KR20010000135A - Elevator Door Frame and Construction Method - Google Patents

Elevator Door Frame and Construction Method Download PDF

Info

Publication number
KR20010000135A
KR20010000135A KR1020000030961A KR20000030961A KR20010000135A KR 20010000135 A KR20010000135 A KR 20010000135A KR 1020000030961 A KR1020000030961 A KR 1020000030961A KR 20000030961 A KR20000030961 A KR 20000030961A KR 20010000135 A KR20010000135 A KR 20010000135A
Authority
KR
South Korea
Prior art keywords
elevator
door frame
elevator door
bracket
hall
Prior art date
Application number
KR1020000030961A
Other languages
Korean (ko)
Other versions
KR100364341B1 (en
Inventor
서정길
Original Assignee
서정길
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 서정길 filed Critical 서정길
Priority to KR1020000030961A priority Critical patent/KR100364341B1/en
Priority to KR2020000016050U priority patent/KR200203785Y1/en
Publication of KR20010000135A publication Critical patent/KR20010000135A/en
Application granted granted Critical
Publication of KR100364341B1 publication Critical patent/KR100364341B1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B13/00Doors, gates, or other apparatus controlling access to, or exit from, cages or lift well landings
    • B66B13/30Constructional features of doors or gates
    • B66B13/301Details of door sills
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B13/00Doors, gates, or other apparatus controlling access to, or exit from, cages or lift well landings
    • B66B13/24Safety devices in passenger lifts, not otherwise provided for, for preventing trapping of passengers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • EFIXED CONSTRUCTIONS
    • E05LOCKS; KEYS; WINDOW OR DOOR FITTINGS; SAFES
    • E05YINDEXING SCHEME ASSOCIATED WITH SUBCLASSES E05D AND E05F, RELATING TO CONSTRUCTION ELEMENTS, ELECTRIC CONTROL, POWER SUPPLY, POWER SIGNAL OR TRANSMISSION, USER INTERFACES, MOUNTING OR COUPLING, DETAILS, ACCESSORIES, AUXILIARY OPERATIONS NOT OTHERWISE PROVIDED FOR, APPLICATION THEREOF
    • E05Y2900/00Application of doors, windows, wings or fittings thereof
    • E05Y2900/10Application of doors, windows, wings or fittings thereof for buildings or parts thereof
    • E05Y2900/104Application of doors, windows, wings or fittings thereof for buildings or parts thereof for elevators

Landscapes

  • Elevator Door Apparatuses (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PURPOSE: A door frame of an elevator and a construction method thereof are provided to improve productivity by performing a construction work without a stop even while replacing water. CONSTITUTION: An elevator door opens/closes an elevator(1) as the elevator stops on a certain position. A guide groove(210) is formed on an upper part to make a guide shoe(110) movable. A door rail(200) forms a bracket settlement stand(220) in a recessed groove on one side. A lower end of a gate(300) is fixed on a bracket to be fixed on the bracket settlement stand. One side of a material dividing stand(400) is inserted in the bracket settlement stand. A waterproofing plate insertion groove(410) is formed on the other upper portion to readily insert a waterproofing plate(420).

Description

엘레베이터 도어프레임과 그 시공방법{Elevator Door Frame and Construction Method}Elevator door frame and construction method {Elevator Door Frame and Construction Method}

본 발명은 엘레베이터 도어레일의 일측에 결합하여 엘레베이터의 시공을 용이하게 시행하도록 하고, 또한, 인조석 바닥물갈기 복도바닥공사도 동시에 시공이 가능하도록 하는 재료분리대에 관한 것으로, 더욱 더 상세하게는 엘레베이터의 게이트프레임, 즉, 엘레베이터 도어프레임의 시공시 바닥 레벨의 기준이 되도록 하고, 엘레베이터 도어레일 일측에 결합되어 방파판(防波板) 장착홈에 방파판을 삽입으로 고정하므로 바닥시공시 인조석물갈기 작업에 의해 생성된 돌가루의 점상(粘狀) 오염물이 엘레베이터 도어내부로 침투하는 것을 방지하여 엘레베이터 시공과 바닥시공이 동시에 가능하도록 한 엘레베이터 도어프레임과 그 시공방법에 관한 것이다.The present invention relates to a material separator to be coupled to one side of the elevator door rail to facilitate the construction of the elevator, and also to allow the construction of artificial floor mane corridor floor construction at the same time, and more specifically to the elevator When building the gate frame, that is, the elevator door frame, it is to be a standard of floor level, and it is coupled to one side of the elevator door rail and fixed by inserting the blast wave into the blast wave mounting groove. The present invention relates to an elevator door frame and a method for constructing the elevator door and floor construction by preventing the dust contaminants generated by the stone from penetrating into the inside of the elevator door.

통상적인 바닥시공작업(인조석 물갈기)에 대해 간략히 설명하면, 일단 엘레베이터의 도어와 도어레일, 게이트의 설치작업이 완료되면, 상기 엘레베이터 도어레일의 레벨에 맞추어 아파트복도나 홀(Hall)의 바닥에 백시멘트+광물질안료+인조석+돌가루를 혼합하여 두께 1.5 ~ 3cm정도로 바탕위에 바르는 것으로(속칭: 도끼다시), 인조석의 정벌 바름 후 시멘트의 경화정도를 판단하여 숯돌로 초벌갈기, 재벌갈기와 정벌갈기를 하고, 물을 분사하며 회전하는 숯돌등의 연마재가 구비된 연마기로 갈아서 표면을 매끄럽게 하는 것이다.("건축용어 사전"에서 발췌.)Briefly, the general floor construction work (artificial water change), once the installation of the door, the door rail, the gate of the elevator is completed, according to the level of the elevator door rail to the floor of the apartment corridor or hall (Hall) By mixing white cement + mineral pigment + artificial stone + powder on the ground with a thickness of about 1.5 ~ 3cm (aka ax), judge the degree of hardening of cement after applying the artificial stone finish Grind, grind the surface with a grinder equipped with abrasives such as charcoal that rotates and sprays water to smooth the surface (excerpt from "Architecture Dictionary").

이때, 물을 분사하는 이유는 상기의 갈기를 하는 과정에서 발생하는 돌가루 분진에 의한 먼지발생을 방지하기위한 것이다.At this time, the reason for spraying water is to prevent the dust generated by the dust dust generated in the process of grinding.

그러나, 엘레베이터를 시공하는 작업자등은 상기 물갈기작업을 시행할 때에는 물과 백시멘트의 점상이 주위로 튀어 작업을 수행할 수 없으므로, 작업이 완료되지 않은 상태에서도 철수하는등 작업의 공백이 생겨 작업계획에 차질이 생기는 문제가 있었다.However, the worker, etc., who constructs the elevator cannot carry out work by splashing water and back cement on the ground when performing the above-mentioned grind work, so that the work can be withdrawn even when the work is not completed. There was a problem with the plan.

상기 인조석 물갈기 시공을 할때에는 도시하지는 않았으나 게이트와 도어 사이에 합판을 끼워 넣고 접촉면에 실리콘을 도포하여 오염물의 침투를 방지하도록 하는 방법을 시행하기도 하였다.Although not shown, the artificial pavement was not shown, but a plywood was inserted between the gate and the door, and silicon was applied to the contact surface to prevent contamination.

그러나, 인조석 물갈기 연마석에 의해 하부에 실링된 부위가 떨어져 나가거나 하부가 찢겨나가는 문제로 오염물의 침투를 원천적으로 방지하기에는 문제가 있었고, 시공작업도중 수시로 도어를 개폐하며 수직을 맞추는 작업을 시행할 수 없으므로 작업진행이 근본적으로 이루어지지 않은 문제가 있었다.However, there was a problem to prevent the infiltration of contaminants due to the problem that the part sealed at the bottom by the artificial grinded abrasive stone fell off or the bottom was torn, and the operation of vertically opening and closing the door was frequently performed during the construction work. There was a problem that the work was not fundamentally done.

또한, 도 1에 단면으로 도시한 바와 같이, 1차 시공이 완료된 엘레베이터 도어프레임의 각 구성, 즉, 전층 엘레베이터 도어레일의 내부로 흘러든 오염물(돌가루 분진+물)이 흘러 바로 하부층의 각 엘레베이터 도어를 개폐하도록 하는 기구장치에 점착(粘着)되어 엘레베이터 도어및 엘레베이터 도어의 개폐를 위한 기구장치의 동작을 방해하는 문제가 있고, 시공작업자가 일일히 제거한 후, 시공작업을 시행함으로 생산성이 저하되는 문제가 있었다.In addition, as shown in cross-section in Figure 1, each configuration of the elevator door frame, the primary construction is completed, that is, the contaminants (dust dust + water) flowing into the interior of the elevator door rail of the entire floor flows directly to each elevator of the lower layer It is adhered to the mechanism for opening and closing the door, which hinders the operation of the elevator door and the mechanism for opening and closing the elevator door, and after the construction worker removes it, the productivity is reduced by performing the construction work. There was a problem.

또한, 완전히 제거되지 않은 오염물에 의해 또 다른 엘레베이터의 구성에 까지 영향을 미쳐 엘레베이터의 보수가 잦아 사용자들로 부터 기계에 대한 신뢰성을 잃는 문제가 있었다.In addition, the contaminants that were not completely removed affect the configuration of another elevator, so that the elevator is frequently repaired, thereby losing the reliability of the machine from users.

간략하게 도시한 엘레베이터 도어의 핵심부품이라 할 수 있는 인터록 리밋트 스윗치(Interlock Limit Switch)(LM10)에 상기 오염물이 침투할 경우 전기적인 오동작으로 도어가 열린상태에서 엘레베이터가 동작할 수 있는 안전상 치명적인 문제가 발생할 수도 있다.If the contaminants penetrate into the Interlock Limit Switch (LM10), which is a key part of the elevator door, which is briefly shown, there is a safety critical problem that the elevator can operate while the door is opened due to an electrical malfunction. May occur.

또한, 도어의 수직과 게이트와의 수직정렬을 위해 도어를 여닫을 경우 도어레일의 요홈에 고인 오염물이 경화되어 가이드 슈를 해체하고 요홈에 고인 오염믈을 청소해야 하는 문제가 있다.In addition, when opening and closing the door for vertical alignment of the door and the gate, there is a problem that the contaminants accumulated in the grooves of the door rail are hardened to dismantle the guide shoe and clean the contaminants accumulated in the grooves.

아울러, 시공이 완료된 후에도 상술한 오염물에 의해 도어가 완전히 닫히지 않아 고장수리가 잦아 사용자로부터 신뢰를 잃는 문제가 있다.In addition, even after the construction is completed, the door is not completely closed by the above-mentioned contaminants, and thus there is a problem that frequent troubleshooting is lost and the user loses trust.

본 발명은 상기와 같은 문제점을 해결하기 위해 안출된 것으로서, 본 발명의 목적은 엘레베이터를 설치하는 시공자등은 상기 물갈기작업을 시행하는 중에도 동시에 중단없는 시공작업이 가능하여 생산성을 높이도록 하는데 있다.The present invention has been made to solve the above problems, the object of the present invention is to increase the productivity by enabling the construction work without interruption at the same time during the installation of the elevator work, such as the mandatory work.

본 발명의 다른 목적은 재료분리대(이하, "홀실"이라 칭한다.)에 의해 오염물(백시멘트+물)의 침투를 원천적으로 봉쇄하여 엘레베이터 각 작동기구의 작동을 원활히 하도록 하여 엘레베이터의 수명을 연장시키고, 도어개폐장치의 오염을 방지하여 오동작을 방지하도록 하는데 있다.Another object of the present invention is to block the infiltration of contaminants (back cement + water) by the material separator (hereinafter referred to as "hole chamber") to facilitate the operation of each elevator mechanism to extend the life of the elevator. In order to prevent malfunction of the door opening and closing device, it is to prevent malfunction.

본 발명의 또 다른 목적은 상기의 방법으로 오염물에 의한 피해가 없는 엘레베이터를 공급하여 엘레베이터의 정숙한 운전분위기를 조성하고, 사용중에도 유지, 보수를 용이하게 하도록 하는데 있다.Still another object of the present invention is to provide an elevator which is free from damage by contaminants in the above-described manner, to create a quiet operating atmosphere of the elevator, and to facilitate maintenance and repair during use.

또한, 방파판을 설치했던 홀실에 의해 바닥면의 인테리어 효과까지 내도록 하여 사용자들이 선호하고 신뢰감을 갖는 제품을 공급하도록 하는데 있다.In addition, the interior of the floor surface by the hall room where the blast board is installed to provide a user with a product with a preference and trust.

도 1은 종래 엘레베이터 도어레일과 바닥시공시 오염물이 침투된 상태를 도시한 단면도이고,1 is a cross-sectional view showing a state in which contaminants have penetrated during construction of a conventional elevator door rail and a floor;

도 2는 본 발명의 엘레베이터 도어레일과 재료분리대의 결합상태를 도시한 참고 사시도로써, 바닥시공과 측벽시공에 대해 설명하기 위한 것이고,Figure 2 is a reference perspective view showing the coupling state of the elevator door rail and the material separator of the present invention, for explaining the floor construction and side wall construction,

도 3의 가)는 도 2의 "A"-"A"선의 단면을 도시한 평단면도이고, 나)는 도 2의 "B"-"B"선의 단면을 도시한 측단면도이고,(A) of FIG. 3 is a sectional plan view showing the cross section of the "A"-"A" line of FIG. 2, b) is a side sectional view showing the cross section of the "B"-"B" line of FIG.

도 4의 가)는 도 3 가)의 "C"-"C"선을 도시한 단면도로써, 엘레베이터 도어레일과 게이트프레임의 결합상태를 도시한 단면도이고, 나)는"D"-"D"선외 엘레베이터 도어레일과 재료분리대의 결합상태를 도시한 단면도이고,Fig. 4A) is a cross-sectional view showing the "C"-"C" line of Fig. 3A), which is a cross-sectional view showing the coupling state of the elevator door rail and the gate frame, and b) is "D"-"D". Cross-sectional view showing the engagement state of the outboard elevator door rail and material separator,

도 5는 본 발명의 재료분리대와 엘레베이터 도어레일이 결합한 상태를 도시한 참고도이다.5 is a reference diagram illustrating a state in which the material separator and the elevator door rail of the present invention are coupled.

*도면의 주요 부분에 대한 부호의 설명* Explanation of symbols for the main parts of the drawings

1; 엘레베이터 10; 도어 프레임One; Elevator 10; Door frame

100;엘레베이터 도어 110;가이드 슈100; elevator door 110; guide shoe

200; 도어레일 210;가이드 홈200; Door rail 210; guide groove

220; 브라켓 안치대 300; 게이트220; Bracket lining 300; gate

310; 브라켓 400; 홀실310; Bracket 400; Hall Room

410; 방파판 삽입홈 420; 방파판410; Blast plate insert groove 420; Breakwater

430; 돌출턱 W ; 측벽430; Protruding jaw W; Sidewall

BR ; 벽돌 LM10; 인터록 리미트 스윗치BR; Brick LM10; Interlock Limit Switch

본 발명은 고층빌딩이나 아파트에 설치되어 각 층마다 승하강하는 엘레베이터가 소정의 위치에 정지하면 양측으로 개폐하도록 하는 엘레베이터 도어와, 그 엘레베이터 도어 하부에 구비된 가이드 슈가 이동할 수 있도록 상부에 가이드홈이 형성되고, 일측에 요홈으로 브라켓 안치대가 형성된 도어레일과, 상기 브라켓 안치대에 통상의 체결수단으로 고정이 가능하도록 한 브라켓에 하단을 고정하도록 하는 게이트로 구성된 엘레베이터 도어프레임에 관한 것으로,The present invention is installed in a high-rise building or apartment, the elevator door to move up and down on each floor when the elevator stops at a predetermined position, the elevator door to open and close to both sides, and the guide groove provided in the upper portion so that the guide shoe provided in the elevator door lower And an elevator door frame including a door rail having a bracket staple formed as a recess on one side, and a gate configured to fix a lower end to a bracket to be fixed to the bracket stabilizer by a general fastening means.

상기 도어레일의 브라켓 안치대에 일측이 삽입으로 결합되고, 타측상부에는 수분등이 함유된 오염물의 침투를 방지하는 방파판을 꽂기 용이하도록 하는 방파판 삽입홈이 요홈으로 형성된 홀실로 구성된다.One side is inserted into the bracket restraint of the door rail, and the other side is composed of a hole chamber formed with a recessed groove formed in the recess to facilitate the insertion of the break-proof plate to prevent the penetration of contaminants containing moisture and the like.

또한, 빌딩의 각 층마다 도어프레임과 도어와 도어를 개폐하도록 하는 기구를 설치하고, 내측으로는 수직으로 엘레베이터용 레일을 설치한 후 승, 하강하며 소망하는 위치에 정지하도록 하는 엘레베이터와 엘레베이터 도어프레임의 시공에 있어서,In addition, an elevator and an elevator door frame are installed on each floor of the building to install a door frame, a mechanism for opening and closing the door and the door, and an elevator rail vertically inward, and then lift, descend, and stop at a desired position. In the construction of

상기 도어프레임의 하부에 구비된 도어레일 일측에 결합된 홀실과 방파판에 의해 인조석 물갈기 바닥시공과 엘레베이터의 시공이 동시에 가능하도록 한 것이다.The construction of the artificial water grind floor construction and the elevator by the hall seal and the blast plate coupled to one side of the door rail provided in the lower portion of the door frame to enable at the same time.

이하, 첨부한 예시도를 참조하여 본 발명의 바람직한 실시예에 대해 상세히 설명한다.Hereinafter, with reference to the accompanying drawings illustrating a preferred embodiment of the present invention in detail.

도 2는 본 발명의 엘레베이터 도어레일과 홀실의 결합상태를 도시한 참고 사시도로써, 바닥시공과 측벽시공에 대해 설명하기 위한 것이고, 도 3의 가)는 도 2의 "A"-"A"선의 단면을 도시한 평단면도이고, 나)는 도 2의 "B"-"B"선의 단면을 도시한 측단면도이고, 도 4의 가)는 도 3 가)의 "C"-"C"선을 도시한 단면도로써, 엘레베이터 도어레일과 게이트프레임의 결합상태를 도시한 단면도이고, 나)는 엘레베이터 도어레일과 홀실의 결합상태를 도시한 단면도이고, 도 5는 본 발명의 홀실과 엘레베이터 도어레일이 결합한 상태를 도시한 참고도이다.FIG. 2 is a reference perspective view illustrating a coupling state of an elevator door rail and a hall seal of the present invention. FIG. 2 is for explaining floor construction and side wall construction. A cross-sectional view showing a cross-sectional view, b) is a side cross-sectional view showing a cross section of the "B"-"B" line of Figure 2, a) of Figure 4 is a "C"-"C" line of FIG. As a cross-sectional view shown, a cross-sectional view showing a coupling state of the elevator door rail and the gate frame, b) is a cross-sectional view showing a coupling state of the elevator door rail and the hall seal, Figure 5 is a combination of the hall seal and the elevator door rail of the present invention It is a reference figure which shows the state.

도 2 내지 도 4에 도시한 것은, 엘레베이터 도어프레임(10)의 설치작업에 대해 설명하기 위한 것으로써, 도어프레임(10)이 장착되는 통상의 측벽(W)은 콘크리트(Concreate) 시공특성상 엘레베이터(1) 게이트(300)의 폭을 정확히 맞추기 어려운 관계로 측벽 개구부를 크게 형성하도록 콘크리트 타설을 시행한다.2 to 4 are for explaining the installation operation of the elevator door frame 10, the normal side wall (W) to which the door frame 10 is mounted is an elevator (concrete) construction characteristics ( 1) Concrete placement is performed to form sidewall openings large because it is difficult to accurately match the width of the gate 300.

또한, 슬라브(SL) 상부에 "ㄴ"자로 형성된 지지앵글(11)을 다수의 앵커볼트(AC)로 고정하고 외부측면으로는 "ㄱ"자의 지지앵글(12)을 다수개의 볼트로 결합하여 시공작업을 위한 준비작업은 완료되고, "ㄱ"자 지지앵글(12)의 상부에 도어레일(200)의 하부에 형성된 체결홈(230)에 볼트를 체결함으로써 고정이 완료되게 된다.In addition, the support angle (11) formed in the upper portion of the slab (SL) is fixed by a plurality of anchor bolts (AC) and the outer side "a" of the support angle 12 of the construction by combining a plurality of bolts Preparation work for the work is completed, the fixing is completed by fastening the bolt to the fastening groove 230 formed in the lower portion of the door rail 200 on the upper portion of the "a" shaped support angle (12).

한편, 상기 정위치에 수직 추(현장용어 일명"사게부리")로 수직을 맞춘 도어프레임(10)을 정중앙에 구비시킨 후, 본 발명의 홀실(Hall Sill)(400)을 상기 도어레일(200)의 일측에 형성된 브라켓 안치대(220)에 삽입하고, 그 홀실(400)의 양측으로는 브라켓(310)을 삽입한 후, 하부 바닥면에 소정의 레벨을 맞춰 바닥에 앵커 볼트(미도시)등으로 고정하고, 상기 브라켓(310)의 상부에 게이트(300)를 대칭으로 구비시킨 후 통상의 볼트, 너트로 결합한다.On the other hand, after the door frame 10 which is vertically aligned with a vertical weight (site term aka "cage beak") at the right position in the center, the hall sil (400) of the present invention (Hall Sill) 400 of the door rail 200 Insert the bracket into the bracket support 220 formed on one side of the side, and the bracket 310 is inserted into both sides of the hole chamber 400, the anchor bolt (not shown) at the bottom to match a predetermined level on the bottom bottom surface And the like, fixed to the upper portion of the bracket 310, the gate 300 is provided symmetrically and then coupled with a conventional bolt, nut.

이때, 도 2와 도 3의 가)에 도시한 바와 같이, 상기 게이트(300)의 양측부와 상부는 크게 형성된 측벽 개구부(가상선 표시)의 콘크리트 철근(SW)에 장착하여 고정하고, 크게 형성된 개구부를 벽돌(BR)조적한 후, 외부를 미장으로 마무리하여 도어프레임(10)의 장착은 1차로 완료되게 되고, 각 층도 상술한 바와 동일하게 시행한다.At this time, as shown in Figures 2 and 3 a), both sides and the upper portion of the gate 300 is mounted and fixed to the concrete reinforcement (SW) of the side wall opening (virtual line display) formed large, and formed large After masonry the openings BR, the exterior is finished with plastering, and the mounting of the door frame 10 is completed first, and each layer is performed in the same manner as described above.

또한, 도 3의 가)에 도시한 평단면도 좌, 우의 케이트(300)를 2종류로 도시한 것은 1층 로비(Lobby)에 구비되는 게이트(300)는 좌측에 도시한 바와 같은 큰 단면의 게이트를 사용하고, 2층 이상 최상층까지는 통상적으로 우측에 도시한 바와 같은 작은 단면의 게이트(300)를 사용하고 있는 것을 모두 도시한 것이고, 후술하는 상세한 설명에서는 작은 단면의 게이트(300)를 기준으로 하여 설명하기로 한다.In addition, the two types of the gates 300 shown on the left and right sides of the flat cross-sectional view shown in Fig. 3A are shown in the left-hand side of the gate 300 provided in the lobby on the first floor. 2 to the uppermost layer, the gate 300 having a small cross section as shown in the right side is usually shown. In the following description, the gate 300 having a small cross section is used as a reference. Let's explain.

도 4와 도 5에 도시한 바에 의하면, 상기의 도어레일(200)과 브라켓(310)과 게이트(300)를 결합한 상태를 도시한 것으로, 상기의 브라켓(310)은 볼트(Bolt)가 가조립되도록 헐겁게 체결한 후, 상기 도어레일(200)의 일측에 요홈으로 형성된 브라켓 안치대(220)의 내부로 볼트의 머리부분을 삽입하고, 반대측인 타측으로는 후술할 홀실(400) 일측의 형성된 돌출턱(430)을 삽입한 뒤 타측으로 반대편의 브라켓(310)을 상술한 방법과 같이 삽입하여 고정한다.4 and 5, the door rail 200, the bracket 310, and the gate 300 are coupled to each other, and the bracket 310 may be temporarily assembled with bolts. After loosely fastening, the head of the bolt is inserted into the inside of bracket bracket 220 formed as a recess on one side of the door rail 200, and the other side of the other side of the hole protrusion 400 formed later on the other side After inserting 430, the other side of the bracket 310 is inserted and fixed in the same manner as described above.

또한, 철근에 장착 고정되어 있는 게이트(300)의 하단을 상기의 브라켓(310)과 볼트, 너트로 결합하여 게이트(300)의 장착은 완료됨으로써, 상기 홀실(400)의 레벨에 맞추어 바닥시공이 이루어지게 된다.In addition, the bottom of the gate 300 is fixed to the reinforcing bar by combining the bracket 310 with the bolts, nuts, the mounting of the gate 300 is completed, the floor construction in accordance with the level of the hall chamber 400 Will be done.

도 4의 나)와 도 5에 도시한 바에 의하면, 본 발명 홀실(400)의 레벨에 맞추어 바닥(F) 인조석 시공하는 작업에 대해 설명하기 위한 것으로, 줄눈작업에 대한 설명은 생략한다.As shown in FIG. 4B) and FIG. 5, the operation for constructing the floor F artificial stone in accordance with the level of the hall room 400 of the present invention is omitted, and the description of the joint operation is omitted.

홀실(400)의 일측으로는 속칭 도끼다시(이하, "인조석"이라 칭함)라고 하는 돌가루를 섞은 시멘트를 미장하고, 소정의 시간이 경과한 후 경화가 완료된 인조석의 표면을 매끄럽게 하기 위한 인조석 물갈기 작업을 시행하게 된다.One side of the hall chamber 400 is plastered with cement mixed with a stone powder (called "artificial stone"), and then artificial stone water for smoothing the surface of the cured artificial stone after a predetermined time has elapsed. The grind work is carried out.

상술한 바와 마찬가지로 돌가루(石粉)의 발생을 방지하도록 물을 분사하는것이 불가피하기 때문에 도시한 바와 같은, 본 발명의 홀실(400)의 높이보다 높게 형성된 인조석의 레벨을 연마석으로 갈아 레벨을 맞추고 그에 따라 표면도 매끄럽게 하도록 하는 것이다.As described above, since it is inevitable to spray water to prevent the generation of stone dust, the level of the artificial stone formed higher than the height of the hall chamber 400 of the present invention as shown in the figure is ground by grinding the stone and then Therefore, the surface is also smoothed.

이때, 도시한 바와 같이, 홀실(400)의 일측으로 접촉되는 인조석의 레벨이 높게 형성됨으로 경화가 완료되지 않은 수분을 함유한 인조석의 분진(이하, "오염물"이라 함.)이 흘러드는 것을 방지하도록 방파판(420)을 설치하게 되는 것이다.At this time, as shown, the level of the artificial stone in contact with one side of the hall chamber 400 is formed high to prevent the dust of the artificial stone containing the hardening is not completed (hereinafter referred to as "contaminants"). To install the breakwater plate 420 to.

즉, 도시한 바와 같이, 홀실(400)의 일측 인조석이 접촉되는 부위에 깊은 요홈으로 방파판삽입홈(410)이 형성되어 알루미늄, 합성수지 또는 목재의 재질로 이루어진 방파판(420)을 삽입하고 양측면에 수직으로 구비된 게이트(300) 측면의 외부로 실리콘(Silicon) 또는 청테이프를 도포하면 누수의 염려없이 견고하게 고정된 상태를 유지하게 되는 것이고, 인조석 물갈기 시공을 하는 중에도 엘레베이터의 시공을 동시에 가능하도록 하는 것이다.That is, as shown, the breakhole insertion groove 410 is formed as a deep groove in the site where one side artificial stone of the hall chamber 400 is contacted, inserting the blast plate 420 made of aluminum, synthetic resin or wood material and both sides When silicon or blue tape is applied to the outside of the side of the gate 300 which is provided perpendicular to the gate 300, it is maintained firmly without leaking and the construction of the elevator is carried out even during the artificial grind. To make it possible.

여기서, 상기 방파판 삽입홈(410)의 깊이는 가능하면 깊게 형성하는 것이 바람직하다. 그 이유로는 상기의 기술한 방파판(420)이 견고하게 지지되도록 하기 위한 것이고, 그에 따라 깊이 삽입되어 지지된 방파판(420)의 물갈기용 연마기에 의해 꺾이는 것을 방지하고 견고하게 지지되도록 하기 위한 것이다.Here, it is preferable that the depth of the breakthrough plate insertion groove 410 is formed as deep as possible. The reason for this is to ensure that the above-described blast plate 420 is firmly supported, and thus to be prevented from being bent by a grinder for the grinding of the blast plate 420 deeply inserted and supported thereto, and to be firmly supported. .

또한, 상술한 바와 같은 방파판(420)을 이용하여 막아 놓으면 물갈기 바닥시공을 하는 중에도 전혀 지장을 초래하지 않고 엘레베이터(1)의 시공작업이 가능한 것이고, 엘레베이터 도어(100)의 내부로 물갈기에 의한 오염물의 침투를 방지함으로 엘레베이터(1) 운행구간 내부에서 엘레베이터 도어를 자유롭게 여닫으며 시공작업을 수행하기가 용이하고, 또한 엘레베이터(1)의 핵심이라 할 수 있는 도어개폐 장치에 구비된 인터록 리미트 스위치(LM10)를 오염시키는 일이 없으므로 정확한 엘레베이터 도어(100)및 엘레베이터(1)의 작동을 도모할 수 있다.In addition, if the blocking using the blast plate 420 as described above, the construction work of the elevator (1) can be performed without causing any trouble even during the construction of the bottom of the water, the water to the inside of the elevator door 100 It is easy to carry out construction work by opening and closing the elevator door freely inside the operating section of the elevator (1) by preventing the infiltration of contaminants by the interlock limit provided in the door opening and closing device, which is the core of the elevator (1). Since the switch LM10 is not contaminated, the accurate operation of the elevator door 100 and the elevator 1 can be achieved.

한편, 상기의 홀실(400)과 방파판(420)의 결합에 의해 인조석 물갈기 바닥시공을 하며 연마석에 의해 엘레베이터 도어(100)와 게이트(300) 하단에 손상을 입는 일이 없어짐으로써, 시공 작업완료 후 손상된 부위에 재도장작업을 하지 않으므로 시공 후 사후 관리가 용이하여 생산성을 향상시킨 효과가 있는 것이다.On the other hand, by the combination of the hall chamber 400 and the blast plate 420, the artificial stone grind floor construction, and no damage to the elevator door 100 and the bottom of the gate 300 by the abrasive stone, construction work After completion of the work is not repainted on the damaged area is easy to follow-up management after construction has the effect of improving productivity.

또한, 인조석물갈기의 바닥시공이 완료되면, 상술한 바와 같은 방파판(420)을 해체하여 보관하고 다른 현장에서 사용할 수 있으므로 원가절감을 할 수 있고, 홀실(400)의 방파판삽입홈(410)에는 상기의 방파판(420)을 제거한 후 동재질 또는 합성수지재의 줄눈을 삽입하면 바닥의 인테리어 효과도 있는 것이다.In addition, when the bottom construction of the artificial stone grind is completed, the breakwater plate 420 as described above can be dismantled and stored at another site, so that the cost can be reduced, and the breakwater insertion groove 410 of the hall room 400 is provided. ) Is inserted into the joint of the same material or synthetic resin after removing the blast plate 420 will have the interior effect of the floor.

본 발명은 상술한 특정 바람직한 실시예에 한정되지 아니하며 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 본 발명이 속하는 기술분야에서 통상의 지식을 가진자라면 누구든지 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위내에 있게 된다.The present invention is not limited to the above-described specific preferred embodiments and may be modified by anyone of ordinary skill in the art without departing from the gist of the present invention as claimed in the claims. Such changes will fall within the scope of the claims.

본 발명에 의하면, 엘레베이터를 설치하는 시공자들은 인조석 물갈기작업과 동시에 시공작업을 가능하게 하여 생산성을 높인 효과가 있고, 홀실에 의해 오염물(백시멘트+물)의 침투를 원천적으로 봉쇄하여 엘레베이터의 각 작동기구의 동작을 원활히 하도록 하고, 정숙한 작동을 하도록 한 효과가 있다.According to the present invention, the installers to install the elevator has the effect of increasing the productivity by enabling the construction work at the same time as the artificial grind work, by blocking the infiltration of contaminants (back cement + water) by the hall chamber of each elevator It is effective to make the operation of the implement smooth and quiet operation.

상기 방법으로 인해 엘레베이터의 시공작업을 바닥시공과 동시에 용이하게 시행하고, 도어를 개폐하도록 하는 기구에 오염물 침투를 방지하여 엘레베이터의 오동작을 예방함으로 안전한 운행을 하도록 한 효과가 있다.Due to the above method, the construction work of the elevator can be easily performed at the same time as the construction of the floor, and the safe operation can be prevented by preventing the contamination of the elevator by preventing contaminants from penetrating into the mechanism for opening and closing the door.

또한, 오염물에 의한 피해가 없는 제품을 공급하여 엘레베이터의 차후보수 및 유지관리가 용이하고, 본 발명의 홀실에 의해 바닥면의 인테리어 효과로 사용자들이 선호하는 엘레베이터 홀 분위기를 조성하여 신뢰감을 준 효과가 있다.In addition, by providing a product that is not damaged by contaminants, easy maintenance and maintenance of the elevator, the hall room of the present invention by the interior effect of the floor surface to create the elevator hall atmosphere that users prefer the effect of giving confidence have.

또한, 연마작업시 발생하는 도어와 게이트 하단부의 파손을 방지함으로써 마감작업후 시공자가 도어의 손상부위를 재도장하는 생산외 작업을 없앰으로 시공의 생산성을 높인 효과가 있다.In addition, by preventing the breakage of the door and the gate lower portion generated during the polishing operation, the construction after the finishing work eliminates the non-production work to repaint the damaged part of the door has the effect of increasing the productivity of the construction.

Claims (8)

빌딩의 측벽에 설치되어 각 층마다 승하강하는 엘레베이터 소정의 위치에 정지하면 양측으로 개폐하도록 하는 엘레베이터 도어와, 그 엘레베이터 도어 하부에 구비된 가이드 슈가 이동할 수 있도록 요홈으로 가이드홈이 형성되고, 일측에 요홈으로 브라켓 안치대가 형성된 도어레일과, 그 도어레일 일측에 형성된 브라켓 안치대에 통상의 체결수단으로 고정이 가능하도록 한 브라켓에 하단을 고정하도록 하는 게이트로 구성된 엘레베이터 도어프레임에 있어서,The elevator is installed on the side wall of the building, and the elevator lifts up and down for each floor. The elevator door is opened and closed to both sides when stopped at a predetermined position. An elevator door frame comprising a door rail having a bracket staple formed as a recess, and a gate configured to fix a lower end to a bracket that can be fixed to a bracket stabilizer formed on one side of the door rail by a conventional fastening means. 상기 브라켓 안치대의 일측에 삽입으로 결합되고, 타측상부에는 수분등이 함유된 오염물의 침투를 방지하는 방파판을 꽂기 용이하도록 방파판 삽입홈이 요홈으로 형성된 홀실로 구성된 것을 특징으로 하는 엘레베이터 도어프레임.The elevator door frame is coupled to one side of the bracket settlement, the other side upper portion is formed of a hall chamber formed with a groove to insert the break-proof plate insertion groove to easily plug the break-proof plate to prevent the penetration of contaminants containing moisture and the like. 제 1항에 있어서, 상기 홀실은 일측에 돌출로 형성된 돌출턱에 의해 도어레일일측 요홈으로 형성된 브라켓 안치대에 삽입으로 고정이 가능한 것을 특징으로 하는 엘레베이터 도어프레임.The elevator door frame according to claim 1, wherein the hall chamber is inserted and fixed to a bracket support formed by a door rail side groove by a protruding jaw protruding from one side. 제 1항에 있어서, 상기 홀실의 재질은 알루미늄인 것을 특징으로 하는 엘레베이터 도어프레임.The elevator door frame according to claim 1, wherein the hall seal is made of aluminum. 제 1항에 있어서, 상기 방파판은 하측이 방파판 삽입홈에 삽입되고, 양측은 게이트에 실리콘으로 실링됨으로 물과 오염물의 침투를 방지하도록 하는 것을 특징으로 하는 엘레베이터 도어프레임.The elevator door frame according to claim 1, wherein the breakthrough plate is inserted into the breakthrough insert groove at the lower side thereof and the both sides are sealed with silicon in the gate to prevent penetration of water and contaminants. 제 1항에 있어서, 상기 방파판의 재질은 알루미늄, 합성수지, 철판중 어느하나인 것을 특징으로 하는 엘레베이터 도어프레임.The elevator door frame according to claim 1, wherein the material of the breakwater plate is one of aluminum, synthetic resin, and iron plate. 빌딩의 각 층마다 도어프레임과 도어와 도어를 개폐하도록 하는 기구를 설치하고, 내측에는 수직으로 설치된 엘레베이터용 레일을 타고 승, 하강하며 소망하는 위치에 정지하도록 하는 엘레베이터와 엘레베이터 도어프레임의 시공에 있어서,In each floor of the building, the door frame and the mechanism for opening and closing the door and the door are installed.In the construction of the elevator and the elevator door frame, which are lifted, lowered and stopped at a desired position on a vertically installed elevator rail. , 상기 도어프레임의 하부에 구비된 도어레일 일측에 결합된 홀실과 방파판에 의해 인조석 물갈기 바닥시공과 엘레베이터의 시공이 동시에 가능하도록 한 것을 특징으로 하는 엘레베이터 도어프레임의 시공방법.The construction method of the elevator door frame, characterized in that the construction of the artificial grind floor and the elevator can be simultaneously enabled by a hall seal and a blast plate coupled to one side of the door rail provided in the lower portion of the door frame. 제 6항에 있어서,The method of claim 6, 상기 홀실에 의해 복도바닥의 레벨이 정해지는 것을 특징으로 하는 엘레베이터 도어프레임의 시공방법.The construction method of the elevator door frame, characterized in that the level of the corridor floor is determined by the hall room. 제 6항에 있어서,The method of claim 6, 상기 홀실의 방파판삽입홈에는 동재질 또는 합성수지재의 줄눈을 삽입하여 마감하는 것을 특징으로 하는 엘레베이터 도어프레임의 시공방법.The construction method of the elevator door frame, characterized in that to insert and finish the joint of the same material or synthetic resin in the blast board insertion groove of the hall chamber.
KR1020000030961A 2000-06-07 2000-06-07 Elevator Door Frame KR100364341B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020000030961A KR100364341B1 (en) 2000-06-07 2000-06-07 Elevator Door Frame
KR2020000016050U KR200203785Y1 (en) 2000-06-07 2000-06-07 Elevator door frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020000030961A KR100364341B1 (en) 2000-06-07 2000-06-07 Elevator Door Frame

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020000016050U Division KR200203785Y1 (en) 2000-06-07 2000-06-07 Elevator door frame

Publications (2)

Publication Number Publication Date
KR20010000135A true KR20010000135A (en) 2001-01-05
KR100364341B1 KR100364341B1 (en) 2002-12-11

Family

ID=19671284

Family Applications (2)

Application Number Title Priority Date Filing Date
KR2020000016050U KR200203785Y1 (en) 2000-06-07 2000-06-07 Elevator door frame
KR1020000030961A KR100364341B1 (en) 2000-06-07 2000-06-07 Elevator Door Frame

Family Applications Before (1)

Application Number Title Priority Date Filing Date
KR2020000016050U KR200203785Y1 (en) 2000-06-07 2000-06-07 Elevator door frame

Country Status (1)

Country Link
KR (2) KR200203785Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200473964Y1 (en) * 2014-02-04 2014-08-11 장귀경 Stiffener for elevator door sill
KR102582746B1 (en) 2023-03-13 2023-09-26 라이트하우스(주) Control method, device and system of platform service for providing travel video content based on virtual currency payment according to travel scenario publication and selection

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100667901B1 (en) 2004-08-19 2007-01-11 장귀경 Separation object of a elevator hall
KR100736110B1 (en) 2005-10-04 2007-07-06 장귀경 Appearance board equipment of separation object of a elevator hall
KR100736113B1 (en) 2005-10-04 2007-07-06 장귀경 Upper plate equipment of separation object of a elevator hall
KR100923619B1 (en) 2007-10-10 2009-10-23 장귀경 Separation object of a elevator hall

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS52133640A (en) * 1976-04-30 1977-11-09 Hitachi Ltd Elevator cage
JPH01156289A (en) * 1987-12-11 1989-06-19 Toshiba Corp Small-sized elevator for low floor
JP2579176B2 (en) * 1987-12-26 1997-02-05 株式会社チューオー Building panel connection structure
KR910008230Y1 (en) * 1989-06-14 1991-10-12 금성기전 주식회사 Door still device of elevator
KR0138242B1 (en) * 1993-11-01 1998-07-01 김충엽 Roof parapet waterproof layer protective plate, waterproof structure including the same and construction method
KR960014558A (en) * 1994-10-05 1996-05-22 윤성섭 Wall panel and construction method of wall using same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200473964Y1 (en) * 2014-02-04 2014-08-11 장귀경 Stiffener for elevator door sill
KR102582746B1 (en) 2023-03-13 2023-09-26 라이트하우스(주) Control method, device and system of platform service for providing travel video content based on virtual currency payment according to travel scenario publication and selection

Also Published As

Publication number Publication date
KR200203785Y1 (en) 2000-11-15
KR100364341B1 (en) 2002-12-11

Similar Documents

Publication Publication Date Title
KR100364341B1 (en) Elevator Door Frame
KR102033453B1 (en) Method for Construction Threshold of Gate for Elevator Cabin
CN105909122A (en) Mounting method of plastic steel door and window
GB2352753A (en) Flood barrier
KR200417507Y1 (en) Concrete Crack Prevention Device
KR100667901B1 (en) Separation object of a elevator hall
EP1991755A2 (en) Blind frame for a window or a door
CN211622769U (en) Water-proof structure of shower room
KR100545344B1 (en) Window frame of living room for building
EP0566562B1 (en) Structure panel and a joint between such panels and method of using and manufacturing the panel
KR20040021432A (en) Construction supporting structure for piling up bricks of the upper lintel
JP7246711B2 (en) Method of installing metal fittings
CN210659248U (en) Straight-line-shaped constructional column cement template set
CN218205714U (en) Antiseep mould for building
CN216075804U (en) Closing-in structure of bathroom platform and curtain wall
CN219197076U (en) Prefabricated door head
KR100694176B1 (en) Indoor wall of building
KR200402508Y1 (en) Concrete Crack Prevention Device
CN115653126A (en) Penetrating and sealing construction method for basement outer wall post-cast strip
KR200262708Y1 (en) A work mold of an outlet box
KR100689026B1 (en) Concrete Crack Prevention Device
KR200407071Y1 (en) Concrete Crack Prevention Device
KR101716334B1 (en) Structure of bath frame
KR200436704Y1 (en) window structure with sustainer
KR20010087827A (en) The operation method of metal lath bonding exterior insulation and finishing system

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121102

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20131113

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20141105

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20150826

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20161111

Year of fee payment: 15

LAPS Lapse due to unpaid annual fee