KR200361080Y1 - Caisson Supporting Structure for Deep Water - Google Patents

Caisson Supporting Structure for Deep Water Download PDF

Info

Publication number
KR200361080Y1
KR200361080Y1 KR20-2004-0014174U KR20040014174U KR200361080Y1 KR 200361080 Y1 KR200361080 Y1 KR 200361080Y1 KR 20040014174 U KR20040014174 U KR 20040014174U KR 200361080 Y1 KR200361080 Y1 KR 200361080Y1
Authority
KR
South Korea
Prior art keywords
caisson
reinforcement
pile
wall
panel
Prior art date
Application number
KR20-2004-0014174U
Other languages
Korean (ko)
Inventor
배석동
Original Assignee
(주) 선암기술연구소
배석동
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 선암기술연구소, 배석동 filed Critical (주) 선암기술연구소
Priority to KR20-2004-0014174U priority Critical patent/KR200361080Y1/en
Application granted granted Critical
Publication of KR200361080Y1 publication Critical patent/KR200361080Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

본 고안은 심해에 설치되어 열악한 환경에서 견딜 수 있도록 케이슨의 지지력을 확보하며, 케이슨 내부로 침투되는 침출수를 완전 차단하기 위한 대심도용 케이슨 지지구조에 관한 것이다.The present invention secures the support of the caisson to be installed in the deep sea to withstand the harsh environment, and relates to a deep caisson support structure for completely blocking the leachate penetrated into the caisson.

이를 위하여 본 고안은 복수개의 패널이 결합되며 내측패널과 외측패널 내부에 이중패널로 구성되고 복수개의 균형탱크가 형성되며 최 하측에 위치되는 패널의 하단에 수밀부가 구비된 공지의 케이슨에 있어서, 상기 케이슨의 내부에 천공되는 다수의 구멍에 매설되는 전단말뚝과, 상기 케이슨 내부의 하부에 콘크리트 타설되어 상기 전단말뚝과 일체로 결합되도록 차수벽으로 이루어져, 상기 전단말뚝과 상기 차수벽에 의해 케이슨 하부를 지지층에 고정되도록 하는 것을 특징으로 한다.To this end, the present invention is a combination of a plurality of panels, the inner panel and the outer panel is composed of a double panel, a plurality of balance tanks are formed in the bottom of the panel located in the bottom of the known caisson provided with watertight, Shear piles are embedded in a plurality of holes perforated inside the caisson, and the lower portion of the caisson is cast concrete wall to be integrally coupled with the shear pile, the shear pile and the lower wall of the caisson by the support wall It is characterized in that to be fixed.

또한, 본 고안은 상기 전단말뚝 사이에 암반층 절리선보다 더 깊게 다수개 천공된 보정구와, 상기 보정구에 그라우팅하여 암반층 절리선을 메꿔 케이슨 내측으로 침투되는 침출수를 차단하도록 하는 그라우팅재를 더 포함하여 이루어지는 것을 특징으로 한다.In addition, the present invention further comprises a correction hole drilled a plurality of deeper than the rock layer joint line between the shear piles, and a grouting material to grind the rock layer joint line by grouting the correction hole to block the leachate that penetrates into the caisson inside It is characterized by.

또, 본 고안은 복수개의 패널이 결합되며 내부에 균형탱크가 구비되고 최 하측에 위치되는 패널의 하단에 수밀부가 구비된 공지의 케이슨에 있어서, 상기 케이슨 하부에 콘크리트 타설되어 상기 케이슨을 지지층에 고정되도록 하는 차수벽과, 상기 케이슨의 내측에 매설되는 다수의 보강말뚝과, 상기 케이슨 내측의 하부에 콘크리트 타설되어 상기 보강말뚝과 일체로 결합되며 상기 케이슨의 내측패널과 접하는 보강벽과, 상기 보강벽에 매설되어 상기 보강말뚝과 상기 케이슨의 내측패널 사이에 위치하여 상기 보강말뚝으로부터 상기 케이슨의 내측패널을 지지하도록 보강하는 보강빔으로 이루어져, 상기 보강말뚝과 상기 보강벽 및 상기 보강빔에 의해 상기 케이슨 하부를 지지층에 고정되도록 하는 것을 특징으로 한다.In addition, the present invention is a well-known caisson having a plurality of panels are coupled to the balance tank inside and the watertight portion is provided at the bottom of the panel located on the bottom, the concrete is placed in the lower caisson to fix the caisson to the support layer And a plurality of reinforcement walls, a plurality of reinforcement piles embedded in the caisson, concrete reinforcement in the lower portion of the caisson to be integrally connected with the reinforcement piles, and to contact the inner panel of the caisson, and to the reinforcement wall. It is buried between the reinforcement pile and the inner panel of the caisson is made of a reinforcement beam for supporting the inner panel of the caisson from the reinforcement pile, the reinforcement pile and the reinforcement wall and the lower reinforcement beam by the reinforcement beam To be fixed to the support layer.

이에 따라 본 고안은 대심도에서의 케이슨을 지지층에 견고하게 고정되도록 보강하여 안정성을 확보할 수 있고, 수압에 의한 케이슨의 변형이 적으며, 연결부가 적어 누수가 발생되지 않아 차수효과가 크다. 또한, 토사를 축토하는 종래의 공법에서와 같이 과대한 차수벽체를 확보할 필요가 없고 공기가 단축되며 비용을 절감할 수 있는 효과가 있다. 또, 암반층 절리(규열)에서 침투되는 침출수를 차단함으로써 쾌적한 수중 작업공간을 확보할 수 있는 효과가 있다.Accordingly, the present invention can secure the stability by reinforcing the caisson at the depth to be firmly fixed to the support layer, the deformation of the caisson due to the hydraulic pressure is small, the connection part is small, no leakage occurs, the order effect is large. In addition, there is no need to secure an excessive order wall, as in the conventional construction method of soil excavation, there is an effect that the air can be shortened and the cost can be reduced. In addition, there is an effect that can secure a comfortable underwater work space by blocking the leachate infiltrate in rock bed joint (gyueul).

Description

대심도용 케이슨 지지구조{Caisson Supporting Structure for Deep Water}Caisson Supporting Structure for Deep Water

본 고안은 대심도에 사용되는 케이슨의 지지구조에 관한 것으로, 특히, 대심도에서의 열악한 환경에서도 지지층에 케이슨을 견고하게 고정될 수 있도록 하는 구조에 관한 것이다.The present invention relates to a support structure of a caisson used in a large depth, and more particularly, to a structure that can be firmly fixed to the support layer in a poor environment at a large depth.

주지하는 바와 같이, 수중구조물의 확장이나 개,보수를 위해서는 물막이 공법이 이용된다.As is well known, a water barrier method is used to expand, renovate, or repair an underwater structure.

종래에 사용된 물막이 공법으로 강널말뚝을 이용한 셀(Sell)공법을 도 1에 단면도로 도 2에 평면도로 도시하였다.The cell method using a steel sheet pile as a conventional water barrier method is shown in a cross-sectional view in FIG. 1 and a plan view in FIG. 2.

도시된 바와 같이, 강널말뚝(101)을 박고 볼트와 같은 결합수단을 이용하여 이음부를 이은 다음 강널말뚝(101)의 내부에 토사(102)를 축토하여 물막이를 하게 된다. 이 강널막뚝(101)을 이용한 물막이 공법은 내부에 토사(102)를 메꾸고 외부에 토사(102)를 축토함으로써 차수벽(103)을 형성시키게 되므로, 점용면적이 넓어 안정성 측면은 양호하게 된다. 그러나, 물막이 대상규모에 비해 설치규모가 크며, 방대한 채움재의 확보가 어렵고, 토사 유용이 많아 환경피해가 우려되며, 설치기간이 장기간 소요되며 연결부(104)가 많아 비용에 비해 차수효과가 적은 단점이 있었다. 또한, 수압에 견디기 위해 말뚝(101)을 박아 지지함으로 지지층(105)을 손상시키며 차수를 위해 지지층(105)과 말뚝(101) 주변의 그라우팅 비용이 많이 소요되고 말뚝간 이음부(104) 틈새에 누수가 발생되는 문제점이 있다.As shown in the figure, the steel sheet pile 101 is connected to the joint using a coupling means such as bolts, and then the soil is piled up to the inside of the steel sheet pile 101 to make a water barrier. In the water barrier method using the steel sheet film 101, the soil wall 102 is filled inside and the soil layer 102 is piled up on the outside, so that the order wall 103 is formed. However, the installation size is larger than the target size of the water barrier, it is difficult to secure a large amount of filling material, there is a concern about environmental damage due to the availability of earth and sand, the installation period is long, and the connection part 104 has a lot of low order effect compared to the cost there was. In addition, damage to the support layer 105 by driving the pile 101 in order to withstand the hydraulic pressure, the grouting cost around the support layer 105 and the pile 101 for the order is high, and the gap between the joint 104 between the piles There is a problem that leaks occur.

특히, 수심이 깊을 경우 수압에 의한 말뚝의 변형이 많아 다수의 버팀대 설치가 필요하고 안전성이 떨어지는 단점이 있었다. 또한, 암반층 절리(규열)에서의 침출수 차단이 어려워, 쾌적한 수중 작업공간의 확보가 어려운 문제점이 있다.In particular, when the depth is deep, there is a lot of deformation of the pile by the water pressure required a number of brace installation and there was a disadvantage that the safety is low. In addition, it is difficult to block the leachate in the rock layer joint (gyuyeol), there is a problem that it is difficult to secure a comfortable underwater workspace.

본 고안은 상기한 바와 같은 종래 기술의 문제점을 해결하기 위하여 안출된 것으로, 본 고안의 목적은 대심도에서의 케이슨을 견고하게 고정되도록 보강하여 안정성을 확보하고 암반층 절리(규열)에서 침투되는 침출수를 차단할 수 있도록 하는 대심도용 케이슨 지지구조를 제공하는 것이다.The present invention has been devised to solve the problems of the prior art as described above, the object of the present invention is to reinforce the caisson firmly fixed at a large depth to ensure stability and to infiltrate the leachate that penetrates in the rock layer joint (gyueul) It is to provide a deep caisson support structure that can be blocked.

도 1은 종래에 사용된 물막이 공법의 일례로 강널말뚝을 이용한 물막이 공법을 나타낸 단면도.1 is a cross-sectional view showing a water barrier method using a steel sheet pile as an example of a conventional water barrier method.

도 2는 도 1의 평면도.2 is a plan view of FIG.

도 3은 본 고안의 실시예에 의한 대심도용 케이슨 지지구조를 나타낸 단면도.Figure 3 is a cross-sectional view showing a caisson support structure for large depths according to an embodiment of the present invention.

도 4는 도 3의 차수부의 상세도.4 is a detailed view of the order portion of FIG. 3;

도 5는 도 3의 평면도.5 is a plan view of FIG.

도 6은 끝날 압착케이슨을 이용한 대심도용 케이슨 지지구조를 나타낸 단면도.Figure 6 is a cross-sectional view showing a caisson support structure for the depth using the crimping caisson end.

도 7은 도 6의 차수부의 상세도.FIG. 7 is a detailed view of the order portion of FIG. 6; FIG.

도 8은 본 고안의 바람직한 실시예에 따른 대심도용 케이슨 지지구조를 나타낸 단면도.Figure 8 is a cross-sectional view showing a caisson support structure for a depth in accordance with a preferred embodiment of the present invention.

도 9는 도 8의 평면도.9 is a plan view of FIG. 8.

도 10은 본 고안의 다른 실시예에 의한 대심도용 케이슨 지지구조를 나타낸 단면도.10 is a cross-sectional view showing a caisson support structure for large depths according to another embodiment of the present invention.

도 11은 도 10의 차수부의 상세도.FIG. 11 is a detailed view of the order portion of FIG. 10; FIG.

도 12는 도 10의 평면도.12 is a plan view of FIG. 10.

도 13a 내지 도 13k는 본 고안에 따른 대심도용 케이슨 설치공정을 나타낸 도면.Figure 13a to Figure 13k is a view showing a deep caisson installation process according to the present invention.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

1: 케이슨 2: 지지층1: caisson 2: support layer

3: 전단말뚝 3a: 철근3: shear pile 3a: rebar

3b: 콘크리트 4: 차수벽3b: Concrete 4: Order Wall

5: 보정구 6: 그라우팅재5: Corrector 6: Grouting material

7: 패널 7a: 내측패널7: Panel 7a: inner panel

7b: 외측패널 7c: 이중패널7b: outer panel 7c: double panel

8: 수밀부 9: 패킹재8: watertight part 9: packing material

10: 암반층 절리선 11: 끝날10: Rock Formation Joint 11: End

12: 균형탱크 13: 중공부12: balance tank 13: hollow part

14: 보강벽 15: 집수정14: reinforcement wall 15: water collecting well

16: 배수유도로 17: 배수펌프16: drainage path 17: drainage pump

18: 수위측정센서 19: 배수관18: Water level sensor 19: Drain pipe

20: 배수설비 21: 보강말뚝20: drainage system 21: reinforcement pile

22: 보강벽 23: 보강빔22: reinforcement wall 23: reinforcement beam

30: 작업구 31: 가이드 파일30: Work Tool 31: Guide File

이러한 목적을 달성하기 위하여 본 고안은, 복수개의 패널이 결합되며 내측패널과 외측패널 내부에 이중패널로 구성되고 복수개의 균형탱크가 형성되며 최 하측에 위치되는 패널의 하단에 수밀부가 구비된 공지의 케이슨에 있어서, 상기 케이슨의 내부에 천공되는 다수의 구멍에 매설되는 전단말뚝과, 상기 케이슨 내부의 하부에 콘크리트 타설되어 상기 전단말뚝과 일체로 결합되도록 차수벽으로 이루어져, 상기 전단말뚝과 상기 차수벽에 의해 케이슨 하부를 지지층에 고정되도록 하는 것을 특징으로 한다.In order to achieve the above object, the present invention is a combination of a plurality of panels, consisting of a double panel inside the inner panel and the outer panel, a plurality of balance tanks are formed and the water-tight portion is provided at the bottom of the panel located at the bottom In the caisson, the shear pile is embedded in a plurality of holes perforated in the caisson, and the lower portion of the caisson is made of concrete to be integrally combined with the shear pile, the shear pile and the order wall by It is characterized in that the lower caisson is fixed to the support layer.

또한, 본 고안은 상기 전단말뚝 사이에 암반층 절리선보다 더 깊게 다수개 천공된 보정구와, 상기 보정구에 그라우팅하여 암반층 절리선을 메꿔 케이슨 내측으로 침투되는 침출수를 차단하도록 하는 그라우팅재를 더 포함하여 이루어지는 것을 특징으로 한다.In addition, the present invention further comprises a correction hole drilled a plurality of deeper than the rock layer joint line between the shear piles, and a grouting material to grind the rock layer joint line by grouting the correction hole to block the leachate that penetrates into the caisson inside It is characterized by.

또, 본 고안은 복수개의 패널이 결합되며 내부에 균형탱크가 구비되고 최 하측에 위치되는 패널의 하단에 수밀부가 구비된 공지의 케이슨에 있어서, 상기 케이슨 하부에 콘크리트 타설되어 상기 케이슨을 지지층에 고정되도록 하는 차수벽으로 구성되며, 추가보강이 필요할시 케이슨 내부 배수작업후 상기 케이슨의 내측에 매설되는 다수의 보강말뚝과, 상기 케이슨 내측의 하부에 콘크리트 타설되어 상기 보강말뚝과 일체로 결합되며 상기 케이슨의 내측패널과 접하는 보강벽과, 상기 보강벽에 매설되어 상기 보강말뚝과 상기 케이슨의 내측패널 사이에 위치하여 상기 보강말뚝으로부터 상기 케이슨의 내측패널을 지지하도록 보강하는 보강빔으로 이루어져, 상기 보강말뚝과 상기 보강벽 및 상기 보강빔에 의해 상기 케이슨 하부를 지지층에 고정되도록 하는 것을 특징으로 한다.In addition, the present invention is a well-known caisson having a plurality of panels are coupled to the balance tank inside and the watertight portion is provided at the bottom of the panel located on the bottom, the concrete is placed in the lower caisson to fix the caisson to the support layer Consisting wall to be made, and if additional reinforcement is required, after the internal caisson drainage work, a plurality of reinforcement piles embedded in the inside of the caisson, concrete is laid in the lower portion of the inside of the caisson is integrally combined with the reinforcement piles of the caisson A reinforcing wall contacting the inner panel and a reinforcing beam embedded in the reinforcing wall and positioned between the reinforcing pile and the inner panel of the caisson to reinforce the inner panel of the caisson from the reinforcing pile. The lower part of the caisson is fixed to the support layer by the reinforcing wall and the reinforcing beam It is characterized in that the lock.

이에 따라 본 고안은 대심도에 사용되는 케이슨을 지지층에 견고하게 고정할 수 있고, 변형 발생을 방지할 수 있으며, 암반층 절리를 통해 케이슨 내부로 침투되는 침출수를 차단할 수 있게 된다.Accordingly, the present invention can firmly fix the caisson used in the large depth to the support layer, to prevent the occurrence of deformation, it is possible to block the leachate penetrated into the caisson through the rock bed joint.

상기한 바와 같은 구성을 가지는 본 고안의 실시예에 의한 대심도용 케이슨 지지구조의 실시예로 첨부된 도면을 참고하여 상세하게 설명한다.With reference to the accompanying drawings as an embodiment of a large depth caisson support structure according to an embodiment of the present invention having a configuration as described above will be described in detail.

도 3은 본 고안의 실시예에 의한 대심도용 케이슨 지지구조를 나타낸 단면도이고, 도 4는 도 3의 차수부의 상세도이며, 도 5는 도 3의 평면도이다.3 is a cross-sectional view showing a caisson support structure for a large depth in accordance with an embodiment of the present invention, Figure 4 is a detailed view of the order of Figure 3, Figure 5 is a plan view of FIG.

도시된 바와 같이, 본 고안의 실시예에 의한 대심도용 케이슨 지지구조는 케이슨(1) 하부의 지지층(2)에 매설되는 전단말뚝(3)과, 케이슨(1) 내부의 하부에 콘크리트 타설되는 차수벽(4)과, 케이슨(1) 내측으로 침투되는 침출수를 차단하도록 하는 보정구(5)를 메꾸는 그라우팅재(6)로 구성된다.As shown, the large depth caisson support structure according to the embodiment of the present invention is a shear pile 3 embedded in the support layer (2) below the caisson 1, and the order of the concrete pour in the lower portion of the caisson (1) (4) and the grouting material 6 which fills in the correction | amendment 5 which blocks the leachate which penetrates into the caisson 1 inside.

상기 케이슨(1)은 복수개의 패널(7)이 결합되며 내측패널(7a)과 외측패널(7b) 내부에 이중패널(7c)로 구성되고, 복수개의 균형탱크(12)가 구비되며, 최 하측에 위치되는 패널(7)의 하단에 수밀부(8)가 구비되어 있다. 상기 케이슨(1)은 작업하고자하는 작업구(30) 둘레에 설치된다.The caisson 1 has a plurality of panels 7 are coupled to the inner panel (7a) and the outer panel (7b) is composed of a double panel (7c), a plurality of balance tank 12 is provided, the bottom The watertight part 8 is provided in the lower end of the panel 7 located in. The caisson 1 is installed around the work tool 30 to be worked.

상기 수밀부(8)는 패킹재(9)가 내측패널(7a)과 외측패널(7b)의 하부에 각각 설치되어 있으며, 이 패킹재(9)는 케이슨(1)의 자중에 의해 압착되어 케이슨(1) 내부를 실링하게 된다.In the watertight portion 8, a packing material 9 is provided at the lower portions of the inner panel 7a and the outer panel 7b, respectively, and the packing material 9 is compressed by the weight of the caisson 1 and is caisson. (1) The interior is sealed.

상기 전단말뚝(3)은 상기 케이슨(1)의 내부에 천공되어 매설되며 상기 케이슨(1)을 지지층(2)에 견고하게 고정시키는 역할을 한다. 상기 전단말뚝(3)은 콘크리트(3a)로 되며 내부에는 철근(3b)이 설치되어 압축 및 인장력에 견딜 수 있도록 되어 있다.The shear pile 3 is perforated and embedded in the caisson 1 and serves to firmly fix the caisson 1 to the support layer 2. The shear pile 3 is made of concrete (3a) and is provided with a reinforcing bar (3b) to withstand compression and tensile forces.

상기 차수벽(4)은 상기 케이슨(1) 내부의 하부에 콘크리트 타설되어 상기 전단말뚝(3)과 일체로 결합된다. 상기 차수벽(4)은 상기 수밀부(8)의 패킹재(9)와 같이 케이슨(1) 내부를 실링하는 역할을 수행할 뿐만 아니라, 상기 전단말뚝(3)과 함께 상기 케이슨(1)을 지지층(2)에 견고하게 고정시키는 역할을 하게 된다.The order wall 4 is placed in the lower portion of the inside of the caisson 1 is integrally coupled to the shear pile (3). The order wall 4 not only serves to seal the inside of the caisson 1 like the packing material 9 of the watertight part 8, but also supports the caisson 1 together with the shear pile 3. It serves to fix it firmly in (2).

상기 보정구(5)는 상기 전단말뚝(3)들 사이에 다수개를 천공하여 암반층 절리선(침운선, 암반층에 물이 통과하는 선)(10)보다 더 깊게 천공된다.The corrector 5 is drilled more deeply than the rock bed joint line (water line, the line through which water passes through the rock bed) 10 by drilling a plurality of the shear piles (3).

상기 그라우팅재(6)는 상기 보정구(5)에 그라우팅(Grouting)하여 암반층 절리선을 메꿔 암반층 절리선(10)을 통해 침투되는 침출수를 차단하게 된다. 상기 그라우팅재(6)를 상기 보정구(5)에 그라우팅하게 되면 상기 보정구(5)에 근접한 암반층 절리선(10)의 일부를 메꿈으로써 상기 케이슨(1) 내부로 침투되는 침출수를 차단할 수 있게 된다. 따라서, 본 고안은 상기 그라우팅재(6)와 상기 차수벽(4) 및 수밀부(8)의 패킹재(9)에 의해 상기 케이슨(1) 내측으로 침투되는 모든 침출수를 차단함으로써 케이슨(1) 내측에서의 쾌적한 작업공간을 확보할 수 있게 된다.The grouting material (6) is grouted (Grouting) to the corrector (5) to fill the rock layer joint line to block the leachate that penetrates through the rock layer joint line (10). When the grouting material 6 is grouted to the corrector 5, a portion of the rock layer joint line 10 proximate to the corrector 5 may be filled to block the leachate that penetrates into the caisson 1. do. Therefore, the present invention blocks all leachate water penetrated into the caisson 1 by the grouting material 6 and the packing material 9 of the order wall 4 and the watertight part 8 inside the caisson 1. It is possible to secure a comfortable working space in.

심해물막이의 특성상 자연재해에 대비해야 하는바 케이슨(1) 지지력 증가를 위해 케이슨(1) 설치가 완료되면 균형탱크(12)나 중공부(13) 내부공간에 모래 등을 충진하여 파랑이나 파압에 대한 지지력을 증대시키며, 공사를 완료한 후에는 케이슨(1) 철거전에 충진모래를 제거한다.Due to the characteristics of the deep sea water barrier, it is necessary to prepare for natural disasters. Cayenne (1) After the installation of the caisson (1) is completed to increase the bearing capacity, sand or the like is filled in the balance tank (12) or the hollow part (13). After the construction is completed, the filling sand is removed before the demolition of the caisson (1).

도 6은 끝날 압착케이슨을 이용한 대심도용 케이슨 지지구조를 나타낸 단면도이고, 도 7은 도 6의 차수부의 상세도이다.Figure 6 is a cross-sectional view showing a caisson support structure for a large depth using a crimping caisson edge, Figure 7 is a detailed view of the order portion of FIG.

도시된 바와 같이, 케이슨(1)의 일례로 케이슨(1)의 최하부가 끝날(11)로 되어 있으며, 케이슨(1)의 내부 중공부(13)에 매설되는 전단말뚝(3)과 상기 전단말뚝(3)과 일체로 콘크리트 타설하는 차수벽(4)에 의해 상기 케이슨(1)을 지지층(2)에 견고하게 고정된 상태를 나타낸다.As shown, as an example of the caisson 1, the bottom end of the caisson 1 is the end 11, the shear pile 3 and the shear pile embedded in the inner hollow 13 of the caisson 1 It shows the state where the said caisson 1 was firmly fixed to the support layer 2 by the order wall 4 which concrete-pours integrally with (3).

도 8은 본 고안의 바람직한 실시예에 따른 대심도용 케이슨 지지구조를 나타낸 단면도이고, 도 9는 도 8의 평면도이다.8 is a cross-sectional view showing a caisson support structure for a large depth in accordance with a preferred embodiment of the present invention, Figure 9 is a plan view of FIG.

도시된 바와 같이, 전술한 본 고안의 실시예에 따른 대심도용 케이슨 지지구조에서 케이슨(1) 내측에 접하여 설치되는 보강벽(14)과, 집수정(15), 배수유도로(16), 배수펌프(17), 수위측정센서(18), 배수관(19) 및 로 구성된 배수설비(20)가 더 포함되어 있다.As shown, in the caisson support structure for a large depth according to the embodiment of the present invention described above, the reinforcing wall 14 is installed in contact with the inside of the caisson (1), the sump well 15, the drainage flow path 16, drainage A pump 17, a water level sensor 18, a drain pipe 19, and a drainage system 20 are further included.

상기 보강벽(14)은 상기 케이슨(1)의 내측에 접하도록 설치되어 케이슨(1) 내측에서 외부 수중 압력을 견딜수 있도록 보강하게 된다.The reinforcing wall 14 is installed to be in contact with the inside of the caisson 1 is to be reinforced to withstand the external underwater pressure inside the caisson (1).

상기 배수설비(20)는 상기 케이슨(1) 내부로 침투되는 우수 등을 상기 집수정(15)으로 유도하는 배수유도로(16)와 케이슨(1) 내부로 침투되는 우수 등을 집수하는 집수정(15)과 상기 집수정(15) 하부에 설치되는 배수펌프(17)와 상기 집수정(15) 내에 설치되어 집수정(15)에 집수된 물이 일정량 모이면 상기 배수펌프(17)를 가동시키는 수위측정센서(18)와 상기 배수펌프(17)와 연결되어 집수된 물을 배수하는 배수관(19)으로 이루어져 있다.The drainage facility 20 is a collection well for collecting the rainwater penetrating into the caisson (1), such as the drainage flow path 16 to guide the water collecting well (15) and the rainwater penetrating into the caisson (1). 15 and the drain pump 17 installed below the sump 15 and the sump 15 installed in the sump 15 to operate the drain pump 17 when a certain amount of water collected in the sump 15 is collected. The water level measuring sensor 18 and the drain pump 17 is connected to the drain pipe 19 for draining the collected water.

도 10은 본 고안의 다른 실시예에 의한 대심도용 케이슨 지지구조를 나타낸 단면도이고, 도 11은 도 10의 차수부의 상세도이며, 도 12는 도 10의 평면도이다.10 is a cross-sectional view showing a caisson support structure for a large depth according to another embodiment of the present invention, FIG. 11 is a detailed view of the order portion of FIG. 10, and FIG. 12 is a plan view of FIG. 10.

도시된 바와 같이, 본 고안의 다른 실시예에 의한 대심도용 케이슨 지지구조는 케이슨(1) 내부의 하부에 콘크리트 타설되는 차수벽(4)과, 케이슨(1) 내측 하부의 지지층(2)에 매설되는 보강말뚝(21)과, 케이슨(1) 내측의 하부에 콘크리트 타설되어 상기 보강말뚝(21)과 일체로 결합되어 상기 케이슨(1)을 지지하는 보강벽(22)과, 상기 보강벽(22)에 매설되어 상기 케이슨(1)의 내측패널(7a)을 지지하도록 보강하는 보강빔(23)으로 구성된다.As shown, the caisson support structure for a large depth according to another embodiment of the present invention is embedded in the order wall (4) to be cast in the lower portion of the inside of the caisson 1, and the support layer (2) of the lower inner portion of the caisson (1) Reinforcement pile 21 and the concrete in the lower portion of the inside of the caisson (1), the reinforcement wall 22 is integrally coupled with the reinforcement pile 21 to support the caisson (1), and the reinforcement wall (22) It is embedded in the reinforcement beam 23 is reinforced to support the inner panel (7a) of the caisson (1).

상기 케이슨(1)은 본 고안의 실시예에서와 같이 복수개의 패널(7)이 결합되며 최 하측에 위치되는 패널(7)의 하단에 수밀부(8)가 구비되어 있다. 또한, 상기 케이슨(1)의 내부에는 균형탱크(12)가 형성되어 상기 케이슨(1) 하상 설치시에 균형탱크(12)에 물이나 모래를 채워 자중증가시켜 케이슨(1)의 하상을 용이하게 한다.The caisson (1) is provided with a watertight portion (8) at the bottom of the panel (7) which is coupled to the plurality of panels (7) located at the bottom as in the embodiment of the present invention. In addition, a balance tank 12 is formed inside the caisson 1 so that the bottom of the caisson 1 is easily increased by filling water or sand in the balance tank 12 when installing the lower bed of the caisson 1. do.

상기 수밀부(8)는 패킹재(9)가 내측패널(7a)과 외측패널(7b)의 하부에 각각 설치되어 있으며, 이 패킹재(9)는 케이슨(1)의 자중에 의해 압착되어 케이슨(1) 내부를 실링하게 된다.In the watertight portion 8, a packing material 9 is provided at the lower portions of the inner panel 7a and the outer panel 7b, respectively, and the packing material 9 is compressed by the weight of the caisson 1 and is caisson. (1) The interior is sealed.

상기 차수벽(4)은 지지층(2)에 콘크리트 타설되어 상기 케이슨(1)을 지지층(2)에 고정시키는 역할을 한다. 또한 상기 차수벽(4)은 상기 수밀부(8)의 패킹재(9)와 같이 상기 케이슨(1) 내부를 실링하는 역할을 수행하게 된다.The order wall 4 is concrete cast on the support layer 2 and serves to fix the caisson 1 to the support layer 2. In addition, the order wall 4 serves to seal the inside of the caisson 1 like the packing material 9 of the watertight part 8.

상기 보강말뚝(21)은 상기 케이슨(1)의 내측에 다수개 매설되어 상기 보강벽(22)과 상기 보강빔(23)과 함께 상기 케이슨(1)을 지지층(2)에 견고하게 고정시키는 역할을 한다.The reinforcement pile 21 is embedded in the plurality of the caisson 1 is a role of fixing the caisson 1 to the support layer 2 together with the reinforcing wall 22 and the reinforcing beam 23. Do it.

상기 보강벽(22)은 상기 케이슨(1) 내측의 하부에 콘크리트 타설되어 상기 보강말뚝(21)과 일체로 결합되며 상기 케이슨(1)의 내측패널(7a)과 접하여 상기 케이슨(1)을 지지고정하게 된다.The reinforcing wall 22 is placed in the lower portion of the inside of the caisson 1 is integrally coupled with the reinforcement pile 21 and in contact with the inner panel 7a of the caisson 1 to support the caisson 1 It will be fixed.

상기 보강빔(23)은 상기 보강벽(22)에 매설되어 상기 보강말뚝(21)과 상기 케이슨(1)의 내측패널(7a) 사이에 위치하여 상기 보강말뚝(21)으로부터 상기 케이슨(1)의 내측패널(7a)을 지지하도록 상기 보강벽(22)을 보강하는 역할을 한다. 따라서, 상기 보강말뚝(21)과 상기 보강벽(22) 및 상기 보강빔(23)에 의해 상기 케이슨(1) 하부 내측을 지지층(2)에 견고하게 고정되도록 한다.The reinforcement beam 23 is buried in the reinforcement wall 22 and is located between the reinforcement pile 21 and the inner panel 7a of the caisson 1 and the caisson 1 from the reinforcement pile 21. It serves to reinforce the reinforcing wall 22 to support the inner panel 7a. Therefore, the inner bottom of the caisson 1 is firmly fixed to the support layer 2 by the reinforcing pile 21, the reinforcing wall 22, and the reinforcing beam 23.

또한, 본 고안의 다른 실시예에 의한 대심도용 케이슨 지지구조도 본 고안의 실시예에서와 같이, 상기 보강말뚝(21)들 사이에 보정구(5)를 다수개 천공하고 상기 보정구(5)에 그라우팅하여 암반층 절리선(침운선, 암반층에 물이 통과하는 선)(10)을 메꿔 암반층 절리선(10)을 통해 침투되는 침출수를 차단할 수도 있다(도 4,5 참조).In addition, a large depth caisson support structure according to another embodiment of the present invention, as in the embodiment of the present invention, perforated a plurality of correction spheres (5) between the reinforcing piles 21 and the correction sphere (5) Grouting to fill the rock layer joint line (sunken, the line through which water passes through the rock layer) 10 may block the leachate that penetrates through the rock layer joint line 10 (see FIGS. 4 and 5).

도 13a 내지 도 13k는 본 고안에 따른 대심도용 케이슨 설치공정을 나타낸 도면이다.13A to 13K are diagrams illustrating a caisson installation process for a large depth according to the present invention.

상기와 같은 구성으로 된 본 고안에 따른 대심도용 케이슨 지지구조는 다음과 같은 과정으로 설치된다.The caisson support structure for the depth according to the present invention having the configuration as described above is installed in the following process.

먼저, 수중현황을 측량하고 수중에 축적된 토사를 제거하고 지지층(2) 암반을 평탄하게 한다(도 13a). 이어서, 케이슨(1)을 제작하고 케이슨(1) 하부에 패킹재(9)를 부착하여 수상에서 진수하고 현장으로 이동시킨다(도 13b). 이동시킨 케이슨(1)을 침설위치 주변에 가이드 파일(31)을 박고 케이슨 균형탱크(12) 내부에 물을 주입하여 이 가이드 파일(31)에 의해 가이드하여 케이슨(1)을 침설한다(도 13c). 이어서, 2열의 균형탱크 압착케이슨의 경우에는 케이슨(1) 내부 중공부(13)를 통하여 케이슨(1) 하부에 전단말뚝(3)을 시공한다(도 13d). 이때, 케이슨(1)의 내부가 균형탱크로만 된 경우에는 파압에 의한 케이슨(1)의 전도방지용 보강말뚝(21)을 케이슨(1) 내측에 시공하고(도 13g), 보강말뚝(21)과 결합되는 보강벽(22)을 케이슨(1) 내측에 시공한다(도 13h). 이어서, 케이슨 내부에 시공된 전단말뚝(3) 사이에 보정구(5)를 시공한다(도 13e). 이어서, 케이슨 내측을 차수하고 시공한 보정구(5)에 그라우팅재(6)를 채운다. 이어서, 2열의 균형탱크 압착케이슨의 경우에는 케이슨(1) 내부의 하부 지지층(3)에 상기 차수벽(4)을 시공한다(도13f). 이러한 상태는 케이슨(1) 설치가 완료가 된 상태가 된다. 이어서, 케이슨(1) 내측에 집수정(15), 배수유도로(16), 배수펌프(17) 등의 배수설비(20)를 설치한다(도 13i). 이어서, 케이슨(1) 내측에서 지지층(2)을 굴착하고 및 구조물을 시공한다(도 13j). 마지막으로 균형탱크(12) 내부의 물을 배수하여 케이슨(1)을 부상하고 이동시킨다(도 13k).First, the current state of the water is measured, the soil accumulated in the water is removed, and the rock of the support layer 2 is flattened (FIG. 13A). Subsequently, the caisson 1 is manufactured and the packing material 9 is attached to the lower part of the caisson 1 to be launched from the water phase and moved to the site (FIG. 13B). The guide caisson 1 is placed around the immersion position of the moved caisson 1, and water is injected into the caisson balance tank 12 to guide the caisson 1 by guiding the guide ridge 31 (Fig. 13C). ). Subsequently, in the case of the two-row balanced tank crimp caisson, the shear pile 3 is constructed in the lower part of the caisson 1 through the hollow portion 13 inside the caisson 1 (FIG. 13D). At this time, when the inside of the caisson 1 is only a balance tank, construct a fall prevention reinforcement pile 21 of the caisson 1 by the wave pressure inside the caisson 1 (Fig. 13g), and the reinforcement pile 21 and A reinforcing wall 22 to be joined is constructed inside the caisson 1 (FIG. 13H). Subsequently, the correction tool 5 is constructed between the shear piles 3 constructed inside the caisson (FIG. 13E). Next, the grouting material 6 is filled in the correction | amendment tool 5 which ordered and constructed the inside of a caisson. Subsequently, in the case of two rows of balanced tank press caissons, the order wall 4 is constructed on the lower support layer 3 inside the caisson 1 (Fig. 13F). This state becomes a state in which the caisson 1 installation is completed. Subsequently, drainage facilities 20 such as a sump 15, a drainage inlet 16 and a drainage pump 17 are provided inside the caisson 1 (FIG. 13I). Subsequently, the support layer 2 is excavated inside the caisson 1 and the structure is constructed (FIG. 13J). Finally, the water inside the balance tank 12 is drained to lift and move the caisson 1 (FIG. 13K).

상기한 바와 같이 본 고안은 대심도에서의 케이슨을 지지층에 견고하게 고정되도록 보강하여 안정성을 확보할 수 있고, 수압에 의한 케이슨의 변형이 적으며, 연결부가 적어 누수가 발생되지 않아 차수효과가 크다. 또한, 토사를 축토하는 종래의 공법에서와 같이 과대한 차수벽체를 확보할 필요가 없고 공기가 단축되며 비용을 절감할 수 있는 효과가 있다. 또, 암반층 절리(규열)에서 침투되는 침출수를 차단함으로써 쾌적한 수중 작업공간을 확보할 수 있는 효과가 있다.As described above, the present invention can secure the stability by reinforcing the caisson at a large depth to be firmly fixed to the support layer, the deformation of the caisson due to water pressure is small, and the connection part is small, so that no leakage occurs, the ordering effect is large. . In addition, there is no need to secure an excessive order wall, as in the conventional construction method of soil excavation, there is an effect that the air can be shortened and the cost can be reduced. In addition, there is an effect that can secure a comfortable underwater work space by blocking the leachate infiltrate in rock bed joint (gyueul).

Claims (3)

복수개의 패널(7)이 결합되며 내측패널(7a)과 외측패널(7b) 내부에 이중패널(7c)로 구성되고 복수개의 균형탱크(12)가 구비되며 최 하측에 위치되는 패널(7)의 하단에 수밀부(8)가 구비된 공지의 케이슨에 있어서,A plurality of panels (7) are coupled to the inner panel (7a) and the outer panel (7b) inside the double panel (7c) consisting of a plurality of balance tanks (12) and the bottom of the panel (7) In the known caisson provided with the watertight portion 8 at the bottom, 상기 케이슨(1)의 내부에 천공되어 매설되는 다수개의 전단말뚝(3)과,A plurality of shear piles 3 perforated and embedded in the caisson 1, 상기 케이슨(1) 내부의 하부에 콘크리트 타설되어 상기 전단말뚝(3)과 일체로 결합되도록 차수벽(4)으로 이루어져,Concrete is placed in the lower portion of the caisson (1) is made of the order wall (4) to be integrally coupled with the shear pile (3), 상기 전단말뚝(3)과 상기 차수벽(4)에 의해 케이슨(1) 하부를 지지층(2)에 고정되도록 하는 것을 특징으로 하는 대심도용 케이슨 지지구조.The caisson support structure for the depth of depth characterized in that the lower end of the caisson (1) by the shear pile (3) and the order wall (4). 제 1 항에 있어서,The method of claim 1, 상기 전단말뚝(3) 사이에 암반층 절리선(10)보다 더 깊게 다수개 천공된 보정구(5)와, 상기 보정구(5)에 그라우팅하여 암반층 절리선(10)을 메꿔 케이슨(1) 내측으로 침투되는 침출수를 차단하도록 하는 그라우팅재(6)를 더 포함하여 이루어지는 것을 특징으로 하는 대심도용 케이슨 지지구조.A plurality of perforations (5) perforated deeper than the rock layer joint line (10) between the shear pile (3), grouting the rock layer joint line (10) by grouting the corrector (5) inside the caisson (1) A caisson support structure for a deep depth, characterized in that it further comprises a grouting material (6) to block the leachate infiltrated into. 복수개의 패널(1)이 결합되며 내부에 균형탱크(12)가 구비되고 최 하측에 위치되는 패널(7)의 하단에 수밀부(8)가 구비된 공지의 케이슨에 있어서,In the known caisson in which a plurality of panels 1 are coupled and a balance tank 12 is provided therein and a watertight portion 8 is provided at a lower end of the panel 7 positioned at the lowermost side. 상기 케이슨(1) 하부에 콘크리트 타설되어 상기 케이슨(1)을 지지층(2)에 고정되도록 하는 차수벽(4)과,A concrete wall under the caisson (1) so as to secure the caisson (1) to the support layer (2); 상기 케이슨(1)의 내측에 매설되는 다수의 보강말뚝(21)과,A plurality of reinforcement piles 21 embedded in the caisson 1, 상기 케이슨(1) 내측의 하부에 콘크리트 타설되어 상기 보강말뚝(21)과 일체로 결합되며 상기 케이슨(1)의 내측패널(7a)과 접하는 보강벽(22)과,Reinforcement wall 22 is placed in the lower portion of the inside of the caisson (1) is integrally coupled with the reinforcement pile 21 and in contact with the inner panel (7a) of the caisson (1), 상기 보강벽(22)에 매설되어 상기 보강말뚝(21)과 상기 케이슨(1)의 내측패널(7a) 사이에 위치하여 상기 보강말뚝(21)으로부터 상기 케이슨(1)의 내측패널(7a)을 지지하도록 보강하는 보강빔(23)으로 이루어져,Buried in the reinforcement wall 22 and located between the reinforcement pile 21 and the inner panel 7a of the caisson 1 to remove the inner panel 7a of the caisson 1 from the reinforcement pile 21. It consists of a reinforcing beam 23 to reinforce to support, 상기 보강말뚝(21)과 상기 보강벽(22) 및 상기 보강빔(23)에 의해 상기 케이슨(1) 하부를 지지층(2)에 고정되도록 하는 것을 특징으로 하는 대심도용 케이슨 지지구조.The caisson support structure for large depths, characterized in that the bottom of the caisson (1) is fixed to the support layer (2) by the reinforcing pile (21), the reinforcing wall (22) and the reinforcing beam (23).
KR20-2004-0014174U 2004-05-21 2004-05-21 Caisson Supporting Structure for Deep Water KR200361080Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0014174U KR200361080Y1 (en) 2004-05-21 2004-05-21 Caisson Supporting Structure for Deep Water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0014174U KR200361080Y1 (en) 2004-05-21 2004-05-21 Caisson Supporting Structure for Deep Water

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020040035693A Division KR100645324B1 (en) 2004-05-19 2004-05-19 Caisson Supporting Structure for Deep Water

Publications (1)

Publication Number Publication Date
KR200361080Y1 true KR200361080Y1 (en) 2004-09-06

Family

ID=49436842

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0014174U KR200361080Y1 (en) 2004-05-21 2004-05-21 Caisson Supporting Structure for Deep Water

Country Status (1)

Country Link
KR (1) KR200361080Y1 (en)

Similar Documents

Publication Publication Date Title
CN103882881B (en) Go deep into rock construction method under water
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN105002913A (en) Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof
KR20100115019A (en) Panel joint for construction for underground diaphragm well and underground diaphragm well constructing method using the same
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN112695803B (en) Supporting and water-stopping construction method for pipe-jacking working well and pipe ditch on beach
CN111535328A (en) Pit shaft type underground garage foundation pit supporting system in water-rich stratum and construction method
CN108071122A (en) Assembled underground pipe gallery and its construction method
CN109578014A (en) Anti- dash forward of one kind gushes back cover structure and construction method
CN106480891B (en) A kind of shaft construction method
CN108867723A (en) The method of frame structure building rectification and underground increasing layer
KR20130013287A (en) Wet-type constructing method of pier foundation
CN113482021A (en) Half-pile supporting structure for excavating shallow foundation pit above underground structure floor and construction method
KR100645324B1 (en) Caisson Supporting Structure for Deep Water
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN209260739U (en) A kind of foundation pit water-stopping system close to river permeable stratum
CN110080234A (en) A method of it is excavated in the secondary central island of deep foundation pit of soft soil foundation
CN111155429A (en) Construction method for bridge sand blowing island building in still water deep water area
KR200361080Y1 (en) Caisson Supporting Structure for Deep Water
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN212477744U (en) Pit shaft type underground garage foundation pit supporting system in water-rich stratum
CN204435321U (en) A kind of steam power station water intaking open channel
JPH11209998A (en) Impermeable construction method of underground structure by self-standing type double impermeable walls
CN106498951A (en) A kind of shaft excavation construction method
CN106988337A (en) A kind of reinforcement means for being used to reduce bar shaped shallow foundation house differential settlement

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20050829

Year of fee payment: 3

EXTG Extinguishment