KR20050066024A - Construction method of temporary apparatus of thnnel for direct digging - Google Patents
Construction method of temporary apparatus of thnnel for direct digging Download PDFInfo
- Publication number
- KR20050066024A KR20050066024A KR1020030097210A KR20030097210A KR20050066024A KR 20050066024 A KR20050066024 A KR 20050066024A KR 1020030097210 A KR1020030097210 A KR 1020030097210A KR 20030097210 A KR20030097210 A KR 20030097210A KR 20050066024 A KR20050066024 A KR 20050066024A
- Authority
- KR
- South Korea
- Prior art keywords
- shaft
- excavation
- slope
- tunnel
- steel pipe
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
Abstract
본 발명은 가설 구조물을 이용하여 터널 갱구부 공사시 갱구부 사면을 형성않고 자연 사면을 유지하면서 굴착을 진행시키도록 하여 공기를 단축시키고 환경훼손을 최소화할 수 있으며, 터널 형성후 일부 압성토를 시행하여 갱구부 사면의 안정성을 이루도록 하는 터널 갱구부 시공 방법에 관한 것이다.The present invention can shorten the air and minimize environmental damage by maintaining excavation without maintaining the shaft slope during construction of the tunnel shaft using a temporary structure, and can minimize the environmental damage, and after the tunnel formation some pressure It relates to a tunnel shaft construction method to achieve the stability of the shaft slope.
본 발명은, 구조용 탄소강관, 에이취(H)-형강, 토류판, 웨일(WALE), 제거형 앵커가 포함되고 터널 갱구부에 설치되는 가시설에 있어서, 에이취(H)-형강에 지지대를 이용하여 구조용 탄소강관을 용접으로 접합한 후 굴착 예정부에 가시설(20)을 밀착시키고 천단부에 대하여 강관다단 그라우팅을 실시하여 보강후 굴착을 시행토록 하여 갱구부 사면에 대한 훼손을 방지시키는 한편, 라이닝 설치후 갱문의 형성부로부터 성토를 시행하여 자연 사면에 대한 압성토 효과를 발휘하여 사면을 안정화시킬수 있도록 하고, 터널굴착 진행시 진동 등의 영향으로 자연 사면의 소규모 붕락에 대하여는 구조용 탄소강관 및 토류판으로 지지토록 하여 갱구부 사면을 형성시키지 않고 가시설을 이용하여 즉시 터널을 굴착할 수 있도록 하는 직접 굴착식 터널 갱구 가시설 시공 방법을 제공한다.The present invention includes a structural carbon steel pipe, H-shaped steel, earth plate, wale (WALE), removable anchor is installed in the tunnel shaft portion, the structural structure using a support in the H-shaped steel After joining the carbon steel pipe by welding, close the temporary facility 20 to the excavation scheduled part and perform steel pipe multi-stage grouting on the top end part to perform excavation after reinforcement to prevent damage to the slope of the shaft part. It is possible to stabilize the slope by applying the sedimentary soil effect on the natural slope by forming the ground from the formation part of the gang gate.For the small scale collapse of the natural slope due to the vibrations during tunnel excavation, it is supported by structural carbon steel pipe and earth plate. Construction of a direct excavation tunnel shaft facility that enables the excavation of a tunnel immediately by using the temporary facility without forming a shaft slope Provide a method.
Description
본 발명은 자연 사면을 유지하며 별도의 갱구부 사면의 형성없이 터널의 굴착이 가능하도록 하는 직접 굴착식 터널 갱구 가시설에 관한 것으로서, 더욱 상세하게는 구조용 탄소 강관을 이용하여 터널 갱구부의 경사 사면을 보호하고, 친환경적으로 자연 사면의 훼손을 최대한 방지할 수 있도록 사전 갱구부 가시설에 강관다단 그라우팅을 위한 강관을 접합한 후 굴착 예정부로 이동하여 굴착 천단부를 그라우팅으로 보강하여 즉시 굴착이 가능하도록 하며, 또한 환경 피해를 최소화하고 공기를 단축시키도록 보완한 직접 굴착식 터널 갱구 가시설 시공 방법에 관한 것이다.The present invention relates to a direct excavated tunnel shaft provisional facility for maintaining a natural slope and to enable the excavation of the tunnel without the formation of a separate shaft slope, and more specifically to protect the slope slope of the tunnel shaft using a structural carbon steel pipe In order to prevent damage to natural slopes in an eco-friendly manner, the steel pipes for multi-stage grouting are joined to the pre-shaft provisional facilities, and then moved to the excavation scheduled part to reinforce the excavation top end by grouting to enable immediate excavation. The present invention relates to a method of constructing a direct excavation tunnel shaft refurbishment that has been supplemented to minimize damage and shorten air.
일반적으로 터널 굴착을 위하여 사전 갱구부 비탈면을 조성하고 이후 갱구부 예정지에 가시설을 설치한 후 굴착 작업이 이루어지게 되는 바, 상기 갱구부 비탈면 조성시 상당한 기일이 소요되고, 대부분 작업시 자연 사면을 훼손하게 되어 환경적인 측면에서 상당히 불리한 상태이다.In general, the excavation work is performed after the preliminary shaft slope is formed for the tunnel excavation, and after the temporary facility is installed at the site of the shaft portion, a considerable time is required when the shaft slope is formed, and most of the work damages the natural slope. This is a very disadvantageous condition in terms of environment.
도 1은 일반적인 터널굴착시 선시행하게 되는 갱구부 비탈면의 조성 상태를 나타내는 도면으로서, 자연 사면(1)이 절취되고, 그 절취된 사면에 억지 말뚝(2)과 표면 보호공(3)이 설치된다.1 is a view showing the state of the composition of the shaft slope to be pre-executed during the general tunnel excavation, the natural slope 1 is cut, the interference pile (2) and the surface protection hole (3) is installed on the cut slope do.
이때, 절취된 사면에는 하부에 콘크리트 옹벽이 설치되는 경우가 많다.At this time, the cut surface is often provided with a concrete retaining wall in the lower portion.
상기 자연 사면(1)의 상당 부분을 훼손하며 절취를 진행하게 되는 바, 굴착으로 인하여 응력이 해방되며 이완된 부분에서 붕락이 발생할 가능성을 내포하게 된다.Barring a substantial portion of the natural slope (1) proceeds to the cutting, the stress is released due to the excavation and will contain the possibility of collapse in the relaxed portion.
도 2는 터널 갱구부에 설치하는 가시설의 형태를 나타내는 도면으로서, 갱구부 비탈면 조성후 마대(5) 및 통나무(4)를 이용하여 가시설을 설치한 후 굴착을 진행하게 되는 것이 일반적이다.Figure 2 is a view showing the form of the temporary installation to be installed in the tunnel shaft portion, it is common to proceed with the excavation after installing the temporary facility using the rod 5 and the log 4 after the shaft slope is formed.
상술한 일반적인 종래의 방법과 같이 사전 자연 사면을 훼손하며 갱구부 비탈면을 형성함과 아울러, 갱구부 가시설을 설치한 후 터널 굴착을 시행하게 되는 경우에는, 인위적으로 형성된 사면의 안정성을 확보하기 위하여 별도의 보강공 및 표면 보호공을 시공하게 되어 공사비가 많이 소요되며 비탈면을 조성하기 위하여 상당한 공기가 소요되는 등 문제점이 파생된다.As in the conventional conventional method described above, in order to damage the pre-natural slope and form the shaft slope, and when the tunnel excavation is performed after the installation of the shaft provisional provision, the artificially formed slope is additionally secured. As construction of reinforcement and surface protection is required, construction costs are high, and a considerable amount of air is required to create a slope.
본 발명은 상술한 문제점을 해결하기 위하여, 본 발명은, 자연 사면을 유지하며 별도의 갱구부 사면의 형성없이 터널의 굴착이 가능하도록 하는 기성 제품의 갱구부 가시설에 관한 것으로서, 더욱 상세하게는 구조용 탄소 강관을 이용하여 터널 갱구부의 경사 사면을 보호하고 친환경적으로 자연사면의 훼손을 최대한 방지할 수 있도록 사전 갱구부 가시설에 강관다단 그라우팅을 위한 강관을 접합한 후 굴착예정부로 이동하여 굴착 천단부를 그라우팅으로 보강하여 즉시 굴착이 가능하도록 하므로, 환경 피해를 최소화하며 공기를 단축시키도록 보완한 직접 굴착식 터널 갱구 가시설 시공 방법을 제공하는 것을 목적으로 한다.The present invention, in order to solve the above-described problems, the present invention relates to a shaft provisional provision of a ready-made product to maintain the natural slope and to enable the excavation of the tunnel without the formation of a separate shaft slope, more specifically for structural Carbon steel pipe is used to protect the sloped slope of the tunnel shaft and to prevent the damage of natural slope as much as possible. The purpose of the present invention is to provide a method of constructing a direct excavation tunnel shaft rehabilitation system which is supplemented to minimize the environmental damage and to shorten the air since it can be immediately excavated.
본 발명은 상술한 목적을 달성하기 위하여, 본 발명은, 구조용 탄소강관, 에이취(H)-형강, 토류판, 웨일(WALE), 제거형 앵커가 포함되고 터널 갱구부에 설치되는 가시설에 있어서, 에이취(H)-형강에 지지대를 이용하여 구조용 탄소강관을 용접으로 접합한 후 굴착 예정부에 가시설(20)을 밀착시키고 천단부에 대하여 강관다단 그라우팅을 실시하여 보강후 굴착을 시행토록 하여 갱구부 사면에 대한 훼손을 방지시키는 한편, 라이닝 설치후 갱문의 형성부로부터 성토를 시행하여 자연 사면에 대한 압성토 효과를 발휘하여 사면을 안정화시킬수 있도록 하고, 터널굴착 진행시 진동 등의 영향으로 자연 사면의 소규모 붕락에 대하여는 구조용 탄소강관 및 토류판으로 지지토록 하여 갱구부 사면을 형성시키지 않고 가시설을 이용하여 즉시 터널을 굴착할 수 있도록 하는 직접 굴착식 터널 갱구 가시설 시공 방법을 제공한다.The present invention, in order to achieve the above object, the present invention, structural carbon steel pipe, H (H) -beam, earth plate, wale (WALE), including a removable anchor is installed in the tunnel shaft, (H)-After joining the structural carbon steel pipe by welding using the support, weld the temporary facility 20 to the excavation scheduled part and perform steel pipe multi-stage grouting on the top end to perform excavation after reinforcement. After the lining is installed, the soil is formed from the forming part of the gang to stabilize the slopes by exerting the soil effect on the natural slopes. In case of collapse, it can be supported by structural carbon steel pipe and earth plate so that tunnel can be excavated immediately by using temporary facility without forming shaft slope. It provides direct drilling shaft gasiseol Tunnel construction method.
이하, 첨부된 도면을 참조하여 본 발명의 구성과 작용 상태를 설명한다.Hereinafter, with reference to the accompanying drawings will be described the configuration and operation state of the present invention.
도 3a는 가시설에 구조용 탄소 강관(6)을 설치한 후 굴착 예정부로 이동시킨 상황을 나타내는 도면이고, 도 3b는 가시설의 사시도이며, 도 3c는 도 3a의 "A"부 확대도이고, 도 3d는 도 3b의 "B"부 확대도이다.FIG. 3A is a view showing a situation in which the structural carbon steel pipe 6 is installed in the temporary facility and moved to the excavation scheduled part, FIG. 3B is a perspective view of the temporary facility, FIG. 3C is an enlarged view of part “A” of FIG. 3A, and FIG. 3D Is an enlarged view of a portion “B” of FIG. 3B.
사전에 제작된 갱구부 가시설(20)에 구조용 탄소 강관(6)을 일정간격으로 용접을 이용하여 접합한 후 굴착 예정부로 이동하여 굴착 천단부를 강관다단 그라우팅을 이용하여 보강할 수 있도록 한다.Structural carbon steel pipe (6) to the prefabricated shaft part provisional facility 20 by welding at regular intervals to be bonded to move to the excavation scheduled portion to be reinforced by using the steel pipe multi-stage grouting.
상기 가시설(20)은, 콘크리트 기초(11)의 상부에 다수개의 H-형강(7)이 라운딩되도록 터널 형태로 형성되고, 그 H-형강(7)의 사이에 토류판(10)이 삽입되어 결합되며, 그 H-형강(7)의 외측에 웨일(WALE)(12)이 보강되어 가시설을 지지하게 된다.The temporary facility 20 is formed in the form of a tunnel so that a plurality of H-shaped steel 7 is rounded on the top of the concrete foundation 11, and the earth plate 10 is inserted between the H-shaped steels 7 to be coupled. The wale 12 is reinforced on the outside of the H-beam 7 to support the temporary facility.
또한, 도 3b와 3c에서 알 수 있듯이, 상기 가시설(20)은, H-형강(7)이 라운딩되도록 형성된 상단의 사이에 철근(8)이 용접되고, 상기 H-형강(7)에 구조용 탄소 강관(6)이 용접시 그 구조용 탄소 강관(6)의 양측에 지지대(9)가 맞대어져 더욱 견고하게 용접하게 된다.In addition, as can be seen in Figures 3b and 3c, the temporary facility 20, the reinforcing bar 8 is welded between the upper end formed so that the H-shaped steel 7 is rounded, structural carbon to the H-shaped steel (7) When the steel pipe 6 is welded, the support 9 is abutted on both sides of the structural carbon steel pipe 6 to weld more firmly.
도 4a는 가시설 구조물을 굴착 예정부에 고정시키는 측단면 구성 형태를 나타내는 도면이고, 도 4b는 가시설 구조물의 전방에서 본 상태를 나타내는 도면이다.4A is a view showing a side cross-sectional configuration of fixing the temporary structure to the excavation scheduled portion, and FIG. 4B is a view showing a state seen from the front of the temporary structure.
강관다단 그라우팅의 원활한 작업을 위하여 제거형 앵커(13)를 이용 갱구부 가시설(20)을 굴착 예정부 법면에 고정시키도록 한다.In order to smoothly work the multi-stage grouting of the steel pipe, a removable anchor 13 is used to fix the shaft provisional fixture 20 to the excavation scheduled part surface.
상기 제거형 앵커(13)는, H-형강에 일측이 용접되는 앵커형 부재로, 가시설(20)을 사용하고 난 후 터널의 작업이 완료되면 해체하게 된다.The removable anchor 13 is an anchor-type member on which one side is welded to the H-shaped steel, and is dismantled when the work of the tunnel is completed after using the temporary facility 20.
도 5는 가시설 설치후 굴착을 시행하는 상황을 나타내는 도면이다.5 is a view showing a situation of carrying out excavation after installation of temporary installation.
갱구부 가시설(20)이 설치된 후, 갱구부 비탈면을 형성하지 않고 자연 사면(1)을 유지한 채 굴착 천단부를 보강하고 터널의 굴착을 진행시키도록 한다.After the shaft provisional installation 20 is installed, the excavation top end is reinforced while the natural slope 1 is maintained without forming the shaft slope, and the excavation of the tunnel is performed.
도 6은 굴착 및 라이닝(15) 설치 완료후 법면 형성상태를 나타내는 도면이다.6 is a view showing the state of forming the surface after completion of the excavation and lining (15) installation.
터널의 굴착이 완료되고 라이닝(15)을 설치하게 되면 갱구부 가시설(20)을 해체하고 갱문부(14)로부터 자연사면에 이르기까지 성토(16)를 시행하여 사면의 안정성을 추가 확보할 수 있도록 한다.When the excavation of the tunnel is completed and the lining 15 is installed, the shaft part temporary facility 20 is dismantled and the soil 16 is carried out from the shaft part 14 to the natural slope to secure additional slope stability. do.
<실시예><Example>
1. 구조용 탄소강관1. Structural Carbon Steel Pipe
1) 직경 : 100mm 1) Diameter: 100mm
2) 길이 : 2.0∼5.0m(자연사면의 경사에 따라 변경) 2) Length: 2.0 ~ 5.0m (change according to natural slope)
3) 설치간격 : 200mm 3) Installation interval: 200mm
4) 설치범위 : 천단부 기준 120°, 2열 설치 4) Mounting range: 120 °, 2 rows for ceiling ends
2. 제거형 앵커2. Removable Anchor
1) 자유장 : 6m 1) Free field: 6m
2) 정착장 : 3m 2) Settlement Site: 3m
3) Strand : 직경 12.7, 4가닥 3) Strand: Diameter 12.7, 4 strands
3. 강관 지지대3. Steel pipe support
1) 크기 : 상부 50mm×50mm, 하부 200mm×200mm 1) Size: Upper 50mm × 50mm, Lower 200mm × 200mm
2) 높이 : 70mm∼200mm 2) Height: 70mm ~ 200mm
4. H형강4. H section steel
1) 규격 : 200×200×8×12 1) Specification: 200 × 200 × 8 × 12
5. WALE5. WALE
1) 규격 : 200×200×8×12 1) Specification: 200 × 200 × 8 × 12
6. 토류판6. Earth plate
1) 크기 : 700×150 1) Size: 700 × 150
2) 두께 : 80mm 2) Thickness: 80mm
상술한 <실시예>에서 알 수 있는 바와 같이, 사전에 갱구부 가시설(20)에 접합한 구조용 탄소강관(6)을 이용하여 굴착예정부 천단을 보강하여 갱구부 사면을 형성시키지 않고 터널 굴착을 진행할 수 있는 바, 경제성 및 공시측면에서 상당히 유리하며 원지반을 훼손시키지 않고 굴착을 진행하는 바 환경 친화적인 이동이 가능한 갱구부 가시설을 제공하게 된다.As can be seen in the above-described <Example>, using a structural carbon steel pipe 6 bonded to the shaft provisional provision 20 in advance, the drilling preliminary top end is reinforced to form tunnel excavation without forming a shaft slope. As it can be proceeded, it is very advantageous in terms of economics and disclosure, and the excavation is carried out without damaging the ground, which provides an environment-friendly movable shaft fitting facility.
상술한 본 발명의 구성과 작용 상태에 따른 효과를 설명한다.The effects according to the configuration and operation state of the present invention described above will be described.
본 발명의 직접 굴착식 터널 갱구 가시설은, 구조용 탄소강관을 사전에 갱구부 가시설에 접합하여 굴착 예정부 천단을 보강함으로써 갱구부 사면을 형성시키지 않아 환경 훼손을 최소화 할 수 있으며 공기를 단축할 수 있는 효과를 얻을 수 있다.Directly drilled tunnel shaft temporary installation of the present invention, by joining the structural carbon steel pipe to the shaft temporary provision in advance to reinforce the drilling plan part to form a shaft slope can minimize environmental damage and can shorten the air The effect can be obtained.
또한, 본 발명의 이동형 갱구부 가시설은, 터널 라이닝 공사 완료후에 갱문부에서 추가 성토를 실시하게 되므로 압성토 효과를 이용하여 기존 자연사면의 안정성을 추가 확보할 수 있으므로 비탈면의 장기적인 안정성에 기여할 수 있는 효과를 가진다. In addition, since the movable shaft part temporary installation of the present invention, after the completion of the tunnel lining construction is carried out additional filling in the shaft part can be additionally secured the stability of the existing natural slope by using the crushed soil effect can contribute to the long-term stability of the slope Has an effect.
또한, 본 발명의 직접 굴착식 터널 갱구 가시설은, 이동형 구조를 지니고 있으므로 지형에 적합하게 크기와 모양이 변경 가능하여 경제성 측면에서 유리하며 산업폐기물의 발생을 최소화할 수 있는 효과가 있다.In addition, the direct drilling tunnel shaft temporary installation of the present invention, because it has a mobile structure can be changed in size and shape to suit the terrain is advantageous in terms of economics and has the effect of minimizing the generation of industrial waste.
특히, 상술한 이유로 인하여, 시공 공기의 단축, 공사비의 절감, 자연비탈면의 안정과 환경적인 측면을 모두 만족할 수 있는 이동형 갱구부 가시설을 제공하는 효과를 얻을 수 있다.In particular, due to the above-described reasons, it is possible to obtain an effect of providing a movable shaft provisional facility that can satisfy both the construction air shortening, construction cost reduction, stability of the natural slope and environmental aspects.
도 1은 일반적인 터널 굴착시 선시행하는 갱구부 비탈면 형성 상태를 나타내는 도면.1 is a view showing a shaft slope formed state pre-executed during general tunnel excavation.
도 2는 일반적인 갱구부에 설치되는 가시설 구성 형태를 나타내는 도면.2 is a view showing a configuration of a temporary facility installed in a general shaft portion.
도 3a는 가시설에 구조용 탄소 강관을 설치한 후 굴착 예정부로 이동시킨 상황을 나타내는 도면, 도 3b는 가시설의 사시도, 도 3c는 도 3a의 "A"부 확대도, 도 3d는 도 3b의 "B"부 확대도.Figure 3a is a view showing a state moved to the excavation scheduled portion after installing the structural carbon steel pipe in the temporary facility, Figure 3b is a perspective view of the temporary facility, Figure 3c is an enlarged view "A" of Figure 3a, Figure 3d is a "B" of Figure 3b "Wealth of Magnification.
도 4a는 가시설 구조물을 굴착 예정부에 고정시키는 측단면 구성 형태를 나타내는 도면, 도 4b는 가시설 구조물의 전방에서 본 상태를 나타내는 도면.Figure 4a is a view showing a side cross-sectional configuration of fixing the temporary construction to the excavation scheduled portion, Figure 4b is a view showing a state seen from the front of the temporary construction structure.
도 5는 가시설 설치후 굴착을 시행하는 상황을 나타내는 도면.5 is a view showing a situation of carrying out excavation after installation of temporary facilities.
도 6은 굴착 및 라이닝 설치 완료후 법면 형성 상태를 나타내는 도면.Figure 6 is a view showing the state formed on the surface after completion of excavation and lining installation.
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
1 : 자연 사면 2 : 억지말뚝1: natural slope 2: hard pile
3 : 표면보호공 4 : 통나무3: surface protector 4: log
5 : 마대 6 : 구조용 탄소강관5: Stable 6: Structural Carbon Steel Pipe
7 : 에이취(H) 8 : 철근7: H (H) 8: Rebar
9 : 지지대 10 : 토류판9: support 10: earth plate
11: 콘크리트 기초 12 : WALE11: concrete foundation 12: WALE
13 : 제거형 앵커 14 : 면벽 옹벽13: removable anchor 14: face wall retaining wall
15 : 라이닝 16 : 성토15: lining 16: fill
20 : 가시설20: provisional facilities
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020030097210A KR100546998B1 (en) | 2003-12-26 | 2003-12-26 | Construction method of temporary apparatus of thnnel for direct digging |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020030097210A KR100546998B1 (en) | 2003-12-26 | 2003-12-26 | Construction method of temporary apparatus of thnnel for direct digging |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR20-2003-0040211U Division KR200346088Y1 (en) | 2003-12-26 | 2003-12-26 | Construction structure of temporary apparatus of thnnel for direct digging |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20050066024A true KR20050066024A (en) | 2005-06-30 |
KR100546998B1 KR100546998B1 (en) | 2006-01-31 |
Family
ID=37257155
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020030097210A KR100546998B1 (en) | 2003-12-26 | 2003-12-26 | Construction method of temporary apparatus of thnnel for direct digging |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100546998B1 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100711576B1 (en) * | 2005-11-08 | 2007-04-27 | 삼성물산 주식회사 | Reinforcement structure for entrance of tunnel and construction method thereof |
CN101818645A (en) * | 2010-03-22 | 2010-09-01 | 中铁十二局集团第二工程有限公司 | Construction method for newly increasing arched open cut tunnel at railway operating line tunnel portal |
CN103967504A (en) * | 2014-05-21 | 2014-08-06 | 中国能源建设集团广东省电力设计研究院 | Supporting structure of tunnel opening of power plant circulating water system and construction method |
CN107060803A (en) * | 2016-01-26 | 2017-08-18 | 又炅技术株式会社 | A kind of method for tunnel construction of utilization pipe curtain slip casting |
CN109372541A (en) * | 2018-11-27 | 2019-02-22 | 中铁第四勘察设计院集团有限公司 | A kind of portal temporary plugging structure and its construction method suitable for shield tunnel |
CN109812277A (en) * | 2019-02-28 | 2019-05-28 | 中铁十八局集团有限公司 | A kind of vertical cliff tunnel active defense bimetallic tube canopy of high drop is appeared safely method |
CN111706351A (en) * | 2020-05-07 | 2020-09-25 | 中铁十八局集团有限公司 | Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into |
WO2022122052A1 (en) * | 2021-05-06 | 2022-06-16 | 中铁九局集团第七工程有限公司 | Comprehensive construction method for shallow buried section of tunnel using urban railway mine tunneling method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104818991B (en) * | 2015-03-30 | 2016-09-21 | 中铁二十四局集团福建铁路建设有限公司 | A kind of construction method in Shallow-buried residual soil slope tunnel |
CN109630162B (en) * | 2018-12-24 | 2020-02-14 | 中铁十八局集团有限公司 | Method for quickly connecting heavy steel and pipe curtain based on advanced support |
-
2003
- 2003-12-26 KR KR1020030097210A patent/KR100546998B1/en not_active IP Right Cessation
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100711576B1 (en) * | 2005-11-08 | 2007-04-27 | 삼성물산 주식회사 | Reinforcement structure for entrance of tunnel and construction method thereof |
CN101818645A (en) * | 2010-03-22 | 2010-09-01 | 中铁十二局集团第二工程有限公司 | Construction method for newly increasing arched open cut tunnel at railway operating line tunnel portal |
CN103967504A (en) * | 2014-05-21 | 2014-08-06 | 中国能源建设集团广东省电力设计研究院 | Supporting structure of tunnel opening of power plant circulating water system and construction method |
CN103967504B (en) * | 2014-05-21 | 2016-05-18 | 中国能源建设集团广东省电力设计研究院有限公司 | A kind of supporting construction and construction method of electric power plant circulating water system tunnel mouth |
CN107060803A (en) * | 2016-01-26 | 2017-08-18 | 又炅技术株式会社 | A kind of method for tunnel construction of utilization pipe curtain slip casting |
CN107060803B (en) * | 2016-01-26 | 2020-07-03 | 又炅技术株式会社 | Tunnel construction method by utilizing pipe curtain grouting |
CN109372541B (en) * | 2018-11-27 | 2023-09-26 | 中铁第四勘察设计院集团有限公司 | Temporary blocking structure for tunnel portal of shield tunnel and construction method thereof |
CN109372541A (en) * | 2018-11-27 | 2019-02-22 | 中铁第四勘察设计院集团有限公司 | A kind of portal temporary plugging structure and its construction method suitable for shield tunnel |
CN109812277A (en) * | 2019-02-28 | 2019-05-28 | 中铁十八局集团有限公司 | A kind of vertical cliff tunnel active defense bimetallic tube canopy of high drop is appeared safely method |
CN109812277B (en) * | 2019-02-28 | 2020-07-17 | 中铁十八局集团有限公司 | Active protection double-layer pipe shed safety hole-exiting method for high-fall vertical suspended rock tunnel |
CN111706351A (en) * | 2020-05-07 | 2020-09-25 | 中铁十八局集团有限公司 | Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into |
CN111706351B (en) * | 2020-05-07 | 2022-03-11 | 中铁十八局集团有限公司 | Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into |
WO2022122052A1 (en) * | 2021-05-06 | 2022-06-16 | 中铁九局集团第七工程有限公司 | Comprehensive construction method for shallow buried section of tunnel using urban railway mine tunneling method |
Also Published As
Publication number | Publication date |
---|---|
KR100546998B1 (en) | 2006-01-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6762800B2 (en) | Reinforcement method and structure of existing pile foundation | |
KR101696916B1 (en) | Construction method of permanent wall with retaining wall combined PHC pile and steel pipe | |
KR20170005991A (en) | soil retaining wall using PHC pile and its construction method | |
KR100794609B1 (en) | Construction method of underground structure using concrete filled pipe roof and concrete wall | |
KR100914158B1 (en) | Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut | |
KR101123668B1 (en) | The methods of Civil Foundation Safety using Plasma melting and Water cooling technology for supporting Facilities on Weak Bedsoil | |
KR101536209B1 (en) | Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method | |
JP2010090608A (en) | Method for constructing underground space and structure of the underground space | |
KR20100107937A (en) | Method for constructing fabric for undergound tunnel | |
KR100712593B1 (en) | Construction method of pipe roof structures | |
KR100546998B1 (en) | Construction method of temporary apparatus of thnnel for direct digging | |
KR20140013497A (en) | Method for constructing block type reinforced retaining wall in cut site | |
KR20070076553A (en) | Construction method of underground structure using concrete filled pipe roof and concrete wall | |
KR20030038237A (en) | Construction establishment method and the structure for underground tunnel formation | |
KR102113291B1 (en) | Soil retaining wall using phc pile and construction method thererof | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR100989984B1 (en) | Bult-in timbering roof type tunnel method | |
KR20030065963A (en) | A method of constrution method for tunnel of structure pipe | |
KR200346088Y1 (en) | Construction structure of temporary apparatus of thnnel for direct digging | |
KR20080059951A (en) | Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor | |
KR100984040B1 (en) | Method of reinforced earth retaining wall for cutting face through double reinforcing execution | |
KR20190072213A (en) | Method Of Ground Half-Openning For Tunnel Excavation | |
KR102150531B1 (en) | Retaining wall structure using vertical underground insert and its construction method | |
KR20180112453A (en) | Soil Retaining Wall using PHC Pile and Construction Method | |
KR20110034831A (en) | Method for non excavated excavating construction using steel pipe and steel pipe with hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130121 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20140410 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20141210 Year of fee payment: 10 |
|
LAPS | Lapse due to unpaid annual fee |