KR200405546Y1 - Non-removable type nail of singel body using method of soil nailing - Google Patents
Non-removable type nail of singel body using method of soil nailing Download PDFInfo
- Publication number
- KR200405546Y1 KR200405546Y1 KR2020050030445U KR20050030445U KR200405546Y1 KR 200405546 Y1 KR200405546 Y1 KR 200405546Y1 KR 2020050030445 U KR2020050030445 U KR 2020050030445U KR 20050030445 U KR20050030445 U KR 20050030445U KR 200405546 Y1 KR200405546 Y1 KR 200405546Y1
- Authority
- KR
- South Korea
- Prior art keywords
- nail
- soil nailing
- removable
- nailing method
- singel
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 28
- 239000002689 soil Substances 0.000 title claims abstract description 18
- 239000002245 particle Substances 0.000 claims abstract description 7
- 239000000463 material Substances 0.000 claims description 12
- 239000004746 geotextile Substances 0.000 claims description 2
- 239000000835 fiber Substances 0.000 abstract description 9
- 230000002093 peripheral effect Effects 0.000 abstract description 5
- 230000002787 reinforcement Effects 0.000 description 8
- 238000009412 basement excavation Methods 0.000 description 7
- 239000004567 concrete Substances 0.000 description 4
- 238000010276 construction Methods 0.000 description 4
- 238000005260 corrosion Methods 0.000 description 4
- 230000007797 corrosion Effects 0.000 description 4
- 238000002347 injection Methods 0.000 description 3
- 239000007924 injection Substances 0.000 description 3
- 230000008878 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reaction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0006—Plastics
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0085—Geotextiles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0006—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by the bolt material
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
본 고안은 소일네일링(soil nailing) 공법용 비제거식 일체형 네일에 관한 것으로, 더욱 상세하게는 원통형의 몸체 외주면에 다수의 돌기가 방사형으로 형성되고, 상기 몸체의 전단부와 후단부에는 각각 수나사부와 암나사부가 형성되어, 다수의 네일을 결합할 수 있어 길이를 자유로이 조절할 수 있으며, 상기 네일은 부식이 용이한 플라스틱 입자와 토목섬유로 형성하여, 지중에 삽입된 네일을 차후에 인발하여 제거하지 않아도 자연부식되어 소멸되도록 한 소일네일링 공법용 네일을 제공한다.The present invention relates to a non-removable one-piece nail for the soil nailing method, more specifically, a plurality of projections are formed radially on the outer peripheral surface of the cylindrical body, each of the male screw portion on the front end and the rear end of the body And female thread is formed, can be combined with a plurality of nails can be adjusted freely, the nail is formed of plastic particles and geosynthetic fiber, which is easy to corrode, so that the nail inserted in the ground does not have to be removed later To provide a nail for the nailing method to be corroded and extinguished.
Description
도 1 내지 도 1b는 종래의 소일네일링 공법의 시공방법을 나타낸 설명도.1 to 1b is an explanatory view showing a construction method of a conventional soil nailing method.
도 2는 본 고안상의 소일네일링 공법용 비제거식 일체형 네일을 도시한 사시도.Figure 2 is a perspective view of a non-removable one-piece nail for the soil nailing method of the present invention.
도 3는 본 고안상의 소일네일링 공법용 비제거식 일체형 네일을 도시한 단면도.Figure 3 is a cross-sectional view showing a non-removable one-piece nail for the soil nailing method of the present invention.
도 4는 본 고안상의 소일네일링 공법용 비제거식 일체형 네일을 지중에 삽입한 후 보강 콘크리트로 그라우팅을 실시한 상태를 나타낸 단면도.Figure 4 is a cross-sectional view showing a state in which the grouting with reinforced concrete after inserting the non-removable integral nail for the soil nailing method of the present invention in the ground.
도 5 내지 도 5b는 본 고안상의 비제거식 일체형 네일을 사용한 소일네일링 시공방법을 나타낸 설명도.5 to 5b is an explanatory diagram showing a method of constructing a small nail using a non-removable integral nail in the present invention.
<도면의 주요부분에 대한 부호설명><Code Description of Main Parts of Drawing>
N. 비제거식 일체형 네일 10. 몸체N. Non-removable one-
11. 돌기 12. 수나사부 11.
13. 암나사부 100. 그라우팅재13. Female thread 100. Grouting material
110. 지압판 120. 볼트110.
본 고안은 소일네일링(soil nailing) 공법용 비제거식 일체형 네일에 관한 것으로, 더욱 상세하게는 원통형의 몸체 외주면에 다수의 돌기가 방사형으로 형성되고, 상기 몸체의 전단부와 후단부에는 각각 수나사부와 암나사부가 형성되어, 다수의 네일을 결합할 수 있어 길이를 자유로이 조절할 수 있으며, 상기 네일은 부식이 용이한 플라스틱 입자와 토목섬유로 형성하여, 지중에 삽입된 네일을 차후에 인발하여 제거하지 않아도 자연부식되어 소멸되도록 한 소일네일링 공법용 네일에 관한 것이다.The present invention relates to a non-removable one-piece nail for the soil nailing method, more specifically, a plurality of projections are formed radially on the outer peripheral surface of the cylindrical body, each of the male screw portion on the front end and the rear end of the body And female thread is formed, can be combined with a plurality of nails can be adjusted freely, the nail is formed of plastic particles and geosynthetic fiber, which is easy to corrode, so that the nail inserted in the ground does not have to be removed later The present invention relates to a nail for a soil nailing method that is caused to corrode and disappear.
일반적으로 소일네일링(soil nailing) 공법이란 절취사면이 토사나 리핑암일 때 사면의 붕괴를 방지하기 위해 보강하는 공법으로서 비탈면이나 터파기 굴착면을 자립할 수 있는 안정높이로 굴착함과 동시에 숏크리트(shotcrete)로 표면보호면을 형성하고 굴착면을 천공하여 네일을 삽입한 후 그라우팅을 실시하여 보강토체를 조성하는 방법으로, 터파기, 흙막이, 철도 및 도로에 인접한 자연사면 및 인공사면의 보강, 지하구조물 및 터널 등과 같은 토목 관련 시설물 축조, 기존 옹벽의 보수 및 옹벽 설치공사에서 주로 이용되고 있다.Generally, the soil nailing method is a reinforcing method to prevent the collapse of the slope when the cut slope is soil or ripping arm, and excavates at a stable height that can stand the slope or the excavation surface at the same time. shotcrete) to form the surface protection surface and drill the excavation surface to insert nails and grout to form reinforcement soils, reinforcement of natural and artificial slopes adjacent to trenches, mudstones, railways and roads, underground It is mainly used in construction of civil engineering facilities such as structures and tunnels, repair of existing retaining walls, and installation of retaining walls.
그러나, 종래의 소일네일링 공법은 도 1 내지 도 1b에서 보는 바와 같이, 굴 착면에 케이싱 천공을 하고, 이 케이싱 내부에 보강체를 삽입한 다음, 상기 케이싱을 인발하고, 다시 주입관을 삽입하여 상기 보강체를 중심으로 콘크리트를 주입하여 그라우팅을 실시한 후 주입된 콘크리트가 양생되면 굴착면에 돌출된 보강체의 끝단에 지압판을 설치하고 너트를 체결하여 토압으로부터 굴착면을 지지케 함으로써 굴착면의 붕괴를 방지하였다. However, in the conventional small nailing method, as shown in Figs. 1 to 1b, the casing is drilled in the excavation surface, the reinforcement is inserted into the casing, the casing is drawn out, and the injection tube is inserted again. When the injected concrete is cured after injecting concrete around the reinforcement, when the injected concrete is cured, it installs a pressure plate at the end of the reinforcement projecting on the excavation surface and tightens the nut to support the excavation surface from earth pressure. Was prevented.
이와 같이 종래의 소일네일링 공법은 시공방법이 복잡하고 번거로워 작업시간이 많이 소요될 뿐 아니라 지중에 삽입된 네일은 네일이 대지경계선을 지나 설치되는 경우 타인의 재산권을 침해하게 되므로, 공사 후 이를 제거하여야 하나 그라우팅으로 인해 네일의 제거가 거의 불가능하였다. 따라서, 타인소유대지 속에 삽입된 네일로 인해 점용료에 관한 분쟁 문제와, 추후 이루어질 수 있는 상수도, 하수도, 전선관, 케이블관, 지하철 등의 지하공간개발작업에 있어 장애가 되는 문제가 빈번하게 발생되었다.As described above, the conventional soil nailing method is not only complicated and cumbersome, but also takes a lot of work time, and nails inserted into the ground infringe on the property rights of others when the nail is installed across the land boundary. However, the grouting made it almost impossible to remove the nail. Therefore, the nail inserted into the land owned by others caused frequent disputes about the occupancy fee, and the problem of obstacles in the development of underground spaces such as waterworks, sewerage, conduits, cables, and subways.
상술한 바와 같은 문제점을 해결하기 위하여, 본 고안은 소일네일링 공법용 네일을 부식이 가능한 재질로 형성하고, 원통형 네일의 외주면에는 다수의 돌기를 형성하여 그라우팅재와 네일의 마찰저항을 극대화시키며, 상기 네일의 전단부와 후단부에는 각각 수나사부와 암나사부를 형성하여 결합 및 분리가 용이하도록 함으로써 자유로이 네일의 길이조절을 할 수 있도록 하고, 종래의 소일네일링 공법에서 보강체 삽입공정과 주입관 삽입공정을 생략하고도 시공이 가능하므로 공기를 단축 할 수 있을 뿐 아니라, 차후 지중에 삽입된 네일을 제거하지 않아도 자연부식되어 소멸되므로 타인소유대지의 재산권 침해 및 지하공간개발작업에서의 장애문제 등을 원천적으로 해소할 수 있는 소일네일링 공법용 비제거식 일체형 네일을 제공하는 데 그 목적이 있다.In order to solve the problems as described above, the present invention is to form a nail for a nail nailing method with a corrosive material, to maximize the frictional resistance of the grouting material and nail by forming a plurality of projections on the outer peripheral surface of the cylindrical nail, The front and rear ends of the nail are formed with male threads and female threads, respectively, so that the length of the nail can be freely adjusted by easy coupling and separation, and the reinforcement insertion process and the injection tube are inserted in the conventional small nailing method. The construction can be done even if the process is omitted, and not only shortens the air, but also causes natural corrosion and disappears without removing nails inserted into the ground. The purpose is to provide a non-removable one-piece nail for the soil nailing process that can be solved at the source. have.
전술한 바와 같은 목적을 달성하기 위하여, 본 고안상의 소일네일링 공법용 비제거식 일체형 네일은, 원통형 몸체의 외주면에 다수의 돌기가 형성되고, 상기 몸체의 전단부와 후단부에는 각각 수나사부와 암나사부가 형성되며, 또한 네일의 재질은 소정의 네일 수명이 다한 후에 지중에서 부식이 용이한 부식성 섬유로 이루어진 것을 특징으로 한다. In order to achieve the object as described above, the non-removable one-piece nail for the small nailing method of the present invention, a plurality of projections are formed on the outer peripheral surface of the cylindrical body, the male and female threads on the front end and the rear end of the body, respectively In addition, the material of the nail is characterized in that made of corrosive fibers that are easily corroded in the soil after a predetermined nail life.
첨부된 도면에 의거하여 본 고안의 구성을 이하에 상세히 설명한다.On the basis of the accompanying drawings will be described in detail the configuration of the subject innovation.
본 고안상의 소일네일링 공법용 비제거식 일체형 네일(N)은, 도 2 내지 도 3에서 보는 바와 같이 원통형의 몸체(10) 외주면에 다수의 돌기(11)를 방사형으로 돌출되게 형성하여 그라우팅재(100)와 네일(N) 표면과의 마찰저항이 극대화되도록 하고, 상기 몸체(10)의 전단부와 후단부에는 각각 수나사부(12)와 암나사부(13)를 형성하여 다수 네일(N)의 결합 및 분리가 용이하도록 하여 자유로이 전체 네일(N)의 길이조절이 가능하도록 한다.Non-removable one-piece nail (N) for the soil nailing method of the present invention, as shown in Figure 2 to Figure 3 to form a plurality of projections (11) on the outer peripheral surface of the
또한, 상기 네일(N)의 재질은 소정의 네일 수명이 끝난 후에는 지중에서 부 식이 용이하도록 플라스틱 입자와 토목섬유로 구성함으로써 지중에 삽입된 채로 시간이 경과함에 따라 자연부식되어 소멸되도록 한다.In addition, the material of the nail (N) is made of plastic particles and geosynthetic fibers to facilitate corrosion in the ground after a predetermined nail life is to be naturally corroded and disappear as time passes while being inserted into the ground.
상기 네일의 재질은 부식이 용이한 부식성의 플라스틱 입자와 이 플라스틱 입자와 혼합가능할 정도의 단섬유로 구성된 역시 부식성의 통상적인 섬유, 즉 토목공사에 사용되는 부식성 섬유이면 어떠한 종류의 섬유라도 관계 없으며, 이러한 부식성 섬유와 플라스틱 입자를 혼합하여 성형한 것이면 그 어떤 것이라도 좋다.The material of the nail may be any type of fiber as long as it is also a common corrosive fiber composed of corrosive plastic particles that are easily corroded and short fibers that can be mixed with the plastic particles, that is, a corrosive fiber used in civil engineering. Any material may be used as long as it is molded by mixing such corrosive fibers and plastic particles.
이상과 같이 구성된 본 고안상의 비제거식 일체형 네일을 사용한 소일네일링 시공방법을 설명한다.The method of constructing a soil nailing using the non-removable integral nail of the present invention configured as described above will be described.
도 5 내지 도 5b에서 보는 바와 같이, 먼저 굴착면에 케이싱 천공을 실시하고, 그 천공된 길이에 맞게 본 고안상의 네일을 다수개 결합하여 상기 케이싱 내부로 삽입한 후 상기 케이싱을 인발한다.As shown in Fig. 5 to 5b, first the casing is perforated on the excavation surface, and the plurality of nails according to the present invention are combined to fit the perforated length and inserted into the casing and then the casing is drawn out.
다음으로 종래처럼 보강체나 주입관을 삽입하는 공정 없이 바로 삽입된 네일의 후단부로부터 보강 콘크리트를 압입하여 그라우팅을 실시한다.Next, grouting is performed by pressing the reinforcement concrete from the rear end of the nail which is directly inserted without the process of inserting the reinforcement body or the injection tube as in the prior art.
주입된 그라우팅재가 양생되면 네일의 굴착면측 끝단부에 지압판을 설치하고 볼트를 체결하여 시공을 완료한다.When the injected grouting material is cured, the pressure plate is installed at the end of the nail's excavation surface and the bolts are tightened to complete the construction.
이상과 같이 구성된 본 고안에 의해서, 소일네일링 공법용 네일을 부식이 가능한 재질로 형성하고, 네일의 외주면에는 다수의 돌기를 형성하여 그라우팅재와 네일의 마찰저항을 극대화시키며, 상기 네일의 전단부와 후단부에는 각각 수나사부와 암나사부를 형성하여 결합 및 분리가 용이하도록 함으로써 자유로이 네일의 길이조절을 할 수 있고, 종래의 소일네일링 공법에서 보강체 삽입공정과 주입관 삽입공정을 생략하고도 시공이 가능해지므로 공기를 단축할 수 있을 뿐 아니라, 차후 지중에 삽입된 네일을 제거하지 않아도 자연부식되어 소멸되므로 타인소유대지의 재산권 침해 및 지하공간개발사업에서의 장애문제 등을 원천적으로 해소할 수 있으며, 또한 중량이 가벼워 운반 및 생산이 용이하고 생산단가를 절감할 수 있는 등의 다양한 효과를 얻을 수 있고 친환경적으로 토목섬유 및 PE를 활용하여 차후 네일을 제거하지 않아도 환경적으로 문제가 되지 않는 장점이 있다.According to the present invention configured as described above, the nail for the nailing method is formed of a material capable of corrosion, and a plurality of protrusions are formed on the outer circumferential surface of the nail to maximize the frictional resistance of the grouting material and the nail, and the shear portion of the nail The length of the nail can be freely controlled by forming male and female threads at the rear end and the female thread, respectively, so as to facilitate the coupling and detachment. This will not only shorten the air, but will also cause natural corrosion and disappear without removing nails inserted into the ground in the future, thereby fundamentally eliminating the infringement of property rights and obstacles in underground space development projects. In addition, its light weight makes it easy to transport and produce, and can reduce production costs. There is an advantage that can be obtained and environmentally friendly by using geotextiles and PE does not have a problem in the environment without removing the nail in the future.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2020050030445U KR200405546Y1 (en) | 2005-10-26 | 2005-10-26 | Non-removable type nail of singel body using method of soil nailing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR2020050030445U KR200405546Y1 (en) | 2005-10-26 | 2005-10-26 | Non-removable type nail of singel body using method of soil nailing |
Publications (1)
Publication Number | Publication Date |
---|---|
KR200405546Y1 true KR200405546Y1 (en) | 2006-01-10 |
Family
ID=41757292
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR2020050030445U KR200405546Y1 (en) | 2005-10-26 | 2005-10-26 | Non-removable type nail of singel body using method of soil nailing |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR200405546Y1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100795469B1 (en) | 2006-02-23 | 2008-01-16 | 삼성중공업 주식회사 | Slime mixing soil nailing method |
KR101060286B1 (en) | 2008-11-17 | 2011-08-29 | 주식회사그라운드이엔씨 | Flexible Soil Nail and Flexible Soil Nailing |
KR101162442B1 (en) | 2010-07-14 | 2012-07-04 | 임성호 | Fixing apparatus for equipments in the sea bottom |
-
2005
- 2005-10-26 KR KR2020050030445U patent/KR200405546Y1/en not_active IP Right Cessation
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100795469B1 (en) | 2006-02-23 | 2008-01-16 | 삼성중공업 주식회사 | Slime mixing soil nailing method |
KR101060286B1 (en) | 2008-11-17 | 2011-08-29 | 주식회사그라운드이엔씨 | Flexible Soil Nail and Flexible Soil Nailing |
KR101162442B1 (en) | 2010-07-14 | 2012-07-04 | 임성호 | Fixing apparatus for equipments in the sea bottom |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100771904B1 (en) | Earth Reinforcement System by Using Bamboo Reinforcement | |
KR102264250B1 (en) | Block style reinforced soil retaining wall and constructing method thereof | |
KR100966148B1 (en) | Ground adhering soil nailing structure and ground reinforcement method using the same | |
CN109026012A (en) | Vertical shaft surrounding rock supporting structure and its excavation supporting method | |
KR101510297B1 (en) | A removable prestressing steel pipe soil nailing structure | |
KR100937237B1 (en) | Multiple soil-nailing ground reinforcement apparatus and multiple soil-nailing method | |
KR200405546Y1 (en) | Non-removable type nail of singel body using method of soil nailing | |
KR100978629B1 (en) | Soil nailing for reinforce slope and method for reinforce slope using thereof | |
KR200352267Y1 (en) | Slope-reinforcing structure for soil nailing having function of drainage | |
KR20060100790A (en) | The structure of screw anchor for slope reinforcement construction and the method using thereof | |
KR200450097Y1 (en) | Perforating drill of earth anchor operative without draining water and soil | |
KR100995815B1 (en) | Shortcrete retaining wall construction method | |
KR100862387B1 (en) | Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this | |
KR100361108B1 (en) | Green Slope Reinforcement Method | |
KR101460180B1 (en) | Nail connectors for soil nailing method | |
KR100697001B1 (en) | Multi-Protector System | |
KR100556668B1 (en) | Structure of a slop reinforced of carrying out by physical environment | |
CN110359450B (en) | Assembled round pile structure and construction method | |
KR100869369B1 (en) | The ground reinforcement apparatus and method grouting type using bundle steel pipe | |
KR200409269Y1 (en) | Earth Reinforcement System by Using Bamboo Reinforcement | |
KR101330211B1 (en) | Connecting method of deformed bar and spiral reinforcement for panel installation nail of soil cutting face | |
JP2007170115A (en) | Water collecting/draining pipe with restraining function | |
KR102120216B1 (en) | Leading end reinforcement head for the soil nail | |
KR101452180B1 (en) | Non-open cut excavation construction method for underground structure using concrete segment | |
KR200298683Y1 (en) | Apparatus to reinforce a slope |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
REGI | Registration of establishment | ||
FPAY | Annual fee payment |
Payment date: 20091230 Year of fee payment: 5 |
|
LAPS | Lapse due to unpaid annual fee |