KR200376891Y1 - Coupling device between carrying channel and main t-bar for ceiling work - Google Patents

Coupling device between carrying channel and main t-bar for ceiling work Download PDF

Info

Publication number
KR200376891Y1
KR200376891Y1 KR20-2004-0033235U KR20040033235U KR200376891Y1 KR 200376891 Y1 KR200376891 Y1 KR 200376891Y1 KR 20040033235 U KR20040033235 U KR 20040033235U KR 200376891 Y1 KR200376891 Y1 KR 200376891Y1
Authority
KR
South Korea
Prior art keywords
main
rail
clip
carrying channel
hole
Prior art date
Application number
KR20-2004-0033235U
Other languages
Korean (ko)
Inventor
박상열
Original Assignee
주식회사 한국호머
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 한국호머 filed Critical 주식회사 한국호머
Priority to KR20-2004-0033235U priority Critical patent/KR200376891Y1/en
Application granted granted Critical
Publication of KR200376891Y1 publication Critical patent/KR200376891Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • E04B9/12Connections between non-parallel members of the supporting construction
    • E04B9/16Connections between non-parallel members of the supporting construction the members lying in different planes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

본 고안은 건축물의 천장 시공에 사용되는 캐링 채널과 메인 티바의 체결 장치에 관한 것으로, 판재 중간부에 상기 캐링 채널(20)이 완전히 삽입될 수 있게 하단이 개방되고 상부가 막힌 일자형의 삽입공(207)을 길게 형성하여 상기 삽입공(207) 양측 날개(201, 203)가 상기 메인 티바(10)의 레일 하단(15)까지 이르게 하고, 상기 양측 날개(201, 203)의 하부에는 레일(15)의 일측을 감싸서 지지할 수 있는 레일파지부(217, 219)를 형성하며, 상기 날개(201, 203) 중 하나에는 관통공(209)을 형성한 주 클립(200); 상기 관통공(209)을 형성한 날개(203)에 형상이 부합될 수 있는 판재의 상단을 절곡하여 상기 관통공(209)에 삽입될 수 있는 행거(305, 307)를 형성하고, 그 하부에는 레일(15)의 타측을 감싸서 지지할 수 있는 레일파지부(313)를 형성한 보조 클립(300); 및 평판형의 판재 중앙에 슬릿(107)을 형성하고, 후단에는 수직 형성된 가압부(109)를 구비하여, 상기 주 클립(200)과 보조 클립(300)이 상기 캐링 채널(20) 및 메인 티바의 레일(15)에 결합한 상태에서, 상기 관통공(209)이 형성된 날개(203) 및 보조 클립(200)의 몸체(301)를 겹쳐진 채로 슬릿(107)에 삽입하고 가압하여 서로 체결할 수 있는 결속핀(100);을 포함하여 구성함을 특징으로 한다.The present invention relates to the fastening device of the main channel and the carrying channel used in the ceiling construction of the building, the lower end is open so that the insertion channel (20) is completely inserted into the middle of the plate, the insertion hole of the straight shape ( 207 is formed long so that both wings 201 and 203 of the insertion hole 207 reach the lower end 15 of the rail of the main tee 10, and a rail 15 is provided below the both wings 201 and 203. A main clip 200 which forms rail holding parts 217 and 219 which can wrap and support one side of the blade), and one of the wings 201 and 203 has a through hole 209; The upper end of the plate material can be bent to the wing 203 formed with the through hole 209 to form a hanger (305, 307) that can be inserted into the through hole 209, the lower portion An auxiliary clip 300 having a rail gripping portion 313 capable of wrapping and supporting the other side of the rail 15; And a slit 107 formed at the center of the flat plate and having a pressing portion 109 vertically formed at a rear end thereof, so that the main clip 200 and the auxiliary clip 300 are connected to the carrying channel 20 and the main t-bar. In the state coupled to the rail 15 of the through-hole 209, the wing 203 and the body 301 of the auxiliary clip 200 is inserted into the slit 107 while overlapping and can be pressed to each other The binding pin 100; characterized by including a configuration.

Description

천장 시공용 캐링 채널과 메인 티바의 체결 장치{COUPLING DEVICE BETWEEN CARRYING CHANNEL AND MAIN T-BAR FOR CEILING WORK} CALLING DEVICE BETWEEN CARRYING CHANNEL AND MAIN T-BAR FOR CEILING WORK}

본 고안은 건축물의 천장 시공에 사용되는 캐링 채널과 메인 티바의 체결 수단에 관한 것으로, 더 상세하게는 메인 티바의 고정 위치 설정 및 티바의 격자 정렬이 용이하고, 체결 시공을 간편하게 수행할 있는 구조의 천장 시공용 캐링 채널과 메인 티바의 체결 수단에 관한 것이다.The present invention relates to a fastening means of a caring channel and a main tee used for ceiling construction of a building, and more particularly, a fixed position of the main tee and alignment of the grid of the tee are easy, and the structure of the fastening construction can be easily performed. It relates to a fastening means of the carrying channel for ceiling installation and the main tee.

일반적으로 아파트, 빌딩, 오피스텔 등 건축물의 천장을 시공하기 위해서는, 슬라브 하측에 캐링 채널(Carrying Channel)을 행거 볼트(Hanger Bolt) 및 행거 클립(Hanger Clip)에 의하여 설치하고, 상기 캐링 채널의 하측에는 메인 티바(Main T-bar)를 캐링 채널에 체결하여 설치하며, 상기 메인 티바 간에는 수직 방향으로 가로 지르면서 메인 티바와 함게 격자를 형성하는 크로스 티바(Cross T-bar)를 설치한다. 이렇게 형성된 격자 내에는 천장이 되는 실링보드(ceiling board)를 배치한다. 실링보드는 통상 정사각형 또는 직사각형이기 때문에 메인 티바 및 크로스 티바에 의하여 형성되는 격자의 각 귀퉁이(corner)가 직각이 잘 유지되어야 한다. 메인 티바와 크로스 티바가 정확한 직각을 유지한 격자 형태로 시공되지 않으면, 실링 보드 시공이 어렵고, 캐링 채널에도 불균형한 하중이 전달되어 시간이 경과하면서 메인 티바나 캐링 채널이 뒤틀릴 수 있기 때문이다.In general, in order to construct a ceiling of an apartment, a building, an officetel, and the like, a carrying channel is installed at the lower side of the slab by a hanger bolt and a hanger clip, and at the bottom of the carrying channel. The main T bar is installed by fastening to a carrying channel, and a cross T bar is formed between the main t bars and forms a lattice with the main t bar while crossing in the vertical direction. In the grid formed as described above, a ceiling board (ceiling board) is disposed. Since the sealing board is usually square or rectangular, each corner of the lattice formed by the main t-bar and the cross t-bar should be well maintained at right angles. If the main t-bar and cross t-bar are not constructed in the form of a grid that maintains the right angle, it is difficult to install the sealing board, and an unbalanced load is transmitted to the carrying channel, and the main t-bar or the carrying channel may be distorted over time.

종래, 메인 티바는 상단에는 길이 방향을 따라 클립홀을 미리 형성하고, 천장 시공시 이 클립홀과 이 클립홀에 결합되는 클립에 의하여 캐링 채널에 고정하였다. 즉, 클립의 상단을 볼트에 의해 캐링 채널의 상단에 체결하고, 양방향으로 엇갈리게 절곡된 클립의 단부를 메인 티바에 형성된 이웃하는 2개의 클립홀에 삽입하여 메인 티바를 캐링 채널에 고정한 것이다. 따라서, 정확한 티바 격자를 형성하기 위해서는 인접하는 메인 티바의 클립홀을 서로 정확히 일치시켜야 했다. 그러나, 클립홀이 메인 티바 상단에 길이 방향을 따라 미리 일정한 간격으로 뚫려 있어, 인접하는 메인 티바간에 이들 클립홀을 나란히 맞추는 것은 매우 까다로운 작업이었다.Conventionally, the main tee is previously formed with a clip hole along the longitudinal direction at the top, and is fixed to the carrying channel by the clip coupled to the clip hole and the clip hole during the ceiling construction. That is, the upper end of the clip is fastened to the upper end of the carrying channel by bolts, and the end of the clip bent in both directions is inserted into two neighboring clip holes formed in the main t-bar to fix the main t-bar to the carrying channel. Therefore, in order to form an accurate T-bar lattice, the clip holes of adjacent main T-bars had to exactly match each other. However, since the clip holes were previously drilled at regular intervals along the longitudinal direction on the top of the main tee, it was very difficult to align these clip holes side by side between adjacent main tee bars.

이를 해결하고자 본 출원인은 대한민국 등록실용신안 제20-346434호 고안에서, 메인 티바의 몸체 상단에 양측에 걸림턱을 형성하고, 메인 티바를 캐링 채널에 체결하는 클립을 체결하되, 상기 클립을 상기 캐링 채널의 상하부를 지지하여 고정볼트로 체결되는 단면이 ㄷ자형의 가이드부와 상기 가이드부의 측부에 일체로 형성되어 상기 메인 티바의 걸림턱의 일측을 지지하는 지지부로 이루어진 클립 본체와, 상기 클립 본체의 지지부와 대응되게 클립 본체에 볼트 및 너트로 결합되어 상기 메인 티바의 걸림턱의 타측을 지지하는 지지판으로 구성하는 것을 특징으로 하는 메인 티바와 캐링 채널간의 체결 장치를 개시한 바 있다.In order to solve this problem, the present applicant, in the Republic of Korea Utility Model Registration No. 20-346434 devised, to form a locking jaw on both sides of the main body of the main tee, fastening the clip to fasten the main tee to the carrying channel, the clip carrying the The upper and lower ends of the channel are fastened by fixing bolts to form a U-shaped guide part and a guide part integrally formed on the side of the guide part to support one side of the locking jaw of the main tee, and the clip body of the The fastening device between the main t-bar and the carrying channel is characterized in that the support body is coupled to the clip body with a bolt and a nut to support the other side of the locking jaw of the main t-bar corresponding to the support.

상기 제20-346434호 고안은 메인 티바에 클립홀을 형성하지 않고, 그 대신 걸림턱을 형성하여, 클립의 고정 위치를 쉽게 변경할 수 있게 한 점에서 매우 유용한 고안이었으나, 구조가 복잡하여 제조가 용이하지 않을 뿐만 아니라, 캐링 채널에 체결 장치를 먼저 고정볼트로 체결한 후 다시 메인 티바에 체결하여야 하므로, 시공이 번거롭고 시공 시간이 많이 소요되는 문제점이 있었다. 본 고안은 상기 제20-346434호 고안에서 이러한 문제점들을 개선한 고안인 것이다. The design of No. 20-346434 was a very useful design in that it did not form a clip hole in the main tee, but instead formed a locking jaw, so that the fixing position of the clip could be easily changed, but the structure was complicated and easy to manufacture. Not only, but the fastening device to the carrying channel to fasten the fixed bolt first and then to the main tie bar, there is a problem that the construction is cumbersome and takes a lot of construction time. The present invention is a design that improves these problems in the design of the 20-346434.

상술한 문제점을 해결하고자 안출된 본 고안은 캐링 채널에 고정되는 메인 티바의 고정 위치를 자유롭게 선택하여 정확한 격자를 형성할 수 있는 구조의 천장 시공용 캐링 채널과 메인 티바의 체결 장치를 제공하는데 그 목적이 있다. The present invention devised to solve the above-mentioned problems is to provide a fastening device for the ceiling installation and the main tiba structure of the ceiling construction that can form a precise grid by freely selecting the fixed position of the main tiba fixed to the carrying channel. There is this.

본 고안의 다른 목적은 구조가 단순하면서도 캐링 채널과 메인 티바를 용이하게 체결할 수 있는 구조의 천장 시공용 캐링 채널과 메인 티바의 체결 장치를 제공하는데 있다. It is another object of the present invention to provide a fastening device for a ceiling channel carrying channel and a main tee, which is simple in structure and can easily fasten the carrying channel and the main tee.

상술한 목적을 달성하고자 하는 본 고안은The present invention to achieve the above object

체결용 레일을 상단에 길이 방향을 따라 형성한 메인 티바를 슬라브에 고정된 캐링 채널에 직교 방향으로 연결하는 체결 장치에 있어서,In the fastening device for connecting the main t-bar formed in the longitudinal direction on the upper rail in the orthogonal direction to the carrying channel fixed to the slab,

상기 체결 장치를The fastening device

판재 중간부에 상기 캐링 채널이 완전히 삽입될 수 있게 하단이 개방되고 상부가 막힌 일자형의 삽입공을 길게 형성하여 상기 삽입공 양측 날개가 상기 메인 티바의 레일 하단까지 이르게 하고, 상기 양측 날개의 하부에는 레일의 일측을 감싸서 지지할 수 있는 레일파지부를 형성하며, 상기 날개 중 하나에는 관통공을 형성한 주 클립;The lower end is opened and the upper part is formed to have a straight insertion hole having a closed upper portion so that the carrying channel can be completely inserted in the middle of the sheet material so that both wings of the insertion hole reach the bottom of the rail of the main tee, A rail gripping portion formed to surround and support one side of the rail, and one of the wings includes a main clip having a through hole;

상기 관통공을 형성한 날개에 형상이 부합되는 판재의 상단을 절곡하여 상기 관통공에 삽입될 수 있는 행거를 형성하고, 그 하부에는 레일의 타측을 감싸서 지지할 수 있는 레일파지부를 형성한 보조 클립; 및Bending the upper end of the sheet material that conforms to the shape of the blade formed through the through hole to form a hanger that can be inserted into the through hole, the lower portion of the auxiliary rail formed to support the wrap around the other side of the rail Clip; And

평판형의 판재 중앙에 슬릿을 형성하고, 후단에는 수직 형성된 가압부를 구비하여, 상기 주 클립과 보조 클립이 상기 캐링 채널 및 메인 티바의 레일에 결합한 상태에서, 상기 관통공이 형성된 날개 및 보조 클립의 몸체를 겹쳐진 채로 슬릿에 삽입하고 가압하여 서로 체결할 수 있는 결속핀;를 포함하여 구성함을 특징으로 한다.Slit is formed in the center of the plate-like plate, and the rear end is provided with a vertically formed pressing portion, the body of the wing and auxiliary clip formed with the through hole in the state in which the main clip and the auxiliary clip is coupled to the rail of the carrying channel and the main tee It characterized in that it comprises a; binding pins that can be fastened to each other by inserting and pressing in the slit while overlapping.

이하, 본 고안의 바람직한 실시 예에 따른 천장 시공용 캐링 채널과 메인 티바의 체결 장치를 첨부한 도면을 참조하면서 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the fastening device of the ceiling carrying channel and the main tee according to an embodiment of the present invention will be described in detail.

도 1은 본 고안에 따른 천장 시공용 캐링 채널과 메인 티바의 체결 장치를 분리하여 도시한 분해 사시도를, 도 2a 내지 도 2e는 도 1에 도시된 체결 장치를 이용하여 캐링 채널과 메인 티바를 연결하는 과정을 보여 주는 시공도를, 도 3은 캐링 채널에 메인 티바와 크로스 티바를 모두 연결하여 실링 보드를 배치할 수 있는 격자를 완성한 상태를 도시한 부분 사시도를 각각 나타낸다.1 is an exploded perspective view showing the ceiling of the carrying channel and the main tie bar separated by the installation according to the present invention, Figures 2a to 2e is connected to the carrying channel and the main tea bar using the fastening device shown in FIG. 3 illustrates a partial perspective view showing a state in which a lattice in which a sealing board can be arranged by connecting both a main tee and a cross tee to a carrying channel is completed, respectively.

우선 도 3을 참조하면, 천장을 시공하기 위해서 슬라브의 하측으로 행거볼트를 이용하여 캐링 채널(20)을 설치하고, 캐링 채널(20) 하부에는 캐링 채널(20)의 진행 방향과 직교하여 메인 티바(10)를 다수 설치하며, 메인 티바(10)에 대하여 수직방향으로 다수의 크로스 티바(30)를 직교 방향으로 설치하여 실링 보드(6)를 배치할 수 있는 격자를 완성한다. 본 고안에 따른 체결장치는 캐링 채널(20)과 메인 티바(10)을 결합 및 고정하여 주는 장치이다.First, referring to FIG. 3, in order to construct a ceiling, a carrying channel 20 is installed at the lower side of the slab by using a hanger bolt, and a lower portion of the carrying channel 20 is perpendicular to the traveling direction of the carrying channel 20. A large number of (10) is provided, and a plurality of cross t-bars (30) are installed in the orthogonal direction with respect to the main t-bar (10) to complete the lattice for arranging the sealing board (6). Fastening device according to the present invention is a device for coupling and fixing the carrying channel 20 and the main t-bar 10.

도 1을 참조하면, 본 고안에 따른 체결 장치는 금속 판재 등을 프레스 가공하여 성형한 주 클립(200) 및 보조 클립(300)과, 이들 주 클립(200) 및 보조 클립(300)을 체결하는 결속핀(100)을 구비한다. Referring to FIG. 1, a fastening device according to the present invention includes a main clip 200 and an auxiliary clip 300 formed by pressing a metal sheet or the like, and fastening the main clip 200 and the auxiliary clip 300. A binding pin 100 is provided.

도 1에 도시된 바와 같이, 본 고안은 상기 주 클립(200)의 중간부에 캐링 채널(20)이 완전히 삽입될 수 있게 상단이 개방되고 상부가 막힌 일자형의 삽입공(207)을 형성하여, 작업자가 주 클립(200)을 캐링 채널(20)의 상단으로 부터 하방으로 쒸워서 삽입하는 것 만으로도 캐링 채널(20)을 고정할 수 있게 한데 그 특징이 있다. 또한, 상기 주 클립(200)의 삽입공(207) 양측에 형성되는 날개(201, 203)의 하부에는 상기 삽입공(207)의 관통 방향과 직교하는 방향으로 메인 티바의 레일(15) 일측을 감쌀 수 있게 외측으로 볼록한 레일파지부(217, 219)를 형성하여, 날개(201, 203)의 상부로는 캐링 채널(20)을 내부에 고정 및 지지하면서, 동시에 날개 하부의 레일파지부(217, 219)로는 메인 티바(10)를 상기 캐링 채널(20)에 직교하는 방향으로 연결하게 한데 본 고안의 특징이 있다. 이를 위해 주 클립(200)의 양측 날개(201, 203)의 높이는 상기 캐링 채널(20)의 높이 및 레일(15)의 높이를 합한 것과 거의 일치하게 한다. 상기 레일파지부(217, 219)는 상기 날개(201, 203) 하부의 적당한 지점을 외측으로 절곡하여 절곡부(213, 215)를 형성하고, 다시 날개(201, 203)의 하단을 내측으로 절곡하여 걸림턱(221, 223)을 형성함으로써 성형한다. 주 클립(200)의 상단 모서리에도 절곡부(205)를 성형할 수 있다. As shown in FIG. 1, the present invention forms a straight insertion hole 207 having an upper end and a closed upper part to allow the carrying channel 20 to be fully inserted into a middle portion of the main clip 200. The operator is able to fix the carrying channel 20 only by inserting the main clip 200 from the top of the carrying channel 20 downward. In addition, a lower portion of the wings 201 and 203 formed at both sides of the insertion hole 207 of the main clip 200 may have one side of the rail 15 of the main tee in a direction orthogonal to the penetration direction of the insertion hole 207. The rail holding portions 217 and 219 which are convex outwardly to be wrapped are formed so that the upper portions of the wings 201 and 203 fix and support the carrying channel 20 therein, while at the same time the rail holding portions 217 below the wings. , 219 is to connect the main t-bar 10 in the direction orthogonal to the carrying channel 20 is characterized by the present invention. To this end, the heights of both wings 201 and 203 of the main clip 200 are approximately equal to the sum of the height of the carrying channel 20 and the height of the rail 15. The rail gripping portions 217 and 219 bend the appropriate points below the wings 201 and 203 to the outside to form the bent portions 213 and 215, and again the lower ends of the wings 201 and 203 to the inside. By forming the locking step (221, 223). The bent portion 205 may be formed at the upper edge of the main clip 200.

또한, 상기 주 클립(200)의 날개 중 하나에는 상기 보조 클립(300)을 걸어서 결합할 수 있는 관통공(209)을 더 형성한다.In addition, one of the wings of the main clip 200 is further formed with a through hole 209 that can be coupled to the auxiliary clip 300 by walking.

다시 도 1을 참조하면, 상기 주 클립(200)에 결합하여 캐링 채널(20)과 메인 티바(10)를 체결하는 보조 클립(300)은 금속 판재등을 프레스 가공하여 그 형상이 상기 관통공(209)이 형성된 주 클립(200)의 날개(203)에 부합되게 성형한다. 따라서, 상기 보조 클립 몸체(301)에도 상기 날개의 레일파지부(217)에 대응되는 부분에 레일파지부(313)를 형성한다. 상기 보조 클립(300)의 레일파지부(313)도 몸체(301) 하부에 절곡부(311)를 형성하고 몸체 하단에 걸림턱(315)을 형성하여 성형한다. Referring back to FIG. 1, the auxiliary clip 300 coupled to the main clip 200 to fasten the carrying channel 20 and the main t-bar 10 is formed by pressing a metal plate and the like into the through hole ( 209 is molded to conform to the wing 203 of the main clip 200 is formed. Accordingly, the rail gripping portion 313 is formed at a portion of the auxiliary clip body 301 corresponding to the rail gripping portion 217 of the wing. The rail gripping portion 313 of the auxiliary clip 300 is also formed by forming a bent portion 311 at the bottom of the body 301 and a locking jaw 315 at the bottom of the body.

주 클립(200)과 보조 클립(300) 간의 체결 작업을 용이하게 하기 위하여 상기 보조 클립(300)의 상단을 절곡하여 상기 주 클립(200)의 날개(203)에 형성된 관통공(209)에 삽입하여 걸 수 있는 행거(305, 307)를 형성한다. 상기 행거는 그 머리(305)의 폭을 그 목(307)의 폭 보다 넓게 형성하고, 상기 관통공(209)의 세로 길이를 상기 행거 머리(305)의 폭 보다 길게 하며, 상기 관통공(209)의 가로 길이를 상기 행거 머리(305)의 폭 보다 작게 하여, 보조 클립(300)을 옆으로 누여서 행거 머리(305)를 상기 관통공(209)에 삽입한 후 세우면 행거 머리(305)가 상기 관통공(209)에 걸려서 이탈하지 않도록 한다. In order to facilitate the fastening operation between the main clip 200 and the auxiliary clip 300, the upper end of the auxiliary clip 300 is bent and inserted into the through hole 209 formed in the wing 203 of the main clip 200. Hangers 305 and 307 which can be hung are formed. The hanger forms the width of the head 305 wider than the width of the neck 307, the longitudinal length of the through hole 209 is longer than the width of the hanger head 305, the through hole 209 The width of the hanger head 305 is smaller than the width of the hanger head 305, the auxiliary clip 300 is pushed to the side to insert the hanger head 305 into the through hole 209, and the hanger head 305 is raised. Do not get caught in the through hole 209 to be separated.

도 2a 내지 도 2e를 참조하여, 상술한 구조를 갖는 본 고안에 따른 체결 장치를 이용하여 캐링 채널(20)과 메인 티바(10)를 체결하는 방법을 살펴 보면 다음과 같다.Referring to Figures 2a to 2e, using the fastening device according to the present invention having the above-described structure to look at the method of fastening the carrying channel 20 and the main t-bar 10 as follows.

도 2a를 참조하면, 본 고안을 이용하여 체결되는 메인 티바(10)는 몸체(11)의 상단에 길이 방향을 따라 메인 티바 몸체(13) 보다 훨씬 두껍운 레일(15)을 형성하고, 레일(15) 하단에는 체결이 용이도록 각 진 레일턱(17, 19)을 형성한다. 또한, 메인 티바(10)의 하단에는 티바 몸체(13)에 대하여 직교하여 수평 방향으로 확장한 실링 보드 지지부(11)를 형성한다. 캐링 채널(20)은 웨브(23)가 수직이 되도록 배치하고, 상플랜지(25)를 슬라브에 고정하며, 하플랜지(21)의 하면에 메인 티바(10)를 직교 방향으로 결합하게 된다. Referring to Figure 2a, the main tie bar 10 is fastened using the present invention to form a rail (15) much thicker than the main tie bar body 13 in the longitudinal direction at the top of the body 11, the rail ( 15) The lower rail jaw (17, 19) is formed to facilitate the fastening. In addition, the lower end of the main t-bar 10 is formed with a sealing board support 11 extending in the horizontal direction perpendicular to the t-bar body 13. The carrying channel 20 is disposed so that the web 23 is vertical, and fixes the upper flange 25 to the slab, and the main t-bar 10 is coupled to the lower surface of the lower flange 21 in the orthogonal direction.

시공을 위하여 우선, 도 2b에 도시된 바와 같이, 주 클립(200)의 삽입공(207)에 캐링 채널(20)을 삽입하고, 주 클립(200)의 레일파지부(217, 219) 하단에 형성된 걸림턱(221, 223)이 메인 티바(10)의 각진 레일턱(17)에 걸리게 한다. 주 클립(200)과 캐링 채널(20)의 결합은 주 클립(200) 중간부에 형성된 일자형의 삽입공(207)에 의하여 이루어지고 별도의 체결이 필요 없으므로 시공 작업이 매우 빠르고 간편해 진다. For construction, first, as shown in FIG. 2B, the carrying channel 20 is inserted into the insertion hole 207 of the main clip 200, and the lower end of the rail holding parts 217 and 219 of the main clip 200. The formed locking jaws 221 and 223 are caught by the angled rail jaw 17 of the main t-bar 10. Combination of the main clip 200 and the carrying channel 20 is made by a straight insertion hole 207 formed in the middle of the main clip 200, and does not require a separate fastening, so the construction work is very fast and simple.

다음, 도 2c에 도시된 바와 같이, 보조 클립(300)을 눕혀 보조 크립(300)의 행거 머리(305)를 주 클립(200)의 날개(203)에 형성된 관통공(209)에 삽입한 후 돌려 세운다. Next, as shown in FIG. 2C, after the auxiliary clip 300 is laid down, the hanger head 305 of the auxiliary creep 300 is inserted into the through hole 209 formed in the wing 203 of the main clip 200. Turn it up.

다음, 도 2d에 도시된 바와 같이 상기 주 클립(200)과 보조 클립(300)을 상기 캐링 채널(20) 및 메인 티바의 레일(15)에 결합한 상태에서, 메인 티바(10) 길이 방향을 따라, 결속핀(100)의 슬릿(107) 내부에 관통공(209)이 형성된 날개(203)와 보조 클립(200)의 몸체가 겹쳐진 채로 삽입될 수 있게 밀어 넣는다. Next, as shown in FIG. 2D, the main clip 200 and the auxiliary clip 300 are coupled to the carrying channel 20 and the rail 15 of the main tee, along the longitudinal direction of the main tee 10. In the slit 107 of the binding pin 100, the wing 203 having the through hole 209 formed therein and the body of the auxiliary clip 200 are pushed so that they can be inserted while overlapping.

도 2e를 참조하면, 상술한 결속핀(100)의 압착만으로 주 클립(200)에 의하여 캐링 채널(20) 및 메인 티바(10)의 일측을 고정하고, 보조 클립(300)에 의하여 메인 티바(10)의 타측을 고정하여 견고하게 캐링 채널(20)과 메인 티바(10)를 체결할 수 있게 된다.Referring to FIG. 2E, only one side of the carrying channel 20 and the main t-bar 10 is fixed by the main clip 200 only by pressing the binding pin 100, and the main t-bar by the auxiliary clip 300. By fixing the other side of 10) it is possible to firmly fasten the carrying channel 20 and the main t-bar 10.

도 3을 참조하면, 이렇게 시공된 다수의 메인 티바(10)를 크로스 티바(30)에 의하여 직각 방향으로 연결하여 실링 보드를 배치할 수 있는 천장 시공용 격자가 완성되는 것이다.Referring to FIG. 3, the grids for ceiling construction can be completed by connecting the plurality of main T bars 10 constructed in this way to the right angle direction by the cross T bars 30.

그리고, 캐링 채널(20)에 체결된 메인 티바(10)들 간의 간격이 상이하여 정확한 격자 형성이 이루어 지지 않은 경우에는 보조 클립(300)을 주 클립(200)의 날개(203)에서 결속핀(100)을 해제한 후 체결 장치의 위치를 메인 티바(10)의 레일(15)에서 좌측 또는 우측 방향으로 적당히 이동시켜 다시 삽입함으로써 정확한 격자를 형성할 수 있게 된다.In addition, when the gap between the main t-bars 10 fastened to the carrying channel 20 is not accurate and the grid is not formed accurately, the auxiliary clip 300 may be connected to the binding pins at the wings 203 of the main clip 200. After releasing 100, the position of the fastening device is properly moved in the left or right direction from the rail 15 of the main tee 10 and reinserted to form an accurate grating.

본 고안에 의하면, 구조가 간편하여 제작 비용이 적게 소요되면서도, 짧은 시간에 손쉽게 메인 티바와 캐링 채널을 연결할 수 있는 체결 장치를 제공할 수 있을 뿐만 아니라, 메인 티바가 캐링 채널에서 설치되는 위치를 간편하게 변경하여 재설치할 수 있어 캐링 채널과 메인 티바들 간의 직진도 및 격자의 정확도를 용이하게 조절할 수 있고, 시공후 유지 보수도 간편해지는 효과가 있다. According to the present invention, the structure is simple and the manufacturing cost is low, and it is not only possible to provide a fastening device that can easily connect the main t-bar and the carrying channel in a short time, but also the position where the main t-bar is installed in the carrying channel. It can be changed and re-installed to easily adjust the straightness and the accuracy of the grating between the carrying channel and the main t-bars, and has the effect of easy maintenance after construction.

도 1은 본 고안에 따른 천장 시공용 캐링 채널과 메인 티바의 체결 장치를 분리하여 도시한 분해 사시도이다.Figure 1 is an exploded perspective view showing the separation of the fastening device of the main channel and the carrying channel for ceiling construction according to the present invention.

도 2a 내지 도 2e는 도 1에 도시된 체결 장치를 이용하여 캐링 채널과 메인 티바를 연결하는 과정을 보여 주는 시공도이다.2A to 2E are construction views showing a process of connecting the carrying channel and the main t-bar using the fastening device shown in FIG.

도 3은 캐링 채널에 메인 티바와 크로스 티바를 모두 연결하여 실링 보드를 배치할 수 있는 격자를 완성한 상태를 도시한 부분 사시도이다.FIG. 3 is a partial perspective view illustrating a state in which a lattice for arranging a sealing board may be completed by connecting both a main tee and a cross tee to a carrying channel.

* 도면의 주요 부분에 대한 부호의 설명 *            Explanation of symbols on the main parts of the drawings

10 : 메인 티바(main T-bar) 11 : 보드 지지부10: main T-bar 11: board support

13 : 티바 몸체 15 : 레일(rail)13: Tiba body 15: Rail

17, 19 : 레일턱 20 : 캐링 채널(carrying channel)17, 19: rail jaw 20: carrying channel

21, 25 : 플랜지(flange) 23 : 웨브(web)21, 25: flange 23: web

30 : 크로스 티바(cross T-bar) 100 : 결속핀30: cross T-bar 100: binding pin

103, 105 : 핑거 107 : 슬릿103, 105: finger 107: slit

109 : 가압부 200 : 주 클립109: pressurization 200: main clip

201, 203 : 날개 205, 213, 215 : 절곡부201, 203: wing 205, 213, 215: bend

207 : 삽입공 209 : 관통공207: insertion hole 209: through hole

211 : 볼트공 217, 219 : 레일파지부211: bolt hole 217, 219: rail holding part

221, 223 : 걸림턱 300 : 보조 클립 221, 223: jaw 300: auxiliary clip

301 : 몸체 303 : 볼트공301: body 303: bolt hole

305 : 행거 머리 307 : 행거 목305: hanger head 307: hanger neck

309, 311 : 절곡부 313 : 레일파지부309, 311: bending portion 313: rail holding portion

315 : 걸림턱315: jamming jaw

Claims (1)

체결용 레일(15)을 상단에 길이 방향을 따라 형성한 메인 티바(10)를 슬라브에 고정한 캐링 채널(20)에 직교 방향으로 연결하는 체결 장치에 있어서,In the fastening device for connecting the main t-bar 10 formed in the longitudinal direction at the upper end of the fastening rail 15 to the carrying channel 20 fixed to the slab in an orthogonal direction, 상기 체결 장치는 The fastening device 판재 중간부에 상기 캐링 채널(20)이 완전히 삽입될 수 있게 하단이 개방되고 상부가 막힌 일자형의 삽입공(207)을 길게 형성하여 상기 삽입공(207) 양측 날개(201, 203)가 상기 메인 티바(10)의 레일 하단(15)까지 이르게 하고, 상기 양측 날개(201, 203)의 하부에는 레일(15)의 일측을 감싸서 지지할 수 있는 레일파지부(217, 219)를 형성하며, 상기 날개(201, 203) 중 하나에는 관통공(209)을 형성한 주 클립(200);The insertion hole 207 of the lower end is opened and the upper part is blocked so that the carrying channel 20 can be completely inserted in the middle of the plate, and the blades 201 and 203 of both sides of the insertion hole 207 are connected to the main part. To reach the lower end of the rail 15 of the T-bar 10, and the rail holding parts 217 and 219 are formed at the lower parts of the two wings 201 and 203 to surround and support one side of the rail 15. One of the wings (201, 203) has a main clip (200) forming a through hole (209); 상기 관통공(209)을 형성한 날개(203)에 형상이 부합될 수 있는 판재의 상단을 절곡하여 상기 관통공(209)에 삽입될 수 있는 행거(305, 307)를 형성하고, 그 하부에는 레일(15)의 타측을 감싸서 지지할 수 있는 레일파지부(313)를 형성한 보조 클립(300); 및The upper end of the plate material can be bent to the wing 203 formed with the through hole 209 to form a hanger (305, 307) that can be inserted into the through hole 209, the lower portion An auxiliary clip 300 having a rail gripping portion 313 capable of wrapping and supporting the other side of the rail 15; And 평판형의 판재 중앙에 슬릿(107)을 형성하고, 후단에는 수직 형성된 가압부(109)를 구비하여, 상기 주 클립(200)과 보조 클립(300)이 상기 캐링 채널(20) 및 메인 티바의 레일(15)에 결합한 상태에서, 상기 관통공(209)이 형성된 날개(203) 및 보조 클립(200)의 몸체(301)를 겹쳐진 채로 슬릿(107)에 삽입하고 가압하여 서로 체결할 수 있는 결속핀(100);을 포함하여 구성함을 특징으로 하는 천장 시공용 캐링 채널과 메인 티바의 체결 장치.A slit 107 is formed at the center of the flat plate, and a pressing portion 109 is formed at a rear end thereof so that the main clip 200 and the auxiliary clip 300 are connected to the carrying channel 20 and the main tee. In a state in which it is coupled to the rail 15, the piercing can be inserted into the slit 107 while pressing the through-hole 209 and the body 301 of the auxiliary clip 200 overlapping and fastening to each other. Pin (100); fastening device of the ceiling channel carrying channel and the main tee, characterized in that it comprises a configuration.
KR20-2004-0033235U 2004-11-24 2004-11-24 Coupling device between carrying channel and main t-bar for ceiling work KR200376891Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0033235U KR200376891Y1 (en) 2004-11-24 2004-11-24 Coupling device between carrying channel and main t-bar for ceiling work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0033235U KR200376891Y1 (en) 2004-11-24 2004-11-24 Coupling device between carrying channel and main t-bar for ceiling work

Publications (1)

Publication Number Publication Date
KR200376891Y1 true KR200376891Y1 (en) 2005-03-11

Family

ID=43678645

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0033235U KR200376891Y1 (en) 2004-11-24 2004-11-24 Coupling device between carrying channel and main t-bar for ceiling work

Country Status (1)

Country Link
KR (1) KR200376891Y1 (en)

Similar Documents

Publication Publication Date Title
KR100939322B1 (en) Carring Chanel Hanger for Ceiling Closing
US8955272B1 (en) Accessible stabilizer bar
KR101123408B1 (en) Apparatus for constructing a building ceiling board
KR100763871B1 (en) An operation apparatus of boarded ceiling of a building
KR102039732B1 (en) Apparatus for supporting form of a concrete beam
KR200376891Y1 (en) Coupling device between carrying channel and main t-bar for ceiling work
KR20110029143A (en) Expandable ceiling grid
KR100888209B1 (en) Sapporting bar fixing device for aluminum form
KR200376890Y1 (en) Coupling device between carrying channel and main t-bar for ceiling work
KR101516119B1 (en) Apparatus for constructing a building ceiling board
KR100761569B1 (en) Faxing apparatus of truss beam
EP1880063B1 (en) A wall anchor and a cavity wall comprising such an anchor
RU2554364C2 (en) Supporting device of anchor for concrete elements lifting
KR20090011851U (en) Main t-bar with wide punctures for clips
KR100741312B1 (en) A contract apparatus of frame for fixing ceiling board
KR20110081002A (en) Apparatus for constructing a building ceiling board
JP3865423B2 (en) Assembled temporary passage
KR102052642B1 (en) Wind-load resistance type finishing apparatus
KR200450017Y1 (en) Apparatus for fixing mash-tray
JP4119943B1 (en) Hardware for holding the base formwork spacing and anchor bolts
JP7128560B1 (en) Wallboard installation tool and wallboard installation structure
KR100906553B1 (en) Clamp assembly for scaffolding
KR200405350Y1 (en) device for connecting concrete form
JP3145303U (en) Ceiling board auxiliary support
JPH048754Y2 (en)

Legal Events

Date Code Title Description
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20080218

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee