KR20010070900A - Apparatus laying pipes underground for public engineering and construction - Google Patents

Apparatus laying pipes underground for public engineering and construction Download PDF

Info

Publication number
KR20010070900A
KR20010070900A KR1020010034422A KR20010034422A KR20010070900A KR 20010070900 A KR20010070900 A KR 20010070900A KR 1020010034422 A KR1020010034422 A KR 1020010034422A KR 20010034422 A KR20010034422 A KR 20010034422A KR 20010070900 A KR20010070900 A KR 20010070900A
Authority
KR
South Korea
Prior art keywords
auger
pipe
buried pipe
propulsion
soil
Prior art date
Application number
KR1020010034422A
Other languages
Korean (ko)
Inventor
김대용
Original Assignee
김대용
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김대용 filed Critical 김대용
Priority to KR1020010034422A priority Critical patent/KR20010070900A/en
Publication of KR20010070900A publication Critical patent/KR20010070900A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes

Abstract

PURPOSE: A buried pipe propelling and inserting apparatus for civil engineering works is provided to prevent the twisting and damage of an auger and to effectively discharge earth and sand through the auger by shortening the length of the auger. CONSTITUTION: A cylindrical casing(15) is connected with an inclined pipe(17). An auger(10) is inserted inside the casing. The auger is connected with an auger head(14) and protruded in the back of the casing. The back of the auger is connected with a shaft of a motor(18) inside a backup pipe(13). An earth discharging pump(19) is installed inside the backup pipe to discharge earth and sand from the casing. An earth discharging pipe(21) is connected with an outlet(20) of the earth discharging pump to discharge the earth and sand by penetrating the inside of a buried pipe(2).

Description

토목공사용 매설관 추진삽입장치{Apparatus laying pipes underground for public engineering and construction}Apparatus laying pipes underground for public engineering and construction}

본 발명은 토목공사시에 철도나 도로 및 제방, 하천등의 하부에 매설관을 수평으로 관통되게 설치하는 토목공사용 매설관 추진삽입장치에 관한 것으로, 더욱 상세하게는 매설관을 수평으로 추진하여 삽입하는 매설관 추진 삽입장치의 선도체 내부에 한 개의 오거와 이 오거를 구동시킬 수 있는 모터를 설치하고, 이 오거의 후단에는 오거를 통해 후방으로 배출되는 토사를 매설관의 외부로 배출할 수 있도록 하는 토사배출용 펌프를 설치하며, 펌프의 후단으로는 토사배출용 배출관이 연속적으로 연결될 수 있도록 함으로서, 오거의 길이가 짧아져서 오거의 비틀림과 손상을 방지하고 오거를 통하여 후방으로 배출되는 토사를 효과적으로 배출시킬 수 있도록 하는 것이다.The present invention relates to a buried pipe propulsion insertion device for civil engineering to install a buried pipe horizontally through a lower part of a railroad, a road, a levee, a river, etc., and more specifically, to protrude and insert a buried pipe horizontally. An auger and a motor for driving the auger are installed inside the lead body of the buried pipe propulsion inserter, and the rear end of the auger allows the soil discharged backward through the auger to be discharged to the outside of the buried pipe. By installing a pump for earth and sand discharge, the discharge pipe for earth and sand discharge can be connected continuously to the rear end of the pump, so that the auger's length is shortened to prevent twisting and damage of the auger and effectively discharge the earth and sand discharged backward through the auger. To make it possible.

일반적으로 토목공사시에 철도나 도로 및 제방, 하천등의 하부에 상하수관이나 전선 및 통신케이블 등을 설치하기 위해서는 도로나 제방, 하천등의 하부 땅속에 커다란 매설관을 매설한 뒤에 그 매설관의 내부에 위에서 언급한 상하수관이나 전선 및 통신케이블 등을 설치한다.In general, in order to install water supply and sewage pipes, electric wires, and communication cables in the lower part of railroads, roads, banks, and rivers during civil engineering work, after embedding large burial pipes in the lower ground of roads, banks, rivers, etc. Install water and sewage pipes, wires and communication cables mentioned above.

상기와 같이 땅속에 상하수관이나 전선 및 통신케이블 등을 설치하기 위해서는 땅속에 직경이 큰 흄관이나 강관등의 매설관을 설치해야 하는데, 종래의 일반적인 매설관의 설치과정에 대하여 도 1의 (가)(나)(다)를 참고하여 살펴보면 다음과같다.As described above, in order to install water and sewage pipes, electric wires, and communication cables in the ground, a buried pipe such as a fume pipe or a steel pipe having a large diameter must be installed in the ground, and the installation process of a conventional general buried pipe is shown in FIG. Referring to (b) (c), it is as follows.

매설관을 땅속에 매설하기 위해서는 제일 먼저, 도 1의 (가)에서 보는 바와 같이 매설관(2)이 매설될 깊이만큼 땅을 도랑형태로 파낸 뒤에 파낸 측벽이 무너지지 않도록 H빔 파일(3)을 측벽에 연속적으로 박아서 측벽의 토사가 흘러내리지 않게 한다.In order to embed the buried pipe in the ground, first, as shown in (a) of FIG. 1, the H-beam pile 3 is installed so that the sidewalls dug after digging the ground into the depth to be buried are formed. It is continuously driven into the side wall so that the soil of the side wall does not flow down.

이렇게 도랑형태로 땅을 파내고 양측벽에 토사가 흘러내리지 않게 한 뒤에는 도랑형태의 굴착홈에 다수개의 매설관(2)을 서로 연결되게 나열 배치하고, 이렇게 나열된 다수의 매설관(2)을 이음수단으로 각각의 매설관을 연결하며, 그 뒤에 상기 도랑형태의 굴착홈의 양측에 박아 놓았던 H빔 파일(3)을 제거하고, 그 굴착홈에 토사를 채워서 다수의 매설관(2)이 도 1의 (다)와 같이 땅속에 매설되게 한다. 도 1의 "1"은 제방을 나타내고 있다.After digging the ground in the form of a trench and preventing the soil from flowing down on both sides of the wall, a plurality of buried pipes (2) are arranged to be connected to each other in a trench-shaped excavation groove, and the plurality of buried pipes (2) thus listed are connected. Each buried pipe is connected by means, and after that, the H beam piles 3 which are embedded in both sides of the trench-type excavation groove are removed, and a plurality of buried pipes 2 are filled by filling the excavation groove with soil. To be buried in the ground as "1" in FIG. 1 represents a dike.

이렇게 도랑형태로 땅을 파낸 뒤에 다수의 매설관을 매설하는 종래의 방법은 지반을 직접 절개하므로 절개된 구간으로의 차량 및 행인의 통행이 불가능하여 교통체증을 유발시키는 문제와, 공사비용이 상승되는 등의 심각한 문제가 있었다.The conventional method of embedding a large number of buried pipes after digging in the form of trenches in this way directly cuts the ground, making it impossible to pass vehicles and pedestrians to the cut sections, causing traffic jams and increasing construction costs. There was a serious problem.

따라서, 상기와 같은 문제를 감안하여 지반을 절개하지 않고 매설관을 땅속에 직접 수평으로 관통하게 하는 매설관 추진 삽입장치와 시공방법 개발되어 매우 유용하게 사용되고 있다.Accordingly, in view of the above problems, buried pipe propulsion inserting device and construction method for penetrating the buried pipe directly and horizontally into the ground without cutting the ground have been developed very usefully.

상기와 같은 종래의 매설관 추진 삽입장치(22)는 도 2에서 보는 바와 같이, 매설관을 추진 삽입할 토층을 절개한 절개지(발진입항:a)의 바닥에 설치되는 베드(4)의 후방 상부에는 유압실린더(5)에 의해 베드(4) 상에서 수평으로 슬라이딩이동이 가능한 추진기본체(6)가 설치되고, 이 추진기본체(6)의 전방에는 유압실린더(5)에 밀려나며 매설관(2)을 밀어주는 추진판(7)이 설치되어 있다.The conventional buried pipe propulsion insertion device 22 as described above, as shown in Figure 2, the upper portion of the rear of the bed (4) is installed on the bottom of the incision (entry entry: a) cut in the soil layer to insert the buried pipe The propulsion main body 6 which is slidably moved horizontally on the bed 4 by the hydraulic cylinder 5 is installed, and is pushed by the hydraulic cylinder 5 in front of the propulsion base 6 and the buried pipe 2 The propulsion plate 7 for pushing the pressure is provided.

그리고, 상기 추진판(7) 후방의 추진기본체(6)에는 모터(8)에 의해 회전하며 오거(10)의 후단부를 클램핑하여 오거(10)를 회전시키는 오거클램프(9)가 설치되며, 상기 베드(4)의 상부에는 토층을 수평으로 굴착하며 굴착되는 수평구멍으로 삽입 추진되는 선도체(12)가 착탈식으로 설치된다.In addition, an auger clamp 9 for rotating the auger 10 by rotating the motor 8 and clamping the rear end of the auger 10 is installed in the propulsion body 6 behind the propulsion plate 7. On the upper part of the bed 4, the leader 12 is inserted into a horizontal hole to excavate the soil layer horizontally is excavated and detachably installed.

상기 선도체(12)는 토층으로 추진 삽입되는 백업파이프(13)의 선단부에 토층을 굴착하는 오거헤드(14)가 설치되고, 이 오거헤드(14)의 후단 백업파이프(13)의 내부에는 백업파이프(13)의 전길이에 걸쳐 외부에 케이싱(15)이 삽입된 오거(10)가 설치되어 있다.The lead body 12 is provided with an auger head 14 for excavating the soil layer at the distal end of the backup pipe 13 propelled into the soil layer, and the backing pipe 13 at the rear end of the auger head 14 is backed up. The auger 10 in which the casing 15 was inserted in the outside over the full length of the pipe 13 is provided.

그리고, 선도체(12)에 의해 토층을 굴착하여 수평구멍으로 추진 삽입된 뒤에는 선도체(12)의 오거(10)를 오거클램프(9)에서 분리한 뒤에 추진기본체(6)를 후퇴시켜 추진기본체(6)의 선단부와 선도체(12)의 후단사이에 삽입시켜 연결하는 매설관 결합체(16)가 연속하여 연결되도록 되어 있다.After excavating and inserting the soil layer by the lead body 12 into the horizontal hole, the auger 10 of the lead body 12 is separated from the auger clamp 9, and then the propulsion body 6 is retracted to retract the propulsion body. The buried pipe assembly 16 inserted and connected between the leading end of 6 and the rear end of the lead 12 is connected continuously.

상기 매설관 결합체(16)는 선도체(12)의 백업파이프(13)와 연결되는 매설관(2)의 내부에 선도체(12)의 케이싱(15)과 연결되는 케이싱(11)이 매설관(2)의 전길이에 걸쳐 삽입되고, 이 케이싱(11)의 내부에는 선도체(12)의 오거(10)와 연결되는 오거(10)가 삽입되어 있다.The buried pipe assembly 16 is a buried pipe casing 11 connected to the casing 15 of the leader 12 in the buried pipe (2) connected to the backup pipe 13 of the leader (12) The auger 10 inserted over the full length of (2) and connected to the auger 10 of the lead body 12 is inserted in this casing 11.

이와 같이 구성된 종래의 매설관 추진삽입장치(22)에 의하여 토층에 매설관을 삽입 추진하고자 하는 경우에는 도 2 및 도 3에서 보는 바와 같이 매설관을 매설할 토층의 일측 선단 토층을 굴착하여 발진입항(a)을 형성하고, 이 발진입항(a)에 매설관 추진삽입장치(22)를 설치한다.(도 3의 (가) 참조)When the buried pipe is to be inserted into the soil layer by the conventional buried pipe propulsion insertion device 22 configured as described above, as shown in FIGS. 2 and 3, one end of the soil layer on which the buried pipe is to be buried is excavated to enter and enter the port. (a) is formed, and the buried pipe propulsion insertion device 22 is installed in this oscillation entry port (a) (refer to (a) of FIG. 3).

이때, 매설관 추진삽입장치(22)의 추진기본체(6)의 전방 베드(4)상에 선도체(12)가 장착된 상태이며, 이상태에서 추진기본체(6)에 설치되어 있는 모터(8)와 유압실린더(5)를 구동시키게 되면, 모터(8)의 회전력이 오거클램프(9)에 전달되어 오거클램프(9)을 회전시키게 되고, 이 오거클램프(9)에는 선단부에 오거헤드(14)가 장착된 오거(10)가 회전하여 토층을 굴착하게 되며, 유압실린더(5)에 의해서는 추진기본체(6)를 비롯한 추진기본체(6)의 선단에 설치되어 있는 추진판(7)이 전방으로 수평이동하여 추진판(7)에 말단부가 접촉하고 있는 선도체(12)의 백업파이프(13)가 전방으로 추진하게 된다.At this time, the lead body 12 is mounted on the front bed 4 of the propulsion body 6 of the buried pipe propulsion insertion device 22, and in this state, the motor 8 installed in the propulsion body 6. When the hydraulic cylinder 5 is driven, the rotational force of the motor 8 is transmitted to the auger clamp 9 to rotate the auger clamp 9, and the auger clamp 14 has an auger head 14 at its distal end. Is equipped with auger (10) is rotated to excavate the soil layer, by the hydraulic cylinder (5) the propulsion plate (7) installed at the tip of the propulsion body (6) including the propulsion body (6) to the front. The back-up pipe 13 of the leader body 12 which is distal to the propelling plate 7 in contact with the propulsion plate 7 is moved forward.

상기와 같이 오거헤드(14)가 회전하고 백업파이프(13)가 전방으로 수평이동함에 따라 오거헤드(14)에 의해 토층이 원형으로 굴착되어 수평구멍이 형성된 공간으로 백업파이프(13)를 비롯한 선도체(12)가 추진 삽입하게 되는 것이며, 오거헤드(14)로서 토층을 굴착시 발생하는 토사는 케이싱(15) 내의 오거(10)에 의해 후방으로 밀려나가면서 추진판(7) 후방으로 토사배출공간(7a)으로 배출되게 된다.As the auger head 14 rotates as described above and the backup pipe 13 moves horizontally forward, the soil layer is excavated in a circular shape by the auger head 14, and a diagram including the backup pipe 13 is formed in a horizontal hole. The sieve 12 is to be propelled and inserted, and the earth and sand generated during the excavation of the soil layer as the auger head 14 is pushed backward by the auger 10 in the casing 15, and the earth and sand discharge space behind the propulsion plate 7. It is discharged to 7a.

이렇게 선도체(12)가 토층을 굴착하며 토층에 형성되는 수평구멍으로 모두 삽입되면, 오거(10)의 후단부를 오거클램프(9)에서 분리한 뒤에 유압실린더(5)를 후진되게 동작시켜 추진기본체(6)가 후진하도록 하여 토층으로 추진 삽입된 선도체(12)의 후방과 추진기본체(6)의 전방사이에 매설관 결합체(16)가 삽입될 수있는 공간을 확보한다.When the lead body 12 excavates the soil layer and is inserted into the horizontal hole formed in the soil layer, the rear end portion of the auger 10 is separated from the auger clamp 9, and the hydraulic cylinder 5 is operated backward so as to protrude the main body. (6) to the reverse to secure a space for the buried pipe assembly 16 can be inserted between the rear of the leading body (12) propelled into the soil layer and the front of the propulsion body (6).

상기와 같이 선도체(12)의 후방과 추진기본체(6)의 전방사이에 매설관 결합체(16)가 삽입될 수 있는 공간을 확보한 뒤에는 도 3의 (나)에서 보는 바와 같이 선도체(12)의 후방과 추진기본체(6)의 전방사이에 확보된 공간으로 매설관 결합체(16)를 내려서 매설관 결합체(16)의 오거(10) 선단부는 선도체(12)의 오거(10) 후단부에 연결하면서 선도체(12)의 케이싱(15)과 매설관 결합체(16)의 케이싱(11) 선단부를 연결하고, 매설관 결합체(16)의 후단부는 추진기본체(6)의 오거클램프(9)에 클램핑되게 한다.After securing the space in which the buried pipe assembly 16 can be inserted between the rear of the lead body 12 and the front of the propulsion body 6 as described above, as shown in (b) of FIG. ) The lower end of the auger 10 of the buried pipe joint 16 into the space secured between the rear of the back and the front of the propulsion body 6, and the rear end of the auger 10 of the leader 12. The casing 15 of the lead body 12 and the tip of the casing 11 of the buried pipe joint 16 are connected to each other, and the rear end of the buried pipe joint 16 is an auger clamp 9 of the propelling body 6. To be clamped.

또한, 볼트 또는 끼움식으로 착탈이 가능한 상기 선도체(12)의 백업파이프(13) 후단부와 매설관 결합체(16)의 매설관(2) 선단부를 착탈식으로 설치한 뒤에 유압실린더(5)를 작동시키면서 모터(8)를 구동시키면, 모터(8)의 회전력이 오거(10)에 전달되어 선도체(12)의 선단에 설치되어 있는 오거헤드(14)를 회전시켜서 토층을 굴착하게 되고, 유압실린더(5)의 작동에 의해서는 추진기본체(6)를 전방으로 수평이동시킴에 따라 추진판(7)이 추진기본체(6)와 함께 전방으로 수평이동하면서 매설관 결합체(16)의 매설관(2) 후방을 전방으로 밀게 되어 선도체(12)가 토층을 굴착하면서 그 굴착에 의해 형성되는 수평구멍으로 선도체(12)부터 선도체(12)와 연결된 매설관 결합체(16)가 추진 삽입하게 되며, 이렇게 토층을 굴착하는 과정에서 발생되는 토사는 오거(10)를 통해 후방으로 밀려 나오면서 토사배출공간(7a)을 통해 외부로 배출된다.In addition, the hydraulic cylinder (5) is installed after detachably installing the rear end of the backup pipe (13) of the leader (12) and the buried pipe (2) of the buried pipe assembly (16), which are detachable by bolts or fittings. When the motor 8 is driven while operating, the rotational force of the motor 8 is transmitted to the auger 10 to rotate the auger head 14 installed at the tip of the lead body 12 to excavate the soil layer. The operation of the cylinder 5 causes the propulsion body 6 to move horizontally forward, so that the propulsion plate 7 moves horizontally forward with the propulsion body 6 to bury the buried pipe assembly 16. 2) Push the rear to the front so that the lead body 12 excavates the soil layer so that the buried pipe joint 16 connected to the lead body 12 from the lead body 12 is propelled into the horizontal hole formed by the excavation. Soil generated during the excavation of the soil layer is rear through the auger (10) Naohmyeonseo is pushed through the soil discharge space (7a) discharged to the outside.

이렇게 선도체(12) 후방에 매설관 결합체(16)를 착탈가능하게 연결하여 토층을 굴착하고 추진삽입한 뒤에는 위에서 선도체(12)만을 이용한 뒤에 매설관 결합체(16)를 연결하여 토층을 굴착하고 선도체(12)과 매설관 결합체(16)를 굴착에 의해 형성된 수평구멍으로 추진삽입 시킨 과정을 반복적으로 실시하여 다수개의 매설관 결합체(16)가 서로 연결되면서 매설관을 토층에 수평으로 추진 삽입시키면서 매설한다.The excavation of the soil layer by detachably connecting the buried pipe joint 16 to the rear of the lead body 12 and then pushing and inserting the soil layer after connecting the buried pipe joint 16 using only the lead body 12 from above. The process of repeatedly propelling the lead body 12 and the buried pipe assembly 16 into the horizontal hole formed by excavation is carried out repeatedly, and the buried pipe assembly 16 is connected to each other and the buried pipe is pushed horizontally into the soil layer. Buried while burying.

이때 다수개의 매설관 결합체(16)가 연결되는 것은 케이싱(11) 끼리와 오거(10) 끼리의 연결은 착탈식으로 이루어지나 매설관(2) 끼리의 연결은 용접에 의해서 연결됨을 밝혀 둔다.In this case, the plurality of buried pipe joints 16 are connected to the casing 11 and the auger 10 between the connection is made of detachable, but the connection between the buried pipe (2) is revealed that the connection by welding.

상기와 같은 과정을 통하여 다수개의 매설관(2)을 매설할 길이 만큼 추진 매설하여 선도체(12)가 도달기지의 도착항(b)에 도착하면, 도 3의 (라) 내지 (바)에서 보는 바와 같이 도착항(b)으로 관통하여 나온 선도체(12)를 제일 앞단의 매설관 결합체(16)에서 분리하여 회수하고, 각각의 매설관 결합체(16)의 매설관(2) 내부에 삽입되어 있는 오거(10)와 오거(10) 외측의 케이싱(11)을 분리하여 회수하면 각각의 매설관(2)은 용접에 의해 서로 연결된 상태로 중공상태로 토층 내부에 수평으로 매설되게 된다.Propelled and buried as long as the length of the buried pipe (2) to be buried through the above process, when the lead body 12 arrives at the arrival port (b) of the arrival base, as shown in (d) to (bar) of FIG. As described above, the lead body 12 penetrating into the arrival port (b) is separated and recovered from the buried pipe assembly 16 at the foremost end, and inserted into the buried pipe 2 of each buried pipe assembly 16. When the auger 10 and the casing 11 outside the auger 10 are separated and recovered, each buried pipe 2 is horizontally embedded in the soil layer in a hollow state while being connected to each other by welding.

상기 토층에 매설된 다수의 매설관(2)은 중공상태이므로 상하수도관으로 사용하거나, 또는 그 내부로 상하수도관이나, 전기 및 통신 케이블, 가스배관 등을 삽입설치할 수 있는 것이다.Since the plurality of buried pipes (2) buried in the soil layer is a hollow state can be used as a water and sewage pipe, or can be installed into the water and sewage pipe, electrical and communication cables, gas pipes and the like.

이와 같은 종래의 매설관 추진삽입장치(22)에 의해 매설관을 지중에 매설하게 되면 토층을 절개하지 않기 때문에 차량 및 행인의 통행에 전혀 지장을 주지 않는 효과와 작업이 편리한 효과가 있었다.When the buried pipe is buried in the ground by the conventional buried pipe propulsion insertion device 22, since the soil layer is not cut, there is an effect that does not interfere with the traffic of the vehicle and the pedestrian at all.

그러나, 이는 다수개의 매설관(2)의 내부 전길이에 매설관(2)과 동일한 길이의 오거(10)가 연속적으로 연결되어 설치되므로 이 오거(10)의 전체 연결된 길이가 100여미터에 까지 이르는 관계로 추진기본체(6)의 오거클램프(9)에 클램핑되어 회전하는 오거(10)에 비틀림이 발생하게 되고, 오거(10)의 비틀림에 의해 오거헤드(14)에 의해 굴착되는 토사가 후방으로 제대로 배출되지 못하게됨은 물론이고, 오거회전시 부하가 발생되면서 토층을 제대로 굴착하지 못하게 되는 문제를 지니고 있었다.However, this is because the augers 10 of the same length as the buried pipes 2 are continuously connected to the entire length of the buried pipes 2, so that the total connected length of the augers 10 is up to about 100 meters. Torque is generated in the auger 10, which is clamped to the auger clamp 9 of the propulsion body 6 and rotates, and the soil excavated by the auger head 14 by the auger 10 is rearward. As well as not being properly discharged, as the load is generated when the auger rotation had a problem that can not properly excavate the soil.

본 발명은 상기의 문제점을 해결하기 위하여 매설관을 수평으로 추진하여 삽입하는 매설관 추진 삽입장치의 선도체 내부에 한 개의 오거와 이 오거를 구동시킬 수 있는 모터를 설치하고, 이 오거의 후단에는 오거를 통해 후방으로 배출되는 토사를 매설관의 외부로 배출할 수 있도록 하는 토사배출용 펌프를 설치하며, 펌프의 후단으로는 토사배출용 배출관이 연속적으로 연결될 수 있도록 함으로서, 오거의 길이가 짧아져서 오거의 비틀림과 그로 인한 손상을 방지하고 오거를 통하여 후방으로 배출되는 토사를 효과적으로 배출시킬 수 있도록 하는 것을 기술적 과제로 한다.In order to solve the above problems, an auger and a motor capable of driving the auger are installed in a leader body of a buried pipe propulsion inserting device for horizontally pushing and inserting a buried pipe. Install the pump for earth and sand discharge to discharge the earth and sand discharged to the rear through the auger to the outside of the buried pipe, and the end of the pump can be connected to the discharge pipe for earth and sand discharged continuously, the length of the auger is shortened The technical task is to prevent twisting of the auger and its damage, and to effectively discharge the soil discharged backward through the auger.

상기의 목적을 달성하기 위한 본 발명은 베드의 후방 상부에 추진기본체가 유압실린더에 의해 수평으로 슬라이딩 이동이 가능하게 설치되고, 추진기본체의 전방에는 모터의 동력에 의해 회전하면서 토층을 오거헤드로서 굴착하고 굴착과정에서 발생되는 토사를 오거를 통하여 후방으로 배출시키며 오거헤드에 의해 굴착되는 수평구멍으로 유압실린더에 의해 추진 삽입되는 선도체가 설치되며, 수평구멍으로 추진 삽입된 선도체와 추진기본체가 분리된 뒤에 추진기본체를 후퇴시켜 추진기본체의 선단부와 선도체의 후단사이에 매설관을 삽입시켜 연결하면서 매설관을 토층에 수평으로 매설하는 것에 있어서, 상기 선도체의 선단부 내측에 삽입 설치된 경사관의 후방에는 백업파이프보다 길이가 짧은 원통관 형태의 케이싱이 연결되고, 상기 케이싱의 내부에는 선단부가 오거헤드의 후단부와 연결되고 후단부는 케이싱의 후단으로 돌출되는 오거가 삽입 설치되며, 상기 오거의 후단부는 백업파이프의 내부에 설치된 모터의 축과 연결되며, 케이싱 후방의 백업파이프의 내측에는 케이싱을 통하여 배출되는 토사를 후방으로 배출시키는 토사배출펌프가 설치되고, 상기 토사배출펌프의 배출구 에는 매설관의 내부를 관통하여 후방으로 토사를 배출시키는 토사배출관이 연결설치되는 것을 특징으로 한다.The present invention for achieving the above object is installed on the rear upper portion of the bed so that the propulsion base can be moved horizontally by the hydraulic cylinder, excavation of the soil layer as an auger head while rotating by the power of the motor in front of the propulsion base body And discharge the earth and sand generated in the excavation process to the rear through the auger, and a leader inserted and pushed by the hydraulic cylinder into the horizontal hole excavated by the auger head. In the case of laying the buried pipe horizontally on the soil layer while retracting the propulsion body by inserting the buried pipe between the leading end of the propulsion body and the rear end of the lead body, the burr pipe is placed behind the inclined pipe inserted inside the leading end of the lead body. A casing in the form of a cylindrical tube shorter than the backup pipe is connected, and the casing Inside the front end is connected to the rear end of the auger head, the rear end is inserted into the auger protruding to the rear end of the casing, the rear end of the auger is connected to the shaft of the motor installed inside the backup pipe, the back of the backup pipe of the casing An earth and sand discharge pump for discharging the earth and sand discharged through the casing to the rear is installed, and the earth and sand discharge pipe for discharging the soil to the rear through the inside of the buried pipe is connected to the discharge port of the earth and sand discharge pump. .

도 1의 (가)(나)(다)는 제방등의 토목공사시 매설관의 설치과정을 나타내는 설명도.Figure 1 (a) (b) (c) is an explanatory diagram showing the installation process of the buried pipe during civil engineering works such as levees.

도 2는 종래의 매설관 추진 삽입장치를 나타내는 측단면도.Figure 2 is a side cross-sectional view showing a conventional buried pipe propulsion insertion device.

도 3의 (가) 내지 (바)는 종래의 매설관 추진 삽입장치를 이용하여 매설관을 설치하는 과정을 나타내는 설명도.Figure 3 (a) to (bar) is an explanatory diagram showing a process of installing a buried pipe using a conventional buried pipe propulsion inserting device.

도 4는 본 발명에 따른 매설관 추진 삽입장치를 나타내는 측단면도.Figure 4 is a side cross-sectional view showing a buried pipe propulsion insertion apparatus according to the present invention.

도 5는 도 4의 "A"부를 확대도시한 단면도.5 is an enlarged cross-sectional view of a portion “A” of FIG. 4.

도 6은 본 발명의 주요 구성요소인 토사배출관을 나타내는 도면이다.6 is a view showing a soil discharge pipe that is a major component of the present invention.

〈도면의 주요 부분에 대한 부호의 설명〉<Explanation of symbols for main parts of drawing>

1 : 제방 2 : 매설관 3 : H빔 파일1 Dike 2 Buried Pipe 3 H Beam File

4 : 베드 5 : 유압실린더 6 : 추진기본체4: bed 5: hydraulic cylinder 6: propulsion body

7 : 추진판 8 : 모터 9 : 오거클램프7 propulsion plate 8 motor 9 auger clamp

10 : 오거 11 : 케이싱 12 : 선도체10: Auger 11: Casing 12: Leader

13 : 백업파이프 14 : 오거헤드 15 : 케이싱13: Backup pipe 14: August head 15: Casing

16 : 매설관 결합체 17 : 경사관 18 : 모터16: buried pipe assembly 17: inclined pipe 18: motor

19 : 토사배출펌프 20 : 배출구 21 : 토사배출관19: soil discharge pump 20: outlet 21: soil discharge pipe

이하 본 발명에 따른 토목공사용 매설관 추진삽입장치에 대하여 첨부된 도면 도 4 및 도 5를 참고하여 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings Figures 4 and 5 for the civil engineering buried pipe propulsion insertion apparatus according to the present invention.

본 발명에 의한 토목공사용 매설관 추진삽입장치는, 상면 양측에 길이방향으로 가이드레일을 구비한 베드(4)의 후방 상부에 유압실린더(5)에 의해 수평으로 슬라이딩 이동이 가능한 추진기본체(6)가 설치되고, 이 추진기본체(6)의 전방에는 유압실린더(5)에 밀려나며 매설관(2)을 밀어주는 추진판(7)이 설치되며, 상기 추진판(7) 후방의 추진기본체(6)에는 모터(8)에 의해 회전하며 오거(10)의 후단부를 클램핑하는 오거클램프(9)가 설치되어 있다.The buried pipe propulsion insertion device for civil engineering according to the present invention, the propulsion main body (6) capable of horizontally sliding movement by the hydraulic cylinder (5) on the rear upper portion of the bed (4) having a guide rail in the longitudinal direction on both sides of the upper surface And a propulsion plate 7 pushed by the hydraulic cylinder 5 and pushing the buried pipe 2 in front of the propulsion body 6, and a propulsion body 6 behind the propulsion plate 7. ) Is provided with an auger clamp 9 that rotates by a motor 8 and clamps the rear end of the auger 10.

그리고, 상기 베드(4)의 상부에는 토층을 수평으로 굴착하며 굴착되는 수평구멍으로 삽입 추진되는 선도체(12)가 착탈식으로 설치되며, 상기 선도체(12)에 의해 토층을 굴착하여 수평구멍으로 추진 삽입된 뒤에는 선도체(12)의 오거(10)를 오거클램프(9)에서 분리한 뒤에 추진기본체(6)를 후퇴시켜 추진기본체(6)의 선단부와 선도체(12)의 후단사이에 삽입시켜 연결하는 매설관(2)가 연속하여 연결되도록 되어 있다.And, in the upper part of the bed (4), the leader 12 which is inserted into the horizontal hole is excavated horizontally excavating the soil layer is installed detachably, the soil layer is excavated by the leader 12 to the horizontal hole After propulsion insertion, the auger 10 of the lead body 12 is removed from the auger clamp 9, and then the propulsion body 6 is retracted and inserted between the leading end of the propulsion body 6 and the rear end of the lead body 12. The buried pipe 2 which connects by making it connect is made to connect continuously.

상기 선도체(12)는 원통관 형태로 형성된 백업파이프(13)의 선단부 내측에 전방이 넓고 후방이 좁은 경사관(17)이 설치되고 이 경사관(17)의 후방에는 원통형태의 케이싱(15)이 연결되며, 상기 경사관(17)의 선단부 내측에는 오거헤드(14)가 삽입 설치되고, 상기 케이싱(15)의 내부에는 오거(10)가 삽입되어 오거(10)의 선단부가 오거헤드(14)의 후단부와 연결되어 있다.The leading body 12 is provided with a wide inclined tube 17 having a wide front and a narrow rear in the front end portion of the backup pipe 13 formed in the shape of a cylindrical tube, and a cylindrical casing 15 at the rear of the inclined tube 17. ) Is connected, the auger head 14 is inserted into the tip end of the inclined tube 17, and the auger 10 is inserted into the casing 15 so that the tip end of the auger 10 is auger head ( It is connected to the rear end of 14).

상기 오거(10)의 후단부에는 백업파이프(13)의 내부에 설치된 모터(18)의 축과 연결되며, 케이싱(15) 후방의 백업파이프(13)의 내측에는 케이싱(15)을 통하여 배출되는 토사를 후방으로 배출시키는 토사배출펌프(19)가 설치되어 있다.The rear end of the auger 10 is connected to the shaft of the motor 18 installed inside the backup pipe 13, and is discharged through the casing 15 inside the backup pipe 13 behind the casing 15. A soil discharge pump 19 for discharging soil to the rear is provided.

이때 상기 선도체(12)의 전체길이는 2.5∼3.5M로 제작되며, 그 선도체(12)의 내부에 설치되는 오거(10)가 삽입된 케이싱(15)의 길이는 선도체(12)의 전체길이보다 짧으며, 모터(18)와 토사배출펌프(19)가 백업파이프(13)의 내부에 모두 설치된다.At this time, the overall length of the lead body 12 is made of 2.5 to 3.5M, the length of the casing 15 into which the auger 10 installed in the inside of the lead body 12 is inserted is the length of the lead body 12. Shorter than the total length, both the motor 18 and the soil discharge pump 19 are installed inside the backup pipe (13).

그리고, 상기 토사배출펌프(19)의 배출구(20)에는 선도체(12)가 토층을 굴착하여 수평구멍으로 추진삽입된 뒤에 선도체(12)의 후방에 연결되는 매설관(2)의 내부를 관통하여 후방으로 토사를 배출시키는 토사배출관(21)이 연결 설치된다.In addition, the inside of the buried pipe 2 connected to the rear of the lead body 12 after the lead body 12 is excavated and inserted into the horizontal hole in the discharge port 20 of the soil discharge pump 19. The earth and sand discharge pipe 21 for penetrating and discharging the soil to the rear is connected.

상기 선도체(12)의 후단부와 직접 연결되는 선단 매설관(2)의 선단부는 백업파이프(13)의 후단부로 삽입되도록 단턱지게 형성되며, 이 선단 매설관(2)의 선단 단턱부는 백업파이프(13)의 후단으로 삽입되어 볼트로서 결합되고, 선단 매설관(2)의 후단에 연속적으로 연결되는 후단 매설관(2)과 선단 매설관(2)의 연결은 서로 연결부가 맞대어진 상태에서 용접으로 결합된다.The leading end of the leading buried pipe 2 directly connected to the rear end of the lead body 12 is formed to be stepped into the rear end of the backup pipe 13, and the leading end of the leading buried pipe 2 has a backup pipe. The connection between the rear end buried pipe 2 and the end buried pipe 2, which is inserted into the rear end of (13) and is joined as a bolt and is continuously connected to the rear end of the leading buried pipe 2, is welded in a state where the connecting portions are in contact with each other. Are combined.

상기 각각의 매설관(2)은 전체길이가 2.5∼3.5M로 제작하는 것이 바람직하나,필요에 따라 그 길이를 5∼6M로도 제작할 수 있는 것이다.Each of the buried pipes 2 preferably has a total length of 2.5 to 3.5 M, but can be produced to a length of 5 to 6 M, if necessary.

그리고, 토사배출펌프(19)의 배출구(20)에 연결되는 토사배출관(21)은 도 6에서 보는 바와 같이 양단에 플랜지부(21a)를 구비한 상태로 매설관(2)과 그 길이가 동일한 금속관을 매설관(2)이 연결될 때마다 각각의 토사배출관(21)을 볼트로서 연결할 수 있다.In addition, the earth and sand discharge pipe 21 connected to the outlet 20 of the earth and sand discharge pump 19 is the same length as the buried pipe (2) in the state having a flange portion (21a) at both ends as shown in FIG. Each time the buried pipe 2 is connected to the metal pipe, each soil discharge pipe 21 can be connected as a bolt.

또한, 상기 토사배출관(21)은 다른 예로서 길이가 긴 플랙시블관을 한번 연결하여 사용할 수도 있으며, 이러한 플랙시블관의 길이는 50∼60M용, 70∼80M용, 90∼100M용을 마련하여 작업현장에 적합하게 선택하여 사용할 수 있다.In addition, the soil discharge pipe 21 may be used by connecting a long flexible pipe as another example, the length of the flexible pipe 50 to 60M, 70 to 80M, 90 to 100M for the work site It can be selected and used appropriately.

그리고, 상기 모터(18)와 토사배출펌프(19)로 전원을 공급하는 전원공급선을 그 길이를 100여미터 정도로 길게 하여 추진기본체(6)에서부터 모터(18)와 토사배출펌프(19)로 전원이 공급될 수 있게 한다.Then, the power supply line for supplying power to the motor 18 and the earth and sand discharge pump 19 is lengthened by about 100 meters so that power is supplied from the propulsion body 6 to the motor 18 and the earth and sand discharge pump 19. To be supplied.

도면 부호중 미설명 부호 "23"은 모터(18)와 토사배출펌프(19)에 전원을 공급하는 전선이다.Reference numeral 23 in the reference numerals denotes electric wires for supplying power to the motor 18 and the soil discharge pump 19.

상기와 같이 구성되어 있는 본 발명의 작용 관계를 도 4 내지 도 6을 참고하여 설명하면 다음과 같다.Referring to Figures 4 to 6 the operational relationship of the present invention configured as described above is as follows.

상기와 같이 본 발명의 매설관 추진삽입장치(22)를 이용하여 토층에 매설관을 삽입 추진하고자 하는 경우에는 매설관을 매설할 토층의 일측 선단 토층을 굴착하여 발진입항(a)을 형성하고, 이 발진입항(a)에 매설관 추진삽입장치(22)를 설치한다.As described above, when the buried pipe is to be inserted and pushed into the soil layer by using the buried pipe propulsion insertion device 22 of the present invention, one side of the soil layer on which the buried pipe is to be buried is excavated to form an oscillation entry port (a), A buried pipe propulsion insertion device 22 is installed in this oscillation entry port (a).

이때, 매설관 추진삽입장치(22)의 추진기본체(6)의 전방 베드(4)상에 선도체(12)가 장착된 상태이며, 이상태에서 선도체(12)에 설치되어 있는 모터(18)와, 추진기본체(6)에 설치되어 있는 유압실린더(5)를 구동시키게 되면, 모터(18)의 회전력이 오거(10)와 오거헤드(14)에 전달되어 오거(10)와 오거헤드(14)를 회전시키게 되고, 이렇게 회전하는 오거헤드(14)가 토층을 굴착하게 되는 것이며, 유압실린더(5)에 의해서는 추진기본체(6)를 비롯한 추진기본체(6)의 선단에 설치되어 있는 추진판(7)을 전방으로 수평 이동시켜 추진판(7)에 말단부가 접촉하고 있는 선도체(12)의 백업파이프(13)가 전방으로 추진하게 된다.At this time, the lead body 12 is mounted on the front bed 4 of the propulsion body 6 of the buried pipe propulsion insertion device 22, and in this state, the motor 18 installed in the lead body 12. When the hydraulic cylinder 5 installed in the propulsion body 6 is driven, the rotational force of the motor 18 is transmitted to the auger 10 and the auger head 14, and the auger 10 and the auger head 14. ), The rotating auger head 14 excavates the soil layer, and the hydraulic cylinder 5 is provided at the tip of the propulsion body 6 including the propulsion body 6 by the hydraulic cylinder 5. (7) is moved horizontally forward, so that the backup pipe 13 of the lead body 12 whose distal end contacts the propulsion plate 7 is pushed forward.

상기와 같이 오거헤드(14)가 회전하고 백업파이프(13)가 전방으로 수평이동함에 따라 오거헤드(14)에 의해 토층이 원형으로 굴착되어 수평구멍이 형성된 공간으로 백업파이프(13)를 비롯한 선도체(12)가 추진 삽입하게 되는 것이다.As the auger head 14 rotates as described above and the backup pipe 13 moves horizontally forward, the soil layer is excavated in a circular shape by the auger head 14, and a diagram including the backup pipe 13 is formed in a horizontal hole. Sieve 12 is to be propelled.

이렇게 오거헤드(14)로서 토층을 굴착할 때 발생하는 토사는 오거헤드(14)가 회전하면서 선도체(12) 전체가 전방으로 이동함에 따라 경사관(17)으로 유입되게되고, 경사관(17)으로 유입되는 토사는 회전하고 있는 오거(10)에 의해 케이싱(15)의 내부에서 케이싱(15)의 후방으로 밀려 나가면서 백업파이프(13)의 내부로 배출되게 된다.Soil generated when the soil layer is excavated as the auger head 14 is introduced into the inclined tube 17 as the entire lead 12 moves forward while the auger head 14 rotates, and the inclined tube 17 Soil flowing into the) is discharged to the back of the backup pipe 13 while being pushed to the rear of the casing 15 from the inside of the casing 15 by the rotating auger (10).

상기와 같이 케이싱(15)의 후방으로 토사가 배출되게 되면 토사배출펌프(19)의 펌핑력에 의해 상기 토사를 흡입하여 토사배출펌프(19)의 배출구(20)에 연결된 토사배출관(21)을 통하여 외부로 배출시키게 되는 것이다.When the earth and sand is discharged to the rear of the casing 15 as described above, the earth and sand discharge pipe 21 connected to the outlet 20 of the earth and sand discharge pump 19 by sucking the soil by the pumping force of the earth and sand discharge pump 19. It will be discharged to the outside.

이렇게 선도체(12)가 토층을 굴착하며 토층에 형성되는 수평구멍으로 모두 삽입되면, 유압실린더(5)를 후진되게 동작시켜서 추진기본체(6)가 후진하도록 하여 토층으로 추진 삽입된 선도체(12)의 후방과 추진기본체(6)의 전방사이에 매설관(2)이 삽입될 수 있는 공간을 확보한다.When the lead body 12 excavates the soil layer and is inserted into the horizontal hole formed in the soil layer, the hydraulic cylinder 5 is operated backward so that the propulsion base body 6 moves backward so that the lead body 12 is pushed into the soil layer. Secure a space for the buried pipe (2) can be inserted between the rear of the) and the front of the propulsion body (6).

상기와 같이 선도체(12)의 후방과 추진기본체(6)의 전방사이에 매설관(2)이 삽입될 수 있는 공간을 확보한 뒤에는 선도체(12)의 후방과 추진기본체(6)의 전방사이에 확보된 공간으로 매설관(2)을 내려서 매설관(2)의 선단부와 선도체(12)의 후단부에 연결시킨다.After securing the space in which the buried pipe 2 can be inserted between the rear of the lead body 12 and the front of the propulsion body 6 as described above, the rear of the lead body 12 and the front of the propulsion body 6. The buried pipe 2 is lowered to the space secured therebetween and connected to the front end of the buried pipe 2 and the rear end of the lead body 12.

이때, 선도체(12)의 후단에 직접 연결되는 선단 매설관(2)은 도 5에서와 같이 단턱부를 형성하여서 이 선단 매설관(2)의 단턱부를 선도체(12)의 백업파이프(13) 후단으로 삽입시킨 뒤에 볼트로서 착탈 가능하게 연결한다.At this time, the tip buried pipe 2 directly connected to the rear end of the conductor 12 forms a stepped portion as shown in FIG. 5, so that the stepped portion of the tip buried tube 2 is a backup pipe 13 of the leader 12. After inserting into the rear end, it is detachably connected by bolts.

이렇게 선도체(12)의 후단에 선단 매설관(2)을 연결하고 난 뒤에는 유압실린더(5)를 작동시키면서 모터(18)를 구동시키면, 모터(8)의 회전력이 오거(10)를 통하여 선도체(12)의 선단에 설치되어 있는 오거헤드(14)를 회전시켜서 토층을 굴착하게 되고, 유압실린더(5)의 작동에 의해서는 추진기본체(6)를 전방으로 수평이동시킴에 따라 추진판(7)이 추진기본체(6)와 함께 전방으로 수평이동하면서 추진판(7)이 선단 매설관(2) 후방을 전방으로 밀게 된다.After the tip buried pipe 2 is connected to the rear end of the lead body 12, the motor 18 is driven while operating the hydraulic cylinder 5, and the rotational force of the motor 8 is led through the auger 10. The soil layer is excavated by rotating the auger head 14 installed at the front end of the sieve 12, and by operating the hydraulic cylinder 5, the propulsion base 6 is moved horizontally to the forward direction. 7) The propulsion plate 7 pushes the rear end of the buried pipe 2 forward while horizontally moving forward with the propulsion body 6.

상기와 같이 오거헤드(14)가 회전함에 따라 토층을 굴착하게 되고 그 굴착에 의해 형성되는 수평구멍으로 선도체(12)부터 선도체(12)와 연결된 선단 매설관(2)가 추진 삽입하게 되며, 이렇게 토층을 굴착하는 과정에서 발생되는 토사는 오거(10)의 회전에 의해 경사관(17)과 케이싱(15)의 내부를 통하여 케이싱(15)의 후방으로 밀려 나오게 되고, 이렇게 케이싱(15)으로 밀려 나온 토사는 토사배출펌프(19)의 펌핑력에 의해 토사배출관(21)을 통해 외부로 배출시키게 된다.As the auger head 14 rotates as described above, the soil layer is excavated, and the end buried pipe 2 connected to the lead body 12 is propelled and inserted into the horizontal hole formed by the excavation. , Soil generated in the process of excavating the soil layer is pushed out of the rear of the casing 15 through the interior of the inclined tube 17 and the casing 15 by the rotation of the auger 10, thus the casing 15 Soil is pushed out to be discharged to the outside through the soil discharge pipe 21 by the pumping force of the soil discharge pump (19).

이렇게 선도체(12)와 선도체(12)의 후방에 연결된 선단 매설관(2)이 토층으로 추진 삽입된 뒤에는 유압실린더(5)를 동작시켜 추진기본체(6)를 다시 후방으로 후진 시키며, 선단 매설관(2)의 후단과 추진기본체(6)의 전방사이에 또 다른 후단 매설관(2)을 삽입시킬 수 있는 공간을 마련한다.After the leading buried pipe 2 connected to the rear of the lead body 12 and the lead body 12 is pushed and inserted into the soil layer, the hydraulic cylinder 5 is operated to back the propulsion body 6 back to the rear, Between the rear end of the buried pipe (2) and the front of the propulsion body (6) is provided a space for inserting another rear buried pipe (2).

상기와 같이 매설관(2)와 한 개의 매설관(2)이 토층으로 추진 삽입되고 추진기본체(6)가 후퇴하여 추진기본체(6)의 선단부와 선단 매설관(2)의 후단부의 사이에 또 다른 후단 매설관(2)을 삽입시킬 수 있는 공간을 마련한 뒤에는 이 공간으로 또 다른 매설관(2)을 삽입시키면서 선단 매설관(2)의 후단부와 후단 매설관(2)의 선단부를 서로 맞 댄뒤에 그 맞 대어진 접촉부를 용접하여 결합시킨다.As described above, the buried pipe 2 and one buried pipe 2 are propelled and inserted into the soil layer, and the propulsion body 6 is retracted so that between the tip end of the propulsion body 6 and the rear end of the tip buried pipe 2 is further removed. After providing a space for inserting another trailing buried pipe (2), the other end of the buried pipe (2) and the tip of the trailing buried pipe (2) are fitted with each other while inserting another buried pipe (2) into this space. Weld and join the mated contacts behind them.

이렇게 또 다른 매설관(2)을 연결할 때는 모터(18)와 토사배출펌프(19)에 전원을 공급하는 전선이 추진기본체(6)측으로 빠져 나갈 수 있어야 하는 것은 당연한것이고, 새로운 매설관(2)을 연결할 때마다 토사배출펌프(19)의 배출구(20)에 연결되는 토사배출관(21)도 새로이 연결되는 매설관(2)의 내부를 통하여 외부로 토사를 배출시킬 수 있도록 해야한다.When connecting another buried pipe (2), it is natural that the electric wires for supplying power to the motor (18) and the soil discharge pump (19) must be able to escape to the propulsion body (6) side, the new buried pipe (2) Whenever it is connected to the soil discharge pipe (21) connected to the outlet 20 of the soil discharge pump 19 should also be able to discharge the soil to the outside through the interior of the buried pipe (2) newly connected.

이때, 토사배출관(21)을 도 6에서 보는 바와같이 양측에 플랜지부(21a)를 구비하며 매설관(2)의 길이와 동일한 금속관으로 형성되는 경우에는 새로운 매설관(2)을 연결할 때마다 새로이 연결되는 매설관(2)의 내부에서 양측에 플랜지부(21a)를 구비한 매설관(2)을 앞단의 토사배출관(21)과 볼트로서 연결해야 하는 것이다.At this time, the soil discharge pipe 21 is provided with a flange portion (21a) on both sides as shown in Figure 6, if formed of a metal pipe equal to the length of the buried pipe (2) each time a new buried pipe (2) is connected newly In the interior of the buried pipe (2) to be connected to the buried pipe (2) having a flange portion (21a) on both sides to be connected to the soil discharge pipe (21) of the front end as a bolt.

상기와 같이 새로운 매설관(2)을 용접으로 연결하고 전선과 토사배출관(21)이 후방으로 관통한 뒤에는 유압실린더(5)를 전방으로 돌출되게 동작시켜 추진기본체(6)가 전방으로 수평이동하면서 추진기본체(6)의 전방에 설치된 추진판(7)이 새로이 연결된 매설관(2)의 후방을 전방으로 밀면서 오거(10)의 후방에 설치된 모터(18)를 동작시켜서 오거(10)와 오거헤드(14)를 회전시키게 되면 오거헤드(14)가 토층을 굴착하게 되고, 오거헤드(14)에 의해 토층을 굴착하는 과정에서 발생되는 토사가 오거(10)에 의해 케이싱(15)의 후단으로 배출되게 되며, 토사배출펌프(19)의 펌핑력에 의해 상기 토사가 토사배출관(21)을 통해 외부로 배출되게 되는 것이다.As described above, after the new buried pipe 2 is welded and the electric wire and the earth discharge pipe 21 penetrate backward, the hydraulic cylinder 5 is protruded forward to move the propulsion body 6 horizontally forward. The auger 10 and the auger head are operated by operating the motor 18 installed at the rear of the auger 10 while pushing the rear of the buried pipe 2 newly connected to the propulsion plate 7 installed in front of the propulsion body 6. Rotating the 14 causes the auger head 14 to excavate the soil layer, and the soil generated in the process of excavating the soil layer by the auger head 14 is discharged to the rear end of the casing 15 by the auger 10. The soil is discharged to the outside through the soil discharge pipe 21 by the pumping force of the soil discharge pump (19).

이와 같이 여러개의 매설관(2)을 연속적으로 연결하면서 토층으로 추진 삽입하여 목적지까지 선도체(12)와 다수의 매설관(2)을 추진 삽입하여 선도체(12)가 도착항(b)으로 돌출되어 나오게 되면, 도착항(b)으로 돌출된 선도체(12)를 최선단의매설관(2)과 분리하여 회수한다. 이때는 모터(18)와 토사배출펌프(19)에 전원을 공급하는 전선을 추진기본체(6)에서 뽑아내어 분리시키고, 토사배출관(21)이 플랙시블한 경우에 도착항(b)에서 선도체(12)을 회수하면 상기 전선과 플랙스블한 토사배출관(21)이 선도체(12)와 함께 회수되게 된다.In this way, the plurality of buried pipes 2 are continuously connected to each other while the propellant is inserted into the soil layer, and the lead body 12 and the plurality of buried pipes 2 are propelled and inserted to the destination so that the lead body 12 protrudes into the arrival port (b). When it comes out, the lead body 12 which protrudes in the arrival port (b) is collect | recovered separately from the buried pipe 2 of the uppermost stage. At this time, the electric wires for supplying power to the motor 18 and the earth and sand discharge pump 19 are removed from the propulsion body 6 and separated, and when the earth and sand discharge pipe 21 is flexible, the lead body 12 in the arrival port (b). ), The wire and the flexible soil discharge pipe 21 is recovered together with the leader (12).

상기 토사배출관(21)이 금속관인 경우에는 선도체(12)를 통층에 수평으로 매설되어 있는 최선단의 매설관(2)에서 분리시킨 상태에서 선도체(12)를 전방으로 이동시켜서 선도체(12)의 후방과 최선단의 매설관(2)의 선단부와 작업자의 몸이 들어갈 수 있을 정도로 이동시키며, 그 상태에서 그 벌어진 틈새로 작업자의 몸을 넣어서 토사배출펌프(19)의 배출구(20)에서 금속관으로 된 토사배출관(21)을 분리시킨 상태로 선도체(12)를 회수한다.In the case where the soil discharge pipe 21 is a metal pipe, the lead body 12 is moved forward in a state in which the lead body 12 is separated from the buried pipe 2 at the uppermost end buried horizontally in the tubing layer. 12) and the front end of the buried pipe (2) of the uppermost end and the worker's body is moved so that the body of the worker in the gap between the opening and discharge outlet 20 of the earth and sand discharge pump (19) The lead body 12 is collected in a state in which the earth and sand discharge pipe 21 made of a metal pipe is separated.

이렇게 선도체(12)를 회수하고 난 뒤에는 도착항(b)이나 또는 발진입항(a)에서 금속관으로 된 토사배출관(21)을 당겨 내면서 플랜지부(21a)를 하나씩 분리시켜서 각각의 토사배출관(21)을 분리하게 되며, 다수개가 연결된 매설관(2)의 내부가 빈 상태가 된다.After recovering the lead body 12, the earth and sand discharge pipe 21 is separated by separating the flange portions 21a one by one while pulling out the earth and sand discharge pipe 21 made of a metal pipe from the arrival port (b) or the oscillation entry port (a). It will be separated, the interior of the buried pipe (2) is connected to a plurality of empty state.

상기와 같이 토층에 수평으로 매설된 다수의 매설관(2)은 중공상태이므로 상하수도관으로 사용하거나, 또는 그 내부로 상하수도관이나, 전기 및 통신 케이블, 가스배관 등을 삽입설치할 수 있는 것이다.Since the plurality of buried pipes 2 horizontally buried in the soil layer as described above is hollow, it can be used as a water and sewage pipe, or the water and sewage pipe, electric and communication cables, gas pipes, etc. can be installed therein.

이상에서 살펴본 바와 같은 본 발명의 토목공사용 매설관 추진삽입장치는, 매설관 추진 삽입장치의 선도체 내부에 한 개의 오거와 이 오거를 구동시킬 수 있는 모터를 설치하고, 이 오거의 후단에는 오거를 통해 후방으로 배출되는 토사를 매설관의 외부로 배출할 수 있도록 하는 토사배출용 펌프를 설치하며, 펌프의 후단으로는 토사배출용 배출관이 연속적으로 연결될 수 있도록 함으로서, 오거의 길이가 짧으므로 오거의 비틀림에 의한 손상을 방지하고 오거를 통하여 후방으로 배출되는 토사를 효과적으로 배출시킬 수 있는 효과가 있는 것이다.The buried pipe propulsion insertion device for civil engineering of the present invention as described above is provided with an auger and a motor capable of driving the auger inside the lead body of the buried pipe propulsion inserting device, and the auger is provided at the rear end of the auger. Install a soil pump for discharging the soil to be discharged to the outside of the buried pipe to the outside of the buried pipe, and the rear end of the pump can be connected to the discharge pipe for soil discharge continuously, the auger is short It is effective to prevent the damage caused by the torsion and to effectively discharge the soil discharged backward through the auger.

또한, 종래의 매설관 추진삽입장치에는 선도체의 후단에 연속적으로 연결하는 매설관의 내부에 오거와 오거가 삽입되는 케이싱이 모두 삽입되어 있기 때문에 위에서 언급한 오거의 비틀림 외에도 매설관이 연결될 때 마다 케이싱과 오거를 연속적으로 연결하였으나, 본 발명에서는 선도체의 후방에 연결되는 매설관의 내부에 오거와 케이싱이 삽입되어 있지 않기 때문에 오거와 케이싱을 연결하는 작업과정이 삭제되어 작업시간이 단축되는 효과와, 다량의 오거와 케이싱이 불필요하여 공사비용이 절감되는 효과가 있으며, 종래의 추진기본체에는 오거의 말단부를 클램핑하는 오거클램프와 오거클램프를 회전시킬 수 있는 모터 및 모터의 동력을 오거클램프로 전달하는 동력전달장치가 소요되었으나, 본 발명에서는 그런 장치들이 불필요하여 추진기본체의 구조가 간단해지고 장비의 제작비용이 절감되는 등의 장점이 있는 것이다.In addition, in the conventional buried pipe propulsion insertion device is inserted both the auger and the auger is inserted into the interior of the buried pipe continuously connected to the rear end of the leader, so each time the buried pipe is connected in addition to the twist of the auger mentioned above Although casing and auger are continuously connected, in the present invention, since the auger and the casing are not inserted into the buried pipe connected to the rear of the lead body, the process of connecting the auger and the casing is deleted, thereby reducing the work time. And, a large amount of augers and casings are unnecessary, which reduces the cost of construction, and the conventional propulsion body transmits the auger clamps and the motors capable of rotating the auger clamps to the auger clamps. It takes a power transmission device, but in the present invention such devices are unnecessary because of the propeller The structure of the main body is simplified and the manufacturing cost of equipment is reduced.

Claims (1)

베드(4)의 후방 상부에 추진기본체(6)가 유압실린더(5)에 의해 수평으로 슬라이딩 이동이 가능하게 설치되고, 추진기본체(6)의 전방에는 모터의 동력에 의해 회전하면서 토층을 오거헤드(14)로서 굴착하고 굴착과정에서 발생되는 토사를 오거(10)를 통하여 후방으로 배출시키며 오거헤드(14)에 의해 굴착되는 수평구멍으로 유압실린더(5)에 의해 추진 삽입되는 선도체(12)가 설치되며, 수평구멍으로 추진 삽입된 선도체(12)와 추진기본체(6)가 분리된 뒤에 추진기본체(6)를 후퇴시켜 추진기본체(6)의 선단부와 선도체(12)의 후단사이에 매설관(2)을 삽입시켜 연결하면서 매설관(2)을 토층에 수평으로 매설하는 것에 있어서,The propulsion body 6 is installed on the rear upper part of the bed 4 to be slidably moved horizontally by the hydraulic cylinder 5, and the front of the propulsion body 6 is rotated by the power of a motor while the auger head is rotated. (12) the leading body 12 which is excavated and discharged to the rear through the auger (10) generated in the excavation process and pushed by the hydraulic cylinder (5) into a horizontal hole excavated by the auger head (14) After the propellant body 12 and the propelling body 6 which are propelled and inserted into the horizontal hole are separated, the propelling body 6 is retracted, and between the leading end of the propelling body 6 and the rear end of the leading body 12. In embedding buried pipe 2 horizontally in soil layer while inserting buried pipe 2, and connecting, 상기 선도체(12)의 선단부 내측에 삽입 설치된 경사관(17)의 후방에는 백업파이프(13)보다 길이가 짧은 원통관 형태의 케이싱(15)이 연결되고, 상기 케이싱(15)의 내부에는 선단부가 오거헤드(14)의 후단부와 연결되고 후단부는 케이싱(15)의 후단으로 돌출되는 오거(10)가 삽입 설치되며, 상기 오거(10)의 후단부는 백업파이프(13)의 내부에 설치된 모터(18)의 축과 연결되며, 케이싱(15) 후방의 백업파이프(13)의 내측에는 케이싱(15)을 통하여 배출되는 토사를 후방으로 배출시키는 토사배출펌프(19)가 설치되고,A casing 15 in the form of a cylindrical tube having a length shorter than that of the backup pipe 13 is connected to the rear of the inclined tube 17 inserted into the front end of the lead body 12, and the front end of the casing 15. Is connected to the rear end of the auger head 14, the rear end is inserted into the auger 10 protruding to the rear end of the casing 15, the rear end of the auger 10 is a motor installed inside the backup pipe 13 It is connected to the shaft of (18), inside the back-up pipe 13 of the casing 15 is provided with a soil discharge pump 19 for discharging the soil discharged through the casing 15 to the rear, 상기 토사배출펌프(19)의 배출구(20)에는 매설관(2)의 내부를 관통하여 후방으로 토사를 배출시키는 토사배출관(21)이 연결설치되는 것을 특징으로 하는 토목공사용 매설관 추진삽입장치.Civil engineering works buried pipe propulsion insertion device, characterized in that the discharge port 20 of the soil discharge pump (19) is connected to the soil discharge pipe (21) for discharging the soil by passing through the interior of the buried pipe (2).
KR1020010034422A 2001-06-18 2001-06-18 Apparatus laying pipes underground for public engineering and construction KR20010070900A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020010034422A KR20010070900A (en) 2001-06-18 2001-06-18 Apparatus laying pipes underground for public engineering and construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020010034422A KR20010070900A (en) 2001-06-18 2001-06-18 Apparatus laying pipes underground for public engineering and construction

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020010018188U Division KR200248471Y1 (en) 2001-06-18 2001-06-18 Apparatus laying pipes underground for public engineering and construction

Publications (1)

Publication Number Publication Date
KR20010070900A true KR20010070900A (en) 2001-07-27

Family

ID=19710991

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020010034422A KR20010070900A (en) 2001-06-18 2001-06-18 Apparatus laying pipes underground for public engineering and construction

Country Status (1)

Country Link
KR (1) KR20010070900A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100106587A (en) * 2008-01-31 2010-10-01 차이나 페트로리움 앤드 케미컬 코포레이션 Agglomerated zeolite adsorbent and preparation method thereof
KR101259166B1 (en) * 2012-12-26 2013-04-30 주식회사 이준엔지니어링 Excavator for excavating road
KR101296066B1 (en) * 2013-01-16 2013-08-16 용호건설(주) Steel pipe rotating- pushing apparatus and underground structure buidling method
KR101872971B1 (en) * 2017-08-03 2018-08-02 박금순 water pipe reclaiming method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01315592A (en) * 1989-04-18 1989-12-20 Doboku Kenkyu Center Free cross section shield construction and shield machine
JPH06313397A (en) * 1993-04-30 1994-11-08 Kandenko Co Ltd Small-diameter pipe propulsion construction method and equipment therefor
JPH0941858A (en) * 1995-07-31 1997-02-10 Susumu Nasu Drilling device and pipe pressing-in structure
JPH0960476A (en) * 1995-08-29 1997-03-04 Sanwa Kizai Co Ltd Pipe burying device
JPH11217991A (en) * 1998-02-02 1999-08-10 Ktk Telecommunications Engineering Co Ltd Drift excavation device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01315592A (en) * 1989-04-18 1989-12-20 Doboku Kenkyu Center Free cross section shield construction and shield machine
JPH06313397A (en) * 1993-04-30 1994-11-08 Kandenko Co Ltd Small-diameter pipe propulsion construction method and equipment therefor
JPH0941858A (en) * 1995-07-31 1997-02-10 Susumu Nasu Drilling device and pipe pressing-in structure
JPH0960476A (en) * 1995-08-29 1997-03-04 Sanwa Kizai Co Ltd Pipe burying device
JPH11217991A (en) * 1998-02-02 1999-08-10 Ktk Telecommunications Engineering Co Ltd Drift excavation device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100106587A (en) * 2008-01-31 2010-10-01 차이나 페트로리움 앤드 케미컬 코포레이션 Agglomerated zeolite adsorbent and preparation method thereof
KR101259166B1 (en) * 2012-12-26 2013-04-30 주식회사 이준엔지니어링 Excavator for excavating road
KR101296066B1 (en) * 2013-01-16 2013-08-16 용호건설(주) Steel pipe rotating- pushing apparatus and underground structure buidling method
KR101872971B1 (en) * 2017-08-03 2018-08-02 박금순 water pipe reclaiming method

Similar Documents

Publication Publication Date Title
JP4296549B2 (en) Underground support structure, its construction method and tunnel construction method
KR20010070900A (en) Apparatus laying pipes underground for public engineering and construction
KR200248471Y1 (en) Apparatus laying pipes underground for public engineering and construction
JP2005120622A (en) Construction method of underground structure
JP3170215B2 (en) Pipe burial method
JP2021080798A (en) Pipeline construction method using propulsion method
JP3616898B2 (en) Method for joining underground structures using propulsion device
JP4136902B2 (en) Small-diameter pipe excavation equipment
JPH1163299A (en) Execution method of multi-conduit pipe and multi-conduit pipe
JP3894423B2 (en) Promotion method
JP2005076357A (en) Method for replacing buried pipe and cutter device for buried pipe replacement
JP3680963B2 (en) Method of burying main pipe and branch pipe in buried pipe
JP3235704U (en) Underground drilling equipment
KR200361243Y1 (en) Horizontal excavating devidce for pushing steel pipe
KR100920256B1 (en) Apparatus for pressing front end of steel pipe loop structure
JP3568844B2 (en) Excavator and buried pipe
JP4057439B2 (en) Construction method of underground support work
JP3402437B2 (en) Burial method of pipe
JP3366241B2 (en) Underground pipe laying method and apparatus
JP3473915B2 (en) Small diameter pipe burial method
JP2928462B2 (en) Double pipe muddy water propulsion method
JP3092727U (en) Pipe burial equipment
KR20030005651A (en) Pipe laying apparatus
KR20220155046A (en) Structure and construction method of horizontal excavators that cut the ground by rotating the header to propel the pipe
KR20050094155A (en) Horizontal excavating devidce for pushing steel pipe

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application