CN111706351B - Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into - Google Patents

Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into Download PDF

Info

Publication number
CN111706351B
CN111706351B CN202010379009.3A CN202010379009A CN111706351B CN 111706351 B CN111706351 B CN 111706351B CN 202010379009 A CN202010379009 A CN 202010379009A CN 111706351 B CN111706351 B CN 111706351B
Authority
CN
China
Prior art keywords
newly
ring beam
reinforcing ring
old
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010379009.3A
Other languages
Chinese (zh)
Other versions
CN111706351A (en
Inventor
雷升祥
代敬辉
张京京
赵静波
冀国栋
陈霞飞
陈一夫
岳长城
彭澍
陈自龙
高飞鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN202010379009.3A priority Critical patent/CN111706351B/en
Publication of CN111706351A publication Critical patent/CN111706351A/en
Application granted granted Critical
Publication of CN111706351B publication Critical patent/CN111706351B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a construction structure for communicating and connecting a newly-added underground excavation channel with an existing station hall layer. Arranging a main reinforcement of a reinforcing structure and a stirrup of the reinforcing structure in the reinforcing ring beam and the newly added surface layer; and an interface agent is coated on one side of the old structure of the interface of the new and old structures, so that the bonding performance with the new and old structures is enhanced. The connection form of the connection structure adopts a vertically symmetrical form, so that the structure connection is stable and attractive; meanwhile, the new and old connection structures are effectively connected, so that the consistency between the new and old structures is ensured. The newly added reinforcing ring beam and the newly added surface layer are used for effectively and stably connecting the refute port, so that no protrusion or water seepage is caused in the subsequent practical process, the structure between the newly added structure and the existing structure is effectively utilized, and the integrated structure form of the refute port is increased.

Description

Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
Technical Field
The invention relates to a communicating and connecting interface structure for a shallow-buried urban underground space, in particular to a communicating and connecting interface structure form for a newly-added underground excavation channel and an existing station hall layer in the shallow-buried urban underground space, and belongs to the technical field of urban rail transit connection.
Background
With the development of economy and the change of times, the urban contradiction outbreaks such as poor subway operation capability and crowded underground space exist, and the development and expansion of underground space is an effective measure for relieving the bottleneck of urban development, so that the demand of the existing structure development is brought forward. The method generally adopted in construction is to build a new structure first and break the side wall of the old structure at the joint of the new structure and the old structure, thereby realizing lap joint.
Chinese patent 201710115981.8 discloses a block for constructing a guide wall and a construction method for constructing a guide wall by using the block, which belongs to the field of construction of guide walls for buildings, specifically, the block is in a rectangular strip structure and comprises an upper connection surface, a lower bonding surface, a left side surface and a right side surface, the upper connection surface is a curved surface structure, and the block is provided with a vertical through hole along the axial direction. In the structure of plugging into of its design, adopt prefabricated building block, save the loaded down with trivial details step of site operation, the scene only need bond fixedly just accomplishes the process of leading the wall, labour saving and time saving to adopt prefabricated wall of leading, avoided in the site operation that the wall does not dry thoroughly the wall that leads to the fact and wall body fracture, influence pleasing to the eye and dampproofing waterproof nature problem.
Disclosure of Invention
The invention relates to a method for breaking a communication structure of an existing station hall layer, so that the communication connection with a newly-added underground excavation channel is realized, and a wall body structure of the existing station hall layer is broken, so that the communication connection with the newly-added underground excavation channel (tunnel) is integrated.
In order to achieve the purpose, the technical scheme adopted by the invention is a construction structure for communicating and connecting a newly-added underground excavation channel and an existing station hall layer, and specifically, as follows, a reinforced ring beam 21 and a newly-added surface layer 107 are arranged at a connecting port of a newly-added underground excavation hall 2 and are communicated and connected with an existing station hall layer 1. The structure of the connection place comprises a steel bar planting 103, a new and old structure interface 104, a new and old structure steel bar lap joint 105 and an anchor bar 106. Anchor bars are horizontally arranged on one side of the top plate reinforcing ring beam 101 and the bottom plate reinforcing ring beam 102 in a quincunx mode, and the other side of the top plate reinforcing ring beam and the bottom plate reinforcing ring beam is used as a planting bar and is implanted into a breaking opening of the existing station hall layer 1. Newly adding a strong structure stirrup 110 in the newly added surface layer 107, and welding two rows of outermost reinforcing bars with main reinforcing bars in the existing station hall layer 1 to form new and old structural reinforcing bar lap joints 105; the two rows of reinforcement structure stirrups 110 in the middle are implanted into the existing station hall layer 1 in an extending mode and serve as the planting reinforcements 103 of the old structure. Undercut channel main ribs 108 are extended and buried in the roof reinforcement ring beam 101 and the floor reinforcement ring beam 102. Arranging a reinforcing structure main rib 109 and a reinforcing structure hoop rib 110 in the reinforcing ring beam 21 and the newly added surface layer 107; and the interface agent is coated on one side of the old structure of the new and old structure interface 104 to enhance the bonding performance with the new structure. And pouring concrete of the reinforcing ring beam 21 and concrete of the newly-added surface layer 107 to complete the construction of the connection port structure.
Further, the welding length of the new and old structural steel bar overlap joint 105 is not less than 120 mm.
Furthermore, the interface agent adopts polymer modified cement mortar, epoxy mortar or 1:1 cement mortar and other materials.
Compared with the prior art, the connection form of the connection structure adopts a vertically symmetrical form, and the structure connection is stable and attractive; meanwhile, the new and old connection structures are effectively connected, so that the consistency between the new and old structures is ensured. The newly added reinforcing ring beam and the newly added surface layer are used for effectively and stably connecting the refute port, so that no protrusion or water seepage is caused in the subsequent practical process, the structure between the newly added structure and the existing structure is effectively utilized, and the integrated structure form of the refute port is increased.
Drawings
FIG. 1 is a flow chart of an embodiment of the present invention.
Fig. 2 is a schematic structural diagram of a docking side wall in which a newly-built transfer hall is communicated with an existing tunnel, and (a), (b) and (c) are schematic diagrams of a docking implementation process respectively.
Fig. 3 is a schematic view of a grouting breaking flow.
Fig. 4 is a schematic diagram I of the connection structure.
Fig. 5 is a schematic view of the docking structure II.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are exemplary and intended to be illustrative of the embodiments of the present invention, and should not be construed as limiting the invention.
The present invention will be described in detail below with reference to the accompanying drawings and examples.
Taking the structure of a cross transfer line of a subway in a certain city as an example, a roof reinforcing ring beam 101 with the size of 450mm × 800mm, two rows of upper main ribs 8C22, a waist rib 2C22 and a stirrup A12@150 are arranged at the vault interface of a newly-added underground excavation channel, and a C20 anchor rib 106 with the length of 850mm is arranged between a new structure and an old structure in a 150mm × 300mm quincunx shape and is anchored into the existing station hall layer 1 by 400 mm.
Adding a surface layer 107 with the size of 500mm x 150mm at the top, pouring C40 self-compacting concrete, configuring a reinforcing structure main reinforcement 1095C22 at the bottom, adding a reinforcing structure hoop reinforcement 110C12@100/200, embedding the reinforcing structure hoop reinforcement 110 serving as a planting reinforcement into the existing station hall layer 1, wherein the anchoring length is not less than 250 mm;
a bottom plate reinforcing ring beam 102 with the size of 450 x 1100mm, a main rib, a waist rib C22 and a stirrup A12@150 is arranged at an inverted arch interface of the newly added underground excavation channel; the anchor bars 106 with the length of 850mmC20 are horizontally arranged between the existing station hall layer 1, the anchor bars are arranged in a plum blossom shape with the length of 150mm x 300mm, and the length of the anchor bars anchored into the existing station hall layer 1 is not less than 400 mm.
Adding a surface layer 107 with the size of 500 x 150mm at the bottom, pouring C40 self-compacting concrete, configuring a C20 main rib at the top, adding a reinforcing structure stirrup 110C12@100/200, penetrating through a new and old structure interface 104, and embedding the reinforcing structure stirrup into the existing station hall layer 1.
As shown in fig. 1-2, a construction method for connecting a newly added underground excavation channel with an existing station hall layer, the newly added underground excavation channel 2 is constructed by adopting an underground excavation method under the condition that normal operation of the existing station hall layer 1 is not affected, and the connecting and connecting steps are as follows:
the first step is as follows: deep hole grouting is adopted, and a newly-added underground excavation channel is communicated. Carry out deep hole slip casting to the slip casting scope 3 of undercut passageway 2 from ground, refute the intercommunication and refute the mouth in advance, protect the station to refute the peripheral structure of interface and do not receive destruction, improve the construction operation security of plugging into. The earthwork of the newly-added underground excavation channel 2 is excavated by a CRD method, the hole diameter with the step distance of 1.5 times is kept among pilot tunnels in the earthwork excavation process, and core soil is kept to serve as a stable support during the earthwork excavation, so that the soil body balance in the newly-added underground excavation channel is kept. The first branch 14 of the newly added underground excavation channel is sprayed inside the newly added underground excavation channel after the first branch 4, the second branch 5, the third branch 6 and the fourth branch 7 of the newly added underground excavation channel 2 are sequentially communicated with the first branch 4, the second branch 5, the third branch 6 and the fourth branch 7 of the newly added underground excavation channel.
The second step is that: and (5) breaking a temporary middle partition wall and a temporary inverted arch of the newly-added underground excavation channel, and erecting the full house red. Adopt segmentation subsection to abolish interim middle bulkhead 9 and interim invert 8 between number 1 cavern 4, number 2 cavern 5, number 3 cavern 6 and the number 4 cavern 7 of newly-increased undercut passageway to set up full red scaffold frame 10 in step, in order to ensure newly-increased 2 internal structure stabilities of undercut passageway.
The third step: and constructing a waterproof, secondary lining and steel bar joint for newly-added underground excavated channels. Under the supporting action of the full-hall red scaffold 10, the underground excavated channel waterproof 11 and the underground excavated channel second lining 12 are constructed, the underground excavated channel waterproof 11 is reserved with a waterproof joint, and the underground excavated channel second lining 12 is reserved with a steel bar connector 13 which is used for connecting the waterproof of the connecting port with the new and old structure of the second lining.
The fourth step: and (3) dismantling the scaffolds with the range of 1.2m at the side of the existing station hall layer 1, and providing a space for the connection construction operation, namely the opening range 17. The hole opening range 17 is broken to correspond to the side wall of the newly-added underground excavation channel, the primary underground excavation channel support 14 and the primary underground excavation station floor support 15, and waterproof lap joints are arranged on the surfaces of the primary underground excavation channel support 14 and the primary underground excavation station floor support 15. The dug channel waterproofing 11 and the existing station hall waterproofing 16 are bonded by double-sided butyl adhesive tape.
The fifth step: the concrete structure within the range 17 of the opening hole is broken by bars and blocks and penetrates through the existing station hall layer 1 and the newly-added underground excavation channel 2. The cutting method of the strip and block cutting adopts a rope saw cutting method, the support and the cutting within the opening range 17 are carried out simultaneously, and the preliminary cutting of the connecting port is completed.
And a sixth step: and (5) performing chiseling and bar planting 20 and pouring a reinforcing ring beam 21 on the top and the bottom of the connection port finished in the fifth step.
Fig. 3 is a schematic view of a grouting breaking flow. The deep hole grouting process comprises the following steps: :
deep hole grouting is carried out in groups, each group is 12m in grouting length, the upper group and the lower group are in lap joint for 2m, and the effective reinforcing length is 10 m. The arrangement distance of the grouting holes is 0.8 x 0.8m, the grouting holes are arranged in a quincunx manner, and an earth surface grouting mode is adopted.
Adopting a drilling machine to conduct drainage drilling and retreating type grouting, and mainly using pressure injection of WSS non-shrinkage double-fluid slurry; the holes are uniformly distributed, the holes are drilled longitudinally, the control is easy, the slurry is uniformly dispersed and distributed, and the reinforcing effect on the pebble bed is good.
(1) Pulp classification
The method adopts AC grout (cement, water glass and additive), and when open water exists in a reinforced soil body area, the additive is adjusted to shorten the grout solidification time so as to achieve draining and water squeezing in a grouting area. The AC slurry is suitable for geological conditions such as silty clay layers, medium and coarse sand layers, silty and fine sand layers and the like.
(2) Construction process flow
1) Hole distribution: the method is characterized in that an existing station hall layer primary support is used as a grouting stop wall, quincunx holes are distributed in a deep hole grouting reinforcement area, grouting reinforcement is carried out on the contour line of the grouting area released by a measuring person in a channel according to design requirements, and hole position pre-inspection records are carried out by a special person after numbering.
2) Forming holes: the hole diameter is 42mm, the longitudinal horizontal depth is 2m (based on field technology bottom crossing), and when the hole position meets the main bars of the barrier, the hole position is adjusted within the range of 3-5 cm, so that the grouting hole position avoids the bars.
3) Slurry preparation: the slurry must be formulated strictly in proportion and the agitation must be for a sufficient time to ensure a uniform slurry concentration.
4) Grouting: and after the injection pipe is arranged, closing the end point to perform transverse injection switching. And applying pressure to the sprayed material to realize horizontal penetration effect. And controlling the grouting pressure P value within the water stopping reinforcement range to be 0.8-1.0 Mpa, and controlling the grout spraying positions at different longitudinal distances by controlling the segmented solidification time to start a new grouting cycle. The length of the drawing back drill rod (grouting pipe) is controlled within the range of 0.3-0.5 m.
5) And (4) ending: and when the grouting of all the arranged grouting hole positions is finished and the exploring holes do not have open water, finishing the grouting.
The main grouting parameters were as follows:
grouting depth: the depth is 0-2 m; drilling diameter: 42 mm; slurry diffusion radius: 0.6m to 0.8 m;
setting time of slurry: 8s to 20 s; the grouting pressure is 0.3-0.5 Mpa.
Grouting reinforcement considerations are as follows:
1) if the open flow water is met in the pilot tunnel excavation process and deep hole grouting reinforcement is needed, double-layer net hanging spray anchoring is needed on the excavation face before grouting to form a slurry blocking layer and hole distribution drilling grouting can be carried out after strength is formed; the thickness of the anchor spraying surface of the grout blocking layer is not less than 300 mm.
2) The slurry proportioning solidification time can be flexibly adjusted according to actual conditions on site, and if the grouting property of a pebble layer on site is poor, the slurry solidification time can be properly reduced, and the grouting property is increased; when the water flow is exposed, the setting time of the slurry is preferably 6-10 s according to the size of the water flow.
3) The actual underground rock-soil layer elevation and water level conditions can come in and go out of an exploration report due to flood season and dry season, grouting materials are flexibly adjusted according to actual hydrogeological conditions during construction, grouting amount is increased, and grouting reinforcement effect is guaranteed.
4) In the grouting reinforcement process, regularly checking a ground inspection well of an underground pipeline; and (5) monitoring the elevation change of the monitoring point in time, and controlling the lifting of the grouting ground within an allowable safety range. Strictly forbidding slurry leakage and slurry outflow; the angle of the drill rod is properly adjusted in the grouting range and the area close to the grouting range of the existing pipeline pipe ditch, the drill rod is ensured to have enough safety distance from the existing pipeline pipe ditch, and the disturbance of grouting on the existing pipeline pipe ditch is reduced by adopting comprehensive measures of reducing grouting pressure, proportioning slurry, prolonging the solidification time, reducing the grouting amount and the like.
Fig. 4 is a schematic diagram I of the connection structure.
Fig. 5 is a schematic view of the docking structure II.
And a reinforced ring beam 21 and a newly-added surface layer 107 are arranged at the junction of the newly-added underground excavation hall 2 and communicated with the existing station hall layer 1. The structure of the connection place comprises a steel bar planting 103, a new and old structure interface 104, a new and old structure steel bar lap joint 105 and an anchor bar 106. Anchor bars are horizontally arranged on one side of the top plate reinforcing ring beam 101 and the bottom plate reinforcing ring beam 102 in a quincunx mode, and the other side of the top plate reinforcing ring beam and the bottom plate reinforcing ring beam is used as a planting bar and is implanted into a breaking opening of the existing station hall layer 1. Newly adding a strong structure stirrup 110 in the newly added surface layer 107, and welding two rows of outermost reinforcing bars with main reinforcing bars in the existing station hall layer 1 to form new and old structural reinforcing bar lap joints 105; the two rows of reinforcement structure stirrups 110 in the middle are implanted into the existing station hall layer 1 in an extending mode and serve as the planting reinforcements 103 of the old structure. Undercut channel main ribs 108 are extended and buried in the roof reinforcement ring beam 101 and the floor reinforcement ring beam 102. Arranging a reinforcing structure main rib 109 and a reinforcing structure hoop rib 110 in the reinforcing ring beam 21 and the newly added surface layer 107; and the interface agent is coated on one side of the old structure of the new and old structure interface 104 to enhance the bonding performance with the new structure. And pouring concrete of the reinforcing ring beam 21 and concrete of the newly-added surface layer 107 to complete the construction of the connection port structure.
The welding length of the new and old structural steel bar lap joint 105 is not less than 120 mm.
The interface agent adopts polymer modified cement mortar, epoxy mortar or 1:1 cement mortar and other materials.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (1)

1. Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into, its characterized in that: arranging a reinforcing ring beam (21) and a newly-added surface layer (107) at a junction of the newly-added underground excavation hall (2), and communicating and connecting with the existing station hall layer (1); the structure of the connection part comprises a steel bar planting (103), a new and old structure interface (104), a new and old structure steel bar lap joint (105) and an anchor bar (106); anchor bars are horizontally arranged on one side of the top plate reinforcing ring beam (101) and the bottom plate reinforcing ring beam (102) in a quincunx mode, and the other side of the top plate reinforcing ring beam and the bottom plate reinforcing ring beam is used as a planting bar and is implanted into a breaking opening of the existing station hall layer (1); newly adding a reinforced structure stirrup (110) in the newly added surface layer (107), and welding two rows of reinforced structure stirrups (110) at the outermost side with main reinforcements in the existing station hall layer (1) to form a new and old structure reinforcement lap joint (105); two rows of reinforcement structure stirrups (110) in the middle are implanted into the existing station hall layer (1) in an extending mode to serve as implanted reinforcements (103) of the old structure; the main reinforcement (108) of the underground excavation channel is extended and buried in the top plate reinforcing ring beam (101) and the bottom plate reinforcing ring beam (102); arranging a reinforcing structure main rib (109) and a reinforcing structure hoop rib (110) in the reinforcing ring beam (21) and the newly added surface layer (107); coating an interface agent on one side of the old structure of the new and old structure interface (104) to enhance the bonding performance with the new structure; pouring concrete of the reinforcing ring beam (21) and concrete of the newly added surface layer (107); deep hole grouting is adopted, and a newly-added underground excavation channel is communicated; deep hole grouting is carried out in the grouting range of the underground excavation channel from the ground, and the communicated connection port is pre-reinforced, so that the peripheral structure of the station connection port is protected from being damaged, and the safety of connection construction operation is improved; breaking a temporary middle partition wall and a temporary inverted arch of the newly-added underground excavation channel, and erecting a full red tunnel; synchronously arranging full red scaffolds to ensure the internal structure of the newly-added underground excavation channel to be stable; then, applying waterproof, secondary lining and steel bar joint for newly adding the underground excavation channel; dismantling the existing station hall layer scaffold, and providing a space, namely a hole opening range for the connection construction operation; breaking the concrete structure in the range of opening holes in a strip and block manner, and penetrating through the existing station hall layer and the newly-added underground excavation channel; performing chiseling and rib planting and pouring of a reinforcing ring beam on the top and the bottom of the finished connecting port;
the welding length of the lap joint (105) of the new and old structural steel bars is not less than 120 mm;
the interface agent adopts polymer modified cement mortar, epoxy mortar or 1:1 cement mortar material.
CN202010379009.3A 2020-05-07 2020-05-07 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into Active CN111706351B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010379009.3A CN111706351B (en) 2020-05-07 2020-05-07 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010379009.3A CN111706351B (en) 2020-05-07 2020-05-07 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Publications (2)

Publication Number Publication Date
CN111706351A CN111706351A (en) 2020-09-25
CN111706351B true CN111706351B (en) 2022-03-11

Family

ID=72536772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010379009.3A Active CN111706351B (en) 2020-05-07 2020-05-07 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Country Status (1)

Country Link
CN (1) CN111706351B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111594181B (en) * 2020-05-07 2021-12-10 中铁十八局集团有限公司 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050066024A (en) * 2003-12-26 2005-06-30 김성수 Construction method of temporary apparatus of thnnel for direct digging
CN108385721A (en) * 2018-02-22 2018-08-10 中铁第勘察设计院集团有限公司 The construction unicom system and its construction method at new subway line station and building up station
CN111594181A (en) * 2020-05-07 2020-08-28 中铁十八局集团有限公司 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN213063578U (en) * 2020-05-07 2021-04-27 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050066024A (en) * 2003-12-26 2005-06-30 김성수 Construction method of temporary apparatus of thnnel for direct digging
CN108385721A (en) * 2018-02-22 2018-08-10 中铁第勘察设计院集团有限公司 The construction unicom system and its construction method at new subway line station and building up station
CN111594181A (en) * 2020-05-07 2020-08-28 中铁十八局集团有限公司 Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN213063578U (en) * 2020-05-07 2021-04-27 中铁十八局集团有限公司 Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
既有地铁车站结构侧墙开洞施工安全分析;苑春雨;《市政技术》;20190331;第106-109页 *

Also Published As

Publication number Publication date
CN111706351A (en) 2020-09-25

Similar Documents

Publication Publication Date Title
CN111594181B (en) Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN213063578U (en) Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
CN210013697U (en) Construction structure of near-penetrating building of underground excavation section of subway station entrance and exit
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN108677924B (en) Double-row miniature steel pipe pile grouting wall-forming partition structure and method
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN110067563A (en) Close on the station entrance-exit main structure construction method of urban architecture and road
WO2022100346A1 (en) Reinforcement structure for entry and exit of large-diameter jacking pipe group in water-rich sand stratum, and construction method
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN107091101A (en) Mine shield handing-over tunnel folded type joint design and construction method in the middle part of marine site
CN111535328A (en) Pit shaft type underground garage foundation pit supporting system in water-rich stratum and construction method
CN111305282A (en) Subway station anti-floating system in weak water-rich stratum and construction method thereof
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN106013078A (en) Construction method for strong permeable ground layer strengthened curtain structure
CN111706351B (en) Newly-increased undercut passageway and existing station room layer intercommunication construction structures of plugging into
CN112482415B (en) Consolidation grouting method for underground cavern under high external water pressure and flowing water condition
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN114109442A (en) Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method
CN107642101A (en) A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method
CN209603062U (en) Change the concentrative seepage plugging structure that dynamic water is hydrostatic in gallery
CN107165658A (en) Pass through the inter-laminar dislocation band impermeable management structure and construction method of underground chamber
CN110939150A (en) Emergency rescue method for rapidly constructing large-hydraulic-slope-drop-ratio thin-wall structure in confined water inrush accident state
CN113187487B (en) Construction method of double-layer full-section frozen underground excavation station structure of subway

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Lei Shengxiang

Inventor after: Chen Zilong

Inventor after: Gao Feipeng

Inventor after: Dai Jinghui

Inventor after: Zhang Jingjing

Inventor after: Zhao Jingbo

Inventor after: Ji Guodong

Inventor after: Chen Xiafei

Inventor after: Chen Yifu

Inventor after: Yue Changcheng

Inventor after: Peng Shu

Inventor before: Zhang Jingjing

Inventor before: Zhao Jingbo

Inventor before: Ji Guodong

Inventor before: Chen Xiafei

Inventor before: Chen Yifu

Inventor before: Yue Changcheng

Inventor before: Peng Shu

Inventor before: Chen Zilong

Inventor before: Gao Feipeng

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant