KR200452167Y1 - Jig for installating pipe through deck of ship - Google Patents

Jig for installating pipe through deck of ship Download PDF

Info

Publication number
KR200452167Y1
KR200452167Y1 KR2020090003364U KR20090003364U KR200452167Y1 KR 200452167 Y1 KR200452167 Y1 KR 200452167Y1 KR 2020090003364 U KR2020090003364 U KR 2020090003364U KR 20090003364 U KR20090003364 U KR 20090003364U KR 200452167 Y1 KR200452167 Y1 KR 200452167Y1
Authority
KR
South Korea
Prior art keywords
deck
pipe
jig
ship
support bar
Prior art date
Application number
KR2020090003364U
Other languages
Korean (ko)
Other versions
KR20100009671U (en
Inventor
김성열
박태주
백상필
손인수
백이석
Original Assignee
대우조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대우조선해양 주식회사 filed Critical 대우조선해양 주식회사
Priority to KR2020090003364U priority Critical patent/KR200452167Y1/en
Publication of KR20100009671U publication Critical patent/KR20100009671U/en
Application granted granted Critical
Publication of KR200452167Y1 publication Critical patent/KR200452167Y1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/60Building or assembling vessels or marine structures, e.g. hulls or offshore platforms characterised by the use of specific tools or equipment; characterised by automation, e.g. use of robots
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
    • B23K37/04Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
    • B23K37/053Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work aligning cylindrical work; Clamping devices therefor
    • B23K37/0533Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work aligning cylindrical work; Clamping devices therefor external pipe alignment clamps
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • B25B11/02Assembly jigs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B13/00Conduits for emptying or ballasting; Self-bailing equipment; Scuppers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/14Hull parts
    • B63B3/48Decks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/03Pipe-laying vessels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/40Building or assembling vessels or marine structures, e.g. hulls or offshore platforms characterised by joining methods
    • B63B73/49Building or assembling vessels or marine structures, e.g. hulls or offshore platforms characterised by joining methods by means of threaded members, e.g. screws, threaded bolts or nuts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L23/00Flanged joints
    • F16L23/12Flanged joints specially adapted for particular pipes
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T70/00Maritime or waterways transport
    • Y02T70/10Measures concerning design or construction of watercraft hulls

Abstract

본 고안은 선박의 데크 관통 파이프를 설치함에 있어서 수직 정도를 교정하고 유지시키기 위한 보조용 치공구에 관한 것으로서, 종래에 체인/레바블록 양중공구를 사용하여 어렵게 작업하던 것을 간단한 지그를 이용하여 누구나 쉽게 관통 파이프의 수직 정도를 교정할 수 있도록 한 선박의 데크 관통 파이프 설치 보조용 지그를 제공한다. 본 고안은, 두 개의 지지바의 하단에 너트부를 설치하고 그 너트부에 간격조절볼트를 결합하며, 너트부 하단에 눈금자를 설치하고, 상기 두개의 지지바중 외측 지지바의 상단에 다른 너트부를 설치하고 고정용 볼트를 결합하여 구성된 선박의 데크 관통 파이프 설치 보조용 지그를 제공함으로써, 복수개의 지그를 이용하여 데크 관통공 플랜지와 관통 파이프 사이의 간격을 조절함으로써 관통 파이프의 수직 정도를 조절할 수 있다. The present invention relates to an auxiliary tool for calibrating and maintaining the vertical degree in installing the deck through-pipe of the ship, and anyone can easily penetrate through the difficult jig using a chain / lever block double tool in the past A jig is provided to assist the installation of deck-through pipes for ships so that the verticality of the pipes can be corrected. The present invention, the nut part is installed at the lower ends of the two support bars, the gap adjusting bolt is coupled to the nut part, and the ruler is installed at the bottom of the nut part, and the other nut part is provided at the upper end of the outer support bar of the two support bars. By providing an auxiliary jig for installing deck through-pipe installation of a ship constructed by combining and fixing bolts, the vertical degree of the through-pipe can be adjusted by adjusting the gap between the deck through-hole flange and the through-pipe using a plurality of jigs. .

데크 관통 파이프, 배관, 수직 정도, 교정, 지그 Deck Through Pipes, Plumbing, Vertical, Straightening, Jig

Description

선박의 데크 관통 파이프 설치 보조용 지그{Jig for installating pipe through deck of ship}Jig for installating pipe through deck of ship}

본 고안은 선박의 건조 공정 중에 데크(DECK)를 관통하는 파이프(PIPE)를 설치하는 작업 보조용 치공구에 관한 것으로서, 더욱 상세하게는 파이프 설치시 데크 관통관의 정도 유지를 쉽게 조정할 수 있게 함과 아울러 낙하방지를 위한 선박의 데크 관통 파이프 설치 보조용 지그에 관한 것이다.The present invention relates to a work aid tool for installing a pipe (PIPE) through the deck (DECK) during the drying process of the ship, more specifically, it is possible to easily adjust the degree of maintenance of the deck through-pipe during pipe installation and In addition, the present invention relates to a deck through-pipe installation auxiliary jig for preventing a drop.

선박에는 수 많은 배관(파이프)들이 설치되고, 데크(DECK)를 관통하는 파이프들도 많은 수가 설치된다. 데크를 관통하는 파이프들은 데크의 상하부에서 다른 파이프들과 연결되며, 파이프들 간의 연결을 위해서는 데크 관통 파이프의 수직 정도와 파이프 단부 사이의 간격 및 각도가 정렬되어야 한다. 그런데 데크 관통 파이프는, 데크를 관통하여 파이프를 설치하는 것이므로 한번 설치한 후 쉽게 수직정도나, 간격을 조정하거나 각도를 조정하기 어렵다.Ships are equipped with a number of pipes (pipes), a large number of pipes through the deck (DECK) is also installed. Pipes passing through the deck are connected to other pipes at the top and bottom of the deck, and the connection between the pipes requires that the vertical degree of the deck through pipe and the spacing and angle between the pipe ends be aligned. By the way, since the deck through pipe is to install the pipe through the deck, it is difficult to easily adjust the verticality, spacing or angle after installing it once.

종래에는 데크 관통 파이프를 설치한 후, 수직 정도의 불량이 발생되면, 체 인/레바블록 양중공구를 사용하거나 화기 재절취 작업을 통한 강제적인 방법으로 파이프의 정도 교정 작업을 하고 있었다.Conventionally, after installing the deck through pipe, if the vertical degree of failure occurs, the accuracy of the pipe was made by using a chain / lever block double tool or a forced method through the fire re-cutting work.

이와 같이 종래에는 체인블록/레바블록 양중공구 및 절단기 쐐기 등 강제 조정에 필요한 비 효율적인 도구를 사용하여 작업을 하고 있으므로, 작업 수행이 힘들고 쇄기 및 기타 교정품이 낙하되는 사례가 발생될 수 있어서 안전사고로 이어질 수 있는 문제점이 있고, 작업성이 떨어지고 시간이 많이 걸리기 때문에 생산지연 및 품질저하의 요인이 되고 고객 불만족과 정도 불량으로 시스템 라인 검사 합격율이 저하되는 문제점이 있었다.As such, conventional work is being performed using inefficient tools such as chain block / lever block double tools and cutter wedges, which makes it difficult to carry out work and can lead to the occurrence of falling of wedges and other corrective products. There is a problem that can lead to, and the workability is poor and takes a lot of time, causing a delay in production and quality deterioration, there was a problem that the pass rate of the system line inspection due to customer dissatisfaction and poor quality.

이와 같은 종래의 선박 건조공정에서 데크 관통 파이프를 설치하여 수직 정도의 유지 및 설치작업시 누구나 쉽게 편리하게 사용할 수 있는 보조용 치공구로써 선박의 데크 관통 파이프 설치 보조용 지그를 제공하기 위한 것이다.It is to provide a deck through-pipe installation assistance jig of the ship as an auxiliary tool for anyone can easily and conveniently at the time of maintaining and installing the vertical degree by installing the deck through-pipe in the conventional vessel construction process as described above.

본 고안은 데크 관통 파이프의 수직 정도를 눈금자를 보면서 조정할 수 있도록 함으로써 수직 정도 품질을 향상시킴과 아울러 쉽고 정확하게 교정 및 수직정도를 유지시킬 수 있도록 하기 위한 것이다.The present invention is intended to improve the vertical accuracy by maintaining the vertical accuracy of the deck through pipe while looking at the ruler, and to be able to easily and accurately maintain the calibration and vertical accuracy.

본 고안의 선박의 데크 관통 파이프 설치 보조용 지그는,The deck penetration pipe installation assistance jig of the ship of the present invention,

데크 관통공 플랜지와 관통 파이프 사이에 끼워져 상기 데크 관통공 플랜지의 내측부에 밀착시키기 위한 제1지지바와;A first support bar inserted between the deck through hole flange and the through pipe to be in close contact with an inner side of the deck through hole flange;

상기 제1지지바의 하단부에 고정 설치되어 관통 나사공이 형성된 너트부와;A nut part fixed to the lower end of the first support bar and having a through screw hole formed therein;

상기 너트부의 상단면에 상기 제1지지바와 소정간격 이격되게 고정설치되어 상기 데크 관통공 플랜지의 외측부에 접하여 지지하기 위한 제2지지바와;A second support bar fixed to an upper end surface of the nut part to be spaced apart from the first support bar by a second support bar to be in contact with an outer portion of the deck through hole flange;

상기 너트부에 나사 결합되어 관통파이프와 상기 데크 관통공 플랜지 사이의 간격을 조정하기 위한 간격조절 볼트와;A gap adjusting bolt screwed to the nut to adjust a gap between the through pipe and the deck through hole flange;

상기 너트부의 하면에 설치되어 상기 간격조절 볼트의 간격조절 위치를 측정하기 위한 눈금자를 포함하여 구성됨을 특징으로 한다.It is installed on the lower surface of the nut portion characterized in that it comprises a ruler for measuring the gap adjustment position of the gap adjustment bolt.

또한, 본 발명은 상기 제2지지바의 상단부에 고정설치되고 관통 나사공이 형성된 제2너트부와;In addition, the present invention and the second nut portion is fixed to the upper end of the second support bar and the through screw hole is formed;

상기 제2너트부에 나사 결합으로 삽입되어 상기 데크 관통공 플랜지의 외측면에 지그를 고정설치하기 위한 고정용 볼트를 더 포함하여 구성됨을 특징으로 한다.It is characterized in that it further comprises a fixing bolt is inserted into the second nut portion screwed to securely install the jig to the outer surface of the deck through-hole flange.

이와 같은 본 고안에 의한 선박의 데크 관통 파이프 설치 보조용 지그를 사용하게 되면, 데크 관통공 플랜지와 관통 파이프 사이에 지그를 설치하여 간격조절 볼트로 간격을 조절한 상태로 고정된 상태를 유지시킬 수 있다. 따라서 복수개의 지그를 사용하여 원형의 관통 파이프와 데크 관통공 플랜지 사이의 간격을 조절함으로써 수직 정도 교정이 가능하고 교정된 상태로 유지시킬 수 있는 효과가 있으며, 간편한 치공구만으로 관통 파이프의 수직 정도 교정이 가능하게 되어 작업의 편리성과 작업시간 단축 및 안전사고 발생을 방지할 수 있고, 눈금자를 보고 간격을 조절할 수 있어서 수직 정도의 품질을 향상시킬 수 있는 장점이 있다.When the deck through-pipe installation auxiliary jig of the present invention is used as described above, a jig is installed between the deck through-hole flange and the through-pipe to maintain a fixed state with the gap adjusting bolts. have. Therefore, by adjusting the gap between the circular through pipe and the deck through-hole flange by using a plurality of jigs, it is possible to correct the vertical accuracy and to maintain the corrected state. It is possible to prevent the convenience of work and the reduction of working time and the occurrence of safety accidents, and to adjust the interval by looking at the ruler has the advantage of improving the quality of the vertical degree.

이하, 본 고안의 실시예를 첨부된 도면을 참조해서 상세히 설명하면 다음과 같다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 고안에 의한 선박의 데크 관통 파이프 설치 보조용 지그의 일실시 예를 보인 구성도이고, 도 2는 본 고안에 의한 선박의 데크 관통 파이프 설치 보조용 지그의 다른 실시예를 보인 구성도이다.1 is a configuration diagram showing an embodiment of the deck through-pipe installation auxiliary jig of the ship according to the present invention, Figure 2 is a configuration diagram showing another embodiment of the deck through-pipe installation auxiliary jig of the ship according to the present invention. to be.

이에 도시된 바와 같이, As shown therein,

본 고안의 선박의 데크 관통 파이프 설치 보조용 지그는,The deck penetration pipe installation assistance jig of the ship of the present invention,

데크 관통공 플랜지(1)와 데크 관통 파이프(2) 사이에 끼워져 상기 데크 관통공 플랜지(1)의 내측부에 밀착시키기 위한 제1지지바(10)와;A first support bar (10) fitted between the deck through hole flange (1) and the deck through pipe (2) to be in close contact with the inner side of the deck through hole flange (1);

상기 제1지지바(10)의 하단부에 고정 설치되어 관통 나사공이 형성된 너트부(20)와;A nut part 20 fixed to the lower end of the first support bar 10 and having a through screw hole formed therein;

상기 너트부(20)의 상단면에 상기 제1지지바(10)와 소정간격 이격되게 고정설치되어 상기 데크 관통공 플랜지(1)의 외측부에 접하여 지지하기 위한 제2지지바(40)와;A second support bar 40 fixed to an upper end surface of the nut part 20 so as to be spaced apart from the first support bar 10 by a predetermined distance so as to be in contact with an outer side of the deck through hole flange 1;

상기 너트부(20)에 나사 결합되어 데크 관통파이프(2)와 상기 데크 관통공 플랜지(1) 사이의 간격을 조정하기 위한 간격조절 볼트(30)와;A gap adjusting bolt 30 screwed to the nut part 20 to adjust a gap between the deck through pipe 2 and the deck through hole flange 1;

상기 너트부(20)의 하면에 설치되어 상기 간격조절 볼트(30)의 간격조절 위치를 측정하기 위한 눈금자(70)를 포함하여 구성된다.Is installed on the lower surface of the nut portion 20 is configured to include a ruler 70 for measuring the gap adjustment position of the gap adjustment bolt 30.

또한, 본 발명은 상기 제2지지바(40)의 상단부에 고정설치되고 관통 나사공이 형성된 제2너트부(50)와;In addition, the present invention is fixed to the upper end of the second support bar 40 and the second nut portion 50 formed with a through screw hole;

상기 제2너트부(50)에 나사 결합으로 삽입되어 상기 데크 관통공 플랜지(1)의 외측면에 지그를 고정하기 위한 고정용 볼트(60)를 더 포함하여 구성된다.It is inserted into the second nut portion 50 by a screw coupling further comprises a fixing bolt 60 for fixing the jig on the outer surface of the deck through-hole flange (1).

이와 같이 구성된 본 고안의 선박의 데크 관통 파이프 설치 보조용 지그는, 데크 관통공 플랜지(1)와 관통 파이프(2)의 사이에 끼워져 데크 관통공 플랜지(1)와 데크 관통 파이프(2) 사이의 간격을 조절하는 것으로서 원형의 파이프 둘레에 복수개의 지그(100)를 설치하여 간격을 조절함으로써 수직 정도를 교정할 수 있도록 하는 것이다.The deck through-pipe installation auxiliary jig of the ship of the present invention configured as described above is fitted between the deck through-hole flange 1 and the through-pipe 2 so as to be provided between the deck through-hole flange 1 and the deck through-pipe 2. By adjusting the spacing is to install a plurality of jig 100 around the circular pipe to adjust the spacing to be able to correct the vertical degree.

도 3은 본 고안에 의한 지그를 이용한 데크 관통 파이프의 교정작업 사진 예시도이다.Figure 3 is an illustration of the calibration operation of the deck through pipe using a jig according to the present invention.

선박의 데크(3)에는 데크 관통 파이프(2)를 설치하기 위하여 데크 관통공에 데크 관통공 플랜지(1)가 설치되어 있으며, 데크 관통 파이프(2)는 상기 데크 관통공 플랜지(1)를 통해서 설치된다.The deck through-hole flange 1 is installed in the deck through-hole in order to install the deck through-pipe 2 in the deck 3 of the ship, and the deck through-pipe 2 passes through the deck through-hole flange 1 Is installed.

데크 관통 파이프(2)의 수직 정도를 교정하기 위해서 본 고안에 의한 지그(100)를 적정한 간격으로 데크 관통공 플랜지(1)와 관통 파이프(2)의 사이에 결합하여 설치하고, 간격조절볼트(30)를 조절하여 데크 관통공 플랜지(1)와 관통 파이프(2) 사이의 간격을 조절한다. 이때 하면의 눈금자(70)를 보고 간격조절볼트(30)의 위치를 정확하게 파악하여 원하는 간격으로 조절하게 된다. 그리고 다른 지그(100)들도 마찬가지로 간격조절볼트(30)를 이용하여 데크 관통 플랜지(1)와 데크 관통 파이프(2) 사이의 각격을 조절함으로써, 데크 관통 파이프(2)의 수직정도를 정확하게 교정하여 그 상태를 유지 고정시킬 수 있게 된다.In order to calibrate the verticality of the deck through-pipe (2), the jig 100 according to the present invention is installed by coupling between the deck through-hole flange (1) and the through pipe (2) at appropriate intervals, and the space adjusting bolt ( 30) to adjust the gap between the deck through hole flange (1) and the through pipe (2). At this time, by looking at the ruler 70 of the lower surface to accurately determine the position of the spacing adjusting bolt 30 is adjusted to the desired interval. In addition, the other jig 100 adjusts the angle between the deck through flange 1 and the deck through pipe 2 by using the adjusting bolt 30 as well, thereby accurately correcting the verticality of the deck through pipe 2. The state can be maintained and fixed.

본 고안에 의한 도 2와 도 3은 고정용 볼트(60)의 유무가 서로 다른데, 고정용 볼트(60)가 없는 경우에도 간격조절볼트(30)를 돌려서 데크관통 파이프(2)에 밀착되면, 제1지지바(10)가 데크 관통공 플랜지(1)의 내측벽에 밀착되면서 지그(100) 가 지지 고정되기 때문에 고정용 볼트(60)가 없어도 지그(100)를 고정 설치할 수 있다. 고정용 볼트(60)가 있는 경우(도1)에는 먼저 고정용 볼트(60)를 이용하여 데크 관통공 플랜지(1)에 지그(100)를 고정시킨 상태에서 간격조절볼트(30)를 돌려서 간격을 조절할 수 있게 된다. 즉, 고정용 볼트(60)가 있는 경우에는 지그(100)를 설치하여 간격조절시에 선행으로 지그(100)를 고정시켜두고 간격을 조절할 수 있어서 좀더 편리하게 작업할 수 있다.2 and 3 according to the present invention is the presence or absence of the fixing bolt 60, even if there is no fixing bolt 60, if the close contact with the deck through the pipe (2) by turning the adjusting bolt 30, Since the jig 100 is supported and fixed while the first support bar 10 is in close contact with the inner wall of the deck through hole flange 1, the jig 100 may be fixedly installed even without the fixing bolt 60. If there is a fixing bolt (60) (Fig. 1), first, by using the fixing bolt 60 to fix the jig 100 to the deck through-hole flange (1) by rotating the gap adjusting bolt 30 Can be adjusted. That is, when the fixing bolt 60 is installed, the jig 100 may be installed and the jig 100 may be fixed in advance when the gap is adjusted, and thus the gap may be adjusted.

본 고안의 실시예를 설명함에 있어서, 데크 관통 파이프에 대해서 수직 정도 교정을 예로 설명하였으나, 수직 벽을 통과하는 파이프의 수평 정도나 기타 경사지게 벽체를 통과하는 경우에서도 모두 적용이 가능하며, 본 고안의 지그를 이용하여 간편하게 관통 파이프의 정도를 교정 및 조절할 수 있다.In describing the embodiment of the present invention, the vertical accuracy of the deck through pipe was described as an example, but it is also applicable to the horizontal degree of the pipe passing through the vertical wall or other obliquely passing through the wall. The jig can be used to easily calibrate and adjust the accuracy of through-pipes.

도 1은 본 고안에 의한 선박의 데크 관통 파이프 설치 보조용 지그의 일실시예를 보인 구성도.1 is a block diagram showing an embodiment of the deck through-pipe installation auxiliary jig of the ship according to the present invention.

도 2는 본 고안에 의한 선박의 데크 관통 파이프 설치 보조용 지그의 다른 실시예를 보인 구성도.Figure 2 is a schematic view showing another embodiment of the deck through-pipe installation auxiliary jig of the ship according to the present invention.

도 3은 본 고안에 의한 지그를 이용한 데크 관통 파이프의 교정작업 사진 예시도.Figure 3 is an illustration of a calibration operation of the deck through pipe using a jig according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

1 : 데크 관통공 플랜지 2 : 데크 관통 파이프1: Deck Through Hole Flange 2: Deck Through Pipe

3 : 데크 10 : 제1지지바3: deck 10: first support bar

20 : 너트부 30 : 간격조절볼트20: nut part 30: spacing adjustment bolt

40 : 제2지지바 50 : 너트부40: second support bar 50: nut part

60 : 고정용 볼트 70 : 눈금자60: fixing bolt 70: ruler

Claims (3)

선박의 데크를 관통하는 데크 관통 파이프를 설치하고 수직 정도를 교정하기 위한 보조용 지그에 있어서,In the auxiliary jig for installing a deck through pipe penetrating the deck of the ship and correct the vertical degree, 데크 관통공 플랜지(1)와 데크 관통 파이프(2) 사이에 끼워져 상기 데크 관통공 플랜지(1)의 내측부에 밀착시키기 위한 제1지지바(10)와;A first support bar (10) fitted between the deck through hole flange (1) and the deck through pipe (2) to be in close contact with the inner side of the deck through hole flange (1); 상기 제1지지바(10)의 하단부에 고정 설치되어 관통 나사공이 형성된 너트부(20)와;A nut part 20 fixed to the lower end of the first support bar 10 and having a through screw hole formed therein; 상기 너트부(20)의 상단면에 상기 제1지지바(10)와 소정간격 이격되게 고정설치되어 상기 데크 관통공 플랜지(1)의 외측부에 접하여 지지하기 위한 제2지지바(40)와;A second support bar 40 fixed to an upper end surface of the nut part 20 so as to be spaced apart from the first support bar 10 by a predetermined distance so as to be in contact with an outer side of the deck through hole flange 1; 상기 너트부(20)에 나사 결합되어 데크 관통파이프(2)와 상기 데크 관통공 플랜지(1) 사이의 간격을 조정하기 위한 간격조절 볼트(30)로 구성된 것을 특징으로 하는 선박의 데크 관통 파이프 설치 보조용 지그.The deck through pipe installation of the ship, characterized in that consisting of a gap adjusting bolt 30 for adjusting the distance between the deck through pipe (2) and the deck through hole flange (1) screwed to the nut portion (20) Auxiliary jig. 제 1 항에 있어서, 상기 선박의 데크 관통 파이프 설치 보조용 지그는,According to claim 1, Deck through pipe installation assistance jig of the vessel, 상기 너트부(20)의 하면에 설치되어 상기 간격조절 볼트(30)의 간격조절 위치를 측정하기 위한 눈금자(70)를 더 포함하여 구성된 것을 특징으로 하는 선박의 데크 관통 파이프 설치 보조용 지그.Jig for deck penetration pipe installation assistance of the ship, characterized in that further comprises a ruler (70) is installed on the lower surface of the nut portion 20 for measuring the gap adjustment position of the gap adjustment bolt (30). 제 1 항 또는 제 2 항에 있어서, 상기 선박의 데크 관통 파이프 설치 보조용 지그는,The deck penetrating pipe installation assistance jig of claim 1, wherein 상기 제2지지바(40)의 상단부에 고정설치되고 관통 나사공이 형성된 제2너트부(50)와;A second nut part 50 fixed to an upper end of the second support bar 40 and having a through screw hole formed therein; 상기 제2너트부(50)에 나사 결합으로 삽입되어 상기 데크 관통공 플랜지(1)의 외측면에 지그를 고정하기 위한 고정용 볼트(60)를 더 포함하여 구성된 것을 특징으로 하는 선박의 데크 관통 파이프 설치 보조용 지그.Is inserted into the second nut portion 50 by screwing the deck penetration of the ship, characterized in that it further comprises a fixing bolt 60 for fixing the jig to the outer surface of the deck through-hole flange (1) Jig for auxiliary pipe installation.
KR2020090003364U 2009-03-24 2009-03-24 Jig for installating pipe through deck of ship KR200452167Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020090003364U KR200452167Y1 (en) 2009-03-24 2009-03-24 Jig for installating pipe through deck of ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020090003364U KR200452167Y1 (en) 2009-03-24 2009-03-24 Jig for installating pipe through deck of ship

Publications (2)

Publication Number Publication Date
KR20100009671U KR20100009671U (en) 2010-10-04
KR200452167Y1 true KR200452167Y1 (en) 2011-02-11

Family

ID=44200075

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020090003364U KR200452167Y1 (en) 2009-03-24 2009-03-24 Jig for installating pipe through deck of ship

Country Status (1)

Country Link
KR (1) KR200452167Y1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200477760Y1 (en) * 2014-04-29 2015-07-16 한전케이피에스 주식회사 Zig for aligning motor shaft
KR20230151279A (en) 2022-04-25 2023-11-01 현대삼호중공업 주식회사 Method for connecting pipes being installed in ship block and zig for setting for performing the method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR920003842Y1 (en) * 1989-11-06 1992-06-12 대우조선공업 주식회사 Jig for sleeve
JPH08150495A (en) * 1994-11-28 1996-06-11 Nippon Sanso Kk Joining member tack welding jig
KR19990042031U (en) * 1998-05-29 1999-12-27 김형국 Flange Alignment Tool
KR200284902Y1 (en) 2002-05-22 2002-08-07 대우조선해양 주식회사 Jig for setting a piping
KR20020084902A (en) * 2001-05-04 2002-11-13 아스라브 쏘시에떼 아노님 Radiofrequency signal receiver with means for improving the reception dynamic of said signals

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR920003842Y1 (en) * 1989-11-06 1992-06-12 대우조선공업 주식회사 Jig for sleeve
JPH08150495A (en) * 1994-11-28 1996-06-11 Nippon Sanso Kk Joining member tack welding jig
KR19990042031U (en) * 1998-05-29 1999-12-27 김형국 Flange Alignment Tool
KR20020084902A (en) * 2001-05-04 2002-11-13 아스라브 쏘시에떼 아노님 Radiofrequency signal receiver with means for improving the reception dynamic of said signals
KR200284902Y1 (en) 2002-05-22 2002-08-07 대우조선해양 주식회사 Jig for setting a piping

Also Published As

Publication number Publication date
KR20100009671U (en) 2010-10-04

Similar Documents

Publication Publication Date Title
US20090100796A1 (en) Devices and Methods for Use in Construction
KR200452167Y1 (en) Jig for installating pipe through deck of ship
CN203270600U (en) Fixed support for installing embedded bolts of high-precision equipment
CN107366301A (en) A kind of method for improving bolt installation accuracy
JP4929331B2 (en) Steel frame exposed column base construction method
JP2006337058A (en) Load measuring method for existing anchor and re-tensing method for existing anchor
US6712655B1 (en) Adjustable engine mount bracket assembly
CN102353317A (en) Portable large-sized flange plane survey meter
KR20110010248A (en) Multi u-head bracket apparatus for bridge construction
JP3189564U (en) Fall prevention fence for concrete structures
CN112343180A (en) Foundation bolt pre-embedding deviation processing structure and method
CN210067488U (en) Outdoor curtain wall unwrapping wire appurtenance
KR101276658B1 (en) Safety fence device
JP2011241680A (en) Fixing structure for surface lattice
KR20130123644A (en) Pipes jig
KR200471684Y1 (en) Insttallation jig for heavy pipe support
CN211257347U (en) Positioning and fixing device for water stop steel plate
CN111287368A (en) Construction process of high-strength aluminum plate curtain wall
KR20220029197A (en) Handrail device
JP5963578B2 (en) Wall panel mounting method and wall panel mounting structure
KR101066443B1 (en) Ship piping assembly method using 3-step round bar jig
KR20130003984U (en) Centering Jig
KR200492533Y1 (en) Jig for installation of through flanged pipe
CN219953377U (en) Pin locking guide tool
JP6347483B2 (en) Floor board fixture

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20140103

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20141222

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20151229

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170125

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee