KR20020068988A - Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land - Google Patents

Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land Download PDF

Info

Publication number
KR20020068988A
KR20020068988A KR1020020040891A KR20020040891A KR20020068988A KR 20020068988 A KR20020068988 A KR 20020068988A KR 1020020040891 A KR1020020040891 A KR 1020020040891A KR 20020040891 A KR20020040891 A KR 20020040891A KR 20020068988 A KR20020068988 A KR 20020068988A
Authority
KR
South Korea
Prior art keywords
soft ground
water
load
improvement method
soft
Prior art date
Application number
KR1020020040891A
Other languages
Korean (ko)
Inventor
김윤상
박현일
Original Assignee
김윤상
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김윤상 filed Critical 김윤상
Priority to KR1020020040891A priority Critical patent/KR20020068988A/en
Priority to KR10-2002-0049446A priority patent/KR100463314B1/en
Publication of KR20020068988A publication Critical patent/KR20020068988A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Abstract

PURPOSE: An improvement method for the soft ground of a large site using seawater as consolidation load is provided to minimize environmental disruption and to improve the soft ground with low construction expenses. CONSTITUTION: The improvement method for the soft ground of a large site using seawater as consolidation load comprises the steps of spreading a sand mat layer on the soft ground, placing vertical drains, installing a membrane liner and draining consolidated leachate, then containing water.

Description

바닷물을 재하 하중으로 이용한 대규모 부지의 연약지반 개량공법{Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land}Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land}

본 발명은 연약지반 개량을 위하여 일반적으로 사용되는 프리로딩(pre-loading)+연직 배수재 공법 중 프리로딩으로 사용되는 하중을 바닷물로 가하는 공법으로서, 연약지반에 균등한 하중을 일시에 재하 할 수 있도록 한 새로운 연약 지반 개량 공법에 관한 것이다The present invention is a method of applying the load used as the preloading of seawater in the pre-loading + vertical drainage method commonly used for the improvement of the soft ground, so as to be able to load an equal load on the soft ground at one time. It is about a new soft ground improvement method

일반적으로, 컨테이너 부두 축조공사 같은 항만건설공사에서 컨테이너 야적 부지나 관련 부지로 사용되는 지반은 해성 점토를 준설 매립된 초연약지반이거나, 연약한 해성 원지반 점토 지반이다. 이러한 지반은 위에서 거론된 사용 용도에 맞게 사용하기에는 너무 연약하여 지반 개량없이 사용하는 경우 지지력이 부족하며 사용시에 하중이 작용할 때 상당히 큰 침하량이 발생하여 사용시 문제가 발생하게 된다. 이러한 문제를 해결하기 위하여 연약지반을 개량하는 방법으로써 일반적으로 사용되는 공법이 pre-loading 공법이다. 이 공법은 사용시 작용될 하중보다 더 큰 하중을 먼저 재하시켜 침하량을 미리 발생시키는 공법으로 사용중에는 나중에 발생하는 침하량이 부지 이용에 허용될 수 있도록 한다.In general, in the port construction work such as container wharf construction, the ground used as container yard or related site is super soft ground dredged by sea clay or soft sea clay ground. These grounds are too soft to be used for the above-mentioned usages, and when used without ground improvement, there is a lack of bearing capacity and a large amount of settlement occurs when a load is applied in use, which causes problems in use. In order to solve this problem, the pre-loading method is a commonly used method to improve the soft ground. This method loads a load that is greater than the load to be applied in advance and generates the settlement in advance so that later settlement during use can be allowed to use the site.

pre-loading 공법은 하중 재하와 더불어 sand drain, P.B.D. 등의 연직배수재를 이용하여 압밀 침출수의 배수 거리를 줄여서 연약 지반의 신속한 압밀 침하를 도모하는 것이 일반적이다. Pre-Loading 공법에서 하중으로 사용하는 것으로는 토사, 대기압과 물 등이 있으며 이중에서 토사가 일반적으로 사용되나, 토사를 사용하는 경우 토사가 갖는 태생적인 문제점 -토사 성토에 따른 전단 파괴 가능성 및 압밀 침하량을 계산시 제안된 가정과 차이 등-으로 인하여 연약지반 개량시 국부적인 함몰 등의 부등 침하 등의 문제가 발생한다. 대기압을 이용한 재하 방법은 일명 진공압밀공법이라고 하며, 진공펌프를 이용하여 지반에 부압을 걸어 연약지반을 등방 압밀시키는 방법으로 압밀기간 단축 및 균등 재하의 장점을 가지고 있으나, 기밀시트 및 특수 연직배수재 사용과 진공펌프 운용 등에 의하여 공사비가 고가인 점이 치명적인 단점이며 적용 면적이 작으며 하중을 약 8 t/m2까지 밖에 작용시킬 수 없는 단점이 있다.In the pre-loading method, it is common to achieve rapid consolidation settlement of soft ground by reducing the drainage distance of consolidation leachate by using vertical drainage such as sand drain and PBD in addition to loading. As the load used in the pre-loading method, there are soil, atmospheric pressure, and water. Among them, soil is generally used. However, when soil is used, it is a native problem of soil-soil. Due to differences in the proposed assumptions and differences, the problems such as local sinking and other subsidence during soft ground improvement occur. The loading method using atmospheric pressure is called vacuum consolidation method. It is a method of isotropically consolidating the soft ground by applying negative pressure to the ground using a vacuum pump, which has the advantages of shortening the consolidation period and equal load, but using airtight sheets and special vertical drainage. It is a fatal disadvantage that the construction cost is high due to the operation of the vacuum pump and the like, and the application area is small and the load can only be applied to about 8 t / m 2 .

한편, 물을 하중으로 이용하는 방법은 하중 재하 재료로서 물을 상요하기 때문에 압밀침하 계산 이론과 실제가 잘 일치하며 아주 저렴한 공사비가 소요되는 장점을 가지고 있으나, 차수막 개발, 압밀침출수 배수 방법, 모니터링 방법, 차수막 균열 보수 방법 등의 문제점으로 인하여 대규모 부지에 물을 하중으로 재하하는 것이 불가능하여 극히 일부 공사에서 작은 면적에서 토사나 진공압밀의 부족분의 하중을 물로써 재하하는 부수적인 역할로서 사용되어왔다.On the other hand, the method of using water as a load has the advantage that the consolidation settlement calculation theory and practice are well matched and very inexpensive construction cost is required because it uses water as a loading material, but the development of water curtain, condensate leachate drainage method, monitoring method, Due to problems such as the repair of cracks in the membrane, it is impossible to load water on a large-scale site, and in some constructions, it has been used as an ancillary role to load a load of soil or vacuum condensation in a small area.

따라서, 물을 하중으로 사용하는 연약지반 개량공법을 대규모 부지에 사용하기 위해서는 차수막 개발, 압밀침출수 배수 방법, 차수막의 모니터링 방법 및 보수 방법이 해결되어야 할 것이다.Therefore, in order to use the soft ground improvement method using water as a load on a large-scale site, the development of a water curtain, consolidation leachate drainage method, a monitoring method and repair method of the water curtain should be solved.

본 발명은 상기의 문제를 해결하기 위한 것으로, 본 발명의 목적은 자연환경 파괴를 최소화와 저렴한 공사비 및 압밀침하 계산 이론과 시공이 잘 일치하는 장점을 가진 물하중재하 연약지반 개량공법이 가능하도록 한 공법을 제공하는 것이다.The present invention is to solve the above problems, and an object of the present invention is to minimize the damage to the natural environment, and to enable a water-loaded soft ground improvement method with the advantages that the construction theory and consolidation settlement calculation theory and construction are well matched It is to provide a method.

도 1은 본 발명에 따른 연약지반 개량 공법의 개요도1 is a schematic diagram of a soft ground improvement method according to the present invention

도 2는 본 발명에 따른 연약지반 개량 공법의 상세도1Figure 2 is a detailed view of the soft ground improvement method according to the invention 1

도 3은 본 발명에 따른 연약지반 개량 공법의 상세도2Figure 3 is a detailed view of the soft ground improvement method according to the invention 2

도 4은 본 발명에 따른 연약지반 개량 공법의 상세도3Figure 4 is a detailed view of the soft ground improvement method according to the invention 3

<도면 부호의 설명><Explanation of Drawing Symbols>

1. 연성 차수막 2. 전단 저항방지용 차수막1. Flexible lining 2. Shear resisting lining

3. PVC 파이프 4. 강관3. PVC pipe 4. Steel pipe

5. 강관 지지대 6. 펌프5. Steel pipe support 6. Pump

7. 수평 배수재 8. 제체7. Horizontal drainage 8. Housing

9. 연직 배수재9. Vertical drainage

본 발명에 따르면, 물을 손쉽게 이용할 수 있는 바닷가나 강가의 대규모 연약지반에서 물을 하중으로 이용하여 연약지반을 개량할 수 있도록 물을 담수할 수 있는 차수막, 압밀침출수 배수방법, 차수막의 모니터링 방법 및 보수 방법으로 구성된다. 연약지반위에 sand mat층을 포설한 하고 연직배수재를 타설한 후 그 위에 차수막을 설치하고 압밀침출수를 배수할 수 있도록 한 다음 담수를 하여 연약지반을 개량하는 것을 특징으로 하는 연약지반 개량공법이 제공된다.According to the present invention, in a large-scale soft ground on the beach or river, where water is easily available, a water curtain, a condensed leachate drainage method, a method of monitoring the water curtain, and the fresh water to improve the soft ground using water as a load. It consists of a repair method. A soft ground improvement method is provided, which includes laying a sand mat layer on the soft ground, placing a vertical drainage material, installing a water barrier on it, draining the consolidation leachate, and then improving the soft ground by fresh water. .

본 발명의 첫 번째 특징에 따르면, 물을 담수하기 위하여 소정 높이의 제체와 물이 지반과 격리될 수 있도록 하는 차수막이 필요하게 된다. 이때, 차수막은 발생 응력에 저항하는 경성 차수막과 변형이 자유로운 연성 차수막이 사용될 수 있으나, 연약 지반에서 침하 및 변형이 상당히 크므로 연성 차수막이 사용된다. 이러한 연성 차수막은 극한 응력이 작으므로 가능한 응력이 발생하지 않도록 조치해야 한다. 응력이 발생될 수 있는 곳은 제체와 차수막이 접촉되는 부분으로, 토사로 쌓여진 제체에 차수막이 접촉되면 지반침하에 따라 차수막의 변위를 유발하게 되며 접촉부에서 전단저항이 발생하여 차수막에 인장력이 발생하기 때문에 차수막이 자유롭게 이동할 수 있도록 처리된다. 이러한 인장력이 발생하지 않도록 제체위에 그림 2에서 보여주는 바와 같이 얇은 지오텍스타일이나 차수막을 포설하여 차수막과 제체의 토사가 직접 접촉하지 않도록 하거나 그림 3과 같이 제체와 연약지반이 만나는 곳에 연약지반의 침하량만큼 설치시 차수막을 주름지게 하여 차수막에 인장력이 발생하지 않도록 하는 것을 특징으로 한다.According to the first aspect of the present invention, there is a need for a body of a predetermined height and a water shield to separate the water from the ground in order to desalination water. In this case, the rigid layer may be used to resist the generated stress and the flexible layer may be free of deformation, but the soft layer may be used because the settlement and deformation of the soft ground are considerably large. These flexible barriers have low ultimate stresses, so care should be taken to avoid possible stresses. The place where stress can be generated is the part where the body and the lining layer are in contact. When the lining layer comes in contact with the piled up soil, it causes the displacement of the lining layer due to the ground subsidence. Therefore, the curtain is processed to move freely. In order to prevent this tension from occurring, a thin geotextile or a lining film is placed on the body to prevent direct contact between the sediment and the soil of the body or as settled in the soft ground where the body and the soft ground meet as shown in Fig. 3. When the installation is characterized in that the wrinkles to prevent the tensile force is generated in the membrane.

본 발명의 두 번째 특징에 따르면, 물하중을 가하여 연약지반을 압밀침하시킬 때 발생하는 압밀침출수를 배수하기 위하여 그림 4와 같이 연성차수막을 관통하여 sand mat 층에 도달한 파이프를 설치하고, 파이프 안에 펌프를 설치하여 압밀침출수를 배수할 수 있도록 되어 있는 장치가 제공된다.According to the second aspect of the present invention, in order to drain the condensed leachate generated when the soft ground is consolidated by applying water load, a pipe having reached the sand mat layer through the flexible water barrier as shown in Fig. 4 is installed, and A device is provided which allows the installation of a pump to drain consolidation leachate.

본 발명의 세 번째 특징에 따르면, 연성 차수막을 연약지반 위에 설치하므로 연약지반의 침하 양상 및 침하 관리를 위한 침하계와 과잉간극수압계는 지중에 매설되게 되며 무선이나 지중에 매설된 유선으로 계측을 수행하게 된다. 또한, 물 하중 재하시 연성 차수막의 안정성을 확보하기 위하여 연성 차수막의 균열 발생 여부를 확인할 수 있는 모니터링 시스템으로 쓰레기 매립지 관리 방법으로 이용되는 전기적 방법이나 음향 모니터링 시스템이 사용되는 것을 특징으로 한다.According to the third aspect of the present invention, since the soft liner is installed on the soft ground, the settlement system and the excess pore pressure gauge for the settlement and settlement management of the soft ground are buried in the ground, and the measurement is performed by wire or wirelessly embedded in the ground. Will be performed. In addition, in order to ensure the stability of the flexible liner under water load load, the electric system or the acoustic monitoring system used as a landfill management method is used as a monitoring system that can determine whether the crack of the flexible liner.

이하, 본 발명의 바람직한 실시 예를 첨부한 도면에 의거하여 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

도 1은 본 발명에 따른 물을 재하 하중으로 이용한 연약지반 개량공법을 도시한 것으로, 연약지반에서 물을 하중으로 이용하여 연약지반을 개량할 수 있도록 물을 담수할 수 있는 차수막, 압밀침출수 배수방법, 차수막의 모니터링 방법 및 보수 방법으로 구성된다.1 illustrates a soft ground improvement method using water as a loading load according to the present invention, a water repellent membrane and consolidation leachate drainage method capable of freshening water to improve the soft ground using water as a load in the soft ground. It consists of a monitoring method and a repair method of the curtain.

도 1과 같이 연약지반위에 sand mat층을 포설한 하고 연직배수재를 타설한 후 그 위에 차수막을 설치하고 압밀침출수를 배수할 수 있도록 한 다음 담수를 하여 연약지반을 개량하는 것을 특징으로 하는 연약지반 개량공법이 제공된다.After installing a sand mat layer on the soft ground as shown in Figure 1 and installing a vertical drainage material, install a water curtain on it to drain the condensed leachate, and then improve the soft ground, characterized in that to improve the soft ground by fresh water A method is provided.

도 2와 3은 차수막이 제체와 접촉하는 경우 발생할 수 있는 응력 발생을 배제하기 위하여 방법을 제시한 것으로, 차수막이 제체와 접촉하지 않거나 미리 침하량 만큼 주름을 주어 인장 응력 발생을 억제한다.2 and 3 illustrate a method for excluding stresses that may occur when the liner is in contact with the body, and the liner is not in contact with the body or is wrinkled by the amount of settlement in advance to suppress the generation of tensile stress.

도 4는 압밀 중에 발생하는 압밀 침출수를 배수하는 방법으로 파이프를 sand mat층까지 설치하고 파이프안에 펌프를 설치하여 압밀 침출수를 배수하는 방법을 보여준다.4 shows a method of draining the consolidation leachate by installing the pipe to the sand mat layer and installing a pump in the pipe by the method of draining the consolidation leachate generated during consolidation.

이상에서와 같이 본 발명에 의하면, 자연환경의 파괴를 최소화하며 저렴한 공사비로 연약지반을 개량할 수 있는 연약지반 개량 공법이 제안되어 해수나 강물이 이용될 수 있는 대규모 연약지반에 대하여 개량이 용이해져 국토개발에 상당한 도움이 될 것으로 판단된다.As described above, according to the present invention, a soft ground improvement method for minimizing the destruction of the natural environment and improving the soft ground at an inexpensive construction cost is proposed, so that the improvement of the large soft ground where seawater or river water can be used becomes easy. It is expected to be of great help to national development.

Claims (1)

물을 재하 하중으로 이용한 대규모 연약지반 개량공법에 관한 특허Patent on large-scale soft ground improvement method using water as load 연약지반에서 물을 하중으로 이용하여 연약지반을 개량할 수 있도록 물을 담수할 수 있는 차수막, 압밀침출수 배수방법, 차수막의 모니터링 방법 및 보수 방법으로 구성되며, 담수시 차수막의 안정성을 확보하며 압밀침출수를 배수할 수 있고, 차수막의 유지보수가 가능한 연약지반 개량공법.It consists of a water line membrane, condensed leachate drainage method, a monitoring method and a repair method of the water layer to improve the soft ground by using water as a load on the soft ground. It is a soft ground improvement method that can drain water and maintain the curtain.
KR1020020040891A 2002-07-12 2002-07-12 Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land KR20020068988A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020020040891A KR20020068988A (en) 2002-07-12 2002-07-12 Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land
KR10-2002-0049446A KR100463314B1 (en) 2002-07-12 2002-08-21 Soil Improvement Method of Soft Clay Using Water as Surcharge Load in Large Land

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020020040891A KR20020068988A (en) 2002-07-12 2002-07-12 Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land

Publications (1)

Publication Number Publication Date
KR20020068988A true KR20020068988A (en) 2002-08-28

Family

ID=27727289

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1020020040891A KR20020068988A (en) 2002-07-12 2002-07-12 Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land
KR10-2002-0049446A KR100463314B1 (en) 2002-07-12 2002-08-21 Soil Improvement Method of Soft Clay Using Water as Surcharge Load in Large Land

Family Applications After (1)

Application Number Title Priority Date Filing Date
KR10-2002-0049446A KR100463314B1 (en) 2002-07-12 2002-08-21 Soil Improvement Method of Soft Clay Using Water as Surcharge Load in Large Land

Country Status (1)

Country Link
KR (2) KR20020068988A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100870465B1 (en) * 2007-02-12 2008-11-25 장지건 Preloading method by controlling of buoyancy

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS569515A (en) * 1979-07-05 1981-01-31 Okumura Constr Co Ltd Load applying method for consolidation of weak ground
JPS5751321A (en) * 1980-09-13 1982-03-26 Matsuo Consultant Kk Gradual increase of effective load by low atmospheric pressure in acceleration method for consolidation under water
JPS57146817A (en) * 1981-03-03 1982-09-10 Matsuo Consultant Kk Confinement of sludge by promoting vacuum consolidation
JPS6160919A (en) * 1984-09-03 1986-03-28 Hazama Gumi Ltd Method of improving ground for prevention of liquefaction
FR2627202B1 (en) * 1988-02-15 1992-04-17 Menard Soltraitement METHOD AND APPARATUS FOR CONSOLIDATION OF LANDS
JPH02136419A (en) * 1988-11-15 1990-05-25 Kajima Corp Ground improvement of artificial island
JP2564500Y2 (en) * 1993-02-15 1998-03-09 株式会社ジャレコ Flag swing game machine
KR0155668B1 (en) * 1995-11-28 1998-11-16 이재영 Water loading method of poor subsoil
KR100195689B1 (en) * 1996-09-14 1999-06-15 유영을 Quick consolidated method using pipe drain system
JP4058550B2 (en) * 1997-08-22 2008-03-12 丸山工業株式会社 Improvement method for soft ground
KR200209544Y1 (en) * 1998-07-15 2001-01-15 최문규 Flexible synthetic resin lining for landfill construction
JP2001011847A (en) * 1999-07-01 2001-01-16 Mitsui Harbour & Urban Construction Co Ltd Mounting load increasing and decreasing method
KR100348515B1 (en) * 1999-10-22 2002-08-10 (주)대우건설 Engineering methods to improve subsurface of soft ground
KR200188225Y1 (en) * 2000-02-08 2000-07-15 주식회사한국 종합엔지니어링 Air tube dike to make water reservoir instead of soil fill for surcharge load to use soil improvement of cohesion soil
KR20020024199A (en) * 2002-02-02 2002-03-29 김정 Land stabilization method by vacuum dehydration
KR100995251B1 (en) * 2008-07-11 2010-11-19 한국표준과학연구원 Current transformer comparator system

Also Published As

Publication number Publication date
KR20040007191A (en) 2004-01-24
KR100463314B1 (en) 2004-12-29

Similar Documents

Publication Publication Date Title
Chu et al. Geosynthetic tubes and geosynthetic mats: Analyses and applications
Chu et al. Vacuum preloading techniques—recent developments and applications
CN100443672C (en) Underpinning method of pile ground underground
CN101144281B (en) Floating flashboard machine and large area ultra-weak foundation fast directly draining concretion method
CN109083100B (en) River channel excavation construction process after mud blowing and landing
CN112523264B (en) High-steep side slope seepage prevention system and laying method thereof
Jebelli et al. Excavation failure during micro-tunneling in fine sands: A case study
CN204825926U (en) Utilize excavation supporting system of atmosphere pressure as holding power
Saowapakpiboon et al. Vacuum-PVD combination with embankment loading consolidation in soft Bangkok clay: a case study of the Suvarnabhumi Airport Project
Cossu Engineering of landfill barrier systems
CN108589694B (en) Subway protection method for unloading earthwork on tunnel by adopting vacuum preloading
JP2015031148A (en) Device for both cavity volume inspection and uplift pressure removal, and method for installing the same
KR20020068988A (en) Soil Improvement Method of Soft Clay Using Sea Water as Surcharge Load in Large Land
Song et al. Improvement of estuarine marine clays for coastal reclamation using vacuum-applied consolidation method
Dixit Damage mechanism in problematic soils
Chu et al. Embankments on soft ground and ground improvement
Griffin et al. Sustainability of combined vacuum and surcharge preloading
CN209353360U (en) The anti-floating drainage arrangement of basement structure
CN105089060A (en) Foundation pit support system using atmospheric pressure as support force
JP2007107316A (en) Method of temporarily recovering pavement surface in burying work of underground buried object
CN210216453U (en) Slope roof supporting and drainage ditch structure
JP2007105618A (en) Water barrier structure of waste landfill site
CN216892565U (en) Non-excavation of sewer line inspection shaft bottom part local seepage restores structure
CN218845305U (en) Protection structure for existing underground pipeline in foundation pit
TW496921B (en) Pressure relief construction method of foundation used in existed building with damage problem caused by floating force

Legal Events

Date Code Title Description
A201 Request for examination