KR200303949Y1 - The supporting bar for deck panels - Google Patents

The supporting bar for deck panels Download PDF

Info

Publication number
KR200303949Y1
KR200303949Y1 KR20-2002-0033813U KR20020033813U KR200303949Y1 KR 200303949 Y1 KR200303949 Y1 KR 200303949Y1 KR 20020033813 U KR20020033813 U KR 20020033813U KR 200303949 Y1 KR200303949 Y1 KR 200303949Y1
Authority
KR
South Korea
Prior art keywords
support
deck
plate
formwork
bar
Prior art date
Application number
KR20-2002-0033813U
Other languages
Korean (ko)
Inventor
김귀환
강석환
Original Assignee
주식회사 거혁
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 거혁 filed Critical 주식회사 거혁
Priority to KR20-2002-0033813U priority Critical patent/KR200303949Y1/en
Application granted granted Critical
Publication of KR200303949Y1 publication Critical patent/KR200303949Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/16Members, e.g. consoles, for attachment to the wall to support girders, beams, or the like carrying forms or moulds for floors, lintels, or transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

본 고안은 콘크리트 슬라브 시공용 데크지지대에 관한 것이다.The present invention relates to a deck support for concrete slab construction.

본 고안의 데크지지대는, 전체적으로 "ㄷ"자형 평단면을 하는 바형 포스트(P)와, 이 포스트의 하단면에 부착되는 하판(L)과, 상기 포스트(P)의 두 대향 측벽 상부 외면에 부착되는 판상의 가이드브라케트(BK)로 이루어진 바형 고정지지대(21)와; 사각형상의 상판(22A)과, 상판(22A) 저면의 두 대향 단부측 전길이에 걸쳐 하향직립하여 부착되는 두 측판(22B)과, 대향하는 두 측판(22B) 후방단부측과 중앙부에 상·하 방향으로 부착되는 후판(22C) 및 전판(22D)으로 이루어져 상기 고정지지대(21)의 상부 내면에 상·하 유동가능하게 결합되는 유동지지대(22)와; 상기 각 가이드브라케트(BK)의 외면에 유동가능하게 결합되어 상기 유동지지대(24B)를 이동 또는 고정시키는 역할을 하는 사각 판상의 다수 걸림편(23)으로 구성되므로써 상단부측의 높이가 조절되는 동시에 일측방향으로 회전가능한 구조를 갖게 됨에 본 고안의 기술적 특징이 있다.The deck support of the present invention is a bar post (P) having a "c" shaped flat section as a whole, a bottom plate (L) attached to the bottom surface of the post, and attached to the upper outer surface of the two opposite side walls of the post (P). Bar-shaped fixing support (21) made of a plate-shaped guide bracket (BK); 22A of rectangular top boards, the two side plates 22B which are affixed in the upright direction across the whole length of two opposing end sides of the bottom face of the top board 22A, and the upper and lower parts in the rear end side and center part of the opposing two side plates 22B. A flow support 22 composed of a rear plate 22C and a front plate 22D attached in a direction so as to be movable up and down on an upper inner surface of the fixed support 21; The height of the upper end side is adjusted by being composed of a plurality of engaging pieces 23 of the square plate that is movably coupled to the outer surface of each guide bracket (BK) to move or fix the flow support (24B). There is a technical feature of the present invention to have a structure rotatable in one direction.

Description

콘크리트 슬라브 시공용 데크지지대{The supporting bar for deck panels}Deck Support for Concrete Slab Construction {The supporting bar for deck panels}

본 고안은 콘크리트 슬라브 시공용 데크지지대에 관한 것으로, 더 자세하게는 배면이 상호 대향하는 벽체용 두 내벽거푸집의 각 좌·우측 모서리와 두 모서리를 균등분할하는 다수 곳에, 상·하 유동 및 회전이 가능한 유동부가 상부에 결합된 데크지지대를 내벽거푸집과 함께 연결하여 거푸집의 기둥의 역할을 수행하도록 함으로써, 슬라브용 데크를 지지하기 위하여 바닥면에 직립설치해야 하는 종래의 수 많은 지지대 없이도 그 상단면에 설치되는 슬라브용 데크와 데크지지대를 지지할 수 있으며, 해체시에는 상기 데크지지대 유동부의 높이를 낮춤과 동시에 하향 회존시켜 데크의 해체가 간편하게 이루어질 수 있도록 하는 동시에 목재류 거푸집 시공재들을 사용하지 않도록 함으로써, 거푸집 설치 구조물들의 재활용성을 향상시킨 콘크리트 슬라브 시공용 데크지지대에 관한 것이다.The present invention relates to a deck support for the construction of concrete slabs, and more specifically, the upper and lower flow and rotation is possible in a number of places evenly split the left and right edges and the two corners of the two inner wall formwork for the wall facing each other. By connecting the deck support coupled to the upper part with the inner wall formwork to perform the role of the formwork pillar, it is installed on the upper surface without numerous conventional supports that need to be installed upright on the floor to support the deck for slabs. The slab deck and the deck support can be supported, and when dismantling, the deck support lowers the flow portion and simultaneously rotates downward to facilitate the dismantling of the deck, while avoiding the use of timber formwork. Concrete slabs improve the recyclability of installation structures It relates to a construction deck support.

콘크리트 철근 구조의 다층 건축물은 콘크리트 벽체와 슬라브 시공용 거푸집의 설치로부터 시작되는 바, 내부 공간이 벽체의 형상을 하는 주형과 같은 틀을 먼저 만들고, 그 틀의 상단에 천정 슬라브 시공용 판재를 지면에 수평하도록 설치한 후, 상기 틀의 내부와 판재의 상면에 콘크리트를 채우고 양생시키는 방법으로 형성되며, '거푸집'이라 불리우는 상기 '틀'과 '판재'는 일반적으로 거푸집판넬이라고 불리는 사각 판상의 판넬들을 다수 연결하여 만들어진다.The multi-layered structure of concrete reinforcing structure begins with the installation of concrete wall and slab construction formwork. First, the interior space is made into a mold like a wall shape, and the ceiling slab construction board is placed on the ground. After horizontal installation, the concrete is formed by filling and curing the inside of the frame and the upper surface of the plate, and the 'frame' and the 'plate', called 'forms' are generally rectangular panels called formwork panels. It is made by connecting a number.

따라서, 벽체와 슬라브의 시공은 상기 다수의 거푸집판넬들을 연결하여 콘크리트를 채울 수 있는 내부 공간과 상면을 갖는 형틀인 거푸집을 설치하는 것으로부터 시작된다.Therefore, the construction of the wall and the slab starts by installing the formwork, which is a mold having an interior space and an upper surface to connect the plurality of formwork panels to fill concrete.

본 고안과 종래의 기술을 설명하기에 앞서, 상기 거푸집의 용어에 대한 혼동을 피하기 위하여 다음과 같이 거푸집에 대한 용어를 정의한다.Prior to describing the present invention and the prior art, terms for the formwork are defined as follows to avoid confusion about the terminology of the formwork.

벽체 시공용 거푸집은 각 벽체의 내·외측 두 면에 각각 밀착되는 두 부분으로 이루어지고, 각 부분은 상·하단으로 구분할 수 있으며, 각 상·하단은 다수의 단위 판넬로 분리되는 바, 상기 각 단위 판넬을 '거푸집판넬', 다수의 거푸집판넬들이 좌·우로 결합되어 상단에 위치하는 것을 '상단거푸집', 하단에 위치하게 되는 것을 '하단거푸집', 상·하단거푸집을 구성하는 다수 거푸집판넬들의 전면들이 동일 평면상에 위치하도록 거푸집판넬들이 각종 결합부재에 의해 결합되어 벽체의 일측 면 전체에 밀착되는 것을 '내벽거푸집'이라 한다.Formwork for wall construction consists of two parts that are in close contact with each of the inner and outer two surfaces of each wall, each part can be divided into upper and lower ends, each upper and lower ends are separated into a plurality of unit panels, The unit panel is composed of 'form panel', a number of form panels are combined to the left and right, 'top formwork' to be located at the top, 'down formwork' to be located at the bottom, and a number of formwork panels constituting the top and bottom formwork. Formwork panels are coupled by various coupling members so that the front surfaces are located on the same plane and are in close contact with one side of the wall.

따라서, 하나의 벽체는, 벽체의 두께만큼 이격된 상태에서 각 전면이 서로 대향하도록 설치되는 두 내벽거푸집 사이의 공간에 채워지는 콘크리트에 의해서 만들어진다.Thus, one wall is made of concrete filled in the space between two inner wall formwork, each side of which is installed so as to face each other while being spaced by the thickness of the wall.

그리고, 천정이 되는 슬라브용 거푸집은, 다수의 거푸집판넬들의 상면이 동일 평면을 이루고 상기 대향하는 두 내벽거푸집 사이의 간격이 막히지 않도록 내벽 커푸집의 상단부에 바닥과 평행하도록 결합되고, 벽체가 되는 두 내벽거푸집 사이와 상기 슬라브용 거푸집의 상면에 코크리트가 함께 타설되는 바, 벽체용 거푸집과 구분하기 위하여 상기 슬라브용 거푸집을 '데크'라 하고, 데크를 구성하는 거푸집판넬을 '데크판넬'이라 하며, 내벽거푸집과 데크 모두를 '거푸집'이라 정의하기로 한다.In addition, the ceiling slab formwork is coupled to the upper end of the inner wall formwork parallel to the floor so that the upper surface of the plurality of formwork panels form the same plane and the gap between the two opposing inner wall formwork is not blocked. Cocrete is placed together between the inner wall formwork and the upper surface of the slab formwork. The slab formwork is called 'deck' to distinguish it from the wall formwork, and the formwork panel constituting the deck is called 'deck panel'. In other words, both the interior formwork and the deck are defined as 'forms'.

거푸집의 기본 구성 요소이며, 콘크리트에 밀착되는 판재와 판재를 지지하는 프레임으로 구성된 상기 거푸집 또는 데크판넬의 재료로서 종래에는 목재만이 주로 사용되어 왔으나, 목재 판넬을 이용할 경우에는 판넬들간의 연결조립이 못질 또는 와이어의 조임에 의해서 이루어지기 때문에, 거푸집 설치 작업에 많은 인력과 시간이 필요로 되며, 또한 콘크리트 양생 후 거푸집의 철거 작업에도 많은 시간과 인력이 소요된다.It is a basic component of formwork, and as a material of the formwork or deck panel, which is composed of a plate that adheres to concrete and a frame supporting the plate, only wood has been mainly used in the past, but in the case of using a wood panel, connection assembly between panels is Since it is made by nailing or tightening of wires, a lot of manpower and time are required for the formwork installation work, and also a lot of time and manpower is required for the demolition work of the formwork after concrete curing.

또한, 목재 판넬은 합판의 배면에 각형 목재 바가 보강되어 있기는 하나, 목재의 특성상 거푸집에 채워지는 콘크리트의 하중에 의한 압력으로 변형되기 쉬우며, 벽체의 규모가 클수록 그러한 경향은 더욱 증가하게 되고, 그 결과 벽체의 외면이 평탄면을 이루지 못하게 되는 경우가 종종 발생되기도 한다.In addition, the wood panel is reinforced with a rectangular wooden bar on the back of the plywood, but due to the nature of the wood it is easy to be deformed by the pressure of the concrete filled in the formwork, the larger the size of the wall, the more the tendency increases, As a result, the outer surface of the wall often fails to form a flat surface.

따라서, 상기와 같은 목재 판넬의 변형을 방지하기 위하여 거푸집을 만든 상태에서 콘크리트를 거푸집에 채우기전 별도의 보강재로 거푸집판넬들을 보강해야 하는 불편함이 있으며, 거푸집의 설치 및 철거 과정에서 목재 판넬들이 변형되거나파손되는 경우가 많아서 반복하여 재사용되는 횟수가 극히 제한되어 그 수명이 짧은 단점이 있을 뿐 아니라, 파손되어 못쓰게 된 목재 판넬의 처리도 문제가 된다.Therefore, in order to prevent the deformation of the wood panel as described above, there is an inconvenience of reinforcing the formwork panels with a separate reinforcement before filling the formwork with concrete, the wood panels are deformed during the installation and demolition of the formwork. In many cases, the number of times of repeated reuse can be extremely limited, and the short lifespan is not only short, but also the treatment of damaged and damaged wood panels becomes a problem.

상기와 같은 목재 판넬의 제반 문제점들을 해결하기 위하여 판재는 목재로 하되 프레임을 철재나 알루미늄 합금(이하에서는 '알루미늄'이라함)과 같은 금속으로 사용한 목재-금속 판넬이 개발되어 각종 건축물 시공현장에서 사용되고 있으며, 그 사용 범위 및 규모가 급속히 증가되고 있는 추세에 있다.In order to solve the above problems of the wood panel, the board is made of wood, but the wood-metal panel has been developed and used in various construction sites using a frame made of metal such as steel or aluminum alloy (hereinafter referred to as 'aluminum'). In addition, the range and scale of its use are rapidly increasing.

그러나, 상기 철재 프레임 판넬의 경우에는 그 중량이 상당하기 때문에 핸들링이 어려워 거푸집 설치 작업성이 낮을 뿐만 아니라, 녹이 쉽게 발생되고 녹에 의한 내구성 저하가 크기 때문에 보관에 어려움이 있다.However, in the case of the steel frame panel, since the weight is considerable, it is difficult to handle because it is difficult to handle, and the workability is low, and since rust is easily generated and durability deterioration due to rust is large.

상기 철재 프레임 판넬의 단점을 해결하기 위하여 개발된 것이 알루미늄 프레임 판넬으로써, 철재 프레임 판넬에 비하여 무게가 매우 가벼울 뿐 아니라, 자체 강성이 크기 때문에 콘크리트 압력에 의한 변형이 없어 양생되어 나오는 벽체의 품질이 우수하고 설치 및 철거 작업이 용이하고, 반복적인 재사용이 가능하여 수명이 반영구적이라는 장점이 높이 평가되고 있다.The aluminum frame panel was developed to solve the shortcomings of the steel frame panel, which is very light in weight compared to the steel frame panel, and because of its high rigidity, there is no deformation due to the pressure of the concrete, so the quality of the cured wall is excellent. In addition, it is highly appreciated that the service life is semi-permanent because it is easy to install and dismantle and can be reused repeatedly.

상기와 같은 각종 판넬들을 조립하여 콘크리트가 부어지는 일종의 형틀인 거푸집을 만들기 위해서는, 타설 후 양생되기전까지 상기 각 판넬들에 상당한 압력을 부여하게 되는 콘크리트의 중량에 의해 거푸집의 최초 설치 형상이 변형되지 않도록, 즉 콘크리트의 중량을 견딜 수 있도록 각 판넬들의 배면에 각종 지지대들이 설치되어야 하며, 특히 양 단부만이 내벽거푸집의 상단부에 의해 지지되는 슬라브용 데크에는 과도한 하중이 걸리기 때문에 상당히 많은 수의 지지대들이 바닥면과 상기 데크판넬들의 저면 사이에 세워져야 하는 등 종래의 거푸집 구조는 많은 문제점들을 가지고 있는 바, 이를 종래의 거푸집 구조를 도시한 도 1에 의거하여 살펴보면 다음과 같다.In order to assemble the various panels as described above to form a form of a form in which the concrete is poured, so that the initial installation shape of the formwork is not deformed by the weight of the concrete to give a significant pressure to each panel until curing after pouring. In other words, various supports should be installed on the back of each panel to withstand the weight of concrete. Especially, because the slab deck is supported by the upper end of the inner wall formwork only at both ends, a considerable number of supports are placed on the floor. Conventional formwork, such as to be built between the surface and the bottom of the deck panel has a number of problems, looking at on the basis of Figure 1 showing the conventional formwork as follows.

도시된 바와 같이, 종래의 거푸집은 각 벽체(W)를 시공하기 위하여 바닥면(A)에 고정 설치된 목재 기초가름대(12)의 상면에 직립되며 상·하 2단으로 이루어진 벽체당 두 내벽거푸집(11)과, 이 내벽거푸집의 상단부에 바닥과 평행하게 데크(13)가 놓여진다.As shown, the conventional formwork is upright on the upper surface of the wooden foundation bar 12 fixed to the bottom surface (A) for the construction of each wall (W) and two inner wall formwork per wall consisting of two stages up and down ( 11) and a deck 13 is placed at the upper end of the inner wall formwork in parallel with the floor.

상기 종래의 데크(13)로는 보통 목재 합판이 사용되는 바, 슬라브로 타설되는 콘크리트를 지탱하기 위하여 상기 합판으로 이루어진 데크(13)의 저면에는 다수의 평행한 가로바(14)(장선,長線)들이 밀착되고, 이 가로바(14)들의 저면에는 이들과 직교하며 평행한 다수의 세로바(15)(멍에)들이 밀착된 후 각 세로바(15)들의 저면을 따라 다수의 지지대(S3)들이 바닥면(A)까지 직립하여 상기 데크(13)를 지지하게 되는 구조이며, 내벽거푸집 배면 상단부를 따라 상기 가로바(14)와 평행한 각목(T)이 결합되어 데크(13)와 내벽거푸집(11)을 연결하게 된다.The conventional deck 13 is usually a wooden plywood is used, the bottom of the deck 13 made of plywood in order to support the concrete poured into the slab a plurality of parallel horizontal bars 14 (long line, long line) Are closely attached to the bottom of the horizontal bars 14, and a plurality of vertical bars 15 (yokes) orthogonal to and parallel to them are closely attached to each other, and then a plurality of supports S3 are formed along the bottom of each vertical bars 15. Upright to the bottom surface (A) is a structure to support the deck 13, along the upper end of the inner wall formwork, the wood (T) parallel to the horizontal bar 14 is coupled to the deck 13 and the inner wall formwork ( 11).

이때, 평탄한 전면이 벽체(W)의 두께만큼 이격된 상태로 대향하는 두 내벽거푸집(11)은 벽체를 두께 방향으로 가로지르게 되는 다수의 연결편(C)으로 결합되며, 벽체 시공 완료 후 상기 각 연결편(C)의 양단부를 절단하여 내벽거푸집을 해체하게 되고, 각 연결편(C)의 중간부는 벽체 콘크리트속에 매몰된 상태가 된다.At this time, the two inner wall formwork 11 facing each other in a state in which the flat front face is spaced apart by the thickness of the wall (W) is coupled to a plurality of connecting pieces (C) to cross the wall in the thickness direction, and after completion of the wall construction each connecting piece Both ends of (C) are cut to dismantle the inner wall formwork, and the intermediate portion of each connecting piece (C) is buried in the wall concrete.

그리고, 상기 내벽거푸집(11)의 각 배면에는, 벽체(W) 시공용으로 타설되는콘크리트의 하중에 의한 압력으로 각 내벽거푸집을 이루는 거푸집판넬들이 처음의 조립 위치에서 이탈되는 것을 방지하기 위하여 다수의 수직지지대(S1)들과 수평지지대(S2)들이 결합된다.In addition, on each rear surface of the inner wall formwork 11, a plurality of formwork panels constituting the inner wall formwork are prevented from being separated from the initial assembly position by the pressure of the concrete that is poured for the construction of the wall W. The vertical supports S1 and the horizontal supports S2 are combined.

또한, 슬라브용 거푸집인 상기 데크(13)는, 서로 대향하는 두 측벽의 두 대향면에 각각의 전면이 밀착되며 바닥(A)면의 거리만큼 이격되어 각각의 배면이 서로 대향하게 되는 두 내벽거푸집의 각 전면측 상단부로부터 배면측으로 양 단부가 각각 놓여져 두 교각에 걸쳐진 다리의 상판과 같은 형태가 되기 때문에, 슬라브를 시공하기 위하여 상기 합판 데크 상면으로 타설되는 전체 콘크리트의 하중이 데크의 양 단부에 상단부가 결합된 두 내벽거푸집에 의해서만 지지되는 구조가 된다.In addition, the deck 13, which is a slab formwork, has two front walls closely contacted with two opposing surfaces of two side walls facing each other, and are spaced apart by a distance from the bottom (A) surface so that each back surface faces each other. Since both ends are placed from the front end of each front side to the back side to form the top plate of the bridge spanning the two piers, the load of the entire concrete cast into the top surface of the plywood deck to construct the slab is the upper end at both ends of the deck. The structure is supported only by the two inner wall formwork combined.

따라서, 상기와 같은 구조에서는 합판으로 이루어진 데크가 콘크리트의 하중을 견딜 수 없기 때문에 상기와 같이 데크(13)의 저면과 바닥면(A) 사이에 수 많은 가로바(14), 세로바(15) 및 지지대(S3)들이 설치된다.Therefore, in the structure as described above, since the deck made of plywood can not withstand the load of the concrete, as described above, a number of horizontal bars 14, vertical bars 15 between the bottom and the bottom surface (A) of the deck (13) And supports S3 are installed.

따라서, 상기와 같이 설치되는 종래의 거푸집은 다음과 같은 여러가지 문제점들을 갖게 된다.Therefore, the conventional formwork installed as described above has various problems as follows.

첫째, 내벽거푸집의 각 하단부에 설치되는 기초가름대는 통상 다수의 목재를 적층한 것이기 때문에 벽체와 밀착하게 되는 측면과 그 높이를 평탄하게 맞추기 어렵고, 따라서 거푸집판넬들 간의 수평도와 수직도를 맞추기가 쉽지 않아 거푸집 설치 작업성이 떨어진다.First, since the base bar installed at each lower end of the inner wall formwork is usually stacked with a plurality of timbers, it is difficult to level the sides and the height of the form panels closely, so it is easy to match the horizontality and verticality between the formwork panels. It does not reduce workability of formwork installation.

둘째, 합판으로 이루어진 데크의 단부만이 내벽거푸집에 의해 지지되기 때문에 내벽거푸집에 큰 하중이 걸리게 되어 내벽거푸집의 형상이 뒤틀리기 쉬우며, 이를 방지하기 위해서는 많은 수의 수직지지대와 수평지지대를 내벽거푸집의 배면에 결합시켜야 하는 바, 거푸집 설치 시간이 길어져 시공 기간이 연장된다.Second, since only the end of the deck made of plywood is supported by the inner wall formwork, a large load is placed on the inner wall formwork, and the shape of the inner wall formwork tends to be distorted, and in order to prevent this, a large number of vertical supports and horizontal supports are formed in the inner wall formwork. Should be bonded to the back of the bar, the formwork installation time is long, the construction period is extended.

세째, 내벽거푸집에 의해 지지되는 데크의 양 단부 이외의 중간부를 지지하기 위하여 가로바, 세로바, 각목, 지지대 등과 같은 지지수단들이 과다하게 필요하고, 그 지지수단들을 설치하고 해체하는데 필요한 시간이 길어질 뿐 아니라, 특히 바닥면에 직립하는 다수의 밀집된 지지대들에 의하여 시람의 동작이 제한되기 때문에 내벽거푸집과 데크의 배면과 저면에서 벽체와 슬라브의 타설 상태를 검사하거나 별도의 부수적인 바닥 공사를 실시하기가 어렵다.Third, an excessive amount of supporting means such as horizontal bars, vertical bars, lumber, and a support is necessary to support an intermediate portion other than both ends of the deck supported by the inner wall formwork, and the time required for installing and dismantling the supporting means will be longer. In addition, since the operation of shiram is limited by a number of dense supports standing upright on the floor, it is necessary to inspect the casting condition of walls and slabs on the back and bottom of the inner wall formwork and deck, or to perform additional floor construction. Is difficult.

네째, 거푸집을 설치하기 위한 각종 부자재, 즉 데크, 수평지지대, 수직지지대, 가로바, 세로바, 지지대, 기초가름대, 각목 등은 주로 합판, 각목 내지는 파이프 등이 주로 사용되며, 각 목재들은 못 등으로 결합되는 바, 거푸집의 설치와 해체시 상기 각종 부자재의 파손율이 높아 재활용도가 낮아지기 때문에 초기 거푸집 비용은 저렴하나 결과적으로는 시공비가 증가하게 되고, 폐자재 처리를 위한 비용이 발생하게 된다.Fourth, various subsidiary materials for installing the formwork, namely deck, horizontal support, vertical support, horizontal bar, vertical bar, support, foundation bar, etc. are mainly used plywood, wood or pipe, each wood is nail, etc. When combined with the formwork, since the damage rate of the various subsidiary materials during the installation and dismantling of the form is high and the recycling rate is low, the initial form cost is low, but as a result, the construction cost increases, and the cost for processing waste materials is generated.

본 고안은 상기와 같은 종래의 거푸집이 가지고 있는 제반 문제점들을 해결하기 위하여 창안된 것으로, 건축물의 기둥 역할을 수행하며, 그 높이의 조절이 가능하여 많은 지지대 없이도 데크를 지지할 수 있는 동시에 데크를 손쉽게 해체시킬 수 있도록 할 뿐 아니라, 목재의 사용을 배재함으로써, 거푸집의 설치 및 해체 시간과 노동력을 최소화하고, 거푸집 구조에 사용되는 각종 자재들의 재활용성을 향상시켜 최초 투자비가 상승됨에도 불구하고 결과적으로는 시공비의 절감이 가능한 콘크리 슬라브 시공 데크 설치용 지지구를 제공함에 본 고안의 목적이 있다.The present invention was devised to solve all the problems of the conventional formwork as described above, and serves as a pillar of the building, the height can be adjusted to support the deck without many supports at the same time easy to deck Not only can it be dismantled, but by eliminating the use of wood, it minimizes the installation and dismantling time and labor of the formwork, and improves the recyclability of the materials used in the formwork. An object of the present invention is to provide a support for installing a concrete slab construction deck that can reduce the construction cost.

도 1은 종래 벽체와 슬라브 시공용 거푸집의 구조를 보인 것으로,1 shows a structure of a conventional wall and slab construction formwork,

(가)는 사시도이고,(A) is a perspective view,

(나)는 측면도이다.(B) is a side view.

도 2는 본 고안 일실시예 데크지지대의 사시도.Figure 2 is a perspective view of the deck support one embodiment of the present invention.

도 3은 본 고안 일실시예 데크 지지대의 분리 사시도.Figure 3 is an exploded perspective view of the deck support one embodiment of the present invention.

도 4는 데크지지대를 구성하는 일실시예 유동지지대의 측단면도.Figure 4 is a side cross-sectional view of an embodiment of the flow support constituting the deck support.

도 5는 본 고안 데크지지대의 사용상태도Figure 5 is a state of use of the present invention deck support

((도면의 주요 부분에 대한 부호의 설명))((Explanation of symbols for main part of drawing))

2. 데크지지대 11. 내벽거푸집 12. 기초가름대2. Deck support 11. Inner wall formwork 12. Foundation strainer

13,26. 데크 14. 가로바(장선) 15. 세로바(멍에)13,26. Deck 14. Horizontal bar (joist) 15. Vertical bar (yoke)

21. 고장지지대 22. 유동지지대 23. 걸림편21. Breakdown support 22. Floating support 23. Hanging piece

22A. 상판 22B. 측판 22C. 후판22A. Top plate 22B. Shroud 22C. Plate

22D. 전판 A. 바닥면 BK. 가이드브라케트22D. Front plate A. Bottom surface BK. Guide Bracket

C. 연결편 G. 걸림편가이드 GB. 상부 가이드바C. Connecting piece G. Hanging guide GB. Top guide bar

GB'. 하부 가이드바 H1,H2. 관통공 H1',H2'. 통과공GB '. Lower guide bar H 1 , H 2 . Through hole H 1 ', H 2 '. Through ball

H3. 걸림공 h. 결합공 L. 하판H 3 . Gonghole h. Joiner L. Bottom Plate

S1. 수평지지대 S2. 수직지지대 S3. 지지대S1. Horizontal support S2. Vertical support S3. support fixture

T. 각목 W. 벽체T. Hardwood W. Wall

본 고안의 상기 목적은, 상·하 이동 및 회전이 가능한 부위가 상단부에 결합된 바(bar)형 데크지지대 및 굴곡가능한 데크지지바에 의하여 달성된다.The object of the present invention is achieved by a bar-shaped deck support and a bendable deck support bar coupled to the upper end portion is movable and rotated.

본 고안 콘크리트 슬라브 시공용 데크지지대는, 내벽거푸집 사이에 다수가 함께 설치되어 슬라브용으로 타설된 콘크리트와 데크의 하중을 받아냄으로써 내벽거푸집의 안정성을 향상시키게 되며, 서로 대향하는 두 내벽거푸집에 각각 설치된 두 데크지지대의 상단면에 H-빔으로 이루어진 데크지지바를 설치하고 그 상면에 데크를 구성하는 다수의 데크판넬들을 설치할 수 있도록 하여 전체적으로 거푸집의 설치와 해체를 손쉽게 하여 준다.The deck support for the concrete slab construction of the present invention is installed between a plurality of inner wall formwork to increase the stability of the inner wall formwork by receiving the load of the concrete and the deck placed for the slab, respectively installed on the two inner wall formwork facing each other The deck support bar made of H-beams is installed on the upper surfaces of the two deck supports, and a number of deck panels constituting the deck can be installed on the upper surface of the deck support to facilitate the installation and dismantling of the formwork as a whole.

특히, 데크의 해체시 데크의 높이를 낮추어 데크의 해체를 손쉽게 할 수 있도록 하기 위하여 데크지지바가 놓여지는 본 고안 데크지지대의 상부에 그 높이가 조절되며 회전이 가능한 유동부를 구비한 구조에 기술적 특징이 있다.In particular, when the deck is dismantled to lower the height of the deck so that the deck can easily dismantle the deck support bar, the height of the deck support bar is designed to adjust the height of the structure is equipped with a movable rotatable flow part have.

본 고안의 상기 데크지지대는, 데크지지대의 배면이 벽체면과 밀착되는 내벽거푸집을 구성하는 장척거푸집판넬들 사이에서 내벽거푸집의 전면과 동일 평면을 이루도록, 한 칸의 공간에서 대향하는 두 내벽거푸집 각 내부에서 서로 대향하게 각각 다수가 바닥면에 직립하도록 설치되며, 각 데크지지대는 고정지지대와 유동지지대로 구성되어 거푸집의 해체시에는 상기 유동지지대를 하강 및 전방하향으로 회전시키므로써 유동지지대가 상승되었던 설치시의 데크지지대 높이를 축소시킬 수 있고, 그렇게 함으로써 데크지지대 상단의 상기 유동지지대 상면에 양 단부 저면이 결합된 데크지지바를 굴곡시켜 양 단부 사이의 중간부 높이를 낮출 수 있게 된다.The deck support according to the present invention has two inner wall formwork faces facing each other in a space such that the back of the deck support forms the same plane as the front surface of the inner wall formwork between the long formwork panels constituting the inner wall formwork in close contact with the wall surface. Each of the deck supports are installed so as to stand upright on the floor, and each deck support is composed of a fixed support and a flow support. When the form is dismantled, the flow support was raised by rotating the flow support downward and forward downward. It is possible to reduce the height of the deck support at the time of installation, thereby bend the deck support bar coupled to the bottom surface of both ends to the upper surface of the flow support at the top of the deck support it is possible to lower the height of the middle portion between the two ends.

그리고, 배면이 대향하는 두 내벽거푸집 내부에 직립하여 대향하는 각 쌍의 데크지지대 상단면에 보와 같이 양 단부 저면이 놓여져 분리가능하게 결합될 수 있으며, 굴곡이 가능도록 단척의 H-빔들이 다관절 링크에 의해 결합되는 데크지지바를 함께 사용하는 것이 바람직하다.In addition, the bottom faces of the two ends of the deck support stand upright inside the two inner wall formwork to be opposed to each other can be detachably coupled by placing the bottom of both ends as a beam, the short H-beams to bend all It is preferable to use a deck support bar coupled by a joint link.

상기 본 고안의 목적과 기술적 구성을 비롯한 그에 따른 작용 효과에 관한 자세한 사항은 본 고안의 바람직한 실시예를 도시하고 있는 도면을 참조한 아래의 설명에 의해 명확하게 이해될 것이다.The details of the purpose and technical constitution according to the present invention, including the effect thereof, will be clearly understood by the following description with reference to the drawings showing preferred embodiments of the present invention.

도 2에 본 고안 일실시예 데크지지대의 사시도를, 도 3에 분리사시도를, 도 4에 유동지지대의 단면도를 도시하였다.Figure 2 is a perspective view of one embodiment of the present invention deck support, Figure 3 is an exploded perspective view, Figure 4 is a cross-sectional view of the flow support.

도시된 바와 같이 본 고안의 데크지지대(2)는, 전체적으로 "ㄷ"자형 평단면을 갖는 바형 포스트(P)와, 이 포스트의 하단면에 부착되는 하판(L)과, 상기 포스트(P)의 두 대향 측벽 상부 외면에 부착되는 판상의 가이드브라케트(BK)로 이루어진 바형 고정지지대(21)와;As shown in the deck support 2 of the present invention, the bar-shaped post (P) having a "c" shaped flat cross section as a whole, the bottom plate (L) attached to the bottom surface of the post, and the post (P) A bar-shaped fixing support (21) consisting of a plate-shaped guide bracket (BK) attached to two opposite sidewall upper outer surfaces;

다수의 관통공(h)들이 구비된 사각형상의 상판(22A)과, 상판(22A) 저면의 두 대향 단부측 전길이에 걸쳐 하향직립하여 부착되며 하부로 갈수록 폭이 감소하여 상·하 동일측 두 내각이 90°인 사다리꼴 형상을 하고 각 외면의 상·하부에 가이드바(GB)(GB')가 각각 분리가능하게 직립 결합되는 두 측판(22B)과, 대향하는 두 측판(22B) 내면의 후방단부측 각 중앙부에 양 선단면 전체가 각각 부착되는 사각형상의 후(後)판(22C)과, 후판(22C) 전방의 두 측판(22B) 대향면에 상기 후판(22C)과 평행하게 양 선단면 전체가 각각 부착되는 사각형상의 전(前)판(22D)으로 이루어져 상기 고정지지대(21)의 상부 내면에 상·하 유동가능하게 결합되는 유동지지대(22)와;A rectangular top plate 22A provided with a plurality of through holes h and a bottom upright are attached over the entire lengths of two opposite end sides of the bottom surface of the top plate 22A, and the width decreases toward the bottom, so that the top and bottom sides are the same. Two side plates 22B having a trapezoidal shape having an internal angle of 90 ° and detachable uprights of the guide bars GB and GB 'are respectively separated on the upper and lower portions of each outer surface, and the rear of the inner surfaces of the two opposite side plates 22B. Both front end faces in parallel with the rear plate 22C on the opposing surfaces of the rectangular rear plate 22C and the two side plates 22B in front of the rear plate 22C, in which both front end surfaces are respectively attached to the central portions at the end sides. A flow support 22 which consists of a rectangular front plate 22D to which the whole is attached, and is coupled to the upper inner surface of the fixed support 21 so as to be movable up and down;

상기 각 가이드브라케트(BK)의 외면에 유동가능하게 결합되어 상기 유동지지대(24B)를 이동 또는 고정시키는 역할을 하는 사각 판상의 다수 걸림편(23)으로 구성된다.It is composed of a plurality of engaging pieces 23 of the square plate that is movably coupled to the outer surface of each guide bracket (BK) serves to move or fix the flow support (24B).

그리고, 상기 각 가이드브라케트(BK)의 상·하부에는 상·하 일자형 관통공(H1)(H2)들이 일직선상에서 서로 이격되어 형성되며, 각 관통공(H1)(H2)을 중심으로 그 상·하 단부에 인접하면서 서로 대향하며 대칭되는 한 쌍씩의 걸림편가이드(G1,G1')(G2,G2')들이 전·후 방향으로 부착되고, 각 가이드브라케트(BK)가 부착되는 상기 고정지지대(24A)의 두 대향 측벽에도 상기 두 관통공(H1)(H2)들과 각각 일치하는 통과공(H1')(H2')들이 형성된다.The upper and lower straight through holes H 1 and H 2 are formed on the upper and lower portions of the guide brackets BK, and are spaced apart from each other in a straight line, and each through hole H 1 and H 2 are formed. A pair of engaging piece guides G 1 , G 1 ′ (G 2 , G 2 ′), which are adjacent to the upper and lower ends of the center and face each other and are symmetrical, are attached in the front and rear directions, and each guide bracket Through holes H 1 ′ (H 2 ′) corresponding to the two through holes H 1 and H 2 are also formed at two opposite sidewalls of the fixing support 24A to which BK is attached.

또한, 중앙부에 "ㄱ"자형 걸림공(H3)이 관통형성된 상기 걸림편(23)은 상기 각 걸림편가이드(G1,G1')(G2,G2')들 사이에 조립되어 전·후방으로 이동가능한 상태가 된다.In addition, the locking piece 23 through which the "a" shaped locking hole H 3 is formed in the center portion is assembled between the respective locking piece guides G 1 , G 1 ′ (G 2 , G 2 ′). It becomes the state which can move forward and backward.

따라서, 상기 걸림편(23)들이 각 걸림편가이드(G1,G1')(G2,G2')들에 각각 조립된 고정지지대(21)의 상부 내면측에 유동지지대(22)를 넣고, 상기 걸림공(H3)과 관통공(H1)(H2) 및 통과공(H1')(H2')을 통하여 상·하부 가이드바(GB)(GB')들을 상기 유동지지대(22)의 두 측벽 상·하부에 각각 결합시킨 상태에서, 상기 걸림편(23)들을 전·후방향으로 이동시켜 각 걸림공(H3)의 수직부가 상기 관통공(H1)(H2)들과 일치하게 되면 상기 가이드바(GB)(GB')들이 관통공(H1)(H2)들을 따라 이동이 가능하여 유동지지대의 상·하 이동이 가능하게 되나 그 위치가 고정되지 않은 상태가 된다.Accordingly, the locking pieces 23 are provided with the flow support 22 on the upper inner surface side of the fixed support 21 assembled in the respective locking piece guides G 1 , G 1 ′ (G 2 , G 2 ′). The upper and lower guide bars (GB) (GB ') through the engaging hole (H 3 ), through hole (H 1 ) (H 2 ) and through hole (H 1 ') (H 2 '). In the state coupled to the upper and lower sides of the two side walls of the support 22, respectively, the engaging pieces 23 are moved in the forward and rearward directions so that the vertical portion of each locking hole H 3 is the through hole H 1 (H). 2 ) the guide bar (GB) (GB ') can be moved along the through holes (H 1 ) (H 2 ) to be able to move up and down the flow support, but the position is not fixed It is not in a state.

그리고, 상기 유동지지대(22)를 상향이동시킨 후 걸림편들을 이동시켜 상기 각 걸림공(H3)의 수직부가 상기 관통공(H1)(H2)과 일치되지 않도록 하면 가이드바들이 상기 걸림공의 수평부에 걸리게 되므로써 유동지지대는 상승된 위치에서 고정된다.In addition, the guide bars are caught when the moving support 22 is moved upward and the locking pieces are moved so that the vertical portions of the respective locking holes H 3 do not coincide with the through holes H 1 and H 2 . By being caught in the horizontal part of the ball, the flow support is fixed in the raised position.

또한, 상기 유동지지대(22)를 하강시킨 상태에서 유동지지대의 두 측판(22B) 외면에 각각 결합된 상부 가이드바(GB)들을 분리하면 상기 유동지지대(24)는 두 하부 가이드바(GB')들을 회전축으로 하여 전방하향측으로 회전가능하게 된다.In addition, when the upper support bar (GB) coupled to the outer surface of the two side plates (22B) of the flow support in the state in which the flow support 22 is lowered, the flow support (24) is the two lower guide bar (GB ') They are rotatable forward and downward with the rotation axis.

상기와 같이 구성되는 본 고안 데크지지바는 도 5에 도시된 바와 같이 굴곡이 가능한 데크지지바(3)를 결합시킨 상태로 사용하는 것이 가장 바람직한 바, 이를 살펴보면 다음과 같다.The deck support bar of the present invention configured as described above is most preferably used in a state in which the bent deck support bar 3 is coupled as shown in FIG. 5.

장척의 H-빔 한 본을 단척의 세 본으로 절단한 후 절단된 단척 H-빔들을 링크(LK)로 결합시켜 굴곡가능한 구조를 갖는 데크지지바(3)의 양 단부를 서로 대향하여 직립한 본 고안 데크지지대의 유동지지대(22) 상단면에 분리가능하게 결합시킨다.After cutting one long H-beam into three short pieces, the short H-beams are cut by a link LK, and both ends of the deck support bar 3 having a bendable structure are erected to face each other. Detachable coupling to the upper surface of the flow support 22 of the present invention deck support.

벽체(W)와 슬라브(S) 큰크리트의 양생이 완료되어 거푸집을 해체시 대향하는 두 데크지지대 상부의 각 유동지지대(22)를 상기 데크지지바(3)와 함께 하강시켜 데크지지바(3)와 슬라브측과의 사이에 공간을 형성시킨 후 각 유동지지대(22)의 상부 가이드바(GB)들을 분리하면, 상기 각 유동지지대(22)가 하부 가이드바(GB')들을 회전축으로 하여 그 상면에 결합된 데크지지바의 양측 단부와 함께 전방하향측으로 회전하면서 데크지지바 저면의 다관절의 링크가 펼쳐지면서 데크지지바(3)의 높이가 낮아져 상면에 설치된 데크(26)를 쉽게 해체할 수 있게 된다.Wall (W) and slab (S) is completed by curing the large-crete, each of the flow support 22 of the upper deck support opposite the deck support bar when dismantling the formwork bar (3) to lower the deck support bar (3) ) And the upper guide bars (GB) of each of the flow supports (22) after forming a space between the slab side and each of the flow supports (22) to the lower guide bar (GB ') as the axis of rotation Rotating forward and downward with both ends of the deck support bar coupled to the upper surface, the articulated link of the bottom of the deck support bar is extended, the height of the deck support bar (3) is lowered to easily dismantle the deck 26 installed on the upper surface It becomes possible.

그리고, 본 고안을 구성하는 상기 고정지지대의 포스트(P)와 데크지지바는 알루미늄 합금 압출재를 사용하는 것이 가장 바람직하며, 그렇게 함으로써 경량화에 의한 핸들링성과 반복사용성이 향상될 수 있다.또한, 상기와 같은 본 고안 데크지지대의 배면은 내벽거푸집의 전면과 동일 평면을 이루도록 결합되어 내벽거푸집의 역할도 수행하게 되는 바, 데크지지대의 적층구조를 살펴보면, 데크지지대-데크지지바-데크판넬의 순이 되는 바, 데크지지바의 상면은 내벽거푸집의 상단면과 동일 평면상에 위치하고, 데크의 저면이 상기 데크지지바의 상면과 내벽거푸집의 상단면에 함께 밀착되는 동시에, 벽체면에 밀착되는 내벽거푸집의 전면과 데크판넬의 일측 선단면이 동일 평면을 이루게 된다.이때, 데크지지대 상단부의 평단면에서 유동지지대가 결합되는 부위는 고정지지대의 전체 단면에 해당되지 않고 유동지지대 배면측 후방부에 유동지지대에 의해 점유되지 않는, 고정지지대의 배면과 두 측벽으로 이루어진 'ㄷ'자형 잔여 단면부가 있으며, 이 부분의 상단면은 유동지지대의 상단면보다 낮기 때문에, 유동지지대가 최고 높이에 있을 때, 고정지지대의 상기 'ㄷ'자형 잔여 단면부의 상단면으로부터 유동지지대의 상단에 놓여진 데크지지바의 상단면 사이의 벽체측에 공간이 형성되는 바, 상기 공간, 즉 고정지지대의 'ㄷ'자형 잔여 단면부 상단면에, 데크지지대의 배면폭과 내벽거푸집의 두께 및 'ㄷ'자형 잔여 단면부 상단면으로부터 데크지지바 상면까지의 길이를 갖는 별도의 거푸집판넬이 결합되어야 한다.따라서, 상기와 같은 별도의 거푸집판넬 대신, 고정지지대의 'ㄷ'자형 잔여 단면부를 상기 별도의 거푸집판넬의 높이만큼 연장형성시키는 것도 바람직하다.즉, 고정지지대 포스트에서 유동지지대의 배면 후방측 'ㄷ'자형 상단면을 내벽거푸집의 상단면 높이까지 상향 연장시키게 되면, 상기 별도의 거푸집판넬이 필요 없게 되며, 이때 고정지지대 포스트의 높이는 내벽거푸집의 높이와 같고, 최고 높이에 위치한 유동지지대의 상단면 높이에 데크지지바의 높이를 더한 것과 같게 된다.And, the post (P) and the deck support bar of the fixed support constituting the present invention is most preferably using an aluminum alloy extruded material, thereby improving handling and repeatability by weight reduction. The same back of the deck support of the present invention is combined to form the same plane as the front of the inner wall formwork to perform the role of inner wall formwork. The upper surface of the deck support bar is located on the same plane as the upper surface of the inner wall formwork, the bottom of the deck is in close contact with the upper surface of the deck support bar and the upper surface of the inner wall formwork, and at the same time the front surface of the inner wall formwork in close contact with the wall surface The end face of the deck panel and the one side of the deck panel is the same plane, at this time, the flow support is coupled in the flat section of the upper end of the deck support The part has a 'c' shaped remaining cross section consisting of the back side of the fixed support and two sidewalls, which does not correspond to the entire cross section of the fixed support and is not occupied by the flow support on the rear side of the rear side of the fixed support. Since is lower than the top surface of the flow support, when the flow support is at the highest height, the space on the side of the wall between the top surface of the deck support bar placed on the top of the flow support from the top surface of the 'c' shaped remaining cross section of the fixed support. This space is formed in the space, that is, the upper surface of the 'c' shaped remaining cross section of the fixed support, the back width of the deck support and the thickness of the inner wall formwork and the upper surface of the 'c' shaped remaining cross section from the upper surface of the deck support bar. A separate formwork panel having a length should be combined. Therefore, instead of a separate formwork panel as described above, the 'c' shaped remaining cross section of the fixing support is raised. It is also preferable to extend the height of a separate formwork panel. That is, when the rear of the back of the floating support 'c'-shaped upper surface of the fixed support post is extended upward to the height of the top surface of the inner wall formwork, the separate formwork panel In this case, the height of the fixed support post is equal to the height of the inner wall formwork, and the height of the top surface of the floating support located at the highest height is equal to the height of the deck support bar.

이상에서 살펴본 바와 같이, 본 고안의 데크지지대는 내벽거푸집의 안정성을 향상시켜주며, 이에 데크지지바를 함께 사용하므로써 데크의 설치 및 해체가 극히 쉬워질 뿐 아니라, 종래 데크를 짖지하기 위하여 많은 수가 설치되었던 지지대가 필요 없게 되어 거푸집의 설치 및 해체 시간이 현저히 감소되어 시공비으 절감이 가능하다.As discussed above, the deck support of the present invention improves the stability of the inner wall formwork, and by using the deck support bar together with the deck support bar is very easy to install and dismantle, as well as a large number was installed to bark the conventional deck Since no support is required, the installation and dismantling time of the formwork is significantly reduced, thereby reducing the construction cost.

그리고, 상기 데크지지대와 데크지지바는 금속 재질로서, 볼트-너트 등의 결합 수단으로 분리가능하게 조립되기 때문에 재활용도가 높아 초기 제작비가 상승됨에도 불구하고 충분한 경제성을 가지며, 거푸집 설치 및 해체 시간의 단축과 용이성에 의해 전체 시공비와 인건비의 감소가 가능하다.In addition, since the deck support and the deck support bar are made of metal and are detachably assembled by a coupling means such as a bolt-nut, they have sufficient economical efficiency even though the initial manufacturing cost is increased due to high recyclability. Shortening and ease of use can reduce the overall construction cost and labor cost.

Claims (4)

전체적으로 "ㄷ"자형 평단면을 하며 두 대향 측벽 상부에 일자형 통과공(H1')(H2')들이 상·하 일직선상에 형성된 바형 포스트(P)와, 이 포스트의 하단면에 부착되는 하판(L)과, 상기 포스트(P)의 두 대향 측벽 상부 외면에 부착되는 판상의 가이드브라케트(BK)로 이루어진 바형 고정지지대(21)와;The bar post (P) is formed on the upper and lower straight lines, having a "c" shaped flat cross section and formed with two straight through-holes (H 1 ') (H 2 ') on the two opposite sidewalls. A bar-shaped fixing support (21) consisting of a lower plate (L) and a plate-shaped guide bracket (BK) attached to two outer sidewall upper outer surfaces of the post (P); 다수의 관통공(h)들이 구비된 사각형상의 상판(22A)과, 상판(22A) 저면의 두 대향 단부측 전길이에 걸쳐 하향직립하여 부착되며 하부로 갈수록 폭이 감소하여 사다리꼴 형상을 하고 각 외면의 상·하부에 가이드바(GB)(GB')가 각각 분리가능하게 직립 결합되는 두 측판(22B)과, 대향하는 두 측판(22B) 내면의 후방단부측 각 중앙부에 양 선단면 전체가 각각 부착되는 사각형상의 후판(22C)과, 후판(22C) 전방의 두 측판(22B) 대향면에 상기 후판(22C)과 평행하게 양 선단면 전체가 각각 부착되는 사각형상의 전판(22D)으로 이루어져 상기 고정지지대(21)의 상부 내면에 상·하 유동가능하게 결합되는 유동지지대(22)와;A rectangular top plate 22A provided with a plurality of through holes h and two upright ends of the bottom plate 22A are attached upright, and the width decreases toward the bottom to form a trapezoidal shape. Two side plates 22B, each of which guide bars (GB) (GB ') are detachably uprightly coupled to the upper and lower portions thereof, and both front end surfaces of each of the central portions of the rear end portions of the inner surfaces of the two opposite side plates (22B), respectively. The fixed plate consists of a rectangular rear plate 22C to be attached and a rectangular front plate 22D to which both front end surfaces are respectively attached in parallel with the rear plate 22C on opposite surfaces of the two side plates 22B in front of the rear plate 22C. A flow support 22 coupled to the upper inner surface of the support 21 to be movable up and down; 상기 각 가이드브라케트(BK)의 외면에 유동가능하게 결합되어 상기 유동지지대(24B)를 이동 또는 고정시키는 역할을 하는 사각 판상의 다수 걸림편(23)으로 구성된 것을 특징으로 하는 콘크리트 슬라브 시공용 데크지지대.Concrete slab construction deck, characterized in that composed of a plurality of engaging pieces 23 of the square plate that is movably coupled to the outer surface of each guide bracket (BK) to move or fix the flow support (24B). support fixture. 제 1항에 있어서, 상기 가이드브라케트(BK)의 상·하부에는 상기 통과공(H1')(H2')들과 일치하는 관통공(H1)(H2)들이 일직선상에서 서로 이격되어 형성되며, 각 관통공(H1)(H2)을 중심으로 그 상·하 단부에 인접하면서 서로 대향하고 대칭되는 한 쌍씩의 걸림편가이드(G1,G1')(G2,G2')들이 부착된 것을 특징으로 하는 콘크리트 슬라브 시공용 데크지지대.The method of claim 1, wherein the upper and the lower part of the guide bracket (BK) the through hole (H 1) (H 2) are separated from each other in a straight line, consistent with the through hole (H 1 ') (H 2 ') is is, each through-hole forming (H 1) (H 2) to the center to the upper and the lower adjacent to the end portion while facing each other and clamping members guide of a pair of symmetric (G 1, G 1 ') (G 2, G Deck support for concrete slab construction, characterized in that the 2 ') is attached. 제 1항에 있어서, 상기 유동지지대(22)를 구성하는 각 측판(22B)의 상·하 동일측 두 내각은 90°인 사다리꼴 형상을 하고 각 외면의 상·하부에 가이드바(GB)(GB')가 각각 분리가능하게 직립 결합되는 것을 특징으로 하는 콘크리트 슬라브 시공용 데크지지대.The upper and lower sides of each side plate 22B constituting the flow support 22 have a trapezoidal shape of 90 °, and a guide bar (GB) (GB) on the upper and lower portions of each outer surface. Deck support for concrete slab construction, characterized in that ') is detachably coupled to each other. 제 1항에 있어서, 상기 각 걸림편(23)의 중앙부에는 "ㄱ"자형 걸림공(H3)이 관통형성된 것을 특징으로 하는 콘크리트 슬라브 시공용 데크지지대.The deck support for concrete slab construction according to claim 1, characterized in that the "a" shaped locking hole (H 3 ) is formed through the central portion of each engaging piece (23).
KR20-2002-0033813U 2002-11-12 2002-11-12 The supporting bar for deck panels KR200303949Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2002-0033813U KR200303949Y1 (en) 2002-11-12 2002-11-12 The supporting bar for deck panels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2002-0033813U KR200303949Y1 (en) 2002-11-12 2002-11-12 The supporting bar for deck panels

Publications (1)

Publication Number Publication Date
KR200303949Y1 true KR200303949Y1 (en) 2003-02-11

Family

ID=49400679

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2002-0033813U KR200303949Y1 (en) 2002-11-12 2002-11-12 The supporting bar for deck panels

Country Status (1)

Country Link
KR (1) KR200303949Y1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100484512B1 (en) * 2002-11-12 2005-04-20 (주)거혁건설 The constructing and dismantling method of concrete forms constructed for wall and slab
KR100484513B1 (en) * 2002-11-12 2005-04-20 (주)거혁건설 The structure of concrete forms constructed for wall and slab
KR101007538B1 (en) * 2008-04-07 2011-01-14 삼목정공주식회사 Connecting Device For Slab Wall Form
KR101029829B1 (en) 2009-05-01 2011-04-18 김시영 A supporting device for a yoke the mold

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100484512B1 (en) * 2002-11-12 2005-04-20 (주)거혁건설 The constructing and dismantling method of concrete forms constructed for wall and slab
KR100484513B1 (en) * 2002-11-12 2005-04-20 (주)거혁건설 The structure of concrete forms constructed for wall and slab
KR101007538B1 (en) * 2008-04-07 2011-01-14 삼목정공주식회사 Connecting Device For Slab Wall Form
KR101029829B1 (en) 2009-05-01 2011-04-18 김시영 A supporting device for a yoke the mold

Similar Documents

Publication Publication Date Title
KR20180045140A (en) The structure of non-binding dismantling formwork beams and deck plates without the need to secure jobs
KR100484513B1 (en) The structure of concrete forms constructed for wall and slab
KR100484512B1 (en) The constructing and dismantling method of concrete forms constructed for wall and slab
KR100750997B1 (en) The elements for concrete forms of slab crossbeam
KR200303949Y1 (en) The supporting bar for deck panels
KR100818609B1 (en) The construction structure of slab form being dismantled easily
KR200384389Y1 (en) The supporter for concrete forms of slab
KR100373783B1 (en) A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same
KR100599059B1 (en) table form estabishment apparatus for building and estabishment method thereof
KR200303775Y1 (en) The base bar for wall concrete-forms
KR100475700B1 (en) The structure of Al-forms constructed for a wall
JP6910101B1 (en) Formwork equipment for concrete structures and formwork methods for concrete structures
KR100695877B1 (en) Form with removable coner-form and method thereof
KR200375081Y1 (en) The construction structure of concrete forms
KR200303948Y1 (en) The structure of concrete forms constructed for wall and slab
KR100723542B1 (en) The supporter for concrete forms of slab
KR200292762Y1 (en) The fixers of a central supporting bar to construct Al-forms for a wall
KR200292761Y1 (en) The fixers of horizontal supporting bars to construct Al-forms for a wall
KR200213539Y1 (en) Frame of safety workbench
KR20060041382A (en) The construction structure of concrete forms
KR200380884Y1 (en) The construction structure of concrete forms for slab
KR20060041384A (en) The construction structure of concrete forms
KR200292760Y1 (en) The base bar of Al-forms for a wall
KR101078292B1 (en) Concrete slab mold assembly and method for constructing slab
KR200291526Y1 (en) The panel for concrete form

Legal Events

Date Code Title Description
N231 Notification of change of applicant
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20120202

Year of fee payment: 10

EXPY Expiration of term