,
Performing chipping of large pipeline facilities after the step of performing an internal spin using the wheeled internal spinnerette;
Washing the chipping part after the chipping of the large pipeline facility;
When the upper construction after the process of washing the chipping unit and the process of installing a wheel-mounted removable temporary stand,
In the upper construction, the process of mounting the upper reinforcing material on the outer surface of the wheel-mounted mobile tent, after the process of installing the wheel-mounted removable temporary,
After the process of mounting the upper reinforcement on the outer surface of the wheel-mounted mobile temporary placing table, the process of moving the upper reinforcing material and the wheel-mounted mobile temporary placing table to the repair target position by any one of the traction or thrust type,
Installing the upper reinforcement on the upper part of the large pipeline facility after the step of moving the upper reinforcement and the wheel-mounted movable temporary stand to a maintenance target position by one of traction or thrust;
Moving the lower reinforcement to the lower part of the large pipeline facility after installing the upper reinforcement to the upper part of the large pipeline facility;
After the process of moving the lower reinforcement to the lower portion of the large pipeline installation process of capping the wheel cap of the wheeled internal spinneret;
Applying a primer to an inner surface of a large pipeline facility after the process of capping the wheel cap of the wheeled internal spinneret;
A process of pouring a repair mortar onto the primer after the process of applying the primer to the inner surface of the large pipeline facility;
Curing the mortar after the process of pouring the mortar onto the primer;
Repairing reinforcement method for large pipeline facilities including sewage culvert, characterized in that the process consisting of applying a finish coating on the repaired mortar after the process of curing the repair mortar.
청구항 1에 있어서,
대형 관로 시설물의 보수 구간에는 상기 상부 보강재와 하부 보강재의 사용을 각각 삭제하여 구성된 것을 특징으로 하는 하수암거를 포함한 대형 관로 시설물 보수 보강공법.
The method according to claim 1,
Repairing reinforcement method of large pipeline facilities, including sewage culvert, characterized in that the repair section of the large pipeline facility is configured to eliminate the use of the upper reinforcement and the lower reinforcement, respectively.
청구항 1에 있어서,
상기 상부 보강재와 하부 보강재는 각각 선재형 보강재로 구성된 것을 특징으로 하는 하수암거를 포함한 대형 관로 시설물 보수 보강공법.
The method according to claim 1,
The upper reinforcement and the lower reinforcement is a repair method for reinforcing large pipeline facilities, including sewage culvert, characterized in that each consisting of a wire-shaped reinforcement.
청구항 3에 있어서,
상기 선재형 보강재는 망형 보강재로 치환하여 구성된 것을 특징으로 하는 하수암거를 포함한 대형 관로 시설물 보수 보강공법.
The method according to claim 3,
The wire reinforcement reinforcement method for repairing large pipeline facilities, including sewage culvert, characterized in that configured by replacing the reinforcement mesh.
청구항 3에 있어서,
상기 선재형 보강재는 복합형 보강재로 치환하여 구성된 것을 특징으로 하는 하수암거를 포함한 대형 관로 시설물 보수 보강공법.
The method according to claim 3,
The wire reinforcement reinforcement method for repairing large pipeline facilities including sewage culvert, characterized in that by replacing with a composite reinforcement.
KR1020130007253A 2013-01-23 2013-01-23 Repair and reinforcement of large pipeline facilities including sewage culverts KR101310580B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130007253A KR101310580B1 (en) 2013-01-23 2013-01-23 Repair and reinforcement of large pipeline facilities including sewage culverts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130007253A KR101310580B1 (en) 2013-01-23 2013-01-23 Repair and reinforcement of large pipeline facilities including sewage culverts

Publications (1)

Publication Number Publication Date
KR101310580B1 true KR101310580B1 (en) 2013-09-23

Family

ID=49456524

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130007253A KR101310580B1 (en) 2013-01-23 2013-01-23 Repair and reinforcement of large pipeline facilities including sewage culverts

Country Status (1)

Country Link
KR (1) KR101310580B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190092170A (en) 2018-01-30 2019-08-07 공주대학교 산학협력단 Reinforcement apparatus and method thereof
KR20200110637A (en) 2020-09-16 2020-09-24 공주대학교 산학협력단 Reinforcement apparatus and method thereof
KR20200127134A (en) 2020-09-16 2020-11-10 공주대학교 산학협력단 Reinforcement apparatus and method thereof
KR102607504B1 (en) 2022-06-13 2023-11-30 박영진 Underground pipes repair method using high-performance mortar

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3231472B2 (en) * 1992-06-29 2001-11-19 ノガワケミカル株式会社 Piping rehabilitation method
JP3316136B2 (en) * 1996-07-02 2002-08-19 株式会社栗本鐵工所 Repair units for existing waterways and their repair methods
KR100986199B1 (en) * 2009-08-20 2010-10-07 (주)로터스지이오 An apparatus for mending a portion of conduct line and method for mending a portion of conduct line using the same
KR20120135670A (en) * 2011-06-07 2012-12-17 (주)엔코텍 Central part reduction device for diameter reduction and partial repair method using the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3231472B2 (en) * 1992-06-29 2001-11-19 ノガワケミカル株式会社 Piping rehabilitation method
JP3316136B2 (en) * 1996-07-02 2002-08-19 株式会社栗本鐵工所 Repair units for existing waterways and their repair methods
KR100986199B1 (en) * 2009-08-20 2010-10-07 (주)로터스지이오 An apparatus for mending a portion of conduct line and method for mending a portion of conduct line using the same
KR20120135670A (en) * 2011-06-07 2012-12-17 (주)엔코텍 Central part reduction device for diameter reduction and partial repair method using the same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190092170A (en) 2018-01-30 2019-08-07 공주대학교 산학협력단 Reinforcement apparatus and method thereof
KR20200110637A (en) 2020-09-16 2020-09-24 공주대학교 산학협력단 Reinforcement apparatus and method thereof
KR20200127134A (en) 2020-09-16 2020-11-10 공주대학교 산학협력단 Reinforcement apparatus and method thereof
KR102607504B1 (en) 2022-06-13 2023-11-30 박영진 Underground pipes repair method using high-performance mortar

Similar Documents

Publication Publication Date Title
KR101310580B1 (en) Repair and reinforcement of large pipeline facilities including sewage culverts
CN110318776B (en) Tunnel construction method based on inverted arch and inverted arch filling layer replacing steel-concrete composite structure
CN201972252U (en) External water stopper structure
CN110645418B (en) Connecting method for mounting large-diameter pipeline
KR101732669B1 (en) Reinforcement member, concrete box reinforced with the same and the construction method thereof
CN104790302A (en) Hanging-basket and bent-cap-support matched integral construction method for side span linear segment of high-pier continuous rigid frame bridge
KR101415106B1 (en) The back feel grouting apparatus for upper part of tunnel
CN103726670B (en) Adopt steel beam concrete slab on inhering architecture, increase the method for interlayer
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
CN110629792B (en) Splicing construction method for corrugated steel pipe gallery
KR100895342B1 (en) Water veer type dry maintenance and reinforce engineering methode of sewer using water isolation robot
KR102543992B1 (en) The inner surface of pipelines medium and large repair and reinforcement
KR20100086110A (en) Temporary composite pipe and pipeline and tunnel unexcavation laying method using the same
CN104895014A (en) Construction method of high altitude long span cast-in-place multi-arch aqueduct supporting die system
JP2012184575A (en) Method for repairing steel structure
KR100803512B1 (en) Pipeless Excavation Composite Reinforcement Method
KR100735619B1 (en) The revival method which lays the new waterworks pipe on the waterworks pipe inside which is been old
CN109695347B (en) Building construction method based on round steel holding bender
CN104213515B (en) The method repairing corrugated steel embedded structure with steel fibrous shotcrete
KR20080062484A (en) Equal plastering for facilities and equalizing plaster reinforcement method using the same
RU172192U1 (en) GOFROLIST WITH PIPES
KR101489227B1 (en) lining method of tunnels using fiber rods, polymer mortar and adhesion waterproofer
KR101737411B1 (en) Common duct pipe with downcomer with epoxy resin
CN214616564U (en) Reinforcing and reinforcing device for existing railway tunnel lining defect treatment
KR20220064031A (en) When using internal watering and reinforcing materials, it is a method of manpower construction on the inside of a pipe that is not excavated and maintains an even thickness under the conditions of uncured super and chaebol plasterers and does not generate plaster marks.

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161124

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170921

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190729

Year of fee payment: 7