KR20020081531A - Well form for the base operation of pier and it's operation method - Google Patents

Well form for the base operation of pier and it's operation method Download PDF

Info

Publication number
KR20020081531A
KR20020081531A KR1020010020888A KR20010020888A KR20020081531A KR 20020081531 A KR20020081531 A KR 20020081531A KR 1020010020888 A KR1020010020888 A KR 1020010020888A KR 20010020888 A KR20010020888 A KR 20010020888A KR 20020081531 A KR20020081531 A KR 20020081531A
Authority
KR
South Korea
Prior art keywords
well
construction
line
piers
passage
Prior art date
Application number
KR1020010020888A
Other languages
Korean (ko)
Other versions
KR100403641B1 (en
Inventor
손영일
김유진
오재범
Original Assignee
동부엔지니어링 주식회사
동부건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 동부엔지니어링 주식회사, 동부건설 주식회사 filed Critical 동부엔지니어링 주식회사
Priority to KR10-2001-0020888A priority Critical patent/KR100403641B1/en
Publication of KR20020081531A publication Critical patent/KR20020081531A/en
Application granted granted Critical
Publication of KR100403641B1 publication Critical patent/KR100403641B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/04Flat foundations in water or on quicksand
    • E02D27/06Floating caisson foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0032Steel; Iron in sheet form, i.e. bent or deformed plate-material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

PURPOSE: Provided is caisson for foundation construction of pier, which is for quicker and more convenient transportation by self-buoyance and good constructability. CONSTITUTION: The caisson for foundation construction of pier is comprised of the following as: the steel caisson boat(10) which has self buoyance in an empty double-walled structure of inner and outer walls(11,12); many anchors(13) installed to lift them by tow line(15) of winch(14) in upper rim of the caisson boat.

Description

교각의 기초 시공용 우물통과 그 시공방법{Well form for the base operation of pier and it's operation method}Well form for the base operation of pier and it's operation method

본 발명은 교각의 기초 시공용으로 사용되는 우물통과 그 시공방법에 관한 것으로서, 더욱 상세히는 수심이 깊은 해상에서 초연약 점성토층이 두껍게 분포하는 지반조건에 수평 및 연직 하중의 규모가 매우 큰 기초가 요구되는 조건에서 교각의 기초 시공용 우물통을 보다 손쉽고 신속 간편하게 설치할 수 있도록 하여 시공성 양호에 의한 공기단축과 공사의 안정성 및 신뢰성을 확보할 수 있는 교각의 기초 시공용 우물통과 그 시공방법을 제공하기 위한 것이다.The present invention relates to a well bucket used for the foundation construction of bridge piers and a construction method thereof, and more particularly, to a ground condition in which super soft viscous soils are thickly distributed in a deep sea, Providing the foundation well of the piers and the construction method of the piers, which can secure the air shortage and the stability and the reliability of the construction by making it easier and faster to install the foundation wells for the piers under the required conditions. It is for.

일반적으로 해상에서 교각 기초를 시공하기 위해 사용하는 방법으로는 말뚝기초공법과 우물통 기초공법 및 가물막이 공법이 있으며, 수심이 깊은 해상에서 초연약 점성토층(N값 1내외)(이하 "초연약층"이라 함)이 두껍게 분포하는 지반은 수평 및 연직하중의 규모가 매우 큰 기초가 요구되므로 이러한 조건의 경우에는 말뚝 기초공법이나 우물통 기초공법을 적용할 수 없어 그 대체공법인 가물막이 공법을 주로 적용하여 왔다. 그러나, 가물막이 공법은 아래에서와 같이 많은 문제점을 갖고 있어서 효율적이지 못한 문제점이 있다.In general, the methods used to construct the piers foundations at sea include the pile foundation method, the well foundation method and the temporary barrier method, and the super soft viscous soil layer (N value 1 or more) in deep waters (hereinafter referred to as "ultra soft layer"). Since the foundations with thick distributions require very large horizontal and vertical loads, the pile foundation method or the well foundation method cannot be applied in these conditions, so the temporary barrier method, which is an alternative method, is mainly applied. Has come. However, the temporary clogging method has a number of problems as described below, which is not efficient.

즉, 기존의 말뚝 기초공법은 수평 및 연직 하중이 크고 초연약층이 두껍게 분포할 경우 초연약층을 관통하여 양호한 암반층에 말뚝기초를 설치하면 연직 지지력은 확보할 수 있으나, 수평지지력을 확보하기 어렵고 지지층을 직접 확인할 수가 없으므로 수심이 깊고 초연약층이 두껍게 분포하는 지반에서는 적용할 수 없었다.In other words, the existing pile foundation method has a large horizontal and vertical load, and if the super soft layer is thickly distributed, it is possible to secure vertical support by penetrating the super soft layer and installing a pile foundation in a good rock layer. Because it could not be directly identified, it could not be applied in the ground where the water depth was deep and the super soft layer was thickly distributed.

그리고, 우물통 기초의 시공방법은 기초가 설치될 위치에 수면 위로 상단부가 노출될 수 있을 정도의 높이를 갖도록 콘크리트로 제작된 우물통을 견인기로 들어서 우물통 설치위치에 놓으면 콘크리트 우물통이 자중에 의해 물속으로 가라앉으면서 침하되어 초연약층 및 토사층을 거쳐 암반층에 닿은 다음 우물통 내부의 흙을 크램쉘 등의 굴착장비를 이용하여 굴착해 내려가면서 소정의 암반 지지층 깊이까지 우물통 자중에 의하여 침하시키는 공법을 사용하였다.In addition, the construction method of the well basin foundation is to lift the wells made of concrete so that the upper portion is exposed to the water surface at the position where the foundation is to be installed as a retractor and put the concrete well in the well installation position It sinks while sinking into the water, touches the rock layer through the super soft layer and the soil layer, and then excavates the soil inside the well using excavation equipment such as cram shells, and sinks it by the well's own weight to a predetermined rock support layer depth. The method was used.

또한, 그 후 우물통내 물과 연약층을 펌핑하여 퍼내고 우물통 바닥을 정리하는 공정을 행한 다음 우물통내에 물담기와 수중콘크리트,채움재,콘크리트 타설공정을 행하는 과정을 거쳐 완료되는 공법으로서, 상기 종래의 우물통 공법은 그동안 우물통을 쉽게 침하시키는 방향으로만 개선되어 왔다.In addition, after the process of pumping out and pumping the water and the soft layer in the well and cleaning the bottom of the well, the process is completed through the process of dipping and submerged concrete in the well and underwater concrete, filling material, concrete pouring process, The conventional well-hole method has been improved only in the direction of easily sinking the well.

이러한 우물통 기초 시공방법은 연직 지지력뿐만 아니라 수평지지력이 매우 크므로 안정성 측면이 유리하고 지지층의 육안 확인이 가능하지만 콘크리트 구조물의 우물통은 중량이 상당히 많아나가 꽤 무겁기 때문에 견인하여 들어 옮기려면 용량이 상당히 큰 기중기선이 필요하며, 또한 그 높이를 높게 만드는데 한계가 있어서 수심이 깊은 곳에서는 적용할 수가 없었다.This well construction method is not only vertical support but also very large horizontal support, which is advantageous in terms of stability and visual confirmation of the support layer.However, the wells of concrete structures are quite heavy and are quite heavy. A fairly large crane was needed, and there was a limit to raising the height so that it could not be applied in deep waters.

즉, 초연약층 위에 거치시키게 되면 콘크리트 구조물의 우물통이 자중에 의하여 초연약성 점성토층 속으로 상당부분이 가라앉게 되므로 초연약층이 두꺼운 곳에서 사용하려면 우물통을 아주 높게 만들어야 하는데 이는 제작하기도 힘들지만 제작후 견인기구로 견인 운반하기도 힘들고 들어 올리기도 힘들어서 수심이 깊고 초연약층이 두껍게 분포하는 지반에서는 적용할 수가 없다.In other words, if it is mounted on the super soft layer, the well of the concrete structure will sink into the super soft viscous soil layer by its own weight. Therefore, if the super soft layer is used in a thick place, the well should be made very high. It is difficult to transport and lift by the traction mechanism, so it is not applicable to the ground where the depth is deep and the super soft layer is thickly distributed.

따라서, 수심이 깊고 초연약층이 두껍게 분포하는 지반에서는 상기와 같은 우물통 기초공법의 한계성으로 가물막이 공법이 대체공법으로 사용되고 있으나, 이중 조립틀을 이용하는 일반 가물막이 공법은 조립틀의 제작(SHEET PILE조립) 운반 및 거치에 따라 가물막이할 범위가 넓어 항로확보 등 제약이 많으며, 시공수가 많고 시공성이 복잡하여 공기가 길어짐에 따라 공사비 증가 및 해양오염이 심해 이에 대한 대책이 요구되는 등의 문제점이 있다.Therefore, in the ground where the depth of water and the super soft layer are thickly distributed, the temporary barrier method is used as an alternative method due to the limitations of the above-mentioned basic method of the well tank, but the general temporary barrier method using the double assembly frame is the production of the assembly frame (SHEET PILE). Assembly) There are many limitations such as securing the route due to wide range of barriers due to transportation and mounting, and there are problems such as increase of construction cost and marine pollution due to the long air due to the large number of constructions and the complexity of construction. .

그리고, 벽강관 우물통을 이용하는 가물막이 공법은 "공사용 가교설치→가이드파일 및 강관파일 설치→굴토 및 강지보공 설치→물담기 및 수중콘크리트 타설→물푸기 및 기초콘크리트 타설"의 공정의 거쳐 시공을 완료하게 되는데, 이 역시 시공성이 복잡하고 공기가 오래 걸려 공사비가 증가하게 되고 안전사고 등의 위험성이 큰 문제점이 있다.In addition, the façade construction method using wall steel pipe wells is carried out through the process of "cross-linking installation for construction → guide pile and steel pipe pile installation → excavation and cultivation of earthen ground construction → water dipping and underwater concrete placement → watering and foundation concrete casting". This is completed, too, the construction is complicated and the air takes a long time to increase the construction cost, there is a big risk of safety accidents.

본 발명은 상기와 같은 종래의 문제점을 감안하여 개발된 것으로서, 본 발명의 목적은 수심이 깊고 초연약층이 두껍게 분포하는 지반조건에서 교각 기초용 우물통을 신속 간편하면서도 안정성있게 시공할 수 있도록 하여 공기단축과 공사의 안정성 및 신뢰성을 확보할 수 있는 교각의 기초 시공용 우물통과 그 시공방법을 제공하는데 있다.The present invention was developed in view of the above-described conventional problems, and an object of the present invention is to provide a quick and simple and stable construction of a well for a piers foundation under ground conditions in which a deep depth and a super soft layer are thickly distributed. The main purpose is to provide a well for the foundation construction of the piers that can be shortened and ensure the stability and reliability of the construction and its construction method.

상기 목적을 달성하기 위해 본 발명은 우물통 전체를 철판의 강재 재질로 형성하되 내/외 벽체의 내부가 비어있는 상태로 교각의 기초 시공용 우물통을 구성함을 특징으로 하는 것으로써, 이러한 본 발명의 우물통은 내/외 벽체가 비어있어 무게가 가볍기 때문에 제작 후 기중기선 등으로 견인 운반 및 들어올리기가 용이하여 시공성이 좋으므로 상기 목적을 효과적으로 달성할 수가 있다.In order to achieve the above object, the present invention is characterized in that the well is formed by the steel material of the iron plate as a whole, but the internal construction of the well for the foundation of the piers with the interior of the outer wall is empty, Since the well of the present invention has an empty inside / outer wall and is light in weight, it is easy to carry and lift by a crane ship after manufacture, and thus the construction is good, thereby achieving the above object effectively.

이러한 본 발명의 다른 목적은 상기와 같이 제작되는 우물통을 자체 부력을 이용하여 먼저 시공하고자 하는 위치에 부양시켜 놓은 상태에서 그 내/외 벽체 속에 담수를 속채움하여 1차 침하시킨 다음 다시 내/외 벽체 속에 수중 콘크리트를 타설하여 2차 침하를 시키는 과정을 반복하여 우물통을 소정 깊이까지 침하시키는 기초 시공용 우물통 시공방법으로 구성함으로써 달성되는 것이다.Another object of the present invention is to firstly settle the fresh water in the inner / outer wall in a state in which the well is manufactured as described above by using its own buoyancy in a position to be constructed first, and then back into the inner / outer wall again. It is achieved by constructing the well construction method for the foundation construction to submerge the well to a predetermined depth by repeating the process of placing the underwater concrete in the outer wall to the secondary settlement.

이와 같은 본 발명은 우물통을 부양식으로 띄운 상태에서 담수를 채워 1차 침하를 시키므로 수평성이 매우 양호하게 유지되면서 침하되며, 수중콘크리트를 채워 2차 침하를 시킨 다음 굴착작업 등을 행하는 것이므로 암반층에 지지되는 것을 확인하기가 좋고, 기초에 작용하는 수평 및 연직하중의 규모가 매우 커 대규모의 수평지지력 및 연직 지지력이 요구되는 장대교량의 시공에 적합하며, 초연약층이 두껍게 분포하고 수심이 깊은 해상에서의 우물통 시공이 신속 간편한 등 시공성이 좋아 공기단축의 효과가 상당하므로 상기 목적을 효과적으로 달성할 수가 있다.As the present invention is filled with fresh water in the state of floating the well bucket in the form of the primary settlement, so that the level of the submerged while maintaining a very good horizontal, the submerged by filling the concrete concrete and then excavation work and so on rock bed It is good to confirm that it is supported on the bridge, and the scale of horizontal and vertical loads acting on the foundation is very large, so it is suitable for the construction of long bridges requiring large horizontal and vertical bearing capacity. Since the construction of the well in the well, such as quick and easy construction, the effect of shortening the air is considerable, the above object can be effectively achieved.

도 1a 는 본 발명의 우물통을 일례로 보인 사시도Figure 1a is a perspective view showing an example of the well bucket of the present invention

도 1b 는 본 발명의 우물통 구조를 보이기 위한 횡단면도Figure 1b is a cross-sectional view for showing the well structure of the present invention

도 2a 는 본 발명의 우물통을 해상에서 운반하는 상태도Figure 2a is a state carrying the well container of the present invention at sea

도 2b 는 본 발명의 우물통을 닷으로 고정시키는 상태도Figure 2b is a state diagram fixing the well bucket of the present invention with a dot

도 2c 는 본 발명의 우물통 내/외 벽체속에 담수를 채워 침하시키는 상태도Figure 2c is a state diagram for sinking fresh water in the inside / outside wall of the well bucket of the present invention

도 2d 는 본 발명의 침하된 우물통 주변에 작업용 가설파일을 박는 상태도Figure 2d is a state diagram in which the working hypothesis piles around the sink well of the present invention

도 2e 는 본 발명의 우물통 내/외 벽체속에 수중콘크리트를 타설하는 상태도Figure 2e is a state diagram for pouring underwater concrete in the wall inside / outside the well of the present invention

도 3 은 본 발명의 우물통이 2차 침하된 상태도Figure 3 is a state in which the well bucket of the present invention is secondary settled

도 4 는 본 발명의 침하된 우물통 속에서 물,초연약층 등을 퍼내는 상태도Figure 4 is a state of pumping water, ultra soft layer, etc. in the sink well of the present invention

도 5 는 본 발명의 침하된 우물통 바닥 암반층을 굴착하여 우물통을 암반층에 안착시키는 상태도Figure 5 is a state diagram for sinking the well bottom bottom rock layer of the present invention to seat the well in the rock bed

도 6 은 암반층에 안착된 본 발명의 우물통속에 담수를 채우고 수중콘크리트를 타설한 상태도6 is a state in which the fresh water is filled in the well bucket of the present invention seated on the rock bed and poured underwater concrete

도 7 은 도 6 공정후 본 발명의 우물통 속에 채움재와 배근 및 콘크리트를채운 상태도Figure 7 is a state filled with filler and reinforcement and concrete in the well of the present invention after the process of Figure 6

도 8 은 본 발명의 우물통에 의해 교각 기초의 시공이 완성된 상태도8 is a state diagram in which the construction of the piers foundation by the well of the present invention

도면의 주요 부분에 대한 부호의 설명Explanation of symbols for the main parts of the drawings

10 : 우물통선 11,12 : 내,외 벽체10: well passage 11,12: inside and outside walls

13 : 닷 17,70 : 수중콘크리트13: dot 17,70: underwater concrete

20 : 가설파일 30 : 초연약층20: Hypothesis file 30: Ultra soft layer

40 : 토사층 50 : 암반층40: soil layer 50: rock layer

71 : 채움재 72 : 배근 및 콘크리트71: Filler 72: reinforcement and concrete

100 : 교각용 기초100: foundation for piers

이하, 본 발명의 목적을 효과적으로 달성할 수 있는 바람직한 교량의 교각 시공용 우물통 시공방법을 실시예로 첨부한 도면에 의해 공정별로 상세히 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings, the method for constructing a well for a bridge construction of the bridge construction that can effectively achieve the object of the present invention will be described in detail by the process as follows.

본 발명은 도 1a 및 도 1b 에서와 같이 교각의 기초 시공용 우물통을 구성할 때 철판의 강재 재질로 자체 부력이 있는 우물통선(10)으로 형성하되 내/외 벽체(11)(12)를 속이 비어있는 2중벽 구조로 상단은 개구되고 하단은 막혀있는 형태로 형성하고, 상기 우물통선(10)의 상단 테두리면에는 다수의 닷(13)을 윈치(14)의 견인줄(15)로 승강시킬 수 있도록 설치한 것을 특징으로 한다.1A and 1B, but when forming a well for the foundation construction of the piers as shown in Figure 1a and 1b is formed as a steel material of the steel plate with a buoyancy well line 10 of its own buoyancy, but the inner / outer walls (11, 12) It is a hollow double-walled structure formed at the top of the opening and the bottom is blocked, and a plurality of dots (13) on the upper edge of the well line 10 to the lifting line 15 of the winch (14) It is characterized in that the installation so that.

이하에서는 상기한 본 발명의 우물통 본체로 시공하는 과정을 공정별로 상세히 설명하기로 한다.Hereinafter will be described in detail for each process the construction process to the well body of the present invention described above.

제1공정(우물통선 제작과 운반 공정)1st process (Well line production and transportation process)

제작장에서는 도 1a 및 도 1b 와 같이 철판의 강재 재질로 우물통선(10)을 제작하되 내/외 벽체(11)(12)를 속이 비어있는 2중벽 구조로 만들어 자체 부력이있게 하되 그 상단은 개구되고 하단은 막혀있는 상태로 제작하며, 상기 우물통선 (10)의 상단 테두리면에는 다수의 닷(13)을 윈치(14)의 견인줄(15)로 승강시킬 수 있도록 설치하여 제작한다.1A and 1B in the workshop to produce the well line 10 from the steel material of the steel plate, but the inner and outer walls (11) (12) to make a double-wall structure of the hollow hollow to have its own buoyancy but the top The opening and the lower end is manufactured in a closed state, and is installed on the upper edge surface of the well line 10 so that a plurality of dots 13 can be elevated by the tow line 15 of the winch 14.

그 후 상기 제작된 우물통선(10)을 도 2a 와 같이 자체 부력으로 해상에 띄운 상태에서 시공위치까지 견인선으로 운반한 다음 도 2b 와 같이 우물통선(10)의 상단 테두리에 매달려 있는 닷(13)을 내려서 우물통선(10)의 위치를 고정시킨다.Then, the manufactured well line 10 is transported to the construction position in the state floating on the sea by its own buoyancy as shown in Figure 2a and then a dot 13 hanging on the upper edge of the well line 10 as shown in Figure 2b Lower the well to fix the position of the well line (10).

제2공정(우물통선의 1차 침하)2nd process (the 1st settlement of well route)

상기 1공정 완료 후 우물통선(10)의 내/외 벽체(11)(12)의 상단 개구부를 통해 내부에 담수를 펌핑하여 채운다. 그러면 우물통선(10)은 채워지는 담수의 무게에 의해 서서히 가라앉게 되는데, 이때 채워지는 담수는 벽체 내부에 고르게 퍼져 저절로 평형성을 맞추기 때문에 우물통선(10)의 자중과 부력만을 검토하면 될 뿐 수평을 맞추지 않아도 됨에 따라 작업성이 좋다.After completion of the first step, the fresh water is filled by pumping the fresh water through the upper openings of the inner and outer walls 11 and 12 of the well passage line 10. Then the well passage 10 sinks slowly by the weight of the freshwater being filled, and the freshwater filled is spread evenly inside the wall to balance itself by itself, so only the self-weight and buoyancy of the well passage 10 need to be reviewed horizontally. Workability is good as there is no need to fit.

제3공정(작업용 가설파일 시공)3rd process (work construction temporary file construction)

우물통선(10)의 1차 침하가 되면 우물통선(10) 테두리를 따라 소정간격을 두고 작업용 가설파일(20)을 도 2d 와 같이 초연약층(30)과 토사층(40)을 거쳐 암반층(50)에 꽂힐 때까지 박아서 시공한다. 그러면 우물통선(10)은 사방을 가설파일 (20)이 막아주고 있으므로 그 위치가 그대로 유지된다.When the first settlement of the well passage line 10 becomes a predetermined interval along the boundary of the well passage line 10, the temporary construction pile 20 for work is passed through the super soft layer 30 and the soil layer 40 as shown in FIG. 2D, and the rock layer 50. Drive until it is plugged into the construction. Then the well line 10 is blocked by the hypothesis pile 20, the position is maintained as it is.

제4공정(수중콘크리트 속채움에 의한 2차 침하)4th process (second subsidence by underwater concrete filling)

도 2e 와 같이 우물통선(10)의 내/외 벽체(11)(12) 내부에 수중 콘크리트 (17)를 타설하여 속채움한다. 그러면 우물통선(10)은 벽체속에 채워지는 수중 콘크리트(17)의 무게에 의하여 더 가라앉아 2차 침하된다. 이때 수중 콘크리트(17)에 의해 증가되는 우물통선(10)의 자중과 부력을 검토하여 우물통선(10)은 한쪽이 기울지 않도록 균형되게 수중 콘크리트를 타설함이 바람직하며, 우물통선(10) 하단은 이때 대부분 초연약층(30)을 지나 토사층(40)속에 머물거나 암반층(50)까지 닿게 된다.As shown in FIG. 2E, the inner concrete 17 is poured into the inner and outer walls 11 and 12 of the well passage line 10. Then, the well passage line 10 sinks further by the weight of the underwater concrete 17 filled in the wall and is submerged. At this time, by examining the self-weight and buoyancy of the well passage line 10 increased by the underwater concrete 17, the well passage line 10 is preferably placed under water concrete in a balanced manner so that one side is not inclined, and the bottom of the well passage line 10 At this time, most pass through the super soft layer 30 to stay in the soil layer 40 or to reach the rock layer 50.

제5공정(우물통선 내부의 물, 연약층 펌핑 및 굴착 공정)5th process (water, weak layer pumping and excavation process inside the well passage)

상기 제4공정 후 도 4 와 같이 우물통선(10) 내에 채워진 물과 초연약층(30)을 펌프로 펌핑하여 퍼내는 작업을 행한다. 그리고, 우물통선(10) 내부의 물과 초연약층(30)을 퍼내는 작업이 완료되어 우물통선(10) 바닥에 암반층(50)이 나타나면 도 5 와 같이 크램쉘 등의 굴착장비를 이용하여 암반을 굴착해 내려가면서 소정의 암반층(50) 깊이까지 우물통선(10)이 침하되어 지지될 때까지 우물통선(10)을 인위적으로 침하시키는 공정과 우물통선(10) 바닥을 깨끗하게 정리하는 공정을 행한다.After the fourth step, as shown in FIG. 4, the water filled in the well passage 10 and the ultra soft layer 30 are pumped out. When the rock layer 50 appears on the bottom of the well passage line 10 after the operation of discharging the water and the ultra soft layer 30 inside the well passage line 10 is completed, the rock bed is excavated using cram shells or the like as shown in FIG. 5. Excavating and performing the process of artificially sinking the well passage line 10 and the process of cleanly cleaning the bottom of the well passage line 10 until the well passage line 10 is submerged and supported to a predetermined rock layer 50 depth. .

제6공정(수중콘크리트,채움재,콘크리트 타설공정)6th process (underwater concrete, filling material, concrete pouring process)

상기 제5공정에 의해 암반층(50)에 안정적으로 안착되면 우물통선(10) 내부에 물을 소정 높이까지 담은 다음 도 6 과 같이 수중콘크리트(70)를 부력 저항위치까지 타설하는 공정과 우물통선(10) 내부의 물을 완전히 퍼내는 공정을 거쳐 도 7 과 같이 채움재(71)와 배근공사 및 콘크리트(72) 타설공사를 차례로 하여 양생시키는 공정을 행한 다음 최종 정리를 하면 도 8 과 같이 상단이 수면위로 노출되는 교각용 기초(100)의 시공이 완료되는 것이다.When it is stably seated on the rock layer 50 by the fifth process, the water is contained in the well passage 10 up to a predetermined height, and then the water concrete 70 is poured to the buoyancy resistance position as shown in FIG. 6 and the well passage ( 10) After the process of completely discharging the water inside the curing material 71 and the reinforcement work and concrete 72 pouring process in turn to perform the curing process and then the final clean up when the upper surface as shown in Figure 8 Construction of the piers foundation 100 exposed to the top is completed.

이상에서와 같이 본 발명은 교각의 기초시공용 우물통을 자체 부력이 있는 우물통선으로 제작한 후 이를 자체 부력으로 해상에 띄워 견인 운반하는 것이므로 이송과정이 신속 간편하고, 깊은 수심과 초연약층이 두껍게 분포하는 지반조건의 해상에서 우물통선을 2차에 걸쳐 침하시키면서 암반층에 지지되는 것을 확인하기가 쉬워 시공성이 양호한 효과가 있다.As described above, the present invention is to make the well-container for the foundation construction of the piers in the well line with its own buoyancy, and then to float it on the sea with its own buoyancy, so that the transport process is quick and simple, deep water depth and ultra soft layer thick It is easy to confirm that it is supported by the rock layer while settling the well line for 2 times in the sea of the distributed ground conditions, and it has an effect with favorable constructability.

또한, 기초에 작용하는 수평 및 연직하중의 규모가 커서 대규모의 수평지지력 및 연직 지지력이 요구되는 장대교량의 시공에 적합한 효과가 있으며, 교각의 기초시공용 우물통을 설치하는데 따른 공기단축에 의해 공사비의 절감효과가 높고, 공사의 안정성 및 신뢰성을 확보할 수 있어 매우 획기적인 발명이라고 할 수 있다.In addition, the large horizontal and vertical load acting on the foundation has the effect of being suitable for the construction of long bridges that require large horizontal and vertical bearing capacity. It is a very innovative invention because it has high saving effect and can secure construction stability and reliability.

Claims (2)

교각의 기초 시공용 우물통을 구성함에 있어서,In constructing the wells for the foundation construction of the piers, 강재 재질이면서 내/외 벽체(11)(12)가 속이 비어있는 2중벽 구조로 형성되어 자체 부력이 있는 우물통선(10)으로 형성하고, 상기 우물통선(10)의 상단 테두리면에는 다수의 닷(13)을 윈치(14)의 견인줄(15)로 승강시킬 수 있도록 설치한 것을 특징으로 교각의 기초 시공용 우물통.The inner and outer walls 11 and 12 are made of steel and are formed in a hollow wall structure having a hollow inside, and are formed as well wells 10 having their own buoyancy, and a plurality of dots are formed on the upper edge surface of the wells 10. A well for construction of a piers, characterized in that (13) is installed so that the winch 14 can be elevated by the traction line (15). 교각의 기초 시공용 우물통을 시공함에 있어서,In constructing the wells for the foundation construction of the piers, 내/외 벽체(11)(12)의 속이 비어있어 자체 부력이 있으면서 상단 테두리면에 다수의 닷(13)이 승강되게 설치된 우물통선(10)을 자체 부력으로 해상에 띄워 시공위치까지 운반한 다음 상기 닷(13)을 내려 우물통선(10)을 고정시키는 제1공정과;The inner and outer walls (11) and (12) are hollowed out so that they have their own buoyancy and a plurality of dots (13) installed on the upper edge surface are lifted and lifted to the construction site by floating on the sea with their own buoyancy. A first step of fixing the well communication line 10 by lowering the dot 13; 상기 1공정 후 우물통선(10)의 내/외 벽체(11)(12) 내부에 담수를 채워서 우물통선(10)을 1차 침하시키는 제2공정과;A second step of first submerging the well passage line 10 by filling fresh water into the inner / outer walls 11 and 12 of the well passage line 10 after the first step; 우물통선(10)의 테두리를 따라 소정간격을 두고 작업용 가설파일(20)을 박는 제3공정과;A third step of embedding the working temporary file 20 at a predetermined interval along the edge of the well passage line 10; 우물통선(10)의 내/외 벽체(11)(12) 내부에 수중 콘크리트(17)를 타설하여 우물통선(10)을 2차 침하시키는 제4공정과;A fourth step of placing the underwater concrete 17 inside the inner / outer walls 11 and 12 of the well passage 10 to secondly sink the well passage 10; 상기 2차 침하된 우물통선(10) 내에 채워진 물과 초연약층(30) 및 토사층(40)을 퍼낸 다음 암반층(50)을 굴착해 우물통선(10)을 암반층(50)에 지지시키는 제5공정과;A fifth step of discharging the water filled in the second submerged well passage 10 and the super soft layer 30 and the soil layer 40 and then excavating the rock layer 50 to support the well passage line 10 to the rock layer 50. and; 상기 암반층(50)에 지지된 우물통선(10) 내에 물을 담고 수중콘크리트(70)를 부력 저항위치까지 타설한 다음 우물통선(10) 내부의 물을 완전히 퍼내고 채움재 (71)와 배근공사 및 콘크리트(72) 타설공사를 차례로 행하는 제6공정;Water is contained in the well passage 10 supported by the rock bed 50, and the underwater concrete 70 is poured to the buoyancy resistance position, and then the water inside the well passage 10 is completely drained and the filling material 71 and the reinforcement work and A sixth step of sequentially placing the concrete 72; 으로 이루어진 것을 특징으로 하는 교각의 기초 시공용 우물통 시공방법.Well construction method for the foundation construction of piers, characterized in that consisting of.
KR10-2001-0020888A 2001-04-18 2001-04-18 Operation method of well form bucket of one style for the base operation of pier KR100403641B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0020888A KR100403641B1 (en) 2001-04-18 2001-04-18 Operation method of well form bucket of one style for the base operation of pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0020888A KR100403641B1 (en) 2001-04-18 2001-04-18 Operation method of well form bucket of one style for the base operation of pier

Publications (2)

Publication Number Publication Date
KR20020081531A true KR20020081531A (en) 2002-10-28
KR100403641B1 KR100403641B1 (en) 2003-10-30

Family

ID=27701622

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0020888A KR100403641B1 (en) 2001-04-18 2001-04-18 Operation method of well form bucket of one style for the base operation of pier

Country Status (1)

Country Link
KR (1) KR100403641B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100440726B1 (en) * 2002-03-15 2004-07-19 삼성중공업 주식회사 Apparatus for confirming well barrel's foundation on rock floor in the bridge base
KR101680794B1 (en) 2015-09-21 2016-12-12 현대건설 주식회사 Basic structure for constructing a caisson foundation and the construction method using the same
CN107119703A (en) * 2017-05-10 2017-09-01 刘丽娟 A kind of water conservancy rushes heavy well construction equipment
CN109235479A (en) * 2018-09-21 2019-01-18 中交航局第二工程有限公司 Large-tonnage pier and its prefabricated and floatation type dock construction method
CN109853602A (en) * 2019-03-04 2019-06-07 中交第二航务工程局有限公司 A kind of steel caisson and construction method of blade foot filling UHPC material

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100847245B1 (en) 2007-01-08 2008-07-18 (주)평화엔지니어링 A direct base construction method of underwater concrete using a hollow cylindrical steel mold having a buoyancy

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5673725A (en) * 1979-11-20 1981-06-18 Kawasaki Steel Corp Construction of foundation under water
JPS60215924A (en) * 1984-04-10 1985-10-29 Sumitomo Metal Ind Ltd Settlement of steel skeleton for underwater foundation structure
JP2815492B2 (en) * 1991-03-26 1998-10-27 株式会社熊谷組 How to build an underwater foundation
JPH11229404A (en) * 1998-02-19 1999-08-24 Kumagai Gumi Co Ltd Construction of bridge foundation in deep water

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100440726B1 (en) * 2002-03-15 2004-07-19 삼성중공업 주식회사 Apparatus for confirming well barrel's foundation on rock floor in the bridge base
KR101680794B1 (en) 2015-09-21 2016-12-12 현대건설 주식회사 Basic structure for constructing a caisson foundation and the construction method using the same
CN107119703A (en) * 2017-05-10 2017-09-01 刘丽娟 A kind of water conservancy rushes heavy well construction equipment
CN109235479A (en) * 2018-09-21 2019-01-18 中交航局第二工程有限公司 Large-tonnage pier and its prefabricated and floatation type dock construction method
CN109235479B (en) * 2018-09-21 2024-05-14 中交一航局第二工程有限公司 Large-tonnage abutment and prefabricating and floating type butt joint construction method thereof
CN109853602A (en) * 2019-03-04 2019-06-07 中交第二航务工程局有限公司 A kind of steel caisson and construction method of blade foot filling UHPC material

Also Published As

Publication number Publication date
KR100403641B1 (en) 2003-10-30

Similar Documents

Publication Publication Date Title
AU2009289381B2 (en) Offshore station, foundation for an offshore station, and method for building an offshore station
US9567720B2 (en) Offshore platform for a marine environment
US3528254A (en) Offshore platform structure and construction method
KR101211811B1 (en) Cast in concrete pile With precast type Caisson
KR100714179B1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
US3624702A (en) Offshore platform support
CN111502725A (en) Artificial island type middle well structure of submarine tunneling tunnel
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
KR20110107888A (en) Construction method of the pier without the temporary dam in the sea or the river
KR100403641B1 (en) Operation method of well form bucket of one style for the base operation of pier
KR100418268B1 (en) Well form bucket of division style for the base operation of pier and it's operation method
WO2016109962A1 (en) Construction method for fixing offshore marine platform to a seabed having layers of a soil/clay nature
CN109518674B (en) Artificial island segment, assembled artificial island and construction method of assembled artificial island
US3091937A (en) Underwater foundation structure and method therefor
KR101041282B1 (en) Construction Method of Marine Structure
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
KR100768552B1 (en) steel well foundation construction and equipment
KR20200014531A (en) Fixed anchor construction method of marine structure
US2935854A (en) Offshore drilling platform
CN209741887U (en) Steel caisson pile body structure for bank abrupt slope
CN109629587B (en) Steel caisson pile body structure for bank abrupt slope and construction method
KR200404677Y1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
US3965688A (en) Underwater structures, in particular for underwater drilling operations
KR0130745B1 (en) Construction method of port district structure at the poor subsoil

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121016

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20131015

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20141014

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20151013

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20161013

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20171013

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20190917

Year of fee payment: 17