KR20030065999A - A method of floor installating for warehouse - Google Patents

A method of floor installating for warehouse Download PDF

Info

Publication number
KR20030065999A
KR20030065999A KR1020020006131A KR20020006131A KR20030065999A KR 20030065999 A KR20030065999 A KR 20030065999A KR 1020020006131 A KR1020020006131 A KR 1020020006131A KR 20020006131 A KR20020006131 A KR 20020006131A KR 20030065999 A KR20030065999 A KR 20030065999A
Authority
KR
South Korea
Prior art keywords
angle
epoxy
warehouse
concrete
floor
Prior art date
Application number
KR1020020006131A
Other languages
Korean (ko)
Other versions
KR100427596B1 (en
Inventor
이강성
Original Assignee
(주)티엘코리아
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)티엘코리아 filed Critical (주)티엘코리아
Priority to KR10-2002-0006131A priority Critical patent/KR100427596B1/en
Publication of KR20030065999A publication Critical patent/KR20030065999A/en
Application granted granted Critical
Publication of KR100427596B1 publication Critical patent/KR100427596B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/10Devices for levelling, e.g. templates or boards

Abstract

PURPOSE: A construction method for the floor of a warehouse is provided to minimize the range of tolerance in leveling and to secure solidity, cleanness and economical efficiency of the floor of a warehouse. CONSTITUTION: The construction method for the floor of a warehouse comprises the steps of: after leveling up a site for a warehouse, installing a form and a steel frame on the ground and placing/curing concrete to the appointed thickness9S10); anchoring and bolting many leveling devices composed of a leg angle, a column angle and a leveling angle all over a foundation and adjusting a horizontal level of the leveling angle(S20); placing/curing concrete all over the foundation of the floor to the upper side of the leveling angle of the leveling device, and installing a guide angle for dividing up the floor into a rack section for installing a pallet rack and a passage section for moving a shift(S30); placing concrete on each rack section between guide angles installed on the leveling angle, then curing the concrete surface(S40); applying epoxy primer, epoxy coating agent and epoxy resins on the reinforcement surface of the rack section in order(S50), then finishing up the surface; and surfacing by placing mortar and lining epoxy(S60).

Description

물류창고용 바닥 시공방법{A METHOD OF FLOOR INSTALLATING FOR WAREHOUSE}A METHOD OF FLOOR INSTALLATING FOR WAREHOUSE}

본 발명은 물류창고용 바닥 시공방법에 관한 것으로서, 보다 상세하게는 물류창고의 바닥면 시공 작업시, 수평조정기구를 통하여 각 시공 단계별로 수차례 수평을 조정하여 바닥면 평탄오차 범위를 최소로 줄이며, 랙구간과 통로구간의 마무리 시공단계를 분리하여 바닥면의 견고성과 청결성 및 경제성을 동시에 확보할 수 있도록 하는 물류창고용 바닥 시공방법에 관한 것이다.The present invention relates to a floor construction method for a warehouse, and more particularly, when the floor construction of a warehouse is performed, the horizontal flatness can be adjusted several times for each construction step through a horizontal adjustment mechanism to reduce the floor flatness error range to a minimum. The present invention relates to a floor construction method for warehouses that separates the finishing construction stage between the rack section and the passage section to secure the bottom surface firmness, cleanliness, and economics at the same time.

주지하는 바와 같이, 물류창고(또는 물류 적재장고)는 공장 또는 생산지에서 대량으로 생산된 각 종 식, 음료 및 의류, 가전, 잡화 등의 일상에서 사용되는 모든 물품들을 일시 또는 장기간 적재 보관하기 위한 저장창고로서, 최근 물류산업의 급속한 발달로 인하여, 단순한 물류의 관리차원에서 벗어나 물류창고 내 보관재고의 제품배치에서부터 효율적인 입출하 및 재고관리 등의 새로운 비즈니스의 창출을 도모하는 바, 대량 생산된 물품의 보다 신속한 입출하와 더불어 물류 적재공간의 보다 효율적인 활용을 통해 대량의 물류를 보관할 수 있도록 설계, 시공되고 있다.As is well known, a warehouse (or warehouse) is a storage for temporary or long-term storage of all goods used in daily life, such as various foods, beverages and clothing, home appliances, and general merchandise, which are produced in large quantities at a factory or production site. As a warehouse, due to the recent rapid development of the logistics industry, it is not only to manage logistics, but also to create new business such as efficient shipment and inventory management from product placement of storage inventory in the warehouse. It is designed and constructed to store large quantities of logistics through faster loading and unloading and more efficient use of logistics loading space.

이러한 물류창고의 설계 및 운용은 일반적으로 일정규격의 파레트가 출납될 수 있는 폭과 높이를 갖는 파레트 랙을 각각의 통로구간으로 분할하여 수직하게 다단으로 설계하며, 상기 통로구간을 통하여 포크 리프트, 오토 크레인 또는 지게차 등을 통하여 물류가 적재된 상태의 파레트를 상기 파레트 랙에 채워 보관함으로서, 1실 1파레트 방식으로 운용된다.The design and operation of such a warehouse is generally designed in multiple stages vertically by dividing the pallet rack having a width and height into which the pallet of a certain standard can be put in and out, and forklift and auto through the passage section. By storing a pallet in a state where logistics is loaded through a crane or a forklift, etc. in the pallet rack, it is operated in a one-room one pallet system.

또한, 적재된 상태의 물류를 출항하고자 하는 경우에는 마찬가지로 포크 리프트, 오토 크레인 또는 지게차 등을 통하여 물류가 적재된 상태의 파레트를 지면 또는 운반용 차량으로 이동하는 것이다.In addition, if you want to depart the logistics of the loaded state is to move the pallet in the loaded state to the ground or transport vehicle through the forklift, auto crane or forklift.

이러한 물류창고의 설계 시, 그 바닥면의 시공에 있어서, 가장 중요한 요소는 바닥면의 평탄도(수평)를 정확하게 맞추는 것이며, 이외에도 바닥면의 견고성과 청결성을 유지하면서, 시공에 따른 경제성 또한 간과해서는 안될 중요한 요소라 할 것이다.When designing such a warehouse, the most important factor in the construction of the floor surface is to accurately match the flatness (horizontal) of the floor surface. In addition, the economical efficiency of construction is not to be overlooked while maintaining the firmness and cleanliness of the floor surface. It is an important factor that should not be.

특히, 물류창고 바닥면의 평탄도가 정확하게 설정되지 않는다면, 포크 리프트, 오토 크레인 또는 지게차 등을 통하여 파레트 랙 상에 제품이 적제된 파레트를 적재 또는 취출 작업시, 파레트 랙의 최상단으로 갈수록 파레트 랙의 적재위치와 작업장비 간의 작업위치 오차가 크게 발생하게 되어 제품의 입출하 작업이 불가능하게 되는 등의 문제점을 내포함으로, 물류창고 바닥면 시공에 있어, 평탄도의 정확성은 무엇보다 중요하다 할 것이다.In particular, if the flatness of the warehouse floor is not set correctly, when loading or taking out pallets loaded with products on the pallet racks through forklifts, auto cranes or forklifts, the pallet racks are moved to the top of the pallet racks. The accuracy of flatness is most important in the construction of warehouse floors, including problems such as large working position error between loading position and working equipment, which makes it impossible to get in and out of products. .

또한, 바닥면 시공을 위한 소재의 선택 및 시공방법의 선택은 바닥면의 견고성과 청결성 및 경제성 등이 충분히 고려되어 수요자의 요구에 충분히 부합하여야 하며, 이는 견고성과 청결성을 확보하면서도 시공비용을 절감할 수 있는 경제적인 시공방법의 선택으로 귀결될 것이다.In addition, the selection of materials and construction methods for floor construction should fully meet the demands of the users, taking into account the firmness, cleanliness, and economics of the floor, which will reduce construction costs while ensuring robustness and cleanliness. This will result in a choice of economical construction methods.

따라서, 본 발명은 상기한 바와 같은 문제점을 해결하기 위한 바닥면 평탄도의 확보와 동시에, 수요자의 요구를 충분히 고려하기 위하여 발명된 것으로서, 본 발명의 목적은 물류창고의 바닥면 시공 작업시, 수평조정기구를 통하여 각 시공 단계별로 수차례 수평을 조정하여 바닥면 평탄오차 범위를 최소로 줄이며, 랙구간과 통로구간의 마무리 시공단계를 분리하여 바닥면의 견고성과 청결성 및 경제성을 동시에 확보할 수 있도록 하는 물류창고용 바닥 시공방법을 제공하는 것이다.Therefore, the present invention was invented in order to secure the bottom flatness to solve the above problems and at the same time to fully consider the needs of the consumer, the object of the present invention is the horizontal construction of the warehouse during the construction work, By adjusting the level several times for each construction step through the adjustment mechanism, the flat surface area of the floor is reduced to the minimum, and the finishing construction stage of the rack section and the passage section can be separated to secure the bottom surface firmness, cleanliness and economic efficiency simultaneously. It is to provide a floor construction method for the warehouse.

도 1은 본 발명이 적용되는 랙형 물류창고의 내부 부분 사시도이다.1 is a perspective view of an internal portion of a rack-type logistics warehouse to which the present invention is applied.

도 2는 본 발명의 물류창고용 바닥 시공방법에 따른 단계별 시공순서를 도시한 블록도이다.Figure 2 is a block diagram showing the step-by-step construction sequence according to the floor construction method for logistics warehouse of the present invention.

도 3은 본 발명에 따른 물류창고용 바닥 시공방법에 의한 단계별 시공방법을 도시한 도면이다.3 is a view showing a step-by-step construction method by the logistics floor construction method according to the invention.

도 3A는 본 발명에 의한 기초 콘크리트 타설 단계의 단면도,3A is a cross-sectional view of the foundation concrete pouring step according to the present invention,

도 3B는 본 발명에 의한 수평 조정 기구 설치 단계의 설치 사시도,3B is an installation perspective view of the horizontal adjustment mechanism installation step according to the present invention;

도 3C는 본 발명에 의한 기준 바닥면 콘크리트 타설 단계의 단면도,3C is a cross-sectional view of the reference floor concrete pouring step according to the present invention,

도 3D는 본 발명에 의한 랙구간 보강 콘크리트 타설 단계의 단면도,3D is a cross-sectional view of the reinforcement concrete pouring step of the rack section according to the present invention;

도 3E는 본 발명에 의한 랙구간 마무리 시공 단계의 단면도,Figure 3E is a cross-sectional view of the rack section finishing construction step according to the present invention,

도 3F는 본 발명에 의한 랙 통로구간 마무리 시공 단계의 단면도이다.3F is a cross-sectional view of the rack passage section finishing construction step according to the present invention.

도 4는 도 3E의 A부분의 일실시예에 의한 확대 단면도이다.4 is an enlarged cross-sectional view of an embodiment of portion A of FIG. 3E.

도 5는 도 3F의 B부분의 일실시예에 의한 확대 단면도이다.FIG. 5 is an enlarged cross-sectional view of an embodiment B of FIG. 3F.

상기의 목적을 실현하기 위한 본 발명에 따른 물류창고용 바닥 시공방법은,Logistics floor construction method according to the present invention for realizing the above object,

물류창고 부지의 정지(整地)작업 후, 지면에 거푸집과 철골을 설치하여 콘크리트를 소정의 두께까지 타설, 양생시키는 기초면 콘크리트 타설 단계와;After the work of the logistic warehouse site, the foundation surface concrete placing step of placing and curing the concrete to a predetermined thickness by installing the formwork and steel frame on the ground;

다리앵글과 기둥앵글 및 레벨조정앵글로 이루어지는 다수개의 수평조정기구를 상기 기초면 전체에 걸쳐 일정간격으로 앵커링 및 볼팅하여 설치함과 동시에, 상기 레벨조정앵글의 수평레벨을 조정하는 수평조정기구 설치 단계와;A step of installing a horizontal adjustment mechanism for anchoring and bolting a plurality of horizontal adjustment mechanism consisting of a leg angle, a column angle and a level adjustment angle at regular intervals throughout the base surface, and at the same time adjust the horizontal level of the level adjustment angle Wow;

상기 수평조정기구 설치 단계에서 설치된 수평조정기구의 레벨조정앵글의 상면까지, 창고 바닥의 기초면 전체에 걸쳐 콘크리트를 타설하여 양생시킨 후, 창고 바닥면 상에 파레트 랙을 설치하기 위한 랙구간과, 이동수단의 이동을 위한 통로구간을 분할하기 위한 가이드 앵글을 상기 레벨조정앵글의 상면에 설정된 간격으로 설치하는 기준면 콘크리트 타설 단계와;A rack section for installing a pallet rack on the floor of the warehouse after the concrete is laid and cured to the upper surface of the level adjustment angle of the leveling mechanism installed in the leveling mechanism installation step; A reference surface concrete placing step of installing a guide angle for dividing a passage section for moving the moving means at a predetermined interval on an upper surface of the level adjustment angle;

상기 레벨조정앵글 상에 레벨조정된 상태로 설치된 가이드 앵글 사이사이의 각 랙구간에만 다시 콘크리트를 타설하여 양생시키는 랙구간 보강 콘크리트 타설 단계와;A step of reinforcing concrete placing the rack section to cast and cure concrete only in each rack section between the guide angles installed in the level adjusting state on the level adjusting angle;

상기 랙구간 보강 표면에 에폭시 프라이머, 에폭시 코팅제 및 에폭시 수지제를 순차적으로 도포하는 에폭시 코팅시공을 통하여 표면을 마무리 처리하는 랙구간 마무리 시공 단계와;A rack section finishing construction step of finishing the surface through an epoxy coating construction in which an epoxy primer, an epoxy coating agent, and an epoxy resin are sequentially applied to the rack section reinforcing surface;

상기 통로구간 기준면의 표면에 소재 자체의 흐름성을 이용하여 수평레벨을맞추는 모르타르 작업 및 에폭시 라이닝 시공을 통하여 표면을 처리하는 통로구간 마무리 시공 단계를 포함하는 것을 특징으로 하며,It characterized in that it comprises a passage section finishing construction step of treating the surface through the mortar work and epoxy lining construction to match the horizontal level using the flow of the material itself on the surface of the passage section reference surface,

상기 수평조정기구는 L형 앵글로 이루어져 기초면 전체에 걸쳐 각각 일정간격으로 앵커볼트를 통하여 체결하여 고정되는 다리앵글과; L형으로 이루어지며, 일측면에는 길이방향으로 슬롯을 형성하여 상기 다리앵글 상의 일측면으로 수직방향으로 세워서 볼트 체결되는 기둥앵글 및 L형으로 이루어지며, 적어도 2개 이상의 상기 기둥앵글을 연결하여 각 슬롯을 통하여 볼트 체결되며, 상기 슬롯을 따라 수평레벨의 조정이 가능하도록 구성되는 레벨조정앵글로 이루어지는 것을 특징으로 하며,The horizontal adjustment mechanism is made of an L-shaped angle and the leg angle is fixed by fastening through the anchor bolt at regular intervals over the entire base surface; It is made of L-shaped, and formed in the longitudinal direction slots on one side of the vertical angle to the one side on the leg angle is made of a pillar angle and L-shaped bolts, by connecting at least two or more pillar angles Bolted through the slot, characterized in that consisting of the level adjustment angle is configured to enable the adjustment of the horizontal level along the slot,

상기 기준면 콘크리트 타설 단계의 상기 가이드 앵글의 수평레벨 조정은, 레벨 게이지를 통하여 검출된 오차만큼, 레벨조정앵글과의 사이에 라이너(LINER)를 개재하여 조정함으로서 이루어지는 것을 특징으로 하고,The horizontal level adjustment of the guide angle of the reference surface concrete placing step is made by adjusting a liner between the level adjusting angles by an error detected through the level gauge,

상기 에폭시 코팅시공은 랙구간 콘트리트 보강 표면에 대하여, 먼저, 레이턴스(laitance) 또는 유분 등을 갈아내는 하지작업과; 표면 크랙 부위를 V 컷팅한 후, 에폭시 실링제를 발라 평활하게 하는 표면보수작업과; 에폭시 프라이머의 주제와 경화제를 약 4:1로 혼합한 후, 소정량을 롤라로 균일하게 도포하는 하도; 에폭시 코팅제를 균일하게 혼합하여 규정 도포량을 롤라 또는 붓으로 평활하게 도포하는 중도; 및 에폭시 수지제를 균일하게 혼합하여 규정 도포량을 롤라 또는 붓으로 평활하게 도포하는 상도로 이루어지는 것을 특징으로 하며,The epoxy coating is a ground work for grinding the surface area of the reinforcing concrete section, the first (latency) or oil; A surface repair operation of V-cutting the surface crack area and then applying an epoxy sealant to smooth the surface; After mixing the main ingredient of the epoxy primer and the curing agent at about 4: 1, the predetermined amount is evenly applied with a roll; The epoxy coating is evenly mixed to smoothly apply a prescribed coating amount with a roll or a brush; And by mixing the epoxy resin uniformly, characterized in that consisting of a top coat to smoothly apply the prescribed coating amount with a roll or a brush,

상기 통로구간 마무리 시공 단계는 통로구간 기준면의 콘크리트 양생시 표면에 생성되는 레이턴스(laitance) 또는 유분 등을 갈아내는 하지작업과; 기준면 표면 크랙이나, 기포발생을 방지하기 위하여 프라이머를 균일하게 도포하는 프라이머 작업과; 시멘트재에 수지 및 무기질을 첨가하여 기준면에 고르게 흘려 자체의 흐름성 및 평활성에 의해 수평레벨 조정작용이 이루어지도록 하는 모르타르(MORTAR)작업; 및 에폭시 프라이머, 에폭시 라이닝제 및 에폭시 무용제를 순차적으로 각 주제와 경화제를 약 4:1로 균일하게 혼합하여 소정 도포량을 롤라 또는 붓으로 평활하게 도포한 후, 양생시키는 에폭시 라이닝 작업을 포함하여 이루어지는 것을 특징으로 한다.The finishing step of the passage section is a ground work to grind the latent (laitance) or oil generated on the surface during the concrete curing of the passage section reference plane; Primer work for uniform application of primer to prevent reference surface surface cracking and foaming; Mortar (MORTAR) operation to add a resin and inorganic to the cement material to flow evenly on the reference surface to achieve a horizontal level adjustment action by its flowability and smoothness; And an epoxy lining operation in which an epoxy primer, an epoxy lining agent, and an epoxy solvent are sequentially mixed with each other and a curing agent at about 4: 1 to uniformly apply a predetermined amount with a roll or brush, and then cured. It features.

이하, 상기의 목적을 구체적으로 실현할 수 있는 본 발명의 바람직한 실시예를 첨부한 도면에 의거하여 상세히 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings, preferred embodiments of the present invention that can specifically realize the above object will be described in detail.

도 1은 본 발명이 적용되는 랙형 물류창고의 내부 부분 사시도이고, 도 2는 본 발명의 물류창고용 바닥 시공방법에 따른 단계별 시공순서를 도시한 블록도로서, 먼저, 본 발명이 적용되는 랙형 물류창고(1)의 바닥면(3)은, 상기 도 1에서와 같이, 파래트 랙(5)이 설치되는 랙구간(7)과, 이와 단차지게 형성되어 포크 리프트 또는 지게차(9) 등의 이동을 위한 통로구간(11)으로 나누어진다.1 is a perspective view of an internal part of a rack-type logistics warehouse to which the present invention is applied, and FIG. 2 is a block diagram showing a step-by-step construction sequence according to the floor construction method for the warehouse according to the present invention. First, the rack-type logistics warehouse to which the present invention is applied As shown in FIG. 1, the bottom surface 3 of the warehouse 1 includes a rack section 7 in which the pallet rack 5 is installed, and is stepped to move the forklift or the forklift 9. It is divided into a passage section 11 for.

여기서, 상기 랙구간(7)에는 일정규격의 파레트(미도시)가 출납될 수 있는 폭과 높이를 갖는 다수개의 파레트 랙(5)이 일정간격으로 수직하게 다단으로 설치되며, 상기 파레트 랙(5) 사이사이에는 소정의 간격으로 통로구간(11)을 확보하여 이루어진다.Here, the rack section 7 is provided with a plurality of pallet racks (5) having a width and height in which a pallet (not shown) of a predetermined standard can be put in and out at a predetermined interval vertically, and the pallet rack (5) The passage section 11 is secured at predetermined intervals between the gaps).

이러한 물류창고(1)의 설계 시, 그 바닥면(3)의 시공에 있어서, 가장 중요한요소인 바닥면(3)의 평탄도(수평)와 함께, 견고성과 청결성을 유지하면서, 시공에 따른 경제성을 고려한 본 발명에 따른 물류창고용 바닥 시공방법은, 상기 도 2에서와 같이, 크게 기초면 콘크리트 타설 단계(S10), 수평조정기구 설치 단계(S20), 기준면 콘크리트 타설 단계(S30), 랙구간 보강 콘크리트 타설 단계(S40), 랙구간 마무리 시공 단계(S50) 및 통로구간 마무리 시공 단계(S60)의 6단계로 나누어진다.In the design of the warehouse 1, in the construction of the bottom 3, with the flatness (horizontal) of the bottom 3, which is the most important factor, while maintaining the firmness and cleanliness, the economical efficiency of the construction Floor construction method for the warehouse according to the present invention in consideration of, as shown in Figure 2, the base surface concrete placing step (S10), horizontal adjustment mechanism installation step (S20), the reference surface concrete placing step (S30), rack section Reinforced concrete pouring step (S40), rack section finishing construction step (S50) and passage section finishing construction step (S60) is divided into six stages.

먼저, 기초면 콘크리트 타설 단계(S10)는, 도 3A에서와 같이, 물류창고 부지를 건설장비 등을 이용하여 부지 정지(整地)작업을 한 후, 지면(21)에 대하여 거푸집(23)과 철골(25)을 그대로 설치하는 등의 토목작업 후, 이에 콘크리트를 소정의 두께까지 타설하여 양생시킴으로서 기초면(20)을 이룬다.First, the base surface concrete placing step (S10), as shown in FIG. 3A, after the site stop operation using the construction equipment, such as the warehouse, the formwork 23 and steel frame with respect to the ground (21) After the civil works, such as installing (25) as it is, the foundation surface 20 is formed by casting concrete to a predetermined thickness and curing it.

이러한 기초면 콘크리트 타설 단계(S10)에 의하여 콘크리트가 완전히 양생되면, 상기 기초면(20)에 대하여, 상기 수평조정기구 설치 단계(S20)를 수행하게 되는데, 이 수평조정기구 설치 단계(S20)는, 도 3B에서 도시한 바와 같이, 다리앵글(31)과 기둥앵글(33) 및 레벨조정앵글(35)로 이루어지는 수평조정기구를 상기 기초면(20) 상에 일정간격으로 앵커링 및 볼팅하여 설치하게 되는 것이다.When the concrete is completely cured by the foundation concrete placing step (S10), to perform the horizontal adjustment mechanism installation step (S20) for the foundation surface 20, this horizontal adjustment mechanism installation step (S20) 3B, the horizontal adjustment mechanism consisting of the leg angle 31, the pillar angle 33 and the level adjustment angle 35 is anchored and bolted to the base surface 20 at a predetermined interval to be installed. Will be.

즉, 먼저, L형 앵글로 이루어지는 다수개의 다리앵글(31)을 기초면(20) 전체에 걸쳐 각각 일정간격으로 앵커볼트(39)를 통하여 체결하여 고정하고, 상기 각각의 다리앵글(31)에는 그 일측면으로 L형으로 이루어지는 기둥앵글(33)을 수직방향으로 세워서 각각 볼트(41) 체결하여 고정한다.That is, first, a plurality of leg angles 31 formed of L-shaped angles are fastened and fixed through anchor bolts 39 at regular intervals over the entire base surface 20, respectively, and in each of the leg angles 31. The pillar angle 33 made of an L shape is erected in the vertical direction on one side thereof and fastened to each other by fastening the bolts 41.

여기서, 상기 각각의 기둥앵글(33)에는 그 일면에 수직방향으로 슬롯(37)이 형성되며, 이 슬롯(37)을 통하여 상기 L형의 레벨조정앵글(35)이 볼트 체결되는데,하나의 레벨조정앵글(35)은 2개 혹은 그 이상의 기둥앵글(33)을 통하여 상기 기초면(20)에 대하여 소정간격 이격된 상태로 지지된다.Here, each pillar angle 33 is formed with a slot 37 in a vertical direction on one surface thereof, through which the L-level level adjustment angle 35 is bolted, one level The adjustment angle 35 is supported at a predetermined interval from the base surface 20 through two or more pillar angles 33.

또한, 상기 레벨조정앵글(35)을 각 기둥앵글(33)에 볼트 체결할 때에는 건설용 레벨 게이지(미도시) 등을 이용하여 각각의 수평레벨을 상기 슬롯(37)을 따라 조정하며, 전체 레벨의 오차범위를 약 ±2mm 이내의 범위에서 맞추는 것이 중요하며, 전체적으로 레벨의 오차범위가 허용범위에 들어오면, 상기 레벨조정앵글(35)과 기둥앵글(33)은 그 연결부에서 상호 용접처리하여 고정하게 된다.In addition, when bolting the level adjustment angle 35 to each column angle 33, the level of each level is adjusted along the slot 37 by using a level gauge (not shown) for construction, etc. It is important to fit the error range within about ± 2mm, and when the error range of the level is within the allowable range as a whole, the level adjustment angle 35 and the pillar angle 33 are fixed by welding at the connection part. Done.

이 때, 상기 각 레벨조정앵글(35)은 상호간의 간격을 3M 이내로 하여 설치하게 되는데, 레벨조정앵글(35) 간의 간격이 너무 넓을 경우에는 다음 단계에서의 콘크리트 타설 시, 콘크리트 꺼짐 등에 의해 수평조정이 어려운 문제점이 있기 때문이다.At this time, the level adjustment angles 35 are installed to each other within 3M intervals, when the distance between the level adjustment angles 35 is too wide, when the concrete in the next step, when the concrete leveling, etc. This is because there are difficult problems.

이와 같은 수평조정기구 설치 단계(S20)에 기초면(20) 상에 수평조정기구의 설치가 완료되면, 상기한 기준면 콘크리트 타설 단계(S30)가 이루어진다.When the installation of the horizontal adjustment mechanism is completed on the base surface 20 in the horizontal adjustment mechanism installation step (S20), the reference surface concrete placing step (S30) is made.

상기 기준면 콘크리트 타설 단계(S30)에서는, 도 3C에서와 같이, 상기 수평조정기구 설치 단계(S20)에서 설치된 수평조정기구의 레벨조정앵글(35)의 상면(T)까지, 창고 바닥의 기초면(20) 전체에 걸쳐 콘크리트를 타설하여 양생시킴으로 기준면(30)을 형성하게 된다.In the reference concrete placing step (S30), as shown in Figure 3C, up to the upper surface (T) of the level adjustment angle 35 of the leveling mechanism installed in the leveling mechanism installation step (S20), the base surface of the warehouse floor ( 20) by placing concrete throughout the curing to form the reference plane (30).

이 때, 기준면(30)의 수평레벨은 상기 레벨조정앵글(35)의 상면(T)을 기준으로 정확하게 조정할 수 있는 잇점이 있다.At this time, the horizontal level of the reference plane 30 has the advantage that can be accurately adjusted based on the upper surface (T) of the level adjustment angle (35).

이러한 기준면 콘크리트 타설 단계(S30)에 의해 기준면(30)의 콘크리트가 완전히 양생되면, 창고 바닥면(3) 상에 파레트 랙(5)을 설치하기 위한 랙구간(7)과, 포크 리프트, 또는 지게차(9) 등의 이동을 위한 통로구간(11)을 분할하기 위한 가이드 앵글(43)을 상기 레벨조정앵글(35)의 상면(T)에 설정된 간격으로 설치하여, 도 3D에서와 같이, 랙구간 보강 콘크리트 타설 단계(S40)를 진행하게 된다.When the concrete of the reference surface 30 is completely cured by the reference surface concrete placing step S30, the rack section 7 for installing the pallet rack 5 on the warehouse floor surface 3, a forklift or a forklift truck. (9) and the guide angle 43 for dividing the passage section 11 for the movement of the back and the like at the interval set on the upper surface (T) of the level adjustment angle 35, as shown in Figure 3D, rack section The reinforcement concrete pouring step (S40) is to proceed.

이 때, 상기 가이드 앵글(43)의 수평레벨 조정은, 상기 도 3D에서 도시한 바와 같이, 건설용 레벨 게이지(미도시)를 통하여 검출된 오차만큼, 레벨조정앵글과의 사이에 라이너(45; LINER)를 여러장 개재하여 조정함으로서 바닥면 평탄도를 더욱 정확하게 맞추게 된다.At this time, the horizontal level adjustment of the guide angle 43, as shown in Figure 3D, by the error detected through the level gauge (not shown) for construction, the liner 45 between the level adjustment angle; By adjusting the LINER) through several sheets, the flatness of the floor can be more accurately adjusted.

그리고 랙구간 보강 콘크리트 타설 단계(S40)에서는, 상기한 바와 같이, 레벨조정앵글(35) 상에 레벨조정된 상태로 설치된 가이드 앵글(43) 사이사이의 각 랙구간(7)에만 다시 콘크리트를 타설하여 양생시킴으로서 보강면(40)을 이루게 된다.And in the rack section reinforcement concrete placing step (S40), as described above, the concrete is placed again only in each rack section 7 between the guide angles 43 installed in the level adjustment state on the level adjustment angle (35). By curing the reinforcement surface 40 is achieved.

이와 같이, 랙구간 보강 콘크리트 타설 단계(S40)까지 완료하게 되면, 상기 랙구간(7)과 통로구간(11)은 각각 바닥표면의 정밀한 수평 평탄도를 확보하기 위한 마무리 시공을 하게되는데, 먼저 랙구간 마무리 시공 단계(S50)에서는, 도 3E와 도 4에서 도시한 바와 같이, 랙구간 보강면에 에폭시 코팅시공(A)을 통하여 처리하게 되는데, 그 구체적인 작업순서는, 상기 도 4에서와 같이, 먼저, 콘크리트 양생시 표면에 생성되는 레이턴스(laitance) 또는 유분 등을 하지작업(W1)을 통하여 갈아내어 접착력을 강화시키고, 다음으로 표면 크랙 부위는 V 컷팅한 후, 에폭시 실링제를 발라 평활하게 보수한다(W2).As such, when the rack section reinforcement concrete placing step (S40) is completed, the rack section (7) and the passage section (11) is a finishing construction to ensure precise horizontal flatness of the bottom surface, respectively, first rack In the section finishing construction step (S50), as shown in Figure 3E and Figure 4, through the epoxy coating construction (A) on the reinforcement surface of the rack section, the specific work order, as shown in FIG. First, when the concrete is cured, the latent (laitance) or oil generated on the surface is ground through the ground work (W1) to strengthen the adhesive force, and then the surface crack area is V-cut, and then the epoxy sealant is applied smoothly. Repair (W2).

그 다음에는 하도(W3), 중도(W4), 상도(W5)과정을 통하여 표면을 처리하게되는데, 하도(W3)에서는, 에폭시 프라이머의 주제와 경화제를 약 4:1로 혼합한 후, 소정량(약 0.3Kg)을 롤라로 균일하게 도포하며, 중도(W4)에서는 에폭시 코팅제를 균일하게 혼합하여 규정 도포량을 롤라 또는 붓으로 평활하게 도포하며, 상도(W5)에서는 에폭시 수지제를 균일하게 혼합하여 규정 도포량을 롤라 또는 붓으로 평활하게 도포하여 이루어진다.Then, the surface is treated through the process of undercoat (W3), midway (W4), and top coat (W5). In undercoat (W3), after mixing the main agent of the epoxy primer and the curing agent at about 4: 1, (Approximately 0.3Kg) is applied evenly with a roll, and in the middle (W4), the epoxy coating agent is uniformly mixed, and the prescribed coating amount is evenly applied with a roll or a brush, and in the top coat (W5), the epoxy resin agent is uniformly mixed. It is made by applying a prescribed coating amount smoothly with a roll or a brush.

그리고 상기 통로구간 마무리 시공 단계(S60)는 , 도 3F와 도 5에서 도시한 바와 같이, 상기 통로구간 기준면(30)의 표면에 모르타르 및 라이닝 시공을 통하여 처리하게 되는데, 그 구체적인 작업순서는, 상기 도 5에서와 같이, 먼저, 콘크리트 양생시 표면에 생성되는 레이턴스(laitance) 또는 유분 등을 하지작업(W10)을 통하여 갈아내어 접착력을 강화시키고, 그 다음으로 표면 크랙이나 기포발생을 방지하기 위하여 프라이머를 균일하게 도포하는 프라이머 작업(W20)을 수행하게 된다.And the passage section finishing construction step (S60), as shown in Figure 3F and 5, will be processed through the mortar and lining construction on the surface of the passage section reference surface 30, the specific work order, the As shown in FIG. 5, first, the latent (laitance) or oil generated on the surface during concrete curing is ground through the lower work (W10) to strengthen the adhesive force, and then to prevent the occurrence of surface cracks or bubbles. A primer operation (W20) of uniformly applying the primer is performed.

이러한 하지작업(W10) 및 프라이머 작업(W20)이 원활하게 진행되지 않을 경우에는 하지 및 프라이머 작업을 각각 2차에 걸쳐 진행할 수 있으며, 이 때, 2차 하지작업시(W11)에는 세척, 보강 및 실링 등의 작업을 병행하며, 프라이머 작업(W20,W21)은 1차시(W20)에 침투성 프라이머를, 2차시에(W21)는 접착성 프라이머를 구분하여 도포하는 것이 바람직하다.If the lower leg work (W10) and the primer work (W20) does not proceed smoothly, the lower leg and primer work can be carried out in each of the second, at this time, during the second lower work (W11), washing, reinforcement and It is preferable to apply a sealant or the like in combination with the primer work (W20, W21) for the permeable primer at the first time (W20), and the adhesive primer at the second time (W21).

이와 같이, 하지작업(W10) 및 프라이머 작업(W20)을 통하여 표면작업이 완료되면, 모르타르(MORTAR)작업(W30)을 진행하는데, 이 모르타르작업(W30)은 시멘트재에 수지 및 무기질을 첨가하여 평활성과 흐름성이 우수하도록 하여 바닥면에 고르게 흘려 자체의 흐름성 및 평활성에 의해 수평이 맞추어지도록 하여 이루어진다.As such, when the surface work is completed through the ground work W10 and the primer work W20, the mortar work W30 is performed, and the mortar work W30 is performed by adding resin and inorganic material to the cement material. It is made to be leveled by its flowability and smoothness by flowing evenly on the bottom surface to make the smoothness and flowability excellent.

상기 모르타르가 양생된 후에는, 에폭시 라이닝 작업(W40)을 진행하게 되는데, 이 에폭시 라이닝 작업 또한, 상기 에폭시 코팅 작업과 마찬가지로 하도, 중도, 상도과정을 통하여 표면을 처리하게 된다.After the mortar is cured, an epoxy lining operation (W40) is performed, and the epoxy lining operation is also treated with a surface through a process of middle, top, and topcoat similarly to the epoxy coating.

이러한 에폭시 라이닝 작업(W40)의 하도에서는, 에폭시 프라이머의 주제와 경화제를 약 4:1로 혼합한 후, 소정량(약 0.3Kg)을 롤라로 균일하게 도포하되, 수지분의 광택이 나는 정도로 도포한다.In the underlining of such epoxy lining operation (W40), after mixing the main material of the epoxy primer and the curing agent at about 4: 1, a predetermined amount (about 0.3Kg) is uniformly applied with a roll, but applied to the degree of gloss of the resin powder. do.

중도에서는 에폭시 라이닝제의 주제와 경화제를 약 4:1로 균일하게 혼합하여 소정 도포량(약 3.6Kg)을 롤라 또는 붓으로 평활하게 도포하며, 상도에서는 에폭시 무용제의 주제와 경화제를 약 4:1로 균일하게 혼합하여 소정 도포량(약 2.4Kg)을 롤라 또는 붓으로 평활하게 도포한 후, 적어도 48시간이상 양생하여 이루어진다.In the middle, the main body of the epoxy lining agent and the curing agent are uniformly mixed at about 4: 1, and a predetermined amount of coating (approximately 3.6Kg) is smoothly applied with a roll or a brush. After uniformly mixing, a predetermined coating amount (approximately 2.4 Kg) is smoothly applied with a roll or a brush, and then cured for at least 48 hours.

따라서 상기한 바와 같은 본 발명의 물류창고용 바닥 시공방법에 의하면, 6단계의 단계별 시공작업(S10,S20,S30,S40,S50,S60) 중에서, 최초 레벨조정앵글(35) 및 가이드 앵글(43)의 설치시와, 모르타르 작업(W30) 등에서 다수회의 수평레벌 조정작업 및 모르타르의 흐름성을 이용한 자동수평 조정작용에 의해 물류창고의 바닥면(3)의 평탄도를 더욱 정확하고 정밀하게 맞출 수 있으며, 수평조정기구를 이용하여 통로구간(11) 등의 불필요한 부분의 콘크리트 타설을 배제할 수 있도록 함으로서, 경제성이 우수한 것이다.Therefore, according to the logistic floor construction method of the present invention as described above, among the six stages of construction work (S10, S20, S30, S40, S50, S60), the first level adjustment angle 35 and guide angle 43 ), The flatness of the bottom 3 of the warehouse can be adjusted more precisely and precisely by multiple horizontal level adjustments in the mortar work (W30) and automatic horizontal adjustment action using the flow of mortar. In addition, by using the horizontal adjustment mechanism to be able to exclude the concrete placing of unnecessary parts such as the passage section 11, it is excellent in economic efficiency.

또한, 가이드 앵글(43)을 통하여 바닥면(3)의 랙구간(7)과 통로구간(11)의 경계를 더욱 견고하게 유지할 수 있도록 하며, 통로구간(11)의 최상위 표면을 청결성이 우수한 에폭시 라이닝 작업(W40)을 통하여 처리함으로서, 물류창고 내부의 쾌적한 작업환경을 제공할 수 있는 효과가 있는 것이다.In addition, through the guide angle 43, it is possible to more securely maintain the boundary between the rack section 7 and the passage section 11 of the bottom surface 3, and the top surface of the passage section 11 is epoxy with excellent cleanliness. By processing through the lining operation (W40), there is an effect that can provide a comfortable working environment inside the warehouse.

이상에서와 같이, 본 발명의 물류창고용 바닥 시공방법에 의하면, 수평조정기구를 통하여 각 시공 단계별로 수차례 수평레벨을 정밀하게 조정하여 바닥면 평탄오차 범위를 최소로 줄이며, 랙구간과 통로구간의 마무리 시공단계를 분리하여 바닥면의 견고성과 청결성 및 경제성을 동시에 확보하는 물류창고의 바닥면을 제공할 수 있다.As described above, according to the logistics floor construction method of the present invention, by horizontally adjusting the horizontal level several times for each construction step through the horizontal adjustment mechanism to reduce the floor flat surface error range to a minimum, rack section and passage section By separating the finishing construction stage, it is possible to provide the floor surface of the warehouse which secures the firmness, cleanliness and economical efficiency of the floor.

Claims (5)

물류창고용 바닥 시공방법에 있어서,In the floor construction method for logistics warehouse, 물류창고 부지의 정지(整地)작업 후, 지면에 거푸집과 철골을 설치하여 콘크리트를 소정의 두께까지 타설, 양생시키는 기초면 콘크리트 타설 단계와;After the work of the logistic warehouse site, the foundation surface concrete placing step of placing and curing the concrete to a predetermined thickness by installing the formwork and steel frame on the ground; 다리앵글과 기둥앵글 및 레벨조정앵글로 이루어지는 다수개의 수평조정기구를 상기 기초면 전체에 걸쳐 일정간격으로 앵커링 및 볼팅하여 설치함과 동시에, 상기 레벨조정앵글의 수평레벨을 조정하는 수평조정기구 설치 단계와;A step of installing a horizontal adjustment mechanism for anchoring and bolting a plurality of horizontal adjustment mechanism consisting of a leg angle, a column angle and a level adjustment angle at regular intervals throughout the base surface, and at the same time adjust the horizontal level of the level adjustment angle Wow; 상기 수평조정기구 설치 단계에서 설치된 수평조정기구의 레벨조정앵글의 상면까지, 창고 바닥의 기초면 전체에 걸쳐 콘크리트를 타설하여 양생시킨 후, 창고 바닥면 상에 파레트 랙을 설치하기 위한 랙구간과, 이동수단의 이동을 위한 통로구간을 분할하기 위한 가이드 앵글을 상기 레벨조정앵글의 상면에 설정된 간격으로 설치하는 기준면 콘크리트 타설 단계와;A rack section for installing a pallet rack on the floor of the warehouse after the concrete is laid and cured to the upper surface of the level adjustment angle of the leveling mechanism installed in the leveling mechanism installation step; A reference surface concrete placing step of installing a guide angle for dividing a passage section for moving the moving means at a predetermined interval on an upper surface of the level adjustment angle; 상기 레벨조정앵글 상에 레벨조정된 상태로 설치된 가이드 앵글 사이사이의 각 랙구간에만 다시 콘크리트를 타설하여 양생시키는 랙구간 보강 콘크리트 타설 단계와;A step of reinforcing concrete placing the rack section to cast and cure concrete only in each rack section between the guide angles installed in the level adjusting state on the level adjusting angle; 상기 랙구간 보강 표면에 에폭시 프라이머, 에폭시 코팅제 및 에폭시 수지제를 순차적으로 도포하는 에폭시 코팅시공을 통하여 표면을 마무리 처리하는 랙구간 마무리 시공 단계와;A rack section finishing construction step of finishing the surface through an epoxy coating construction in which an epoxy primer, an epoxy coating agent, and an epoxy resin are sequentially applied to the rack section reinforcing surface; 상기 통로구간 기준면의 표면에 소재 자체의 흐름성을 이용하여 수평레벨을맞추는 모르타르 작업 및 에폭시 라이닝 시공을 통하여 표면을 처리하는 통로구간 마무리 시공 단계와;A passage section finishing construction step of treating the surface through mortar work and epoxy lining to adjust the horizontal level by using the flow of the material itself on the surface of the passage section reference plane; 를 포함하는 것을 특징으로 하는 물류창고용 바닥 시공방법.Floor construction method for the warehouse, characterized in that it comprises a. 제1항에 있어서, 상기 수평조정기구는The method of claim 1, wherein the horizontal adjustment mechanism L형 앵글로 이루어져 기초면 전체에 걸쳐 각각 일정간격으로 앵커볼트를 통하여 체결하여 고정되는 다리앵글과;A leg angle consisting of an L-shaped angle and fastened through anchor bolts at predetermined intervals over the entire base surface; L형으로 이루어지며, 일측면에는 길이방향으로 슬롯을 형성하여 상기 다리앵글 상의 일측면으로 수직방향으로 세워서 볼트 체결되는 기둥앵글과;It is made of L-shaped, the side angle and the slot angle to form a slot in the longitudinal direction and bolted to stand in a vertical direction to one side on the leg angle; L형으로 이루어지며, 적어도 2개 이상의 상기 기둥앵글을 연결하여 각 슬롯을 통하여 볼트 체결되며, 상기 슬롯을 따라 수평레벨의 조정이 가능하도록 구성되는 레벨조정앵글로 이루어지는 것을 특징으로 하는 물류창고용 바닥 시공방법.L-shaped, the bottom of the warehouse for connecting the at least two pillar angles are bolted through each slot, consisting of a level adjustment angle configured to adjust the horizontal level along the slot Construction method. 제1항에 있어서, 상기 기준면 콘크리트 타설 단계의 상기 가이드 앵글의 수평레벨 조정은, 레벨 게이지를 통하여 검출된 오차만큼, 레벨조정앵글과의 사이에 라이너(LINER)를 개재하여 조정함으로서 이루어지는 것을 특징으로 하는 물류창고용 바닥 시공방법.The horizontal level adjustment of the guide angle in the reference surface concrete placing step is performed by adjusting a liner between the level adjusting angles by an error detected through the level gauge. Logistics floor construction method. 제1항에 있어서, 상기 에폭시 코팅시공은The method of claim 1, wherein the epoxy coating 랙구간 콘트리트 보강 표면에 대하여, 먼저, 레이턴스(laitance) 또는 유분등을 갈아내는 하지작업과;For the rack section concrete reinforcement surface, first, a ground work for grinding a lattance or oil; 표면 크랙 부위를 V 컷팅한 후, 에폭시 실링제를 발라 평활하게 하는 표면보수작업과;A surface repair operation of V-cutting the surface crack area and then applying an epoxy sealant to smooth the surface; 에폭시 프라이머의 주제와 경화제를 약 4:1로 혼합한 후, 소정량을 롤라로 균일하게 도포하는 하도;After mixing the main ingredient of the epoxy primer and the curing agent at about 4: 1, the predetermined amount is evenly applied with a roll; 에폭시 코팅제를 균일하게 혼합하여 규정 도포량을 롤라 또는 붓으로 평활하게 도포하는 중도; 및The epoxy coating is evenly mixed to smoothly apply a prescribed coating amount with a roll or a brush; And 에폭시 수지제를 균일하게 혼합하여 규정 도포량을 롤라 또는 붓으로 평활하게 도포하는 상도로 이루어지는 것을 특징으로 하는 물류창고용 바닥 시공방법.A floor construction method for a distribution warehouse, characterized in that the epoxy resin is uniformly mixed to form a top coat that applies a prescribed coating amount smoothly with a roll or a brush. 제1항에 있어서, 상기 통로구간 마무리 시공 단계는According to claim 1, The passage section finishing construction step 통로구간 기준면의 콘크리트 양생시 표면에 생성되는 레이턴스(laitance) 또는 유분 등을 갈아내는 하지작업과;A ground work to grind the lattance or oil generated on the surface during the concrete curing of the passage section reference plane; 기준면 표면 크랙이나, 기포발생을 방지하기 위하여 프라이머를 균일하게 도포하는 프라이머 작업과;Primer work for uniform application of primer to prevent reference surface surface cracking and foaming; 시멘트재에 수지 및 무기질을 첨가하여 기준면에 고르게 흘려 자체의 흐름성 및 평활성에 의해 수평레벨 조정작용이 이루어지도록 하는 모르타르(MORTAR)작업; 및Mortar (MORTAR) operation to add a resin and inorganic to the cement material to flow evenly on the reference surface to achieve a horizontal level adjustment action by its flowability and smoothness; And 에폭시 프라이머, 에폭시 라이닝제 및 에폭시 무용제를 순차적으로 각 주제와 경화제를 약 4:1로 균일하게 혼합하여 소정 도포량을 롤라 또는 붓으로 평활하게 도포한 후, 양생시키는 에폭시 라이닝 작업을 포함하여 이루어지는 것을 특징으로 하는 물류창고용 바닥 시공방법.Epoxy primer, epoxy lining agent, and epoxy solvent are sequentially mixed with each other and the curing agent to about 4: 1 uniformly by applying a predetermined coating amount with a roll or brush, and then curing the epoxy lining operation Floor construction method for logistics warehouse.
KR10-2002-0006131A 2002-02-04 2002-02-04 A method of floor installating for warehouse KR100427596B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0006131A KR100427596B1 (en) 2002-02-04 2002-02-04 A method of floor installating for warehouse

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0006131A KR100427596B1 (en) 2002-02-04 2002-02-04 A method of floor installating for warehouse

Publications (2)

Publication Number Publication Date
KR20030065999A true KR20030065999A (en) 2003-08-09
KR100427596B1 KR100427596B1 (en) 2004-04-29

Family

ID=32220326

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0006131A KR100427596B1 (en) 2002-02-04 2002-02-04 A method of floor installating for warehouse

Country Status (1)

Country Link
KR (1) KR100427596B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101957644B1 (en) 2018-09-20 2019-07-04 씨제이대한통운 (주) Method for constructing structure with leveling and reinforcing floor using special equipment
KR102182536B1 (en) 2019-10-10 2020-11-24 동서 피, 씨, 씨 주식회사 Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same
KR102382111B1 (en) 2021-05-26 2022-04-01 (주)대원건영 Construction method of floor of new building or remodeling building

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5038139U (en) * 1973-07-30 1975-04-19
KR0145117B1 (en) * 1996-01-25 1998-07-15 현기일 Epoxy resin mortar
KR100218982B1 (en) * 1996-07-05 1999-09-01 홍달식 Method and its laminated structure of building floor
KR20010084168A (en) * 2000-02-24 2001-09-06 김기태 Composite of mortar for flor finishing at inside and outside and its constructing method
KR20000063402A (en) * 2000-07-03 2000-11-06 김광식 apparatus for setting a horizontal floor
KR200226645Y1 (en) * 2000-12-29 2001-06-15 송영택 A leveling device for carrying out the ground
KR20010079411A (en) * 2001-07-13 2001-08-22 장남종 elvan resin mortar applied building finishing method

Also Published As

Publication number Publication date
KR100427596B1 (en) 2004-04-29

Similar Documents

Publication Publication Date Title
CN104895101B (en) The construction method of raft foundation high accuracy integral built-in large diameter bolt group structure
CA2867964C (en) Prefabricated modular rebar modules and methods of using the same
US9874036B2 (en) Prefabricated, deconstructable, multistory building construction
US20160108618A1 (en) Prefabricated modular rebar modules and methods of using the same
US7596909B1 (en) Prefabricated building having a pre-cast concrete chain wall foundation
US20040261326A1 (en) Rectangular tilt-up concrete tank construction
US20020092249A1 (en) Partially prefabricated waffle slab
KR100427596B1 (en) A method of floor installating for warehouse
JP2010126955A (en) Sunk floor correction method
Murari et al. Precast construction methodology in construction industry
US9347599B2 (en) Support system for an equipment item on a concrete slab
KR101327378B1 (en) Drain board for base floor of construction
US20170121971A1 (en) Method for producing a ceiling in a building
RU2549423C2 (en) Method of laying of continuous subrail supports in two-pipe tunnels
CN206128611U (en) A positioning and clamping device for surmounting integrated construction platform in layer or die carrier
CN109469073B (en) Chute equipment and construction method thereof, and construction method of backfilling engineering
US11794293B2 (en) Automated modular construction factory method and system
KR102246944B1 (en) Prefab rack pannel for logistics warehouse including concret
JP6424058B2 (en) Construction method of equipment foundation
KR102639995B1 (en) Self-leveling Construction Method of Using Mortar and Structure for Self-leveling Construction
CN108427805A (en) A kind of platform mould layout method and device based on BIM
US20200399886A1 (en) Building construction method
US20240149493A1 (en) Concrete panel assembly system and method of use thereof
KR20130081850A (en) Caisson having assembly-type or single block-type base slab, and manufacturing system and method thereof
JP2572470B2 (en) Floor method

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
N231 Notification of change of applicant
FPAY Annual fee payment

Payment date: 20070406

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee