KR20040078146A - An erection unit for a building floor slab and the erection method thereof - Google Patents
An erection unit for a building floor slab and the erection method thereof Download PDFInfo
- Publication number
- KR20040078146A KR20040078146A KR10-2004-7011736A KR20047011736A KR20040078146A KR 20040078146 A KR20040078146 A KR 20040078146A KR 20047011736 A KR20047011736 A KR 20047011736A KR 20040078146 A KR20040078146 A KR 20040078146A
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- bottom layer
- floor slab
- layer slab
- towing
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/48—Supporting structures for shutterings or frames for floors or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B1/3516—Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by erecting a vertical structure and then adding the floors from top to bottom
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/38—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for plane ceilings of concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/16—Members, e.g. consoles, for attachment to the wall to support girders, beams, or the like carrying forms or moulds for floors, lintels, or transoms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
바닥층 슬래브를 상승시키기 위한 하중지지 부재를 포함하는 건물 바닥층 슬래브용 가설 유닛이 개시되어 있다. 상기 하중지지 부재는 바닥층 슬래브가 놓인 평면보다 더 높고 벽에 고정되고 견인 부재의 도움으로 바닥층 슬래브와 연결된다. 바닥층 슬래브 몰드를 설치하는 단계와, 견인 부재의 상단부를 상기 바닥층 슬래브 위의 하중지지 부재에 연결하는 단계와, 견인 부재의 하단부를 바닥층 슬래브가 위치되는 높이에 위치시키는 단계와, 그 후 콘크리트를 주입시키는 단계와, 몰드를 해체시키고 바닥층 슬래브가 경화된 후 다음 하부층을 설치하는 단계와, 바닥층이 그 자중을 지지하기에 충분한 강도로 응고된 후 견인 부재를 제거하는 단계를 포함하는 상기 가설 유닛으로 바닥층 슬래브를 가설하기 위한 방법이 개시되어 있다.A construction unit for building floor slabs is disclosed that includes a load bearing member for raising a floor slab. The load bearing member is higher than the plane on which the bottom layer slab is laid and is fixed to the wall and connected with the bottom layer slab with the aid of the traction member. Installing a bottom layer slab mold, connecting an upper end of the traction member to a load bearing member on the bottom layer slab, positioning a lower end of the traction member at a height at which the bottom layer slab is located, and then injecting concrete A bottom layer with the hypothesis unit comprising the steps of disassembling the mold and installing the next lower layer after the bottom layer slab has cured, and removing the traction member after the bottom layer has solidified to sufficient strength to support its own weight. A method for constructing a slab is disclosed.
Description
바닥층 슬래브(floor slab)는 건물의 공간을 고객의 요구사항에 따라 복수의 바닥층으로 수직 분할하는데 사용된다. 현재, 대부분의 건물의 바닥층 슬래브는 도1에 도시된 바와 같이 콘크리트로 형성되고, 그 가설 방법은 각각의 바닥층에 대한 (콘크리트 구조물과 같은) 하중지지 구조물(load-bearing structure) 또는 전체 건물에 대한 하중지지 구조물이 완성된 후 다음 상부 바닥층 슬래브를 설치하는 것이다. 하부 바닥층의 콘크리트가 주입된 후, 콘크리트가 임의 중량을 지지하기에 충분히 경화될 때까지 일정 시간의 기간동안 기다리는 것이 요구된다. 그 후 지지 프레임이 다음 상부 바닥층 슬래브용으로 다른 설치를 수행하도록 이 바닥층 슬래브 위에 설치될 수 있다. 그러나, 이 가설 방법은 여전히 다음에서 설명되는 두 개의 단점을 갖는다. 즉, 1) 바닥층 슬래브가 경화되기 전 일정 시간의 기간동안 기다려야 하고, 그 후 다음 상부 바닥층 슬래브가 설치될 수 있다. 더욱이, 지지 프레임과 바닥층 슬래브 몰드가 각 바닥층이 완성된 후 반복적으로 조립되고 해체되어야 하기 때문에 시간 소모적이다. 2) 다중 바닥층 슬래브가 동시에 설치될 때 하부 바닥층 슬래브가 복수의 상부 바닥층 슬래브, 지지 프레임 및 바닥층 슬래브 몰드의 중량을 지지하여야 하기 때문에 바닥층 슬래브의 구조적 강도에 나쁜 영향을 주고, 이는 도1에 도시된 바와 같이 바닥층 슬래브의 변형을 야기한다. 따라서, 지지 프레임의 구조적 강도에 대한 요구사항은 비교적 더 높다. 상술된 조건의 관점에서, 건물 바닥층 슬래브에 대한 향상된 가설 방법이 "건물 바닥층 슬래브에 대한 가설 유닛 및 그 가설 방법"이라는 방법의 명칭의 SIPO 특허 제01,129,796호(2001년 10월 22)에 개시되어 있다. 이 방법은 건물의 상부 바닥층으로부터 하향으로 시작해서 하부 바닥층으로 바닥층 슬래브를 설치하는데 이용되고, 이는 일반적으로 다음의 단계, 즉, 건물의 하중지지 구조물 위에 제1 복수의 위치고정 부재를 고정시키는 단계와, 제1 복수의 위치고정 부재 위에 바닥층 슬래브를 위치시키는 단계와, 상기 바닥층 슬래브 몰드는 견인 부재(traction member)를 통해 제1 복수의 위치고정 부재 위에 현수된 지지 구조물로 지지되고, 그 후 콘크리트를 주입하는 단계와, 콘크리트가 임의 정도로 경화된 후 하부 바닥층 슬래브가 놓인 위치에 제2의 복수의 위치고정 부재를 설치하는 단계와, 견인 부재를 통해 하부 바닥층의 위치고정 부재 위에 지지 구조물을 현수시키는 단계와, 그 후 견인 부재의 견인의 도움에 의해 및 중력의 영향으로 상부 바닥층 슬래브의 제2의 복수의 위치고정 부재를 제거하는 단계와, 상기 바닥층 슬래브 몰드는 하부 바닥층 슬래브가 놓이고 위치고정 부재의 상단부에 위치된 위치로 하강되고, 그 후 콘크리트를 주입하는 단계를 포함한다. 이러한 가설 방법으로, 다중 바닥층 슬래브가 동시에 설치될수 있다. 더욱이, 바닥층 슬래브 몰드의 조립과 해체가 생략되고, 그 결과 설치를 가속화하고 하부 바닥층 슬래브 위에 적재되는 상부 바닥층 슬래브를 방지할 수 있다. 그러나, 이러한 가설 방법은 여전히 바닥층 슬래브가 그 자중(deadweight)을 지지하기에 충분히 경화될 때까지 일정 시간의 기간을 기다려야 하고, 그 후 바닥층 슬래브 몰드가 제거될 수 있다.Floor slabs are used to vertically divide a building's space into multiple floors according to customer requirements. Currently, the bottom floor slab of most buildings is formed of concrete as shown in FIG. 1, and the hypothesis method is a load-bearing structure (such as a concrete structure) for each floor layer or an entire building. After the load bearing structure is completed, the next top floor slab is installed. After the concrete in the lower bottom layer has been injected, it is required to wait for a period of time until the concrete has hardened sufficiently to support any weight. A support frame can then be installed on this bottom layer slab to perform another installation for the next top layer slab. However, this hypothesis still has the two disadvantages described below. That is, 1) it is necessary to wait for a period of time before the bottom layer slab is cured, and then the next top layer slab can be installed. Moreover, the support frame and the bottom layer slab mold are time consuming because each floor layer must be assembled and disassembled repeatedly after completion. 2) When the multiple bottom slabs are installed at the same time, the bottom floor slab has to support the weight of the plurality of top floor slabs, the supporting frame and the bottom layer slab mold, which adversely affects the structural strength of the floor slab, which is shown in FIG. As a result, deformation of the bottom layer slab occurs. Thus, the requirements for the structural strength of the support frame are relatively higher. In view of the conditions described above, an improved hypothesis method for building floor slabs is disclosed in SIPO Patent No. 01,129,796 (October 22, 2001) entitled "Placement Unit for Building Floor Slabs and Its Hypothesis Method". . This method is used to install a floor slab starting from the top floor of the building downwards to the bottom floor, which is generally the next step, i.e., securing the first plurality of positioning members on the load bearing structure of the building; Positioning the bottom layer slab over the first plurality of positioning members, wherein the bottom layer slab mold is supported by a support structure suspended over the first plurality of positioning members via a traction member, and then the concrete Injecting, installing a second plurality of positioning members in a position where the lower floor slab is placed after the concrete has hardened to an arbitrary degree, and suspending the support structure over the positioning members of the lower floor layer through the traction member. And secondly of the top floor slab by the aid of the towing of the towing member and under the influence of gravity Removing the plurality of positioning members of the slab mold, wherein the bottom layer slab mold is lowered to a position where the lower bottom layer slab is placed and positioned at an upper end of the positioning member, and then injecting concrete. In this hypothesis, multiple floor slabs can be installed simultaneously. Moreover, the assembly and disassembly of the bottom layer slab mold is omitted, as a result of which it is possible to accelerate the installation and to prevent the upper floor layer slab from being loaded onto the lower floor layer slab. However, this hypothesis still requires waiting a period of time until the bottom layer slab is sufficiently cured to support its deadweight, after which the bottom layer slab mold can be removed.
본 발명은 상술한 단점을 완화시키거나 그리고/또는 제거하기 위한 것이다.The present invention is intended to mitigate and / or eliminate the aforementioned drawbacks.
본 발명은 건물 바닥층 슬래브용 가설 유닛 및 그 가설 방법에 관한 것이고, 특히 다중 바닥층 슬래브용 가설 유닛 및 그 가설 방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction unit for building floor slabs and a construction method thereof, and more particularly, to a construction unit for multi-floor floor slabs and a construction method thereof.
도1은 바닥층 슬래브를 가설하기 위한 종래의 가설 방법을 도시한 개략 평면도.1 is a schematic plan view showing a conventional construction method for laying a bottom layer slab;
도2는 본 발명의 제1 실시예에 따른 바닥층 슬래브에 대한 설치 공정을 도시하기 위한 제1 개략 평면도.Fig. 2 is a first schematic plan view showing the installation process for the bottom layer slab according to the first embodiment of the present invention.
도3은 본 발명의 제1 실시예에 따른 바닥층 슬래브에 대한 설치 공정을 도시하기 위한 제2 개략 평면도.Fig. 3 is a second schematic plan view showing the installation process for the bottom layer slab according to the first embodiment of the present invention.
도4는 본 발명의 제1 실시예에 따른 바닥층 슬래브에 대한 설치 공정을 도시하기 위한 제3 개략 평면도.Fig. 4 is a third schematic plan view showing the installation process for the bottom layer slab according to the first embodiment of the present invention.
도5는 본 발명의 제1 실시예에 따른 바닥층 슬래브에 대한 설치 공정을 도시하기 위한 제4 개략 평면도.Fig. 5 is a fourth schematic plan view showing the installation process for the bottom layer slab according to the first embodiment of the present invention.
도6은 본 발명의 제1 실시예의 상부도.Figure 6 is a top view of the first embodiment of the present invention.
도7은 도1의 "A"부분의 확대도.7 is an enlarged view of portion “A” of FIG. 1;
도8은 본 발명의 제2 실시예의 구조도.8 is a structural diagram of a second embodiment of the present invention;
도9는 도8의 "B"부분의 확대도.9 is an enlarged view of a portion “B” in FIG. 8;
도10은 도8의 "C"부분의 확대도.Fig. 10 is an enlarged view of the portion "C" in Fig. 8;
도11은 본 발명의 제3 실시예의 구조도.Figure 11 is a structural diagram of a third embodiment of the present invention.
도12는 도11의 "D"부분의 확대도.12 is an enlarged view of a portion “D” in FIG. 11;
도13은 도11의 "E"부분의 확대도.FIG. 13 is an enlarged view of portion “E” in FIG. 11;
도14는 본 발명의 제4 실시예의 구조도.14 is a structural diagram of a fourth embodiment of the present invention.
도15는 도14의 "F"부분의 확대도.15 is an enlarged view of a portion “F” in FIG. 14;
도16은 도14의 "G"부분의 확대도.FIG. 16 is an enlarged view of a portion “G” of FIG. 14;
도17은 본 발명의 제5 실시예의 구조도.Fig. 17 is a structural diagram of a fifth embodiment of the present invention.
도18은 도17의 "H"부분의 확대도.18 is an enlarged view of a portion “H” in FIG. 17;
도19는 본 발명의 제6 실시예의 구조도.Fig. 19 is a structural diagram of a sixth embodiment of the present invention.
도20은 도19의 "I"부분의 확대도.20 is an enlarged view of a portion “I” of FIG. 19;
도21은 본 발명의 제7 실시예의 구조도.Figure 21 is a structural diagram of a seventh embodiment of the present invention.
도22는 도21의 "J"부분의 확대도.FIG. 22 is an enlarged view of a portion “J” of FIG. 21;
<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>
1 : 장착 부재1: mounting member
2 : 인장 로드2: tension rod
3 : 바닥층 슬래브3: bottom layer slab
4 : 바닥층 슬래브 몰드4: bottom layer slab mold
5 : 위치고정 부재5: position fixing member
6 : 견인 부재6: towing member
7 : 플레이트7: plate
8 : 지지 구조물8: support structure
9 : 벽9: wall
10 : 나사식 헤드10: screw head
11 : 슬리브11: sleeve
12 : 하강 행거12: descending hanger
13 : 왯지 블록13: wedge block
14 : 연결 로드14: connection load
본 발명의 주 목적은 바닥층 슬래브 몰드를 제거하고 바닥층 슬래브가 일정 수준으로 응고된 후 다음 하부층을 설치할 수 있는 건물 바닥층 슬래브용 가설 유닛 및 그 가설 방법을 제공하는 것이다. 따라서, 설치 속도가 증가할 뿐 아니라, 바닥층 슬래브의 품질도 향상된다.It is a main object of the present invention to provide a construction unit for a building floor slab and a method of laying the same, which can remove the floor slab mold and install the next lower layer after the floor slab solidifies to a certain level. Therefore, not only the installation speed is increased, but the quality of the bottom layer slab is also improved.
본 발명에 다른 건물 바닥층 슬래브용 가설 유닛은 바닥층 슬래브를 상승시키기 위한 하중지지 부재를 포함하고, 상기 하중지지 부재는 바닥층 슬래브가 놓인 평면보다 더 높이 위치되고 견인 부재를 통해 바닥층 슬래브에 연결된다.The construction unit for building floor slab according to the present invention includes a load supporting member for raising the floor slab, which is positioned higher than the plane on which the floor slab is placed and connected to the floor slab through the traction member.
장착 부재는 스크루 볼트를 통해 벽에 고정된 장착 블록일 수 있거나 또는 상부 바닥층 슬래브를 지지하는 위치고정 부재의 트러스(truss)일 수 있거나 또는 상부 바닥층 슬래브를 당기는 견인 부재일 수 있다.The mounting member may be a mounting block fixed to the wall via a screw bolt or may be a truss of a positioning member that supports the upper bottom layer slab or may be a pull member that pulls the upper bottom layer slab.
견인 부재는 인장 로드, 나사식 로드, 강철 끈 또는 철제 체인일 수 있다.The towing member may be a tension rod, a threaded rod, a steel string or an iron chain.
본 발명에 따른 바닥층 슬래브를 가설하기 위한 방법은 바닥층 슬래브 몰드를 설치하는 단계와, 견인 부재의 상단부를 상기 바닥층 슬래브 위의 하중지지 부재에 연결하는 단계와, 견인 부재의 하단부를 바닥층 슬래브가 위치되는 높이에 위치시키는 단계와, 그 후 콘크리트를 주입시키는 단계와, 바닥층 슬래브 몰드를 해체시키고 바닥층 슬래브가 일정 수준으로 응고된 후 다음 하부층을 설치하는 단계와, 바닥층이 그 자중을 지지하기에 충분한 강도로 응고된 후 견인 부재를 제거하는 단계를 포함한다.The method for laying the bottom layer slab according to the present invention comprises the steps of installing a bottom layer slab mold, connecting an upper end of the towing member to a load supporting member on the bottom layer slab, and a lower layer of the towing member to which the bottom layer slab is located. Positioning at a height, then injecting concrete, dismantling the bottom slab mold and installing the next lower layer after the bottom slab has solidified to a certain level, and the floor layer with sufficient strength to support its own weight. Removing the traction member after solidification.
본 발명에 따른 건물 바닥층 슬래브용 가설 유닛 및 그 가설 방법을 사용하여, 바닥층 슬래브는 응고화 과정 동안 상부 바닥층 슬래브에 의해 가압되지 않아서, 하부 바닥층 슬래브는 상부 바닥층 슬래브의 중량에 의해 야기된 변형으로부터 방지된다. 더욱이, 견인 부재의 도움으로, 바닥층 슬래브 몰드가 제거될 수 있고 다음 하부 바닥층 슬래브는 바닥층 슬래브가 완전히 응고하기 전 설치될 수 있어서 설치 속도가 사실상 증가된다. 바닥층 슬래브의 설치가 상부층에서 시작해서 하부층으로 수행되기 때문에, 바닥층 슬래브 몰드를 제거한 후 바닥층 슬래브는 하강되고 견인 부재를 사용함으로써 중력의 영향으로 다음 층에 설치될 수 있어서, 바닥층 슬래브 몰드의 설치 및 수송이 간단해진다.Using the construction unit for building floor slabs according to the invention and the construction method thereof, the floor slab is not pressed by the upper floor slab during the solidification process, so that the lower floor slab is prevented from deformation caused by the weight of the upper floor slab. do. Moreover, with the aid of the traction member, the bottom layer slab mold can be removed and the next bottom layer slab can be installed before the bottom layer slab is completely solidified, thus increasing the installation speed substantially. Since the installation of the bottom layer slab is carried out from the top layer to the bottom layer, after removing the bottom layer slab mold, the bottom layer slab is lowered and can be installed in the next layer under the influence of gravity by using a traction member, thereby installing and transporting the bottom layer slab mold. This becomes simpler.
본 발명은 첨부 도면과 연관하여 취해진 다음의 상세한 설명으로부터 명백해질 것이며, 상기 도면은 단지 예시를 목적으로 본 발명에 따른 양호한 실시예를 도시하고 있다.BRIEF DESCRIPTION OF THE DRAWINGS The present invention will become apparent from the following detailed description taken in conjunction with the accompanying drawings, which show a preferred embodiment according to the invention for illustrative purposes only.
본 발명에 따른 건물 바닥층 슬래브의 신속한 가설을 위한 가설 유닛 및 그 가설 방법은 다음에서 설명되는 SIPO 특허 제01,129,796호에 개시된 것과 같이 다양한 방법으로 사용될 수 있다.The construction unit for rapid construction of the building floor slab according to the present invention and its construction method can be used in various ways as disclosed in SIPO Patent No. 01,129,796 described below.
도2를 참조하면, 제1 복수의 위치고정 부재(5)는 바닥층 슬래브(3)가 설치되는 높이에 고정되고, 그 후 바닥층 슬래브 몰드(4)는 제1 복수의 위치고정 부재(5) 위에 설치된다. 복수의 견인 부재(6)를 통해, 지지 구조물(8)은 위치고정 부재(5)의 하단부에 현수되고 바닥층 슬래브 몰드(4)를 지지하도록 채용된다. 바닥층 슬래브(3)는 그 후 바닥층 슬래브 몰드(4) 안으로 콘크리트를 주입시킴으로써 주조된다. 콘크리트를 주입시키기 전에, 그 하단부에 나사식 헤드(10)를 가진 복수의 인장 로드(2)는 (도2 및 도7에 도시된 바와 같이) 인장 로드(2)의 상부 후크 단부가 벽(9) 위의 장착 부재(1)인 복수의 하중지지 부재에 현수되는 방식으로 상부로부터 바닥층 슬래브 몰드(4) 안으로 경사지게 삽입된다. 콘크리트가 주입되고 일정 정도로 경화된 후, 제2의 복수의 위치고정 부재(5)는 하부 바닥층의 위치에 설치되고, 지지 부재(8)와 바닥층 슬래브 몰드(4)는 견인 부재(6)를 통해 제2의 복수의 위치고정 부재(5)에 연결된다. 주조 후에, 바닥층 슬래브(3)는 복수의 인장 로드(2)에 의해 당겨진다. 그 후 장착 부재(1)가 해체되고, 바닥층 슬래브(3)가 경화된 후, 인장 로드(2)는 바닥층 슬래브 몰드(4)에 나사식 헤드(10)를 남기면서 제거된다. 바닥층 슬래브의 설치 동안 남겨진 구멍은 시멘트로 충진된다.2, the first plurality of positioning members 5 are fixed at a height at which the bottom layer slabs 3 are installed, and the bottom layer slab mold 4 is then placed on the first plurality of positioning members 5. Is installed. Through the plurality of traction members 6, the support structure 8 is suspended to the lower end of the positioning member 5 and is employed to support the bottom layer slab mold 4. The bottom layer slab 3 is then cast by pouring concrete into the bottom layer slab mold 4. Before injecting the concrete, the plurality of tension rods 2 with threaded heads 10 at their lower ends are provided with the upper hook ends of the tension rods 2 (as shown in FIGS. 2 and 7). ) Is inserted obliquely from the top into the bottom layer slab mold 4 in such a way as to be suspended in a plurality of load bearing members, the mounting member 1 above. After the concrete is injected and cured to a certain degree, the second plurality of positioning members 5 are installed at the position of the lower bottom layer, and the support member 8 and the bottom layer slab mold 4 are pulled through the traction member 6. It is connected to the second plurality of positioning members 5. After casting, the bottom layer slab 3 is pulled by the plurality of tension rods 2. After the mounting member 1 is dismantled and the bottom layer slab 3 is cured, the tension rod 2 is removed while leaving the threaded head 10 in the bottom layer slab mold 4. The holes left during installation of the bottom layer slab are filled with cement.
도3을 참조하면, 제1 복수의 위치고정 부재(5)는 다음 하부 바닥층 슬래브를주조하기 전 해체되어 지지 프레임(8)과 바닥층 슬래브 몰드(4)가 제2의 복수의 위치고정 부재(5)에 적재된다. 도4 및 도5를 참조하면, 견인 부재(6)의 견인의 도움에 의해 및 중력의 영향으로 바닥층 슬래브 몰드(4)는 제2 장착 부재(5)로 하강된다. 그 후, 다음 하부 바닥층에 대한 설치가 수행된다.Referring to FIG. 3, the first plurality of positioning members 5 are dismantled before casting the next lower bottom layer slab so that the support frame 8 and the bottom layer slab mold 4 are separated from the second plurality of positioning members 5. Are loaded). 4 and 5, the bottom layer slab mold 4 is lowered to the second mounting member 5 with the aid of the pulling of the traction member 6 and under the influence of gravity. Thereafter, installation to the next lower bottom layer is performed.
본 발명의 제2 실시예에 따른 가설 유닛을 도시하는 도8, 도9 및 도10을 참조하면, 본 실시예의 견인 부재(6)는 후크형 인장 로드이다. 바닥층 슬래브 몰드(4) 및 강철 바아의 설치 후에, 후크 형상의 인장 로드(2)의 각각의 단부는 바닥층 슬래브(3)에 삽입되고 일정 각으로 절첩되고, 인장 로드(2)의 각각의 다른 단부는 후크 안으로 절첩되고 벽(9) 위의 강철 바아(9')에 연결된다. 인장 로드(2)는 경사지게 배열된다.8, 9 and 10 showing the hypothesis unit according to the second embodiment of the present invention, the traction member 6 of this embodiment is a hook type tension rod. After installation of the bottom layer slab mold 4 and the steel bar, each end of the hook-shaped tension rod 2 is inserted into the bottom layer slab 3 and folded at an angle, and each other end of the tension rod 2. Is folded into a hook and connected to a steel bar 9 'above the wall 9. The tension rods 2 are arranged obliquely.
본 발명의 제3 실시예에 따른 가설 유닛을 도시하는 도11, 도12 및 도13을 참조하면, 여기서 플레이트(7)는 벽(9)에 삽입되는 "T"자 형상의 장착 부재를 형성하는 연결 로드(14)와 납땜된다. 연결 로드(14)의 하단부는 나사로 형성되고 벽(9)으로부터 돌출하고, 유사하게 인장 로드(2)와 바닥층 슬래브(3) 사이의 연결은 또한 플레이트(7)와 연결 로드(14)에 의해 형성된 "T"자 형상의 장착 부재를 통해 수행된다. 견인 부재(6)는 나사로 형성된 슬리브(11)의 형태일 수 있다.11, 12 and 13 showing a hypothesis unit according to a third embodiment of the present invention, where the plate 7 forms a “T” shaped mounting member inserted into the wall 9. It is soldered with the connecting rod 14. The lower end of the connecting rod 14 is formed with a screw and protrudes from the wall 9, and similarly the connection between the tension rod 2 and the bottom layer slab 3 is also formed by the plate 7 and the connecting rod 14. It is carried out through the mounting member of the "T" shape. The traction member 6 may be in the form of a sleeve 11 formed with a screw.
도11 내지 도13에 도시된 견인 부재는 인장 로드(2)이고, 인장 로드(2)의 양단부는 바닥층 슬래브(3)를 통해 각각 바닥층 슬래브(3)와 벽(9)에 연결된다. 플레이트(7)는 인장 로드(2)에 나사식으로 연결된다.The towing members shown in Figs. 11 to 13 are tension rods 2, and both ends of the tension rods 2 are connected to the bottom layer slab 3 and the wall 9 through the bottom layer slab 3, respectively. The plate 7 is threadedly connected to the tension rod 2.
본 발명의 제4 실시예에 따른 가설 유닛을 도시하는 도14 내지 도16을 참조하면, 본 실시예의 인장 로드(2)의 양단부는 후크 안으로 절첩되고 각각 바닥층 슬래브(3)의 강철 바아(3')와 벽(9) 위의 강철 바아(9')에 연결된다. 인장 로드(2)는 슬리브(11)에 나사식으로 연결되어 인장 로드(2)는 상이한 방향으로 슬리브(11)를 회전시킴으로써 인장되거나 해제될 수 있다.14 to 16 showing a hypothesis unit according to a fourth embodiment of the present invention, both ends of the tension rods 2 of this embodiment are folded into hooks and respectively the steel bars 3 'of the bottom layer slab 3; ) And a steel bar 9 'above the wall 9. The tension rod 2 is threadedly connected to the sleeve 11 so that the tension rod 2 can be tensioned or released by rotating the sleeve 11 in different directions.
본 발명의 제5 실시예에 따른 가설 유닛을 도시하는 도17 및 도18을 참조하면, 보강성 바아(2')의 제1 단부는 경화되지 않은 바닥층 슬래브(3)를 통해 삽입되고, 그의 제2 단부는 경화되지 않은 바닥층 슬래브(3) 위의 하중지지 부재에 연결된다. 설치시, 보강성 바아(2')는 콘크리트를 주입하기 전에 바닥층 슬래브(3)를 관통하고, 콘크리트는 응고된 후 팽창되고 보강성 바아(2')에 압력 효과를 생성한다. 경화되지 않은 바닥층 슬래브(3)가 중력의 영향으로 약간 변형될 때 보강성 바아(2')가 선과 홈을 형성하기 때문에 보강성 바아(2')와 콘크리트 사이에 발생된 마찰력은 허용 범위 내에서 바닥층 슬래브(3)의 변경을 제한하기에 충분히 더 크다. 경화되지 않은 바닥층 슬래브(3) 위의 하중지지 부재가 장착 부재의 트러스에 연결될 때, 보강성 바아(2')의 상단부는 보강성 바아(2')의 하단부가 경화되지 않은 바닥층 슬래브(3)를 관통하는 동안 트러스에 연결된다. 만약 경화되지 않은 바닥층 슬래브(3) 위의 견인 부재가 다음 상부 바닥층 슬래브, 즉, 보강성 바아(2')를 당기는 작용을 하는 견인 부재이면, 다음에 보강성 바아(2')는 납땜 방법에 의해 서로 연결되고, 그 납땜 지점은 각각의 바닥층 슬래브 위에 위치된다.Referring to Figures 17 and 18, which show a hypothesis unit according to a fifth embodiment of the present invention, the first end of the reinforcing bar 2 'is inserted through an uncured bottom layer slab 3, The two ends are connected to the load bearing member above the uncured bottom layer slab 3. In installation, the reinforcing bar 2 'passes through the bottom layer slab 3 before injecting the concrete, the concrete solidifies and expands and creates a pressure effect on the reinforcing bar 2'. Since the reinforcing bar 2 'forms lines and grooves when the uncured bottom layer slab 3 slightly deforms due to the force of gravity, the frictional forces generated between the reinforcing bar 2' and the concrete are within acceptable limits. It is larger enough to limit the change of the bottom layer slab 3. When the load bearing member on the uncured bottom layer slab 3 is connected to the truss of the mounting member, the upper end of the reinforcing bar 2 'is the lower layer slab 3 of which the lower end of the reinforcing bar 2' is not cured. It is connected to the truss while penetrating. If the traction member on the uncured bottom layer slab 3 is the traction member acting to pull the next upper bottom layer slab, ie the reinforcement bar 2 ', then the reinforcement bar 2' is then subjected to the soldering method. Connected to each other, the soldering points being located above each bottom layer slab.
본 발명의 제6 실시예에 따른 가설 유닛을 도시하는 도19 및 도20을 참조하면, 여기서 본 발명의 견인 부재는 강철 끈(2'')이고, 그의 제1 단부는 상부 하강행거(12)를 통해 경화되지 않은 바닥층 슬래브(3)에 연결되고, 그의 제2 단부는 경화되지 않은 바닥층 슬래브(3) 위의 하중지지 부재에 연결된다. 상부 하강 행거(12)의 하단부는 작은 상단부와 큰 하단부를 가진 왯지 블록(13)과 연결되고, 왯지 블록(13)은 바닥층 슬래브(3)를 관통한다. 왯지 블록(13)의 하단부는 중량을 현수함으로써 강철 끈(2'')을 조이는 데 사용되는 하부 하강 행거(12)와 연결되고, 콘크리트를 주입 후에, 당기는 힘이 경화되지 않은 바닥층 슬래브(3)의 중량을 방해하도록 생성될 수 있다. 바닥층 슬래브(3) 위의 하중지지 부재가 위치고정 부재의 트러스와 연결될 때, 강철 끈(2'')의 상단부는 트러스에 연결되고, 강철 끈(2'')의 하단부는 왯지 블록(13)을 통해 경화되지 않은 바닥층 슬래브(3)를 관통한다. 만약 경화되지 않은 바닥층 슬래브(3) 위의 하중지지 부재가 상부 바닥층 슬래브의 견인 부재이면, 강철 끈(2'')은 강철 끈(2'')의 각각의 부분이 하강 행거(12)와 왯지 블록(13)에 의해 서로 연결되는 방식으로 복수의 바닥층 슬래브를 관통할 수 있다.19 and 20 showing a hypothesis unit according to a sixth embodiment of the present invention, wherein the traction member of the present invention is a steel string 2 '', the first end of which is an upper descending hanger 12 Through the uncured bottom layer slab 3, the second end of which is connected to the load bearing member on the uncured bottom layer slab 3. The lower end of the upper lowering hanger 12 is connected with a wedge block 13 having a small upper end and a larger lower end, the wedge block 13 penetrating the bottom layer slab 3. The lower end of the wedge block 13 is connected with the lower lower hanger 12 used to tighten the steel string 2 '' by suspending the weight, and after pouring the concrete, the bottom layer slab 3 with no pulling force hardened It can be produced to interfere with the weight of. When the load bearing member on the bottom layer slab 3 is connected with the truss of the positioning member, the upper end of the steel string 2 '' is connected to the truss, and the lower end of the steel string 2 '' is wedge block 13. Through the bottom layer slab (3) not cured through. If the load-bearing member on the uncured bottom layer slab 3 is the towing member of the upper bottom layer slab, the steel strings 2 " each part of the steel strings 2 " It is possible to penetrate a plurality of bottom layer slabs in a manner connected to each other by a block 13.
본 발명의 제6 실시예에 따른 가설 유닛을 도시하는 도21 및 도22를 참조하면, 본 실시예의 견인 부재는 철제 체인(2)이고, 다른 부품은 상술된 제6 실시예와 동일하므로, 다른 설명은 생략하기로 한다.21 and 22 showing the hypothesis unit according to the sixth embodiment of the present invention, the towing member of the present embodiment is an iron chain 2, and other parts are the same as those of the sixth embodiment described above. The description will be omitted.
본 발명에 따른 다양한 실시예가 도시되고 기술되었지만, 다른 실시예가 본 발명의 범위 내에서 있을 수 있다는 것을 당업자라면 명확히 알 수 있을 것이다.While various embodiments in accordance with the present invention have been shown and described, it will be apparent to those skilled in the art that other embodiments may be within the scope of the present invention.
본 발명에 의하면, 바닥층 슬래브는 응고화 과정 동안 상부 바닥층 슬래브에의해 가압되지 않아서, 하부 바닥층 슬래브는 상부 바닥층 슬래브의 중량에 의해 야기된 변형으로부터 방지될 수 있는 효과가 있다. 또한, 견인 부재의 도움으로, 바닥층 슬래브 몰드가 제거될 수 있고 다음 하부 바닥층 슬래브는 바닥층 슬래브가 완전히 응고하기 전 설치될 수 있어서 설치 속도가 증가되는 효과가 있다. 또한, 바닥층 슬래브의 설치가 상부층에서 시작해서 하부층으로 수행되기 때문에, 바닥층 슬래브 몰드를 제거한 후 바닥층 슬래브는 하강되고 견인 부재를 사용함으로써 중력의 영향으로 다음 층에 설치될 수 있어서, 바닥층 슬래브 몰드의 설치 및 수송이 간단한 효과를 제공한다.According to the present invention, the bottom layer slab is not pressed by the top bottom layer slab during the solidification process, so that the bottom bottom slab has an effect that can be prevented from deformation caused by the weight of the top bottom layer slab. In addition, with the aid of the traction member, the bottom layer slab mold can be removed and the next bottom layer slab can be installed before the bottom layer slab is completely solidified, which has the effect of increasing the installation speed. In addition, since the installation of the bottom layer slab is performed from the top layer to the bottom layer, after removing the bottom layer slab mold, the bottom layer slab is lowered and can be installed in the next layer by the influence of gravity by using a traction member, thereby installing the bottom layer slab mold. And transportation provides a simple effect.
Claims (19)
Applications Claiming Priority (7)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 02114828 CN1364967A (en) | 2002-02-01 | 2002-02-01 | Fast mounting device and method for building floor |
CN02114828.7 | 2002-02-01 | ||
CN02250110.X | 2002-12-09 | ||
CN 02250110 CN2589586Y (en) | 2002-12-09 | 2002-12-09 | Fixing device for architecture floor plate |
CN 02250109 CN2589585Y (en) | 2002-12-09 | 2002-12-09 | Architecture floor plate fixing apparatus |
CN02250109.6 | 2002-12-09 | ||
PCT/CN2003/000069 WO2003064781A1 (en) | 2002-02-01 | 2003-01-24 | An erection unit for a building floor slab and the erection method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20040078146A true KR20040078146A (en) | 2004-09-08 |
Family
ID=27669601
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2004-7011736A KR20040078146A (en) | 2002-02-01 | 2003-01-24 | An erection unit for a building floor slab and the erection method thereof |
Country Status (11)
Country | Link |
---|---|
US (1) | US20050076599A1 (en) |
EP (1) | EP1484457A4 (en) |
JP (1) | JP2005525485A (en) |
KR (1) | KR20040078146A (en) |
AU (1) | AU2003240022B2 (en) |
BR (1) | BR0307536A (en) |
CA (1) | CA2473755A1 (en) |
MX (1) | MXPA04007379A (en) |
NO (1) | NO20043225L (en) |
RU (1) | RU2281364C2 (en) |
WO (1) | WO2003064781A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101445365B1 (en) * | 2012-12-10 | 2014-09-26 | (주)나우기술 | Fxied ventilating slab at tunnel lining |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100460613C (en) * | 2005-08-02 | 2009-02-11 | 浙江展诚建设集团股份有限公司 | Suspension holder construction method |
CN109403523B (en) * | 2018-11-27 | 2024-01-05 | 福建卓越建设工程开发有限公司 | Prefabricated assembled laminated slab suspension type supporting structure and laminated slab construction method |
US11408188B1 (en) | 2019-06-04 | 2022-08-09 | Peri Formwork Systems, Inc. | Suspended translating platform |
TWI789970B (en) * | 2021-03-05 | 2023-01-11 | 台灣櫻花股份有限公司 | Embedded structure |
TWI762228B (en) * | 2021-03-05 | 2022-04-21 | 台灣櫻花股份有限公司 | Method for assembling embedded structure |
CN114809579B (en) * | 2022-05-08 | 2023-07-07 | 山西三建集团有限公司 | Erection method of lifting construction platform for erecting formwork system around lighting well |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1701113A (en) * | 1927-05-09 | 1929-02-05 | Will E Keller | Method of and apparatus for pouring concrete walls and floors of steel and concrete frame buildings |
US3275719A (en) * | 1963-08-07 | 1966-09-27 | Brian H Dudson | Method of building in situ construction using sequential molding techniques |
DE1684430C3 (en) * | 1966-08-09 | 1978-10-05 | Dyckerhoff & Widmann Ag, 8000 Muenchen | Method for building high-rise buildings or the like. and device for carrying out the method |
JPH04505040A (en) * | 1989-02-08 | 1992-09-03 | ルベカ・コンストラクション・システムズ・ピーテーワイ・リミテッド | building construction system |
US5469684A (en) | 1993-08-10 | 1995-11-28 | Franklin; James W. | Concrete building frame construction method |
CN1131225A (en) * | 1995-03-10 | 1996-09-18 | 李文元 | Building floor form unit construction method and device |
JPH0921184A (en) * | 1995-07-05 | 1997-01-21 | Satougumi:Kk | Construction method of building foundation |
CH688417A5 (en) * | 1995-10-25 | 1997-09-15 | Pecon Ag | Formwork element. |
JP2000045524A (en) * | 1998-07-24 | 2000-02-15 | Hazama Gumi Ltd | Construction method of building |
CN1203239C (en) * | 2001-10-22 | 2005-05-25 | 李渊河 | Method and equipment for installing floor slabs of building |
-
2003
- 2003-01-24 EP EP03734643A patent/EP1484457A4/en not_active Withdrawn
- 2003-01-24 BR BR0307536-2A patent/BR0307536A/en not_active IP Right Cessation
- 2003-01-24 KR KR10-2004-7011736A patent/KR20040078146A/en active IP Right Grant
- 2003-01-24 AU AU2003240022A patent/AU2003240022B2/en not_active Expired - Fee Related
- 2003-01-24 JP JP2003564362A patent/JP2005525485A/en active Pending
- 2003-01-24 RU RU2004126670/03A patent/RU2281364C2/en not_active IP Right Cessation
- 2003-01-24 US US10/503,017 patent/US20050076599A1/en not_active Abandoned
- 2003-01-24 WO PCT/CN2003/000069 patent/WO2003064781A1/en active Application Filing
- 2003-01-24 CA CA002473755A patent/CA2473755A1/en not_active Abandoned
- 2003-01-24 MX MXPA04007379A patent/MXPA04007379A/en not_active Application Discontinuation
-
2004
- 2004-07-30 NO NO20043225A patent/NO20043225L/en unknown
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101445365B1 (en) * | 2012-12-10 | 2014-09-26 | (주)나우기술 | Fxied ventilating slab at tunnel lining |
Also Published As
Publication number | Publication date |
---|---|
CA2473755A1 (en) | 2003-08-07 |
AU2003240022B2 (en) | 2007-03-22 |
RU2004126670A (en) | 2006-02-10 |
RU2281364C2 (en) | 2006-08-10 |
JP2005525485A (en) | 2005-08-25 |
WO2003064781A1 (en) | 2003-08-07 |
MXPA04007379A (en) | 2004-12-06 |
NO20043225L (en) | 2004-10-27 |
BR0307536A (en) | 2005-06-28 |
EP1484457A4 (en) | 2006-06-07 |
EP1484457A1 (en) | 2004-12-08 |
US20050076599A1 (en) | 2005-04-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8291676B2 (en) | Mold-concrete composite crossbeam and construction method using the same | |
JP4738886B2 (en) | Equipment foundation | |
CN105464216B (en) | Construction method based on integral lifting formwork-strengthening system superelevation super-section batter post | |
JPH11181725A (en) | Method for constructing horizontal beam of main tower made of concrete | |
KR20040078146A (en) | An erection unit for a building floor slab and the erection method thereof | |
KR100832100B1 (en) | Temporal structure and temporal setting method for stress control of the pylon base | |
KR20070107495A (en) | Concrete-mold assembly and construction method using the same | |
US6036165A (en) | Method and apparatus for constructing a building unit | |
JP2001115422A (en) | Dismantling method of supporting for form fixed to concrete slab | |
JP2003306908A (en) | Connecting structure of superstructure work and substructure work of bridge and its construction method | |
KR100477223B1 (en) | A mold supporting device of slab | |
JPH0657956A (en) | Construction of concrete structure | |
KR102311332B1 (en) | Method for constructing bridge inspection facility using form tie | |
CN113027132A (en) | Concrete stepped pouring method for subway slope section plate | |
CN110409820B (en) | Formwork supporting device for construction of cantilever structure and construction method thereof | |
ZA200406087B (en) | An erection unit for a building floor slab and theerection method thereof. | |
JP5437876B2 (en) | Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct | |
KR100507597B1 (en) | Formwork supporting apparatus for hanging type formwork system and formwork using the same | |
JP3146172B2 (en) | Construction method of bridge using extension cable | |
CN115043330B (en) | Support structure of inner climbing frame of tower crane in non-core tube area, inner climbing frame and tower crane | |
JP3078195U (en) | Prestressed concrete structure | |
JP2000160834A (en) | Step-up construction of concrete caisson | |
KR101594961B1 (en) | Connecting device for slab wall form | |
CN115324344A (en) | Construction method suitable for fireproof door frame column | |
JPS638260B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application | ||
J201 | Request for trial against refusal decision | ||
J301 | Trial decision |
Free format text: TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20091022 Effective date: 20110830 |
|
S901 | Examination by remand of revocation | ||
GRNO | Decision to grant (after opposition) | ||
NORF | Unpaid initial registration fee |