KR20040028221A - Support construction for slab of prestressed concrete beam of bridge - Google Patents
Support construction for slab of prestressed concrete beam of bridge Download PDFInfo
- Publication number
- KR20040028221A KR20040028221A KR1020020059357A KR20020059357A KR20040028221A KR 20040028221 A KR20040028221 A KR 20040028221A KR 1020020059357 A KR1020020059357 A KR 1020020059357A KR 20020059357 A KR20020059357 A KR 20020059357A KR 20040028221 A KR20040028221 A KR 20040028221A
- Authority
- KR
- South Korea
- Prior art keywords
- slab
- pedestal
- cantilever
- support
- support frame
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/12—Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
- E01D19/125—Grating or flooring for bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
본 발명은 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조에 관한 것으로서, 더욱 상세하게는 피.에스.씨-빔 교량의 상판 슬래브의 가시설 구조물인 거푸집 설치가 편리하고 안전하도록 하여 시공 기간을 단축할 수 있고, 와이어(또는 철사)를 사용하지 않는 관계로 시공 완료 후 부식의 문제를 완전히 차단할 수 있는 구조를 가지는 피.에스.씨-빔 교량의 상판 슬래브 지지용 가시설 구조물에 관한 것이다.The present invention relates to a top slab temporary structure of a P. S. C-beam bridge, and more particularly, to provide a convenient and safe formwork construction of the formwork of a top slab of a P. S-beam bridge. The present invention relates to a temporary slab support structure for supporting slab of a P.S.C-beam bridge having a structure that can be shortened and can completely prevent the problem of corrosion after completion of construction since no wire (or wire) is used.
일반적으로 피.에스.씨-빔 교량 상판 슬래브의 가시설을 하기 위해서는 피.에스.씨-빔 거치후 피.에스.씨-빔 상면에 노출되어 있는 철근에 반생을 연결하여 피.에스.씨-빔 하부에 철재 파이프를 설치하여 연결고정하고, 상기의 철재 파이프 위에 합판을 거치하고 또 다시 반생으로 합판과 철재 파이프를 체결고정한다.In general, in order to install the S-C beam beam slab, the steel is exposed to the rebar exposed on the upper surface of the S-C beam after the beam is mounted. The steel pipe is installed in the lower part of the beam to fix the connection, and the plywood is mounted on the steel pipe, and again, the plywood and the steel pipe are fastened and fastened.
이러한 가시설의 작업 공간을 확보하여 피.에스.씨-빔 측면에 목재를 이용하여 슬래브 받침대를 거치하고 그 다음 슬래브 받침대의 상판에 슬래브 거푸집을 설치하며, 상기의 피.에스.씨-빔 양측에 캔틸레버 받침틀을 반생으로 고정하여 캔틸레버 슬래브 구간의 가시설의 설치를 완료하였다.Secure the working space of this temporary facility by mounting the slab pedestal using wood on the side of the P.S. beam and then installing the slab formwork on the top plate of the slab support, and on both sides of the P.S. beam. The cantilever support frame was fixed to half life to complete the installation of the temporary facility in the cantilever slab section.
도 1은 일반적인 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조의 시공도로서, (a)는 1단계에서 4단계까지를 나타내는 순서도, (b)는 5단계에서 8단계까지를나타내는 순서도이다.1 is a construction diagram of a top slab temporary structure of a general PS-C beam beam, (a) is a flow chart showing the steps 1 to 4, (b) is a flow chart showing the steps 5 to 8. .
제 1 단계는 피.에스.씨-빔을 교각에 거치하는 단계로, 도면에는 교각을 도시하지 않았고, 상기의 교각에는 그 직상부에 수평하게 4본의 피.에스.씨-빔(10)이 안착된다.The first step is to mount the P.S.C-Beam to the pier, in which the pier is not shown in the drawing, in which the four P.S.C-Beams 10 are arranged horizontally above the pier. Is seated.
제 2 단계는 피.에스.씨-빔(10)의 하부, 즉 교각의 길이방향에 철재 파이프(12)를 설치한 후 피.에스.씨-빔이 유동이 없도록 피.에스.씨-빔(10)과 철재 파이프(12)를 와이어(14)로 고정하는 단계로, 상기의 와이어(14)는 주로 철사를 이용하여 사용한다.The second step is to install the steel pipe 12 at the lower part of the P.S.C-beam 10, i.e., in the longitudinal direction of the piers, so that the P.S.C-Beam is free of flow. 10 and the steel pipe 12 is fixed to the wire 14, the wire 14 is mainly used by using a wire.
제 3 단계는 4본의 피.에스.씨-빔(10)의 사이에 받침 합판(16)을 설치하고 피.에스.씨-빔(10)의 사이에 슬래브 받침 목재(18)를 설치하는 단계로, 상기의 받침 합판(16)은 4본의 피.에스.씨-빔(10)의 사이에 안착되어 와이어(14)로 철재 파이프와 고정되고, 상기의 슬래브 받침 목재(18)는 상,하부에 수평 받침목재가 형성되는 한편, 상기의 수평 받침목재의 사이에는 수직 받침목재가 다수개 연결되는 구조로, 하부 수평 받침목재가 상부 수평 받침목재보다 길이가 길다.The third step is to install the supporting plywood 16 between the four PS-beams 10 and the slab support wood 18 between the PS-beams 10. In the step, the supporting plywood 16 is seated between the four P.S.C-beams 10 and fixed to the steel pipe with a wire 14, and the slab supporting wood 18 is The horizontal support timber is formed at the bottom, while the vertical support timber is connected between the horizontal support timbers, and the lower horizontal support timber is longer than the upper horizontal support timber.
제 4 단계는 피.에스.씨-빔(10)의 양측면에는 콘크리트 타설시 양측에 설치된 피.에스.씨-빔(10)이 유동이 없도록 캔틸레버 받침틀(20)이 와이어로 고정되도록 설치되고 상기의 슬래브 받침 목재(18)의 상부에 슬래브 바닥판(22)을 설치하는 단계이다.In the fourth step, the cantilever support frame 20 is installed on both sides of the PS-beam 10 so that the cantilever support frame 20 is fixed with wires so that the CS-beam 10 installed on both sides of the concrete is not flown. Step of installing the slab bottom plate 22 on top of the slab support wood 18.
상기의 슬래브 바닥판(22)은 목재 합판을 사용하는 경우가 많고, 설치시 그 직하부에 사각 목재가 설치되며, 상기의 캔틸레버 받침틀(20)은 하부가 철재 파이프와 와이어로 고정된다.The slab bottom plate 22 is often using a wooden plywood, the square wood is installed directly below the installation, the cantilever support frame 20 is fixed to the lower portion of the steel pipe and wire.
제 5 단계는 캔틸레버 받침틀(20)의 상부 측면에 슬래브 콘크리트를 타설하여 상판 슬래브를 시공할 수 있도록 측면 수직 거푸집(24)을 설치하는 단계이다.The fifth step is to install the side vertical formwork 24 so that the slab concrete is placed on the upper side of the cantilever support frame 20 to construct the upper slab.
제 6 단계는 슬래브 바닥판(22)과 측면 측면 수직 거푸집(24)의 사이, 즉 피.에스.씨-빔(10)에 수평 및 수직하도록 슬래브 철근(26)을 조립하고 콘크리트를 타설하는 단계이다.The sixth step is to assemble the slab reinforcement 26 and pour concrete between the slab bottom plate 22 and the lateral side vertical formwork 24, i.e., horizontally and perpendicular to the P.S.C-beam 10. to be.
제 7 단계는 콘크리트 슬래브의 양생이 완료되면 캔틸레버 받침틀과 슬래브 받침 목재 및 가시설 구조물을 해체하는 단계이다.The seventh step is to dismantle the cantilever support frame, the slab support wood and the temporary structure after the curing of the concrete slab is completed.
이때 교각 상부에 설치된 철재 파이프(12)와 받침 합판(16)은 그대로 유지된 상태이다.At this time, the steel pipe 12 and the supporting plywood 16 installed in the upper portion of the pier is maintained as it is.
제 8 단계는 피.에스.씨-빔(10)의 하부에 있는 받침 합판(16)과 철재 파이프(12)를 해체하고 와이어(14)를 절단하여 피.에스.씨-빔(10)의 상부에 상판 슬래브(28)를 시공완공하는 단계로, 상기의 받침 합판(16)과 철재 파이프(12)는 도면상 참조 번호가 없는 상태임을 잘 알 수 있다.The eighth step is to dismantle the supporting plywood 16 and the steel pipe 12 at the bottom of the P. C-beam 10 and to cut the wire 14 to the P. In the step of completing the construction of the upper slab 28 on the top, it can be seen that the supporting plywood 16 and the steel pipe 12 has no reference number in the drawings.
상술한 제 1 단계와 제 8 단계에 점선으로 표시한 것은 도면상 교각 상부에 피.에스.씨-빔이 안착되는 상태를 설명하기 위함이다.The first step and the eighth step are indicated by dotted lines in order to explain a state in which the P.S.C-beam is seated on the pier.
상술한 순서도에서 알 수 있는 바와 같이, 피.에스.씨-빔(10)의 하부에 있는 받침 합판(16)과 철재 파이프(12)의 해체가 어려워 작업자가 작업 도중 교각의 하부로 추락할 가능성이 높아 인명 사고가 발생될 소지가 많고, 상판 슬래브(28)의 밑면에 있는 와이어(14)는 철사를 사용하는 일이 많아 공기중에 노출시 부식이 발생되며, 이러한 와이어(14)의 부식은 슬래브 철근(26)까지 부식시켜 철근의 팽창에 의한 콘크리트의 균열이 발생되어 상판 슬래브의 하자로 이어져 교량의 안전성을 해하는 등 문제점이 있다.As can be seen from the above-described flow chart, the disassembly of the supporting plywood 16 and the steel pipe 12 in the lower portion of the P.C-beam 10 is difficult and the worker may fall to the lower part of the piers during the operation. Due to the high risk of human accidents, the wire 14 on the bottom of the upper slab 28 is often used for the wire, the corrosion occurs when exposed to the air, the corrosion of the wire 14 is slab Corrosion to the reinforcing bar (26) is caused by the cracking of the concrete due to the expansion of the reinforcing bar leads to a defect of the slab of the slab, there is a problem such as deteriorating the safety of the bridge.
또한, 상술한 순서와 같이 개략적으로 8단계로 시공이 이루어지는 관계로 공정이 복잡하고 가시설의 해체 및 설치에 시공 기간이 길어지는 문제점이 있다.In addition, there is a problem in that the construction is complicated in the eight steps as described above, the process is complicated, and the construction period is long to dismantle and install the temporary facility.
또한, 피.에스.씨-빔(10)의 상부에 상판 슬래브(28)를 시공하는데 사용되는 가시설은 철거 후 목재가 많이 사용되는 관계로 폐기물로 처리되어 폐기물의 처리비용이 상승되는 문제점이 있다.In addition, the temporary facility used to construct the top slab 28 on the top of the P. C-beam (10) has a problem that the disposal cost of the waste is increased because it is treated as a waste because a lot of wood is used after demolition. .
본 고안은 상술한 문제점을 해결하기 위하여, 본 고안은, 피.에스.씨-빔 교량의 상판 슬래브의 가시설 구조물인 거푸집 설치가 편리하고 안전하도록 하여 시공 기간을 단축할 수 있고, 와이어(또는 철사)를 사용하지 않는 관계로 시공 완료 후 부식의 문제를 완전히 차단할 수 있는 구조를 가지는 피.에스.씨-빔 교량의 상판 슬래브 지지용 가시설 구조물을 제공함을 그 목적으로 한다.The present invention, in order to solve the above problems, the present invention, the formwork structure of the upper plate slab of the P. S. C-beam bridge can be convenient and safe to install and shorten the construction period, the wire (or wire It is an object of the present invention to provide a temporary slab support structure for supporting slab of P.S.C-Beam Bridge which has a structure that can completely prevent the problem of corrosion after completion of construction.
도 1은 일반적인 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조의 시공도로서, (a)는 1단계에서 4단계까지를 나타내는 순서도, (b)는 5단계에서 8단계까지를 나타내는 순서도.1 is a construction diagram of a top slab temporary structure of a general P. S. C-beam bridge, (a) is a flow chart showing the first to four stages, (b) is a flow chart showing the five to eight steps.
도 2는 본 발명의 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조를 나타내는 제작 개념도.Figure 2 is a production conceptual diagram showing the top slab temporary structure of the P. S. C-beam bridge of the present invention.
도 3은 본 발명의 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조의 시공도로서, (a)는 1단계에서 4단계까지를 나타내는 순서도, (b)는 5단계에서 7단계까지를 나타내는 순서도.3 is a construction diagram of the upper slab temporary structure of the P.S.C-beam bridge of the present invention, (a) is a flow chart showing the steps 1 to 4, (b) shows a five to seven steps Flowchart.
<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>
50 : 피.에스.씨-빔 52 : ㄷ형강50: P.S.C-Beam 52: C-beam
54,58,132: 체결볼트홀 56,112: 체결볼트54,58,132: Tightening bolt hole 56,112: Tightening bolt
60 : 하부 받침틀 70,90 : 상,하부 슬래브 받침대60: lower support frame 70,90: upper and lower slab support
80 : 길이조정 받침대 100: 슬래브 바닥판80: length adjustment base 100: slab bottom plate
102: 절곡부 110: 캔틸레버 하부 받침틀102: bent portion 110: cantilever lower support frame
120: 캔틸레버 슬래브 받침대 130: 격자형 패널120: cantilever slab pedestal 130: grid panel
136: 슬래브 철근 140: 슬래브 측면 거푸집136: slab reinforcement 140: slab side formwork
150: 상판 슬래브150: top slab
본 고안은 상술한 목적을 달성하기 위하여, 본 고안은, 피.에스.씨-빔(50)에는 길이방향의 하부 양측면에 ㄷ형강(52)이 체결 볼트(56)로 고정된 상태로 교각 상부에 다수본(本)이 거치되는 한편, 수 본(本)의 피.에스.씨-빔(50)중 폭 방향 외측에 거치되는 피.에스.씨-빔(50)에는 상부 일측면에 체결 볼트홀(58)이 형성되고, 피.에스.씨-빔(50)의 하부 고정된 ㄷ형강(52)에는 내측을 관통하도록 체결볼트홀(54)이 형성되며, 수 본의 피.에스.씨-빔(50)이 설치된 사이에는 하부 받침틀(60)과 하부 슬래브 받침대(70)가 일체로 결합된 상태로 형성되어 ㄷ형강(52)의 내측에 하부 받침틀(60)이 삽입되어 안착된 형태로 설치되고, 하부 슬래브 받침대(70)에는 상부에 다수개의 길이조정 받침대(80)가 설치되고, 그 길이조정 받침대(80)의 상부에는 상부 슬래브 받침대(90)가 볼팅되거나 용접되어 고정되며, 상부 슬래브 받침대(90)의 상부에는 슬래브 바닥판(100)이 안착되고, 그 슬래브 바닥판(100)은 폭 방향의 양측에 절곡부(102)가 형성되며, 피.에스.씨-빔(50)의 ㄷ형강(52)에는 F자 형태로 제작된 캔틸레버 하부 받침틀(110)이 누운 형태로 삽입된 상태에서 장경의 체결 볼트(112)로 체결되고, 캔틸레버 하부 받침틀(110)에는 일측 상부에 캔틸레버 슬래브 받침대(120)가 설치되는 때 하부가 체결 볼트(56)로 체결되는 한편, 상기의 캔틸레버 슬래브 받침대(120)는, 상부가 피.에스.씨-빔(50)의 상부 체결 볼트홀(58)에 체결 볼트(56)가 체결되어 고정되고, 캔틸레버 슬래브 받침대(120)에는 상부에 슬래브 측면 거푸집(140)이 용접 또는 볼트로 체결되는 구조로 슬래브 측면 거푸집(140), 캔틸레버 슬래브 받침대(120), 슬래브 바닥판(100)이 연접되게 설치된 상부에 콘크리트가 타설되어 상판 슬래브(150)를 시공할 수 있도록 구성된 것을 특징으로 하는 피.에스.씨-빔 교량의 상판 슬래브 지지용 가시설 구조물을 제공한다.In order to achieve the above object, the present invention, the P. S. C-beam 50, the upper portion of the piers in the state in which the c-shaped steel 52 is fixed to the fastening bolt 56 on both sides of the lower side in the longitudinal direction While the majority is mounted on the P. S. C-beam 50 of the male bone, the P. S. C-beam 50 mounted on the outer side in the width direction is fastened to one side of the upper portion. A bolt hole 58 is formed, and a fastening bolt hole 54 is formed in the C-shaped steel 52 fixed to the lower portion of the P.S.C-beam 50 so as to penetrate the inside thereof. The lower support frame 60 and the lower slab pedestal 70 are integrally formed between the seed beams 50 and the lower support frame 60 is inserted into the c-beam 52 to be seated. The lower slab pedestal 70 is provided with a plurality of length adjustment pedestal 80 at the top, the upper slab pedestal 90 is bolted to the upper portion of the length adjustment pedestal 80 or The welded and fixed, the slab bottom plate 100 is seated on the upper portion of the upper slab pedestal 90, the slab bottom plate 100 is bent portion 102 is formed on both sides of the width direction, P. S. The c-beam (50) of the c-beam (52) is fastened with a fastening bolt 112 of the long diameter in the state in which the cantilever lower support frame (110) made in the shape of F is inserted in a lying state, the cantilever lower support frame (110) When the cantilever slab pedestal 120 is installed on one side of the upper portion, the lower portion is fastened by the fastening bolt 56, while the cantilever slab pedestal 120 has an upper portion of the P.S.C-beam 50. The fastening bolt 56 is fastened and fixed to the fastening bolt hole 58, and the slab side formwork 140 is welded or bolted to the cantilever slab pedestal 120 at an upper portion thereof. The upper part of the slab base 120, the slab bottom plate 100 is installed in contact Concrete is poured into the top plate slab 150 to provide a structural structure for supporting the top plate slab of the P. S. C-beam bridge, characterized in that configured to be constructed.
이하, 첨부 도면을 참조하여 본 고안의 구성과 작동 상태를 설명한다.Hereinafter, with reference to the accompanying drawings will be described the configuration and operating state of the present invention.
도 2는 본 발명의 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조를 나타내는 제작 개념도이다.Fig. 2 is a production conceptual diagram showing the top slab temporary structure of the P.S.C-beam bridge of the present invention.
도 2에서 알 수 있는 바와 같이, 피.에스.씨-빔 교량은, 교각 상부에 피.에스.씨-빔(50)을 거치하고 콘크리트를 타설하여 상판 슬래브를 시공하는 경우, 가시설 구조물을 설치하는 개념을 잘 나타내고 있다.As can be seen in Figure 2, the P. S. C-beam bridge is installed on the top of the pier, the concrete slab is installed by mounting the P. S. C-beam (50) in the upper portion of the bridge, the installation of the temporary structure It shows the concept to say well.
상기의 피.에스.씨-빔(50)이 2 본(本)(또는 4본이 설치가 가능)이 교각 상부에 거치되는 때 미리 피.에스.씨-빔(50)의 길이방향의 측면에 ㄷ형강(52)이 체결 볼트(56)로 결합되는 한편, 상기의 피.에스.씨-빔(50)과 결합된 ㄷ형강(52)에는 내측을 관통하도록 체결 볼트홀(54)이 형성되고, 상기의 피.에스.씨-빔(50)에는 상부에 체결 볼트홀(58)이 각각 일측에 형성된다.The longitudinal side of the P.S.C-beam 50 in advance when the P.S.C-beam 50 is mounted on the top of the piers when two (or four) can be mounted. While the c-beams 52 are coupled to the fastening bolts 56, the fastening bolt holes 54 are formed in the c-beams 52 coupled with the P. C-beam 50 to penetrate the inside thereof. In the above P.S.C-beam 50, fastening bolt holes 58 are formed on one side thereof, respectively.
상기의 2본의 피.에스.씨-빔(50)이 설치된 사이에는 하부 받침틀(60)이 ㄷ형강(52)에 삽입된 상태로 형성되고, 상기의 하부 받침틀(60)과 하부 슬래브 받침대(70)는 강재 구조물로 일체로 형성된다.The lower support frame 60 is formed in the state where the lower support frame 60 is inserted into the c-beam 52 between the two P.S.C-beams 50, and the lower support frame 60 and the lower slab supporter ( 70 is integrally formed of a steel structure.
상기의 하부 슬래브 받침대(70)에는 상부에 다수개의 길이조정 받침대(80)가 안착되는데, 상기의 길이조정 받침대(80)는 높이를 조정할 수 있는 일반적인 지지 구조물로 공사 현장에서 많이 사용되는 관계로 자세한 설명은 생략한다.The lower slab pedestal 70 has a plurality of length adjustment pedestal 80 is seated on the upper side, the length adjustment pedestal 80 is a general support structure that can adjust the height in relation to use a lot in construction sites in detail Description is omitted.
상기의 길이조정 받침대(80)의 상부에는 강재 구조물로 제작되는 상부 슬래브 받침대(90)가 형성되고, 상기의 상부 슬래브 받침대(90)의 상부에는 슬래브 바닥판(100)이 결합되며, 특히 상기의 길이조정 받침대(80), 상부 슬래브 받침대(90) 및 슬래브 바닥판(100)은 일체 구조로 제작하여 크레인 등의 인양 장비를 이용하여 교각 상부 피.에스.씨-빔(50)이 다수본 거치된 사이에 설치된다.The upper slab pedestal 90 is formed on the upper portion of the length adjustment pedestal 80 is made of a steel structure, the slab bottom plate 100 is coupled to the upper portion of the upper slab pedestal 90, in particular the The length adjustment pedestal 80, the upper slab pedestal 90 and the slab bottom plate 100 are manufactured in an integrated structure, and the pier upper P.S.C-beam 50 is attached to the pier by using lifting equipment such as a crane. Is installed between.
상기의 슬래브 바닥판(100)은 폭방향(도면상 전단모습의 형태)의 양측에 절곡부(102)가 경사지게 형성된 형태로, 콘크리트를 타설하여 상판 슬래브를 시공하는 경우 피.에스.씨-빔(50)의 상부의 상판 슬래브의 두께보다 이격된 사이의 두께가 적도록 상부 슬래브 받침대(90)의 높이만큼 차이가 나도록 설치함이 적정하다.The slab bottom plate 100 has a bent portion 102 formed to be inclined on both sides in the width direction (shape of shear on the drawing), when the concrete slab is installed when constructing the top slab It is appropriate to install so as to be different by the height of the upper slab pedestal 90 so that the thickness between the spaced apart than the thickness of the upper slab of the upper portion of the upper 50.
상기의 2본의 피.에스.씨-빔(50)에는 ㄷ형강(52)의 체결 볼트홀(54)에 캔틸레버 하부 받침틀(110)이 체결 볼트(112)로 체결되는 구조로, 상기의 캔틸레버 하부 받침틀(110)은 F자 형태로 제작되고 누워진 상태로 ㄷ형강(52)이 설치된 사이에 삽입되어 결합된다.In the two P.S.C-beams 50, the cantilever lower support frame 110 is fastened to the fastening bolt hole 54 of the c-shaped steel 52 by the fastening bolt 112. The lower support frame 110 is manufactured in an F shape and inserted and coupled between the c-shaped steels 52 installed in a laid state.
상기의 캔틸레버 하부 받침틀(110)에는 일측 상부, 즉 피.에스.씨-빔(50)이 거치된 측면에 캔틸레버 슬래브 받침대(120)가 설치되는 한편, 상기의 캔틸레버 슬래브 받침대(120)는, 직삼각형 형태로 제작되는 구조물로, 캔틸레버 슬래브 받침대(120)는 사각 강재가 직삼각형 구조로 형성되고, 수평한 사각 강재의 상부에 격자형 패널(130)이 용접되어 일체로 구성되며, 상기의 격자형 패널(130)에는 수직한 면에 체결 볼트홀(132)이 형성되어 피.에스.씨-빔(50)의 상부에 체결 볼트(56)로 체결되고, 상부면을 아연 도금 처리하여 콘크리트 타설시 서로 접착되지 않도록 형성된다.The cantilever slab pedestal 120 is installed on one side of the cantilever slab pedestal 110, that is, the side on which the P.S.C-beam 50 is mounted, while the cantilever slab pedestal 120 is a right triangle. The cantilever slab pedestal 120 has a rectangular steel structure formed in a right triangle structure, and the grid-shaped panel 130 is welded to the upper portion of the horizontal square steel to be integrally formed, and the grid-shaped panel ( 130, a fastening bolt hole 132 is formed on a vertical surface and fastened to the upper part of the P.S.C-beam 50 by fastening bolts 56, and the upper surface is galvanized to adhere to each other during concrete pouring. It is formed so as not to.
즉, 상기의 캔틸레버 슬래브 받침대(120)는, 상부가 피.에스.씨-빔(50)의 상부에 단경의 체결 볼트(56)로 고정되고, 하부가 캔틸레버 하부 받침틀(110)의 상부에 안착된 상태에서 장경의 체결 볼트(112)로 체결되는 구조이다.That is, the cantilever slab pedestal 120 has an upper portion fixed to the upper portion of the P.S.C-beam 50 by a fastening bolt 56 having a short diameter, and the lower portion thereof is seated on the upper portion of the cantilever lower support frame 110. It is a structure that is fastened with a fastening bolt 112 of the long diameter in the state.
이때, 상기의 피.에스.씨-빔(50)은 양측 하부에 소경의 체결 볼트(56)로 ㄷ형강(52)을 수평하게 체결하고, 상기의 피.에스.씨-빔(50)에는 상부 일측에 소경의체결 볼트(56)로 캔틸레버 슬래브 받침대(120)를 체결하며, 한편 상기의 피.에스.씨-빔(50)에는 양측에 장경의 체결 볼트(112)를 사용하여 ㄷ형강(52), 캔틸레버 하부 받침틀(110), 캔틸레버 슬래브 받침대(120)를 수직하게 체결하여, 콘크리트를 타설하여 상판 슬래브를 시공하는 경우 하부에서 지지하는 가시설을 구성하게 된다.At this time, the P.S.C-beam 50 is fastened horizontally to the c-beams 52 by the fastening bolt 56 of the small diameter on both lower sides, the P.S.C-beam 50 Fasten the cantilever slab supporter 120 with a small fastening bolt 56 on the upper side, while the above C. C-beam 50 uses long fastening bolts 112 on both sides of the c-shaped steel ( 52), the cantilever lower support frame 110, the cantilever slab pedestal 120 is vertically fastened, when constructing the concrete slab to construct the upper slab to configure the temporary support from the bottom.
상기의 캔틸레버 슬래브 받침대(120)에는 상부에 슬래브 측면 거푸집(140)이 용접 또는 볼팅되어 수직하게 지지되는데, 상기의 슬래브 측면 거푸집(140)은 수직한 패널의 측면에 지지 막대가 형성된 구조로 콘크리트 타설시 측면을 수직하게 유지하도록 구성된다.The cantilever slab pedestal 120 is vertically supported by welding or bolting the slab side formwork 140 on the upper side, wherein the slab side formwork 140 has a structure in which a support bar is formed on the side of the vertical panel to form concrete. It is configured to keep the city side vertical.
상술한 설명과 같이, 상기의 피.에스.씨-빔(50)에는 상부에 하부 받침틀(60), 하부 슬래브 받침대(70), 길이조정 받침대(80), 상부 슬래브 받침대(90) 및 슬래브 바닥판(100)이 설치되고, 상기의 피.에스.씨-빔(50)에는 양측에 캔틸레버 하부 받침틀(110), 캔틸레버 슬래브 받침대(120) 및 슬래브 측면 거푸집(140)이 가시설 구조물로 설치되는데, 상기의 부재들은 모두 강(鋼) 구조물로 형성된다.As described above, the P.S.C-beam 50 has a lower support frame 60, a lower slab support 70, a length adjustment bracket 80, an upper slab support 90 and a slab bottom at the top. The plate 100 is installed, and the P.S.C-beam 50 is provided with a cantilever lower support frame 110, a cantilever slab pedestal 120 and a slab side formwork 140 on both sides as a temporary structure. The above members are all formed of a steel structure.
도 3은 본 발명의 피.에스.씨-빔 교량의 상판 슬래브 가시설 구조의 시공도로서, (a)는 1단계에서 4단계까지를 나타내는 순서도, (b)는 5단계에서 7단계까지를 나타내는 순서도이다.3 is a construction diagram of the upper slab temporary structure of the P.S.C-beam bridge of the present invention, (a) is a flow chart showing the steps 1 to 4, (b) shows a five to seven steps Flowchart.
제 1 단계는 피.에스.씨-빔(50)을 교각(도면상 미도시됨) 상부에 거치하는 단계로, 상기의 피.에스.씨-빔에는 측면에 ㄷ형강(52)이 체결 볼트(56)로 체결된상태로 교각에 다수개가 안착된다.The first step is to mount the PS-beam 50 to the top of the piers (not shown in the figure), the c-beams 52 are fastened to the side of the PS beam. A plurality of the pier is seated in the fastened state (56).
제 2 단계는 피.에스.씨-빔(50)이 4본이 교각 상부에 안착된 상태에서 하부 받침틀(60)과 하부 슬래브 받침대(70) 및 캔틸레버 하부 받침틀(110)을 설치하는 단계로, 상기의 피.에스.씨-빔(50)이 다수개가 설치되면 그 사이에 하부 받침틀(60)을 ㄷ형강(52)의 사이에 삽입하여 하부 슬래브 받침대(120)가 설치되고, 피.에스.씨-빔(50)이 다수개가 설치된 양측에 각각 캔틸레버 하부 받침틀(110)을 누워진 형태로 안착시킨다.The second step is to install the lower support frame 60, the lower slab pedestal 70 and the cantilever lower support frame 110 in the state that the four S-beam 50 is seated on the upper piers, When the plurality of P.S.C-beams 50 is installed, the lower support frame 60 is inserted between the c-shaped steels 52 between the lower slab pedestals 120, and the P.S. The C-beam 50 seats the cantilever lower support frame 110 in a laid form, respectively, on both sides of which a plurality of seams are installed.
제 3 단계는 하부 슬래브 받침대(70)의 상부에 길이조정 받침대(80), 상부 슬래브 받침대(90) 및 슬래브 바닥판(100)이 순차적으로 설치되는 단계이다.The third step is a step in which the length adjustment pedestal 80, the upper slab pedestal 90 and the slab bottom plate 100 are sequentially installed on the lower slab pedestal 70.
이때 상기의 길이조정 받침대(80), 상부 슬래브 받침대(90) 및 슬래브 바닥판(100)은 일체 구조로 형성하여 설치할 수도 있고 각각의 부재로 형성하여 크레인 등과 같은 장비를 이용하여 교각 상부에서도 고정할 수도 있지만, 작업자들의 안전성을 고려하여 일체 구조로 형성하여 사용함이 바람직하다 할 것이다.At this time, the length adjustment pedestal 80, the upper slab pedestal 90 and the slab bottom plate 100 may be formed in an integrated structure or formed by each member to be fixed in the upper piers using equipment such as cranes, etc. Although it may be, in consideration of the safety of the workers it would be preferable to use the integral structure formed.
제 4 단계는 피.에스.씨-빔(50)이 다수개가 설치된 경우, 폭 방향의 양측에 캔틸레버 슬래브 받침대(120)를 거치한 후 소경 및 장경의 체결 볼트(56)(112)를 사용하여 피.에스.씨-빔에 체결하는 단계이다.The fourth step is to mount the cantilever slab pedestal 120 on both sides in the width direction when a plurality of P.S.C-beam 50 is installed, and then using fastening bolts 56 and 112 of small diameter and long diameter. It is the step of fastening to the PS-beam.
제 5 단계는 피.에스.씨-빔(50)의 폭 방향 양측에 설치된 캔틸레버 슬래브 받침대(120)의 상부에 각각 슬래브 측면 거푸집(140)을 설치하는 단계이다.The fifth step is to install the slab side formwork 140 on top of the cantilever slab pedestal 120 provided on both sides in the width direction of the P.S.C-beam 50.
이때 상기의 슬래브 측면 거푸집(140)은 캔틸레버 슬래브 받침대(120)의 상부에 용접 또는 체결 볼트에 의해 체결된다.At this time, the slab side formwork 140 is fastened by welding or fastening bolts on the upper portion of the cantilever slab pedestal 120.
제 6 단계는 슬래브 철근(136)을 조립하고 콘크리트를 타설하여 상판 슬래브를 시공하는 단계이다.The sixth step is to assemble the slab reinforcing bars 136 and to cast concrete to construct the upper slab.
제 7 단계는 상판 슬래브(150)를 지지하고 있는 하부 슬래브 받침대, 캔틸레버 하부받침틀, 길이조정 받침대, 상부 슬래브 받침대, 슬래브 바닥판, 캔틸레버 슬래브 받침대 및 슬래브 측면 거푸집을 역순으로 해체하는 단계이다.The seventh step is to dismantle the lower slab pedestal, cantilever lower support frame, length adjustment pedestal, upper slab pedestal, slab bottom plate, cantilever slab pedestal and slab side formwork supporting the upper slab 150 in the reverse order.
상술한 제 1 단계에서 부터 제 7 단계까지는, 시공을 원활하게 하기위한 순서이며, 필요에 따라 작업의 효율화를 고려하여 2단계를 동시에 작업할 수 있음은 자명하다 할 것이다.From the first to the seventh step described above is a sequence for smooth construction, it will be apparent that the two steps can be performed simultaneously in consideration of the efficiency of the work if necessary.
상술한 구성을 가지는 가시설 구조물은, 교량의 유지관리용이 아닌 신설 교량의 상판 슬래브를 시공하는 경우에 사용되는 가시설 구조물로, 작업중 가시설 구조물의 파손을 방지하여 시공 기간을 단축할 수 있도록 각각의 부재가 지지력이 뛰어난 강 구조물로 형성하였고, 작업자들의 작업성을 향상하기 위하여 피.에스.씨-빔(50)의 측면에 캔틸레버 슬래브 받침대(120)를 사용하고 있다.The provisional structure having the above-described configuration is a provisional structure used when constructing a slab of a new bridge, which is not for maintenance of the bridge, and each member is designed to shorten the construction period by preventing damage of the provisional structure during operation. It is formed of a steel structure with excellent support, and cantilever slab pedestal 120 is used on the side of the P.S.C-beam 50 to improve the workability of the workers.
상술한 본 고안의 구성과 작동 상태에 따른 효과를 설명한다.The effect of the configuration and operation of the present invention described above will be described.
본 고안의 피.에스.씨-빔 교량의 상판 슬래브 지지용 가시설 구조물은, 피.에스.씨-빔 제작시 측면에 앵커 볼트홀을 설치하고 ㄷ형강을 체결 볼트로 체결한 상태로 교각 상부에 다수본의 피.에스.씨-빔을 거치한 후 그 피.에스.씨-빔의 양 측면과 그 사이에 가시설 구조물을 설치하게 되는데, 이러한 가시설 구조물은 종래와 같이 반생을 전혀 사용하지 않는 관계로 가시설 구조물의 해체후 문제점으로 대두되던 슬래브 철근의 부식을 최대한 방지할 수 있고, 그로인한 상판 슬래브의 균열의 문제를 완전히 해소할 수 있음은 물론 가시설 구조물에 대한 시공 및 해체가 용이한 효과를 얻을 수 있다.The temporary slab supporting structure of the PS S-beam bridge of the present invention is installed at the top of the pier with the anchor bolt hole installed at the side of the PS S-beam and fastening the c-beams with the fastening bolts. After the majority of the CS beams are mounted, temporary structures are installed between the sides of the PS beams and between them. Such temporary structures do not use any half-life as in the prior art. It is possible to prevent the corrosion of slab reinforcement, which has emerged as a problem after dismantling of the temporary structure structure, to completely solve the problem of cracking of the slab of the top slab, and also to easily construct and dismantle the temporary structure. Can be.
또한, 가시설 구조물은 강 구조물을 이용하여 구성하는 관계로 종래와 같이 목재를 사용하지 않아 상판 슬래브의 시공후 발생되던 폐기물의 발생을 근본적으로 방지할 수 있고, 이로 인하여 종래에 비하여 공사 기간을 최대한 단축할 수 있는 효과를 얻을 수 있다.In addition, since the temporary structure is constructed by using steel structures, it is possible to fundamentally prevent the generation of waste generated after the construction of the top slab by not using wood as in the prior art, and thus shorten the construction period as compared to the prior art. The effect can be obtained.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2002-0059357A KR100469638B1 (en) | 2002-09-30 | 2002-09-30 | Support construction for slab of prestressed concrete beam of bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2002-0059357A KR100469638B1 (en) | 2002-09-30 | 2002-09-30 | Support construction for slab of prestressed concrete beam of bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20040028221A true KR20040028221A (en) | 2004-04-03 |
KR100469638B1 KR100469638B1 (en) | 2005-02-07 |
Family
ID=37330447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2002-0059357A KR100469638B1 (en) | 2002-09-30 | 2002-09-30 | Support construction for slab of prestressed concrete beam of bridge |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100469638B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101941942B1 (en) * | 2018-07-03 | 2019-04-11 | 김문홍 | Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same |
KR102524229B1 (en) * | 2022-10-11 | 2023-04-24 | 황민희 | Working platform for bridges with enhanced safety |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101571860B1 (en) * | 2008-12-26 | 2015-11-26 | 재단법인 포항산업과학연구원 | Construction method of a bridge using temporary installation bracing |
KR101660888B1 (en) * | 2016-02-16 | 2016-09-29 | (주)비티엠이엔씨 | Girder with pressing embed ahchorage apparatus and the girder construction method therewith |
KR101682923B1 (en) * | 2016-06-15 | 2016-12-06 | 주식회사 노빌테크 | Manufacturing method of channel type prestressed girder and the construction method using the girder manufactured thereby |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR910007423B1 (en) * | 1988-02-19 | 1991-09-26 | 삼환기업 주식회사 | Method for construction p.c - beam on the bridge |
KR950033370U (en) * | 1994-05-09 | 1995-12-16 | Prefabricated copper for construction of slab railing of bridge | |
KR20010044894A (en) * | 1999-11-01 | 2001-06-05 | 이하영 | Slab sheeting construction-method for bridge |
KR20000050107A (en) * | 2000-05-16 | 2000-08-05 | 이석원 | Matrix construction method for concrete casting of bridge slabs |
KR200201606Y1 (en) * | 2000-06-12 | 2000-11-01 | 박영재 | The psc bridge beam which can institute slab mold and safety net |
KR200235400Y1 (en) * | 2000-12-18 | 2001-09-26 | 동신기술개발 주식회사 | Sheeting iron mat of upper slav |
KR20030060263A (en) * | 2002-01-08 | 2003-07-16 | 박영재 | PCCbridge beam and method of constructing the same |
-
2002
- 2002-09-30 KR KR10-2002-0059357A patent/KR100469638B1/en not_active IP Right Cessation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101941942B1 (en) * | 2018-07-03 | 2019-04-11 | 김문홍 | Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same |
KR102524229B1 (en) * | 2022-10-11 | 2023-04-24 | 황민희 | Working platform for bridges with enhanced safety |
Also Published As
Publication number | Publication date |
---|---|
KR100469638B1 (en) | 2005-02-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100837608B1 (en) | J.K Bracket Method | |
KR100982974B1 (en) | Method for manufacturing multi-span continuous re-prestressed preflex composite bridge | |
JP2994222B2 (en) | Construction method of cast-in-place slab of precast concrete girder and its formwork | |
JP2011157720A (en) | Method for constructing railway reinforced concrete rigid-frame structure viaduct | |
CN113279582A (en) | Hanging construction method for overhanging and hanging type cast-in-place plate | |
KR101941942B1 (en) | Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same | |
KR100469638B1 (en) | Support construction for slab of prestressed concrete beam of bridge | |
KR101116345B1 (en) | Holder for preventing conduction of beam bridge and maintaining spaces and method for constructing bridge using thereof | |
KR100565384B1 (en) | Structure of continuous PSC beam with connection member and steel cross beam and bridge construction method using the same | |
JP2002194704A (en) | Method for constructing girder | |
KR20070001410A (en) | Mounting structure of steel cross-beam in multi-girder concrete bridge and its construction method | |
KR20010044894A (en) | Slab sheeting construction-method for bridge | |
JP3991071B2 (en) | H-shaped steel-framed frame construction method for base-lifting construction of wooden buildings | |
KR200392341Y1 (en) | Fixing Device for Aerial Scaffolding | |
CN209907886U (en) | Adjustable assembled stair construction platform | |
CN111455817A (en) | Cable-stayed bridge integral steel anchor beam and construction method thereof | |
KR200351989Y1 (en) | Concrete slab sheeting apparatus For P.C beam girder bridge | |
CN110847529A (en) | Simple to operate's pin-connected panel railing | |
KR20070082435A (en) | Temporary bridge consruction method using composite slab girder | |
KR100339440B1 (en) | Construction method using mold equipped with shape steel and plywood | |
CN219754221U (en) | Can have enough to meet need and use and enclose fender basis | |
KR100691847B1 (en) | Prefabricated beams reinforced with connecting steel boxes | |
CN217151146U (en) | Super 5 meters girder steel subassembly of encorbelmenting of concrete form support system that encorbelments | |
CN220202430U (en) | Steel-concrete composite beam structure of assembled cantilever arm support | |
KR200245272Y1 (en) | A cross beam sheeting structure of a prestressed concrete beam bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
N231 | Notification of change of applicant | ||
FPAY | Annual fee payment |
Payment date: 20120120 Year of fee payment: 8 |
|
LAPS | Lapse due to unpaid annual fee |