KR20030038237A - Construction establishment method and the structure for underground tunnel formation - Google Patents

Construction establishment method and the structure for underground tunnel formation Download PDF

Info

Publication number
KR20030038237A
KR20030038237A KR1020010069941A KR20010069941A KR20030038237A KR 20030038237 A KR20030038237 A KR 20030038237A KR 1020010069941 A KR1020010069941 A KR 1020010069941A KR 20010069941 A KR20010069941 A KR 20010069941A KR 20030038237 A KR20030038237 A KR 20030038237A
Authority
KR
South Korea
Prior art keywords
steel pipe
tunnel
pipe
steel
earth
Prior art date
Application number
KR1020010069941A
Other languages
Korean (ko)
Other versions
KR100442712B1 (en
Inventor
김정윤
Original Assignee
김정윤
정덕교
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김정윤, 정덕교 filed Critical 김정윤
Priority to KR10-2001-0069941A priority Critical patent/KR100442712B1/en
Publication of KR20030038237A publication Critical patent/KR20030038237A/en
Application granted granted Critical
Publication of KR100442712B1 publication Critical patent/KR100442712B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PURPOSE: An installation method of a structure for underground tunnel formation is provided to execute a tunnel stably and safely and to form a tunnel economically and firmly. CONSTITUTION: The installation method of a structure for underground tunnel formation comprises the steps of: measuring the appropriate position exactly according to a plane to be tunneled before jacking a steel tube, forming a lagging plate inlet on the front end of a steel tube, coupling a leading tube provided with a jacking directional control device; locating a steel tube on the driving location exactly, then jacking in stages using a hydraulic jack and an auxiliary thrust pipe, and taking a positional measurement at intervals of 1 meter to install within the minimum limit of an error using a jacking directional control device; digging up earth through a lagging plate inlet, then placing and connecting lagging plates in order; grouting around a lagging plate through a grouting injection valve to prevent the outflow of soil and to cut off water; forming a pipe fitting hole on the side of steel tubes, interposing a steel tube connecting pipe and fixing with a structure not to move or fall off; installing a form in the steel tube according to the size of a tunnel formation part and a structure; arranging reinforcing bars in the steel tube; placing concrete in the steel tube; after curing the concrete surface in the steel tube, excavating a tunnel in the steel tube; and cutting off the inside of the steel tube along a tunnel face.

Description

지하터널 형성용 구조물 설치방법 및 그 구조{Construction establishment method and the structure for underground tunnel formation}Construction method and the structure for underground tunnel formation

본 발명은 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 지하터널 형성용 구조물 설치방법 및 그 구조에 관한 것으로, 더욱 상세하게는 지하터널 구조물을 경제적이고 안전하며 정확하게 설치 할 수 있도록 하며, 구조물의 설치시는 물론 설치후에도 그 구조물이 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있도록 함은 물론 터널 완성 후에는 그 수명이 장구하도록 한 것이다.The present invention is to install a structure for forming tunnels in the ground without digging out the soil of the tunnel excavation in advance to sufficiently endure the stress in advance, and then to excavate the inside of the structure to form an underground tunnel forming structure and It relates to the structure, and more specifically, it is possible to install the underground tunnel structure economically, safely and accurately, and to make the tunnel excavation work stable as the structure is very solid structurally after installation and even after installation. Of course, after the tunnel is completed, its life is long.

일반적으로 터널을 형성하기 위해서는 반드시 터널외부로 부터 발생하는 응력에 견딜 수 있도록 터널구조물이 설치되는바, 이와같은 터널구조물을 설치하기 위한 종래의 터널구조물 설치방법의 일실시예를 설명하면 다음과 같다.In general, in order to form a tunnel, a tunnel structure is installed so as to withstand the stress generated from the outside of the tunnel. Hereinafter, an embodiment of a conventional tunnel structure installation method for installing such a tunnel structure will be described. .

먼저 도1에 도시된 바와같이 지중에 소정간격으로 대구경의 강관(10)을 터널과 같은 형태로 압입하여 강관(10)내부 및 강관(10) 외면을 그라우팅한 후에 강관(10)내측 터널면을 일정깊이로 굴착한다음 여러개로된 지보공(100)을 다수개의 볼트로 연결하여서된 지보공(100)을 구조물 내측전체에 걸쳐 설치한다음 그내측으로 콘크리트(60)를 타설하여 가시설공사를 완료하는 방법을 수차례 반복하면서 지하터널 형성용 구조물을 설치하였던바, 이와같은 일실시예에 의한 종래의 방법은 물론 그 밖의 터널구조물 설치방법들은 거의 모두가 공통적으로 일정깊이로 미리터널굴착을 한다음 가시설공사를 완료하고 지하터널 구조물을 설치하는 공법을 반복하는 방법들이어서,First, as shown in FIG. 1, a large diameter steel pipe 10 is press-fitted into a tunnel-like shape at a predetermined interval in the ground to grout the inside of the steel pipe 10 and the outer surface of the steel pipe 10, and then the inner tunnel surface of the steel pipe 10. Excavation to a certain depth and then install the jibo ball (100) by connecting a plurality of jibo ball 100 with a plurality of bolts throughout the inside of the structure and then poured concrete (60) to the inside to complete the construction work The structure for forming the underground tunnel was repeated several times, and the conventional method according to one embodiment as well as the other tunnel structure installation methods are almost all common tunneling in advance to a predetermined depth. How to complete the process and repeat the process of installing underground tunnel structures,

첫째로는 먼저 터널굴착을 선행한 후 가시설공사를 진행하여야 하므로 매번 가시설공사를 하여야 하는 번거로움이 있었으며, 안전사고의 문제점을 안고 있었다.First of all, there was a hassle of having to construct a temporary facility every time because the construction of a temporary facility should be carried out before the tunnel excavation, and there was a problem of a safety accident.

둘째로는 가시설공사를 진행하기 위해서는 먼저 터널굴착후 여러개로된 지보공(100)을 다수개의 볼트로 연결하여서 설치하여야 하는데 이 또한 작업이 매우 까다롭고 힘들어 많은 인력이 소요되고 공정이 길어 비경제적이며, 가시설의 작업으로 시공상의 작업이 매우 더딘 문제점이 있었다.Secondly, in order to proceed with the temporary construction, first, after the tunnel excavation, several jiborongs (100) must be installed by connecting them with a plurality of bolts. There was a problem that the construction work was very slow due to the work of the temporary facility.

셋째로는 선행되는 굴착작업시 너무 깊이 굴착을 하면 지반이 약할 경우 굴착도중에는 물론이고 굴착후 가시설공사중에 지반 또는 암반등이 붕괴하거나 낙하할 염려가 매우 높아서 항상 안전사고의 발생위험이 많아 항상 적은 깊이로만 굴착을 선행하여야 하므로 작업이 연관성이 결여된 문제점이 있었다.Thirdly, if the excavation is too deep during the preceding excavation work, if the ground is weak, it is very likely that the ground or rock will collapse or fall during the excavation construction as well as during the temporary construction work. Since the excavation was to be preceded only by the operation, there was a problem that the work was not related.

결국, 상기와 같이 종래의 터널구조물설치공법에 의하면 미리 터널굴착작업을선행한 후 가시설공사를 설치하고 나면 기설치된 가시설물이 간섭을 줌으로 공기가 길며, 위험하고 터널구조물을 설치할때 최소단위로 반복되는 방법이어서 많은 인력과 장비 및 자재가 소요되어 작업이 비능률적이고 비 경제적이며, 터널구조물의 지구력의 취약점때문에 항상 터널붕괴 및 안전사고의 발생위험으로 부터 벗어날 수 가 없는등의 여러가지 문제점을 않고 있었다.As a result, according to the conventional tunnel structure installation method as described above, after installing the temporary construction work after the tunnel excavation work in advance, the installed temporary facilities interfere with the air, which is long, dangerous, and at the minimum unit when installing the tunnel structure. As it is a repetitive method, it requires a lot of manpower, equipment and materials, which makes the work inefficient and inexpensive, and because of the weakness of the endurance of the tunnel structure, it was not always able to escape from the risk of tunnel collapse and safety accidents. .

이에, 상기한 방법들에 의한 터널 굴착시의 결점을 배제하여 작업상 위험성이 없고, 작업을 일관되게 능률적으로 할 수 있도록 미리 땅을 굴착하지 않은 상태에서 일시에 연속적인 굴착 공사만을 할 수 있도록 지하터널 형성용 구조물 설치방법이 안출되었는데, 이는 첨부도면 도2에 도시된 바와같이, 1.5m~2m의 대구경 강관을 터널시공예정면을 따라 지중에 압입한 다음, 상기 강관(10)과 강관(10)사이에 소구경 파이프(110)를 강관(10)과 나란히 수평으로 설치하고, 상기 양 강관(10)에 걸친 상부를 통상의 시멘트, 규산, 폴리우레탄과 같은 것으로 감싸거나 동결공법으로 감싸서 토사 붕괴 방지용 그라우팅부(70)를 형성한다음, 상기 강관들 측면의 대향되는 일정길이의 곡면 부위를 절개하여 상호 개방된 절개부를 형성하고 절개된 절개부의 상,하 양끝을 철판(120)으로 용접연결한 후 강간지주(strut)(140)를 설치하여 지지토록 하여서, 상기 강관 내부 하측을 스티로폴로 채운 후에 나머지 공간에 콘크리트로 타설하는 방법으로 지하터널 형성용 구조물을 설치하도록 한 것이다.Therefore, there is no risk of work by excluding the defects in tunnel excavation by the above methods, and only underground excavation work can be done at a time without excavating the ground so that work can be performed efficiently and consistently. A method for installing a structure for forming a tunnel was devised. As shown in FIG. 2, a large diameter steel pipe of 1.5 m to 2 m was press-fitted into the ground along the tunnel construction plan, and then the steel pipe 10 and the steel pipe 10 were inserted. The small diameter pipe 110 is installed horizontally in parallel with the steel pipe 10, and the upper portion over the both steel pipes 10 is wrapped with a cement, silicic acid, polyurethane or the like, or wrapped with a freezing method to collapse the soil. After forming the prevention grouting portion 70, by cutting the curved portion of the opposite length of the side of the steel pipe to form an incision open to each other and the upper and lower ends of the cut incision to the iron plate (1) 20) after the welding connection to install the rape column (strut) (140) to support, by filling the lower side of the inside of the steel pipe with styropol to install the structure for underground tunnel formation by placing concrete in the remaining space. .

그러나, 이와같은 방법은 첫째로는 강관과 강관사이마다 길이가 긴 소구경파이프를 전부 강제 압입하여 설치하여야 하므로, 길이가 길땐 파이프의 선도관 및 조정장치가 없어 방향성 및 직진도가 결여되어 설치가 곤란하고, 강관과 강관 사이 폭이 넓어지면 소구경 강관으로 토사방지가 불가하여 자재비 및 시공비가 많이 소요되고, 돌이 있거나 토층이 상이할 시 방향이 틀어지는등 직진도가 불확실하며, 호박돌이나 그 이상의 암석이 산재해 있을시 시공이 매우 어려우며, 강관내부에 충진공법을 병행 안할시 부식되어 취약하게 되여, 지하수 및 토류유실을 방지하기가 어렵게 되며, 파이프 내부를 충진 할시 비 경제적이다.However, in such a method, first, all long diameter pipes must be forcedly installed between the steel pipes and the steel pipes. Therefore, when the length is long, the pipes and the adjustment device of the pipes are lacking, which leads to lack of directivity and straightness. Difficult, wider width between steel and steel pipes, small diameter steel pipes are not possible to prevent earth and sand, it takes a lot of material and construction cost, and the straightness is uncertain, such as the direction is changed when there is a stone or the soil is different, amber stone or more rock When scattered, the construction is very difficult, and when the filling method is not combined with the steel pipe, it becomes vulnerable to corrosion, making it difficult to prevent groundwater and earth leakage, and it is uneconomical when filling the pipe.

둘째로는 상기 강관(10)들 측면의 대향되는 일정길이의 곡면 부위를 절개하여 상호 개방된 절개부를 형성할대 이미 상재 토압에 의해 붕괴의 우려가 있고 절개된 절개부의 상,하 양끝을 철판(120)으로 용접연결한 후 강간지주(strut)(140)를 설치하여야 하는데 이때 하부철판으로 토압이 전달되므로 보강판을 따로 설치하여 작업이 복잡하고, 별도의 철판자재가 필요하여 자재비가 과다하게 들어가 비 경제적이며, 외부응력에 견디는 힘이 약하여 사전 필요한 조치가 없을 시 구조적으로 불안전하였다.Secondly, when cutting the curved portions of a predetermined length of the sides of the steel pipes (10) to form the mutually open incisions, there is a fear of collapse by the earth pressure, and the upper and lower ends of the incisions are cut out. After the welding connection to 120), the rape column (strut) (140) should be installed. At this time, the earth pressure is transferred to the lower steel plate, so that the work is complicated by installing the reinforcement plate separately, and additional steel plate material is required, so the material cost is excessively increased. It was uneconomical and weak in external stress, structurally unstable in the absence of necessary measures.

셋째로는 상기 강관 내부 하측에 거푸집용으로 스티로폴로 채우는 작업에 있어서, 자재비가 과다하게 들며, 시공물량이 적을 경우 스치로폴의 구매가 어려위 관에 맞추어 스티로폴을 가공하거나 주문생산하여야 하고, 강관의 치수가 달라지면 치수에 맞는 스치로폴을 재 구입하여야 하므로 불편하였다.Thirdly, in filling the styropol for formwork in the lower side of the steel pipe, the material cost is excessive, and if the construction volume is small, it is difficult to purchase Styropol, and the styropol must be processed or made to order according to the pipe, and the dimensions of the steel pipe Was different, it was inconvenient because you have to repurchase Schiropol according to the dimensions.

그리고, 공사완료후 스티로폴의 폐기물은 환경에 오염을 주며 처리도 곤란하였다.After completion of the construction, Styropol's wastes were contaminated with the environment and difficult to dispose of.

넷째로는 강관내부가 무근콘크리트로 되어 있어 외부응력에 약하고 구조적으로 해석이 어렵고 또한, 보강공법을 써야 하므로 추가비용이 많이 발생되어 비경제적이고 위험요소가 산재해 있었다.Fourth, the steel pipe inside is made of plain concrete, so it is weak to external stress, difficult to interpret structurally, and reinforcement method is required.

그리고 또다른 방법으로서 안출된 것이 있는데, 이는 첨부도면 도3 에 도시된 바와같이 1m~2m의 대구경 강관을 터널시공예정면을 따라 지중에 압입한 다음, 상기 강관(10)과 강관(10)사이에 소구경 파이프(130)를 강관(10)과 나란히 수평으로 설치하고, 상기 소구경 파이프(130)와 양 강관(10)에 걸친 상부를 통상의 시멘트, 규산, 폴리우레탄과 같은 것으로 감싸거나 동결공법으로 감싸서 토사 붕괴 방지용 그라우팅부(70)를 형성한다음, 상기 강관들 측면에 지보공의 단면 직경크기 만큼 절개부를 형성하고 이에 지보공을 삽입한다음 지보공(110)과 강관들사이의 절개부의 간극을 용접후 각 지보공들의 연결부(115)를 연결하고, 상기 강관 내부에 콘크리트를 타설하는 방법을 반복하되, 그 구조물 내부위 토사를 굴착하고 상기 강관들의 하부측면을 철판(120)으로 상호연결 용접한 후 통상의 거푸집에 의한 콘크리트타설공법으로 지하구조물을 사전축조하는 방법이다.And another method has been devised, which is pressurized 1m ~ 2m large diameter steel pipe in the ground along the tunnel construction plan as shown in Figure 3, and then between the steel pipe 10 and the steel pipe (10) Install a small diameter pipe 130 in parallel with the steel pipe 10, and wrap or freeze the upper portion of the small diameter pipe 130 and the both steel pipes 10 with normal cement, silicic acid, and polyurethane. After forming a grouting part 70 to prevent the earth and sand collapse by wrapping the method, and forming a cutout in the side of the steel pipe as much as the cross-sectional diameter of the support hole and inserting the support hole therein, the gap between the support hole 110 and the incision between the steel pipes is formed. After welding, connecting the connection portion 115 of each support hole, and repeating the method of placing concrete in the steel pipe, excavating the soil inside the structure and the lower side of the steel pipe to the upper plate 120 Connected after welding is a method of pre-built an underground structure with cast-in-place concrete construction method according to a conventional die.

그러나, 이와같은 방법 또한 첫째로는 강관과 강관사이마다 길이가 긴 소구경파이프를 전부 원형식으로 설치하여야 하므로, 강관을 원형식으로 제작하기도 어렵고 제작비도 과다하며, 길이가 길어 설치가 곤란하고, 자재비 및 시공비가 많이 들며, 강관내에 추가로 충진공법이 없을 시 부식되어 취약하게 되며, 강관과 강관사이 고정연결핀이 없어 토압에 의해 강관이 이동될 수 있으며 구조물이 움직여 결정적인 문제가 야기 된다.However, in such a method, first of all, a long diameter pipe between the steel pipes and the steel pipes must be installed in a circular form. Therefore, it is difficult to manufacture the steel pipes in a circular form, the manufacturing cost is excessive, and the length is difficult to install. It costs a lot of materials and construction costs, and when there is no additional filling method in the steel pipe, it becomes vulnerable to corrosion, and there is no fixed connecting pin between the steel pipe and the steel pipe, so the steel pipe can be moved by earth pressure, and the structure moves, which causes a critical problem.

둘째로는 상기 강관 측면에 원형링의 단면 직경크기 만큼 절개부를 형성하고 이에 지보공(110)을 삽입하여야 하는데 강관길이가 길어 설치가 불가하며 단관으로 할땐 용접부위가 많아 시공이 어렵고 구조적으로 문제가 야기된다.Secondly, the incision is formed on the side of the steel pipe as much as the cross-sectional diameter size of the circular ring, and the support hole 110 is inserted therein, but the length of the steel pipe is long, so that it is impossible to install. do.

또한, 지보공(110)과 강관사이의 절개부의 간극을 용접후 각 지보공들의 연결부(115)를 연결설치하여야 하는 작업이 매우 복잡하고, 별도의 연결공정과 소구경 강관속채움이 필요하고 자재비가 과다하며 시공이 난이하다.In addition, after welding the gap of the cutout between the support hole 110 and the steel pipe, the work to connect and install the connection portion 115 of each support hole is very complicated, requires a separate connection process and small diameter steel pipe filling and excessive material costs The construction is difficult.

셋째로는 상기 대구경 강관(10) 내부 전체에 콘크리트를 타설하여야 하므로이 또한 자재비가 과다하게 들 뿐 아니라 소구경 파이프내에 콘크리트 타설이 어려워 부식으로 인한 구조해석이 안되며 강관과 강관 사이를 긴 파이프를 횡으로 설치하기가 어렵다.Third, since concrete should be poured in the entire inside of the large-diameter steel pipe 10, the material cost is not only excessive, but also concrete is difficult to be placed in the small-diameter pipe, and structural analysis due to corrosion is not possible. Difficult to install

넷째로는 상기 강관(10)들의 하부측면을 철판(120)으로 상호연결 용접하는 작업이 굴착후 천정에 용접해야 하는데 직진도(오차범위100mm)가 결여되어 용접이 불가하여 불편할 뿐만 아니라 별도의 철판(120)이 필요하므로 자재비가 과다하게 들어간다.Fourth, the work of interconnecting and welding the lower side of the steel pipes 10 to the steel plate 120 should be welded to the ceiling after excavation. Since 120 is required, the material cost is excessive.

다섯째로는 이또한 강관(10)내부가 무근콘크리트이므로 외부응력에 약하여 구조적으로 해석이 안된다.Fifthly, the steel pipe (10) inside the plain concrete, so weak to the external stress can not be interpreted structurally.

본 발명은 상기와 같은 종래의 제반 문제점을 감안하여 안출한 것으로, 터널굴착부의 토사를 미리 파내지 않고 먼저 지중에 터널형성용 구조물을 설치하여 사전에 충분히 응력에 견디도록 한다음 구조물 내측을 굴착하여 지하터널을 형성하도록 하는 지하터널 형성용 구조물 설치방법을 이용하되,The present invention has been made in view of the above-mentioned conventional problems, without first digging out the earth and sand of the tunnel excavation portion to install a tunnel-forming structure in the ground first to sufficiently withstand the stress in advance to excavate the inside of the structure Using the method of installing the underground tunnel forming structure to form the underground tunnel,

지하터널 구조물을 더욱 편리하고 신속하면서도 시공이 정확하고, 경제적으로 설치 할 수 있으며, 구조물의 설치시는 물론 설치후에도 그 구조물이 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있는 새로운 축조방법을 제공하여 결국 작업상 위험성을 완전배제하여 안심하고 터널을 형성할 수 있도록 하는 것은 물론 적은 인력과 장비 및 자재를 재활용토록 하여 경제적이고 친환경적이며 튼튼한 터널을 구축할 수 있도록 하여줌에 그 목적을 둔 것이다.It is possible to install underground tunnel structures more conveniently, quickly and accurately, and economically, and to build new tunneling method for stable tunnel excavation work because the structures are very solid structurally after installation. It aims to provide a safe and secure tunnel by completely eliminating work risks and to recycle economically, eco-friendly and durable tunnels by recycling less manpower, equipment and materials. .

도1은 종래 발명의 일실시예도.1 is an embodiment of a conventional invention.

도2는 종래 발명의 다른 실시예도.Figure 2 is another embodiment of the prior invention.

도3은 종래 발명의 또 다른 실시예도.Figure 3 is another embodiment of the prior invention.

도4는 본 발명의 일실시예를 나타낸 공정도.Figure 4 is a process diagram showing an embodiment of the present invention.

도5는 본 발명을 실시하는 선도관과 파이프의 구성도.5 is a configuration diagram of a lead pipe and a pipe according to the present invention.

도6은 본 발명의 강관을 연결파이프로 연결 지지하도록한 사각터널 시공상태 예시 정단면도.Figure 6 is a sectional front view illustrating a rectangular tunnel construction state to support the connection of the steel pipe of the present invention by connecting pipes.

도7은 본 발명의 강관을 연결파이프로 연결 지지하도록한 돔형 터널 시공상태 예시 정단면도.Figure 7 is a front sectional view illustrating a domed tunnel construction state to support the steel pipe of the present invention by connecting pipes.

도8은 본 발명을 실시하는데 따른 강관 연결상태 예시도.Figure 8 is an exemplary view of a steel pipe connection state according to the practice of the present invention.

도9는 본 발명을 실시하는데 따는 벽체 조성상태 예시도.Figure 9 is an exemplary view of the wall composition according to the practice of the present invention.

도10은 본 발명의 다른 실시상태 공정 예시도.Figure 10 is another exemplary embodiment process of the present invention.

도11은 본 발명의 다른 실시상태를 예시한 돔형터널의 정단면도.11 is a front sectional view of a domed tunnel illustrating another embodiment of the present invention.

도12는 본 발명의 다른 실시에 따른 보강상태 예시도.Figure 12 is an illustration of a reinforcement state according to another embodiment of the present invention.

도13은 본 발명의 다른 실시에 따른 사각 터널 구성상태 예시도.13 is a diagram illustrating a rectangular tunnel configuration according to another embodiment of the present invention.

♣도면의 주요 부분에 대한 부호의 설명♣♣ Explanation of symbols for the main parts of the drawing

10 : 강관 11 : 절개부10: steel pipe 11: incision

12 : 파이프삽입공 13 : 거푸집12: pipe insertion hole 13: die

15 : 보강후레임 16 : 강관 연결 파이프15: reinforcement frame 16: steel pipe connection pipe

17 : 강봉 20 : 선도관17: steel rod 20: lead pipe

21 : 토류 방지판 투입구 30 : 압입 방향 조정장치21: earth prevention plate inlet 30: indentation direction adjustment

40 : 토류 방지판 50 : 토류판40: earth prevention plate 50: earth plate

51 : 스포트잭 60 : 콘크리트51: Spot Jack 60: Concrete

70 : 그라우팅부 80 : 거푸집70: grouting part 80: formwork

90 : 보강빔 110 : 지보공90: reinforcement beam 110: jibo

111 : 콘크리트층 120 : 철판111: concrete layer 120: iron plate

130 : 소구경 파이프 200 : 터널130: small diameter pipe 200: tunnel

상기와 같은 목적을 달성하기 위한 본 발명을 일실시예에 따라 상세히 설명하면 다음과 같다.Referring to the present invention in detail according to an embodiment for achieving the above object is as follows.

실시예1Example 1

본 발명의 실시예1은 첨부도면 도4 내지 도9 에 의거 상세히 설명한다.Embodiment 1 of the present invention will be described in detail with reference to the accompanying drawings, FIGS.

(강관압입 위치측량 및 선도관설치공정)(Steel pipe press position measurement and lead pipe installation process)

강관(10)압입전 터널시공예정면을 따라 알맞는 위치를 정확하게 측량하고 도5에서와 같이 강관(10)선단에 토류방지판투입구(21)가 형성되있고 압입방향 조정장치(30)가 형성된 선도관(20)을 결합하여 강관(10)압입을 위한 준비작업을 완료한다.Precisely measure the proper position along the tunnel construction plan before press-fitting the steel pipe (10), and as shown in FIG. 5, a flow prevention plate inlet (21) is formed at the tip of the steel pipe (10) and the press-fitting direction adjusting device (30) is formed. Combine the pipe 20 to complete the preparation work for the steel pipe 10 indentation.

(강관압입공정)(Steel Pipe Intrusion Process)

강관(10)을 추진위치에 정확하게 위치시킨후 유압 잭(JACK) 및 추진보조관을 이용하여 단계적으로 압입하여 강관내부의 토사를 제거하는데 매 1M마다 위치측량을 실시하고 선도관(20)에 형성된 압입방향조정장치(30)를 이용하여 최소의 오차범위에 시공되도록 관리한다,Position the steel pipe 10 accurately in the propulsion position and press the step by step using the hydraulic jack and the propulsion auxiliary pipe to remove the earth and sand inside the steel pipe. It is managed to be installed in the minimum error range using the press-fit direction adjusting device 30,

(토류방지판 설치공정)(Earth prevention plate installation process)

도6 내지 도7 에서와 같이 상기 강관(10)압입공정에서 강관(10)을 압입할 시선도관(20)에 형성된 토류방지판투입구(21)를 통해 주변 흙을 파낸 다음 토류방지판(40)을 순차적으로 투입하여 안정되게 연결한다.As shown in Figure 6 to Figure 7 in the steel pipe 10 indentation process by digging the surrounding soil through the earth pressure plate injection hole 21 formed in the line of sight line 20 to press the steel pipe 10, the earth prevention plate 40 Connect them in order to connect stably.

(갱외 그라우팅 공정)(Outdoor grouting process)

상기 강관(10)압입 및 토류방지판(40)의 설치가 완료되면 강관(10)의 그라우팅주입밸브를 통해 토류방지판(40)주변에 그라우팅(70)하여 강관(10)하부 절개시 토사유출을 방지하도록 함은 물론 차수역활을 하도록 한다.When the steel pipe 10 is pressurized and the installation of the earth prevention plate 40 is completed, grouting (70) around the earth leakage prevention plate 40 through the grouting injection valve of the steel pipe 10 to discharge the earth and sand when cutting the bottom of the steel pipe 10. In addition to preventing them, they also play a role.

(강관연결파이프 설치공정)(Steel pipe connection pipe installation process)

상기 강관(10)압입이 완료되면 강관(10) 측면에 파이프삽입공(12)을 절개 형성하고 강관연결파이프(16)를 설치하여 움직이지 않도록 강관과 용접한다.When the pressurization of the steel pipe 10 is completed, a pipe insertion hole 12 is formed in the steel pipe 10 and cuts and a steel pipe connection pipe 16 is installed to weld the steel pipe so as not to move.

(측벽형성용 토류판설치공정)(Earth plate installation process for forming side walls)

도7 또는 도8 에서와 같이 양측 최하단의 강관(10)하측을 조성할 벽체의 폭으로 절개하고 절개부(11)를 통해 조성할 벽체의 폭으로 흙을 파내면서 측벽형성용 토류판(50)을 스포트잭(51)으로 압밀지지하여 고정하고 단계적으로 굴착하는방법으로 소정의 깊이까지 도달시키다.As shown in FIG. 7 or FIG. 8, the earth plate 50 for forming the side wall is cut while cutting the width of the wall to form the lower side of the steel pipe 10 at both ends and digging soil with the width of the wall to be formed through the cutout 11. It is brought to a predetermined depth by a method of consolidating and fixing it with a spot jack (51) and drilling stepwise.

(강관내 거푸집설치공정)(Forming process in steel pipe)

터널형성부 및 구도체의 크기에 따라 강관(10)내측에 거푸집(80)을 설치한다.Formwork 80 is installed inside the steel pipe 10 according to the size of the tunnel forming portion and the sphere.

(철근배근 공정)(Reinforcement step)

상기 강관(10)내부와 측벽형성용 토류판(50)내에 철근배근 또는 빔을 설치한다.Reinforcement bars or beams are installed inside the steel pipe 10 and the earth plate 50 for forming side walls.

(강관 및 측벽형성용 거푸집에 콘크리트 타설공정)(Concrete placing process on formwork for steel pipe and side wall formation)

상기 강관(10)내부 및 측벽형성용 토류판(50)내에 콘크리트를 주입하여 양생시킨다.The concrete is injected into the steel pipe 10 and the earth plate 50 for forming the side wall to cure.

(터널면 굴착공정)(Tunnel surface excavation process)

상기 강관(10)내부 및 측벽형성용 토류판(50)내부에 주입된 콘크리트가 모두 양생되면 강관(10) 내측의 터널(200)을 굴착한다.When all the concrete injected into the steel pipe 10 and the inside of the side plate forming earth plate 50 is cured, the tunnel 200 inside the steel pipe 10 is excavated.

(강관의 터널면절단공정)(Tunnel plane cutting process of steel pipe)

상기 강관(10)내측을 터널(200)을 따라 절단하여 지하터널 형성용 구조물 설치를 완료한다.The inside of the steel pipe 10 is cut along the tunnel 200 to complete the installation of the underground tunnel forming structure.

실시예2Example 2

본 발명의 실시예2는 첨부도면 도5 와 도9 내지 도12 에 의거 상세히 설명한다.Embodiment 2 of the present invention will be described in detail with reference to the accompanying drawings, Figs.

(강관압입 위치측량및 선도관설치공정)(Steel pipe press position measurement and lead pipe installation process)

강관(10)압입전 터널시공예정면을 따라 알맞는 위치를 정확하게 측량하고 강관(10)선단에 토류방지판투입구(21)가 형성되있고 압입방향조정장치(30)가 형성된 선도관(20)을 결합하여 강관(10)압입을 위한 준비작업을 완료한다.Precisely measure the proper position along the tunnel construction plan before press-fitting the steel pipe (10), and the leading pipe (20) having the earth prevention plate inlet (21) formed at the tip of the steel pipe (10) and the press-fitting direction adjusting device (30) formed. Combine and complete the preparation work for the press-fitting of the steel pipe (10).

(강관압입공정)(Steel Pipe Intrusion Process)

강관(10)을 추진위치에 정확하게 위치시킨후 유압 잭(JACK) 및 추진보조관을 이용하여 단계적으로 압입하며 매 1M마다 위치측량을 실시하고 선도관(20)에 형성된 압입방향조정장치(30)를 이용하여 최소의 오차범위에 시공되도록 관리한다,Position the steel pipe 10 precisely in the propulsion position and press-in step by step using a hydraulic jack and a propulsion auxiliary pipe, perform a position measurement every 1M, and a press-fit direction adjusting device 30 formed in the lead pipe 20. Use to manage the construction to the minimum error range,

(강관보강공정)(Steel Pipe Reinforcement Process)

횡빔 및 상판등을 설치하기 위해 강관을 절개할 시 토압을 견딜 수 있도록 강관(10)내부에 우선 보강판 또는 보강후레임(15)등을 관제작시 부착한 것으로 설치한다.To reinforce the steel pipe in order to install the transverse beam and the top plate, install the reinforcement plate or reinforcement frame (15) in the steel pipe (10) in order to withstand earth pressure.

(토류방지판 설치공정)(Earth prevention plate installation process)

상기 강관압입공정에서 강관(10)을 압입할 시 선도관(20)에 형성된 토류방지판투입구(21)를 통해 주변 흙을 파낸다음 토류방지판(40)을 순차적으로 투입하여안정되게 연결한다.When the steel pipe 10 is press-fitted in the steel pipe pressurizing process, the earth is prevented by digging up the surrounding soil through the earth prevention plate inlet 21 formed in the lead pipe 20 and then connecting the earth prevention plate 40 in order to connect stably.

(그라우팅 공정)(Grouting Process)

상기 강관(10)압입 및 토류방지판(40)의 설치가 완료되면 강관(10)에 기 제작시 부착되어 있는 그라우팅주입밸브를 통해 토류방지판(40)주변에 그라우팅(70)하여 강관(10)하부 절개시 토사유출을 방지하도록 함은 물론 차수역활을 하도록 한다.When the installation of the pressurization and the earth prevention plate 40 of the steel pipe 10 is completed, the steel pipe 10 is grouted around the earth leakage prevention plate 40 through a grouting injection valve attached to the steel pipe 10. In order to prevent sediment leakage during the lower incision, it is also necessary to play a role.

(강관연결공정)(Steel Pipe Connection Process)

강관(10)의 측면을 소정폭으로 길이방향 끝까지 절개한다음 강관과 강관사이를 철판(120)으로 연결한다.The side surface of the steel pipe 10 is cut to the lengthwise end in a predetermined width and then connected between the steel pipe and the steel pipe with an iron plate 120.

이때 가드 및 횡빔을 설치하여 보강 할 수도 있다.At this time, guards and side beams can be installed and reinforced.

(측벽형성용 토류판 설치공정)(Installation process of earth plate for side wall formation)

양측 최하단의 강관(10)하측을 조성할 벽체의 폭으로 절개하고 절개부(11)를 통해 조성할 벽체의 폭으로 흙을 파내면서 측벽형성용 토류판(50)을 스포트잭으로 압밀지지하여 고정하고 단계적으로 굴착하는방법으로 소정의 깊이까지 도달시키다.Incision is made by cutting the width of the wall to form the lower side of the steel pipe (10) at the bottom of both sides and digging soil into the width of the wall to be formed through the incision (11) while holding the earth plate for sidewall formation by consolidating with a spotjack. Reach to a predetermined depth by excavation step by step.

(강관내 거푸집설치공정 )(Formwork installation process in steel pipe)

터널부(200) 및 구조체의 크기에 따라 강관(10)내측에 거푸집(80)을 설치한다.Formwork 80 is installed inside the steel pipe 10 according to the size of the tunnel 200 and the structure.

(철근배근 공정)(Reinforcement step)

상기 강관(10)내부와 측벽형성용 토류판(50)내에 철근배근 또는 빔을 설치한다.Reinforcement bars or beams are installed inside the steel pipe 10 and the earth plate 50 for forming side walls.

(강관 및 측벽형성용 거푸집에 콘크리트 타설공정)(Concrete placing process on formwork for steel pipe and side wall formation)

상기 강관(10)내부 및 측벽형성용 토류판(50)내에 콘크리트를 주입하여 양생시킨다.The concrete is injected into the steel pipe 10 and the earth plate 50 for forming the side wall to cure.

이와같이 하면 강관(10)내부의 콘크리트가 처음부터 끝까지 서로 연결된 견고한 콘크리트구조물을 얻을 수 있음은 물론 터널형성시 노출되는 파이프의 부식방지와 장기간 유지보수비의 비용이 절약되어 경제적이고 또한 차수역활을 완벽하게 할 수 있다.In this way, not only can the concrete inside the steel pipe 10 be connected to each other from the beginning to the end, but also the cost of corrosion prevention and long-term maintenance costs of the pipes exposed during the tunnel formation can be saved economically and perfectly fulfill the order role. can do.

(터널면 굴착공정)(Tunnel surface excavation process)

상기 강관(10)내부 및 측벽형성용 토류판(50)내부에 주입된 콘크리트가 모두 양생되면 강관(10 내측의 터널부(200)를 굴착한다.When both the concrete injected into the steel pipe 10 and the inside of the side plate forming earth plate 50 is cured, the tunnel 200 inside the steel pipe 10 is excavated.

(강관의 터널면절단공정)(Tunnel plane cutting process of steel pipe)

상기 강관(10)내측을 터널면을 따라 절개하여 지하터널 형성용 구조물 설치를 완료한다.The inside of the steel pipe 10 is cut along the tunnel surface to complete the installation of the underground tunnel forming structure.

여기서, 상기 실시예1,2에서 제시된 강관보강공정에서 토압을 견딜 수 있도록 강관(10)내부에 설치되는 보강판 또는 보강후레임(15)등은, 첨부도면 도12 또는 도13 과 같은 일설치예와 같이 강관(10)내부에 소정간격으로 원형링을 용접설치하고 필요에 따라서 원형링을 H빔과 같은 각종 수평후레임 등으로 연결하여서 토압에 견디는 강도를 더욱 보강함으로써 각종작업시 안전하도록 하였다.Here, the reinforcement plate or reinforcement frame 15 installed inside the steel pipe 10 to withstand earth pressure in the steel pipe reinforcing process presented in Examples 1 and 2 is one installation example as shown in FIG. 12 or 13. As described above, the circular ring was welded to the inside of the steel pipe 10 at predetermined intervals, and the circular ring was connected to various horizontal frames such as H beams as needed to further reinforce the strength against earth pressure, thereby making it safe during various operations.

그리고, 상기 토류방지판설치공정에서 강관(10)을 압입할 시 선도관(20)에 형성된 토류방지판투입구(21)를 통해 주변 흙을 파낸다음 순차적으로 투입연결되는 토류방지판(40)은 여러가지를 사용할 수 있지만 주로 값이 싸서 경제적이고 강관(10)과 강관(10)과의 사이가 좁거나 넓을 경우에도 폭에 맞추어 손쉽게 절단하여 설치할 수 있도록 하고 협소한 공간에서도 가볍고 손쉽게 설치 할 수 있는 목재를 사용한다.When the steel pipe 10 is press-fitted in the earth prevention plate installation process, the earth prevention plate 40 which is sequentially inserted and connected to the earth is excavated through the earth prevention plate inlet 21 formed in the leading pipe 20. Although it can be used in various ways, it is mainly cheap, so it is economical and can be easily cut and installed according to the width even when the space between the steel pipe (10) and the steel pipe (10) is narrow or wide, and light and easy to install even in a narrow space. Use

또한, 상기 실시예1의 횡빔 연결파이프 설치공정에서 사용되는 강관연결파이프(16)는,In addition, the steel pipe connection pipe 16 used in the horizontal beam connection pipe installation step of the first embodiment,

소정의 길이에 따라 파이프를 절단한 후 연결파이프 좌,우에 구멍을 뚫은 다음 여기에 강봉(17)을 용접으로 결합하여 콘크리트 타설후 구조체와 일체되게 고정되도록 함으로 강봉(17)에 의해 횡빔이 강관과 강관으로 부터 움직이거나 빠지지 않도록 미연에 방지하도록 하였다.After cutting the pipe according to a predetermined length, the holes are drilled in the left and right connecting pipes, and then the steel bars 17 are welded thereto to be fixed together with the structure after the concrete is placed so that the transverse beams are formed by the steel bars 17. It is to prevent it from moving or falling out of the steel pipe.

이때, 상기 강봉(17)은 십자형태로 결합되도록 구성하는 것이 본 구조체와 고정되는 것이 가장 이상적이다.At this time, the steel bar 17 is configured to be coupled to the cross shape is most ideally fixed with the present structure.

그리고, 상기 실시예2의 강관연결공정에서 사용되는 철판(120)은 강관(10)들 측면을 소정폭으로 길이방향 끝까지 절단하여서 생긴 철판을 재사용하도록 하였다.In addition, the iron plate 120 used in the steel pipe connection process of Example 2 was to reuse the iron plate produced by cutting the steel pipe 10 side to the longitudinal end in a predetermined width.

한편, 상기 실시예1,2의 강관의 터널면절단공정에서 생긴 철판은 수집하였다가 차후의 터널구조물 공사시 상기 실시예1의 그라우트용 강관연결파이프 설치공정에서 그라우트용 강관연결파이프(16)연결시 재사용하거나, 상기 실시예2의 강관연결공정에서 길이방향으로 절단된 부분에 재사용할 수 있도록 하였다.On the other hand, the steel plate produced in the tunnel surface cutting process of the steel pipes of Examples 1 and 2 was collected, and the connection of grout steel pipe connecting pipe 16 in the installation process of the steel pipe connecting pipe for grout of Example 1 during the subsequent tunnel structure construction. When reused or in the steel pipe connection process of Example 2 was to be reused in the longitudinally cut portion.

상기와 같은 본 발명은 종래와 같이 강관과 강관사이에 설치가 불가하고 비경제적인 길이가 긴 소구경의 파이프를 압입하지 않고 선도관에 형성된 토류방지판투입구를 통해 목재로된 토류방지판을 설치하므로 시공이 간편하고 자재비가 저렴하며, 선도관에서 설치함으로 호박돌이나 그 밖의 장해물을 신속히 제거해가면서 진행할 수 있어서 설치가 용이하고 직선도가 우수하며 길이에 제한을 받지 않는 것은 물론 강관가 강관사이의 폭의 넓고 좁은에 상관없이 목재사이즈를 임으로 변경하여 사용할 수 있고 좁은 공간에서 가벼운 목재를 사용함으로 시공성이 좋고 경제적이며 완벽하여 토류를 방지의 효과가 우수하다.The present invention as described above is because it is impossible to install between the steel pipe and the steel pipe as in the prior art, because it is installed through the earth prevention plate inlet formed in the lead pipe without injecting a small diameter pipe of long length uneconomical length It is easy to install and the material cost is low, and it is easy to install, excellent in straightness, not limited by the length, and wide between the steel pipes. Regardless of the narrowness, the wood size can be changed randomly and the lightness of the timber is used in the narrow space.

그리고, 본 발명은 실시예1에서 강관과 강관사이를 연결하는 횡빔파이프는 강관과 강관사이만 부분 적으로 설치하여 보강하므로 자재비가 저렴하고, 제작이 간편하며, 강관연결파이프가 단관이므로 설치하기가 매우 용이함은 물론 횡빔파이프 끝단에 강관과 강관 이탈방지용 강봉을 설치하여 강관연결파이프가 콘크리트 구조체에서 고정되어 움직이지 않도록 미연에 방지하므로 안전하게 구조체를 형성시킬수 있어 구조적으로 안전하다.And, in the present invention, the transverse beam pipe connecting between the steel pipe and the steel pipe in Example 1 is partially installed between the steel pipe and the steel pipe to reinforce the material cost is cheap, easy to manufacture, and is easy to install because the steel pipe connection pipe is short pipe Very easy, of course, by installing a steel pipe and steel pipe separation prevention bar at the end of the lateral beam pipe to prevent the steel pipe connection pipe is fixed in the concrete structure to prevent movement in advance, it is possible to form a structure safely.

또한, 절개부위의 보강재와 방수용 철판은 별도의 보강자재를 사용하는 것이아니라 기 강관내 설치된 강관이 상부토압으로 부터 견딜수 있도록 사전에 제작되어 있으므로 강관에서 절단된 반원형의 철판을 강관연결파이프 주변에 쉽게 보강 또는 방수용으로 사용하므로서 설치가 용이하며 강관폐자재를 재활용할 수 있어서 별도의 자재비가 소요되지 않아 자재비가 절감되며 설치가 매우 용이하고 안전하다.In addition, the reinforcement of the incision and the waterproof steel plate do not use separate reinforcement materials, but the steel pipe installed in the machine pipe is manufactured in advance so that it can withstand the upper earth pressure. As it is used for reinforcement or waterproofing, it is easy to install and recycled steel pipes and materials can be recycled.

또한, 본 발명은 강관내측에 콘크리트 타설을 위한 거푸집용으로 종래와 같이 설치 가공 및 구매가 어렵고 환경오염을 유발시키는 스치로폴을 설치하는 것이 아니라 목재거푸집을 설치하므로 구매가 용이하며, 자재비가 저렴하고 무엇보다도 설치 높이나 두께등에 전혀 제한을 받지 않고 설치할 수 있어 경제적이며 폐자재가 발생되지 않아 환경친화적이다.In addition, the present invention is easy to purchase because it is difficult to install and process as a conventional formwork for concrete placing inside the steel pipe and install wood formwork rather than installing Schiropol to cause environmental pollution, material cost is cheap and what Rather, it can be installed without any restrictions on installation height or thickness, so it is economical and environmentally friendly because no waste materials are generated.

한편, 본 발명은 종래와 같이 강관 내부가 무근콘크리트로 형성되는 것이 아니라 토압을 견딜 수 있도록 강관내부에 소정의 간격으로 횡보를 설치하되, 원형링을 설치한 다음 설치가 용이하고 경제적인 소구경 파이프나 H빔과 같은 각종 수평후레임 등을 원형링과 병행되게 용접설치하여 보강함으로써 구조적으로 안전하게 하였다.On the other hand, the present invention is a steel pipe inside the steel pipe is not formed as a concrete as in the prior art, but to install a sideways at a predetermined interval inside the steel pipe to withstand the earth pressure, the circular ring is easy to install and economical small diameter pipe Various horizontal frames such as H beam were welded and reinforced in parallel with the circular ring to make them structurally safe.

또한, 상판 및 횡빔을 설치하고자 강관측면을 소정폭의 길이방향으로 끝까지 절단할 수 있도록 이미 보강링이 안전하게 설치제작되어 있는등 각종 작업시 안전하도록 함은 물론 철근콘크리트 구조임으로 매우 안정되고 견고하다.In addition, the reinforcement ring is already installed and manufactured so that the steel pipe side can be cut to the end in the longitudinal direction of the predetermined width in order to install the top plate and the transverse beam.

또한, 터널굴착후 노출되는 철판 및 파이프등의 부식방지의 경제적 부담과 요철부위의 미적문제 및 장기간 유지보수비의 과다등을 완전히 해소했다.In addition, the economic burden of corrosion protection of steel plates and pipes exposed after tunnel excavation, aesthetic problems of uneven parts, and excessive maintenance costs have been completely eliminated.

결국, 본 발명은 지하터널 구조물을 더욱 안전하고 신속하면서도 시공이 정확하고, 경제적으로 설치 할 수 있으며 환경친화적으로 시공할 수 있다.As a result, the present invention can be installed more securely and quickly while the construction is accurate, economical installation and environmentally friendly construction of underground tunnel structures.

그리고 구조물의 설치시는 물론 설치후에도 구조적으로 매우 견고하여 터널굴착 작업을 안정적으로 할 수 있는 것은 물론 적은 인력과 장비 및 폐자재를 재사용하는 등 경제적이고 튼튼한 터널을 구축할 수 있는 매우 획기적인 발명이다.In addition, it is a very innovative invention that can construct a tunnel that is economical and sturdy, such as not only stable construction of the tunnel, but also a stable construction of the tunnel, as well as the reuse of less manpower, equipment, and waste materials.

Claims (10)

강관(10)압입전 터널시공예정면을 따라 알맞는 위치를 정확하게 측량하고 강관(10)선단에 토류방지판투입구(21)가 형성되고 압입방향조정장치(30)가 형성된 선도관(20)을 결합하여 강관(10)압입을 위한 준비작업을 완료하는 강관압입 위치측량 및 선도관설치공정과,Precisely measure the proper position along the tunnel construction plan before press-fitting the steel pipe (10), and the leading pipe (20) having the earth prevention plate inlet (21) formed at the tip of the steel pipe (10) and the press-fitting direction adjusting device (30) formed. Steel pipe press position measurement and leading pipe installation process to complete the preparation work for press-fitting the steel pipe (10), 강관(10)을 추진위치에 정확하게 위치시킨후 유압 잭(JACK) 및 추진보조관을 이용하여 단계적으로 압입하며 매 1M마다 위치측량을 실시하고 선도관(20)에 형성된 압입방향조정장치(30)를 이용하여 최소의 오차범위에 시공되도록 하는 강관압입공정과,Position the steel pipe 10 precisely in the propulsion position and press-in step by step using a hydraulic jack and a propulsion auxiliary pipe, perform a position measurement every 1M, and a press-fit direction adjusting device 30 formed in the lead pipe 20. Steel pipe press process to be constructed in the minimum error range using the 상기 강관압입공정에서 강관(10)을 압입할 시 선도관(20)에 형성된 토류방지판투입구(21)를 통해 주변 흙을 파낸다음 토류방지판(40)을 순차적으로 투입연결하는 토류방지판 설치공정과,When the steel pipe 10 is press-fitted in the steel pipe pressurization process, the earth prevention plate is installed through the earth prevention plate inlet 21 formed in the leading pipe 20 to dig out the soil around the earth prevention plate 40. Fair, 상기 강관(10)압입 및 토류방지판(40)의 설치가 완료되면 강관(10)에 그라우팅주입밸브를 통해 토류방지판(40)주변에 그라우팅(70)하여 강관(10)하부 굴착시 토사유출을 방지하도록 함은 물론 차수역활을 하도록 하는 갱외 그라우팅 공정과,When the steel pipe 10 is pressurized and the installation of the earth prevention plate 40 is completed, grouting around the earth prevention plate 40 through the grouting injection valve on the steel pipe 10 to excrete soil leakage during the excavation of the bottom of the steel pipe 10. And the out-of-gang grouting process to serve as a degree of order, 상기 갱외 그라우팅(70) 및 강관(10)압입이 완료되면 강관(10)들 측면에 파이프 삽입공(12)을 형성하고 강관연결파이프(16)를 삽입하여 구조체와 고정시켜 움직이거나 빠지지 않도록 용접하는 거드 및 횡빔용 연결파이프 설치공정과,When the out-of-gang grouting 70 and the steel pipe 10 pressurization is completed, the pipe insertion hole 12 is formed on the sides of the steel pipes 10 and the steel pipe connection pipe 16 is inserted to fix the structure to weld or move so as not to fall out. Connecting pipe installation process for girdle and transverse beam, 터널형성부 및 구조체의 크기에 따라 강관(10)내측에 거푸집(80)을 설치하는강관내 거푸집설치공정과,Formwork installation process in the steel pipe to install the formwork 80 inside the steel pipe 10 according to the size of the tunnel forming portion and the structure, 상기 강관(10)내부에 철근배근을 하는 철근배근 공정과,Reinforcement step and the reinforcement step to the reinforcement inside the steel pipe (10), 상기 강관(10)내부에 콘크리트를 주입하여 양생시키는 콘크리트 타설공정과,Concrete pouring process for curing by injecting concrete into the steel pipe 10, 상기 강관(10)내부에 주입된 콘크리트가 모두 양생되면 강관(10) 내측의 터널부(200)를 굴착하는 터널 굴착공정과,Tunnel excavation process for excavating the tunnel portion 200 inside the steel pipe 10 when all the concrete injected into the steel pipe 10 is cured, 상기 강관(10)내측을 터널면을 따라 절단하여 지하터널 형성용 구조물 설치를 완료하는 강관의 터널면절단공정을 포함하여서 이루어짐을 특징으로 하는 지하터널 형성용 구조물 설치방법.And the tunnel surface cutting process of the steel pipe to cut the inner side of the steel pipe 10 along the tunnel surface to complete the installation of the underground tunnel forming structure. 강관(10)압입전 터널시공예정면을 따라 강관(10)의 직경에 알맞는 위치를 정확하게 측량하고 직경이 1m~3m정도 되는 대구경의 강관(10)선단에 토류방지판투입구(21)가 형성되고 압입방향조정장치(30)가 형성된 선도관(20)을 결합하여 강관(10)압입을 위한 준비작업을 완료하는 강관압입 위치측량및 선도관설치공정과,Precisely measure the position suitable for the diameter of the steel pipe 10 along the planned tunnel construction before the press-fitting of the steel pipe 10, and the earth prevention plate inlet 21 is formed at the tip of the large diameter steel pipe 10 having a diameter of about 1m to 3m. Steel pipe press position measurement and lead pipe installation process to complete the preparation work for pressing the steel pipe 10 by combining the leading pipe 20, the press pipe direction adjusting device 30 is formed, 강관(10)을 추진위치에 정확하게 위치시킨후 유압 잭(JACK) 및 추진보조관을 이용하여 단계적으로 압입하며 매 1M마다 위치측량을 실시하고 선도관(20)에 형성된 압입방향조정장치(30)를 이용하여 최소의 오차범위에 시공되도록 하는 강관압입공정과,Position the steel pipe 10 precisely in the propulsion position and press-in step by step using a hydraulic jack and a propulsion auxiliary pipe, perform a position measurement every 1M, and a press-fit direction adjusting device 30 formed in the lead pipe 20. Steel pipe press process to be constructed in the minimum error range using the 토압을 견딜 수 있도록 강관(10)내부에 보강판 및 보강후레임(15)을 설치하는 강관보강공정과,Steel pipe reinforcement process of installing a reinforcement plate and reinforcement frame (15) in the steel pipe (10) to withstand earth pressure, 상기 강관압입공정에서 강관(10)을 압입할 시 선도관(20)에 형성된 토류방지판투입구(21)를 통해 주변 흙을 파낸다음 토류방지판(40)을 순차적으로 투입연결하는 토류방지판 설치공정과,When the steel pipe 10 is press-fitted in the steel pipe pressurization process, the earth prevention plate is installed through the earth prevention plate inlet 21 formed in the leading pipe 20 to dig out the soil around the earth prevention plate 40. Fair, 상기 강관(10)압입 및 토류방지판(40)의 설치가 완료되면 강관(10)에 그라우트주입밸브를 통해 토류방지판(40)주변에 그라우팅부(70)를 형성하여 강관(10)하부 굴착시 토사유출을 방지하도록 함은 물론 차수역활을 하도록 하는 갱외 그라우팅 공정과,When the installation of the steel pipe 10 press-fit and the earth prevention plate 40 is completed, a grouting part 70 is formed around the earth prevention plate 40 through a grout injection valve in the steel pipe 10 to excavate the bottom of the steel pipe 10. An out-of-gang grouting process that not only prevents soil leakage but also plays a role in 강관(10)측면을 소정폭으로 길이방향으로 끝까지 절개한다음 절개부(11)를 철판(120)으로 연결하는 강관연결공정과,A steel pipe connection process of cutting the side of the steel pipe 10 in the longitudinal direction to a predetermined width and then connecting the cutout portion 11 to the iron plate 120; 터널형성부의 크기에 따라 강관(10)내측에 거푸집(80)을 설치하는 강관내 거푸집설치공정과,Formwork installation process in the steel pipe to install the formwork 80 inside the steel pipe 10 according to the size of the tunnel forming portion, 상기 강관(10)내부와 측벽형성용 거푸집(80)내에 철근배근을 하는 철근배근 공정과,Reinforcing bar reinforcement step to the reinforcement in the steel pipe 10 and the formwork for forming the side wall (80), 상기 강관(10)내부에 콘크리트를 주입하여 양생시키는 콘크리트 타설공정과,Concrete pouring process for curing by injecting concrete into the steel pipe 10, 상기 강관(10)내부에 주입된 콘크리트가 모두 양생되면 강관(10) 내측의 터널부(200)를 굴착하는 터널 굴착공정과,Tunnel excavation process for excavating the tunnel portion 200 inside the steel pipe 10 when all the concrete injected into the steel pipe 10 is cured, 상기 강관(10)내측 터널에 돌출된 부분을 절단하는 강관의 터널면절단공정으로 이루어짐을 특징으로 하는 지하터널 형성용 구조물 설치방법.The steel pipe (10) underground tunnel forming structure installation method, characterized in that made of a tunnel surface cutting process of the steel pipe to cut the protruding portion in the inner tunnel. 직경이 1m~3m정도 되는 다수의 대구경의 강관(10)을 터널시공예정면에 )을 압입하되, 상기 강관(10)들 사이에 흙을 파낸다음 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하며,Press a plurality of large diameter steel pipes 10 having a diameter of about 1m to 3m into a tunnel construction plan, but dig soil between the steel pipes 10 and then connect the earth prevention plate 40 sequentially. And grouting to form a grouting portion 70, 상기 강관(10)들 측면에 파이프삽입공(12)을 형성하고 이에 중공의 강관연결파이프(16)를 삽입하여 강관(10)들과 용접 고정시켜 움직이거나 빠지지 않도록 하고,Pipe insertion hole 12 is formed on the sides of the steel pipes 10 and the hollow pipe connection pipe 16 is inserted therein to fix welding with the steel pipes 10 so as not to move or fall out. 상기 강관(10) 내측에 터널형성부의 크기에 따라 거푸집(80)을 설치한 후에 철근배근 하여서 콘크리트를 주입하고 양생이 완료되면 터널을 굴착한후에 상기 강관(10)의 터널측으로 돌출된 부분을 절단하여 구성됨을 특징으로 하는 지하터널 형성용 구조물 구조.After installing the formwork 80 in accordance with the size of the tunnel forming part inside the steel pipe 10, reinforced concrete is injected, and when curing is completed, the tunnel is excavated after cutting the tunnel to cut the portion projecting to the tunnel side Structure structure for underground tunnel formation, characterized in that configured. 직경이 1m~3m정도 되는 대구경의 강관(10)을 터널시공예정면에 압입하되 상기 강관(10)들 사이에 흙을 파낸다음 토류방지판(40)을 순차적으로 투입하여 연결하고 그라우팅함으로서 그라우팅부(70)를 형성하며,Grouting part by inserting the large diameter steel pipe 10 having a diameter of about 1m ~ 3m to the tunnel construction plan, digging out soil between the steel pipes 10, and then connecting and grouting the earth prevention plate 40 in sequence. Forms 70, 상기 강관(10)을 보강후레임(15)으로 보강한 다음 소정폭으로 길이방향으로 끝까지 절개한다음 두 강관(10)을 철판(120)으로 연결하고,The steel pipe 10 is reinforced with a reinforcement frame 15 and then cut in the longitudinal direction to the end in a predetermined width, and then the two steel pipes 10 are connected to the steel plate 120. 터널형성부의 크기에 따라 강관(10)내측에 거푸집(80)을 설치한 후에 강관(10)내부 보강빔(90)과 철근배근 한다음 상기 강관()내부 및 측벽형성용 거푸집()내에 콘크리트를 주입하고 양생이 완료되면 터널면을 굴착한후에 상기 강관()의 터널면을 절단하여서 구성함을 특징으로 하는 지하터널 형성용 구조물 구조.After the formwork 80 is installed inside the steel pipe 10 according to the size of the tunnel forming part, the reinforcing beam is reinforced with the internal reinforcing beam 90 of the steel pipe 10, and then concrete is formed inside the steel pipe () and the formwork for forming the side wall (). After the injection and curing is completed, the tunnel structure of the underground tunnel forming structure, characterized in that by cutting the tunnel surface of the steel pipe () after excavating the tunnel surface. 제1항 또는 제2항에 있어서The method according to claim 1 or 2 상기 설치된 강관(10)중 양측 최하단의 강관 하측을 조성할 벽체의 폭으로 절개하고 절개부(11)를 통해 조성할 벽체의 폭으로 흙을 파내면서 측벽형성용 토류판(50)을 스포트잭(51)으로 압밀지지하여 고정하고 단계적으로 굴착하는 방법으로 소정의 깊이까지 도달시키는 측벽 형성용 토류판 설치 공정을 더 포함함을 특징으로 하는 지하터널 형성용 구조물 설치방법.Spot the earth plate 50 for sidewall formation while cutting in the width of the wall to form the lower side of the steel pipe of the lower side of the both sides of the installed steel pipe 10 and excavating the soil with the width of the wall to be formed through the incision (11) The method of installing an underground tunnel, characterized in that it further comprises a step of installing the earth plate for forming the side wall to reach a predetermined depth by a method of consolidating and fixing by step and excavation. 제3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 설치된 강관(10)중 양측 최하단의 강간(10) 하측을 벽체를 형성할 폭으로 절개하고 절개부(11) 아래측을 파내서 양측벽면을 토류판(50)으로 막아서 스포트잭(51)으로 압밀고정한 상태에서 철근을 배근하고 콘크리트를 타설하여 상기 강관 내부와 일체로 벽면을 구성함을 특징으로 하는 지하터널 형성용 구조물 구조.The lower side of the rape 10 at the bottom of both sides of the installed steel pipe 10 is cut to a width to form a wall, and the bottom side of the cut pipe 11 is dug to block both side walls with the earth plate 50 to be consolidated with a spot jack 51. A structure structure for underground tunnel formation, comprising reinforcing steel in a fixed state and placing concrete to form a wall integrally with the inside of the steel pipe. 제3항에 있어서,The method of claim 3, 상기 강관연결파이프(16)는,The steel pipe connecting pipe 16, 중공부가 강관(10) 내부와 연통되어 강관(10) 내부에 주입되는 콘크리트(60)가 강관 연결파이프(16)의 내부에 채워져 일체로 성형되도록 함과 동시에 강관으로부터 이탈하지 않도록 양단부에 플랜지나 강봉(17)을 일체로 형성함을 특징으로하는 지하터널 형성용 구조물 구조.The hollow portion communicates with the inside of the steel pipe 10 so that the concrete 60 injected into the steel pipe 10 is filled in the steel pipe connecting pipe 16 to be integrally formed and at the same time flanges or steel bars at both ends so as not to be separated from the steel pipe. Structure structure for forming underground tunnels, characterized in that (17) formed integrally. 제3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 강관(10)내부에 설치되는 보강판 및 보강후레임(15)은, 강관(10)내부에 소정간격으로 원형링을 용접설치하고 필요에 따라서 원형링을 소구경파이프와 수평후레임등으로 연결하여서 토압을 횡으로 전달하여 토압에 견디는 강도를 보강하도록 구성함을 특징으로 하는 지하터널 형성용 구조물 구조.The reinforcement plate and the reinforcement frame 15 installed in the steel pipe 10 are welded and installed with a circular ring at predetermined intervals in the steel pipe 10, and the circular ring is connected with a small diameter pipe and a horizontal frame as necessary. Underground tunnel formation structure structure characterized in that configured to reinforce the strength to withstand the earth pressure by transmitting the earth pressure transversely. 제3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 강관(10)을 압입할 시 선도관(20)에 형성된 토류방지판투입구(21)를 통해 주변 흙을 파낸다음 순차적으로 투입연결되는 토류방지판(40)은,When press-fitting the steel pipe 10, the earth prevention plate 40 is dug through the earth prevention plate inlet 21 formed in the leading pipe 20 and then sequentially connected to the earth, 강관(10)과 강관(10)과의 사이가 좁거나 넓을 경우에도 폭에 맞추어 손쉽게 절단하여 설치할 수 있도록 목재로 구성함을 특징으로 하는 지하터널 형성용 구조물 구조.Structure structure for underground tunnel formation, characterized in that made of wood to be easily cut and installed according to the width, even if the steel pipe 10 and the steel pipe 10 between the narrow or wide. 제7항에 있어서,The method of claim 7, wherein 상기 강관연결파이프(16)의 양측단에 플랜지를 일체로 형성한 것을 특징으로 하는 지하터널 형성용 구조물 구조.Structure structure for underground tunnel formation, characterized in that the flange is formed integrally at both ends of the steel pipe connection pipe (16).
KR10-2001-0069941A 2001-11-10 2001-11-10 Construction establishment method and the structure for underground tunnel formation KR100442712B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0069941A KR100442712B1 (en) 2001-11-10 2001-11-10 Construction establishment method and the structure for underground tunnel formation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0069941A KR100442712B1 (en) 2001-11-10 2001-11-10 Construction establishment method and the structure for underground tunnel formation

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020010034641U Division KR200274812Y1 (en) 2001-11-12 2001-11-12 the structure for underground tunnel formation

Publications (2)

Publication Number Publication Date
KR20030038237A true KR20030038237A (en) 2003-05-16
KR100442712B1 KR100442712B1 (en) 2004-08-02

Family

ID=29568866

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0069941A KR100442712B1 (en) 2001-11-10 2001-11-10 Construction establishment method and the structure for underground tunnel formation

Country Status (1)

Country Link
KR (1) KR100442712B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100723024B1 (en) * 2005-11-17 2007-05-31 주식회사 엔티에스이앤씨 Construction establishment method and the structure for underground tunnel formation
KR100725952B1 (en) * 2005-10-27 2007-06-11 주식회사 엔티에스이앤씨 It establishes the tunnel formation tunnel structure the Maine pipe construction method
KR100781357B1 (en) * 2006-06-22 2007-11-30 주식회사 엔티에스이앤씨 It establishes the tunnel formation tunnel structure the maine pipe construction method
CN111677518A (en) * 2020-07-08 2020-09-18 北京建工土木工程有限公司 Shield receiving end reinforcing structure, reinforcing method and shield receiving method
CN111677519A (en) * 2020-07-08 2020-09-18 北京建工土木工程有限公司 Shield starting end reinforcing structure, reinforcing method and shield starting method
CN113685187A (en) * 2021-08-16 2021-11-23 北京市市政一建设工程有限责任公司 Small-clear-distance multi-hole underground excavation tunnel construction process
CN113982630A (en) * 2021-10-29 2022-01-28 成都未来智隧科技有限公司 Tunnel supporting structure
CN115492598A (en) * 2022-09-27 2022-12-20 中铁第四勘察设计院集团有限公司 Tunnel linear excavation method of single guide pipe

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101041301B1 (en) 2010-07-29 2011-06-14 이평우 Method for digging tunnel
KR101040066B1 (en) 2010-12-07 2011-06-09 홍익컨스텍(주) Method of constructing non-excavation type tunnel
KR101275468B1 (en) * 2011-09-19 2013-06-17 이동헌 The structure assembly for building a tunnel and building method thereof
KR101412033B1 (en) 2013-08-07 2014-06-26 강태욱 The structure assembly for building a tunnel and building method thereof
CN103884324B (en) * 2014-04-16 2016-03-30 天津市管道工程集团有限公司 The orientation measurement method of underground pipeline jacking crossing construction
KR102135566B1 (en) 2020-03-02 2020-07-20 주식회사 그린개발 Non excavation type underground tunnel construction method using steel pipe

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100725952B1 (en) * 2005-10-27 2007-06-11 주식회사 엔티에스이앤씨 It establishes the tunnel formation tunnel structure the Maine pipe construction method
KR100723024B1 (en) * 2005-11-17 2007-05-31 주식회사 엔티에스이앤씨 Construction establishment method and the structure for underground tunnel formation
KR100781357B1 (en) * 2006-06-22 2007-11-30 주식회사 엔티에스이앤씨 It establishes the tunnel formation tunnel structure the maine pipe construction method
CN111677518A (en) * 2020-07-08 2020-09-18 北京建工土木工程有限公司 Shield receiving end reinforcing structure, reinforcing method and shield receiving method
CN111677519A (en) * 2020-07-08 2020-09-18 北京建工土木工程有限公司 Shield starting end reinforcing structure, reinforcing method and shield starting method
CN111677519B (en) * 2020-07-08 2022-05-13 北京建工土木工程有限公司 Reinforcing structure and reinforcing method for shield launching end and shield launching method
CN111677518B (en) * 2020-07-08 2022-05-13 北京建工土木工程有限公司 Shield receiving end reinforcing structure, reinforcing method and shield receiving method
CN113685187A (en) * 2021-08-16 2021-11-23 北京市市政一建设工程有限责任公司 Small-clear-distance multi-hole underground excavation tunnel construction process
CN113685187B (en) * 2021-08-16 2023-12-01 北京市市政一建设工程有限责任公司 Construction process of small-clear-distance multi-hole undercut tunnel
CN113982630A (en) * 2021-10-29 2022-01-28 成都未来智隧科技有限公司 Tunnel supporting structure
CN113982630B (en) * 2021-10-29 2024-04-05 成都未来智隧科技有限公司 Tunnel supporting structure
CN115492598A (en) * 2022-09-27 2022-12-20 中铁第四勘察设计院集团有限公司 Tunnel linear excavation method of single guide pipe

Also Published As

Publication number Publication date
KR100442712B1 (en) 2004-08-02

Similar Documents

Publication Publication Date Title
KR101022382B1 (en) Precast horizontality tubular roof and tunnel construction method using the same
KR100713787B1 (en) The underground structure assembly and the underground structure building method which it uses
KR100442712B1 (en) Construction establishment method and the structure for underground tunnel formation
KR101582173B1 (en) The structure assembly for building a tunnel and building method thereof
CN113294166B (en) Oblique starting method for large-section rectangular jacking pipe
CN109667985B (en) Method for butting pipe pushing jack and receiving well steel sleeve in pipe pushing construction
CN109356183B (en) Open caisson reserved hole plugging structure and construction method thereof
KR100794609B1 (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR101040066B1 (en) Method of constructing non-excavation type tunnel
KR100914158B1 (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR100712593B1 (en) Construction method of pipe roof structures
KR20070076553A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR101479267B1 (en) Method for constructing tunnel by using pipe
KR100505301B1 (en) The structure for underground tunnel formation
KR100784201B1 (en) Method for construction of tunnel
KR100551685B1 (en) Construction establishment method and the structure for underground tunnel formation
KR100521345B1 (en) Construction establishment method and the structure for underground tunnel formation
KR100553979B1 (en) Construction establishment method and the structure for underground tunnel formation
JPH04213695A (en) Segment for shield tunnel
KR200274812Y1 (en) the structure for underground tunnel formation
KR102388843B1 (en) Wall forming method using U-type bending steel plate in the structure for underground tunnel formation
KR200317830Y1 (en) The structure for underground tunnel formation
KR200351426Y1 (en) The structure for underground tunnel formation
KR100362810B1 (en) Shield tunneling apparatus and method
KR100401330B1 (en) A method of construction for earth-protection walls of building

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
J206 Request for trial to confirm the scope of a patent right
J301 Trial decision

Free format text: TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_DEFENSIVE REQUESTED 20060630

Effective date: 20061023

Free format text: TRIAL NUMBER: 2006100001670; TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_DEFENSIVE REQUESTED 20060630

Effective date: 20061023

J206 Request for trial to confirm the scope of a patent right
J301 Trial decision

Free format text: TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_DEFENSIVE REQUESTED 20080228

Effective date: 20080805

Free format text: TRIAL NUMBER: 2008100000597; TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_DEFENSIVE REQUESTED 20080228

Effective date: 20080805

FPAY Annual fee payment

Payment date: 20120723

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20130722

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20140722

Year of fee payment: 11

LAPS Lapse due to unpaid annual fee
FPAY Annual fee payment

Payment date: 20160421

Year of fee payment: 12

R401 Registration of restoration
FPAY Annual fee payment

Payment date: 20160712

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20170628

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20180723

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20190627

Year of fee payment: 16